55
AFFORDABLE GROUP HOUSING COLONY(5 ACRES) LOCATED AT SECTOR 104,GURGAON, HARYANA By M/s. PERFECT BUILDWELL PVT. LTD. (A) HALF-YEARLY COMPLIANCE OF STIPULATED ENVIRONMENTAL CONDITIONS/ SAFEGUARDS IN THE ENVIRONMENTAL CLEARANCE Ref. LETTER NO.SEIAA/HR/2015/280 DATED 09.03.2015FORCONSTRUCTION OF Sl. No. Conditions Status of Compliance PART A - SPECIFIC CONDITIONS:CONSTRUCTION PHASE: 1 “Consent to Establish” shall be obtained from Haryana State Pollution Control Board under Air and Water act and a copy shall be submitted to the SEIAA Haryana before the start of any construction work at the site. Agreed. Consent to Establish” has been obtained from Haryana State Pollution Control Board under Air and Water Act Annexure 1. 2 A First Aid room as proposed in the project report will be provided in both during construction and operation of the project. Agreed. Construction work has just started at site. Site pics have been attached as Annexure 16. First Aid room has been provided at the project site during the construction phase and will be 1

nromoef.gov.innromoef.gov.in/SMPR/25042016/11.docx · Web view“Consent to Establish” shall be obtained from Haryana State Pollution Control Board under Air and Water act and a

Embed Size (px)

Citation preview

AFFORDABLE GROUP HOUSING COLONY(5 ACRES) LOCATED AT SECTOR 104,GURGAON, HARYANA By M/s. PERFECT BUILDWELL PVT. LTD.

(A) HALF-YEARLY COMPLIANCE OF STIPULATED ENVIRONMENTAL CONDITIONS/ SAFEGUARDS IN THE ENVIRONMENTAL CLEARANCE Ref. LETTER NO.SEIAA/HR/2015/280 DATED 09.03.2015FORCONSTRUCTION OF

Sl. No. Conditions Status of Compliance

PART A - SPECIFIC CONDITIONS:CONSTRUCTION PHASE:

1 “Consent to Establish” shall be obtained

from Haryana State Pollution Control

Board under Air and Water act and a

copy shall be submitted to the SEIAA

Haryana before the start of any

construction work at the site.

Agreed. Consent to Establish” has been

obtained from Haryana State Pollution

Control Board under Air and Water Act

Annexure 1.

2 A First Aid room as proposed in the

project report will be provided in both

during construction and operation of the

project.

Agreed. Construction work has just started

at site. Site pics have been attached as

Annexure 16. First Aid room has been

provided at the project site during the

construction phase and will be provided in

the operational phase , its picture has been

attached as Annexure 19.

3 Adequate drinking water and sanitary

facilities shall be provided for

construction workers at the site.

Provision should be made for the mobile

toilets. Open defecation by the laborers is

strictly prohibited. The safe disposal of

waste water and solid wastes generated

during the construction phase should be

ensured.

Agreed. It is assured that adequate drinking

water and sanitation will be provided for

workers at the site. In addition to it, mobile

toilets will be provided along with the

provision of septic tank & soak pit for the

disposal of wastewater.

1

4 All the top soil excavated during

construction activities should be stored

for use in horticulture/landscape

development within the project site.

Agreed. The excavated material will be used

for leveling, refilling and in horticulture/

landscape development within the project

site& surplus will be disposed off outside the

premises with consent to mixing department.

5 The project proponent shall ensure that

the building material required during

construction phase is properly stored

within the project area and disposal of

construction waste should not create any

adverse effect on the neighboring

communities and should be disposed off

after taking the necessary precautions for

general safety and health aspects of

people, only in approved sites with the

approval of competent authority.

Agreed. It will be ensured that the building

materials will be properly stored within the

project area and disposal of construction

waste will not create any adverse effect on

the neighboring communities. It will be

disposed off after taking the necessary

precautions for general safety and health

aspects of people, only in approved sites with

the approval of competent authority.

6 Construction spoils, including

bituminous material and other hazardous

materials, must not be allowed to

contaminate watercourses and the dump

sites for such material must be secured so

that they should not leach into the ground

water and any hazardous waste generated

during construction phase, should be

disposed off as per applicable rules and

norms with necessary approval of the

Haryana State Pollution Control Board.

Agreed. Construction spoils including

bituminous material and other hazardous

material will not be allowed to contaminate

the water courses. No dumping of such

materials will be allowed at project site.

Waste lubricating oil generated from

maintenance of DG sets falls under

hazardous waste category. Such wastes will

be disposed off with the help of waste

recycler with necessary approval from

Haryana State Pollution Control Board.

7 The Diesel generator sets to be used

during construction phase should be of

ultra-low sulphur diesel type and should

conform to Environment (Protection)

Agreed. Ultra-low sulphur diesel will be used

to run the Diesel generator sets to be used

during construction phase with Provisions of

Air and Noise Emissions Standards as per

2

Rulesprescribed for air and noise

emission standards.

EPA Rules, 1986.

8 The diesel required for operating DG sets

shall be stored in underground tanks and

if required, clearance from Chief

Controller of Explosives shall be taken.

Agreed. Used oil from DG sets will be stored

in HDPE drums in isolated covered facility.

This used oil will be sold to authorized

recyclers. Suitable care will be taken to avoid

spills/leaks of used oil from storage. Separate

log books will be maintained for

accountability.

9 Ambient noise levels should conform to

residential standards both during day and

night. Incremental pollution loads on the

ambient air and noise quality should be

closely monitored during construction

phase. Adequate measures should be

taken to reduce ambient air and noise

level during construction phase, so as to

conform to the stipulated residential

standards.

Agreed. Ambient noise level is within the

standard level prescribed by MoEF.

Incremental pollution loads on the ambient

air and noise quality are being closely

monitored. Laboratory data of the

environmental monitoring of air, noise and

soil carried out at the site are enclosed as

Annexure 17.

Similarly, Ambient air quality is also closely

monitored so as to conform to the stipulated

standards.

10 Fly ash should be used as building

material in the construction as per the

provisions of Fly Ash Notification of

September, 1999 and amended as on 27th

August, 2003.

Agreed. Fly ash Bricks will be used as

building material in the construction as per

the provisions of Fly Ash Notification of

September, 1999 and amended as on 27th

August, 2003.

11 Storm water control and its re use as per

CGWB and BIS standards for various

applications should be ensured.

Agreed. Storm water control and its re use

(for various applications) will be ensured as

per BIS and Central Ground Water Board

(CGWB) standards. Adequate number of

harvesting pits will be provided for control of

3

storm water.

12 Water demand during construction

should be reduced by use of pre-mixed

concrete, curing agents and other best

practices.

Agreed. Water demand during construction

will be reduced by the practice of using pre-

mixed concrete, curing agents and other

best practices.

13 In view of the severe constrains in water

supply augmentation in the region and

sustainability of water resources, the

developer will submit the NOC from

CGWA specifying water extraction

quantities and assurances from

HUDA/utility provider indicating source

of water supply and quantity of water

with details of intended use of water –

potable and non-potable. Assurance is

required for both construction and

operation stages separately. It shall be

submitted to the SEIAA and RO, MoEF,

Chandigarh before the start of

construction.

Agreed. Water Assurance for Construction as

well as for operation phase is attached as

Annexure 2&3.

14 Roof must meet prescriptive requirement

as per Energy Conservation Building

Code by using appropriate thermal

insulation material.

Agreed. Roof will be constructed as per

Energy Conservation Building Code.

15 Opaque wall should meet prescriptive

requirement as per Energy Conservation

Building Code which is proposed to be

mandatory for all air conditioned spaces

while it is desirable for non-air-

conditioned spaces by use of appropriate

thermal insulation material to fulfill

Agreed. Opaque wall will meet prescribed

requirement as per Energy Conservation

Building Code (ECBC).

4

requirement.

16 The approval of the competent authority

shall be obtained for structural safety of

the building on account of earthquake,

adequacy of firefighting equipment’s,

etc. as per National Building Code

including protection measures from

lightening etc. If any forest land is

involved in the proposed site, clearance

under The Forest Conservation Act shall

be taken from the competent Authority.

Agreed. The approval of the competent

authority will be obtained in due course of

time for structural safety of the buildings due

to earthquake, adequacy of firefighting

equipment, etc. as per National Building

Code including protection measure from

lightening etc. No forest land is involved in

the project site. NOC from Forest

Department has been obtained from Dy.

Conservator of Forest, Gurgaon vide letter

No. 2065-G dated 18.09.2014 and copy of

the same is enclosed as Annexure 4.

17 Overexploited groundwater and

impending severe shortage of water

supply in the region requires the

developer to redraw the water and energy

conservation plan. Developer shall

reduce the overall footprint of the

proposed development. Project

proponent shall incorporate water

efficiency / saving measures as well as

water reuse/ recycling within 3 months

and before start of construction to the

SEIAA, Haryana and RO, MoEF, GOI,

Chandigarh.

Agreed. Overexploited groundwater and

impending severe shortage of water supply in

the region requires the developer to redraw

the water and energy conservation plan.

Developer will reduce the overall footprint of

the proposed development. Project proponent

will incorporate water efficiency / saving

measures as well as water reuse/ recycling

within 3 months and before start of

construction to the SEIAA, Haryana and RO,

MoEF, GOI, Chandigarh.

18. The project proponents as stated in

proposal shall constructed 05 nos. rain

water harvesting pits shall be designed to

make provision for silting chamber and

removal of floating matter before

Agreed.5 numbers of RWH pits will be

provided with adequate design with silting

chamber after finishing the civil construction

work. RWH plan is attached as Annexure

9.

5

entering harvesting pit. Maintenance

budget and persons responsible for

maintenance must be provided. Care

shall also be taken that contaminated

water do not enter any RWH pit.

19 The project proponent shall provide for

adequate fire safety measures and

equipment’s as required by Haryana Fire

Service Act, 2009 and instructions issued

by the local authority/Directorate of fire

from time to time. Further the project

proponent shall take necessary

permission regarding fire safety

scheme/NOC from competent Authority

as required.

Agreed. Adequate Fire Safety measures and

equipment’s as per Haryana Fire Service Act,

2009 and instructions issued by the local

Authority/ Directorate of fire will be

provided. Necessary permission regarding

fire safety scheme/NOC from competent

authority is attached as Annexure 21.

20. The project proponent shall obtain

assurance from the DHBVN for supply

of 3500 KVA of power supply before the

start of construction. In no case project

will be operational solely on generators

without any power supply from any

external power utility.

Agreed. The project proponent has obtained

assurance from the DHBVN for supply of

electricity. Copy of the same is enclosed as

Annexure 5.

21 Detail calculation of power load and

ultimate power load of the project shall

be submitted to DHBVN under

intimation to SEIAA Haryana before the

start of construction. Provision shall be

made for electrical infrastructure in the

project area.

Agreed. Total power requirement is 3500

kVA. Calculation of power load is enclosed

as Annexure 6.

22. The Project proponent shall not raise any

construction in the natural land

There is no natural land depression/ Nallah/

Water course passing through the project site.

6

depression/Nallah/ Water course and

shall ensure that the natural flow from

the Nallah/ Water course is not

obstructed.

23. The project proponent shall keep the

plinth level of the building blocks

sufficiently above the level of the

approach road to the Project as per

prescribed bye-laws. Levels of the other

areas in the Projects shall also be kept

suitably so as to avoid flooding.

Agreed. The plinth level of the building

blocks will be sufficiently above the level of

the approach road to the project as per

prescribed by-laws. Levels of the other areas

in the projects will also be kept suitably so as

to avoid flooding.

24. Construction shall be carried out so that

density of population does not exceed

norms approved by Director General

Town and Country Department Haryana.

Agreed. Construction will be carried out so

that density of population does not exceed

norms approved by Director General Town

and Country Planning Department Haryana.

25. The Project proponent shall submit an

affidavit with the declaration that ground

water will not be used for construction

and only treated water should be used for

construction.

Agreed. Affidavit regarding no abstraction of

ground water is already submitted to SEIAA,

Haryana.

26. The project proponent shall not cut any

existing tree and project landscaping plan

should be modified to include those trees

in green area.

Agreed. Since the project site is a vacant

land; only small clearing of bushes will be

required.

7

27 The project proponent shall provide 3

meter high barricade around the project

area, dust screen for every floor above

the ground, proper sprinkling and

covering of stored material to restrict

dust and air pollution during

construction.

Agreed. The project proponent will provide 3

meter high barricade around the project area,

dust screen for every floor above the ground,

proper sprinkling and covering of stored

material to restrict dust and air pollution

during construction.

28 The project proponent shall construct a

sedimentation basin in the lower level of

the project site to trap pollutant and other

wastes during rains.

Agreed. Sedimentation basin will be

constructed in the lower level of the project

site to trap pollutant and other wastes during

rains.

29 The Project Proponent shall provide

proper Rasta of proper width and proper

strength for each project before the start

of construction.

Agreed. Proper Rasta of proper width and

proper strength for this project will be

provided before the start of construction.

30 The Project Proponent shall ensure that

the U-value of the glass is less than 3.177

and maximum solar heat gain co-

efficient is 0.25 for vertical fenestration.

Agreed. It will be ensured that the U-value of

the glass is less than 3.177 and maximum

solar heat gain co-efficient is 0.25 for vertical

fenestration.

31 The project proponent shall adequately

control dusts like silica dust, non-silica

and wood dust. Such dust shall not

spread outside project proponent shall

provide respiratory protective equipment

to all construction workers.

Agreed. There will be adequate provision to

control silica dust, non-silica and wood dust.

Such kind of dust will not be spread outside

the project. Respiratory protective

equipments will be provided to all the

construction workers.

32. The project proponent shall develop

complete civic infrastructure of the group

Housing colony including internal roads,

green belt development, sewerage line,

Rain water Harvesting arrangements,

storm water drainage system, solid waste

Agreed.

8

management site and provision for

treatment of biodegradable waste, STP,

water supply line, dual plumbing line,

electric supply line etc. and shall offer

possessions of the units/ flats thereafter.

33. The project proponent shall provide one

refuge area till 24 meter, one till 39

meter and one after 15 meter each, as per

National Building Code. The project

proponent shall not convert any refuse

area in the habitable space and it should

not be sold out/commercialized.

Since , it is an affordable group housing

project , providing refuge area is not

mandatory.

34. The project proponent shall provide fire

control room and fire officer for building

avobe 30 meter as per National Building

Code

Agreed. Fire control room and fire officer

will be provided for building above 30meter

as per National Building Code.

35. The project proponent shall obtain

permission of Mines and Geology

Department for excavation of soil before

the start of construction.

Agreed. Permission from mines and Geology

Department for excavation of soil has been

taken and a copy of it is attached as

Annexure 18.

36. The project proponent shall seek specific

prior approval from concerned local

authority/HUDA regarding provision of

storm drainage and sewerage system

including their integration with external

services of HUDA/ Local authorities

beside other required services of

HUDA /Local authorities beside other

required services before taking up any

construction activity.

Agreed. The project proponent has obtained

permission from HUDA for taking up

construction activity; copy of the same is

enclosed as Annexure 2.

37. The site for solid waste management Agreed. There is solid waste management

9

plant be earmarked on the layout plan

and the detailed project for setting up the

solid waste management plant shall be

submitted to the authority within one

month.

area earmarked on the layout plan and the

detailed project for setting up the solid waste

management plant will be submitted to the

authority in due course of time.

38. The project proponent shall submit the

copy of fire safety plan duly approved

by fire Department before the start of

construction.

Agreed. The approved fire safety scheme has

been attached as Annexure 21.

39. The project proponent shall discharge

excess of treated waste water/storm

water in the public drainage system and

shall seek permission of HUDA before

the start of construction.

Agreed. Permission from competent

authority to discharge sewage into public

sewer will be taken.

40. The project proponent shall maintain the

distance between STP and water supply

line.

Agreed. Suitable difference between STP and

water supply line will be maintained.

41. The project proponent shall ensure that

the stack height is 6 meter more than the

highest tower.

Agreed. Stack height will be provided as per

the CPCB norms.

42. The project proponent shall ensure that

structural stability to withstand

earthquake of magnitude 8.5 on Richter

scale.

Agreed. It is ensured that structural stability

of the building is such that it can withstand

earthquake of magnitude 8.5 on Richter

scale.

43. The project proponent shall implement

the revised site plan marked “A-8/81st”

showing Aaganwadi of 380 sqmt (G+1)

and community center of 380 sqmt

(G+1).

Since , it’s an affordable group housing

project, in Approved Drawing it is only

188.352sqmt & 192.54sqmt

44. The project proponent shall ensure that

no construction activity is undertaken

Agreed. No encroachment of the revenue

rasta will be done while carrying out the

10

either on surface or below or above

surface of revenue rasta passing through

the project area.

construction activities.

45. The project proponent shall indicate the

width and length of revenue rasta passing

through the project area on sign board

and shall display the same at both the

ends of revenue rasta stretch, for

awareness of public. Sign board shall

also display the message that this is a

public rasta/road and any citizen can use

it. There shall not be any gate with or

without guards on revenue rasta further

project proponent shall not encroach

revenue rasta and shall not cross internal

roads over revenue rasta.

Agreed. The width and length of revenue

rasta passing through the project area on sign

board will be displayed on the both the ends

of revenue rasta stretch, for awareness of

public. Sign board will also display the

message that this is a public rasta/road and

any citizen can use it. There will not be any

gate with or without guards on revenue rasta

further, project proponent shall not encroach

revenue rasta and shall not cross internal

roads over revenue rasta.

46. The project proponent shall ensure that

the plinth level of the building block to

be 1.5 meter above 100 years flood level

of the said Najafgarh jheel.

Agreed. The plinth level of the building

block will be kept 1.5 meter above 100 years

flood level of the said Najafgarh Jheel.

47. The project proponent shall obtain NOC

from HUDA as well as Irrigation

Department before the start of

construction, regarding possible adverse

effect of project proposal on the said

Najafgarh Jheel.

Agreed. The required NOC from the

concerned department will be taken in due

course of time.

PART A- SPECIFIC CONDITIONS : Operation Phase

a “Consent to Operate” shall be obtained

from Haryana State Pollution Control

Board under Air and Water Act and a

copy shall be submitted to the SEIAA,

Agreed. “Consent to Operate” will be

obtained from Haryana State Pollution

Control Board under Air and Water Act and a

copy will be submitted to the SEIAA,

11

Haryana. Haryana.

b The STP shall be installed for the

treatment of the sewage to the prescribed

standards including odor and treated

effluent will be recycled. The installation

of STP should be certified by an

independent expert and a report in this

regard should be submitted to the

SEIAA, Haryana before the project is

commissioned for operation. Tertiary

treatment of waste water is mandatory.

Discharge of treated sewage shall

confirm to norms and standards of

HSPCB, Panchkula. Project Proponent

shall implement such STP technology

which does not require filter backwash.

The project proponent shall essentially

provide two number of STP preferably

equipment to 50% of total capacity or

depending upon the initial occupancy as

the case may be.

Agreed. The STP will be installed for the

treatment of the sewage to the prescribed

standards including odor and treated effluent

will be recycled. The installation of STP will

be certified by an independent expert and a

report in this regard will be submitted to the

SEIAA, Haryana before the project is

commissioned for operation. Tertiary

treatment of wastewater is mandatory.

Discharge of treated sewage shall confirm to

norms and standards of HSPCB, Panchkula.

STP technology which does not require filter

backwash will be deployed. Keeping in mind,

the initial occupancy; modular STP will be

provided.

c Separation of the grey and black water

should be done by the use of dual

plumbing line. Treatment of 100% grey

water by decentralized treatment should

be done ensuring that the re-circulated

water should have BOD level less than

5mg/litre and the recycled water will be

used for flushing, gardening and DG set

cooling etc. to achieve zero discharge.

Separation of the grey and black water will

be done by the use of dual plumbing line.

Treatment of 100% grey water by

decentralized treatment will be done ensuring

that the re-circulated water will have BOD

level less than 5mg/litreand the recycled

water will be reused for flushing, gardening,

DG set cooling to achieve zero exit

discharge. Water Balance Diagram showing

Zero Discharge is enclosed as Annexure-7.

12

d For disinfection of the treated waste

water Ultra violet radiation or

ozonization process should be used.

Agreed. For disinfection of the treated

wastewater, UV Disinfection process will be

used.

e Diesel power generating sets proposed as

source of back-up power for lifts,

common area illumination and for

domestic use should be enclosed type

and conform to rules made under the

Environmental (Protection) Act, 1986.

The location of the DG sets should be in

the basement as promised by the project

proponent with appropriate stack height

i.e. above the roof level as per the CPCB

norms. The diesel used for DG sets

should be ultra-low sulphur diesel (35

ppm sulphur) instead of low sulphur

diesel.

Agreed. Diesel power generating sets

proposed as source of back-up power for

lifts, common area illumination and for

domestic use will be of enclosed type and

will conform to the rules made under the

Environmental (Protection) Act, 1986. The

diesel used for DG sets will be ultra-low

sulphur diesel (35 ppm sulphur) instead of

low sulphur diesel. There is no basement in

this project. Picture of D.G. sets is attached

as Annexure 20.

f Ambient noise level should be controlled

to ensure that it does not exceed the

prescribed standards both within and at

the boundary of the proposed Affordable

Group Housing Project.

Agreed. Ambient noise level will be

controlled within and at the boundaries of the

project ensuring compliance to regulatory

norms that is in accordance to Schedule-III of

The Noise Pollution (Regulation and

Control) Rules, 2000. This could be attained

through:

1) Development and maintenance of at

least 20% of the total land area for

tree plantation all around the project.

2) Providing acoustic enclosures to DG

sets.

3) Better traffic management.

4) Regular surveillance monitoring.

13

g The project proponent as stated in the

proposal should maintain at least 18.1%

as green cover area for tree plantation

especially all around the periphery of the

project and on the road sides preferably

with local species so as to provide

protection against noise and suspended

particulate matter. The open spaces

inside the project should be preferably

landscaped and covered with

vegetation/grass, herbs & shrubs. Only

locally available plant species shall be

used.

15.776% of the total project area ( as it is an

affordable group housing project) will be

maintained as used for tree plantation all

around the periphery and the road sides.

Species shall be endemic and chosen to

provide protection from dust and noise. In

addition open spaces within the boundaries

shall be landscaped whenever possible and to

the maximum extent. Landscape Plan is

enclosed as Annexure 8.

h The project proponent shall strive to

minimize water in irrigation of landscape

by minimizing grass area, using native

variety, xeriscaping and mulching,

utilizing efficient irrigation system,

scheduling irrigation only after checking

evapo-transpiration data.

Agreed. Minimum water will be used for

irrigation of landscape by minimizing grass

area, using native variety, xeriscaping and

mulching, utilizing efficient irrigation

system, scheduling irrigation only after

checking evapo-transpiration data.

i Rain water harvesting for roof run-off

and surface, as per plan submitted should

be implemented. Before recharging the

surface run-off, pre-treatment through

sedimentation tanks must be done to

remove suspended matter, oil and grease.

The bore well for rainwater recharging

should be kept at least 5m. Above the

highest ground water table. Care shall be

taken that contaminated water do not

enter any RWH pit. The project

Agreed. Rain water harvesting for roof run-

off and surface, as per plan submitted will be

implemented. Before recharging the surface

run-off, pre-treatment through sedimentation

tanks will be done to remove suspended

matter, oil and grease. The bore well for

rainwater recharging will be kept at least 5m

above the highest ground water table. Rain

water harvesting plan is enclosed as

Annexure 9.

14

proponent shall avoid RWH of first 10

minutes of rain fall. Roof top of the

building shall be without any toxic

material or paint which can contaminate

rain water. Wire mess and filters should

be used wherever required.

j The ground water level and its quality

should be monitored regularly in

consultation with Central Ground Water

Authority.

Agreed. The ground water level and its

quality will be monitored regularly in

consultation with Central Ground Water

Authority.

k A report on the energy conservation

norms finalized by Bureau of energy

efficiency should be prepared

incorporating details about building

material & technology, R & U Factors

etc. and submitted to the SEIAA,

Haryana in three month time.

Agreed. Report on energy conservation

measures conforming to energy conservation

norms finalized by BEE will be submitted in

due course of time. Energy conservation

measures are enclosed as Annexure 10.

l Energy conservation measures like

installation of LED for lighting the-areas

outside the building should be integral

part of the project design and should be

in place before project commissioning.

Use of solar panels must be adapted to

the maximum energy conservation.

Agreed. Energy conservation measures like

installation of LED for lighting the areas

outside the building will be integral part of

the project design and will be in place before

project commissioning. Solar panels will be

adapted for the maximum energy

conservation.

m The project proponent shall use zero

ozone depleting potential material in

insulation, refrigeration, air-conditioning

and adhesive. Project proponent shall

also provide Halon free fire suppression

system.

Agreed. Zero ozone depleting potential

material in insulation, refrigeration, air-

conditioning and adhesive will be used.

Halon free fire suppression will be provided.

15

n The solid waste generated should be

properly collected and segregated as per

the requirement of the MSW Rules, 2000

and as amended from time to time. The

bio-degradable waste should be

composed by vermin-composting at the

site war marked within the project area

and dry/inert solid waste should be

disposed-off to the approved sites for

land-filling after recovering material.

Agreed. The solid waste generated will be

properly collected and segregated as per the

requirement of the MSW Rules, 2000. The

bio-degradable waste will be composed by

the use of organic waste converter at the site

earmarked within the project area and

dry/inert solid waste will be disposed-off to

the approved sites for land-filling after

recovering material. Solid Waste

Management plan is enclosed as Annexure-

11.

o Provision of the solar water heating

systems shall be as per norms specified

by HAREDA & shall be made

operational in each building block

Agreed. The provision of the solar water

heating system will be as per the norms

specified by HAREDA and will be made

operational in each building block.

p The traffic plan and the parking plan

proposed by the project proponent should

be adhered to meticulously with further

scope of additional parking for future

requirement. There should be no traffic

congestion near the entry and exit points

from the roads adjoining the proposed

project site. Parking should be fully

internalized and no public space should

be used.

Agreed. Proposed parking plan will be

adhering to meticulously with further scope

of additional parking for future requirement.

There will be no traffic congestion near the

entry and exit points from the roads adjoining

the proposed project site. Parking will be

fully internalized and no public space should

be used. Parking cum traffic circulation plan

is enclosed as Annexure 12.

q The Project shall be operationalized only

when HUDA/local authority will provide

domestic water supply system in the

area.

Agreed. The Project will be operationalized

only when HUDA/local authority will

provide domestic water supply system in the

area.

r Operation and maintenance of STP, solid

waste management and electrical

Agreed. Operation and maintenance of STP,

solid waste management and electrical

16

Infrastructure, pollution control measures

shall be ensured even after the

completion of project.

Infrastructure, pollution control measures

will be ensured even after the completion of

sale.

s Different type of waste should be

disposed-off as per provisions of

municipal solid waste, biomedical waste,

hazardous waste, e-waste, batteries &

plastic rules made under Environment

Protection Act, 1986. Particularly E-

Waste and Battery waste shall be

disposed of as per existing E-waste

Management Rules 2011 and Batteries

Management Rules 2001. The project

proponent should maintain a collection

center for E-Waste and it should be

disposed of to only registered and

authorized dismantler/recycler.

Agreed. Different type of waste will be

disposed-off as per provisions of municipal

solid waste, biomedical waste, hazardous

waste, e-waste, batteries & plastic rules made

under Environment Protection Act, 1986.

Particularly E-Waste and Battery waste will

be disposed of as per existing E-waste

Management Rules, 2011 and Batteries

Management Rules, 2001. Collection center

for E-Waste will be maintained and it will be

disposed of to only registered and authorized

dismantler/recycler.

t Standards for discharge of environmental

pollutants as enshrined in various

schedules of rules 3 of Environment

Protection Rules 1986 shall be strictly

complied with.

Agreed. Standards for discharge of

environmental pollutants as enshrined in

various schedules of rules 3 of Environment

Protection Rules, 1986 will be strictly

complied with.

u Water supply shall be metered to

different residential units and different

utilities.

Agreed. Water supply will be metered to

different residential units and different

utilities.

v The project proponent shall ensure that

the stack height of DG sets is as per the

CPCB guide lines and also ensure that

the emission standards of noise and air

are within the CPCB prescribed limits.

Noise and Emission level of DG sets are

Agreed. It is ensured that the stack height of

DG sets is as per the CPCB guidelines and

also that the emission standards of noise and

air are within the CPCB prescribed limits.

Noise and Emission level of DG sets greater

than 800KVA will be maintained as per

17

greater than 800KVA shall be as per

CBCB latest standards for high capacity

DG sets.

CBCB latest standards for high capacity DG

sets.

w All electric supply exceeding 100amp, 3-

phase shall maintain the power factor

between 0.98 lag to 1 at the point of

connection.

Agreed. All electric supply exceeding

100amp, 3-phase will maintain the power

factor between 0.98 lag to 1 at the point of

connection.

x The project proponent shall use only

treated water instead of fresh water for

HVAC and DG cooling. The project

proponent shall use evaporative cooling

technology and double stage cooling

system for HVAC in order to reduce

water consumption. Further temperature,

relative humidity during summer and

winter session should be kept at optimal

level. Variable speed drive, best co-

efficient of performance, as well as

optimal integrated point load value and

minimum outside fresh air supply may

be resorted for conservation of power

and water. Coil type cooling DG sets

shall be used for saving cooling water

consumption for water cooled DG sets.

Agreed. It is ensured that treated water

instead of fresh water will be used for

horticulture, flushing and DG cooling. As it

is affordable housing project; so, HVAC will

not be provided. Further temperature, relative

humidity during summer and winter session

will be kept at optimal level. Variable speed

drive, best co-efficient of performance, as

well as optimal integrated point load value

and minimum outside fresh air supply will be

resorted for conservation of power and water.

y The PP shall ensure that the transformer

is constructed with high quality grain

oriented, low loss silicon steel and virgin

electrolyte grade copper. The PP shall

obtain manufacturer’s certificate also for

that.

Agreed. We will ensure that the transformer

is constructed with high quality grain

oriented, low loss silicon steel and virgin

electrolyte grade copper and manufacturer’s

certificate will be obtained.

z The project proponent shall ensure that Agreed. We will ensure that exit velocity

18

exit velocity from the stack should be

sufficiently high. Stack shall be designed

in such a way that there is no stack

down-wash under any meteorological

conditions.

from the stack will be sufficiently high.

Stack will be designed in such a way that

there is no stack down-wash under any

meteorological conditions.

aa The project proponent shall provide

water sprinkling system in the project

area to suppress the dust in addition to

the already suggested mitigation

measures in the Air Environment

Chapter of EMP.

Agreed. Water sprinkling will be carried out

by the labour.

ab The project proponent shall ensure

proper Air Ventilation and light system

in the basement area for comfortable

living of human being and shall ensure

that number of Air Changes per

hour/(ACH) in basement never fall

below 15.In case of emergency capacity

for increasing ACH to the extent of 30

must be provided by the project

proponent.

Agreed. The project proponent will ensure

proper air ventilation and lighting.

ac The project proponent shall ensure

drinking/ domestic water supply as per

prescribed standards till treated water

supply is made available by HUDA.

Agreed. We will ensure drinking/domestic

water supply as per prescribed standards till

treated water supply is made available by

HUDA.

ad The project proponent shall provide

addition green area on terrace and roof

top.

Agreed. The project proponent will provide

additional green area on terrace and roof top.

ae The project proponent shall install solar

panel for energy conservation.

Agreed. The project proponent will install

solar panel for energy conservation

19

PART-B GENERAL CONDITION:

I. The project proponent should ensure the

commitments made in Form-1, Form-1A,

EIA/EMP and other documents

submitted to the SEIAA for protection of

environment and proposed

environmental safeguards are complied

with in letter and spirit. In case of

contradiction between two or more

documents on any point, the most

environmentally friendly commitment on

the point shall be taken as commitment

by project proponent.

Agreed. It will be ensured that commitments

made in Form-1, Form-1A, EIA/EMP and

other documents submitted to the SEIAA for

protection of environment and proposed

environmental safeguards are complied with

in letter and spirit. In case of contradiction

between two or more documents on any

point, the most environmentally friendly

commitment on the point will be taken as

priority.

II. The project proponent shall also submit

six monthly compliance of the reports

on the status of compliance of the

stipulated EC conditions including result

of monitored data (both in hard copy as

well as by e-mail)to the northern regional

Office, MoEF, the respective Zonal

office of CPCB, HSPCB and SEIAA ,

Haryana.

Agreed. This is first compliance. Six monthly

monitoring reports will be submitted to the

northern regional Office, MoEF, the

respective Zonal office of CPCB, HSPCB

and SEIAA, Haryana.

III. STP outlet after stabilization and stack

emission shall be monitored monthly.

Other environmental parameters and

green belt shall be monitored on

quarterly basis. After every 3 months, the

project proponent shall conduct

environmental audit and shall take

corrective measure, if required, without

delay.

Agreed. STP outlet after stabilization and

stack emission will be monitored monthly.

Other environmental parameters and green

belt will be monitored on quarterly basis.

After every 3 months, the project proponent

will conduct environmental audit and will

take corrective measure, if required, without

delay.

20

IV. The SEIAA, Haryana reserves the right

to add additional safeguard measures

subsequently, if found necessary.

Environmental Clearance granted will be

revoked if it is found that false

information has been given for getting

approval of this project. SEIAA reserves

the right to revoke the clearance if

conditions stipulated are not

implemented to the satisfaction of

SEIAA/MOEF.

Agreed.

V. The project proponent shall not violate

any judicial orders/ pronouncements

issued by the Court/ Tribunal.

Agreed.

VI. All other statutory clearances such as the

approvals for storage of diesel from

Chief Controller of Explosives, Fire

Department, Civil Aviation Department,

Forest Conservation Act, 1980 and

Wildlife (Protection) Act, 1972, Forest

Act, 1927, PLPA 1900 etc. shall be

obtained, as applicable by the project

proponents from the respective

authorities prior to construction of the

project.

Agreed. AAI NOC receiving from Civil

Aviation Department for Height clearance

and Aravalli clearance from D.C. has already

been granted and are enclosed as Annexure

– 13& 14respectively. For forest NOC please

refer Annexure 4.

VII. The project proponent should inform the

public that the project has been accorded

Environment Clearance by the SEIAA

and copies of the clearance letter are

available with the Haryana State

Pollution Control Board & SEIAA. This

Agreed. Advertisement copy of notice in

Newspaper will be submitted in the next

compliance report.

21

should be advertised within 7 days from

the date of issue of clearance letter at

least in two local newspapers that are

widely circulated in the region and the

copy of the same be forwarded to SEIAA

Haryana. A copy of Environment

Clearance collections shall also be put on

project proponent’s website for public

awareness.

VIII. Under the provisions of Environment

(Protection) Act, 1986, legal action shall

be initiated against the project proponent

if it was found that construction of the

project has been started without

obtaining Prior Environmental

Clearance.

Agreed. Environmental clearance has been

obtained vide letter no. SEIAA/HR/2014/882

dated 30.06.2014from SEIAA. EC Letter is

attached as Annexure - 15.

IX. Any appeal against this Environmental

Clearance shall lie with the National

Green Tribunal, if preferred within a

period of 30 days as prescribed under

Section 16 of the National Green

Tribunal Act, 2010.

Agreed.

X. The project proponent shall put in place

Corporate Environment Policy as

mentioned in MOEF, GOI, ON No. J-

11013/41/2006-IA II (I) dated 26.04.12

within 3 months period. Latest Corporate

Environment Policy should be submitted

to SEIAA within 3 months of issuance of

this letter.

Agreed. CESR Plan will be submitted to

SEIAA.

XI. The fund ear-marked for environment Agreed.

22

protection measures should be kept in

separate account and should not be

diverted for other purposes and year wise

expenditure shall be reported to the

SEIAA/RO MoEF GOI under rules

prescribed for Environment Audit.

XII. The PP shall ensure the compliance of

Forest Department, Haryana Notification

no. S.O.121/PA2/1900/S.4/97 dated

28.11.1997.

Agreed. The compliance of Forest

Department, Haryana Notification no.

S.O.121/PA2/1900/S.4/97 dated 28.11.1997

will be done.

XIII. The project proponent shall ensure that

no vehicle during construction/operation

phase enter the project premises without

valid ‘Pollution Under Control’

certificate from competent Authority.

Agreed. It will be ensured that no vehicle

during construction/operation phase enters

the project premises without valid ‘Pollution

Under Control’ certificate from competent

Authority.

XIV. The PP is responsible for compliance of

all conditions in Environmental

Clearance letter and project proponent

can not absolve himself/herself of the

responsibility by shifting it to any

contractor engaged by project proponent.

Agreed. We will be responsible for

compliance of all conditions in

Environmental Clearance letter and project

proponent cannot absolve himself/herself of

the responsibility by shifting it to any

contractor engaged by project proponent.

XV. The Project proponent shall seek fresh

Environmental Clearance if at any stage

there is change in the planning of the

proposed project.

Agreed. Fresh Environmental Clearance will

be sought if at any stage there is change in

the planning of the project.

XVI. Besides the developer/ applicant, he

responsibility to ensure the compliance

of Environmental clearance if at any

stage there is change in the planning of

the proposed project.

Agreed. Besides the developer/ applicant, the

responsibility to ensure the compliance of

Environmental clearance if at any stage there

is change in the planning of the project.

XVII. The proponent shall upload the status of Agreed.

23

compliance of the stipulated EC

conditions, including results of

monitored data on their website and shall

update the same periodically. It shall

simultaneously be sent to the regional

office of levels namely: PM2.5, PM10,

SOx, NOx, Ozone, Lead, CO, Benzene,

Ammonia, Benzopyrine, arsenic and

Nickel, (Ambient levels as well as stack

emissions) or critical sectoral parameters,

indicated for the project shall be

monitored and displayed at convenient

location near the main gate of the

company in the public domain.

XVIII. The environmental statement for each

financial year ending 31st March in

form-V as is mandated to be submitted

by the project proponent to the HSPCB

Panchkula subsequently, shall also be

sent to the respective Regional Office of

MoEF by e-mail.

Agreed. The environmental statement for

each financial year ending 31stMarch in

form-V as is mandated to be submitted by the

project proponent to the HSPCB Panchkula

subsequently, will also be sent to the

respective Regional Office of MoEF by e-

mail.

XIX. The project proponent shall conduct

environment audit at every three months

interval and thereafter corrected measure

shall be tken without any delay. Details

of environment audit and corrective

measures shall be submitted in the

monitoring report.

Agreed. We will conduct environment audit

at every three months interval and thereafter

corrected measure shall be taken without any

delay. Details of environment audit and

corrective measures will be submitted in the

monitoring report.

XX. Corporate Environment and Social

Responsibility (CESR) shall be laid

down by the project proponent (2% shall

Agreed. CESR will be carried out during the

construction of the project.

24

be earmarked) as per guidelines of

MoEF, GOI Office Memorandum No. J-

11013/41/2006-IA.II (I) dated

18.05.2012 and ministry of Corporate

Affairs, GOI Notification Dated

27.02.2014. A separate audit statement

shall be submitted in the compliance.

Environment related work proposed to be

executed under this responsibility shall

be undertaken simultaneously. The

project proponent shall select and

prepare the list of the work for

implementation of CESR of its own

choice and shall submit the same before

the start of construction.

(B) COMPLIANCE TO ENVIRONMENTAL IMPACT ASSESSMENT GUIDANCE MANUAL 2010 OF MoEF

SI.

No.Points as per EIA Guidance Manual Status of Compliance

A. Air Environment

1. Wind erosion is a serious problem in

areas where the ground is virtually bare

and devoid of vegetation. Vegetation

methods are found to be most effective

in the form of windbreaks and

shelterbelts.

The site will be enclosed with sufficiently high

barricade wall around the project boundary

which will act as a wind breaker.

Vegetation will be developed during the

operation phase of the project.

25

SI.

No.Points as per EIA Guidance Manual Status of Compliance

2. Sprinkling of water and fine spray from

nozzles to suppress the dust.

Water sprinkling will be carried out through

tanker water regularly at site for dust

suppression and logbook will be maintained.

3. On-Road-Inspection should be done for

black smoke generating machinery.

All the machineries deployed at site will be of

good standard and of reputed make and

comply with emission & noise standards.

Inspections and maintenance of construction

machineries and vehicles will be carried out

periodically.

4. Promotion of use of cleaner fuel should

be done.

Ultra low sulphur diesel (ULSD) (sulphur

content less than 50ppm) will be used for

running of DG sets, vehicles and construction

machineries.

5. All DG sets should comply emission

norms notified by MoEF.

The DG sets will be acoustically enclosed

which will conform to the permissible air

emission and noise standards notified by

MoEF. DG sets will be fitted with stack of

sufficient height as prescribed in emission

norms notified by MoEF. Monitoring of

emissions of DG sets will be carried out

periodically.

6. Vehicles having pollution under control

certificate may be allowed to ply.

Only PUC certified vehicles will be allowed to

enter the project site. The vehicles without

valid Pollution under Check (PUC) certificate

are not permitted at project site.

26

SI.

No.Points as per EIA Guidance Manual Status of Compliance

7. Use of covering sheet to prevent dust

dispersion at buildings and

infrastructure sites, which are being

constructed.

Sheets will be used to prevent dust dispersion.

8. Use of covering sheets should be done

for trucks to prevent dust dispersion

from the trucks, implemented by district

offices.

The trucks carrying construction materials and

debris will be covered by tarpaulin and plastic

sheets.

9. Paving is a more permanent solution to

dust control, suitable for longer duration

projects. High cost is the major

drawback to paving.

During construction, access roads will be

covered with gravels to prevent dust emission.

(At the completion stage of the project, all

permanent internal roads & walkway will be

paved and greeneries will be developed)

10. Reducing the speed of a vehicle to 20

kmph can reduce emissions by a large

extent. Speed bumps are commonly

used to ensure speed reduction. In cases

where speed reduction cannot

effectively reduce fugitive dust, it may

be necessary to divert traffic to nearby

paved areas.

Speed of the vehicles will be restricted by

erecting speed bumps at regular intervals at

project site and proper signage will be

provided for guided vehicular movement and

speed restrictions.

27

SI.

No.Points as per EIA Guidance Manual Status of Compliance

11. Material storages/ warehouses-Care

should be taken to keep all material

storages adequately covered and

contained so that they are not exposed to

situations where winds on site could

lead to dust/ particulate emissions.

Fabrics and plastics for covering piles of

soils and debris is an effective means to

reduce fugitive dust.

We are making concrete at site through Batch

Mix Plant.

B. Noise Environment

1. Setting up the barriers: National

Building Code 2005 suggests that

design solutions such as barrier blocks

should be used to reduce external LA10

noise levels to at least 60-70dB(A) at

any point 1.0 m from any inward

looking façade.

The site will be enclosed with sufficiently high

barricade wall around the project boundary to

control propagation.

The DG sets will be installed in acoustic

enclosure which conforms to the permissible

noise standards notified by MOEF. DG sets

will be new and certified by manufacturers.

C. Water Environment

1. Curing water should be sprayed on

concrete structures; free flow of water

should not be allowed for curing.

Curing water will be sprayed on concrete

structures.

2. After liberal curing on the first day, all

concrete structures should be painted

with curing chemical to save water. This

will stop daily water curing hence save

water.

Curing compounds will be used to save water

for curing.

28

SI.

No.Points as per EIA Guidance Manual Status of Compliance

3. Concrete structures should be covered

with thick cloth/gunny bags and then

water should be sprayed on them. This

would avoid water rebound and will

ensure sustained and complete curing.

Concrete structures will be covered with thick

clothes/ gunny bags and water spraying will be

taken into practice to prevent water loss.

4. Ponds should be made using cement and

sand mortar to avoid water flowing

away from the flat surface while curing

No water will be used for curing hence, ponds

are not proposed in the site.

5. Water ponding should be done on all

sunken slabs; this would also highlight

the importance of having an impervious

formwork.

No water will be used for curing.

(C) COMPLIANCE TO NGT ORDER DATED 10.04.2015 RELATED TO CONSTRUCTION

29

SI.

No.NGT Order dated 10.04.2015 Status of Compliance

1. Every builder or owner shall put tarpaulin on

scaffolding around the area of construction

and the building. No person including

builder, owner can be permitted to store any

construction material particularly sand on

any part of the street, roads in any colony.

Tarpaulin covers will be provided around the area

of construction wherever required. No construction

materials such as cement, sand and aggregates will

be stored at site. Ready-mixed concrete will be used

for concrete work at project site which will be

transported from the off-site batching plant.

2. The construction material of any kind that is

stored in the site will be fully covered in all

respects so that it does not disperse in the Air

in any form.

Tarpaulin covers will be provided around the area

of construction wherever required.

3. All the construction material and debris shall

be carried in the trucks or other vehicles

which are fully covered and protected so as

to ensure that the construction debris or the

construction material does not get dispersed

into the air or atmosphere, in any form

whatsoever.

The trucks carrying construction materials and

debris will be covered by tarpaulin and plastic

sheets.

4. The dust emissions from the construction site

should be completely controlled and all

precautions taken in that behalf.

All necessary precautions will be adopted to control

the dust emissions. Water sprinkling at site will be

carried out through tanker water regularly at site for

dust suppression and logbook will be maintained.

5. The vehicles carrying construction material

and construction debris of any kind should be

cleaned before it is permitted to ply on the

road after unloading of such material.

“Wheel Washing Bay” has been provided at main

entry road and Batching Plant sites. Wheels of

construction equipment/ vehicles and trucks will be

washed before allowing it to ply on the road.

30

SI.

No.NGT Order dated 10.04.2015 Status of Compliance

6. Every worker working on the construction

site and involved in loading, unloading and

carriage of construction material and

construction debris shall be provided with

mask to prevent inhalation of dust particles.

All safety measures will be taken. Construction

workers has been provided with personal protective

equipment (PPE) as required under the health &

safety norms. The pictures of construction workers

using PPE is attached as Annexure 16.

7. Every owner and or builder shall be under

obligation to provide all medical help,

investigation and treatment to the workers

involved in the construction of building and

carry of construction material and debris

relatable to dust emission.

Fully fledged first aid facility has been provided at

the construction site and regular medical check-ups

by Doctor will be conducted for construction

workers. Logbook will be maintained with medical

treatment details of the workers.

8. It shall be the responsibility of every builder

to transport construction material and debris

waste to construction site, dumping site or

any other place in accordance with rules and

in terms of this order.

When debris will be generated, it will be disposed

off at Government Authorized landfills.

9. All to take appropriate measures and to

ensure that the terms and conditions of the

earlier order and these orders should strictly

comply with by fixing sprinklers, creations

of green air barriers.

Regular sprinkling of water will be carried out at

site through tanker.

10. Compulsory use of wet jet in grinding and

stone cutting.

All necessary precautions will be taken in the stone

cutting and grinding area which will be done at later

stage of construction.

11. Wind breaking walls around construction

site.

The site will be enclosed with sufficiently high

barricade wall around the project boundary which

acts as a wind breaker.

31

SI.

No.NGT Order dated 10.04.2015 Status of Compliance

12. All the builders who are building

commercial, residential complexes which are

covered under the EIA Notification of 2006

shall provide green belt around the building

that they construct. All Authorities shall

ensure that such green belts are in existence

prior to issuance of occupancy certificate.

Green area will be developed at the end of

construction stage as per approved building plan.

32