Upload
ten-old-square
View
222
Download
3
Tags:
Embed Size (px)
DESCRIPTION
An introduction to overage agreements
Citation preview
TRIGGERS AND PITFALLS: AN INTRODUCTION TO OVERAGE AGREEMENTS
DAVID SCHMITZ
1. The purpose of overage is to enable the seller of land to participate in profits
which the purchaser or in some cases a successor will receive if specified events
occur – often, though not always, including the grant of planning permission –
and the value of the land thereby increases. Its appeal for the seller lies in the
fact that he may ultimately receive more for his land than he would if he sold it
at its current value, even if that value reflected the possibility that the events
might later come to pass; while its appeal to the buyer lies in the fact that the
presence of an overage clause will persuade the seller to demand less up front
than would otherwise be the case.
2. There are, however, a number of problems which can arise, and often they are
not properly considered. As observed in the leading book on the subject1,
“In practice, overage provisions are often included as a ‘bolt on’, particularly where the prospect of planning consent is remote. The main purpose which the parties have in mind is an immediate sale for a price representing current use value, but sometimes during the discussions, a provision is added to cover the possibility of future development. At the time of the original sale, this may be a distant prospect, and, therefore, the parties may not think it worth paying much attention to or worth going into overage issues in detail.”
1 Jessel, Development Overage and Clawback (2001) page 197
It is therefore not surprising that significant caselaw on mistake and
rectification concerns overage provisions. See, for example, Chartbrook Ltd. v
Persimmon Homes Ltd. [2009] AC 1011.
3. Needless to say, if the hoped-for event should come to pass, but the
expectations of either party are disappointed, any failure on the part of the
solicitor to secure his client’s position could lead to liability in negligence. The
principal sources of difficulty are as follows:
(1) The clause may fail to trigger a right to receive overage in circumstances
where the seller might reasonably have expected it to do so.
(2) The clause may encumber the buyer with an obligation to pay overage
in circumstances where he might reasonably not have expected to be so
encumbered.
(3) The wording may fail correctly to define the amount which the seller is
supposed to receive.
(4) Above all, there may be a failure to preserve the seller’s rights where
the property is transferred to a third party.
It is not possible to enumerate all of the ways in which an agreement may fail,
in any of the ways outlined above, to protect the parties, but it is useful to
elaborate each of the of the above categories and, by way of some cautionary
tales, to give examples of some useful precautions to take.
The general approach
4. The nature of the risks will depend upon the nature of the trigger which the
parties choose – be it, to take the most common examples, the grant of
planning permission, the building of the development or the sale of the
property. The form of trigger which is adopted is, of course, a matter for
negotiation between the parties in the light of their commercial interests, but it
is possible to indicate the kinds of problem to which each can give rise.
5. Where the trigger consists of the grant of planning permission, a problem
generally will only arise, firstly if there is a question as to whether the
permission which is obtained matches the specification in the agreement, or
secondly if payment is to be deferred and the payer defaults. Where the trigger
requires the completion of a development or its sale, the position is less
straightforward. The seller may therefore prefer to have the overage triggered
by the grant of planning permission and for it to be paid immediately
thereafter.
6. On the other hand, the buyer may not be in a position to agree to payment of
overage on the grant of planning permission, because the grant of permission
does not, of itself, produce money. It is only if the buyer is confident of being
able to raise sufficient finance upon obtaining permission, both to pay the
overage and to pay the development costs that this can be a practical solution.
For this reason, or simply because the buyer may wish to accept certain risks in
exchange for being able to obtain a greater reward after the completion of the
development, the parties may choose to define the trigger in terms of the
completion of the development or of its sale. If this is the case, then the
following problems must be addressed:
(1) It may be difficult to determine when the works are done. There may be
no certificate of practical completion, which settles the question.
(2) The buyer may become insolvent and a mortgagee may exercise its
powers of sale to an onward purchaser who may not be bound by the
obligation (see below with regard to the position as against successors in
title).
(3) The buyer, moreover, may simply decide not to build within the period
during which the trigger is expressed to operate.
7. For these reasons, it is wise to consider incorporating into the agreement an
obligation to build in accordance with the planning permission, and to
complete the building on or before the date when overage is to become
payable. Provision can be made for a valuation to be made as at that time,
either of the building as built or of the notional building which ought to have
been built. See Stephens v Cannon [2005] EWCA Civ 222, where valuations were
done on such a notional building in the assessment of damages for breach of
obligations to build in accordance with the planning permission and to pay
overage on the value of what was built. If a term such as this cannot be
achieved, it is especially important to draft so as to avoid ambiguity as to when
the obligation to pay overage is triggered. In this regard, consideration should
be given to some of the drafting matters dealt with below, with a view to
reducing the parties’ risks.
8. It is also necessary, in all circumstances, to consider the means by which the
obligation to pay overage can be secured for the benefit of the seller, both
against the buyer’s mortgagees and against the buyer’s onward purchasers.
Ideally, the obligation to secure the payment will be secured by a charge, which
will protect the seller’s rights not only as against the buyer’s creditors but also
as against the buyer’s onward purchasers. If the charge is expressed to secure
contingent liabilities, it will then protect the seller’s rights, even if they are
dependent upon a contingency which has not yet occurred – Re Rudd & Son
Ltd. [1986] 2 BCC 98, 955. However, a first charge will seldom be possible to
achieve, because the buyer’s mortgagee will almost certainly object to any
charge which has priority to its own charge; indeed the buyer’s mortgagee may
object to there being any charge at all. In such a case it is a matter for
negotiation as to the extent, if at all, to which the buyer and his mortgagee are
willing to subordinate their respective interests to the seller in exchange for the
advantage of paying a lower purchase price which is only subject to increase
upon the happening of certain (possibly remote) contingencies. If it is not
possible to negotiate such a charge, it will be necessary at the least for the
buyer to be required to furnish any relevant information promptly so that the
seller will know, immediately the buyer’s obligations become enforceable. The
solicitor will also need to try to protect the seller’s position by other means as
against onward purchasers, or failing that to advise the seller that his position is
exposed and that he may therefore prefer to give up the idea of overage
altogether and to hold out instead for a higher price, payable once and for all,
which reflects the current “hope value” of the contingency occurring, but which
does not otherwise seek to share the benefits of the contingency. These points
are dealt with further below.
Failure of the trigger
9. The description of the kind of development which, if built, will trigger the
obligation to pay overage, may be expressed too restrictively and may
therefore be treated as excluding developments which might otherwise be
expected to fall within the description.
In Walker v Kenley [2008] EWHC 370 (Ch) the agreement was for overage to be payable if the buyer obtained planning permission to develop the property as residential flats and if he carried out that development within five years. The buyer obtained permission to build properties which were restricted to use as “holiday apartments.” It was held that holiday apartments did not fall within the description of “residential flats” as per the agreement, and that overage therefore was not payable.
As with other cases on points of construction, this case does not support any
rule of law to the effect that to describe a property “residential” will always
import the idea of full-time unrestricted residential occupancy – ie that the
property must be capable of being a full-time home in order for it to be
described thus. In this particular case, the buyer was aided by the fact that the
parties at the time of the agreement were well aware of the distinction
between holiday and permanent accommodation because there was an issue
with the local planning authority on that very point. In other cases, by contrast,
there may be circumstances which aid the seller and lead to the opposite
conclusion. Walker v Kenley, however, does show how a casually placed
adjective (“residential” n this instance) can land the parties into protracted
litigation.
10. Drafting errors which lead to the overage trigger being drawn too narrowly can
occur because very often the obligation to pay overage is not the only
contingency for which a contract of sale may provide. For example, the grant of
planning permission to effect a certain type of development, may be a
condition of the contact becoming binding in the first place, while the actual
building of the development may be the event which triggers the obligation to
pay overage. In such a case, a careless draftsman may unnecessarily equate the
description of the required planning permission with the description of the
building works which trigger the overage obligation. The risk to the seller is that
the buyer, having obtained permission, may change his mind and seek
permission to build something else. It is unlikely that a buyer could get out of
the obligation to pay overage by unilaterally abandoning the planning
permission, because the Court would view the commercial purpose for overage
as providing for the sharing of development profits, the form which the
development takes being irrelevant to this object. Nonetheless, unnecessary
litigation can ensue if the building works that are intended to trigger the
overage obligation are described with unnecessary particularity, and the
draftsman should therefore be alert to the possibility of doing this
inadvertently.
11. Expectations may be disappointed if unforeseen events make it impossible for
the contractual terms to be carried out. Paradoxically, the more detail in which
the purchaser’s obligations are described, the more readily the purchaser may
be enabled to plead supervening impossibility.
In Hildron Finance Ltd. v Sunley Holdings Ltd. [2010] EWHC 1688, an agreement was made in 1986 for the sale of a block of flats, in which all but one of the flats was let out under long leases and the one remaining flat was retained as a porter’s flat. The agreement provided that if the flat should not be required for use as a porter’s flat within the 21 years immediately following, the buyer should sell it and share the proceeds of sale with the seller.
In 1993, Parliament passed the Leasehold Reform, Housing and Urban Development Act which gave the tenants of a block of flats the right to acquire their landlord’s interest through the exercise collective enfranchisement. In November, 2004, the tenants served a notice under the Act, as a result of which it thereafter became unlawful, and indeed impossible, for the buyer to sell the property or to dispose of it otherwise than in accordance with the Act. In proceedings between the buyer and the tenants, it was held that £200,000 was the portion of the of the value of the block which was to be attributed to the value of the flat, while the expert witnesses of the buyer and the tenants agreed it to be worth £300,000 on the open market. The flat in the meantime ceased to be used as a porter’s flat. The block was subsequently acquired by the tenants on terms that included the payment of £200,000 for the flat.
Although the seller contended that an acquisition by the tenants under statutory powers should be treated as equivalent to the sale of the flat, it was held that the buyer was not bound to share the proceeds. The agreement had spelled out exactly what had to be done following the trigger event (the cesser of use as porter’s accommodation), namely the granting of a long lease, the marketing of the lease, and the sale of the lease at a price approved by the seller. These events having become impossible, the obligation lapsed; the Court held that the compulsory disposal via of the flat via the statutory machinery at a price below market value was not equivalent to a sale over which the parties had control.
It is therefore wise for the seller to seek to have the agreement provide that
overage shall be payable, whether the land is sold or acquired compulsorily by
the exercise of a public or private right, entitlement or power. The general
lesson for the seller’s solicitors is that the description of the trigger for the
overage obligation should be drafted in terms that are as broad as possible.
12. It sometimes happens that land which is purchased, subject to an overage
agreement is not itself developed, but is instead kept as open space in order to
facilitate an application for permission to develop neighbouring land, which the
developer happens to own or subsequently acquires. Alternatively, the overage
land may be used to provide access or parking for neighbouring land, in which
case it will either not be sold off or be sold at a relatively low price in
comparison to the land which is built upon. This can happen especially where
parcels of land are being assembled in order to provide a large site for later
development. If the seller envisages the possibility of this occurring, he should
ensure that the agreement provides for overage to be payable as a share of the
uplift of the whole of any land which obtains planning permission and which
includes the land that is sold.
13. Where the overage obligation is expressed to comprise a share of the buyer’s
profits, particular caution is required, as it would be in the case of a joint
venture. First of all, due diligence is required. Secondly, if there is not to be a
joint venture in which the seller is placed in a position to veto over what is
spent, regard must be had to the fact that the buyer may be doing the building
works through persons who are connected with him and paying those persons
accordingly. In order for the profits not to be seen to be depressed artificially,
there must at least be provision for disclosure by the buyer of all bills,
payments and architects’ and surveyors certificates. The solicitor must take
pains to tell the client, especially if the client is not experienced in these
matters, that the client will stand at the end of the queue and will only be paid
(if at all) once the mortgagees and the builders have been paid in full.
The trigger going off unexpectedly
14. It should be remembered that anyone can apply for planning permission to
develop land, whether he owns it or not. Therefore, if the grant of planning
permission is to trigger an obligation to pay overage, care should be taken to
avoid imposing the obligation to pay overage where planning permission is
obtained which the buyer neither seeks nor wants.
In Micro Design Group Ltd. v BDW Trading Ltd. [2008] EWCA Civ 448 the seller sold land under a contract which provided that overage should be payable if “improved planning permission” were granted and which did not specify at whose behest the planning permission should be acquired in order for the overage obligation to be triggered. Following the sale, the seller obtained a further planning permission and then claimed an overage payment from the buyer. The first instance judge allowed the claim. Although the Court of Appeal subsequently dismissed it and observed (at paragraph 22) that , “no person would enter into an agreement to buy development land with planning permission and then give the seller the right after completion to obtain further payments by seeking and obtaining planning permission itself which the buyer might not want.” it is nonetheless strongly arguable that the buyer only succeeded because the contract contained other features which enabled the Court to infer, as a matter of the construction of that
particular contract, that only permission sought by the buyer would “count.” Had those features been absent, the Court might have had to find that the seller was entitled to overage on the true construction of the agreement.
Micro Design was a close run thing which went as far as the Court of Appeal.
The moral for the draftsman, therefore, is not to leave this issue to chance.
14. Sometimes it may be in the buyer’s interest, rather than the seller’s, to contend
that the trigger has gone off.
In Hallam Land Management Ltd. v UK Coal Mining Ltd. [2002] 2EGLR 80 the claimant was granted an option which was exercisable upon submitting an application for the development of a 42.5 acre site at a price to be governed by the number of “developable acres” as determined by the terms of the planning permission. The claimant submitted an application to develop just 2.5 acres and this was granted. The claimant then purported to exercise the option to buy the whole 42.5 acres on the basis that only 2.5 acres was developable. It was held that by the Court of Appeal affirming the judge at first instance that there had been no application for development within the meaning of the agreement, and that therefore there had been no exercise of the option.
Although the seller’s interest was in fact protected, a Court of Appeal decision
was required. It is therefore important that close attention be given to the
definition of the planning permission which is to trigger the overage provision
and that provision be made for repeated payments of overage whenever any
part of the land may receive planning permission, lest the buyer be able to get
out of the obligation too cheaply.
15. Where the overage agreement provides that it will not be payable in certain
circumstances, the Court will not stretch the meaning of that provision,
especially if the buyer seeks to have it apply in circumstances where it was
within the buyer’s control whether the requisite circumstances arose or not.
In Ministry of Defence v County & Metropolitan Homes Conveyancing [2002] NPC 130, the buyer agreed to pay overage if it obtained planning permission for residential land forming part of a 70 hectare site, but it was also provided that overage would not be payable if 37 houses in a portion of the land were demolished. The buyer demolished 35 of them but converted two of them into a village shop to comply with a planning requirement that a village shop should be provided. The seller claimed overage and the buyer sought to defend on the basis that the conversion of the houses amounted to a demolition for the purposes of the agreement. The Court held that the terms of agreement should be given their full effect, that the conversion was not a demolition and that it had been the buyer’s choice that the two houses should remain undemolished.
How much is the seller to receive
15. Often, the amount of overage payable will be determined by a formula which
specifies a percentage. In such cases, the difficult question which can arise is, “a
percentage of what?” Normally these cases will turn solely upon the terms of
the particular agreements which have given rise to them, or upon the facts
which give rise to claims for relief on the basis of mistake or misrepresentation
or to claims for rectification. Four general points, however, are worth making.
16. Firstly, it is necessary to define with care the land which, when sold, will be
subject to the overage obligation. In Bride Hall Estates Ltd. v St. George North
London Ltd. [2004] EWCA Civ 141, a dispute arose as to whether the overage
should represent a percentage of the sale proceeds of a flat, or whether it
should also include a share of the proceeds of the car parking. The Seller
succeeded, but in the Court of Appeal.
17. Secondly, it is risky to provide without elaboration that the overage is to be
calculated as a percentage of the proceeds of sale. The sale may be made at an
undervalue because the onward purchaser Is connected to the buyer, or
because it is done as a loss-leader in aid of another transaction. It is therefore
wise to provide for the seller to be able to require a valuation. Further, it is
necessary to provide for the possibility that the buyer will grant a lease over the
land, rather than sell it, or that the buyer might occupy the land himself. One
way in which these cases could be met would be by providing that if the land is
not sold by a given date, overage will be based upon a valuation to be obtained
as of that date.
18. Thirdly, if one party is relatively inexperienced in these transactions, while the
other party has substantial experience, the Court will be slow to grant the
experienced party relief on the ground of mistake.
In George Wimpey UK Ltd v VI Construction Ltd. [2005] EWCA Civ 77, there was an overage agreement based upon the sale proceeds of flats. Negotiations proceeded on the basis that the value of certain enhancements to the individual flats would be taken into account in the formula and thereby reduce the overage payable. The seller omitted this provision and the draft agreement was approved without it. The Judge at first instance found that the seller had shut its eyes to an obvious mistake and ordered rectification. The Court of Appeal however overruled the Judge and held that in the absence of convincing evidence that it had shut its eyes to the obvious, an inexperienced party would be able to resist a claim by a far more experienced one for the rectification of a contract that had been negotiated at arms’ length. The fact that
there had been a late change in the draft which operated to the substantial disadvantage of the experienced party was not sufficient to enable that party to succeed. The case is particularly significant because of the fact that a decision of the trial judge on a question of fact was overturned as wrong in principle.
19. Fourthly, as in any other contract, the Court will intervene where it is apparent
from the face of the document that the wording as gone wrong, in the sense
that if taken literally it deprives the contract of commercial sense. However, it
is only in rare cases that the Court will find that the wording has gone wrong in
a professionally drawn document.
In Chartbrook Ltd. v Persimmon Homes Ltd. [2009] AC 1101, the House of Lords, overruling the first instance judge and the Court of Appeal, held that this was one of the rare cases where the literal wording of the agreement made no commercial sense and where it could be deduced from the document what the parties had in mind.
In that case, it was apparent from the terms used by the parties in setting
out the formula for calculating overage that their intention was to pay the seller for the current value of the land, and thereafter to pay the seller a further sum for the value of the land if the flats in the development were sold for more than they were expected to reach. However, the formula which was employed, when viewed in accordance with conventional syntax, provided that the price payable as overage (or the “additional retail payment” as was stated in the agreement) should be far greater than any increased value of the land. What it contemplated was that the additional payment for a flat should equal 23.4 % of the price achieved less the initial price payable to the buyer for the land value of the flat, this being called the “minimum guaranteed residential unit value” (or ‘MGRUV’), which was set at £53,438 per flat. The seller, however, contended that the formula should be applied literally. Thus applied, it would have required payment of 23.4% of the difference between the sale price (less marketing costs) and MGRUV – a vastly higher sum bearing no relation to the land value.
This can be demonstrated thus: the flats were expected to fetch about £200,000 and MGRUV represented a percentage which was only slightly over 23.4% of that figure (it was exactly 23.4% of £228,000). Therefore it was apparent that the 23.4% of the actual sale price (less costs) minus MGRUV would represent the increase in the value of the land, and that an enormous windfall to the seller would be produced if he were instead to receive 23.4% of the difference between the sale price (less costs) and MGRUV. To put rival contentions in algebraic notation, the seller was claiming 23.4% x (price – costs – MGRUV), while the buyer was claiming to be liable for no more than 23.4% (price – costs) – MGRUV. To give an example as to how the formulae worked, the first (the seller’s) formula on a sale at £240,000 (net of costs) would have produced an overage figure of £43,655.50, while the second (the buyer’s) formula would have produced a figure of £2,722, which is far more in line with expectations, where the flat sells for only slightly more than the predicted price.
The House of Lords found for the buyer for three reasons. Firstly, the
literal interpretation of the provision was totally at variance with the commercial sense of the contract, secondly the commercial sense of the contract could be determined from the choice of words used in the formula itself (“minimum guaranteed residential unit value” and “additional residential payment”) and thirdly the literal interpretation would make the structure and wording of other provisions in the agreement arbitrary and irrational – see Lord Hoffman at page 1113 G.
The House also reaffirmed, however, that evidence of pre-contractual
negotiations is inadmissible in cases of contractual interpretation, unless it is intended to show either that there had been a definite antecedent agreement which the later written agreement did not correctly embody or else that the parties had negotiated on certain agreed assumptions (for example as to the meaning of a word) so as to raise an estoppels by convention. For such contentions to succeed, they would have to be clearly pleaded and proved.
Overage and successors in title
20. As mentioned above, the most effective means of securing a right to the
payment of overage is by means of a legal charge. However, as also noted, it is
not always possible to achieve this in negotiation. In the absence of such a
charge, there is only one other way in which the seller’s rights can be
effectively secured against a third party, that is by ensuring that that the
contract provides that:
(1) successors in title of the buyer should be liable to pay overage to the
seller if the trigger event occurs during their ownership of the land;
(2) the buyer should agree to the entry of a Restriction on the Land Registry
title under Section 43 of the Land Registration Act 2002 to protect that
obligation by providing that no disposition of the land should be made
without the consent of the seller.
The agreement should also specify the terms under which the seller will be
obliged to give his consent to the registration of the onward disposition.
Generally the seller will be entitled to require that the onward purchaser enter
personally into the overage agreement and in turn permit the entry of a
Restriction which will prevent the entry of further disposition from him without
the consent of the original seller.
Although the matter has not been settled definitely, it is highly likely that such
a device will be effective to protect the seller’s interests – see Akasuc Enterprise
Ltd. v Farmar & Shierreff (a Firm) [2003] EWHC 1275 (Ch), Peter Smith J,
paragraphs 85 – 7. Note that from the buyer’s point of view it is necessary to
define those classes of purchaser who are to be subject to this requirement,
lest leaseholders of relativel;y short terms, for example be caught.
21. Attempts to make the overage agreement binding on the buyer’s mortgagee,
may meet with resistance from mortgagees for the same reasons as apply in
the case of charges. In particular, the mortgagee will be concerned that any
purchaser who buys subject to overage will pay less up front than he would
otherwise do, and this could accordingly lead to a shortfall at the expense of
the mortgagee. The mortgagee might therefore choose to insist that the
obligation should not be binding upon any purchaser who purchases from the
mortgagee under its powers of sale. This would be unattractive to the
seller/overage owner. A possible alternative might be to allow the Restriction
to operate in all cases (including sales by a mortgagee), but for the shortfall in
the mortgagee’s recovery (ideally up to an defined limit) to be secured by a
charge over any sums which may become due by way of overage from the
onward purchaser. Another possibility may be for the overage agreement to
provide that any surplus after the repayment of the mortgage should be paid
into a joint account inm the names of the buyer and seller and used to the
discharge of the overage when it is eventually ascertained. Once again, though,
all would depend upon negotiation. Whatever inadequacies there may be in
securities which are subordinated to the interests of the mortgagee, it is still
important to obtain whatever security one can, because there is plenty of
scope for a solvent buyer to attempt to defeat the seller’s rights, as in the
Akasuc case itself.
What does not protect the seller?
22. An obligation to make payments, whether or not expressed to bind successors
in title, will not be protected by the registration of a unilateral notice under
Section 34 of the 2002 Act, just as a caution was insufficient to protect such a
right under earlier legislation – see the Akasuc case (above). The reason is that
the right is not an interest in land.
23. In certain circumstances, a restrictive covenant could protect the seller’s rights,
but such protection cannot be relied upon. It must be remembered, firstly, that
a positive covenant will not bind successors in title of the person who has the
benefit of the covenant – Rhone Trust v Stephens [1994] 2 AC 310. Therefore, if
it is to be binding upon a successor it must be expressed negatively – for
example in terms of a covenant not to do a particular thing together with an
agreement to release the covenant upon payment of a given sum. Two
difficulties arise here, however. Firstly, the covenantee will not be able to
enforce the covenant if he does not retain any land which is capable of
benefiting from it, and secondly the covenant can be challenged on the basis
that it is not necessary to protect the land retained, and will therefore stand or
fall on its own merits.
The Solicitor’s position
24. In the Akasuc case, Peter Smith J held that:
“[Security] is a matter of a solicitor discharging her retainer. The retainer is to use all reasonable endeavours to obtain security for the overage. It is not a matter of advice in that sense. The solicitor has to come up with a suitable method of securing the overage (assuming that [the buyer] would accept it).”
To this, I would add that the solicitor is also under a duty to inform the client of
the extent to which the overage entitlement is not secured, and to enumerate
the circumstances where the entitlement could be left unsatisfied.
Failure to obtain adequate security: claims for damages
25. A claim by a client who has not received adequate security will aim at first to
recover the benefit which the contract would have provided, had adequate
security been in place. However, because the claim is one of professional
negligence, the question for the Court will be, ”what contractual terms would
have been obtained and what security would have been provided if the solicitor
had not acted negligently and what benefits would such terms have yielded to
the client?”
26. In addressing the first part of that question, the terms of the actual contract
will merely be evidence of what the hypothetical contract would have
contained, and the evidence which the actual contract provides may not be
very strong. After all, a buyer who knows that he can sell to an onward
purchaser at a price which is not depressed by the presence of an overage
obligation affecting the onward purchaser may be willing to make the most
extravagant promises, secure in the knowledge that they will not have to be
honoured. It will therefore be necessary for the client to give evidence as to the
sort of bargain which he had been in a position to strike. The presence of rival
bidders and the client’s own state of financial health (relevant to the question
of whether he could have bided his time until a good offer came along) will be
important considerations, as of course would the state of the market. If the
receipt of the overage money was frustrated by the insolvency of the buyer at
the time of his onward sale, it will also be necessary to consider whether there
were cash buyers (who did not have to please mortgagees) among the potential
purchasers and whether there were mortgagees in the market who would have
been willing to lend in circumstances where the right to overage was be binding
upon onward purchasers. Finally, it would be necessary and useful to know the
value of the land at the time of the agreement, and the amount by which that
value exceeded the actual sale price which – a price which by definition would
have been discounted because the then current hope value would have been
left out in favour of the overage provisions. This is especially important in the
case of a claim by any client who would have been likely to have taken a safe
course rather than a risky one.
27. Limitation The failure by a solicitor to secure an entitlement to overage falls
within that class of case where a person has, through professional negligence,
been caused to part with property on terms which are less advantageous than
would have been the case if the negligence had not occurred. That being so,
the cause of action accrues, and the limitation period begins to run, when the
contract of sale becomes binding – see Law Society v Sephton [2006] 2 AC 543.