Upload
gayan-bandara
View
79
Download
1
Embed Size (px)
DESCRIPTION
Tests availabale at road works
Citation preview
Industrial Training Report
i
PREFACE
Industrial Training program conducted by Industrial Training Division of Faculty of
Engineering, of University of Moratuwa, in collaboration with National Apprentice and
Industrial Training Authorities an important part of the B.Sc. Engineering Honors Degree
Program. It is a great opportunity for undergraduates to obtain a practical knowledge on
theories they have learned. This report contains my own experience and knowledge gained
during 24 weeks of eventful training period.
I was assigned to the Mäga Engineering (Pte) Ltd. for the training. During my training period
from 17/05/2012 to 01/11/2012, I was able to train at Mirijjawila Highway laboratory, in a
road and bridge construction site and in Siribopura interchange at Hambantota. Furthermore I
visited the concrete and asphalt batching plants in order to learn about the processes there.
This report consists of three chaPters. The first chaPter is the introduction to the training
establishment. It provides a brief description about Mäga Engineering (Pte) Ltd, its
performances, strengths and weaknesses etc. The second chaPter describes my training
experience including assigned duties, tests conducted, work done at laboratory and site, lab
equipment and chemicals used, etc. Final chaPter is the conclusion which contains my
comments on this program and suggestions to improve the program.
Industrial Training Report
ii
ACKNOWLEDGEMENT
Industrial Training program was a great opportunity which I acquired in order to enhance my
practical knowledge. During this period I gathered a lot of knowledge and experience by
working with experts. Therefore, I personally owe many personnel and I consider this as an
opportunity to appreciate all of them for their kind guidance.
First of all, I would like to express my appreciation to Eng. N.A. Wijeyewickrema, Director,
Training Division of Faculty of Engineering at University of Moratuwa for his kind guidance.
I would like to convey my gratitude to Dr. Indika, coordinator for Industrial training of
Department of Material Science & Engineering, University of Moratuwa for his kind advices.
And also I would like to convey my gratitude to all the officers of National Apprentice and
Industrial Training Authority (NAITA) for their collaboration for the success of this program.
I gratefully acknowledge the Managing Director of Mäga Engineering (Pte) Ltd, Mr. M. G.
Kularathne, Director (Highway and Bridges), Mr. G. V. S. K. Kumarasiri, Project Manager,
Eng. Kanchana Jayasinghe and Project Manager, Eng. K. H. R. Lakmal, for giving this
valuable opportunity to train under the roof of this leading construction company. I also wish
to express my sincere thanks to the Material Consultant Dr. Franando, Material Engineer Mr.
Indunil Kumara, Senior Material Technician Mr. Sudam Surendra, Other Lab technicians,
Lab helpers and other staff of Mäga Engineering (Pte) Ltd. I specially thank Material
Engineer of Road Development Authoroty, Mr. Jayarathne, who helped me to widen my
knowledge by sharing his knowledge in construction materials testing methods.
I also wish to express my sincere thanks to the Site manager Mr. K. W. P. Renuja, Site
engineer Mr. Thisara Pathirage, Structural engineer Mr. Isitha Lokukodikara, technical
officers,foremen, Concrete batching plant manager, Other staff officers, sub-contractors and
labour of Siribopura Interchange project for their friendliness and kind help during my
training period in that site.
My special thanks are due to Mr. Dimuthu Kumara, Material technician atHighway
laboratory, and Dinesh, lab helper at Highway Laboratory, theyhelpedme to make my asphalt
mix design a success.
Industrial Training Report
iii
Contents CHAPTER 01 ......................................................................................................................................... 1
1. INTRODUCTION TO TRAINING ESTABLISHMENT .............................................................. 1
1.1 Maga engineering (Pte) Ltd. ..................................................................................................... 1
1.1.1 Vision ................................................................................................................................. 1
1.1.2 Mission ............................................................................................................................... 1
1.1.3 Quality Policy .................................................................................................................... 1
1.2 History of Mäga Engineering (Pte) Ltd. ................................................................................... 2
1.3 Main Functions of Mäga Engineering (Pte) Ltd ....................................................................... 3
1.4 Sub Functions of Mäga Engineering (Pte) Ltd ......................................................................... 3
1.4.1 Concrete Batching Plants ................................................................................................... 4
1.4.2 Asphalt Plants and Pavers .................................................................................................. 4
1.4.3 Pre-cast concrete yard ........................................................................................................ 4
1.4.4 Central Workshop .............................................................................................................. 4
1.4.5 Scaffolding leasing section ................................................................................................ 5
1.5 Organizational Structure and Hierarchical Levels .............................................................. 5
1.6 Performances of Mäga Engineering (Pte) Ltd .......................................................................... 6
1.7 SWOT Analysis of Company ................................................................................................... 7
1.7.1 Strengths ............................................................................................................................ 7
1.7.2 Weaknesses ........................................................................................................................ 7
1.7.3 Opportunities for improvement .......................................................................................... 7
1.7.4 Threats for survival ............................................................................................................ 8
CHAPTER 02 ......................................................................................................................................... 9
2. TRAINING EXPERIENCE ............................................................................................................ 9
2.1 Training at highway laboratory-mirijjawila .............................................................................. 9
2.1.1 Soil 10
2.1.1.1 Wash and Gradation .................................................................................................. 10
2.1.1.2 Atterburg Plasticity Index (PI) .................................................................................. 11
2.1.1.3 Moisture – Density relation of soils (Proctor compaction test) ................................ 13
Test Procedure .......................................................................................................................... 14
2.1.1.4 Califonia Bearing Ratio (CBR) ................................................................................. 16
2.1.1.5 Dynamic Cone Penetration (DCP) ............................................................................ 19
2.1.1.6 Field density by sand cone method (In situ density) ................................................. 20
2.1.2 Aggregate ......................................................................................................................... 20
2.1.2.1 Aggregate Impact Value (AIV) ................................................................................. 21
Industrial Training Report
iv
2.1.2.2 Los Anjalese Abression Value (LAAV) ................................................................... 22
2.1.2.3 Aggregate Gradations ............................................................................................... 23
2.1.2.4 Flakiness Index (FI) .................................................................................................. 23
2.1.2.5 Bulk Specific gravity of aggregate ............................................................................ 24
2.1.3 Concrete ........................................................................................................................... 25
2.1.3.1 Production of Concrete ............................................................................................. 25
2.1.3.2 Admixtures Use Flyover Concrete Batching Plant ................................................... 27
2.1.3.3 Concrete Testing. ...................................................................................................... 28
2.1.4 Bitumen ............................................................................................................................ 32
2.1.4.1 Ductility of the bitumen ............................................................................................ 32
2.1.4.2 Penetration of the bitumen ........................................................................................ 33
2.1.4.3 The softening point of the bitumen ........................................................................... 34
Figure 2.22 – Ring and Ball Apparatus ................................................................................. 35
2.1.5 Asphalt ............................................................................................................................. 35
2.1.5.1 Production of Asphalt ............................................................................................... 36
2.1.5.2 Asphalt Testing ......................................................................................................... 37
2.1.5.2.1 Bitumen Extraction Test ............................................................................ 37
2.1.5.2.2 Marshall tablets making by Marshall Compactor and test specific gravity,
flowability and stability ............................................................................................ 38
2.1.5.2.3 Testing Specific Gravity, Stability and Floability ...................................... 38
2.1.5.2.4 Core cutting Test ........................................................................................ 40
Figure 2.27 – Core cutter .......................................................................................... 40
2.1.6 Asphalt Mix Design ......................................................................................................... 40
2.1.6.1 Average gradations of my design .............................................................................. 41
2.1.6.2 Maximum Theoretical Density (Gmm) Test ............................................................. 42
2.1.6.3 Marshall Making Procedure ...................................................................................... 43
2.2 Training at siribopura interchange project. ............................................................................. 44
2.2.1 Introduction ...................................................................................................................... 44
2.2.1.1 Project Details ....................................................................................................... 44
2.2.2 Duties at the Site .............................................................................................................. 46
2.2.3 Road construction ............................................................................................................ 46
2.2.4 Structural Works .............................................................................................................. 52
2.2.4.1 Formworks ................................................................................................................ 52
2.2.4.2 Reinforcement ........................................................................................................... 53
2.2.4.3 Drain construction ..................................................................................................... 54
CHAPTER 03 ....................................................................................................................................... 55
Industrial Training Report
v
3. CONCLUSION ............................................................................................................................. 55
LIST OF ABBREVIATIONS..............................................................................................vii
REFERENCES......................................................................................................................ix
Industrial Training Report
vi
List of Figures
Figure 1.1 – Organizational structure of Mäga Engineering (Pte) Ltd. .................................................. 6
Figure 2.1- Highway Laboratory ............................................................................................................ 9
Figure 2.2 – Sieve analyze test apparatuses .......................................................................................... 10
Figure 2.3 - Graph of passing vs. sieve size .......................................................................................... 11
Figure 2.4 - Liquid limit device ............................................................................................................ 11
Figure 2.5 – Graph of number of blows VS avg. Moisture content ..................................................... 12
Figure 2.6 – Example Graph of avg. Moisture content Vs Dry Density ............................................... 15
Figure 2.7 – Doing a CBR test (left), A CBR mould (right) ................................................................. 16
Figure 2.8 – A soaking tank .................................................................................................................. 17
Figure 2.9 – A CBR tester ..................................................................................................................... 18
Figure 2.10 – Graph of penetration Vs force ........................................................................................ 18
Figure 2.11 – Dynamic Cone Penetrometer .......................................................................................... 19
Figure 2.12 – Aggregate Impact Tester ................................................................................................ 21
Figure 2.13 – LAAV Machine .............................................................................................................. 22
Figure 2.14 – Production process of ready mix concrete ...................................................................... 26
Figure 2.15 – Arrangement of the Batching plant (left), Plant operating unit (right) ........................... 27
Figure 2.16 – Standard test mould and tools (left), Casting a test cube (right) ..................................... 29
Figure 2.17 – compression strength testing machine ............................................................................ 30
Figure 2.18 – Digital display of compression strength testing machine ............................................... 30
Figure 2.19 – Slump test apparatus (left), measuring the slump (right)................................................ 31
Figure 2.20 – Water bath ...................................................................................................................... 32
Figure 2.21 – Bitumen Penetrometer .................................................................................................... 33
Figure 2.23 – Mirijjawila new asphalt plant (left), cold bins and bitumen tanks (right) ...................... 36
Figure 2.24 – Bitumen Extractor........................................................................................................... 37
Figure 2.2 – Marshall Compactor ......................................................................................................... 38
Figure 2.25 – Buoyancy balance ........................................................................................................... 38
Figure 2.26 – Marshall Stability Tester ................................................................................................ 39
Figure 2.26 – Siribopura Flyover .......................................................................................................... 44
Figure 2.30 – Organizational structure of Siripobura interchange project ............................................ 45
Figure 2.31 – A typical road section ..................................................................................................... 47
Figure 2.32 – A typical cross section of road ....................................................................................... 47
Figure 2.33 - Watering a sub base top of a road section ....................................................................... 49
Figure 2.34 - Laying and leveling embankment on a road section ....................................................... 50
Figure 2.35 - Doing a sand cone test on a compacted ABC surface ..................................................... 50
Figure 2.36 - Laying ABC on a sub base top and leveling .................................................................. 50
Figure 2.37 - Applying the prime coat on a cleaned ABC surface ....................................................... 51
Figure 2.38 - Laying an asphalt layer on a prime coated ABC surface ............................................... 51
Figure 2.40 - GI pipe, form tie, P cone arrangement in the formwork ................................................. 53
Figure 2.41 – Arrangement of U drain .................................................................................................. 54
Industrial Training Report
vii
List of tables
Table 2.1 - Table for calulate LL and PL................................................................................13
Table2.2 - Soil Compaction Data............................................................................................16
Table2.3 - Specific ranges of ABC gradation..........................................................................23
Table2.4 - Average Gradation Results.....................................................................................41
Table2.5 - Aggregate Blend and JMF......................................................................................42
Industrial Training Report-Intoduction to Training Establishment
1
CHAPTER 01
1. INTRODUCTION TO TRAINING ESTABLISHMENT
1.1 Maga engineering (Pte) Ltd.
Mäga Engineering (Pte) Ltd, having its vision as “To be the most competitive construction
company in Sri Lanka”- is one of the leading construction companies reputed for quality
construction, timely completion and best customer satisfaction. No doubt that Mäga
Engineering (Pte) Ltd is equipped with the very modern techniques and all kind of
sophisticated equipment, comprising not only born – dexterous and adroit board of
administrative panel, but also dedicated, highly motivated, and vibrant workforce. Even
though Mäga Engineering (Pte) Ltd is established in 1984, with in a very short period of time
a fabulous reputation has been achieved for its quality construction work by satisfying
national and international standards for the best affordable price in the competitive market.
Each and every project which was handled by Mäga Engineering (Pte) Ltd had able to stand
the test of time, make an invincible impression for those who dealt with premier construction
work. Therefore, it has every valid reason to be the “Saga of quality constructions.” Thus all
valuable effort of adroit administrators, innovative professionals, high quality controlling
activities, assurance of the workers safety and health care, use of sound material, high
technical equipment pave the way for Mäga Engineering (Pte) Ltd to acquire ICTAD Grade 1
status under registration number M- 0209, in the category of Buildings, Highways, Bridges,
Water Supply and Drainage.
1.1.1 Vision
To be the most preferred and the best professional construction contractor in Sri Lanka
1.1.2 Mission
To provide the highest quality construction at a competitive price, within a specific time
frame, using superior technology and dedicated professional service.
1.1.3 Quality Policy
Mäga Engineering (Pte) Ltd. is dedicated to provide quality products and services satisfying the needs
and expectations of each customer with a creative, self-motivated and dedicated team united under a
rewarding and healthy environment ensuring continual improvement in an environment friendly
manner.
Industrial Training Report –Intoduction to Training Establishment
2
1.2 History of Mäga Engineering (Pte) Ltd.
Mäga Engineering (Pte) Ltd was incorporated under the Companies Act. No. 12 of 1982 on
2nd December 1983 as a Private Limited Liability Company and was registered at that time
under the name “Chandaranayake and Company (Private) Limited” to carry on the business
mainly on construction of buildings, and other civil, electrical & mechanical engineering
works. Eventually, on 17th October 1989, name of the company was changed to MAGA
Engineering (Pte) ltd.
Since then, vibrant courage, sheer determination and quality management skills with
exemplary leadership of the present Managing Director Captain M.G. Kularatne has paved
the way for Mäga Engineering (Pte) Ltd to acquire the well-established position in current
highly competitive construction field, inspiring clients and developers, while keeping their
confidence towards company unchanged for long period. Mäga is now proudly listed as M1
contractor for the categories of Building construction, Highway and bridge construction and
Water supply and drainage works under the National Registration and Grading of
Construction Contractors by the Institute of Construction Training and Development.
Acquiring of remarkable achievements such as Winner of IFAWPCA Gold Medal and
ICTAD award for construction excellence, ISO-9002 quality certificate for construction
demonstrates the progress and growth of the company over brief history. Currently Mäga has
successfully completed more than one hundred fifty major projects in different kinds of
applications such as administrative buildings, residential and apartment complexes, factories,
hotels, hospitals, educational buildings, hydro-power / water supply systems, roads, and
bridges. This list also includes miscellaneous projects like Sugathadasa Indoor Stadium &
Swimming Pool Complex Project, Service Station at Alexandra Place, Colombo Airport New
Runway & Airport Civil Works Circuit bungalow at Samanalawewa, Dry Port for IWS
Logistics at Wattala, and Residence for Japanese Ambassador in Sri Lanka. As a proud
company being totally Sri Lankan, Mäga is blessed to undertake foreign construction projects
and over twenty projects were successfully completed specially in Maldives. Foreign projects
completed by Mäga includes bulk cement import terminal, sea wall and break water projects,
coastal fisheries projects, port development projects, buildings for medical research center,
and telecommunication development projects.
Industrial Training Report –Intoduction to Training Establishment
3
1.3 Main Functions of Mäga Engineering (Pte) Ltd
As a M1 graded construction company, Mäga has the capability, strength, potential, and
confidence to undertake various kinds of contracts such as administrative buildings,
residential and apartment complexes, factories, hotels, hospitals, educational buildings,
hydro-power / water supply systems, roads, and bridges – not only in Sri Lanka, but also at
over-seas as well. As ISO-9002 quality certified company, Mäga Engineering (Pte) Ltd
maintains the specific regulation in administration, documentation, and construction field.
Huge number of awards obtained for the completed projects by Mäga Engineering (Pte) Ltd
demonstrates the invincible improvement and success during its short period at construction
field.
Further, Mäga Engineering (Pte) Ltd. is recognized as the 27th most respected business entity
in Sri Lanka by LMD, and Mäga Engineering (Pte) Ltd. is the only construction company to
get the titled at the list.
1.4 Sub Functions of Mäga Engineering (Pte) Ltd
Mäga Engineering (Pte) Ltd, which is functioning as M1 graded Construction Company, is
fully equipped with latest constructional technology and knowledge, materials, machines,
equipment, and plants. As a construction contractor, Mäga Engineering (Pte) Ltd has the
privilege of owning concrete batching plants, asphalt plant, pre-cast concrete yards,
mechanical workshops, and scaffolding leasing section.
Apart from only being a construction company, Mäga Engineering (Pte) Ltd has widened its
application to the Civil Engineering and Construction Materials Engineering fields by
stepping in to consulting, designing and developers sections. Maga Engineering (Pte) Ltd has
incorporated its fully owned subsidiary - Maga Developments Lanka (Pte) Ltd., to create a
new revolution in the construction field by providing high quality up-market luxury
residential apartments, through its in-house expertise in architectural & structural design and
advanced construction techniques. Mäga Engineering (Pte) Ltd is now strengthened with its
ablest design division and consultancy divisions, enabling the company undertake even
design & build contracts.
Industrial Training Report –Intoduction to Training Establishment
4
1.4.1 Concrete Batching Plants
Supply of quality ready-mixed concrete and timely transport it to construction sites are most
important tasks when any construction activity is concerned. Therefore, Mäga concrete
batching plants, situated at Rajagiriya, Galle, Gampola, Unawatuna, Kelaniya, and Horana
fulfill those requirements not only to Mäga sites, but also other customers’ orders. Using of
sound materials, high-technology at the batching plant, routine test on materials, regular
calibration of machines, quality controlling system in the production process are the main
reasons behind the success of Mäga ready-mixed concrete and customer satisfaction towards
Mäga ready-mixed concrete.
Not only in the production process, but also in the transportation and placing process Maga
presents a quality service to its customers utilizing modern truck mounted concrete pumps,
cleanly maintained agitators, and amiable work forces. In order to enhance the services
provided by Mäga concrete batching plants, company has scheduled to commence a new
batching plant at Ambewela, and currently it is under construction.
1.4.2 Asphalt Plants and Pavers
Mäga asphalt plants situated at Witharandeniya, Homagama, Neboda, Hambanthota, and
Katupotha are equipped with adequate clod stock capacity for bitumen and aggregates, hot
asphalt storage facility, production process comprising dust collectors and filler storage that
enhancing the environment friendly production ensuring healthy atmosphere. Asphalt plants
are also equipped with testing machines and technical officers for continual monitoring
process to ensure that the final product satisfy the specify quality.
1.4.3 Pre-cast concrete yard
With the development of new technologies such as pre-cast concreting, and when huge
demand for pre-cast concreting is prevailing in the market, Mäga has stepped in to that area
as well, utilizing company expertise and experiences in the construction field. Pre-cast
concrete yard, located at the central work shop at Homagama, produce quality pre-cast
concrete satisfying local and international standards.
1.4.4 Central Workshop
Manipulating skillful mechanical and electrical engineers, technical officers, and motivated
work forces, company maintain a central work shop at Homagama to repair machines, power
tools, motors, generators, elevators, cranes, concrete mixers, agitators, vehicles and many
other equipment and plants. Apart from the manufacturing steel structures, trusses, and
frames, and testing for its strength are carried out at the central workshop.
Industrial Training Report –Intoduction to Training Establishment
5
1.4.5 Scaffolding leasing section
Mäga Engineering (Pte) Ltd. has one of the largest scaffolding stocks, which enable the
company to handle several large scale construction projects simultaneously, without having
any kind of shortage for scaffolding leasing section to undertake the orders from outside the
company sites. Moreover, company now seeks to practice new formwork and supporting
system as “Mivan” where it is already put in to practice at Fairmount Residencies Project.
1.5 Organizational Structure and Hierarchical Levels
Captain M.G. Kularathne acts as Chairman, Managing Director, Director Machinery Plant,
and Director Overseas Projects. Under his leadership and guidance, Major Derrick De Silva
(Director Administration), Mr. M.G. Chandrasekara (Director Finance), Mr. M. Piyadasa
(Director Operations), Mr. C.A. De Silva (Director Engineering - Design & Construction),
and Mr. W.M.S.L.B. Rathnayaka (Director Engineering – Planning & Development) act as
board of directors of Mäga Engineering (Pte) Ltd.
Industrial Training Report –Intoduction to Training Establishment
6
Figure 1.1 - Organizational structure of Mäga Engineering (Pte) Ltd.
Industrial Training Report –Intoduction to Training Establishment
7
1.6 PerformancesofMäga Engineering (Pte) Ltd
At present, Mäga Engineering (Pte) Ltd performed as a leading construction company in all
section of Buildings, Highways, Bridges, Water Supply and Drainage. In addition, being
titled as a M1 construction company by ICTAD, Mäga Engineering (Pte) Ltd. has the
strength to undertake all kinds of large scale premier construction projects. Completing over
one-hundred fifty projects successfully, obtaining more than twenty ICTAD awards for
quality constructions, acquiring ISO 9002 certificate, ensuring workers health and safety,
Mäga Team is inspired to experience a boom in the construction field in Sri Lanka.
1.7 SWOT Analysis of Company
1.7.1 Strengths
Not being just a local construction company, ability to undertake foreign contracts, and step
in to design section as well as consultancy section, which illustrate the remarkable
achievement and strength that Mäga has, in comparison with other construction companies.
Born – dexterous and adroit board of administrative panel, skillful and innovative engineers,
technical officers, dedicated highly motivated workforce, manipulating of modern- high
techniques, equipment are the strength of Mäga Team.
Having its’ own concrete batching plants, asphalt plants, crushing plants, pre-cast concrete
yards, and workshops create a huge advantage to the continual progress of the company.
1.7.2 Weaknesses
Deficiency of a piling construction division for Mäga, is a main draw-back in the vision
journey of the company - “To be the most competitive construction company in Sri Lanka.”
1.7.3 Opportunities for improvement
Mainly it is very important and helpful if they can start a piling division in the company.
Then they can survive individually without renting from others anything. When the company
is fully equipped in any type of constructions without any deficiency if helps the company to
being more success. Furthermore the company is able to go to the zenith by getting well
qualified and experienced people to work and giving them reasonable salaries. As a company
it is very important to satisfy their employees in order to get their maximum outputs. Hence
the company should able to satisfy their employees as well as customers.
Industrial Training Report –Intoduction to Training Establishment
8
1.7.4 Threats for survival
The lack of pilling section can be identified as the one of major treats for the survival of the
company. Further lack of an improved and reputed design section and a consultancy section
also can be identified as future treats. The unsatisfied nature of the middle level staff and
workers, engineers leaving the company and other staff members that is to leave the company
is also treats for the company. Upcoming construction companies can be identified as
external treats for the company.
Industrial Training Report – Training Experience
9
CHAPTER 02
2. TRAINING EXPERIENCE
During my training period I got the opportunity to train in the Highway Laboratory of Mäga
Engineering (Pte) Ltd andFlyover at Siribopura interchange. I got the opportunity to visit
mirijjawia asphalt plant and study about the asphalt batching. Also I did a asphalt binder mix
design for the mirijjawila new asphalt plant. Further I could work full night at readymix
concrete batching plant.
2.1 Training at highway laboratory-Mirijjawila
Figure 2.1- Highway Laboratory
Mäga Engineering (Pte) Ltd is one of the largest construction companies in Sri Lanka. The all
constructions are done in extremely high quality under the supervision QA and QC engineers.
The all QA and QC tests are done at the main Highway laboratory. The main Highway
Laboratory is located at Mirijjawila to where I was assigned first.
The main Highway Laboratory is operated under the supervision of Senior Material
Consultant Dr. Franando. The staff is consisted with the Material Engineer, a Senior Material
Technician, Lab Technicians, Drivers and Lab helpers and also all highway laboratory
equipment are available there.
In this training session the soil, aggregate, concrete, bitumen and asphalt tests were covered.
Also concrete and asphalt batching plants were visited and batching and testing were studied.
Furthermore an asphalt binder mix design was done for Mirijjawila new asphalt plant.
Industrial Training Report – Training Experience
10
2.1.1 Soil
Soil is a very important material for all construction processes. In highway constructions, soil
is used as sub grade, embankment, capping layers and sub bases. There are different
properties require for these each types of soil. The soil is excavated from borrow pits. Then
excavated soil is carried into sites and stockpiles are prepared. Then the required properties
are tested at laboratory and sites. Generally following tests are done for the soil samples.
2.1.1.1 Wash and Gradation
Figure 2.2 - Sieve analyze test apparatuses
Test Procedure
Representative sample of about 500 g s of sand should be taken.
Determine the weight of the sample accurately
Wash the sample by using standard sieves and remove the clay particles.
Determine the weight of the sample accurately.
Wash the sample by using standard sieves and remove the clay particles.
Sample is put in an oven and then weighs it again.
Clay content of the soil can be measured from the weight different. (we can get a idea about
the plasticity index from this test)
Clean all sieves to remove the stucked particles.
Weigh all sieves and the pan separately.
Prepare a stack of sieves. Sieves having larger opening sizes are placed above the
ones having smaller opening sizes. Place the pan at the bottom.
Industrial Training Report – Training Experience
11
Pour the sand in to the top sieve and place the cover.
Shake the set of sieves well.
Measure the mass of each sieve + retained sand.
Calculate the weight retained and then percentage finer.
Draw graph of sieve size vs. % passing. The graph is known as grading curve.
Figure 2.3 - Graph of passing vs. sieve size
2.1.1.2 Atterburg Plasticity Index (PI)
We can obtain liquid limit, plastic limit and plasticity index of soil from the atterburg
plasticity index test.
Figure 2.4- Liquid limit device
0
10
20
30
40
50
60
70
80
90
100
0.010 0.100 1.000 10.000 100.000
% P
assin
g
Sieve size(mm)
Min % PassingMax
Industrial Training Report – Training Experience
12
Test Procedure
300 grams of fine soil sample is prepared before the test the LL and PL.
LL Determination
Liquid Limit device is adjusted to the proper position (exactly above 1cm from the
base).
300g of prepared soil is added on to the glass plate and then sufficient water is added
and the sample is mixed at least 10 minutes.
Mixture is applied inside the cup and it isdivided into two by using the groving tool.
Turn the crank to raise and drop twice per second until two sides groved sample come
in contact for distance of 13mm.
Record the number of blows for above thing is accrued.
Take the 10g of representative sample for the tested sample for determine the
moisture content.
Clean the cup after an each trial and repeat the test 4-5 minimum samples.
Take the weights of the samples and put it in oven and weigh it after drying.
Plot a graph number of blows vs moisture content and mark the moisture content at 25
blows. It is the liquid limit of this soil.
Figure 2.5 -Graph of number of blows VS avg. Moisture content
24.0
26.0
28.0
30.0
32.0
34.0
36.0
10 100
Mo
istu
re c
on
ten
t(%
)
Number of blows
25
Industrial Training Report – Training Experience
13
PL Determination
The 20g of prepared soil mix with water until the mass becomes the plastic enough to
be shaped into a ball.
8-12 grams of moisture soil is formed into a uniform mass roughly elliptical shape.
Samples are rolled by hand, rolling surface with just enough pressure to form
elongated thread as rolling proceeds.
It should have 3mm diameter and 10mm length. Samples add into a container, weigh,
put into oven for getting dry weights.
Repeat for 3 portions of soil.
Table 2.1- Table to calculate LL and PL
Liquid Limit Plastic Limit
Container No. 19 50 14 48 6 40
Number of blows 46 38 29 17
Weight of wet soil
+ container 78.55 80.15 82.65 78.60
52.50 52.15
Weight of dry soil
+ container 69.90 70.55 72.15 68.60
50.15 49.90
Weight of container 37.40 37.55 37.25 37.00 37.05 37.50
Weight of water 8.65 9.60 10.50 10.00 2.35 2.25
Weight of dry soil 32.50 33.00 34.90 31.60 13.10 12.40
Moisture content 26.62 29.09 30.09 31.65 17.94 18.15
PI Value should be lower than 15% for sub bases and it should be lower than 25% for
embankments.
2.1.1.3 Moisture – Density relation of soils (Proctor compaction test)
Compaction of soil is a mechanical process by which the soil particles are constrained to be
packed more closely together by reducing the air voids. Soil compaction causes decreases in
air voids and consequently an increase in dry density. This may result in increase in shearing
strength. Increase the dry density of a soil due to compaction depends on three factors. They
are:
Natural moisture
content W=
% Plasticity Index =
12
%
Liquid Limit LL= 30 % (LL-PL)
Plastic Limit
PL= 18
%
Industrial Training Report – Training Experience
14
The compacting moisture content
The amount of compaction (compactive effort)
The nature of soil
In the laboratory, the dynamic compaction test that the proctor compactions test is tested for
determining the moisture – density relationship of soils. This relationship indicates that under
a given compactive effort every soil has optimum moisture content at which the soil attains
maximum dry density.
From the compaction test, the maximum dry density (MDD) and optimum moisture content
(OMC) of the soil is found for the selected type and amount of compaction. The OMC of the
soil indicates the particular moisture content at which the soil should be compacted to achieve
MDD. The MDD in the proctor compaction test lower value indicating weaker soils.
Test Procedure
The soil to be used in the test is first air dried (temperature should not exceeding
60˚C) and passed through a 20 mm test sieve.
It is then mixed thoroughly with a small amount of water and compacted into the
mould in 5 equal layers.
Each layer being compacted by 56 blows of the 4.54 kg rammer dropped through a
height of 450 mm above the soil surface.
The soil is trimmed to the top of the mould and weighed to determine its dry density.
The test is repeated five times with gradually increasing water contents until the
whole of the relevant range of water content has been covered.
Then, the moisture content and the dry density are determined and plot the Dry density –
Moisture content graph. From this graph, the maximum dry density and optimum moisture
content are read out.
Industrial Training Report – Training Experience
15
Figure 2.6 -Example Graph of avg. Moisture content Vs Dry Density
Wet density =Mass of wet soil
Volume of mould
Mass of water = Mass of (wet soil + can) – Mass of (dry soil + can)
Moisture content =Mass of water X 100%
Mass of dry soil
Dry density =Wet density X 100%
(Moisture content + 100)
1.700
1.750
1.800
1.850
1.900
1.950
7.0 8.0 9.0 10.0 11.0 12.0 13.0 14.0 15.0 16.0
Dry
Den
sit
y(g
/cm
³)
Moisture Content(%)
`
Industrial Training Report – Training Experience
16
Table 2.2- Soil Compaction Data
Wt. Rammer Ht. Drop No.of Layers
No.of Blows per
layer
Wt.
Mold(g)
Vol.
Mold(cm³)
4.5 kg 457 mm 5 56 5056 2124
Test No. 1 2 3 4 5
Wt.of Wet Soil +
Mold g 8981 9293 9467 9445 9384
Wt.of Wet Soil g 3925 4237 4411 4389 4328
Wet Density g/cm3 1.848 1.995 2.077 2.066 2.038
Container No. 106 40 116 51 25
Wt.of Wet Soil +
Container g 326.9 352.4 287.4 300.3 317.4
Wt.of Dry Soil +
Container g 304.5 326.8 262.0 270.1 278.6
Wt.of
Container g 24.7 26.5 23.3 28.1 28.3
Moisture
Content % 8.0 8.5 10.6 12.5 15.5
Dry Density g/cm3 1.711 1.838 1.877 1.837 1.764
Maximum Dry
Density (g/cm3) 1.878
Optimum Moisture Content
(%) 10.8
2.1.1.4 Califonia Bearing Ratio (CBR)
From the CBR testing the bearing ability of the soil can be identified. It is very important in
road constructions.
Figure 2.7 - Doing a CBR test (left), A CBR mould (right)
Industrial Training Report – Training Experience
17
Test Procedure
Sample sieved from 19mm sieve
If the material retained on 19mm sieve, the potion of retained is replaced with
material passing 19mm and retained 4.75 sieve
The representative masses were split 3 equal 6.8 kg samples
Used the optimum moisture content and rammed sample as five layers
10, 30 and 65 blows applied and compacted the each layers (Figure 2.7 left)
Moisture added = (𝑂𝑀𝐶−𝐼𝑀𝐶
100+𝐼𝑀𝐶) × 6800
The two of samples (moisture cups) were weighed and added into oven for determine
the moisture content
After marked the mould volume, mould weight and weight with compacted soil
The samples is soaked in a soaking tank 96 hours (4 days)
Figure 2.8 -A soaking tank
After the 4 days penetration test was done by using the CBR testing machine (44N
load uniformly applied at 0.13mm/min)
Industrial Training Report – Training Experience
18
Figure 2.9 – A CBR tester
Penetration and load values recorded and then calculate the CBR value of tested soil.
Figure 2.10 – Graph of penetration Vs force
CBR Value should be higher than 30% for sub bases, higher than 15% for embankment type
1 and higher than 7% for embankment type 2.
0.00
1.00
2.00
3.00
4.00
5.00
6.00
7.00
8.00
9.00
10.00
11.00
12.00
13.00
14.00
0.00 1.00 2.00 3.00 4.00 5.00 6.00 7.00 8.00
Fo
rce /
(kN
)
Penetration / (mm)
10 Blows 30 Blows 65 Blows
Industrial Training Report – Training Experience
19
2.1.1.5 Dynamic Cone Penetration (DCP)
DCP is a popular test that is used to determine the strength of in-situ soils. It is very
widely use in determining bearing capacity of road subgrades.DCP testing can be
performed directly through thin flexible pavements with uncemented aggregate sub layers.
The DCP can also be used to test directly through lightly cemented materials having
unconfined compressive strengths of less than 3000 kPa (440 psi); otherwise, DCP testing
can be performed only after a core containing pavement and other materials exceeding that
strength are removed.
Figure 2.11 -Dynamic Cone Penetrometer
Test Procedure
The steel ruler was attached to the guide foot and placed on the ground to be tested
with cone tip passing through the hole on foot.
Entire apparatus was hold vertically and ruler reading was recorded as the zero
reading
Drop weight was raised to its maximum height and was allowed to drop freely
Ruler reading was recorded at each blow.
As the penetration is larger than 20mm/blow, Test was conducted to the full height of
the rod.
Determination of CBR using Kleyn and Van Heerden chart
Industrial Training Report – Training Experience
20
2.1.1.6 Field density by sand cone method (In situ density)
This test can be used to determine the density of a material with aggregate size less
than 5cm
This test is accurate to certain depth only. If the hole is too deep, test may give
erroneous results
There shouldn’t be any vibration during test
Hole must be dig. So that sand can go to every location freely.
Test Procedure
The ground was prepared for the test by leveling it
Outline of the circle was marked on the ground
A hole was dig in the marked perimeter carefully to avoid disturbing the soil
outside the marking
All loosen soil were collected in to a container
The cone was filled with sand and weighed
The cone was placed on the hole and the valve was released to fill the hole with
free flowing sand
After filling it with sand the valve was closed and weighed the cone and remaining
sand
A sample of soil was tested for moisture content
2.1.2 Aggregate
Aggregate also a very important material for building and highway constructions. Different
sizes of aggregate used for each applications. Normally Mäga Engineering (Pte) Ltd used
aggregates for their constructions from maga-mirijjawila crusher plant. The lots of
constructions are running under Quality Control (QC) conditions. Otherwise constructions
should be done under Quality Assurance (QA) conditions. Anyway QA and QC testing
should be done for aggregate before used it. Generally following tests are done for aggregate
in laboratory.
Industrial Training Report – Training Experience
21
2.1.2.1 Aggregate Impact Value (AIV)
This testing is done in order to identify the impact strength of the aggregate.
Figure 2.12 – Aggregate Impact Tester
Test Procedure
Three test specimens were produced (14mm, 60, 10mm aggregate sizes)
The specimens were dried 105 ± 5 ˚C for period not more than 4 hours and cooled it
to room temperature before testing
25 blows supplied to test specimens for compressing by tempered rod.
Aggregate sample was removed and recorded the net mass, then used same mass for
the 2nd test specimen. (w1).
Impact machine was rested a suitable position and fixed the cup firmly position of the
base of the machine.
Supplied 15 blows from adjust the height of hammer so that its lower face is 380 ± 5
mm above upper surface of the aggregate sample
Removed the crushed aggregate
Whole specimen was sieved from 2.36 mm sieve size mesh.
Weighted the passing materials. (w2).
Industrial Training Report – Training Experience
22
𝐴𝐼𝑉 = 𝑤2
𝑤1𝑋 100%
This value should be lower than 30%.
2.1.2.2 Los Anjalese Abression Value (LAAV)
The abrasion resistance is most important for aggregate as a construction material. Especially
in road constructions, the aggregate usually contact with vehicle tyres. So then occurred a
friction and we want to know about the abression value of aggregate.
Figure 2.13 – LAAV Machine
Test Procedure
First the aggregate samples sieved from suitable sieves (We can use A,B,C and D eny
method)
In our laboratory we used B method. In this method we weighed,
o 19mm passed 12.5mm retained sample = 2500g
o 12.5mm passed 9.5mm retained sample = 2500g
These samples and 11 steel balls added into the rolling drum of the LAAV machine
Start the machine and rotated it 500 revs and then removed the sample and steel balls
After the sample was sieved from 1.7mm sieve
Got the retained sample weight
Calculated the LAAV Value
Industrial Training Report – Training Experience
23
𝐿𝐴𝐴𝑉 𝑉𝑎𝑙𝑢𝑒 = (5000 − 𝑅𝑒𝑡𝑎𝑖𝑛𝑒𝑑 𝑊𝑒𝑖𝑔ℎ𝑡
5000) × 100%
LAAV Value should be lower than 40%
2.1.2.3 Aggregate Gradations
This testing also same to the normal simple gradation test. Test procedure is also same. But
the sizes of sieves are different from other gradations. We did a gradation for aggregate base
coarse (ABC) for mirijjawila crusher plant.
I used 50mm, 37.5mm, 20mm, 10mm, 5mm for gradation in crusher plant site. Smaller than
5mm aggregates were tested in the laboratory by using 2.36mm, 0.425mm, 0.075mm sieves
and pan.
Specific ranges of passing percentages for ABC are following;
Table 2.3- Specific ranges of ABC gradation
Apparatus Size (mm) Spec. Range of cumulative % Passing
50 100
37.5 95-100
20 60-80
10 40-60
5 25-40
2.36 15-30
0.425 7-19
0.075 5-12
2.1.2.4 Flakiness Index (FI)
Flakiness Index test was done for coarse aggregate for identify about the flaky shape. The FI
Value should not larger than 35. Normally we have to do this testing after aggregate
gradation.
Industrial Training Report – Training Experience
24
Test Procedure
The gradation tested sample sieved from using 28mm, 14mm and 6.3mm sieves.
Then following ranges of samples could be obtained.
o 37.5mm – 28mm
o 28mm – 20mm
o 20mm – 14mm
o 14mm – 10mm
o 10mm – 6.3mm
Then we used a metal thickness gauge and pass aggregates through its suitable holes.
It also has 63mm – 50mm and 50mm – 37.5mm holes. But normally ABC samples
have not larger particles more than 37.5mm.
Obtained the passing percentages and weighed initial sample weight
𝐹𝐼 𝑉𝑎𝑙𝑢𝑒 = (𝑤𝑒𝑖𝑔ℎ𝑡 𝑜𝑓 𝑎𝑔𝑔𝑟𝑒𝑔𝑎𝑡𝑒 𝑝𝑎𝑠𝑠𝑖𝑛𝑔 𝑡ℎ𝑟𝑜𝑢𝑔ℎ 𝑔𝑎𝑢𝑔𝑒
𝑖𝑛𝑖𝑡𝑖𝑎𝑙 𝑤𝑒𝑖𝑔ℎ𝑡 𝑜𝑓 𝑠𝑎𝑚𝑝𝑙𝑒) × 100%
Value should not larger than 35%
2.1.2.5 Bulk Specific gravity of aggregate
The ratio of the weight in air of a unit volume of aggregate at a stated temperature to the
weight in air of an equal volume of gas-free distilled water at the stated temperature.
Test Procedure
Aggregate sample divided to 4 groups.
Then the mould was filled from each groups.
Using a tamping rod removed the excess aggregates.
Then weighted the mould with aggregate (w1)
Mould volume (v1)
Mould weight (w)
Loose density = (𝑤1−𝑤
𝑣1)
(Normally ABC aggregate should have value of 1.4 )
This testing was done for sub base, embankments and concrete aggregates.
Industrial Training Report – Training Experience
25
Ten present Finer Value (TFV) and Aggregate Crushing Value (ACV) tests are done at
special cases. Generally we are done above testing only in our laboratory.
2.1.3 Concrete
2.1.3.1 Production of Concrete
Production Process of concrete is consisting of several steps from measuring quantity at the
site to delivering concrete. It is shown in the figure 2.2. Batching process can be done as
fully automated machine. Because of the software problem, now it is operated manually.
Batching plant is consists of three materials storage bins with a capacity of 36m3 to store
river sand, Manufacture sand and coarse aggregates. There is a silo with a capacity of 100
tones to store cement. This arrangement is shown in the figure 2.3.
Aggregates are weighted by manually with the help of pneumatically operated gates.
Weighted materials are transferred to the mixing machine by a conveyer belt. Cement is
transferred through a screw conveyer. Water and chemicals pumped to the mixing chamber
by pumps. Mixing of materials is done for a period of 20 seconds. Half cubic meter of
concrete can be mix at a one batch.
Industrial Training Report – Training Experience
26
Figure 2.14 – Production process of ready mix concrete
Site Incharge Site QS Director Approval Head office
Transport
manager
Plant Manager
Plant Operator
Production of
concrete
Truck mixers
Materials Approved
suppliers
Lab Technician
Batching Plant
Lab
Test Data
Recording
Site
Pouring, Leveling
and Curing Individual
Laboratory
Concrete
Schedule
Original
Copy
Goods Received
Note
Consultant
Approval
Purchasing
Order
Material
Testing
Slump Test
Test cube casting
Slump Test
Test cube casting
Test
Reports
Delivery
Note
Industrial Training Report – Training Experience
27
Figure 2.15 – Arrangement of the Batching plant (left), Plant operating unit (right)
There are various grades of concretes batch in this plant. The operator has to select the
appropriate mix design and do the necessary adjustments to amount of fine/coarse aggregates,
water and chemicals. The mix designs are done at kelaniya main batching plant.
2.1.3.2 Admixtures Use Flyover Concrete Batching Plant
In flyover concrete batching plant they use admixtures to increase initial setting time of
cement, to increase workability (high slump) and decrease slump lost in fresh concrete and
for water proofing purposes. There are two admixtures used for those purposes.
Adcrete
Supercrete
Adcrete
Advantages
Water reducing and retarding admixture
Control rate of set
Improves finishability
Improves Workability
Reduces Water requirement
Reduces Segregation
Increases the strength
Cement Silo
Three Materials
bins
Mixing Machine
Loading Concrete to a
Truck Mixer
Industrial Training Report – Training Experience
28
Reduces Cracking
Reduces Permeability
Dosage: 0.3 to 0.6 liters per 100 kg s of cement.
Supercrete
Advantages
High range water reducing admixture with retarding effect.
Produces highly fluid concrete with extended workability.
Produces flowing concrete with controlled delay of slump loss and extended
workability.
Reduces Segregation and bleeding in plastic concrete.
Reduces porosity, hence permeability of harden concrete.
Reduces concrete placement time and cost
When used as a water reducing agent without cement reduction, it increases strength
by 70% to 100% depending on dosage and concrete mix design.
Dosage: 0.6 to 2.0 liters per 100 kg s of cement.
2.1.3.3 Concrete Testing.
Followings are the tests done at the laboratory for concrete products.
Sieve analysis
Oven dried representative sample of about 500 g s of sand should be taken.
Determine the weight of the sample accurately.
Clean all sieves to remove the stucked particles.
Weigh all sieves and the pan separately.
Prepare a stack of sieves. Sieves having larger opening sizes are placed above the
ones having smaller opening sizes. Place the pan at the bottom.
Pour the sand in to the top sieve and place the cover.
Shake the set of sieves well.
Measure the mass of each sieve + retained sand.
Calculate the weight retained and then percentage finer.
Draw graph of log sieve size vs. % finer. The graph is known as grading curve.
Industrial Training Report – Training Experience
29
Casting test cubes and testing for compressive strength of concrete
Casting test cubes
Figure 2.16 – Standard test mould and tools (left), Casting a test cube (right)
Standard moulds (150mm x 150mm x 150mm), equipment, and tools should be used
to concrete cube casting and inner surfaces of moulds should be oiled.
In some special cases we used (100mm x 100mm x 100mm) moulds.
Sample should be taken after the rotating the agitator well.
Moulds should be placed on a firm level surface.
Moulds should be filled in three equal layers, and each layer should be compacted by
35 blows from the standard tamping rod. Distribute the strokes uniformly over the
cross-section of the mold.
After the compaction, top surface of the cube should be stroke off and trowel to
produce a flat even surface.
Placed a temporary note, indicating the grade, date, identification mark of the
concrete placing point and Truck number, in order to identify the cube.
Specimen should be stored for 24 hours in such a way as to prevent moisture loss and
avoid disturbances and temperature extremes.
After 24 hours, moulds are removed. Details of the attached label are written on the
cubes permanently. Then, cubes are submerged in a water tank.
Strength of concrete is to be tested at 7 days and 28 days.
Industrial Training Report – Training Experience
30
Testing for strength
Figure 2.17 – compression strength testing machine
Measure the dimensions of the test cube and the weight.
Placed the cube in the machine at the center of the stage.
Slowly bring the blocks to bear on the specimenwithout shock until failure
occurs. Apply the load at a constant rate.
Testing machine available at the main laboratory has a digital display. When the dimensions
of the cube entered to the machine at the beginning, it gives the crushing strength of concrete
directly.
Figure 2.18 – Digital display of compression strength testing machine
Industrial Training Report – Training Experience
31
Slump Test
Figure 2.19 – Slump test apparatus (left), measuring the slump (right)
A representative sample should be taken from the concrete batch. It should mix well
before doing the test.
Test must be done as quickly as possible to avoid slump lost.
Dampen the slump cone and place it on a flat, rigid surface.
Hold it firmly in place by standing on the two foot pieces.
Cone should be filled in three layers. Fill the cone 1/3 full and uniformly rod the layer
25 times to its full depth.
Fill the cone with a second layer until 2/3 full by volume and rod 25 times uniformly,
ensuring that the rod just penetrates into the first layer. Fill the third layer in same
manner.
Excess concrete should be Strike off and level with the top of the cone by a screening
and rolling motion of the tamping rod.
Remove spilled concrete from around the bottom of the cone.
The mold should remove immediately from the concrete by raising it carefully in a
vertical direction without lateral or torsional motion.
Keep the slump cone upside down on the plate. Measure the difference between the
height of the mold and the height of the specimen at its highest point to the nearest 6.3
mm. This distance is the slump of the concrete.
Industrial Training Report – Training Experience
32
2.1.4 Bitumen
Bitumen is a most important material used in road constructions. This is the binder material
of asphalt concrete. Testing for bitumen should be done when we the QA and QC road
projects are done. Basically, Ductility, Penetration and softening point of bitumen test, are
done at laboratory. There was a monopoly in Sri Lankan bitumen market. So bitumen tests
can’t affect to change the bitumen. The Flash point of bitumen, these tests also can be done at
laboratory. But generally we did only following three testing.
2.1.4.1 Ductility of the bitumen
This test is done to determine the ductility of distillation residue of bitumen. The ductility
of a bituminous material is measured by the distance in cm to which it will elongate before
breaking when a standard briquette specimen of the material is pulled apart at a specified
speed (5cm/min) and a specified temperature (25°C).
The ductility test gives a measure of adhesive property of bitumen and its ability to stretch.
In flexible pavement design, it is necessary that binder should form a thin ductile film
around aggregates so that physical interlocking of the aggregates is improved. Binder
material having insufficient ductility gets cracked when subjected to repeat traffic loads
and it provides pervious pavement surface.
Figure 2.20 – Water bath
Industrial Training Report – Training Experience
33
Test Procedure
In order to prepare the test sample the sample of bitumen was heated until it melts
The surface of the base plate and two side parts of mold were coated with grease
Melted bitumen sample was poured in to the mold with little excess amount of
bitumen and let it to cool to room temperature
After that it was placed in a water bath of specified temperature
Excess bitumen was removed to have a flat test specimen of 10mm thick
The specimen was attached to the testing machine and removed two side parts of
the mold.
Specimen was pulled apart with a rate of 5cm/min until it breaks
2.1.4.2 Penetration of the bitumen
Consistency of bitumen is measured using the penetration test. In this test a needle with a
specified load is allowed to penetrate the bitumen at specified temperature (25°C) for a
time of 5s.Controlling the temperature is of critical importance. It is necessary to control
the temperature within ± 0.1°C as bitumen very susceptible for temperature.
Penetration of Bitumen is related to viscosity and empirical relationships have been
developed. If penetration is measured over a range of temperatures, the temperature
susceptibility of the bitumen can be established.
Figure 2.21 – Bitumen Penetrometer
Industrial Training Report – Training Experience
34
Test Procedure
Sample container was kept in water bath at 25°C temperature for about 1.5 hrs.
Needle of the penetration apparatus was cleaned and fixed to the apparatus
Needle was brought down to the surface of the bitumen so that it touches the
surface
Penetration value was set to zero at that position
Position for the test was selected so that it was at least 10mm away from the
container and previous test position
Penetration needle was released to penetrate in to the sample. Measuring time was
started at the same time
Needle was stopped by releasing the lock pin at 5s (5 0.1 s).
Penetration was measured in terms of 0.1mm units
Same procedure was repeated to have 3 test results with a maximum penetration
variation of 4.
2.1.4.3 The softening point of the bitumen
Bitumen is a visco-elastic material without sharply defined melting point. They gradually
become softer and less viscous as the temperature rises. For this reason, softening points
must be determined by an arbitrary and closely defined method if results are to be
reproducible. Ring-Ball test is a simple test that remains popular as a consistency test for
measuring softening point.
The softening point is useful in the classification of bitumen, as one element in
establishing the uniformity of shipments or sources of supply, and is indicative of the
tendency of the material to flow at elevated temperatures encountered in service.
Industrial Training Report – Training Experience
35
Figure 2.22 – Ring and Ball Apparatus
Test Procedure
Two bitumen samples prepared in the rings were given for the test
Apparatus was assembled with specimen rings, ball centering guides, thermometer,
and filled with distilled water up to 105mm
Two balls were kept in the water to become to the same temperature
Two balls were placed in the center of the ring
Apparatus was heated uniformly at a rate of 5°C
Temperature indicated in the thermometer at the instant of bitumen surrounded ball
touching the bottom plate was recorded
2.1.5 Asphalt
Asphalt is the most important material mixture, which is used to the road and highway
constructions. Asphalt is made by mixing four different sizes of aggregates, filler and
bitumen at high temperature (more than 150˚C). Basically asphalt divided into two groups
with respect to mix proportions.
1) Binder (relatively high percentage of course aggregates)
2) Wearing (relatively high percentage of fine aggregates)
Because of these percentages, Binder course has a pours and rough surface. Wearing course
has a smooth surface condition.
Industrial Training Report – Training Experience
36
2.1.5.1 Production of Asphalt
There are two asphalt batching plants at Mäga Engineering (PVT) Ltd, Mirijjawila plant. One
of them is the largest asphalt batching plant in Sri Lanka. Nowadays only new plant (large
plant) is used for batching the asphalt. Old one is being repaired.
Production Process of asphalt is consisting of several steps from measuring quantity at the
site to delivering asphalt. It is shown in the figure 2.2. Batching process is done using a fully
automated machine which can be operated manually as well.
Batching plant consists of four materials storage bins to store four sizes of cold bin
aggregates. Aggregates are weighted by electronic system with the help of pneumatically
operated gates. Weighted materials are transferred to the mixing machine by a conveyer belt.
Cement is transferred through a screw conveyer. Water and chemicals pumped to the mixing
chamber by pumps. Mixing of materials is done for a period of 20 seconds. 1.5 Ton of asphalt
can be batch at a time.
There are various mix designs fed to the computer. The operator has to select the appropriate
mix design and do the necessary adjustments to amount of each aggregates and bitumen.
Figure 2.23 – Mirijjawila new asphalt plant (left), cold bins and bitumen tanks (right)
Industrial Training Report – Training Experience
37
2.1.5.2 Asphalt Testing
2.1.5.2.1 Bitumen Extraction Test
Bitumen extraction test was a very important to check the bitumen content of asphalt in
worksite.
Figure 2.24 – Bitumen Extractor
Test Procedure
We carried an asphalt sample from the layering site at paving time.
Then it added to oven to do a bitumen extraction test.
Dried sample and plate of extraction machine 150 ⁰C.
Because it should be same to the paving temperature.
Then the heated sample carried out and put it in to extraction matching as following
figure.
A filter paper is added to the top of the sample to prevent removing the fine aggregate
sample with bitumen.
Started the vibrator and added the petrol for wash and remove the bitumen.
Add the petrol when it removing as the same color. Then stopped the testing and
weighted sample.
Also weighted filter paper.
From using the initial weights, we can calculate the bitumen percentage.
Then the sample was dried in oven.
After dried, it was used for a gradation.
From the result of gradation, we can identify the asphalt sample same or differ with
the designed the asphalt mix.
Industrial Training Report – Training Experience
38
2.1.5.2.2 Marshall tablets making by Marshall Compactor and test specific gravity,
flowability and stability
Figure 2.2 – Marshall Compactor
Asphalt mixture heated 150˚C
Mixture was placed in the mould and spaded with heated spatula 15 times around the
perimeter and 10 times over the top.
The collar was placed and mould was placed on compacting equipment
Applied 75 blows of hammer drops
The mould was removed and replaced again with top side bottom.
75 hammer blows were applied
Base plate was removed and allowed it to cool overnight
Sample was extracted after cooling
Stability and flow were tested using Marshall testing machine
2.1.5.2.3 Testing Specific Gravity, Stability and Flowability
Specific gravity testing was done by using a buoyancy balance (Specific gravity frame)
Figure 2.25 – Buoyancy balance
Industrial Training Report – Training Experience
39
Test Procedure
Stability tester and recorded the stability and flowabilty values. Weighed the tablet in
air = w1 = vdg
Core sample bathed in water tank few minutes
Then weigh the core in water (using buoyancy balance) (w2 = vdg-vρg+x)
Weighed again in air (w3= vdg+x)
Specific gravity = =𝑑
𝜌 =
𝑤1
𝑤3−𝑤2
Stability and flowability test by using Marshall Stability tester. From the marshall
testing we calculated the flowability and stability of asphalt sample.
o Before the stability test the marshalls were heated at 60 ˚C from using a hot
water bath.
o Then the marshall was fixed to the Marshall
Figure 2.26 – Marshall Stability Tester
Industrial Training Report – Training Experience
40
2.1.5.2.4 Core cutting Test
Core cutting was a field testing of asphalt. It was done for check the thicknesses of asphalt
layers and calculates core density.
Normally core cutting was done each 70m on a road. It was done as zigzag type.
Figure 2.27 – Core cutter
Started the motor and adjusting screw rotated down wise. Then the core cutting barrel was
rotated and touches the asphalt layer. Then cut a core sample from the asphalt layer. There
were some water supplied at the bottom of core cutting barrel.
2.1.6 Asphalt Mix Design
I did an asphalt binder mix design for mirijjawila new asphalt plant. Some details of my
design are flowing. All the asphalt testingis covered in this mix design.The main steps of my
asphalt binder course mix design;
1) Individual Gradations
2) Average Gradations
3) Hot bin aggregate gradation and combined grading
4) Specific gravity of aggregate
5) Maximum specific gravity of mixtures
Industrial Training Report – Training Experience
41
6) Mix design data by the marshall method
7) Selection of optimum bitumen content
First I carried different sizes of hot bin aggregetes, filler and bitumen.
Following materials used for asphalt mix design;
Aggregate – (00-05)mm, (05-10)mm, (10-16)mm, (16-20)mm
Filler (quarry dust), Bitumen (grade-60/70)
Then I started gradation for each sample. I did my asphalt binder design in BS standard. So I
used 28mm, 20mm, 10mm, 5mm, 2.36mm, 1.18mm, 0.6mm, 0.3mm, 0.15mm and 0.075mm
sieves for the gradation. Individual gradation is done twice for one aggregate size particles.
Then average gradation prepared by using the results.
2.1.6.1 Average gradations of my design
Table 2.4- Average Gradation Results
Hot bin
No: 01 02 03 04 05
Sieve Size in
mm
%
Passing
%
Passing
%
Passing
%
Passing
%
Passing
28.0 100.0 100.0 100.0 100.0 100.0
20.0 100.0 100.0 100.0 100.0 100.0
10.0 100.0 90.1 24.4 3.1 100.0
5.00 94.5 7.9 1.0 0.2 100.0
2.36 77.0 0.9 0.3 0.1 100.0
1.18 58.8 0.4 0.2 0.1 100.0
0.600 45.4 0.4 0.2 0.1 98.1
0.300 32.3 0.4 0.2 0.1 97.3
0.150 20.5 0.4 0.2 0.1 94.5
0.075 4.3 0.4 0.2 0.1 79.4
After then I calculated an Aggregate proportions for a most suitable job mix formula. My
aggregate blend and combined grading analysis results are following;
Industrial Training Report – Training Experience
42
Table 2.5- Aggregate Blend and JMF
B. Aggregate Blend
No Aggregate
Proportions% 28 20 10 5 2.36 1.18 0.6 0.3 0.15 0.075
1 37 37.0 37.0 37.0 35.0 28.5 21.8 16.8 12.0 7.6 1.6
2 25 25.0 25.0 22.5 2.0 0.2 0.1 0.1 0.1 0.1 0.1
3 20 20.0 20.0 4.9 0.2 0.1 0.0 0.0 0.0 0.0 0.0
4 15 15.0 15.0 0.5 0.0 0.0 0.0 0.0 0.0 0.0 0.0
5 3 3.0 3.0 3.0 3.0 3.0 3.0 2.9 2.9 2.8 2.4
C. Combined
Grading
% Passing 100.0 100.0 67.9 40.2 31.8 24.9 19.9 15.0 10.6 4.1
Then I did the specific gravity testing for aggregates. The test procedures were different for
fine and coarse aggregates.
The bulk specific gravity was tested as earlier method (test-2.1.2.5)
Maximum specific gravity can be calculated two ways. One is only using theory. Another
method is the Gmm Test.
2.1.6.2 Maximum Theoretical Density (Gmm) Test
Test Procedure
The asphalt sample was put into the oven ( at 150 ⁰C)
Then it was reduced as small particles and weighted a sample nearest weight , 900g
(w0 )
Then Gmm flask was weighted (w1)
Weighted it again after adding water (w3)
Then added asphalt sample into the flask and add water more enough. (1 inch more
over the sample).
Before add water got weight flask with asphalt (w)
Then the flask was fixed with vacuum chamber and vibrated the flask and removed air
voids.
Industrial Training Report – Training Experience
43
Then after the removing air voids carefully added water to the flask when it fully fills
up.
Got the final weight of ( water + sample+ flask ) (w3)
𝐺𝑚𝑚𝑣𝑎𝑙𝑢𝑒 = (𝑤 − 𝑤𝑖)
(𝑤2 − 𝑤1) + 𝑤 − 𝑤3
2.1.6.3 Marshall Making Procedure
Measured the 1240g of hot bin aggregate.
Then Aggregates were heated to 150°C
Heated aggregates were poured in to the mixing bowls and 3.5%, 4.0%, 4.5%, 5.0%,
5.5% of bitumen heated to 150°C was also poured in to each of them.
Asphalt and aggregates were mixed well with the mixer for about 2 min
Mixture was placed in the mould and spaded with heated spatula 15 times around the
perimeter and 10 times over the top.
The collar was placed and mould was placed on compacting equipment
Applied 75 blows of hammer drops
The mould was removed and replaced again with top side bottom.
75 hammer blows were applied
Base plate was removed and allowed it to cool overnight
Sample was extracted after cooling
Stability and flow were tested using Marshall testing machine
Then consider about Mix Design Data by the Marshall Method and selected an optimum
bitumen content.
Specification limits for selection of suitable range (for high traffic)
o Marshall Stability (kN) – Not less than 8.0
o Marshall Flow (0.25mm) – 8 to 16
o Air Voids in Mix (%) – 3 to 7
o Voids in Mineral Aggregate (%) – Not less than 13
Industrial Training Report – Training Experience
44
2.2 Training at Siribopura interchange project.
Figure 2.26 – Siribopura Flyover
2.2.1 Introduction
Siribopura interchange project at Hambantota, was the training bay for me from 03/10/2012
to 01/11/2012. It is a 150m flyover, four turns and four circular roads. Also it has an overpass
sub project. The Project Manager is Mr. Kanchana Jayasekara and Site Manager of the site is
Mr. K. W. P. Renuja.
2.2.1.1 Project Details
1. Project -Construction of Siribopura Intrechange at Siribopura, Hambantota.
1. Fundrd By - China Development Bank.
2. Client and Consultant -Road Development Authority (RDA).
3. Main Contractor - CATIC Engineering Co-orporation.
4. Sub-Contractor - Mäga Engineering (Pte) Ltd.
5. Scope of Work -Construction of Flyover, four turns and four
circular roads.
6. Project Estimate - Rs. 1.59 billion.
7. Construction period - 06th January 2007 – 06th July 2008
8. Post tension beams -UTRACON overseas (Pvt) Ltd is a sub-
contractor for Mäga Engineering (Pte) Ltd for
post tensioning the concrete beams.
Industrial Training Report – Training Experience
45
SUPERVISOR
FF
SITE
MANA
GER
SUB
CONTRA
CTOR-
MAGA
PROJE
CT
MANA
GER
SAFTY
OFFICE
R
STORE KEEPE
R
ACCOU
NTS
ASSIST
ANT
SITE
ENGINEER
Road
Works
TECHN
ICAL
OFFICE
R
TECHN
ICAL
OFFICE
R
TECHN
ICAL
OFFICE
R
ASISTA
NT
QUANT
ITY
SURVE
YOR
(Mr.
M.H.O.
D.
Jayaratn
e)
SURVE
YOR (Mr.
Chamin
da Rajapak
sha)
COSTING
OFFICE
R (Mr.
A.H.
Supun prabodh
a)
DRAU
GHTMAN
(Mr.
N.H.D.S.
Premara
thne)
SITE ENGINE
ER
Structura
l Works
FOREM
AN
FOREM
AN
Figure 2.30 – Organizational structure of Siripobura interchange project
Industrial Training Report – Training Experience
46
2.2.2 Duties at the Site
At this site I got the opportunity to get experience in labour handling. Every day, I was given
labour to perform a particular task. I inspected the backfilling of entering ramps, ABC laying,
stock piles and borrow pits. I studied about formworks; reinforcements and surveying when
train in this site. When a concreting is going on it was my duty to test the slump and cast test
cubes.
2.2.3 Road construction
A road is a hard surface made on an embankment for easy transport of goods and passengers
by vehicles. Usually a road connects two stations. In addition to connect two stations it will
have serve a lot of people around the road. A good road should have following
characteristics.
Straight as much of possible
Short as much of possible
Easy curves
Low gradient
Strong foundation
Good sight distance
The road construction is divided in to three categories such as new construction, re-
construction and stage construction. The new construction is meaning that the road is
conducting from initial stage to connect two stations. Any improvements or constructions
work done in already made road is called re-construction. Stage construction that is the
construction works are carried out in stages. These stages are drain, culvert and retaining wall
construction, preparing sub base, base and asphalt constructions.
In Siribopura interchange project is a new construction of road. The work consists of earth
works, backfill, sub bases, ABC laying , asphalt laying, construction of drains, center median,
foot walk, culvert and construction of flyover. In some places the sub base is removed and
filled by specified soil layer. Therefore excavation and filling is carried out in required design
height.
Industrial Training Report – Training Experience
47
Here in this section some road construction works are described,
Back filling
ABC laying
Asphalt concrete laying
Drain construction
A typical road section
Figure 2.31 – A typical road section
Layer thicknesses
Asphalt layer = 50mm or 40mm
ABC layer = 250mm
Sub base layer = 300mm (for a fill) or 350mm(for a cut)
Capping layer = 200mm
Embankment layer = 150mm (any number of layers, depending on the situation)
Cross section of road
Figure 2.32 – A typical cross section of road
binder course
ABC layer
Sub soil 1
Sub soil 2
wearing course
Carriageway
1.1.
m
1.1 m 4.5 m 4.5 m
0. 70 m
0.15 m
2.5
%%
%%
%
Shoulder
Drain
Industrial Training Report – Training Experience
48
Carriageway
The carriageway is the surface of the road on which the vehicles are expected to run.
Carriageway can be single lane, two lanes, four lanes or multi lanes. A traffic lane is defined
for the use of single line of traffic demarcated by lane marking. In our site Overpass of
flyover road has two lanes.
Shoulders
The shoulder width is measured from edge of the carriageway to the edge of the usable
formation free from obstructions. It is used for pedestrians, pedal cyclists and vehicles for
standing.
Drains
Drains are provided for the efficient discharge of storm water that falls into them from the
road surface. The minimum width of drains should be 0.5 m; the cross section may be
rectangular or trapezoidal. There are two types of drains used in our site such as Box drains
and Dish drains.
Center medin
For multilane roads, center medians are required to drive the carriageway to avoid conflicts
of opposing traffic. They also provide refuge for pedestrians crossing the road. For safety
reasons two-way multilane roads should always have medians.
Right of way
Right of way is the total land area used for the road including the reservation for utility
services and any widening in the future.
Cross fall
The purpose of the cross fall is to drain the road surface. The cross fall of the carriageway is
2.5% and footpath is 4%.
Industrial Training Report – Training Experience
49
Backfilling
The road sections at each 20m interval are drawn by the draftsmen (with camber,
super elevation, soil and asphalt layers) including finished levels.
After receiving the drawings and the data sheets, the centerline of the road is
established using the total station machine. Then the offsets for the road edges with 1
or 1.5m off is established.
Using the drawings of the cross sections, the levels of the center and edges of the road
to the embankment top, sub base top or finished level is marked. In accordance with
that, the excavation or filling is done. And leveled using motor graders, watered and
compacted using rollers.
Figure 2.33 - Watering a sub base top of a road section
Then we request for inspection (RFI) from RDA (Consultant). A technician or a
supervisor of RDA with some and equipments of Material Testing Laboratory of
Maga come to the particular place and do a sand cone test at necessary places.
Normally they are doing two tests for each 100m length of a double lane track. Then
they calculate the amount of compaction by calculating the field density as a
percentage of the Maximum Dry Density (MDD) and the moisture content as well.
The moisture content is compared with the Optimum Moisture Content (OMC). If
they are under permissible levels, the next layer can be laid on it.Each and every layer
has to undergo the same procedure.
Industrial Training Report – Training Experience
50
Figure 2.34 -Laying and leveling embankment on a road section
Figure 2.35 - Doing a sand cone test on a compacted ABC surface
Laying ABC is one of the most important works done in the construction of roads and
a great care should be taken while leveling and compacting ABC. That is because the
levels of the ABC layer should be accurate within ± 5mm and the compaction should
have achieved 98% - 100%.
Figure 2.36 - Laying ABC on a sub base top and leveling
Industrial Training Report – Training Experience
51
Then a 50mm binding layer (a type of an asphalt layer) is laid on it after applying a
prime coat. The prime coat is a bitumen layer applied directly on the brushed and
cleaned ABC surface before the asphalt layers. It’s for the purpose of a good bonding
between the ABC layer and asphalt layer.
Figure 2.37 - Applying the prime coat on a cleaned ABC surface
Then another 40mm wearing layer (a type of an asphalt layer) is applied on it.
Sometimes we apply the wearing layer straight away on ABC layer, then it becomes a
50 mm wearing layer. It depends on the consultant of the project or the condition of
the surface of the previous layer (if the layer is applied on a layer which was existing
for a considerable time period, mostly in road rehabilitation projects when laying
asphalt on prevailing asphalt or macadam roads).
Figure 2.38 - Laying an asphalt layer on a prime coated ABC surface
Industrial Training Report – Training Experience
52
2.2.4 Structural Works
2.2.4.1 Formworks
Here I would describe the formwork with referring to the formwork of the culvert. Majority
of the formworks are done in the same way. There are few main areas where I may pay my
attention in formworks. They are;
Plywood boards
P – cones
The way of using boards with GI pipes and form ties.
Normally the plywood boards are of dimensions 2440mm×1220mm and 12mm thick.
We fix 2"×2" wooden parts at the edges of the boards for the convenience of fixing
and to obtain a rigid connection with other boards.
P – cones are a special technique been used in the formworks to maintain a specified
constant spacing within plywood boards and to fix form ties to the board to support or
connect to the GI pipes which are used to align and support the boards along with
pipes and ‘U’ jacks.
Normally the length of a P-cone is 25mm and the length which another thread bar can
be inserted in to it is 15mm. The P-cone consist of a plastic head which is tapering
towards a one end and a thread bar at the other end.
We cut the thread bars which are to be installed in the P-cone arrangement of the
formwork to a specified length. As the length which a thread bar goes inside of a P-
cone is 15mm, we cut the thread bar leaving space for the P-cone as well. Therefore
we reduce 20mm for the two P-cones at the two ends of a thread bar. We use a
conduit pipe to cover the thread bar from concrete. After setting the concrete, we can
remove the thread bar and then those wholes can be grouted.
Figure 2.39 - A real Pcone thread bar arrangement in the formwork
Industrial Training Report – Training Experience
53
We fix the form ties for the part of the thread bar (of the P-cone) which is extending
outwards of the P-cone of the formwork in the way that is shown in the figure. Then
we connect GI pipes for the form ties at the end of the form tie where it has a part of
thread bar and inside the two curved parts of the form tie to make the plywood boards
stiff and interconnected. While fixing form ties, we maintain the continuity of GI
pipes which are connected from inside of the form tie. The other GI pipe which is at
the end of the form tie is to jack the GI pipe, form tie, plywood board arrangement
from outward to control the deflections or movements of the entire formwork which
can be possibly present when the structure is concreted.
Figure 2.40 -GI pipe, form tie, P cone arrangement in the formwork
When there are few plywood boards to be fixed and aligned, we use this form tie GI
pipe arrangement along with long GI pipes which are connecting two or more of those
boards. And this arrangement gives the rigidity for the formwork.
2.2.4.2 Reinforcement
During my training period in my site I got opportunity to study the reinforcements of Slab,
Lift walls, Columns, Shear walls, Stair cases and Guard walls.
Reinforcement is a very important part in a structure. Special attention should pay when tying
reinforcement. Especially when bar benders don’t have the skill to read drawings, continuous
attention is very essential. That is because if a mistake happens it may very difficult to correct
by the time it identify.
Industrial Training Report – Training Experience
54
2.2.4.3 Drain construction
As the road is built, typical drainage system shall be arranged at side of the road to flow the
water of the area. In this project, there are two types of drains are constructed such as
Concrete U drain and Concrete dish drain.
In my training period I had to inspect a concrete U drain. Concrete U drain is a reinforced
concrete structure. Normally, these are constructed at town areas. Because of this wall has
good strength and small space required for section construction than other types of drains
such as random rubble masonry drain and earth drain. If flowing quantity of water is high,
those area should have U drain instant for dish drain, but concrete drain has a high cost for
construction comparing dish drains because of reinforcement and quantity of concrete. In U
drain we were used reinforcement diameter 12 mm, 10mm and 6mm. Height of U drains is
600mm. The opening of U drain is 600mm and 1200mm, therefore has to be changed design
of reinforcement arrangement. The concrete grade 25 N/mm2 is used for constructing U
drains. The typical cross section of U drain is given below.
Figure 2.41 – Arrangement of U drain
Distribution bars
R6/150
Main bar
R10/275mm
600mm 600mm
Industrial Training Report- Conclusion
55
CHAPTER 03
3. CONCLUSION
I was thirst to learn as much as possible throughout my six months training period from the
day of commencement. I received valuable guidelines from my lectures before starting my
industrial training and those were very helpful throughout the training period. Those six
months were very precious for my life as it was the first time which I gained the experience
of a real industrial environment. Furthermore it was a golden opportunity for my life to being
a trainee at a distinguished company in Sri Lanka.
There I gained an opportunity to obtain the knowledge on various fields by various ways.
Furthermore I was able to enhance my knowledge which was gained through my university
life while getting new things to my life. At my training place freedom was given to obtain
the things into my life as could as possible in order to make my six months training period
fruitful.
Finding a proper training establishment which has resources to cover at least few from the
above was not an easy task. Fortunately I could select Maga Engineering (Pvt) Ltd as my
training establishment. As I heard it was very strict and less paying organization for trainees.
But my thirst to learn made me choose Maga.
According to its system they usually work all seven days in the week without caring about
Poya days, weekend holidays or any other public holidays. Leaves are given only three days
per month. At the beginning this was very hard experience. But eventually I got used to it and
accePted it as a blessing, because that was the real practice in most private construction
companies in Sri Lanka. So it was like a trial session before becoming an occupant in this
industry.
There I learned things such as lot of testing about construction materials, asphalt mix designs,
asphalt and concrete batching plants, site experiences and labor handling. I trained nearly
twenty weeks as a materials engineer at Mirijjawila main highway laboratory. I trained under
Material consultant, Dr. Frenando. He is an experienced and best qualified Materials
consultant in Sri Lanka. It was a great opportunity to get train under him. Also I worked
under Materials engineer Mr. Indunil Kumara. He instructed me about new materials testing
Industrial Training Report- Conclusion
56
methods. Mäga Engineering (Pte) Ltd use new testing methods to improve the quality of the
constructions. Therefore I could learn new testing methods rather than old methods.
Generally we have to do testing under quality control conditions. So we had to work with our
consultants, Road Development Authority, Water Board and etc. So I have to deal with Mr.
Jayarathne, who was a senior experienced material engineer of Road Development Authority.
He also instructed me about the research and development testing of road construction field.
He also advised me about higher studies about the construction materials.
I did an asphalt binder mix design in highway laboratory. All the laboratory staff and helpers
gave me their contribution. Our material consultant Dr. Fernando advised me about the
improvement of the design. After the design project manager appreciated me and he guided
to me to do another design for asphalt wearing. Those designs were very important to
improve my knowledge about asphalt materials. I think as material engineers we can improve
the properties of the asphalt by using latex like materials.
Last month I assigned to the siribopura interchange project. I learned about the site testing in
this training location. Also I got an experience as a site engineer in a road site, learned about
field testing, road construction and some structural constructions. Also deal with various
workers and learned about labor handling in a site.
Even though I got a good training at Mäga Engineering (Pte) Ltd, I got to know that some of
my friends got bad experiences. One of a trainee assigned to Mäga Engineering (Pte) Ltd was
resigned from the company after one week. Because their site works were too hard and
running same process and there is nothing new to learn. But I was very lucky to train in a
highway laboratory with all facilities and experienced staff.
Industrial training program conducted by Industrial training division of University of
Moratuwa in collaboration with NAITA is very valuable for the engineering career of an
undergraduate. Assigning academic advisors and their continual inspection on trainees during
the training period is very important. I must thankful to my advisor for his kind advices and
guidance. Submitting four weeks report is very important to continual assessment of training.
I suppose that two or three training periods rather than a one period may more valuable for
have better experience on various material engineering activities, applications and designs.
Because material engineering is a wide field with including polymer, metal, construction
materials, ceramic, composites etc. As a material engineer in construction field, one should
Industrial Training Report- Conclusion
57
have a thorough knowledge on all sections of construction materials such as concrete, soil,
aggregate, bitumen, asphalt etc. But most of the trainees can get experience only in one
section. I haven’t got wide experience about concrete mix design. Anyway I am lucky to
work in complete main highway laboratory and a large road and bridge construction site.
Industrial Training Report- Abbreviations
vii
LIST OF ABBREVIATIONS
Pte – Private
Ltd – Limited
ICTAD – Institute for Construction Training and Development
QA – Quality Assurance
QC – Quality Control
PI – Plasticity Index
LL – Liquid Limit
PL – Plastic Limit
OMC – Optimum Moisture Content
MDD – Maximum Dry Density
IMC – Initial Moisture Content
CBR – California Bearing Ratio
DCP – Dynamic Cone Penetration
AIV – Aggregate Impact Value
LAAV – Los Angeles Abrasion Value
ABC – Aggregate Base Coarse
FI – Flakiness Index
TFV – Ten percent Finer Value
ACV – Aggregate Crushing Value
QS – Quantity Surveyor
JMF – Job Mix Formula
Gmm – Maximum Theoretical Density
Industrial Training Report- Abbreviations
viii
RDA – Road Development Authority
RFI – Request for Inspection
GI – Galvanized Iron
ME – Material Engineer
PM – Project Manager
SM – Site manager
Industrial Training Report- References
ix
REFERENCES
Standard Specifications for Construction and Maintenance of Roads and Bridges
[2nd Edition – June 2009]
http://www.fhwa.dot.gov/pavement/t504027.cfm
http://docs.lib.purdue.edu/cgi/viewcontent.cgi?article=1496&context=jtrp
http://www.controls-group.com/eng/
Industrial Training Report- Annex
viii