216
TARGET LEVELS OF RELIABILITY FOR DESIGN OF BRIDGE FOUNDATIONS AND APPROACH EMBANKMENTS USING LRFD __________________________________________________________________ A Dissertation presented to the Faculty of the Graduate School University of Missouri __________________________________________________________________ In Partial Fulfillment of the Requirements for the Degree Doctor of Philosophy __________________________________________________________________ by DANIEL R. HUACO, MSCE, E.I.T. Dr. J. Erik Loehr, PE Dissertation Supervisor Dr. John J. Bowders, PE Dissertation Co-Supervisor December 2014

TARGET LEVELS OF RELIABILITY FOR DESIGN OF BRIDGE

  • Upload
    others

  • View
    1

  • Download
    0

Embed Size (px)

Citation preview

Page 1: TARGET LEVELS OF RELIABILITY FOR DESIGN OF BRIDGE

TARGET LEVELS OF RELIABILITY FOR DESIGN OF

BRIDGE FOUNDATIONS AND APPROACH EMBANKMENTS USING LRFD

__________________________________________________________________

A Dissertation

presented to

the Faculty of the Graduate School

University of Missouri

__________________________________________________________________

In Partial Fulfillment

of the Requirements for the Degree

Doctor of Philosophy

__________________________________________________________________

by

DANIEL R. HUACO, MSCE, E.I.T.

Dr. J. Erik Loehr, PE Dissertation Supervisor

Dr. John J. Bowders, PE Dissertation Co-Supervisor

December 2014

Page 2: TARGET LEVELS OF RELIABILITY FOR DESIGN OF BRIDGE

The undersigned, appointed by the Dean of the Graduate School, have examined

the dissertation entitled

TARGET LEVELS OF RELIABILITY FOR DESIGN OF

BRIDGE FOUNDATIONS AND APPROACH EMBANKMENTS USING LRFD

presented by Daniel R. Huaco, MSCE

a candidate for the degree of Doctor of Philosophy in Civil Engineering

and hereby certify that in their opinion it is worthy of acceptance.

____________________________________

Dr. J. Erik Loehr, PE

Department of Civil and Environmental Engineering

____________________________________

Dr. Brent Rosenblad

Department of Civil and Environmental Engineering

____________________________________

Dr. Carmen Chicone

Department of Mathematics

____________________________________

Dr. James Noble, PE

Industrial & Manufacturing Systems Engineering

Page 3: TARGET LEVELS OF RELIABILITY FOR DESIGN OF BRIDGE

To my family …

This dissertation is dedicated to my wife, for her love and support, to my children

for the time my work took me away from them and to my parents for their guidance, love

and support.

Page 4: TARGET LEVELS OF RELIABILITY FOR DESIGN OF BRIDGE

ii

ACKNOWLEDGEMENTS

I would like to express my gratitude to my advisors Dr. Erik Loehr and Dr. John

Bowders for guidance throughout this project and for their patience to share their

knowledge, their advice and support throughout my studies. I would also like to thank the

Missouri Department of Transportation (MoDOT) for providing funding and information

for the project. I would also like to thank Dr. Carmen Chicone, professor of the

Department of Mathematics for his invaluable contributions and recommendations to this

project. I would like to express my sincere appreciation to all of my committee members

for their valuable advice: Dr. Erik Loehr, Dr. John Bowders, Dr. Brent Rosenblad, Dr.

Carmen Chicone and Dr. James Noble. I thank my family for their patience,

understanding and support during my years of study. And finally I would like to express

gratitude to my fellow students of the geotechnical engineering program for their

availability and help during this study.

Page 5: TARGET LEVELS OF RELIABILITY FOR DESIGN OF BRIDGE

iii

TABLE OF CONTENT

ACKNOWLEDGEMENTS .................................................................................... ii

TABLE OF CONTENT ......................................................................................... iii

LIST OF TABLES ................................................................................................ vii

LIST OF ILLUSTRATIONS .................................................................................. x

ABSTRACT ......................................................................................................... xxi

1 INTRODUCTION ................................................................................ 1

1.1 Background ........................................................................................... 1

1.2 Hypothesis and Objective ..................................................................... 2

1.3 Scope of the Work ................................................................................ 3

1.4 Organization of Dissertation ................................................................. 4

2 LITERATURE REVIEW ..................................................................... 6

2.1 Introduction ........................................................................................... 6

2.2 Definitions and Concepts ...................................................................... 6

2.2.1 Risk ........................................................................................................ 6

2.2.2 Acceptable and Tolerable Levels of Risk .............................................. 8

2.2.3 The Value of Life ................................................................................ 11

2.2.4 Willingness to Pay ............................................................................... 13

2.3 FN Charts ............................................................................................ 13

2.3.1 Hong Kong Government Planning Department (1994). ...................... 14

2.3.2 External Safety Policy in the Netherlands (1987). .............................. 16

2.3.3 The Australian National Committee on Large Dams (1994). ............. 18

2.3.4 Risk Assessment of Nambe Falls Dam (1996). ................................... 20

Page 6: TARGET LEVELS OF RELIABILITY FOR DESIGN OF BRIDGE

iv

2.3.5 Historical Performance of Civil Infrastructure .................................... 22

2.4 Current Levels of Reliability for the Design of Bridge Foundations.. 24

2.5 Summary ............................................................................................. 25

3 APPROACH FOR ESTABLISHING TARGET PROBABILITIES OF

FAILURE ............................................................................................ 27

3.1 Introduction ......................................................................................... 27

3.2 Study Background ............................................................................... 27

3.3 General Approach for Establishing Target Probabilities of Failure ... 29

3.4 Economically Optimized Probabilities of Failure............................... 31

3.4.1 Mathematical Representation of Expected Monetary Value ............... 32

3.4.2 Initial Costs .......................................................................................... 33

3.4.3 Consequence Costs .............................................................................. 35

3.4.4 Derivation of Optimum Probability Function and FN Curve .............. 36

3.5 Socially Acceptable Probabilities of Failure ....................................... 37

3.6 Summary ............................................................................................. 40

4 CONSEQUENCE COSTS FOR BRIDGES ....................................... 41

4.1 Introduction ......................................................................................... 41

4.2 Consequence Costs for Strength Limit State ...................................... 42

4.3 Consequence Costs for Service Limit States ...................................... 44

4.4 Development of Relations between Initial Costs and Consequence

Costs .................................................................................................... 47

4.5 Summary ............................................................................................. 50

5 BRIDGE FOUNDATION ECONOMIC ANALYSIS ....................... 51

Page 7: TARGET LEVELS OF RELIABILITY FOR DESIGN OF BRIDGE

v

5.1 Introduction ......................................................................................... 51

5.2 Probability of Failure-Cost Relations ................................................. 51

5.2.1 Taylor Series Method .......................................................................... 52

5.2.2 Probability of Failure – Cost Function Slope Factor ........................... 54

5.2.3 Pile Groups .......................................................................................... 58

5.2.4 Drilled Shafts ....................................................................................... 68

5.2.5 Spread Footing ..................................................................................... 78

5.2.6 Approach Embankments ...................................................................... 88

5.3 Sensitivity Analysis ............................................................................ 99

5.3.1 Pile Groups - Sensitivity Analysis ....................................................... 99

5.3.2 Drilled Shafts - Sensitivity Analysis ................................................. 105

5.3.3 Spread Footings - Sensitivity Analysis .............................................. 110

5.3.4 Approach Embankments - Sensitivity Analysis ................................ 115

5.4 Summary ........................................................................................... 118

6 DEVELOPMENT, ANALYSIS AND CALIBRATION OF

ECONOMIC CURVES .................................................................... 122

6.1 Introduction ....................................................................................... 122

6.2 FN Charts and Economic Curves ...................................................... 122

6.2.1 Pile Group FN Charts ........................................................................ 123

6.2.2 Drilled Shafts FN Charts ................................................................... 126

6.2.3 Spread Footing FN Charts ................................................................. 129

6.2.4 Bridge Approach Embankment FN Charts ........................................ 132

6.3 FN charts from Sensitivity Analysis ................................................. 136

Page 8: TARGET LEVELS OF RELIABILITY FOR DESIGN OF BRIDGE

vi

6.4 Suggested Target Levels of Probabilities of Failure ......................... 144

6.5 LRFD Application ............................................................................ 154

6.6 FN Chart Considerations................................................................... 154

6.7 Summary ........................................................................................... 156

7 PRACTICAL IMPLICATIONS ....................................................... 159

7.1 Introduction ....................................................................................... 159

7.2 Acceptable Probabilities of Failure and FN Charts .......................... 159

7.3 Suggested Target Probabilities of Failure (Pf) and Reliabilities (R) . 164

7.4 Considerations for the Suggested Probabilities of Failure ................ 168

7.5 Summary ........................................................................................... 170

8 SUMMARY, CONCLUSIONS AND RECOMMENDATIONS..... 171

8.1 Summary ........................................................................................... 171

8.2 Conclusions ....................................................................................... 176

8.3 Recommendations ............................................................................. 177

APPENDIX . ....................................................................................................... 178

REFERENCES ................................................................................................... 185

VITA ……………… .......................................................................................... 192

Page 9: TARGET LEVELS OF RELIABILITY FOR DESIGN OF BRIDGE

vii

LIST OF TABLES

Table 2.1 Average risk of death to an individual (US Nuclear Regulatory

Commission 1975, taken from by Baecher and Christian, 2003) ....... 9

Table 2.2 Risk of death to society (US Nuclear Regulatory Commission 1975,

taken from Baecher and Christian, 2003) ............................................ 9

Table 2.3 Suggested tolerable risks for loss of life due to slope failure (AGS,

2000) .................................................................................................. 10

Table 2.4 Value of Statistical Life based on 2000 US dollars (Viscusi, 2003) .... 12

Table 4.1. Present value of initial costs of bridges (2010) that have collapsed in

the US and the cost of replacement. .................................................. 43

Table 4.2. Presents bridge types, sizes and levels of settlement damage ............ 48

Table 4.3. For the selected bridges, the table presents the year and cost of

construction along with the repair costs for three levels of damage

due to settlement. (Information provided by Missouri Department of

Transportation-MoDOT, 2009). ........................................................ 48

Table 5.1. Design parameter values, standard deviations and c.o.v’s used to

develop pile group probability of failure-costs functions. ................ 60

Table 5.2. Design parameter values and standard deviations used to develop

drilled shafts probability of failure-costs functions. .......................... 70

Table 5.3. Design parameter values and standard deviations used to develop

spread footing probability of failure-costs functions. ....................... 80

Page 10: TARGET LEVELS OF RELIABILITY FOR DESIGN OF BRIDGE

viii

Table 5.4 Design parameter values and standard deviations used to develop

embankment probability of failure-costs functions. .......................... 90

Table 5.5 Slope factors b for foundations and embankments considering strength

and service limits ............................................................................. 119

Table 5.6 Upper and lower range values of the slope factors b for bridge

foundations ...................................................................................... 119

Table 5.7 Change in foundation slope factor b values due to sensitivity analysis

when reducing costs, loads and c.o.v. of design parameters by 50

percent of their original value ......................................................... 121

Table 5.8 Change in embankment slope factor b values due to sensitivity analysis

when reducing costs, and soil strength parameters by 50 percent of

their original value ........................................................................... 121

Table 6.1 Suggested target probability of failure, Pf for the design of bridge

foundations and embankments. ....................................................... 152

Table 6.2 Suggested target reliabilities R = (1- Pf) for the design of bridge

foundations and embankments. ....................................................... 152

Table 6.3 Target probability of failure, Pf for the design of bridge foundations and

embankments (modified by MoDOT, July 2010). .......................... 153

Table 6.4 Target reliabilities R = (1- Pf) for the design of bridge foundations and

embankments (modified by MoDOT), July 2010). ......................... 153

Table 7.1 Suggested target probability of failure, Pf for the design of bridge

foundations and embankments ........................................................ 165

Page 11: TARGET LEVELS OF RELIABILITY FOR DESIGN OF BRIDGE

ix

Table 7.2 Suggested target reliabilities R = (1- Pf) for the design of bridge

foundations and embankments ........................................................ 165

Table A.1 Format of the bridge cost information answer sheet for the

questionnaire filled by the Missouri Department of Transportation,

MoDOT……………………………………………………………179

Table A.2 Characteristics and costs of selected Missouri bridges (MoDOT).....179

Table A.3 Repair costs for 5 Missouri bridges considering 3 service limit

states…………………………………………………………….…..180

Table A 4. Missouri bridge costs for Service Limit State A (minor damage)….180

Table A.5 Missouri bridge costs for Service Limit State B (intermediate

damage)………………………………………………….………….181

Table A.6 Missouri bridge costs for Service Limit State C (major

damage)……………………………………………………………..181

Table A.7 Bridge settlement repair costs for 3 service limit states….……...….182

Table A.8 Calculations of different settlement limits for three levels of bridge

damage using angular distortion method…………………………..182

Page 12: TARGET LEVELS OF RELIABILITY FOR DESIGN OF BRIDGE

x

LIST OF ILLUSTRATIONS

Figure 2.1 Value of Life in the United States (EPA, 2008) .................................. 12

Figure 2.2 Societal risk guidelines FN chart of acceptable levels of risk for the

whole population living near a potentially hazardous installation

(Hong Kong Government Planning Department, 1994). ................. 16

Figure 2.3 Netherlands government group risk criterion (Versteeg, 1987) .......... 18

Figure 2.4 Risk guideline from ANCOLD (1994) ................................................ 19

Figure 2.5 FN chart used by the US Bureau of Reclamation on Nambe Falls Dam,

New Mexico to compare risks of the existing dam with ANCOLD

limits (Von Thun, 1996). ................................................................. 21

Figure 2.6. Relationship between annual probability of failure (F) and lives lost

(N) (expressed in terms of $ lost and lives lost) for common civil

facilities (Baecher and Christian, 2003). .......................................... 23

Figure 3.1 Resistance factors developed for design of earth slopes (Loehr et al.,

2005). ............................................................................................... 29

Figure 3.2 FN chart comparing socially acceptable and economically optimized

values for the probability of failure, Pf. ........................................... 31

Figure 3.3 Graphical representation of the relation between expected monetary

value (E), probability of failure (P) and consequence cost (X). ....... 35

Figure 3.4 Expected monetary value curves in which the optimum probability of

failure (Popt) is shown to coincide with the minimum expected

monetary value for different values of consequence X. ................... 36

Page 13: TARGET LEVELS OF RELIABILITY FOR DESIGN OF BRIDGE

xi

Figure 3.5. Relationship between annual probability of failure (F) and lives lost

(N) (expressed in terms of $ lost and lives lost) for common civil

facilities (Baecher and Christian, 2003). .......................................... 38

Figure 3.6. FN chart showing average annual risks posed by a variety of

traditional civil facilities and other large structures along with

several proposed boundaries reflecting acceptable probabilities of

failure. .............................................................................................. 39

Figure 4.1. Repair or replacement versus initial cost of collapsed bridges. ........ 44

Figure 4.2. Design aids for determining the maximum positive and negative stress

increase caused by deferential settlement of the abutment (source:

FHWA/RD-85/10). .......................................................................... 46

Figure 4.3. Design aids for determining the maximum positive and negative stress

increase caused by deferential settlement of the first interior support

(source: FHWA/RD-85/10). ............................................................ 47

Figure 4.4 Initial cost versus repair or replacement cost of bridges for three levels

of damage and cost of bridge replacement. ..................................... 49

Figure 5.1 Elevation view of pile groups showing assumed values. .................... 60

Figure 5.2. Probability of failure-initial cost function for pile groups.................. 62

Figure 5.3. Factor of safety distribution curves for pile groups of 3and 5 piles. .. 63

Figure 5.4. Probability of pile groups to exceed service limit A (about 3 inches or

a distortion of 0.0021). ..................................................................... 66

Figure 5.5. Probability of pile groups to exceed service limit B (5 inches or a

distortion of 0.004)........................................................................... 66

Page 14: TARGET LEVELS OF RELIABILITY FOR DESIGN OF BRIDGE

xii

Figure 5.6. Probability of pile groups to exceed service limit C (about 17 inches).

.......................................................................................................... 67

Figure 5.7. Distribution curves of pile groups of 4 and 9 piles displaying the

probability of exceeding service limit A. ......................................... 67

Figure 5.8. Elevation view of a drilled shaft showing assumed values. ............... 70

Figure 5.9. Probability of failure-cost function for drilled shafts. ........................ 72

Figure 5.10. Factor of safety distribution curves for 3 and 5 ft diameter drilled

shafts. ............................................................................................... 73

Figure 5.11. Probability of drilled shafts to exceed service limit A (about 3

inches). ............................................................................................. 76

Figure 5.12. Probability of drilled shafts to exceed service limit B (about 5

inches). ............................................................................................. 76

Figure 5.13. Probability of drilled shafts to exceed service limit C (about 17

inches). ............................................................................................. 77

Figure 5.14. Distribution curves of drilled shafts of 3 and 5 feet in diameter

displaying the probability of exceeding service limit A. ................. 77

Figure 5.15. Elevation view of a spread footing showing assumed values. ......... 80

Figure 5.16. Probability of failure-cost function for spread footings. .................. 82

Figure 5.17 Factor of safety distribution curves for spread footings of 25 and 49

ft2 under 4000 kip of load. ............................................................... 83

Figure 5.18 Probability of spread footings to exceed service limit A (about 3

inches). ............................................................................................. 86

Page 15: TARGET LEVELS OF RELIABILITY FOR DESIGN OF BRIDGE

xiii

Figure 5.19 Probability of spread footings to exceed service limit B (about 5

inches). ............................................................................................. 86

Figure 5.20 Probability of spread footings to exceed service limit C (about 17

inches). ............................................................................................. 87

Figure 5.21 Distribution curves of spread footings of 25 and 49 ft2 displaying the

probability of exceeding service limit A. ......................................... 87

Figure 5.22. Elevation view of an embankment showing assumed values. .......... 90

Figure 5.23 Probability of failure-cost function for embankments....................... 92

Figure 5.24 Factor of safety distribution curves for embankments. Geofoam

heights of 20 & 24 ft. ....................................................................... 93

Figure 5.25 Accumulated vertical movement (MH, CH soils) 4 year monitoring

period (Vicente et al., 1994). ........................................................... 94

Figure 5.26 Probability of embankments to exceed service limit A (about 3

inches). ............................................................................................. 97

Figure 5.27 Probability of spread footings to exceed service limit B (about 5

inches). ............................................................................................. 97

Figure 5.28 Probability of embankments to exceed service limit C (about 17

inches). ............................................................................................. 98

Figure 5.29 Settlement distribution curves for embankments displaying the

probability of 30 and 31 ft of geofoam fill to exceed service limit A.

.......................................................................................................... 98

Figure 5.30 The cost to reduce the probability of failure of pile groups decreases

to 50 percent when reducing the cost of pile in 50 percent. .......... 100

Page 16: TARGET LEVELS OF RELIABILITY FOR DESIGN OF BRIDGE

xiv

Figure 5.31 Sensitivity of the probability of failure-cost function for pile group

strength limit state when varying the load from 4000 kips (top) to

3000 and 2000 kips (bottom). ........................................................ 100

Figure 5.32 A increase in mean and spread of the pile group factor of safety

distribution (compare Figure 5.3) when decreasing load from 4000

kips to 3000 kips. ........................................................................... 102

Figure 5.33 Sensitivity of the probability of failure-cost function for pile group

strength limit state when varying the c.o.v. of the load from 0.12

(top) to 0.06 (bottom). .................................................................... 103

Figure 5.34 Decrease in mean and spread of the pile group factor of safety

distribution (compare Figure 5.3) when decreasing the c.o.v. of the

load from 0.12 to 0.06. ................................................................... 104

Figure 5.35 Decrease in slope of drilled shaft probability of strength failure

function when reducing the cost by 50 percent (bottom). ............. 106

Figure 5.36 Change in the probability of failure-cost function for drilled shafts

strength limit state when varying the load from 4000 kips (top) to

3000 and 2000 kips (bottom). ........................................................ 106

Figure 5.37 Increase in mean and spread of the drilled shaft factor of safety

distribution (compare Figure 5.10) when decreasing load from 4000

kips to 3000 kips. ........................................................................... 107

Figure 5.38 Sensitivity of the probability of failure-cost function for drilled shafts

strength limit state when varying the c.o.v. of the load from 0.12

(top) to 0.06 (bottom). .................................................................... 109

Page 17: TARGET LEVELS OF RELIABILITY FOR DESIGN OF BRIDGE

xv

Figure 5.39 Change in the probability of failure-cost function due to change in

load coefficient of variation when load is reduces from 4000 kips to

1000 kips. ....................................................................................... 109

Figure 5.40 Increase in spread of the drilled shafts factor of safety distribution

(compare Figure 5.10) when decreasing load c.o.v. from 0.12 to

0.06................................................................................................. 110

Figure 5.41 Decrease in slope of the spread footing probability of strength failure

function when reducing the cost to 50 percent (bottom). .............. 111

Figure 5.42 Change in the probability of failure-cost function for spread footing

strength limit state when varying the load from 4000 kips (top) to

3000 and 2000 kips (bottom). ........................................................ 112

Figure 5.43 Decrease in mean and spread of the spread footing factor of safety

distribution (compare Figure 5.17) when decreasing load from 4000

kips to 3000 kips. ........................................................................... 113

Figure 5.44 Probability of failure-cost function for spread footing strength limit

when varying the load (4000 to 2000 kips) c.o.v. of the load from

0.12 (top) to 0.06 (bottom). ............................................................ 114

Figure 5.45 Decrease in mean and spread of the spread footing factor of safety

distribution (compare Figure 5.17) when decreasing load c.o.v. from

0.12 to 0.06 .................................................................................... 114

Figure 5.46 Decrease in slope of the embankment probability of strength failure

function when reducing the cost by 50 percent (bottom) .............. 116

Page 18: TARGET LEVELS OF RELIABILITY FOR DESIGN OF BRIDGE

xvi

Figure 5.47 Change in the probability of failure-cost function for spread footing

strength limit state when varying the load from 4000 psf (left) to

2000 psf (right). ............................................................................. 116

Figure 5.48 Decrease in mean and spread of the embankment factor of safety

distribution (compare Figure 5.24) when decreasing load from 4000

kips to 3000 kips ............................................................................ 117

Figure 6.1 FN chart for pile group strength limit. ............................................... 124

Figure 6.2 FN chart for pile group service limit A. ............................................ 124

Figure 6.3 FN chart for pile group service limit B. ............................................ 125

Figure 6.4 FN chart for pile group service limit C. ............................................ 125

Figure 6.5 FN chart for drilled shaft strength limit state. ................................... 127

Figure 6.6 FN chart for drilled shaft service limit A. ......................................... 127

Figure 6.7 FN chart for drilled shaft service limit B........................................... 128

Figure 6.8 FN chart for drilled shaft service limit C........................................... 128

Figure 6.9 FN chart for spread footing strength limit state................................. 130

Figure 6.10 FN chart for spread footing service limit A..................................... 130

Figure 6.11 FN chart for spread footing service limit B. .................................... 131

Figure 6.12 FN chart for spread footing service limit C. .................................... 131

Figure 6.13 FN chart for approach embankment strength limit state. ................ 133

Figure 6.14 FN chart for approach embankment service limit A. ...................... 133

Figure 6.15 FN chart for approach embankment service limit B. ...................... 134

Figure 6.16 FN chart for approach embankment service limit C. ...................... 134

Page 19: TARGET LEVELS OF RELIABILITY FOR DESIGN OF BRIDGE

xvii

Figure 6.17 Pile group economic curve sensitivity to 50 percent change (decrease)

in cost. ............................................................................................ 137

Figure 6.18 Pile group economic curve sensitivity to 50 percent change in load.

........................................................................................................ 137

Figure 6.19 Pile group economic curve sensitivity to 50 percent change in load

cov. ................................................................................................. 138

Figure 6.20 Drilled shaft economic curve sensitivity to 50 percent change

(decrease) in cost............................................................................ 139

Figure 6.21 Drilled shaft economic curve sensitivity to 50 percent change in load.

........................................................................................................ 139

Figure 6.22 Drilled shaft economic curve sensitivity to 50 percent change in load

cov. ................................................................................................. 140

Figure 6.23 Spread footing economic curve sensitivity to 50 percent change

(decrease) in cost............................................................................ 141

Figure 6.24 Spread footing economic curve sensitivity to 50 percent change in

load. ................................................................................................ 141

Figure 6.25 Spread footing economic curve sensitivity to 50 percent change in

load cov. ......................................................................................... 142

Figure 6.26 Approach embankment economic curve sensitivity to 50 percent

change (decrease) in cost. .............................................................. 143

Figure 6.27 Approach embankment economic curve sensitivity to 50 percent

change in undrained shear strength Su. .......................................... 143

Page 20: TARGET LEVELS OF RELIABILITY FOR DESIGN OF BRIDGE

xviii

Figure 6.28 Suggested foundation probabilities of failure for strength limit state.

........................................................................................................ 146

Figure 6.29 Suggested foundation probabilities of failure for service limit state A.

........................................................................................................ 146

Figure 6.30 Suggested foundation probabilities of failure for service limit state B.

........................................................................................................ 148

Figure 6.31 Suggested foundation probabilities of failure for service limit state C.

........................................................................................................ 148

Figure 6.32 Suggested embankment probabilities of failure for strength limit state.

........................................................................................................ 149

Figure 6.33 Suggested embankment probabilities of failure for service limit state

A. .................................................................................................... 150

Figure 6.34 Suggested embankment probabilities of failure for service limit state

B. .................................................................................................... 150

Figure 7.1 Regions of acceptable, “as low as reasonably possibly” (ALARP) and

unacceptable levels of risk on FN curves (after Hong Kong

Government Planning Department, 1994) ..................................... 160

Figure 7.2. FN chart: Average annual probabilities for traditional civil facilities

overlying ANCOLD and Hong Kong societal based risk limits (after:

Baecher & Christian, 2003, ANCOLD, 1994, and Hong Kong

Government Planning Department, 1994). .................................... 161

Page 21: TARGET LEVELS OF RELIABILITY FOR DESIGN OF BRIDGE

xix

Figure 7.3. Life-cycle cost curves for specific values of infrastructure

consequence of failure costs, X. Circles denote optimum probability

of failure. ........................................................................................ 162

Figure 7.4. Economic probabilities for the design of drilled shafts overlapping the

socially acceptable probabilities on an FN chart. Coefficient of

variation, c.o.v., represents different levels of uncertainty in design

parameters. ..................................................................................... 163

Figure 7.5. Suggested discrete probabilities of failure versus initial cost of a

bridge for the design of the capacity (strength limit state, LS) of

bridge foundations. ........................................................................ 167

Figure 7.6. Suggested discrete probabilities of reaching a specific service limit

state versus repair cost of the bridge for design foundations. ........ 167

Figure 7.7. Resistance factor relations for undrained shear strength for

probabilities of failure of 0.1, 0.01, 0.001, with respect to stability

analyses of slopes (Loehr et al. 2005). ........................................... 169

Figure 8.1 Example of probability of failure (risk) step function generated within

foundation economic curve envelope according to the consequence

of bridge failure.............................................................................. 175

Figure A.1 Elevation view of Bridge MoDOT A6248 (Fed ID 12126) located in

Jackson County, NB I-435 over Ramp N(71)-E, Ramp N(435)-E,

Ramp N(435)-S, and U.S. 71. It is a concrete continuous deck with

steel plate girders bridge type, with 6 spans, (120, 179, 132, 107.5,

135, 107.5) ft………………………………………...……………183

Page 22: TARGET LEVELS OF RELIABILITY FOR DESIGN OF BRIDGE

xx

Figure A.2 Elevation view of Bridge MoDOT 4824 located in McDonald County,

over Big Sugar Creek, State Road from Rte. KK to Barry CO Line

about 0.2 miles N.E. of Rte KK. It is a prestressed Concrete I-

Girders spans bridge type, with 4 spans, (82, 82, 82, 82) ft. …….183

Figure A.3 Elevation view of Bridge MoDOT 3101 (Fed ID 2664) located in

Jefferson County, Bridge Rock Creek Road Underpass, State Road

21, about 4 miles south of Route 141. It is a continuous deck

composite with steel plate girders bridge type with 2 spans, (120,

120) ft …………………………………………………………….184

Figure A.4 Elevation view of Bridge MoDOT 3390 (Fed ID 2856) located in

Clay County, Ramp 2 over Ramp 9, State Road from Rte. I-35 to

Rte. 210 at I-35 & I-435 Interchange. It is a concrete continuous

bridge type with 4 spans, (48, 60, 48, 35) ft ……………………..184

Page 23: TARGET LEVELS OF RELIABILITY FOR DESIGN OF BRIDGE

xxi

TARGET LEVELS OF RELIABILITY FOR DESIGN OF

BRIDGE FOUNDATIONS AND APPROACH EMBANKMENTS USING LRFD

Daniel R. Huaco, MSCE, EIT

Dr. J. Erik Loehr, Dissertation Supervisor

Dr. John J. Bowders, Co-Supervisor

ABSTRACT

Levels of reliability (safety) for civil engineering designs are normally established

from historical precedent, by specification committees, or based on the variability of

loads and resistances. It is common to establish a single target level of reliability for all

structures of similar type based on general consideration of costs and anticipated

performance. While establishing a single target value makes implementation

straightforward, it requires that target values be established based on broad consideration

of many structures rather than more refined consideration of individual structures. In

some cases, use of broadly established target levels of reliability can lead to excessive

costs for construction, while in other cases use of broadly established targets may lead to

poorer performance than is desired.

The research reported herein proposes an approach to establish target levels of

reliability from combined consideration of socially acceptable risk and economic

optimization. Socially acceptable risk is generally represented through FN curves, which

Page 24: TARGET LEVELS OF RELIABILITY FOR DESIGN OF BRIDGE

xxii

describe socially acceptable relations between frequency of failure (F) and number of

lives lost (N), or some other undesired consequence. Economic optimization involves

minimization of total infrastructure cost through evaluation of the potential costs of

failure or unacceptable performance and the required investment to reduce the likelihood

of unacceptable performance. Total cost (life cycle cost) is expressed as a function of the

probability of failure using the concept of the expected monetary value. The economic

optimization analysis includes mathematical minimization of a total cost function and, in

the present work, probabilistic analysis of the likelihood of unacceptable performance for

bridge foundations and approach embankments.

Cost functions were developed using reliability analyses and estimated or

historical costs for pile groups, drilled shafts, spread footings and bridge approach

embankments for different consequence levels. The minimum values from these

functions were used to establish optimum probabilities of failure that minimize expected

total cost as a function of consequences. These economically optimized probabilities of

failure were plotted on FN charts and compared and evaluated with respect to socially

acceptable risk boundaries. Recommended target levels of reliability were established

from these comparisons using engineering judgment.

Page 25: TARGET LEVELS OF RELIABILITY FOR DESIGN OF BRIDGE

1

1 INTRODUCTION

1.1 Background

Historically, engineers have compensated for variability and uncertainty in bridge

foundation design using experience and subjective judgment. New approaches are

evolving to better quantify the uncertainties involved in design and achieve rational

engineering designs with more consistent levels of reliability. Load and Resistance

Factor Design (LRFD) is one such approach.

Geotechnical engineers have traditionally used the Allowable Stress Design

(ASD) method that collectively accounts for uncertainties in all design loads and

resistances in a single factor of safety. In ASD, load combinations are treated without

explicitly considering the probability of having a higher-than-expected load and a lower-

than-expected strength occurring at the same time and place (Kulicki et al., 2007). In

contrast, LRFD allows designers to independently account for variability and uncertainty

in different loads and resistances by applying different load or resistance factors for each

parameter. The load and resistance factors can be calibrated probabilistically, thereby

allowing designers to achieve more uniform and consistent levels of reliability in super

structure and substructure designs.

Currently there is interest in comprehensive study of appropriate levels of safety

(reliability) for civil engineering designs. Target levels of reliability, which can also be

expressed as the probability of failure, for LRFD are established by an AASHTO

specification committee (Chang, 2006) or are chosen as a function of the variability of

Page 26: TARGET LEVELS OF RELIABILITY FOR DESIGN OF BRIDGE

2

loads and resistances (KDOT, 1998). In the AASHTO LRFD Bridge Design

specifications (AASHTO, 2004), the design probability of failure for bridge foundations

is established as approximately 1 in 10,000 (0.0001). More commonly, the design target

is defined in terms of a “reliability index” (β) that is related to the probability of failure.

For a probability of failure of 0.0001, β equals 3.57 if loads and resistances are assumed

to follow lognormal distributions, and 3.72 if they follow normal distributions.

The research reported herein considers an alternative approach to establish target

levels of reliability based on consideration of socially acceptable risk and economic

optimization. Socially acceptable risk is generally represented through FN curves, which

describe socially acceptable relations between frequency of failure (F) and number of

lives lost (N), or some other undesired consequence. Economic optimization involves

minimization of total infrastructure cost through evaluation of the potential costs of

failure or unacceptable performance and the required investment to reduce the likelihood

of unacceptable performance. The total cost (life cycle cost) for a structure or structural

component is expressed as a function based on the concept of the expected monetary

value. The economic optimization analysis includes the mathematical minimization of

the total cost function and, in the present work, economic analyses considering the

likelihood of failure of bridge foundations and approach embankments.

1.2 Hypothesis and Objective

The hypothesis underlying this research is that target levels of reliability (or levels

of safety) for design of geotechnical infrastructure using LRFD can be established

Page 27: TARGET LEVELS OF RELIABILITY FOR DESIGN OF BRIDGE

3

through combined consideration of economically optimized life cycle costs and societal

tolerance to risk.

The objective of this study is to establish target levels of reliability for bridge

foundations and approach embankments through completion of the following tasks:

1. Document published tolerable limits for socially acceptable levels of risk.

2. Determine the optimum levels of reliability based on minimization of a life

cycle cost function and economic analyses considering the likelihood of

failure for geotechnical infrastructure.

3. Compare optimal levels of reliability established from economic

considerations with socially acceptable levels of risk and make

recommendations for target levels of reliability to be used for design of

geotechnical infrastructure.

1.3 Scope of the Work

The scope of work to evaluate the hypothesis and meet the objectives includes:

Compile and synthesize relevant literature on current levels of safety as well

as information related to societal tolerance for risk.

Establish mathematical functions to quantify life cycle costs for bridge

foundations and approach embankments as a function of the probability of

failure used for design. Required inputs to these functions are derived from

costs for repair/replacement and costs for construction of bridge foundations

and approach embankments designed for different probabilities of failure.

Page 28: TARGET LEVELS OF RELIABILITY FOR DESIGN OF BRIDGE

4

Obtain historical and/or estimated costs for repair and replacement of bridges

subject to different levels of performance in the State of Missouri to establish

required inputs for the economic optimization.

Develop functions relating construction costs for driven piles, drilled shafts,

spread footings, and approach embankments to the probabilities of failure

used for design of these foundations, also used to develop inputs for the

economic optimization analyses.

Perform economic optimization analyses using costs for construction and

repair/replacement to identify economically optimized probabilities of failure

for driven piles, drilled shafts, spread footings and approach embankments.

Compare the optimized probabilities of failure derived from the economic

analyses with probabilities of failure established from societally acceptable

risk and, using engineering judgment, propose target levels of reliability for

design of bridge foundations and approach embankments.

Develop recommendations for use of the proposed target levels of reliability.

1.4 Organization of Dissertation

This dissertation is organized into eight chapters including this introduction. The

literature review in Chapter 2 summarizes important risk concepts, defines relevant

terms, summarizes existing studies and guidelines developed to control and regulate risk

for different types of infrastructure, and describes current practices to establish target

probabilities of failure. The strategy developed to establish target levels of reliability is

Page 29: TARGET LEVELS OF RELIABILITY FOR DESIGN OF BRIDGE

5

described in Chapter 3. Equations used to represent total costs and to establish the

optimum probabilities of failure are also presented in Chapter 3. Data collected to

establish a relation between initial cost and repair/replacement costs for bridges is

presented in Chapter 4. Analyses performed to establish relations between the

probability of failure and construction costs to decrease the probability of failure for

driven piles, drilled shafts, spread footings, and bridge approach embankments are

described in Chapter 5. In addition, analyses performed to evaluate the sensitivity of the

relations to various inputs are also presented. Results of the economic optimization

analyses are presented in the form of curves that identify the economically optimized

probability of failure as a function of consequence costs on FN charts in Chapter 6.

These curves are compared with societally acceptable probabilities of failure to establish

the recommended probabilities of failure for design of bridge foundation and approach

embankments. Considerations for use of the recommended target probabilities of failure

are presented in Chapter 7. Finally, Chapter 8 includes a summary of the dissertation,

along with conclusions and recommendations for expanding this work.

Page 30: TARGET LEVELS OF RELIABILITY FOR DESIGN OF BRIDGE

6

2 LITERATURE REVIEW

2.1 Introduction

There is limited information in the literature regarding acceptable levels of risk

and/or target values for the probability of failure for design of geotechnical infrastructure.

The limited information that is available is mostly derived from other disciplines and

applications.

The information included in this chapter was compiled to develop the analysis

strategy and concepts that were used throughout the research. Section 2.2 includes

information and definitions for several terms such as risk, societal tolerability for risk, the

concept of willingness to pay to reduce risk, and the value of life. Section 2.3 is focused

on studies and guidelines developed by agencies around the world to control and mitigate

risk. Section 2.4 summarizes current target probabilities of failure used for design of

bridge foundations.

2.2 Definitions and Concepts

2.2.1 Risk

Several definitions of risk can be found in the literature. The World English

dictionary defines risk as the possibility of suffering harm or loss. From a quantitative

perspective, the insurance industry quantifies risk as the monetary value of insured

casualty (Baecher and Christian, 2003); from this perspective, risk is taken to be a

Page 31: TARGET LEVELS OF RELIABILITY FOR DESIGN OF BRIDGE

7

function of potential consequences expressed as a monetary value. In the public health

profession, risk is commonly defined as the probability or the fraction of people that

become ill due to some pathogen exposure (disease); in this instance, risk is taken to be a

function of the probability or likelihood of illness. Thus, risk can have different

meanings in different disciplines.

Baecher and Christian (2003) state that risk is derived from a combination of the

likelihood an uncertain event and adverse consequences associated with that event. In

engineering contexts, risk is commonly defined quantitatively as the product of

probability and consequence and is expressed as:

Risk = probability consequence 2.1

An extension of this definition when more than one event may lead to an adverse

outcome is to consider risk being defined as:

n

i

iicpRisk1

2.2

where n is the number of independent and mutually exclusive event scenarios i, pi is the

probability of occurrence (per year) of scenario i, and ci is the consequence associated

with scenario i (Diamantidis et al., 2006). When dealing with physical losses, risk can be

quantified as the product of the cost of an element at risk and the probability of

occurrence of the event with a given magnitude/intensity (Van Western et al., 2005).

Accepting the engineering definition of risk to be the product of two quantitative

factors (probability and consequence), it is intuitive that risk is a quantitative expression.

However, according to the Australian Geomechanics Society (AGS, 2000), a more

Page 32: TARGET LEVELS OF RELIABILITY FOR DESIGN OF BRIDGE

8

general interpretation of risk involves a comparison of the probability and consequences

in a non-product form, therefore risk can also be considered a qualitative expression.

In general, the word “risk” is defined and quantified in various ways depending

on the practice. This research will adopt the definition of risk as the annual likelihood of

an adverse outcome (failure) multiplied by the costs associated with the failure or limit

state event. In this form, risk takes the units of cost and is generally expressed as a dollar

amount.

2.2.2 Acceptable and Tolerable Levels of Risk

It is important to distinguish between acceptable levels of risk that society desires

to achieve, and tolerable risks that they will live with, even though they would prefer

lower risks (AGS, 2000). Risk criteria generally do not have absolute boundaries.

Society shows a wide range of tolerance to risk and quantitative risk criteria are only a

mathematical expression of general societal opinion (AGS, 2000). Tolerable levels of

risk also vary from country to country, and even within countries, depending on historic

exposure. Every individual also has their own perception of acceptable risk (Diamantidis

et al., 2006).

In the United States, levels of acceptable or unacceptable risks are often

established by regulatory agencies such as the Environmental Protection Agency and the

Nuclear Regulatory Commission. However, Baecher and Christian (2003) note that “in

the United States, the government acting through Congress has not defined acceptable

levels of risk for civil infrastructure, or for most regulated activities”. Some insight into

tolerable risks can be derived from looking at statistical occurrence of deaths from

Page 33: TARGET LEVELS OF RELIABILITY FOR DESIGN OF BRIDGE

9

different causes and presuming that these rates are considered acceptable. Tables 2.1 and

2.2 show the average risk of death to individuals and society, respectively, from various

natural and human-caused events. More specifically in the area of geotechnical

engineering, the Australian Geomechanics Society has recommended the tolerable risks

for loss of life due to failure of earth slopes shown in Table 2.3 (AGS, 2000).

Table 2.1 Average risk of death to an individual (US Nuclear Regulatory Commission

1975, taken from by Baecher and Christian, 2003)

Table 2.2 Risk of death to society (US Nuclear Regulatory Commission 1975, taken from

Baecher and Christian, 2003)

Probability of 100 Probability of 1000

or more fatalities or more

Human-Caused

Airplane Crash 1 in 2 yrs. 1 in 2,000 yrs.

Fire 1 in 7 yrs. 1 in 200 yrs.

Explosion 1 in 16 yrs. 1 in 120 yrs.

Toxic Gas 1 in 100 yrs. 1 in 1,000 yrs.

Natural

Tornado 1 in 5 yrs. very small

Hurricane 1 in 5 yrs. 1 in 25 yrs.

Earthquake 1 in 20 yrs. 1 in 50 yrs.

Meteorite Impact 1 in 100,000 yrs. 1 in 1 million yrs.

Type of event

Individual chance

per year

Motor Vehicle 55,791 1 in 4,000

Falls 17,827 1 in 10,000

Fires and Hot Substances 7,451 1 in 25,000

Drowning 6,181 1 in 30,000

Firearms 2,309 1 in 100,000

Air Travel 1,778 1 in 100,000

Falling Objects 1,271 1 in 160,000

Electrocution 1,148 1 in 160,000

Lightning 160 1 in 2,500,000

Tornadoes 91 1 in 2,500,000

Hurricans 93 1 in 2,500,000

All Accidents 111,992 1 in 1,600

Accident type Total number

Page 34: TARGET LEVELS OF RELIABILITY FOR DESIGN OF BRIDGE

10

Table 2.3 Suggested tolerable risks for loss of life due to slope failure (AGS, 2000)

Societal acceptance of risk is influenced by whether the risk is considered

voluntary or involuntary. Heroic acts, participation in sports, and driving a car are

examples of voluntary risks while being exposed to diseases or pollutants are generally

considered involuntary risks. According to Stern et al. (1996), just being alive in the

United States or Europe carries a probability of dying of about 1.5 x 10-6

per hour. Some

risk analysts consider this number, about 10-6

, as a baseline to which other risks might be

compared. In the case of voluntary risk, an individual decides whether or not to accept a

risk. This decision is based on a subjective balance between risk and benefits. In 1969,

Starr (Starr, 1969) stated four conclusions regarding acceptable risk: (1) the public is

willing to accept “voluntary” risks roughly 1000 times greater than “involuntary” risks;

(2) the statistical risk of death from disease appears to be the psychological yardstick for

establishing the level of acceptability of other risks; (3) the acceptability of risk appears

to be proportional to the third power of the benefits; and (4) societal acceptance of risk is

influenced by public awareness of the benefits of an activity, as determined by

advertising, usefulness, and number of people participating.

Societal acceptance or tolerability to risk is also influenced by the costs associated

with reducing the risk. In most cases, decreasing risk requires investment or additional

Situation Suggested Tolerable Risk for Loss of Life.

Existing slopes 10-4

person most at risk

10-5

average of persons at risk

New Slopes 10-5

person most at risk

10-6

average of persons at risk

Page 35: TARGET LEVELS OF RELIABILITY FOR DESIGN OF BRIDGE

11

costs in order to make something more reliable or to guard against potential

consequences. Society has been found to tolerate higher levels of risk in situations where

it is quite costly to decrease risk.

2.2.3 The Value of Life

The value of human life is an important economic consideration that is

quantitatively calculated for purposes that include economics, health care, adoption,

political economy, insurance, worker safety, environmental impact, etc. The correct

numerical value for a life, typically called the “value of a statistical life” (VSL), is

understandably a matter of great controversy (Viscusi, 2005). Some people feel that it is

not possible to put an economic price tag on a human life because it is "priceless". Other

people consider that computing the value of life is an immoral academic exercise.

However, according to Viscusi (2003), these computations are not meant to measure what

should be paid for somebody to forfeit his life, but rather to measure how that person

values risk-reducing or risk-increasing activities.

According to Viscusi (2000), over the past decades, numerous studies have tried

to measure the VSL. Data has come from the labor market, the housing market, and

automobile purchases. In 2003, Viscusi estimated that the VSL in the United States ran

between $3 million and $9 million. Similar valuations held for other developed countries

like Japan and Australia (Table 2.4).

Page 36: TARGET LEVELS OF RELIABILITY FOR DESIGN OF BRIDGE

12

Table 2.4 Value of Statistical Life based on 2000 US dollars (Viscusi, 2003)

In the United States, the most recent evaluation made in July of 2008 by the

Environmental Protection Agency (EPA), estimates the VSL as $6.9 million in 2008

dollars. This value is a drop of nearly $1 million from 2003 (Figure 2.1). The value

estimated by the EPA is not based on people’s earning capacity but instead by what

people are willing-to-pay (WTP) to avoid certain risks and how much employers pay

their workers to take additional risks. As a hypothetical example, if a person is willing to

pay $50,000 dollars to decrease by one percent (1/100) the probability of being killed in

an accident then the value of his life is 100 times $50,000 or $5 million.

Figure 2.1 Value of Life in the United States (EPA, 2008)

Study/Country Value of Statistical Life ($millions)

Median value from 30 US studies 7.0

Australia 4.2

Austria 3.9 - 6.5

Canada 3.9 - 4.7

Hong Kong 1.7

India 1.2 - 1.5

Japan 9.7

South Korea 0.8

Switzerland 6.3 - 8.6

Taiwan 0.2 - 0.9

United Kingdom 4.2

Page 37: TARGET LEVELS OF RELIABILITY FOR DESIGN OF BRIDGE

13

In January of 1993, the United States Department of Transportation adopted a

guidance memorandum, "Treatment of Value of Life and Injuries in Preparing Economic

Evaluations (McCormick, et al., 1993)," which set forth recommended economic values

to be used in Departmental regulatory and investment analyses. The guidance raises the

value of a statistical life to $5.8 million for use by the Department of Transportation

when assessing the benefit of preventing fatalities.

2.2.4 Willingness to Pay

In economics, the willingness to pay is the amount a person is willing to pay, in

order to receive a good or to avoid something undesired. According to Kenkel (2003),

individuals’ willingness to pay (WTP) for a given reduction in mortality risks probably

differs depending upon the cause of death. People may be willing to pay substantially

more to reduce risks where there is a lengthy period of morbidity preceding death, both

because of the value of morbidity avoided and the psychological costs of imminent death.

Limited evidence suggests that WTP to reduce mortality risks varies over the life cycle of

working age adults. A theoretical analysis of the relationship between the VSL and age

showed an inverted U-shape, with a peak around the age of 40 years, dropping to about

50 to 70 percent of the peak by the age of 60 (Kenkel, 2003).

2.3 FN Charts

FN charts are a graphical presentation of information about the frequency of fatal

accidents in a system and the distribution of the numbers of fatalities in such accidents.

FN plots are charts of the frequency F of accidents with N or more fatalities, where N

Page 38: TARGET LEVELS OF RELIABILITY FOR DESIGN OF BRIDGE

14

ranges upward from one (1.0) to the maximum possible number of fatalities in the

system. Values of F for high values of N are often of particular political interest, because

these are the frequencies for high-fatality accidents. Because the values of both F and N

sometimes range across several orders of magnitude, FN graphs are usually drawn with

logarithmic scales (Evans, 2003).

Curves on FN charts can be used to define regions or levels of risks that are

generally dependent on societal acceptability for the loss of life. FN charts assist

analyzing the practicability, from an operational or financial perspective, of taking

measures to reduce the level of risk where measures are available.

The establishment of acceptable levels of risk for bridge foundations and

embankments requires the investigation of FN charts. Studies and guidelines developed

by agencies around the world to control and mitigate risk using FN charts are presented

in the following sections.

2.3.1 Hong Kong Government Planning Department (1994).

The Hong Kong Planning Standards and Guidelines (Hong Kong Government’s

Planning Department, 1994) is a document produced by the Hong Kong Government’s

Planning Department to be used for Potentially Hazardous Installations (PHI) that store

hazardous materials in quantities equal or greater than a specific threshold. According to

the document, all explosive factories and governmental explosive depots are classified as

PHIs. The threshold quantities suggested in the document follow the specifications used

in the UK’s Notification of Installations Handling Substance Regulations (Health and

Safety, 1982). The Hong Kong Government’s policy is to control the potential risks

Page 39: TARGET LEVELS OF RELIABILITY FOR DESIGN OF BRIDGE

15

associated with a PHI to meet internationally acceptable levels. Controlling the potential

risks is generally accomplished by controlling the site and land-use in the vicinity of the

PHI, and by requiring that the installation be constructed and operated to specific

standards.

In December of 1986, the Coordinating Committee on Land-use Planning and

Control relating to Potentially Hazardous Installations (CCPHI) was established to

coordinate government actions in relation to PHIs in Hong Kong. A set of Risk

Guidelines was adopted by CCPHI to assess the off-site risk levels of PHIs. These

guidelines are expressed in terms of individual and societal risks. The individual risk is

defined as the predicted increase in the chance of death per year of an individual that

lives or works near a PHI. The individual risk decreases with distance from the PHI. The

estimated duration of exposure of a person to the PHI is taken into account. The CCPHI

individual Risk Guidelines requires that the maximum level of off-site individual risk

associated with PHIs should not exceed 1 in 100,000 per year, i.e. 1 x 10-5

/year. As a

reference, the Hong Kong Planning Department considers the average annual risk of

dying in a traffic accident is about 1 in 100,000 (10-5

/year).

According to the Risk Guidelines, societal risk expresses the risks to a whole

population living near a PHI. The societal Risk Guidelines is expressed in an FN chart

(Figure 2.2). The accepted societal risk is established from the frequency and number of

deaths of potential incidents at a PHI. In order to avoid major disasters resulting in more

than 1000 deaths, the FN chart includes a vertical cut-off line at the 1000 fatality level

extending down to a frequency of 1 in a billion years.

Page 40: TARGET LEVELS OF RELIABILITY FOR DESIGN OF BRIDGE

16

Figure 2.2 Societal risk guidelines FN chart of acceptable levels of risk for the whole

population living near a potentially hazardous installation (Hong Kong Government

Planning Department, 1994).

2.3.2 External Safety Policy in the Netherlands (1987).

An Approach to Risk Management (Versteeg, 1987) is a document that describes

the use of risk management by the Dutch government in their external safety policy. Few

risk quantification studies and models existed at the time of the policy’s inception apart

from Probabilistic Risk Assessments (PRA) in nuclear industries. The document

addresses aspects such as: risk identification, risk quantification, risk assessment, risk

reduction and risk control. According to the document, it is necessary to quantify risk as

Page 41: TARGET LEVELS OF RELIABILITY FOR DESIGN OF BRIDGE

17

accurately and as scientifically as possible and to compare the results with quantitative

standards to make policy decisions as objective as possible.

Three areas of risk were distinguished: the normal risk level, where permissible

activities lie; excessive risk levels, where risks are unacceptable; and an intermediate

range of risk, where reduction of risk is desirable. This concept is applied to protect

individuals from death and prevents disasters that could affect large populations.

Individual risk is defined as the expected frequency with which a hypothetical person

permanently located at a given distance from the hazardous source would be killed.

Group risk is defined as the probability that a single accident may cause more than a

specified number of prompt fatalities. Mortality per year from natural causes is used as

the evaluation criterion to determine the limit of unacceptability for individual risk. The

lowest magnitude is 10-4

per year for children between 10 and 15 years old. The policy

adopted is that an industrial activity should not increase this background mortality risk by

more than 1 percent. The upper bound of acceptable individual risk is 1 in 1,000,000 per

year (10-6

/year). An individual risk of 1 in 100,000,000 (10-8

/year) or lower is considered

negligible.

To identify the societal impact, two Complementary Cumulative Frequency

Distribution (CCDFs) are chosen in the form of straight lines on log-log scale of the FN

graph shown in Figure 2.3. A slope of negative 2 is chosen for the CCDFs to deal with

risk aversion. Risk levels above the upper CCDF boundary, such having as 10 or more

persons killed with a frequency of 10-5

/year, is considered unacceptable. However below

the lower CCDF, the risk is considered as acceptable. This criterion is applied to persons

in the vicinity of an installation and to employees on the site.

Page 42: TARGET LEVELS OF RELIABILITY FOR DESIGN OF BRIDGE

18

Figure 2.3 Netherlands government group risk criterion (Versteeg, 1987)

2.3.3 The Australian National Committee on Large Dams (1994).

The Australian National Committee on Large Dams (ANCOLD) emphasizes the

importance of planning systematic dam safety programs. The programs cover not only

the assurance of quality in design and construction but also provide a framework for

surveillance and review of safety throughout the life of a dam. ANCOLD guidelines

present a professional body’s ‘recommendations’ rather than ‘requirements’ because

ANCOLD has no authority to promulgate ‘requirements.’ However, ANCOLD

guidelines serve as a de facto standard and they have also been formally adopted by dam

safety regulators, in some cases with some modification. Also, some Australian dam

owners have made meeting ANCOLD guidelines a corporate commitment, which surely

must have some legal implications in itself if they do not meet their own clearly stated

Page 43: TARGET LEVELS OF RELIABILITY FOR DESIGN OF BRIDGE

19

commitments (Marsden, et al. 2007). The quantitative FN curves developed by

ANCOLD are shown in Figure 2.4.

Figure 2.4 Risk guideline from ANCOLD (1994)

The ANCOLD guidelines on risk assessment drew heavily on the tolerability of

risk framework developed by the Health and Safety Executive (HSE) for the United

Kingdom (HSE, 2001), thereby introducing the public safety policy principles recognized

in other industries to the Australian dam safety scene. The importance of ANCOLD

guidelines is that it provides a greater level of guidance than the majority of other

guidelines. The concept of tolerability adopted by ANCOLD is essentially international,

also being applied in 1993 by the United States Bureau of Reclamation (USBR) and is

strongly influenced by the HSE and endorsed by the UK Treasury (HM Treasury, 1996).

Page 44: TARGET LEVELS OF RELIABILITY FOR DESIGN OF BRIDGE

20

The ANCOLD guidelines propose limits of tolerability for both individual and

societal risk. Once risks are reduced to the limit of tolerability, the ALARP (as low as

reasonable practicable) principle is addressed. ALARP is met by comparing benefits and

costs (or cost-effectiveness assessment) to establish whether additional reductions in the

probability of failure will be worthwhile. The benefit-cost criteria for ALARP involve

more than “benefits exceeding costs”. The ALARP principle is applied in a weighted or

leveraged form, by inserting “factors of disproportionality” into the benefit-cost analysis

to skew the outcome in favor of safety, in order to afford the dam owner a measure of

protection against tort liability (Marsden et al., 2007).

2.3.4 Risk Assessment of Nambe Falls Dam (1996).

The risk assessment of Nambe Falls Dam is an investigation conducted under the

US Bureau of Reclamation (USBR) to modify the Nambe Falls Dam (New Mexico). The

investigation included a seismological evaluation, a hydraulic investigation for flood

levels and a geotechnical investigation to evaluate the foundation of the dam. A

comprehensive and quantitative risk assessment was considered to estimate the

probability of failure of the Nambe Falls Dam for several loading conditions. Risk

assessment for the dam safety evaluation required identification of all loadings in the

dam, potential failure modes as a result of those loads, and the consequence of failure.

Probabilistic estimates of the loadings, of failure given by the loadings, and of the

consequences of failure were used to quantify the risk assessment. Safety criteria

involved a comparison of the product of the probabilistic estimates. Thus, quantitative

Page 45: TARGET LEVELS OF RELIABILITY FOR DESIGN OF BRIDGE

21

risk assessment required (1) identification of the risk and (2) determination of the

acceptability of that risk.

The USBR defines hazard for dams as the “potential for adverse consequence”.

The three levels of hazard (low, significant and high), were developed using a “risk

averse” approach (the greater the consequence, the less risk is accepted and the higher the

safety standards). The FN chart shown in Figure 2.5 was used by the US Bureau of

Reclamation for Nambe Falls Dam to compare risks faced by the existing dam with the

ANCOLD limits.

Figure 2.5 FN chart used by the US Bureau of Reclamation on Nambe Falls Dam, New

Mexico to compare risks of the existing dam with ANCOLD limits (Von Thun, 1996).

Page 46: TARGET LEVELS OF RELIABILITY FOR DESIGN OF BRIDGE

22

2.3.5 Historical Performance of Civil Infrastructure

An alternative means to establish acceptable levels of the probability of failure is

to collect and analyze the historical occurrence of specific events or the historical

performance of specific industries. Baecher (1982) investigated the historical

performance of different forms of civil infrastructure for this purpose. Figure 2.6 shows a

graphic in the form of an FN chart that shows the historical performance of mine pit

slopes, foundations, dams, and refineries, among others. If the observed historical

performance is presumed to be “acceptable”, then this performance can be used as a

general guide to establish accepted values for the annual probability of failure for

construction and operation of a variety of traditional civil facilities and other large

structures or projects. Two such boundaries were proposed by Baecher (1982): one

corresponding to “marginally accepted” levels and one corresponding to “accepted”

levels of reliability. These results are widely cited in the literature on geotechnical

reliability analyses. The results are therefore used subsequently in this document as a

reference for values that will be proposed for the target reliability.

Page 47: TARGET LEVELS OF RELIABILITY FOR DESIGN OF BRIDGE

23

Figure 2.6. Relationship between annual probability of failure (F) and lives lost (N)

(expressed in terms of $ lost and lives lost) for common civil facilities (Baecher and

Christian, 2003).

In FN charts, the slope of the lines dividing regions of acceptability expresses a

policy decision between the relative acceptability of low probability/high consequence

events and high probability/low consequence events. Steeper boundary lines reflect

greater concern for high consequence events and relatively less concern for low

consequence events while flatter boundary lines reflect more balanced concern for both

low and high consequence events. Note that the boundary line in the Hong Kong

guidelines (Figure 2.2) has an absolute upper bound of 1000 fatalities, no matter how low

the corresponding probability (Baecher and Christian, 2003).

Page 48: TARGET LEVELS OF RELIABILITY FOR DESIGN OF BRIDGE

24

2.4 Current Levels of Reliability for the Design of Bridge Foundations

Information on the target levels of reliability for design of bridge foundations at

strength and service limit states is scarcely found in the literature. The AASHTO

specification committee established a probability of failure for the strength limit state of

one ten thousandth (1/10,000) in 2004 (Chang, 2006). Alternatively, the target reliability

for design is often quantified using the “reliability index” (β), which is related to the

probability of failure. For a probability of failure of one in ten thousand, β equals 3.57 if

performance is assumed to follow a lognormal distribution, and 3.72 if performance is

assumed to follow a normal distribution. Alternative values have also been proposed by

others. Meyerhof (1970) suggested that the reliability index for bridge foundations

should be between 3 and 3.6. Paikowsky et al. (2004) suggested that a target reliability

index between 2.0 and 2.5 may be appropriate for pile groups and that values as high as

3.0 may be appropriate for single piles. Based on evaluation of such historical

recommendations, Paikowsky et al recommended that a probability of failure of 1 percent

(be adopted for redundant pile groups (5 or more piles) whereas they

recommended a target probability of failure of 0.1 percent () for non-redundant pile

groups. In some instances, the level of reliability is not established as a fix value but to

vary as function of the variability of the loads and resistances. For example, according to

the Kansas Department of Transportation design manual, a β factor of 2.5 is considered

appropriate for conditions where the uncertainty is reduced (KDOT, 1998).

When considering service limit states in the design of bridge foundations, the

target reliability index is generally taken to be lower because the consequences of

Page 49: TARGET LEVELS OF RELIABILITY FOR DESIGN OF BRIDGE

25

exceeding service limit states are less than the consequences of exceeding strength limit

states. AASHTO has no published target value for service limit states. However, the

Eurocode and ISO established a target reliability index of 1.5 for service limit states.

This reliability index was evaluated by examining the relations between the service

criteria (e.g. vertical displacement) and the displacement associated with the maximum

loading capacity of the structure (Paikowsky, 2005).

2.5 Summary

The literature review is divided in three parts. In the first part, the concept of risk

was defined as the annual likelihood of an adverse outcome (failure) multiplied by the

consequence cost of the failure. This first part also includes concepts of the value of

statistical life (VSL), estimates of the VSL and concepts of the willing to pay to reduce

mortality rates.

The second part of the literature review is focused on the studies and guidelines

developed by agencies around the world to control and mitigate risk. What these agencies

have in common is that they all use FN charts to graphically visualize regions of risk

acceptance.

The third part of this chapter addresses practices to establish target levels of

probability of failure, or reliability, for the design of bridge foundations. Currently the

probability of failure is established by an ASSHTO specification committee at one ten

thousandth which is equivalent to a reliability index of .72 (normal distribution). For

service limit, the Eurocode and ISO established a target reliability index of 1.5.

Page 50: TARGET LEVELS OF RELIABILITY FOR DESIGN OF BRIDGE

26

The information found in the literature leads one to conclude that comprehensive

study of appropriate levels of safety for civil engineering designs is lacking. The research

reported herein proposes an alternative approach to establish target levels of reliability

using combined consideration of societal acceptability and economic considerations as

described in Chapter 3.

Page 51: TARGET LEVELS OF RELIABILITY FOR DESIGN OF BRIDGE

27

3 APPROACH FOR ESTABLISHING TARGET PROBABILITIES

OF FAILURE

3.1 Introduction

The hypothesis of this research is that effective and appropriate target levels of

reliability for design of geotechnical infrastructure using LRFD can be established

through combined consideration of economics and societal tolerance to risk. A

description of the approach used to develop these target values for design of bridge

foundations and earth slopes is presented in this chapter.

3.2 Study Background

Traditionally, the factor of safety (FS) for design of earth slopes and foundations

has been calculated following Allowable Stress Design (ASD) concepts. The factor of

safety calculated in ASD is intended to account for the variability and uncertainty in the

loads and resistances collectively. Although this empirical method has been used

successfully for many years, the approach suffers from lack of flexibility that makes it

practically challenging to assign consistent levels of safety (conservatism) to different

sites or different cases with different levels of variability and uncertainty.

In the past 40 years, more rational and flexible approaches for design of earth

slopes and foundations have been developed based on the use of probability theory. New

methods, including the Load and Resistance Factor Design (LRFD) method, allow for

Page 52: TARGET LEVELS OF RELIABILITY FOR DESIGN OF BRIDGE

28

more consistent consideration of variability and uncertainty in a probabilistic way. In

general, the LRFD method consists of increasing the nominal predicted load(s) and

decreasing the nominal predicted resistance(s) using “load factors” and “resistance

factors”, respectively, to separately account for uncertainties in the load and resistance.

While load and resistance factors can be established in several ways, these factors are

most appropriately established as a function of the uncertainty or variability of the design

parameters and some established target probability of failure.

For example, Loehr et al. (2005) developed relationships (curves) that relate

resistance factors to the variability and uncertainty of soil strength parameters and the

target probability of failure for design of earth slopes. An example of these relationships

is shown in Figure 3.1. In Figure 3.1, different curves are provided for different target

values of the probability of slope failure. The resistance factors were established to be

dependent on the variability and uncertainty of the soil shear strength (expressed in terms

of the coefficient of variation, COV) and a selected target probability of failure. The

objective of the research described here is to identify target probabilities of failure for

such calibrations that effectively balance economic considerations and societal

perspectives of risk.

Page 53: TARGET LEVELS OF RELIABILITY FOR DESIGN OF BRIDGE

29

Figure 3.1 Resistance factors developed for design of earth slopes (Loehr et al., 2005).

3.3 General Approach for Establishing Target Probabilities of Failure

Target probabilities of failure recommended in this document were established by

first determining the probabilities of failure that would minimize costs associated with

construction and operation of infrastructure, and then comparing these values with

probabilities of failure that are considered to be “socially acceptable” based on previous

studies presented in the literature. The recommended target probabilities of failure were

taken to be the lesser of the “economically optimized” and “socially acceptable”

probabilities of failure for a given consequence level. Thus, when the economically

optimized probability of failure is less than the socially acceptable probability of failure,

the target probability of failure is taken to be the probability of failure established from

economic considerations. Conversely, when the economically optimized probability of

0.00

0.10

0.20

0.30

0.40

0.50

0.60

0.70

0.80

0.90

1.00

0.00 0.10 0.20 0.30 0.40 0.50 0.60 0.70 0.80 0.90 1.00

Res

ista

nce

Fact

or,

(Y

cf)

Coefficient of Variation for Undrained Shear Strength, (COV)

Pf = 0.100

Pf = 0.010

Pf = 0.001

Page 54: TARGET LEVELS OF RELIABILITY FOR DESIGN OF BRIDGE

30

failure exceeds the socially acceptable probability of failure, the target probability of

failure was taken to be the socially acceptable one. Thus, the recommended probabilities

of failure always satisfy the constraint of social acceptability, but also reflect economic

optimization when such optimization leads to probabilities of failure that are less than

those considered to be “socially acceptable”.

In general, both the economically optimized and socially acceptable probabilities

of failure vary with the level of consequences. Thus, the relation between the two

probabilities of failure also varies with consequence level. Figure 3.2 shows a conceptual

comparison of economically optimized and socially acceptable probabilities of failure in

the form of an FN chart in which the consequences of failure are expressed in terms of

both number of human lives and monetary losses as explained in the literature review. In

this comparison, economically optimized probabilities of failure tend to be lower than

socially acceptable probabilities of failure for relatively low consequence levels while

socially acceptable probabilities of failure tend to be lower than economically optimized

values for greater consequence levels. Thus, in this instance, the target probabilities of

failure would be controlled by economic considerations for low consequence levels and

by socially acceptable probabilities for greater consequence levels. Considerations used

to develop the economically optimized and socially acceptable probabilities of failure are

presented in the following sections.

Page 55: TARGET LEVELS OF RELIABILITY FOR DESIGN OF BRIDGE

31

Figure 3.2 FN chart comparing socially acceptable and economically optimized values

for the probability of failure, Pf.

3.4 Economically Optimized Probabilities of Failure

For the present work, economically optimized probabilities of failure are

established to minimize the expected monetary value. In decision theory, the expected

monetary value, denoted as E, is a measure of the value or utility expected to result from

a given decision. E is taken to be equal to the sum of the initial cost of a civil work and

uncertain future costs, or “consequences”, associated with maintenance and repair. In the

case of civil works, consequences can be classified as recurring maintenance costs (e.g.

painting bridge girders, vegetation control, drainage maintenance, etc) or unexpected

1E-08

1E-07

1E-06

1E-05

1E-04

1E-03

1E-02

1E-01

1E+00

1E+4 1E+5 1E+6 1E+7 1E+8 1E+9 1E+10 1E+11 1E+12

Pro

b o

f fa

ilure

pe

r ye

ar

(Po

ptim

um

)

Failure/repair cost, dollars (X)

Foundations

Dams

Commercial

Aviation

Mine

PitSlopes

Marginally Accepted

Accepted

ANCOLD

Hong Kong

1E-08

1E-07

1E-06

1E-05

1E-04

1E-03

1E-02

1E-01

1E+00

1E+4 1E+5 1E+6 1E+7 1E+8 1E+9 1E+10 1E+11 1E+12

Pro

ba

bili

ty o

f fa

ilure

pe

r ye

ar

Failure/repair cost, dollars

Economic acceptable levels of risk

Fatalities, N10-2 10-1 100 101 102 103 104 105 106

Socially acceptable levels of risk

Page 56: TARGET LEVELS OF RELIABILITY FOR DESIGN OF BRIDGE

32

repair costs (repair of slides, repair or retrofit of bridge components due to excessive

settlement, total failure and complete replacement, etc.).

In the context of the present work, the term “consequence” is used to reflect the

costs associated with a future failure or other form of unacceptable performance (e.g.

excessive deformation, etc.). In general, consequences can also include human injuries or

other less tangible things like legal liability or political consequences such as the loss of

faith by the traveling public. In this dissertation research, all consequences are expressed

in terms of monetary values to make the evaluations convenient.

3.4.1 Mathematical Representation of Expected Monetary Value

The expected monetary value (E) of a civil work can be expressed mathematically

as

𝐸 = 𝐴 + 𝑃 ∙ 𝑋 + (1 − 𝑃) ∙ 𝑇 3.1

where,

E = expected monetary value,

A = initial cost of the civil work,

P = the probability of failure, or unacceptable performance,

X = consequence costs associated with unacceptable performance, and

T = costs associated with acceptable performance, or recurring

maintenance cost.

Since this work is focused on geotechnical infrastructure (piles, drilled shafts,

embankments, etc.) that does not typically require recurring maintenance, the cost of

Page 57: TARGET LEVELS OF RELIABILITY FOR DESIGN OF BRIDGE

33

maintenance, T, in Equation 3.1 is considered negligible. The expression for expected

monetary value can thus be simplified to become

𝐸 = 𝐴 + 𝑃 ∙ 𝑋 3.2

Equation 3.2 involves three independent variables (A, P and X), which are interrelated as

described in subsequent sections.

3.4.2 Initial Costs

The initial cost (A) and the probability of failure (P) are generally inversely

related, meaning that the initial cost increases as the probability of failure decreases. This

relation is generally intuitive. For example, it is intuitive that costs for bridge

foundations will generally increase as the size of the foundations are increased, but the

probability of poor performance (settlement or collapse) will simultaneously decrease.

Thus, there is a direct relation between initial costs and the probability of failure for

bridge foundations and other geotechnical infrastructure.

Specific functions relating the initial costs for geotechnical infrastructure and the

probability of failure are established in Chapter 5. These functions are taken to be of the

form:

𝐴 = 𝑏 ∙ 𝐿𝑛𝑃 + 𝑑 3.3

where,

A = the initial cost of the geotechnical infrastructure,

b = slope factor reflecting costs required to decrease the probability of failure,

Page 58: TARGET LEVELS OF RELIABILITY FOR DESIGN OF BRIDGE

34

P = probability of failure, and

d = vertical intercept representing the required cost to produce P = 1.0.

Values for variables b and d were established through probabilistic analyses for different

specific type of geotechnical infrastructure, as described in Chapter 5.

Substituting the expression for initial costs in Equation 3.3 into Equation 3.2

produces an expression for the expected monetary value that is a function of the

probability, P, the consequence cost, X, and two constants that describe the relation

between initial costs and the probability of failure for specific types of geotechnical

infrastructure:

𝐸 = (𝑏 ∙ 𝐿𝑛𝑃 + 𝑑) + 𝑃 ∙ 𝑋 3.4

This function represents a surface in a space in which the axes are the expected monetary

value (E), the probability (P) and the consequence (X), as shown in Figure 3.3. The

specific shape of the function in Figure 3.3 will depend on the specific coefficients (b and

d) used that, in turn, depend on costs required to reduce the probability of failure for

different types of geotechnical infrastructure (different types of foundations, slopes,

walls, etc.).

Figure 3.4 shows a plot of Equation 3.4 for different assumed values of X. For a

given consequence level, X, the expected monetary value from Equation 3.4 achieves a

minimum value at some probability of failure, P. This “optimum probability”, denoted

Popt, varies with the magnitude of the consequences, X, and tends to decrease with

increasing consequences. The relation between the optimum probability of failure and

the consequences is shown projected onto the X-P plane in Figure 3.3. This plane is

effectively an FN chart, and the projected relation between the optimum probability and

Page 59: TARGET LEVELS OF RELIABILITY FOR DESIGN OF BRIDGE

35

consequence level reflects economically optimized probabilities of failure for different

consequence levels.

Figure 3.3 Graphical representation of the relation between expected monetary value (E),

probability of failure (P) and consequence cost (X).

3.4.3 Consequence Costs

As described in the previous section, the magnitude of the consequences, X, in

Equation 3.4 influences the optimization of expected monetary value. The range of

potential consequence costs are also important because they establish appropriate ranges

over which target probabilities of failure must be established for a particular limit state.

While initial costs reflect only costs associated with the specific geotechnical

infrastructure being considered (e.g. costs for the foundations or slopes alone),

consequence costs may include costs for repair or replacement of other infrastructure

Probability of

Failure (P)

Expected monetary value (E)

Consequence cost of failure (X)

Page 60: TARGET LEVELS OF RELIABILITY FOR DESIGN OF BRIDGE

36

components that may be affected by unacceptable performance of slopes and foundations.

For example, consequence costs associated with excessive settlement of bridge

foundations will often include costs for repair of the entire bridge because excessive

settlement is likely to cause damage to the entire bridge. While consequence costs are

often site specific, it is possible to develop generalizations for different types of

geotechnical infrastructure and different limit states. Analyses performed to develop

generalized estimates for consequence costs are described in Chapter 5.

Figure 3.4 Expected monetary value curves in which the optimum probability of failure

(Popt) is shown to coincide with the minimum expected monetary value for different

values of consequence X.

3.4.4 Derivation of Optimum Probability Function and FN Curve

The optimum probability of failure has been defined as the probability of failure that

minimizes the expected monetary value. An expression for the optimum probability of

failure can therefore be derived by taking the derivative of the expected monetary value

-50,000

-25,000

0

25,000

50,000

75,000

100,000

125,000

150,000

1E-07 1E-06 1E-05 1E-04 1E-03 1E-02 1E-01 1E+00 1E+01 1E+02

Exp

ect

ed

mo

ne

tary

va

lue

-d

olla

rs

Probability of failure, P

Popt (X=1E4)

Popt (X=1E6)

Popt (X=1E7)

Popt (X=1E5)

Popt (X=1E8)

X=1E8

X=1E7

X=1E6

X=1E5

X=1E4

Page 61: TARGET LEVELS OF RELIABILITY FOR DESIGN OF BRIDGE

37

function (Equation 3.4) with respect to the probability of failure (P), and setting that

derivative to be equal to zero:

𝜕𝐸

𝜕𝑃= 𝑏 ∙ 𝑃−1 + 0 + 𝑋 = 0 3.5

Solving Equation 3.5 for the probability (P) leads to an expression for the optimum

probability of failure (Popt):

𝑃𝑜𝑝𝑡 =−𝑏

𝑋 3.6

Equation 3.6 states that the optimum probability of failure is dependent on the parameter

b, which reflects costs required to reduce the probability of failure, and the consequence

costs. Chapters 5 and 6 describe the analyses performed to establish these values for

different types of geotechnical infrastructure for the present work.

3.5 Socially Acceptable Probabilities of Failure

In Chapter 2, several studies and guidelines developed by agencies around the

world to control and mitigate risk were presented. These agencies commonly use FN

charts to graphically represent regions of acceptable probabilities of failure. The graphic

shown in Figure 3.5 illustrates historical performance associated with several different

activities or industries along with boundaries proposed to reflect acceptable probabilities

of failure based on the presumption that historical performance has been acceptable. The

chart provides general guidance on accepted values for the annual probability of failure

for construction and operation of a variety of traditional civil facilities and other large

structures or projects (Baecher, 1982).

Page 62: TARGET LEVELS OF RELIABILITY FOR DESIGN OF BRIDGE

38

Figure 3.5. Relationship between annual probability of failure (F) and lives lost (N)

(expressed in terms of $ lost and lives lost) for common civil facilities (Baecher and

Christian, 2003).

The most well-known FN boundaries were selected to identify common levels of

acceptable probabilities of failure. The FN chart in Figure 3.6 shows socially acceptable

limits for the probability of failure established by the Australian National Committee on

Large Dams (ANCOLD, 1999) and the Hong Kong Government Planning Department

(HKGPD, 1994) superimposed on observations of the performance of traditional civil

facilities from Baecher and Christian (2003) shown in Figure 3.5. The figure shows good

general agreement among what the different agencies have established as “socially

acceptable” probabilities of failure and with the observed performance of civil facilities.

Page 63: TARGET LEVELS OF RELIABILITY FOR DESIGN OF BRIDGE

39

Figure 3.6. FN chart showing average annual risks posed by a variety of traditional civil

facilities and other large structures along with several proposed boundaries reflecting

acceptable probabilities of failure.

The collection of boundaries reflecting socially acceptable probabilities of failure

shown in Figure 3.6 was used, with some judgment, to establish recommended target

probabilities of failure. This was generally accomplished by plotting curves representing

economically optimized probabilities of failure, established as described in this chapter,

on the chart shown in Figure 3.6 and then employing judgment to arrive at final

recommendations for the target probability of failure. Results of analyses performed to

1E-08

1E-07

1E-06

1E-05

1E-04

1E-03

1E-02

1E-01

1E+00

1E+4 1E+5 1E+6 1E+7 1E+8 1E+9 1E+10 1E+11 1E+12

Pro

b o

f fa

ilure

pe

r ye

ar

(Po

ptim

um

)

Failure/repair cost, dollars (X)

Foundations

Dams

Commercial

Aviation

Mine

PitSlopes

Marginally Accepted

Accepted

ANCOLD

Hong Kong

1E-08

1E-07

1E-06

1E-05

1E-04

1E-03

1E-02

1E-01

1E+00

1E+4 1E+5 1E+6 1E+7 1E+8 1E+9 1E+10 1E+11 1E+12

Pro

b o

f fa

ilure

pe

r ye

ar

(Po

ptim

um

)

Failure/repair cost, dollars (X)

Fatalities, N10-2 10-1 100 101 102 103 104 105 106

Foundations

Dams

MinePit

Slopes

Marginally Accepted

Accepted

ANCOLD

Hong Kong

CommercialAviation

Page 64: TARGET LEVELS OF RELIABILITY FOR DESIGN OF BRIDGE

40

establish the recommended target probabilities of failure, and the considerations involved

in establishing these probabilities of failure, are described in Chapter 6.

3.6 Summary

The transition from design following ASD methods to LRFD methods requires

that target levels of reliability or target probabilities of failure be established. The

approach proposed in this chapter to establish target probabilities of failure includes the

evaluation and comparison of probabilities of failure established from considerations of

social acceptability and economic optimization. Socially acceptable probabilities of

failure established by several government agencies and other sources were used to

represent social acceptability considerations. Economically optimized probabilities are

established by mathematically minimizing an expected monetary value function for

bridge foundations and earth slopes. Required inputs for the economic optimization of

expected monetary value include information regarding the consequences associated with

unacceptable performance and information regarding the costs required to reduce the

probability of failure for bridge foundations and earth slopes. Evaluations performed to

quantify this information are presented in the following chapters.

Page 65: TARGET LEVELS OF RELIABILITY FOR DESIGN OF BRIDGE

41

4 CONSEQUENCE COSTS FOR BRIDGES

4.1 Introduction

As described in the previous chapter, consequence costs are one important input

required for establishing appropriate target probabilities of failure based on economic

considerations alone. Unfortunately, consequence costs depend on factors that are often

site specific so it is difficult to establish accurate consequence costs that will be broadly

applicable for all bridges. Nevertheless, reasonable ranges for consequence costs must be

established so that the economic optimization described in Chapter 3 will be applicable

over an appropriate range of consequences. The approach adopted for this work was to

assume that consequence costs are predominantly dependent on the initial cost for a

bridge and the limit state being considered. This approach was adopted because initial

costs for bridges are frequently estimated during planning and design, and because these

estimates can be related to consequence costs if empirical relations between the initial

cost of bridges and the cost of failure or repair can be established.

Cost information was collected from the literature and from Missouri Department

of Transportation (MoDOT) personnel. This information was then used to develop

relationships between initial costs and consequence costs for bridges at four different

limit states. The limit states considered include one strength limit state that corresponds

to complete collapse of a bridge and three serviceability limit states that correspond to

different levels of damage as described in more detail in the following sections.

Page 66: TARGET LEVELS OF RELIABILITY FOR DESIGN OF BRIDGE

42

4.2 Consequence Costs for Strength Limit State

When designing bridges under the conditions of safety and serviceability, it is

required to consider two categories of limit states that are frequently referred to as service

and strength limit states. Strength limit states address the potential for complete

structural or geotechnical failure of the bridge foundation while service limit states

address the potential for loss of functionality without complete collapse. This section

addresses the methods used to develop cost relations for the strength limit state while cost

relations for service limit states are addressed in Section 4.3.

Cases where foundation failures have led to complete collapse of a bridge are

extremely rare. However, this is the specific condition being addressed when designing

foundations for strength limit states. In order to develop adequate costs associated with

failure of bridges, a literature search was conducted to identify cases where bridges had

collapsed, for any reason (not just due to foundation failure), and were subsequently

replaced. Sixteen such cases identified as part of this work are summarized in Table 4.1.

The table includes the location, construction date, and initial cost for each bridge when

this information could be established. The table also includes the date each bridge

collapsed and documented replacement costs for the respective bridges, again when this

information could be established from the literature or other sources. The present (2009)

values of both the initial and replacement costs are also provided in the table. The

present value for these costs was computed using historical inflation rates

(Inflationdata.com) over the period between initial construction or collapse and

September 2009.

Page 67: TARGET LEVELS OF RELIABILITY FOR DESIGN OF BRIDGE

43

Tab

le 4

.1. P

rese

nt

val

ue

of

init

ial

cost

s of

bri

dges

(2010)

that

hav

e co

llap

sed i

n t

he

US

and t

he

cost

of

repla

cem

ent.

PV

Co

st

$2,3

44

,017

$1,5

67

,853

$118

,278

$465

,273

$321

,435

$202

,163

Rep

lacem

en

t

Co

st

$272

M

> $

20

M

$10

M

$1,6

41

,440

$1,4

93

,729

$100

,000

$431

,000

$279

,000

$200

,000

Rep

lacem

en

t

Yea

r

2007

1987

2000

1983

2002

2007

2007

2001

2005

2007

2003

2006

2004

2008

PV

Co

st

$30

M

$481

,143

$417

,990

$65

,15

9

$158

,855

$80

,15

0

$58

,15

5

Init

ial

Co

st

$5.2

M

$77

M

$59

,25

0

$60

,50

0

$5,0

00

$10

,00

0 (

?)

$9,8

70

$6,4

40

Bid

din

g

Yea

r

1964

1954

1970

1933

1930

's

Op

en 1

974

~1

955

~1

965

~1

930

's

~1

932

1955

1950

Loca

tio

n

Min

nea

po

lis,

MN

Montg

om

ery

Coun

ty, N

Y

Mil

wau

kee

, W

I

Gre

enw

ich

, C

T

Web

ber

s F

alls

, O

K

Oak

vil

le,

WA

Oak

land

, C

A

Po

rt I

sabel

, T

X

Lac

led

e C

oun

ty, M

O

Kan

sas

Jeff

erso

n C

ity

, M

O

Way

ne

Co

unty

, M

O

Buch

anan

Cou

nty

, M

O

Gen

try

Coun

ty, M

O

Sco

tt C

oun

ty, M

O

Pro

ject

I-3

5W

Hig

hw

ay B

rid

ge

(9340

)

Sch

ohar

ie C

reek

Bri

dg

e (N

Y 1

02

0940

)

Dan

iel

Hoan

Mem

ori

al B

ridg

e

Mia

nu

s R

iver

Bri

dg

e I-

95

I-4

0 B

rid

ge

Har

p R

oad

bri

dg

e

Oak

land

Bay

Bri

dg

e (3

4+

000

3)

Mac

Art

hu

r M

aze

(I-5

80

Eas

t C

on

nec

tor)

Qu

een

Isa

bel

la C

ause

way

I-4

4 W

ater

tan

k h

it b

ridg

e L

072

3 (

now

A6

737

)

Ex

cavat

or

hit

bri

dge

A1

308

Jef

fers

on S

tree

t (A

76

31

)

T10

29

(n

ow

A70

14

)

S0

445

(no

w A

7391

)

P0

766

(no

w A

7202

)

P0

099

(no

w A

7670

)

Page 68: TARGET LEVELS OF RELIABILITY FOR DESIGN OF BRIDGE

44

Seven of the cases shown in Table 4.1 include costs for initial construction and

costs for replacement. These cases were therefore used to establish a relationship

between initial costs and replacement costs for bridges, as shown in Figure 4.1. A power

function relation was then fit through these data to serve as a mathematical function

relating the consequence costs (replacement costs) to the initial cost for collapsed

bridges.

Figure 4.1. Repair or replacement versus initial cost of collapsed bridges.

4.3 Consequence Costs for Service Limit States

Service limit states are intended to assure adequate service and performance of a

structure. In most cases, service limit states involve consideration of deflections for a

structure to ensure that excessive deflections that would render the structure unusable are

unlikely to occur. For axial design of bridge foundations at service limit states,

deflections resulting from foundation settlement are the predominant concern.

Collapse

y = 0.74x1.13

1.E+04

1.E+05

1.E+06

1.E+07

1.E+08

1.E+09

1.E+04 1.E+05 1.E+06 1.E+07 1.E+08 1.E+09

Present initial cost, dollars (H)

Bri

dg

e re

pai

r co

st, d

oll

ars

(X

)

Page 69: TARGET LEVELS OF RELIABILITY FOR DESIGN OF BRIDGE

45

In attempting to establish acceptable probabilities of failure for serviceability

limits based on economic considerations, it is important to recognize that different levels

of settlement will produce different levels of damage, which in turn will produce different

costs for repair. Thus, an acceptable probability of failure for one level of settlement (or

damage) may be completely unacceptable for another level of settlement. In order to

address this potential, three different levels of settlement/damage were considered in this

study. These three levels are referred to here as the “Service A”, “Service B”, and

“Service C” limit states.

The Service A limit was used to represent settlements that would induce minor,

predominantly cosmetic damage such as minor cracking the bridge decks. Duncan and

Tan (1991) report that such damage tends to occur when the angular distortions reach a

value of 0.0021. The value of angular distortion was therefore used to compute

settlements that are likely to induce minor damage.

The Service B limit was used to represent settlements that would produce

structural damage to a bridge. Moulton et al. (1985) found that structural damage is

likely to occur for continuous-span bridges when angular distortions exceed 0.004. This

value of angular distortion was therefore used to compute settlements that produce

structural damage for the Service B limit.

Finally, the Service C limit was used to represents settlements that are likely to

produce overstress in components that ultimately could compromise the structural

integrity of a bridge. Moulton (1985) provides the following equation that was used to

compute settlements that are likely to lead to overstress of multiple span bridge

components:

∆0𝑐

𝑓0(+) and

∆0𝑐̅

𝑓0(−)

or

∆𝛼𝑐

𝑓𝛼(+) and

∆𝛼𝑐̅

𝑓𝛼(−)

Page 70: TARGET LEVELS OF RELIABILITY FOR DESIGN OF BRIDGE

46

Where:

Δo and Δα are abutment and pier settlement respectively

c and 𝑐̅ are the distance from the neutral axis to the outer fiber

𝑓0(+) and 𝑓𝛼(+) are maximum positive settlement stresses

𝑓0(−) and 𝑓𝛼(−) are maximum negative settlement stresses

Using to Moulton's mathematical model, the levels of positive or negative stresses in the

bridge structure were obtained by entering the span length, l and the number of spans, n

in Figure 4.2 or in Figure 4.3.

Figure 4.2. Design aids for determining the maximum positive and negative stress

increase caused by deferential settlement of the abutment (source: FHWA/RD-85/10).

Page 71: TARGET LEVELS OF RELIABILITY FOR DESIGN OF BRIDGE

47

Figure 4.3. Design aids for determining the maximum positive and negative stress

increase caused by deferential settlement of the first interior support (source: FHWA/RD-

85/10).

4.4 Development of Relations between Initial Costs and Consequence Costs

Although information regarding the construction or initial costs of bridges is

available in the literature, it is difficult to obtain information regarding the costs of repair.

In order to obtain this information, a questionnaire was prepared for MoDOT, inquiring

the action to be taken and the cost to repair specific hypothetical damages due to three

selected levels of the differential settlement of the bridge abutments or piers. The three

levels of settlement were selected based on the state limits A, B and C for minor,

intermediate and sever settlements correspondently. Five continuous-span bridges of

different size (between 35 and 220 feet) and type were selected for the questionnaire. The

information obtained for these bridges is summarized in Table 4.2 along with the levels

of damage produced by the differential settlements.

Page 72: TARGET LEVELS OF RELIABILITY FOR DESIGN OF BRIDGE

48

Table 4.2. Presents bridge types, sizes and levels of settlement damage

The initial costs of the selected bridges and the repair costs associated with the

three levels of damage are summarized in Table 4.3.

Table 4.3. For the selected bridges, the table presents the year and cost of construction

along with the repair costs for three levels of damage due to settlement. (Information

provided by Missouri Department of Transportation-MoDOT, 2009).

Settlement that results in level of damage (inches)

Service A Service B Service C

(Deck Crack) (Structural) (Severe)

A3101 3 6 12

A6248 3 6 30

A5054 2.5 5 18

Pre

-str

ess

continuous

A4824 2.5 4 18

Concr

ete

continuous

A3390 2 4 8

Average 3 5 17

Service Limits

Concr

ete

continuous,

ste

el p

late

s

Bridge

BridgeYear of

Construction

Past

Initial Cost

Present

Initial Cost

Minor

Damage

Interm.

Damage

Severe

Damage

A3390 1981 206,548 491,557 21,000 302,000 702,000

A4824 2005 758,505 840,181 22,000 512,000 1,522,000

A3101 1987 544,144 1,036,221 23,800 351,400 1,462,000

A6248 2001 4,259,949 5,206,524 32,000 542,000 5,702,000

A5054 1996 22,534,581 31,070,146 28,800 793,800 2,732,000

Settlement Repair Cost

Page 73: TARGET LEVELS OF RELIABILITY FOR DESIGN OF BRIDGE

49

The information regarding initial costs and repair costs provided by MoDOT

through the questionnaire were plotted in the log-log graphic shown in Figure 4.4.

Relationships for initial and consequence (repair) costs were established for each level of

damage as well as for the total bridge replacement scenario. The relationships for all four

levels of damage were expressed as mathematical functions generated by the add-on

“Power function” of Excel ®. Good correlation was observed for all four levels of initial

versus consequence costs.

Figure 4.4 Initial cost versus repair or replacement cost of bridges for three levels of

damage and cost of bridge replacement.

Detail information used in this chapter such as magnitudes of bridge settlement,

questionnaire to MoDOT, bridge initial and repair costs MoDOT are summarized in

tables presented in Apendix A.

Minor damage

y = 6959x0.09

Interm. damage

y = 24688x0.20

Severe damage

y = 2698x0.45

Collapse

y = 0.74x1.13

1.E+04

1.E+05

1.E+06

1.E+07

1.E+08

1.E+09

1.E+04 1.E+05 1.E+06 1.E+07 1.E+08 1.E+09

Bri

dge

rep

air

co

st,

do

llars

(X

)

Present initial cost, dollars (H)

Page 74: TARGET LEVELS OF RELIABILITY FOR DESIGN OF BRIDGE

50

4.5 Summary

According to previous chapters, target probabilities of failure for geotechnical

infrastructure through economic considerations require the establishment of accurate

relations between the initial costs of bridges and their costs for repair or replacement.

From the literature and information obtained from MoDOT through a questionnaire, the

costs of repair were found to be associated with the levels of damage produce by different

magnitudes of bridge settlement. In the same way, the cost of bridge replacement was

found to be associated with the initial or construction cost. Detail bridge information and

consequence costs are presented in this chapter as well as plots showing a good

correlation between the consequence costs and initial costs of the bridges for three levels

of damage and collapse.

Page 75: TARGET LEVELS OF RELIABILITY FOR DESIGN OF BRIDGE

51

5 BRIDGE FOUNDATION ECONOMIC ANALYSIS

5.1 Introduction

In Chapter 3 a function was derived to calculate the optimum economic

probability of failure for geotechnical infrastructure. The optimization (minimization) of

this economic function requires establishing a relation between the probability of failure

and the initial cost of the infrastructure. The analysis performed, including assumptions

and considerations to develop equations that relate the probability of failure and the

initial cost of bridge foundations and approach embankments is presented in this chapter.

Sensitivity analyses for material unit costs, foundation geometry and material properties

are also included.

5.2 Probability of Failure-Cost Relations

The probability of failure (Pf) or the probability of an unsatisfactory performance

of a foundation decreases when increasing the certainty of soil and material parameter

values, when increasing the quality and/or size of the foundation or when improving the

design (type) of the foundation. All these options increase the cost of the foundation. The

probability of failure-cost relation (Pf-cost) is a function that relates the probability of

failure and the initial cost of the infrastructure. The slope of this function represents the

cost required to decrease the probability of failure.

Page 76: TARGET LEVELS OF RELIABILITY FOR DESIGN OF BRIDGE

52

The term “probability of failure” is an event that does not necessarily only

describes the chance of catastrophe. The behavior could constitute unsatisfactory

performance but not catastrophic failure (Duncan et al., 1999). The Corps of Engineers

uses the term “probability of unsatisfactory performance” to describe probability of

failure (U.S. Army Corp of Engineers, 1998). In the previous chapter, three levels of

service limits were established in relation to the damage produced by differential

settlements of bridges. This chapter presents Pf-cost relations for service limits of bridge

foundations and approach embankments as well as Pf-cost relations for strength limit

state of bridge foundations.

The probabilities of failure were established through reliability analyses.

“Reliability” as used in reliability theory is “the probability of an event occurring”, or the

probability of a “positive” outcome (Duncan et al., 1999). Reliability calculations

provided a means to evaluate the combined effects of multiple design parameter

uncertainties and variability.

There are numerous methods of employing reliability theory to evaluate reliability

of geotechnical infrastructure. The Taylor’s Series method is described in the following

section.

5.2.1 Taylor Series Method

The Taylor series method is a procedure to compute the standard deviation and/or

the coefficient of variation of the factors of safety for the strength (capacity) limit or

service limits. The use of the method requires previous knowledge of the mean and

Page 77: TARGET LEVELS OF RELIABILITY FOR DESIGN OF BRIDGE

53

standard deviation of all parameters. The mean value of the factor of safety and the mean

value of the probability of exceeding a service limit distribution are referred to in this

method as the most likely value (FMLV). The most likely values of the factors of safety

and the probabilities of exceeding a service limit were established using a deterministic

method that consists of computing the mean value of the distribution using the mean

value of all parameters.

The standard deviation and coefficient of variation, (V) for both the factor of

safety distribution and probability of exceeding a service limit distribution were obtained

by calculating partial factors of safety or partial probability of exceeding a service limit

by varying the values of the input parameters by the value of their standard deviations.

Two partial factors of safety Fi+ and Fi- are obtained when increasing or decreasing the

value of one parameter at a time by the value of their standard deviation while the other

parameters were kept at their mean values. Considering F as the absolute difference

between Fi+ and Fi

-, the standard deviation (F) of the factor of safety was computed by

applying Equation 5.1.

𝜎𝐹 = √(∆𝐹1

2)

2

+ (∆𝐹2

2)

2

+ (∆𝐹3

2)

2

+ ⋯ + (∆𝐹𝑛

2)

2

Equation 5.1

The coefficient of variation of the factor of safety (VF) was computed using the

standard deviation (F) in Equation 5.2.

𝑉𝐹 =𝜎𝐹

𝐹𝑀𝐿𝑉

Equation 5.2

Page 78: TARGET LEVELS OF RELIABILITY FOR DESIGN OF BRIDGE

54

Distributions of factors of safety values for strength limit and settlement values

for service limits were developed using the mean and standard deviations values

computed using Taylor’s Series method. These distributions were assumed to be

lognormal. Using the distributions of factor of safety, the magnitude of the probability of

failure was established by computing the area under the distribution curve (using

cumulative functions) that was less than unity (1.0). The probability of exceeding a

selected service limit was established by computing the area under the settlement value

distribution curve larger than the service limit value.

The initial costs of the foundations depend of the foundation type, there size and

the cost of their materials. Most of the costs used for the materials were obtained from the

Missouri Department of Transportation (MoDOT) cost reports (reference, year).

5.2.2 Probability of Failure – Cost Function Slope Factor

The term “probability of failure” was defined as the probability of occurrence of a

catastrophic event or unsatisfactory performance. At this stage of the dissertation, the

“probability of failure” is used to describe the probability of the factor of safety being

less than unity or the probability of exceeding a service limit.

Probabilities of failure-cost curves were developed by plotting the probability and

cost pairs on semi-log graphs. Probability values were plotted on the horizontal axis in a

log scale while the costs were plotted on the vertical axis in an arithmetic scale. The

probabilities of failure-cost functions were established using the trend line adds-on of

Page 79: TARGET LEVELS OF RELIABILITY FOR DESIGN OF BRIDGE

55

Excel® considering a logarithmic regression type. The functions reported by Excel ® are

displayed on the graphs.

The regression function reported by Excel ® has a linear form with the abscissa

parameter (probability of failure) expressed in a natural log scale instead of a logarithmic

scale. The independent constant, (d) which is an arithmetic value, represents the

intersection of the function curve with a vertical line that passes through the probability

of failure value equal to unity (Pf = 1.0). As shown in Equation 5.3, the term with the

independent variable (probability of failure, P) is affected by a factor (b) which is not the

true slope (m) of the linear function. The factor b is acting on the natural log value of the

probability of failure instead of the logarithmic value of the probability of failure on a

semi log graph.

𝐴 = 𝑏 ∙ 𝐿𝑛(𝑃) + 𝑑

Equation 5.3

Where:

A = the foundation initial cost,

b = the slope factor,

P = the probability of failure, and

d = the vertical intercept at Pf = 1.0

The value of the slope factor b can be expressed in terms of the true function

slope, m. Consider the following linear equation in a semi log graph:

𝐴 = 𝑚 ∙ 𝐿𝑜𝑔(𝑃) + 𝑑 Equation 5.4

Page 80: TARGET LEVELS OF RELIABILITY FOR DESIGN OF BRIDGE

56

Where:

A = the foundation initial cost,

m = the slope of the linear function,

P = the probability of failure, and

d = the vertical intercept at Pf = 1.0

A relation between the slope factor b and the slope m can be established by

comparing the terms with the independent variable P of Equation 5.3 and Equation 5.4.

𝑏 ∙ 𝐿𝑛(𝑃) = 𝑚 ∙ 𝐿𝑜𝑔(𝑃)

𝑏 = 𝑚 ∙𝐿𝑜𝑔(𝑃)

𝐿𝑛(𝑃)

Equation 5.5

The ratio between the log and natural log of P that multiplies the slope m can be

simplified using the following known expression:

𝐿𝑜𝑔𝑎(𝑋) =𝐿𝑛(𝑋)

𝐿𝑛(𝑎)

Replacing the abscissa X with the probability (P) and replacing the general base

value (a) of the logarithmic function to base 10, we have:

𝐿𝑜𝑔10(𝑃) =𝐿𝑛(𝑃)

𝐿𝑛(10) Equation 5.6

Page 81: TARGET LEVELS OF RELIABILITY FOR DESIGN OF BRIDGE

57

Rearranging Equation 5.6, the expression for the ratio between the log and natural

log of P is the following:

𝐿𝑜𝑔(𝑃)

𝐿𝑛(𝑃)=

1

𝐿𝑛(10)

Equation 5.7

The relation between the slope factor b and the true slope m is obtained by

replacing the expression shown in Equation 5.7 into Equation 5.5.

𝑏 = 𝑚 ∙1

𝐿𝑛(10)

or

𝑏 = 0.434 ∙ 𝑚

Therefore quantitatively, the value of the slope factor b is about 40 percent of the

value of the true slope of the probability of failure-cost function in a semi-log plane. As

shown in the previous chapter, the optimum economic probability of failure can be

expressed in terms of slope factor b or in terms of the true slope m of the function.

Considering that Excel® reports the equation of the logarithmic trend using the slope

factor b, for practical purposes, optimum probabilities of failure curves (economic

curves) will be developed in the next chapter using the slope factors reported in this

chapter.

Page 82: TARGET LEVELS OF RELIABILITY FOR DESIGN OF BRIDGE

58

5.2.3 Pile Groups

Probably of failure-cost functions were developed for different types of bridge

foundations. The results and considerations using pile foundation are presented in this

section.

5.2.3.1 Pile group conditions

The relations between the probability of failure and the cost to reduce the

probability of failure (probability of failure-cost functions) of pile groups were developed

by defining failure as exceeding the capacity (strength limit state) and exceeding the

service limits that were established in Chapter 4. Different magnitudes of load were used

to develop the pile group probability of failure-cost function. The impact on the results

caused by using different loads is presented in the sensitivity analysis section of this

chapter.

The probability of failure-cost function for piles groups was established

considering the following assumptions:

a) The mean working load was assumed to be 4000 kips. The coefficient of

variation of the working load was based on the average dead and live loads

standard deviations reported in the NCHRP 20-7/186 report.

b) For a selected load, the probabilities of failure and the cost data points were

obtained by varying the number of piles (between 3 and 10) in the group.

c) Piles were designed to reach bedrock which was located 50 feet below the

ground surface.

Page 83: TARGET LEVELS OF RELIABILITY FOR DESIGN OF BRIDGE

59

d) The selected size for the piles was HP10x57 with a cross sectional area of

16.8 in2 and a yield strength of 50 ksi. The coefficient of variation of the yield

strength was obtained from the NCHRP 20-7/186 report and the coefficient of

variation of the pile cross sectional area (V = 0.06) was obtained from Schmidt

et al. (2001).

e) The elastic modulus of the piles was 29,000 ksi and its coefficient of variation

(V = 0.06) was obtained from the NCHRP 20-7/186 report.

f) The mean value of the elastic modulus for the rock 3,400 ksi was established

by averaging pressuremeter tests results obtained from MoDOT’s research site

at Warrensburg, MO.

Although the cost of steel is normally reported in terms of dollars per unit weight,

calculations for the total pile group costs were simplified by estimating pile costs based

on pile length. The assumed cost of 70 dollars per foot length (FL) of pile was established

considering the unit weight per foot length of the selected pile cross sectional area. The

price was obtained from the Missouri Department of Transportation report: “Missouri

Pay Item Report”, item N° 7061060, “Reinforcing steel bridges (Sanders, 2010). The

average price reported was $1.17 per pound of reinforcing steel. The calculation to

estimate the cost of HP10x57 piles per unit length is summarized as follows (price did

not include installation):

1.17$/lb x 57lb/LF = 66.69 $/LF. Rounded to 70.00 $/LF

Page 84: TARGET LEVELS OF RELIABILITY FOR DESIGN OF BRIDGE

60

An elevation view of the pile group scenario showing the assumed values is

shown in Figure 5.1. A summary of all mean values and their coefficients of variation are

presented in Table 5.1.

Figure 5.1 Elevation view of pile groups showing assumed values.

Table 5.1. Design parameter values, standard deviations and c.o.v’s used to develop pile

group probability of failure-costs functions.

Rock

Soil

Pile cap

50 ft

Qw = 4000 kips

Pile group HD10x57

Pile cost 70.00 $/FL

Standard Plus one Minus one

Deviation Std Dev Std Dev

Load kips 4,000 0.12 480 4,480 3,520

Pile cross sectional in2

16.80 0.03 0.50 17.30 16.30

Steel elastic modulus ksi 29,000 0.06 1,740 30,740 27,260

Rock elastic modulus ksi 33,500 0.50 16,700 50,200 16,700

Parameter Unit Mean COV

Page 85: TARGET LEVELS OF RELIABILITY FOR DESIGN OF BRIDGE

61

5.2.3.2 Pile Group Strength Limit State

The probability of failure-cost function for pile group strength limit state

(capacity) was developed using reliability theory. Factors of safety were calculated using

Equation 5.8. Factors of safety distribution curves were developed with mean and

standard deviation values calculated using the Taylor’s Series method. The values of

probability of failure were calculated from the distribution curves while cost values were

calculated based on MoDOT Pay Item reports.

𝐹. 𝑆. =𝐹𝑦∙𝐴∙𝑛

𝑄𝑊

Equation 5.8

Where,

F.S. = the factor of safety

Fy = the pile yield strength

A = Cross sectional area of pile

n = number of piles in the pile group, and

Qw = working load.

A factor of safety distribution curve was developed for each pile group size. The

size of the pile groups depended on the number of piles in each group and they varied

between 3 and 9 piles. Each factor of safety distribution curve generated a probability of

failure point data (probability of the factor of safety being less than 1.0). Each pile group

size was also associated with a cost depending on the number of piles in a group. Pairs of

probability of failure and costs are plotted on a semi-log graph as shown in Figure 5.2.

Page 86: TARGET LEVELS OF RELIABILITY FOR DESIGN OF BRIDGE

62

Figure 5.2. Probability of failure-initial cost function for pile groups.

Using Excel’s add-on function, a logarithmic type trend line and function

equation were generated for the probability of failure-cost points. Figure 5.2 shows the

probability of failure-cost function generated for pile group strength. The slope factor b

of the function is -1,352. The negative sign of factor b means that the probability of

failure decreases as the cost increases or, the cost increases as reliability increases.

In some cases, the value of the slope factor b varies depending of the range of the

probability of failure points considered. The interval of interest for this dissertation

ranges between 1 a hundred (1x10-2

) and 1 in a million (1x10-6

) probability of failure.

Factor of safety distribution curves were assumed to be log-normal. These distribution

curves were plotted to visually compare their characteristics. Distribution curves, mean

A = -1,352 ln(P) + 17,043

0

5,000

10,000

15,000

20,000

25,000

30,000

35,000

1E-08 1E-07 1E-06 1E-05 1E-04 1E-03 1E-02 1E-01 1E+00

Co

st p

ile g

rou

p, 5

0 f

t lo

ng

, d

olla

rs,

(A)

Probability of elastic failure, (P)

Page 87: TARGET LEVELS OF RELIABILITY FOR DESIGN OF BRIDGE

63

values, standard deviations and probabilities of failure for pile groups of 5 and 7 piles are

shown in Figure 5.3. The probability of failure or the area under the distribution curve

less than 1.0, depends on the location mean value and the standard deviation (spread) of

the distribution curve. The spread of the distribution depends on the variability or

uncertainty of the design parameter variables. When comparing distribution curves,

distributions with large means values (mean values shifted away from 1.0) were observed

to have larger probabilities of failure if their spread is larger.

Figure 5.3. Factor of safety distribution curves for pile groups of 3and 5 piles.

5.2.3.3 Pile Group Service Limit State

The probability of failure-cost function for pile groups was developed for the

probability of pile groups to exceed the three levels of service limit (settlement

thresholds) established in Chapter 3. The probabilities of exceedance were obtained using

reliability theory. Taylor’s Series method was used to calculate probabilities of failure

Pf5 piles = 4.01E-01 m5 piles = 1.05

5 piles = 0.16

Pf7 piles = 6.40E-03 m7 piles = 1.47

7 piles = 0.22

0.E+00

1.E+00

2.E+00

3.E+00

0 1 2 3 4 5

PD

F

Pile group, factor of safety

3.E-04

Page 88: TARGET LEVELS OF RELIABILITY FOR DESIGN OF BRIDGE

64

considering the combined effect of the variability of the input parameters. Pile group

settlement includes the elastic settlement of the pile and the elastic settlement of the

bedrock. The equation used to compute pile group service limits is shown in Equation

5.9.

𝑆𝑒𝑡𝑡𝑇𝑜𝑡 = 𝑆𝑒𝑡𝑡𝑝𝑖𝑙𝑒 + 𝑆𝑒𝑡𝑡𝑟𝑜𝑐𝑘

Equation 5.9

𝑆𝑒𝑡𝑡𝑝𝑖𝑙𝑒 =𝑄𝑊∙𝐿𝑃

𝐸𝑝∙𝐴

𝑆𝑒𝑡𝑡𝑟𝑜𝑐𝑘 =∆𝜎

𝐸𝑠× 𝐿𝑃

Where,

∆𝜎 =𝑄𝑊

[(𝐵 + 𝐿𝑃)

3 + 0.5 ∙(2𝐵 − 𝐿𝑃)

3 ] × [(𝐿 + 𝐿𝑃)

3 + 0.5 ∙(2𝐵 − 𝐿𝑃)

3 ]

and,

Sett = settlement

Qw = working load

LP = pile length

Es = Steel elastic modulus

A = cross sectional area of pile

= increase in stress, and

L and B = Dimensions of the cross section area of pile group.

In this section the probability of exceeding the service limit is referred as the

probability of failure. Each pile group generated a probability of failure point and an

Page 89: TARGET LEVELS OF RELIABILITY FOR DESIGN OF BRIDGE

65

associated cost. Probability of failure values were plotted against the cost value of pile

groups on a semi-log graph. The probability of failure-cost function was generated using

Excel’s ® add-on function for logarithmic regression.

Figure 5.4 shows the probability of failure-cost function for the service limit A

(approximately 3 inches to produce a distortion of 0.0021) while Figure 5.5 and Figure

5.6 show the functions for service limits B and C (approximately 5 inches to produce a

distortion of 0.004 and 17 inches to produce overstress) respectively. The slope factors

(b-values) are valid for probabilities of failure that range between 1 in a hundred (1x10-2

)

to 1 in a million (1x10-6

). The slope factors b for pile group service limits are -12,581, -

6,996 and -2,558 for limits A, B and C respectively.

As the magnitudes of settlement, expressed as service limits, increases (from 3

inches to 17 inches), the absolute value of the slope factor b decreases becoming more

similar to the value of the strength limit. This can be observed by comparing the slope

factor b of service limit C equal to -2,558 with the pile group strength slope factor b of -

1,352. This behavior can be explained by understanding that it is more expensive to

decrease the probability of exceeding a small service limit (i.e. 3 inches) than it is to

decrease the probability of a large service limit (i.e. 17 inches) or of strength limit

(collapse).

Distribution curves showing the probability of exceeding service limit A for 4 and

9 piles are shown in Figure 5.7 The probability of exceeding the service limit drops from

approximately 67 percent for a pile group of 4 piles to 16 percent for a pile group of 9

piles. The improvement in reliability by the increase in the number of piles (or cost) for

service limit A is reflected in Figure 5.4.

Page 90: TARGET LEVELS OF RELIABILITY FOR DESIGN OF BRIDGE

66

Figure 5.4. Probability of pile groups to exceed service limit A (about 3 inches or a

distortion of 0.0021).

Figure 5.5. Probability of pile groups to exceed service limit B (5 inches or a distortion of

0.004).

A = -12,581 ln(P) + 4,768

0

10,000

20,000

30,000

40,000

50,000

60,000

1E-08 1E-07 1E-06 1E-05 1E-04 1E-03 1E-02 1E-01 1E+00

Co

st p

ile g

rou

p, 5

0 f

t lo

ng

, d

olla

rs,

(A)

Probability of exceeding 3 inches of settlement (P)

A = -6,996 ln(P) + 738

0

10,000

20,000

30,000

40,000

50,000

60,000

1E-08 1E-07 1E-06 1E-05 1E-04 1E-03 1E-02 1E-01 1E+00

Co

st p

ile g

rou

p, 5

0 f

t lo

ng

, d

olla

rs,

(A)

Probability of exceeding 5 inches of settlement (P)

Page 91: TARGET LEVELS OF RELIABILITY FOR DESIGN OF BRIDGE

67

Figure 5.6. Probability of pile groups to exceed service limit C (about 17 inches).

Figure 5.7. Distribution curves of pile groups of 4 and 9 piles displaying the probability

of exceeding service limit A.

A = -2,553 ln(P) - 7,172

0

10,000

20,000

30,000

40,000

50,000

60,000

1E-08 1E-07 1E-06 1E-05 1E-04 1E-03 1E-02 1E-01 1E+00

Co

st p

ile g

rou

p, 5

0 f

t lo

ng

, d

olla

rs,

(A)

Probability of exceeding 17 inches of settlement (P)

Pf4 piles = 0.6677 m4 piles = 4.08

4 piles = 2.00

Pf9 piles = 0.1638 m9 piles = 2.10

9 piles = 1.08

0.E+00

1.E-01

2.E-01

3.E-01

4.E-01

5.E-01

6.E-01

0 1 2 3 4 5 6 7 8 9 10

PD

F

Pile group, service state limite A

3.E-04

Page 92: TARGET LEVELS OF RELIABILITY FOR DESIGN OF BRIDGE

68

5.2.4 Drilled Shafts

The probability of failure-cost functions for drilled shafts were developed

following a procedure similar to that of pile groups. This section presents the results and

considerations for the design of probability of failure-cost functions for drilled shafts.

5.2.4.1 Drilled Shafts conditions

The probability of failure-cost functions for drilled shafts were developed for the

probability of exceeding the capacity (strength limit state) of drilled shafts and for the

probability of exceeding the service limits established in Chapter 4. Different magnitudes

of load were used to develop the drilled shaft probability of failure-cost and service limit

state functions. The impact on the function caused by using different loads is presented in

the sensitivity analysis section of this chapter.

The following are the assumptions considered to develop the probability of

failure-cost function for drilled shafts:

a) The mean working load was considered to be 4000 kips. The coefficient of

variation of the working load is based on the average dead and live loads

standard deviations reported in the NCHRP 20-7/186 report.

b) The soil was considered homogeneous along the depth of the drilled shaft

with a mean undrained shear strength, Su of 34,800 psf and a coefficient

of variation, V=0.80. These values were obtained from MoDOT’s research

site at Warrengsburg, Missouri.

Page 93: TARGET LEVELS OF RELIABILITY FOR DESIGN OF BRIDGE

69

c) Drilled shafts varied in length and diameter. Drilled shaft length varied

between 10 and 110 ft while their diameters varied between 3 and 5ft.

The cost of drilled shafts depended on the length, and the unit price of the shaft

per diameter. Unit prices were obtained from Missouri Pay Item Report dated in 2010.

The unit price per foot of 3 ft diameter drilled shafts was reported as: Pay Item 701-

11.04, and is 348.56 dollars per foot long. The unit price per foot of 4 ft diameter drilled

shafts was reported as: Pay Item 701-11.06, and is 646.25 dollars per foot long. The unit

price per foot of 5 ft diameter drilled shafts was reported as: Pay Item 701-11.08, and is

882.50 dollars per foot long.

An elevation view of the drilled shafts showing the assumed values is shown in

Figure 5.8. A summary of all mean values and their coefficients of variation are presented

in Table 5.2.

Page 94: TARGET LEVELS OF RELIABILITY FOR DESIGN OF BRIDGE

70

Figure 5.8. Elevation view of a drilled shaft showing assumed values.

Table 5.2. Design parameter values and standard deviations used to develop drilled shafts

probability of failure-costs functions.

Cap

Qw = 4000 kips

Shaft length: 10<LS<110 ft

Diameters: 3, 4, 5 ft

D = 4 ft then $650/FL

D = 5 ft then $880/FL

Shaft cost: D = 3 ft then $350/FL

Su = 34,800 psf

c.o.v. = 0.80

Standard Plus one Minus one

Deviation Std Dev Std Dev

Load kips 4,000 0.12 480 4,480 3,520

Undrain shear strength psf 34,800 0.80 27,840 62,640 6,960

Soil elastic modulus ksi 33,500 0.50 16,700 50,200 16,700

Parameter Unit Mean COV

Page 95: TARGET LEVELS OF RELIABILITY FOR DESIGN OF BRIDGE

71

5.2.4.2 Drilled Shafts Strength Limit

The probability of failure-cost function for drilled shaft strength limit state

(capacity) was developed using reliability theory. Factors of safety were calculated using

Equation 5.10. Factors of safety distribution curves were developed with mean and

standard deviation values calculated using the Taylor’s Series method. The values of

probability of failure were calculated from the distribution curves while cost values were

calculated based on MoDOT Pay Item reports.

𝐹. 𝑆. =∝∙ 𝑆𝑢 ∙ 𝜋 ∙ 𝐷 ∙ 𝐿𝑆 + 9 ∙ 𝑆𝑢 ∙ 𝜋 ∙

𝐷4

𝑄𝑊

Equation 5.10

Where,

F.S. = the factor of safety

α = skin resistance coefficient

Su = undrained shear strength

D = drilled shaft diameter

LS = drilled shaft length

Qw = working load.

A factor of safety distribution curve is developed for each drilled shaft size. Each

factor of safety distribution curve generated a probability of failure data point. Depending

on the size, each drilled shaft was also associated with a cost. Pairs of probability of

failure and costs are plotted on a semi-log graph as shown in Figure 5.9.

Page 96: TARGET LEVELS OF RELIABILITY FOR DESIGN OF BRIDGE

72

Figure 5.9. Probability of failure-cost function for drilled shafts.

Using Excel’s add-on function, a logarithmic type trend line and function

equation were generated for the probability of failure-cost points. The interval of interest

for this dissertation ranges between 1 a hundred (1x10-2

) and 1 in a million (1x10-6

)

probability of failure. Figure 5.9 shows the probability of failure-cost function generated

for drilled shaft strength. The slope factor b of the function is -17,067. As mentioned

before, the negative sign of the result means that the probability of failure decreases as

the costs increases or as the reliability increases, cost increases. This slope is larger in

magnitude that the slope generated for pile group (b = -1,352). This means that it is more

expensive to reduce the probability of failure for drilled shafts than it is for pile groups.

In the next chapter, optimum probabilities will be presented along with an interpretation

of the different slope function values.

y = -17,067ln(x) - 12,615

0

10,000

20,000

30,000

40,000

50,000

60,000

70,000

80,000

90,000

100,000

1E-06 1E-05 1E-04 1E-03 1E-02 1E-01 1E+00

Dril

led

sh

aft

cost

, d

olla

rs,

(A)

Probability of failure, (P)

Page 97: TARGET LEVELS OF RELIABILITY FOR DESIGN OF BRIDGE

73

Factor of safety distribution curves were assumed to be log-normal distributions.

These distribution curves were plotted to visually compare their characteristics.

Distribution curves, mean values, standard deviations and probabilities of failure for

drilled shafts of 3 and 5 feet diameter are shown in Figure 5.10. The probability of failure

or the area of the distribution curve less than 1.0, depends on the mean value and the

standard deviation (spread) of the distribution curve. The spread of the distribution

depends of the variability or uncertainty of the design parameter variables. Same as with

pile groups, when comparing distribution curves, distributions with a large means values

were observed to often have larger probabilities of failure if their spread is larger.

Figure 5.10. Factor of safety distribution curves for 3 and 5 ft diameter drilled shafts.

Pf3ft diam = 0.1151 m3ft diam = 3.01

3ft diam = 2.44

Pf5ft diam = 0.0188 m5ft diam = 5.64

5ft diam = 4.56

0.E+00

1.E-01

2.E-01

3.E-01

4.E-01

0 1 2 3 4 5 6 7 8 9 10

PD

F

60 ft drilled shafts, factor of safety

3.E-04

Page 98: TARGET LEVELS OF RELIABILITY FOR DESIGN OF BRIDGE

74

5.2.4.3 Drilled Shafts Service Limit State

The probability of failure-cost function for drilled shafts was developed for the

probability of drilled shafts to exceed the 3 levels of service limit (settlements thresholds)

established in Chapter 3. The probabilities of exceedence were obtained using reliability

theory. Taylor’s Series method was used to calculate probabilities of failure considering

the combined effect of the variability of the input parameters. Drilled shaft settlements

were established based on side and tip elastic method proposed by Vesic (1977) in a

homogenous medium. The equation used to compute drilled shaft service limits is shown

in Equation 5.11.

𝑆𝑒(𝑇𝑜𝑡) = 𝑆𝑒(1) + 𝑆𝑒(2)

Equation 5.11

𝑆𝑒(1) =𝑄𝑊𝑝 ∙ 𝐶𝑝

𝐷𝑝 ∙ 𝑞𝑝

𝑆𝑒(2) =𝑄𝑊𝑠

(𝐷𝑏∙𝜋)∙𝐿×

𝐷𝑏

𝐸𝑆× (1 − 𝜇2) × 𝐼𝑊𝑆

Where,

QWp = load carried by the drilled shaft toe

Cp = empirical coefficient dependent on the soil type and construction

method, values range between 0.03 and 0.04.

Dp = diameter of the drilled shaft

qp = theoretical ultimate end bearing pressure

QWs = load carried by the drilled shaft side

Page 99: TARGET LEVELS OF RELIABILITY FOR DESIGN OF BRIDGE

75

Db = diameter of the drilled shaft

ES = modulus of elasticity of the soil along the shaft side

µ = Poisson’s ratio

IWS = empirical influence factor (Vesic, 1977)

The probability of exceeding the service limit is also referred in this dissertation

as the probability of failure. Depending on the size, each drilled shaft generated a

probability of failure point and an associated cost. Probabilities of failure are plotted

against the cost value of drilled shafts on a semi-log graph. The probability of failure-cost

function was generated using Excel’s add-on function for logarithmic regression.

The probability of failure-cost function for the service limit A (approximately 3

inches) is shown in Figure 5.11 while Figure 5.12 and Figure 5.13 show the functions for

service limits B and C (approximately 5 and 17 inches) respectively. The slope factors b

for drilled shafts service limits are -41,526, -34,873 and -23,703 for limits A, B and C

respectively. These slope factors values are valid for probabilities of failure that range

between 1 in a hundred (1x10-2

) to 1 in a million (1x10-6

).

Settlement distribution curves were developed for different drilled shaft sizes. The

probabilities of 3 and 5 feet diameter drilled shafts to exceed limit A are show graphically

in Figure 5.14. Results (approximately 6 and 3 percent chance respectively) show that is

likely to exceed settlement limit A.

Page 100: TARGET LEVELS OF RELIABILITY FOR DESIGN OF BRIDGE

76

Figure 5.11. Probability of drilled shafts to exceed service limit A (about 3 inches).

Figure 5.12. Probability of drilled shafts to exceed service limit B (about 5 inches).

A = -41,526 ln(P) - 113,798

0

10,000

20,000

30,000

40,000

50,000

60,000

70,000

80,000

90,000

100,000

1E-07 1E-06 1E-05 1E-04 1E-03 1E-02 1E-01 1E+00

Co

st d

rille

d s

ha

ft, d

olla

rs,

(A)

Probability of exceeding 3 inch settlement

A = -34,873 ln(P) - 128,517

0

10,000

20,000

30,000

40,000

50,000

60,000

70,000

80,000

90,000

100,000

1E-07 1E-06 1E-05 1E-04 1E-03 1E-02 1E-01 1E+00

Co

st d

rille

d s

ha

ft, d

olla

rs,

(A)

Probability of exceeding 5 inch settlement

Page 101: TARGET LEVELS OF RELIABILITY FOR DESIGN OF BRIDGE

77

Figure 5.13. Probability of drilled shafts to exceed service limit C (about 17 inches).

Figure 5.14. Distribution curves of drilled shafts of 3 and 5 feet in diameter displaying

the probability of exceeding service limit A.

A = -23,703 ln(P) - 156,206

0

10,000

20,000

30,000

40,000

50,000

60,000

70,000

80,000

90,000

100,000

1E-07 1E-06 1E-05 1E-04 1E-03 1E-02 1E-01 1E+00

Co

st d

rille

d s

ha

ft, d

olla

rs,

(A)

Probability of exceeding 17 inch settlement

Pf3ft diam = 0.0571 m3ft diam = 0.96

3ft diam = 1.52

Pf5ft diam = 0.0344 m5ft diam = 0.73

5ft diam = 1.16

0.E+00

1.E+00

2.E+00

0 1 2 3 4 5 6 7 8 9 10

PD

F

20 ft drilled shaft, service state limite A

3.E-04

Page 102: TARGET LEVELS OF RELIABILITY FOR DESIGN OF BRIDGE

78

5.2.5 Spread Footing

The probably of failure-cost functions for spread footing was developed

following a similar procedure to pile groups and drilled shafts. This section will

present the results and considerations using spread footings.

5.2.5.1 Spread Footing conditions

The probability of failure-cost functions for spread footing were developed for the

probability of exceeding the capacity (strength limit state) of spread footing and for the

probability of exceeding the service limits established in Chapter 4. Different magnitudes

of load were considered to develop the spread footing strength and service limit state

functions. The impact on the function caused by using different loads is presented in the

sensitivity analysis section of this chapter.

The following are the assumptions considered to develop the probability of

failure-cost functions for spread footings:

a) The mean working load was considered to be 4000 kips. The coefficient of

variation of the working load is based on the average dead and live loads

standard deviations reported in the NCHRP 20-7/186 report.

b) The soil was considered homogeneous along the depth with a mean

undrained shear strength, Su of 34,800 psf and a coefficient of variation, V

= 0.80. These values were obtained from MoDOT’s research site at

Warrengsburg, Missouri.

c) The bottoms of the spread footings were located at 3 feet below the

surface (3 feet of excavation).

Page 103: TARGET LEVELS OF RELIABILITY FOR DESIGN OF BRIDGE

79

d) Spread foot was considered square in shape. Probability of failure analysis

was performed by decreasing side dimensions, B by steps of 2 and 1 ft.

e) Stress was assumed to decrease with depth. At a depth of 2B, the stress

was considered to be 10% of the stress at the bottom of the footing.

Spread footings were reinforced concrete structures. The cost of each spread

footing varied depending on the volume. The total price per cubic foot included the price

of concrete, steel and excavation. The prices were calculated from MoDOT unit pricing

for foundations publish en February of 2010. The pay items considered were: Pay Item

206-10.03 Class1 Excavation in Rock (130.00 $/yd3), Pay Item 206-20.03 Class-2

Excavation in Rock (230.00 $/yd3), Pay Item 703-20.03 Class-B Concrete- Substructure

(815.80 $/yd3) and Pay Item 706-10.60 Reinforcing Steel-Bridges (1.17 $/lb).

Considering these prices, the price for excavation was 6.70 $/ft3 and 36.00 $/ft3 for

reinforced concrete.

An elevation view of a spread footing showing the assumed values is

shown in Figure 5.15. A summary of all mean values and coefficients of variation are

presented in Table 5.3.

Page 104: TARGET LEVELS OF RELIABILITY FOR DESIGN OF BRIDGE

80

Figure 5.15. Elevation view of a spread footing showing assumed values.

Table 5.3. Design parameter values and standard deviations used to develop spread

footing probability of failure-costs functions.

At 2B, = 0.10 qall

Qw = 4000 kips

Soil

H = 2B (variable)

Spread footing 2.5 ft thick

Reinforced concrete cost 36.00 $/ft3

Standard Plus one Minus one

Deviation Std Dev Std Dev

Load kips 4,000 0.12 480 4,480 3,520

Undrain shear strength psf 34,800 0.80 27,840 62,640 6,960

Soil elastic modulus ksi 4,900 0.76 3,700 8,600 1,200

Bearing factor, Nc 6 0.05 0.30 6.30 5.70

Parameter Unit Mean COV

Page 105: TARGET LEVELS OF RELIABILITY FOR DESIGN OF BRIDGE

81

5.2.5.2 Spread Footing Strength Limit

The probability of failure-cost function for spread footing strength limit (capacity)

was developed using reliability theory. Factors of safety were calculated using Equation

5.12. Factors of safety distribution curves were developed with mean and standard

deviation values calculated using the Taylor’s Series method. The values of probability of

failure were calculated from the distribution curves while cost values were calculated

based on MoDOT Pay Item reports.

𝐹. 𝑆. = 𝑆𝑢 ∙ 𝑁𝑐 ∙𝐴

𝑄𝑊

Equation 5.12

Where,

F.S. = factor of safety

Su = undrained shear strength

Nc = bearing capacity factor

A = area of the spread footing

QW = working load

A factor of safety distribution curve was developed for each spread footing size.

Each factor of safety distribution curve generated probability of failure data point.

Depending on the size of the spread footing, each spread footing size was also associated

with a cost. Pairs of probability of failure and costs are plotted on a semi-log graph as

shown in Figure 5.16.

Page 106: TARGET LEVELS OF RELIABILITY FOR DESIGN OF BRIDGE

82

Figure 5.16. Probability of failure-cost function for spread footings.

Using Excel’s add-on function, a logarithmic type trend line and function

equation were generated for the probability of failure-cost points. The interval of interest

for this dissertation ranges between 1 a hundred (1x10-2

) and 1 in a million (1x10-6

)

probability of failure. Figure 5.16 shows the probability of failure-cost function generated

for spread footing strength. The slope factor b of the function is -8,989. The negative sign

of the result means that the probability of failure decreases as the cost increases or as the

reliability increases, cost increases. This slope is larger in magnitude that the slope

generated for pile group (b = -1,352). This means that it is more expensive to reduce the

probability of failure for spread footings than it is for pile groups. In the next chapter,

optimum probabilities will be presented along with an interpretation of the different slope

function values.

A = -8,989 ln(P) - 17,552

0

20,000

40,000

60,000

80,000

100,000

120,000

1E-07 1E-06 1E-05 1E-04 1E-03 1E-02 1E-01 1E+00

Co

st s

pre

ad

foo

ting

, d

olla

rs,

(A)

Probability of failure, (P)

Page 107: TARGET LEVELS OF RELIABILITY FOR DESIGN OF BRIDGE

83

Factor of safety distribution curves were assumed to be log-normal distributions.

These distribution curves were plotted to visually compare their characteristics.

Distribution curves, mean values, standard deviations and probabilities of failure for

spread footing of 25 ft2 and 49 ft

2 are shown in Figure 5.17. The probability of failure or

the area of the distribution curve less than 1.0, depends on the mean value and the

standard deviation (spread) of the distribution curve. The spread of the distribution

depends of the variability or uncertainty of the design parameter variables. When

comparing distribution curves, distributions with a large means values were observed to

often have larger probabilities of failure if their spread was larger.

Figure 5.17 Factor of safety distribution curves for spread footings of 25 and 49 ft2 under

4000 kip of load.

Pf25 ft2 = 0.4920 m25 ft2 = 1.31

25 ft2 = 1.06

Pf49 ft2 = 0.1660 m49 ft2 = 2.56

49 ft2 = 2.07

0.E+00

2.E-01

4.E-01

6.E-01

8.E-01

0 1 2 3 4 5 6 7 8 9 10

PD

F

Spread footing, factor of safety

3.E-04

Page 108: TARGET LEVELS OF RELIABILITY FOR DESIGN OF BRIDGE

84

5.2.5.3 Spread Footing Service Limit State

The probability of failure-cost function for spread footings was developed for the

probability of spread footings to exceed the three levels of service limit (settlements

thresholds) established in Chapter 3. The probabilities of exceedence were obtained using

reliability theory. Taylor’s Series method was used to calculate probabilities of failure

considering the combined effect of the variability of the input parameters. The equation

used to compute spread footing service limits is shown in Equation 5.13.

𝑆 =𝑄𝑊 ∙ √𝐴

𝐸 ∙ 𝐴

Equation 5.13

Where,

S = spread footing elastic settlement

QW = working load

E = modulus of elasticity of the soil

A = area of the spread footing

The probability of exceeding the service limit is also referred as the

probability of failure. Depending on the area, each spread footing generated a

probability of failure point and an associated cost. Probability of failure values are

plotted against the cost value of spread footings on a semi-log graph. The

probability of failure-cost function was generated using Excel’s add-on function

for logarithmic regression.

Page 109: TARGET LEVELS OF RELIABILITY FOR DESIGN OF BRIDGE

85

The probability of failure-cost function for the service limit A (approximately 3

inches) is shown in Figure 5.18 while Figure 5.19 and Figure 5.20 show the functions for

service limits B and C (approximately 5 and 17 inches) respectively. The slope factors b

for spread footings service limits are -47,701, -31,373 and -17,277 for limits A, B and C

respectively. These slope factors values are valid for probabilities of failure that range

between 1 in a hundred (1x10-2

) to 1 in a million (1x10-6

).

Settlement distribution curves were developed for different spread footing sizes.

The probabilities of 25 and 49 feet square to exceed limit A are show graphically in

Figure 5.21. Results (approximately 6 and 3 percent chance respectively) show that is

very likely to exceed settlement limit A.

Page 110: TARGET LEVELS OF RELIABILITY FOR DESIGN OF BRIDGE

86

Figure 5.18 Probability of spread footings to exceed service limit A (about 3 inches).

Figure 5.19 Probability of spread footings to exceed service limit B (about 5 inches).

A = -47,701 ln(P) - 216,992

0

20,000

40,000

60,000

80,000

100,000

120,000

140,000

160,000

1E-06 1E-05 1E-04 1E-03 1E-02 1E-01 1E+00

Co

st s

pre

ad

foo

ting

, (A

)

Probability of exceeding 3 inches of settlement (P)

A = -31,373 ln(P) - 159,092

0

20,000

40,000

60,000

80,000

100,000

120,000

140,000

160,000

1E-06 1E-05 1E-04 1E-03 1E-02 1E-01 1E+00

Co

st s

pre

ad

foo

ting

, (A

)

Probability of exceeding 5 inches of settlement (P)

Page 111: TARGET LEVELS OF RELIABILITY FOR DESIGN OF BRIDGE

87

Figure 5.20 Probability of spread footings to exceed service limit C (about 17 inches).

Figure 5.21 Distribution curves of spread footings of 25 and 49 ft2 displaying the

probability of exceeding service limit A.

A = -17,277 ln(P) - 132,580

0

20,000

40,000

60,000

80,000

100,000

120,000

140,000

160,000

1E-06 1E-05 1E-04 1E-03 1E-02 1E-01 1E+00

Co

st s

pre

ad

foo

ting

, (A

)

Probability of exceeding 17 inches of settlement, (P)

Pf25 ft2 = 0.0630 m25 ft2 = 0.98

25 ft2 = 1.76

Pf49 ft2 = 0.0351 m49 ft2 = 0.70

49 ft2 = 1.26

0.E+00

1.E+00

2.E+00

0 1 2 3 4 5

PD

F

Spread footing, service state limite A

3.E-04

Page 112: TARGET LEVELS OF RELIABILITY FOR DESIGN OF BRIDGE

88

5.2.6 Approach Embankments

The probably of failure-cost functions for embankment was developed following

a similar procedure to pile groups and drilled shafts and spread footings. Results and

considerations using embankments are presented in this section.

5.2.6.1 Embankments conditions

The probability of failure-cost functions for embankments were developed for the

probability of exceeding the capacity (strength limit state) of embankment and for the

probability of exceeding the service limits established in Chapter 3. Different magnitudes

of load were considered to develop the embankment strength and service limit state

functions. The impact on the function caused by using different loads is presented in the

sensitivity analysis section of this chapter.

The following are the assumptions considered to develop the probability of

failure-cost functions for embankments:

a. The mean working load was considered to be 4000 kips. The coefficient of

variation of the working load is based on the average dead and live loads

standard deviations reported in the NCHRP 20-7/186 report.

b. To calculate settlement, embankments were assumed to be sited over

homogeneous soils that have a mean undrained shear strength, Su of

34,800 psf and a coefficient of variation, V = 0.80. These values were

obtained from MoDOT’s research site at Warrensburg, Missouri.

Page 113: TARGET LEVELS OF RELIABILITY FOR DESIGN OF BRIDGE

89

c. The bridge superstructure was assumed not to rest on the embankment.

The embankments were assumed to provide access to a bridge (bridge

approach).

d. For practical purposes, the geometry of the vertical cross sectional area of

the embankment was assumed to be rectangular.

e. It was assumed that 90 percent of the total ground settlement occurred

before placing a roadway on the embankment.

Design of the embankments considered fill and geofoam. The cost of geofoam

was obtained online from Atlas EPS (http://www.falcongeofoam.com/). The price is

reported by the source is approximately 3.50 $/ft3. The price of the fill was obtained from

MoDOT – Bridge Division. The price reported in 2010 ranged between 5 and 25 dollars

per cubic foot or between 0.20$/ft3 and 1.00$/ft3 depending on the volume. The price per

cubic yard assumed for soil fill was 0.50 dollars.

The elevation view of an embankment showing the assumed values is shown in

Figure 5.22. A summary of all mean values and their coefficients of variation are

presented in Table 5.4.

Page 114: TARGET LEVELS OF RELIABILITY FOR DESIGN OF BRIDGE

90

Figure 5.22. Elevation view of an embankment showing assumed values.

Table 5.4 Design parameter values and standard deviations used to develop embankment

probability of failure-costs functions.

3 ft Sand

Rock

Su =

SoilH = 40 ft

4,000 psf

120 pcfSoil fill cost 0.50 $/ft3

Geofoam cost 3.50 $/ft3

g geofoam = 1.5 pcf

g fill =

Embankment H=40 ft

Standard Plus one Minus one

Deviation Std Dev Std Dev

Undrained shear strgth psf 4,000 0.80 3,200 7,200 800

Geofoam unit weight pcf 1.5 0.0 0.0 1.5 1.5

Fill unit weight pcf 120 0.05 6 126 114

Clay void ratio, eo0.85 0.12 0.10 0.95 0.75

Compression index, Cc0.23 0.31 0.07 0.30 0.16

Parameter Unit Mean COV

yrd3

Page 115: TARGET LEVELS OF RELIABILITY FOR DESIGN OF BRIDGE

91

5.2.6.2 Embankments Strength Limit

The probability of failure-cost function for embankment strength (capacity) limit

was developed using reliability theory. Factors of safety were calculated using Equation

5.14. Factors of safety distribution curves were developed with mean and standard

deviation values calculated using the Taylor’s Series method. The values of probability of

failure were calculated from the distribution curves while cost values were calculated

based on MoDOT Pay Item reports.

𝐹. 𝑆. =5 ∙ 𝑆𝑢

𝛾𝑓𝑖𝑙𝑙 ∙ (𝐻𝑠𝑜𝑖𝑙 − 𝐻𝑔𝑒𝑜) + 𝛾𝑔𝑒𝑜 ∙ 𝐻𝑔𝑒𝑜

Equation 5.14

Where,

F.S. = the factor of safety

Su = undrained shear strength

gfill = unit weight of fill

Hsoil = height (thickness) of soil fill

Hgeo = height (thickness) of geofoam

ggeo = unit weight of geofoam

A factor of safety distribution curve is developed for embankments with different

ratios of fill and geofoam height. Each factor of safety distribution curve generated a

probability of failure point data (probability of the factor of safety being less than 1.0).

Depending on the amount of geofoam in the embankment, each ratio of fill-geofoam in

the embankments was also associated with a cost. Pairs of probability of failure and costs

are plotted on a semi-log graph as shown in Figure 5.23.

Page 116: TARGET LEVELS OF RELIABILITY FOR DESIGN OF BRIDGE

92

Figure 5.23 Probability of failure-cost function for embankments.

Using Excel’s add-on function, a logarithmic type trend line and function

equation were generated for the probability of failure-cost points. The interval of interest

for this dissertation ranges between 1 a hundred (1x10-2

) and 1 in a million (1x10-6

)

probability of failure. Figure 5.16 shows the probability of failure-cost function generated

for spread footing strength. The slope factor b of the function is -412. The negative sign

of the result means that the probability of failure decreases as the cost increases or as the

reliability increases, cost increases. This slope is smaller in magnitude that the slope

generated for pile group (b = -1,352). This means that it is less expensive to reduce the

probability of failure for approach embankments than it is for pile groups. In the next

chapter, optimum probabilities will be presented along with an interpretation of the

different function slope values.

y = -412ln(x) + 2,823

0

2,000

4,000

6,000

8,000

10,000

12,000

1E-06 1E-05 1E-04 1E-03 1E-02 1E-01 1E+00

Co

st o

f fil

l a

nd

ge

ofo

am

em

ab

an

kme

nt,

do

llars

, (A

)

Probability of failure, (P)

Page 117: TARGET LEVELS OF RELIABILITY FOR DESIGN OF BRIDGE

93

Factor of safety distribution curves were assumed to be log-normal distributions.

These distribution curves were plotted to visually compare their characteristics.

Distribution curves, mean values, standard deviations and probabilities of failure for

approach embankments of 20 ft and 24 ft high are shown in Figure 5.24. The probability

of failure or the area of the distribution curve less than 1.0, depends on the mean value

and the standard deviation (spread) of the distribution curve. The spread of the

distribution depends of the variability or uncertainty of the design parameter variables.

When comparing distribution curves, distributions with a large means values were

observed to often have larger probabilities of failure if their spread was larger.

Figure 5.24 Factor of safety distribution curves for embankments. Geofoam heights of 20

& 24 ft.

Pfgeo=20ft = 0.0041 mgeo=20ft = 8.23

geo=20ft = 6.60

Pfgeo=24ft = 0.0016 mgeo=24ft = 10.22

geo=24ft = 8.20

0.E+00

1.E-01

2.E-01

0 5 10 15 20 25 30

PD

F

40 ft embankment, factor of safety

3.E-04

Page 118: TARGET LEVELS OF RELIABILITY FOR DESIGN OF BRIDGE

94

5.2.6.3 Embankments Service Limit State

The probability of failure-cost function for embankments was developed for the

probability of embankments to exceed the 3 levels of service limit (settlements

thresholds) established in Chapter 4. The probabilities of exceedence were obtained using

reliability theory. Taylor’s Series method was used to calculate probabilities of failure

considering the combined effect of the variability of the input parameters.

The settlement of an embankment was assumed to have two components. The

first component of settlement is due to the consolidation of the soil layer beneath the

embankment (i.e. the foundation) and the second component of settlement due to the

deformation of the fill of the embankment itself.

Figure 5.25 Accumulated vertical movement (MH, CH soils) 4 year monitoring period

(Vicente et al., 1994).

Page 119: TARGET LEVELS OF RELIABILITY FOR DESIGN OF BRIDGE

95

The deformation of the fill of the embankment was assumed to be 1 percent of the

height of the fill. Vertical surface measurements increase with increasing fill thickness

(Vicente et al., 1994). Figure 5.25 shows a plot of surface vertical movement data versus

compacted fill thickness monitored in southern California where the predominant soil

was elastic silts (MH), fat clay (CH) and clayey sands (SC). The equation used to

compute the settlement of the embankment for the service limits is shown in Equation

5.15.

𝑆𝑒𝑡𝑡10%𝑇𝑜𝑡 = 0.10 × [𝐶𝑐 ∙𝐻𝑠𝑜𝑖𝑙

1 + 𝑒𝑜∙ 𝐿𝑜𝑔 (

𝜎𝑜,𝑠𝑜𝑖𝑙 + ∆𝜎𝑠𝑜𝑖𝑙

𝜎𝑜,𝑠𝑜𝑖𝑙) + 0.01 ∙ (𝐻 − 𝐻𝑔𝑒𝑜)]

Equation 5.15

Where,

Sett10%Tot = ten percent of total settlement

CC = compression index

Hsoil = height (thickness) of soil fill

eo = initial void ratio

o,soil = initial stress

soil = change in stress

H = height of embankment

Hgeo = height (thickness) of geofoam

The probability of exceeding the service limit was also referred as the probability

of failure. Depending on the ratio between the soil fill and the geofoam, each

Page 120: TARGET LEVELS OF RELIABILITY FOR DESIGN OF BRIDGE

96

embankment design generated a probability of failure point and an associated cost.

Probability of failure values are plotted against the cost value of embankments on a semi-

log graph. The probability of failure-cost function was generated using Excel’s add-on

function for logarithmic regression.

The probability of failure-cost function for the service limit A (approximately 3

inches) is shown in Figure 4.36 while Figure 5.27 and Figure 5.28 show the functions for

service limits B and C (approximately 5 and 17 inches) respectively. The slope factors b

for embankments service limits are -120, -256 and -491 for limits A, B and C

respectively. These slope factors values are valid for probabilities of failure that range

between 1 in a hundred (1x10-2

) to 1 in a million (1x10-6

).

Settlement distribution curves were developed for different soil fill and geofoam

ratios. The probabilities of 30 and 31 feet of geofoam fill to exceed limit A are show

graphically in Figure 5.29. Results (approximately 1 and 0.7 percent chance respectively)

show that is likely to exceed settlement limit A.

Page 121: TARGET LEVELS OF RELIABILITY FOR DESIGN OF BRIDGE

97

Figure 5.26 Probability of embankments to exceed service limit A (about 3 inches).

Figure 5.27 Probability of spread footings to exceed service limit B (about 5 inches).

A = -120 ln(P) + 6,214

0

2,000

4,000

6,000

8,000

10,000

12,000

1E-07 1E-06 1E-05 1E-04 1E-03 1E-02 1E-01 1E+00

Co

st o

f fill

an

d g

eo

foa

m e

ma

ba

nkm

ent,

do

llars

, (A

)

Probability of exceeding 3 inches of settlement, (P)

A = -256 ln(P) + 3,871

0

2,000

4,000

6,000

8,000

10,000

12,000

1E-07 1E-06 1E-05 1E-04 1E-03 1E-02 1E-01 1E+00

Co

st o

f fill

an

d g

eo

foa

m e

ma

ba

nkm

ent,

do

llars

, (A

)

Probability of exceeding 5 inches of settlement, (P)

Page 122: TARGET LEVELS OF RELIABILITY FOR DESIGN OF BRIDGE

98

Figure 5.28 Probability of embankments to exceed service limit C (about 17 inches).

Figure 5.29 Settlement distribution curves for embankments displaying the probability of

30 and 31 ft of geofoam fill to exceed service limit A.

A = -491 ln(P) - 6,814

0

2,000

4,000

6,000

8,000

10,000

12,000

1E-10 1E-08 1E-06 1E-04 1E-02 1E+00

Co

st o

f fill

an

d g

eo

foa

m e

ma

ba

nkm

ent,

do

llars

, (A

)

Probability of exceeding 17 inches of settlement, (P)

Pfgeo=30ft = 0.0132 mgeo=30ft = 1.67

geo=30ft = 0.48

Pfgeo=31ft = 0.0068 mgeo=31ft = 1.54

geo=31ft = 0.45

0.E+00

1.E+00

2.E+00

0 1 2 3 4 5

PD

F

40 ft embankment, service state limite A

3.E-04

Page 123: TARGET LEVELS OF RELIABILITY FOR DESIGN OF BRIDGE

99

5.3 Sensitivity Analysis

In previous sections of this chapter, the probability of failure-cost functions were

developed for bridge foundations (pile groups, drilled shafts and spread footings) and for

embankments. These functions were developed considering assumed values for the

design parameters. The impact (sensitivity) on the probability of failure-cost functions

and the factor of safety distribution curves when varying the assumed bridge foundation

design parameter values, are addressed in this section.

5.3.1 Pile Groups - Sensitivity Analysis

For pile groups as for all bridge foundation types analyzed for this dissertation,

values of material properties and their variability were obtained from the literature. The

assumed structure costs were obtained from the Missouri Department of Transportation

(MoDOT) pay reports. Changes were observed in the probability of failure-cost functions

when varying the values of the variables. These changes are quantified and commented

on in the following sub-sections.

The change in cost per length of pile group was observed to change the

probability of failure-cost function proportionally. The change in the function was

quantified through the change in value of the slope factor b. While the intrinsic values of

the probabilities of failure value were not affected by the change in cost, the ordinate of

the plot (cost) of each point that composes the function varied. An example is shown in

Figure 5.30 where the slope factor b is reduced by 50 percent its value when decreasing

the cost (price) per pile length by 50 percent. The abscissas are the same for both

functions.

Page 124: TARGET LEVELS OF RELIABILITY FOR DESIGN OF BRIDGE

100

Figure 5.30 The cost to reduce the probability of failure of pile groups decreases to 50

percent when reducing the cost of pile in 50 percent.

Figure 5.31 Sensitivity of the probability of failure-cost function for pile group strength

limit state when varying the load from 4000 kips (top) to 3000 and 2000 kips (bottom).

A = -1,352 ln(P) + 17,043

A = -676 ln(P) + 8,521

0

5,000

10,000

15,000

20,000

25,000

30,000

35,000

1E-08 1E-07 1E-06 1E-05 1E-04 1E-03 1E-02 1E-01 1E+00

Co

st p

ile g

rou

p, 5

0 f

t lo

ng

, d

olla

rs,

(A)

Probability of elastic failure, (P)

A = -1,352 ln(P) + 17,043

A = -704 ln(P) + 7,843

A = -964 ln(P) + 13,067

0

5,000

10,000

15,000

20,000

25,000

30,000

35,000

1E-08 1E-07 1E-06 1E-05 1E-04 1E-03 1E-02 1E-01 1E+00

Co

st p

ile g

rou

p, 5

0 f

t lo

ng

, d

olla

rs,

(A)

Probability of elastic failure, (P)

Page 125: TARGET LEVELS OF RELIABILITY FOR DESIGN OF BRIDGE

101

The unit price per pile length is provided by MoDOT and does not vary

significantly. If the cost were to change dramatically, the change in the value of the slope

factor b from -1352 to -676 will still produce a small change in the log-log scaled FN

chart. This change is small compared to the engineering precision or judgment when

establishing the target probability of failure and to the differences generated when

comparing to the results of other foundation type functions.

Similar changes in probability of failure-cost function are observed when

changing the loads (dead and live loads). Assuming dramatic changes in the applied

loads, these will produce proportional changes in the probability of failure-cost function.

Examples of changes in the magnitude of the slope factors b for different loads are shown

in Figure 5.31. In this figure, the ordinates of the points remain constant because there is

no change in costs while the abscissas (probabilities of failure) change due to the change

in load. Similar to the sensitivity to costs, it is unlikely to have large changes in the

applied loads. Is design loads were to increase, these would require to redesign the

foundations and therefore vary completely the probability of failure-cost function.

Therefore it is not likely to generate large changes in the slope factor b. But if the loads

were to change significantly, the changes in the value of the slope factor b (i.e. from -

1352 to -704) would produce a small change in the log-log scaled FN chart compared

with the engineering precision or judgment when establishing the target probability of

failure. The change in probability of failure when changing the load can be also observed

by examining the factor of safety distribution. When decreasing the load, the mean value

of the factor of safety increases displacing the distribution away from 1.0 (F.S. = 1.0).

Page 126: TARGET LEVELS OF RELIABILITY FOR DESIGN OF BRIDGE

102

Therefore probability of failure, which is defined as the area under the distribution curve

to the left of F.S. = 1.0, decreases. This displacement is shown in Figure 5.32.

Figure 5.32 A increase in mean and spread of the pile group factor of safety distribution

(compare Figure 5.3) when decreasing load from 4000 kips to 3000 kips.

Decreasing the variability of the load (coefficient of variation) decreases the

probability of failure and therefore decreases the value of the slope factor b. The changes

in the probability of failure-cost functions are produced by displacing the points to lower

probability magnitudes (decrease in abscissas). An example of the change in function is

displayed in Figure 5.33. In this figure the coefficient of variation of the load decreases

by 50 percent (from 0.12 to 0.06). However the function or slope factor b is less sensitive

Pf5 piles = 1.52E-02 m5 piles = 1.40

5 piles = 0.21

Pf7 piles = 5.27E-06 m7 piles = 1.96

7 piles = 0.30

0.E+00

1.E+00

2.E+00

3.E+00

0 1 2 3 4 5

PD

F

Pile group, factor of safety

3.E-04

Page 127: TARGET LEVELS OF RELIABILITY FOR DESIGN OF BRIDGE

103

to this parameter than it is to costs and loads. Although the coefficient of variation of the

load decreased to 50 percent, slope factor b decreases only to about 70 percent.

The spread of the factor of safety distribution is narrowed when decreasing the load

coefficient of variation. This change can be observed by comparing Figure 5.34 with

Figure 5.3. A more narrow distribution will decrease the area under the curve that is left

to the factor of safety of 1.0.

Figure 5.33 Sensitivity of the probability of failure-cost function for pile group strength

limit state when varying the c.o.v. of the load from 0.12 (top) to 0.06 (bottom).

A = -1,352 ln(P) + 17,043

A = -934 ln(P) + 15,455

0

5,000

10,000

15,000

20,000

25,000

30,000

35,000

1E-08 1E-07 1E-06 1E-05 1E-04 1E-03 1E-02 1E-01 1E+00

Co

st p

ile g

rou

p, 5

0 f

t lo

ng

, d

olla

rs,

(A)

Probability of elastic failure, (P)

Page 128: TARGET LEVELS OF RELIABILITY FOR DESIGN OF BRIDGE

104

Figure 5.34 Decrease in mean and spread of the pile group factor of safety distribution

(compare Figure 5.3) when decreasing the c.o.v. of the load from 0.12 to 0.06.

Pf5 piles = 3.21E-01 m5 piles = 1.05

5 piles = 0.10

Pf7 piles = 3.21E-05 m7 piles = 1.47

7 piles = 0.14

0.E+00

1.E+00

2.E+00

3.E+00

4.E+00

5.E+00

0 1 2 3 4 5

PD

F

Pile group, factor of safety

3.E-04

Page 129: TARGET LEVELS OF RELIABILITY FOR DESIGN OF BRIDGE

105

5.3.2 Drilled Shafts - Sensitivity Analysis

Similar to pile groups, the cost per size of drilled shaft was observed to change the

probability of failure-cost function proportionally. The change in the function was

quantified through the change in value of the slope factor b. While the intrinsic values of

the probabilities of failure value were not affected by the change in cost, the ordinate

(cost) of each point that composes the function varied. An example is shown in Figure

5.35 where the slope factor b is reduced by 50 percent its value when decreasing the cost

(price) per drilled shaft length by 50 percent. The abscissas are the same for the

corresponding points of both functions.

Considering that drilled shaft prices were obtained from MoDOT’s pay reports,

these prices are considered reliable and are not expected to vary significantly. If the cost

were to change significantly, the changes of the slope factor b reported in Figure 5.35

from -17,067 to -8,533 will produce a small change in the log-log scaled FN chart. This

change is small compared to the engineering precision or judgment when establishing the

target probability of failure and to the differences generated when comparing to the

results of other foundation type functions.

The changes generated in the probability function due to the change in loads

(dead and live loads) are similar to the changes produced by costs. Figure 5.36 shows the

change in function due to the decreases in loads from 4000 kips to 3000 kips and to 2000

kips. In this figure, the ordinates (of the points) remain constant because there is no

change in costs while the abscissas (probability of failure) change due to the change in

load.

Page 130: TARGET LEVELS OF RELIABILITY FOR DESIGN OF BRIDGE

106

Figure 5.35 Decrease in slope of drilled shaft probability of strength failure function

when reducing the cost by 50 percent (bottom).

Figure 5.36 Change in the probability of failure-cost function for drilled shafts strength

limit state when varying the load from 4000 kips (top) to 3000 and 2000 kips (bottom).

A4000 = -17,067 ln(P) - 12,615

A3000 = -15,746ln(P) - 23,848

A2000 = -12,993ln(P) - 32,632

0

10,000

20,000

30,000

40,000

50,000

60,000

70,000

80,000

90,000

100,000

1E-06 1E-05 1E-04 1E-03 1E-02 1E-01 1E+00

Dril

led

sh

aft

cost

, d

olla

rs,

(A)

Probability of failure, (P)

A = -17,067 ln(P) - 12,615

A50% = -8,533ln(P) - 6,307

0

10,000

20,000

30,000

40,000

50,000

60,000

70,000

80,000

90,000

100,000

1E-06 1E-05 1E-04 1E-03 1E-02 1E-01 1E+00

Dril

led

sh

aft

cost

, d

olla

rs,

(A)

Probability of failure, (P)

Page 131: TARGET LEVELS OF RELIABILITY FOR DESIGN OF BRIDGE

107

Loads are not expected to change dramatically without changing the foundation

design and therefore the slope factor b, although sensitive to the changes in load, is not

expected to vary significantly. But if the loads were to change dramatically, the changes

in the value of the slope factor b (i.e. from -17,067 to -8,533) would produce a small

change in the log-log scaled FN chart.

The change in probability of failure when changing the load can be also observed

by examining the factor of safety distribution. When decreasing the load, the mean value

of the factor of safety increases displacing the distribution away from 1.0 (F.S. = 1.0).

Therefore probability of failure, which is defined as the area under the distribution curve

to the left of F.S. = 1.0, decreases. This displacement is shown in Figure 5.37 by

comparing to Figure 5.10.

Figure 5.37 Increase in mean and spread of the drilled shaft factor of safety distribution

(compare Figure 5.10) when decreasing load from 4000 kips to 3000 kips.

Pf3ft diam = 0.0548 m3ft diam = 4.02

3ft diam = 3.25

Pf5ft diam = 0.0064 m5ft diam = 7.52

3ft diam = 6.08

0.E+00

1.E-01

2.E-01

3.E-01

4.E-01

0 5 10

PD

F

60 ft drilled shafts, factor of safety

3.E-04

Page 132: TARGET LEVELS OF RELIABILITY FOR DESIGN OF BRIDGE

108

Decreasing the variability of the load (load coefficient of variation), decreases the

probability of failure, changes the function and therefore decreases the value of the slope

factor b. For pile groups, when decreasing the values of the probabilities of failure, the

points that defined the function were displaced to lower probability magnitudes (decrease

in abscissas). This change was not noticeable for drilled shafts as displayed in Figure

5.38. In this figure, although the coefficient of variation of the load decreased from 0.12

to 0.06 (50 percent decrease), there was a small change in the slope factors (from -17,067

to -16,867). To verify the sensitivity of the drilled shaft to the variability of loads, another

analysis was performed considering a mean load of 1000 kips instead of 4000 kips. The

results shown in Figure 5.39 confirm that probabilities of failure-cost functions for drilled

shafts are not sensitive to the variability of the loads.

The small variability of the drilled shaft probabilities of failure-cost functions

were also confirmed by comparing the distribution curves generated with different

variability of loads. Figure 5.40 shows the distribution curves for 3 and 5 foot diameter

drilled shafts for a load variability of 0.06. These curves are very similar to the

distribution curves generated for the load variability of 0.12 shown in Figure 5.10.

Page 133: TARGET LEVELS OF RELIABILITY FOR DESIGN OF BRIDGE

109

Figure 5.38 Sensitivity of the probability of failure-cost function for drilled shafts

strength limit state when varying the c.o.v. of the load from 0.12 (top) to 0.06 (bottom).

Figure 5.39 Change in the probability of failure-cost function due to change in load

coefficient of variation when load is reduces from 4000 kips to 1000 kips.

A12% = -17,067ln(P) - 12,615

A6% = -16,867ln(P) - 12,519

0

10,000

20,000

30,000

40,000

50,000

60,000

70,000

80,000

90,000

100,000

1E-06 1E-05 1E-04 1E-03 1E-02 1E-01 1E+00

Dril

led

sh

aft

cost

, d

olla

rs,

(A)

Probability of failure, (P)

A1000-12% = -8,734ln(P) - 36,202

A1000-6% = -8,613ln(P) - 36,121

0

10,000

20,000

30,000

40,000

50,000

60,000

70,000

80,000

90,000

100,000

1E-06 1E-05 1E-04 1E-03 1E-02 1E-01 1E+00

Dril

led

sh

aft

cost

, d

olla

rs,

(A)

Probability of failure, (P)

Page 134: TARGET LEVELS OF RELIABILITY FOR DESIGN OF BRIDGE

110

Figure 5.40 Increase in spread of the drilled shafts factor of safety distribution (compare

Figure 5.10) when decreasing load c.o.v. from 0.12 to 0.06.

5.3.3 Spread Footings - Sensitivity Analysis

For the case of spread footing, the probability of failure-cost function was also

observed to change in direct proportion to the ratio of change of the cost per area of

spread footing. This change was reported through the change in value of the slope factor

b. As for the previous two foundation types (pile groups and drilled shafts) the intrinsic

values of the probabilities of failure value were not affected by the change in cost.

However the ordinate (cost) of each point that composes the function varied by showing

displacement. An example of the displacement of these points and change in function is

shown in Figure 5.41 where the slope factor b is reduced to 50 percent its value when

decreasing the cost (price) per square foot of spread footing to 50 percent of the initially

Pf3ft diam = 0.1131 m3ft diam = 3.01

3ft diam = 2.42

Pf5ft diam = 0.0179 m5ft diam = 5.64

3ft diam = 4.52

0.E+00

1.E-01

2.E-01

3.E-01

4.E-01

0 5 10

PD

F

60 ft drilled shafts, factor of safety

3.E-04

Page 135: TARGET LEVELS OF RELIABILITY FOR DESIGN OF BRIDGE

111

assumed cost. It is important to notice that in this figure, the abscissas are the same for

the corresponding points of both functions.

Although the slope factors b changes significantly in Figure 5.41, the cost per area

of a spread footing is not expected to suffer major changes as the cost was established

from MoDOT’s pay reports. If the cost were to change by 50 percent, the difference

between slope factor b values (approximately b=-4,500) would generate still a minor

change in the target reliability (economic curves) reported in the log-log scales FN chart

as will be seen in the next chapter. Furthermore, this change will be within the range of

curves generated by the different types of bridge foundations.

Figure 5.41 Decrease in slope of the spread footing probability of strength failure

function when reducing the cost to 50 percent (bottom).

A = -8,989ln(P) - 17,552

A1/2 cost = -4,494ln(P) - 8,776

0

20,000

40,000

60,000

80,000

100,000

120,000

1E-07 1E-06 1E-05 1E-04 1E-03 1E-02 1E-01 1E+00

Co

st s

pre

ad

foo

ting

, d

olla

rs,

(A)

Probability of failure, (P)

Page 136: TARGET LEVELS OF RELIABILITY FOR DESIGN OF BRIDGE

112

Figure 5.42 Change in the probability of failure-cost function for spread footing strength

limit state when varying the load from 4000 kips (top) to 3000 and 2000 kips (bottom).

Similar changes in the probability of failure-cost function are observed when

changing the magnitudes of loads (Figure 5.42). The decrease in load to 50 percent of the

initial has approximately the same effect on the slope factor b values as the change in

cost. Therefore the change in the values of the slope factor b generated by the change in

load would cause a in the location of the curve in the FN chart that will also fall within

the overall range of curves generated by the different foundation type.

The magnitude of the change in the probabilities of failure due to the decrease in

load can be visualized through the distribution curves displayed in Figure 5.43 and

compare with the distribution curves displayed in Figure 5.17. By decreasing the loads,

A4000kip = -8,989ln(P) - 17,552

A3000kip = -5,657ln(P) - 8,541

A2000kip = -4,813ln(P) - 12,585

0

20,000

40,000

60,000

80,000

100,000

120,000

1E-07 1E-06 1E-05 1E-04 1E-03 1E-02 1E-01 1E+00

Co

st s

pre

ad

foo

ting

, d

olla

rs,

(A)

Probability of failure, (P)

Page 137: TARGET LEVELS OF RELIABILITY FOR DESIGN OF BRIDGE

113

the values of the mean factors of safety of the distribution drift the distributions away

from the factor of safety of 1.0 decreasing the probability of failure.

The variability of the loads does not affect significantly the probability of failure-

cost function of spread footings. An example of the sensitivity of the function to the

variability of the loads is shown in Figure 5.44. The change in variability of the load

changes the spread of the factor of safety distribution. Decreasing the variability from

0.12 to 0.06 decreases the factor of safety distribution curves displayed in Figure 5.45.

This change is better observed when comparing the distribution curves of Figure 5.45

with the distribution curves of Figure 5.17.

Figure 5.43 Decrease in mean and spread of the spread footing factor of safety

distribution (compare Figure 5.17) when decreasing load from 4000 kips to 3000 kips.

Pf25 ft2 = 0.3372 m25 ft2 = 1.74

25 ft2 = 1.41

Pf49 ft2 = 0.0853 m49 ft2 = 3.41

49 ft2 = 2.76

0.E+00

2.E-01

4.E-01

6.E-01

0 1 2 3 4 5 6 7 8 9 10

PD

F

Spread footing, factor of safety

3.E-04

Page 138: TARGET LEVELS OF RELIABILITY FOR DESIGN OF BRIDGE

114

Figure 5.44 Probability of failure-cost function for spread footing strength limit when

varying the load (4000 to 2000 kips) c.o.v. of the load from 0.12 (top) to 0.06 (bottom).

Figure 5.45 Decrease in mean and spread of the spread footing factor of safety

distribution (compare Figure 5.17) when decreasing load c.o.v. from 0.12 to 0.06

ACOV=12% = -8,989ln(P) - 17,552

ACOV=6% = -8,879ln(x) - 17,482

0

20,000

40,000

60,000

80,000

100,000

120,000

1E-07 1E-06 1E-05 1E-04 1E-03 1E-02 1E-01 1E+00

Co

st s

pre

ad

foo

ting

, d

olla

rs,

(A)

Probability of failure, (P)

Pf25 ft2 = 0.4920 m25 ft2 = 1.31

25 ft2 = 1.05

Pf49 ft2 = 0.1635 m49 ft2 = 2.56

49 ft2 = 2.06

0.E+00

2.E-01

4.E-01

6.E-01

8.E-01

0 1 2 3 4 5 6 7 8 9 10

PD

F

Spread footing, factor of safety

3.E-04

Page 139: TARGET LEVELS OF RELIABILITY FOR DESIGN OF BRIDGE

115

5.3.4 Approach Embankments - Sensitivity Analysis

The results of the cost sensitivity analysis performed to embankments were

similar to the analyses performed for bridge foundations in which by changing the cost,

the probability of failure-cost function varied directly and in the same proportion as the

change in cost. The changes occur by vertically relocating the points that define the

probability of failure-cost function to a location in agreement with the change in cost

(Figure 5.36). In the example shown in Figure 5.46, the relocation of the points that

define the original function occurred by reducing the values of the ordinates (cost) by 50

percent of its original value.

The change in slope factor b reported in Figure 5.46 (b = -206) produces a small

change in the location of the economic curve in the log-log scaled FN chart. Regardless

of the magnitude of change, this slope factor b value produces an economic curve that

falls on a conservative region of the chart as will be shown in Chapter 5.

Another sensitivity analysis was performed considering the variable undrained

shear strength, Su. The results of this analysis show that the probability of failure-cost

function is sensitive to this variable as it causes direct changes to the function slope

although the change is not in the same proportion as the change in the variable. In Figure

5.47, when decreasing the strength of the soil (undrained shear strength) from 4000 psf to

2000 psf, the points that define the new function are shifted to larger probabilities of

failure values (increase in the abscissas). In this case, although the strength of the soil

decreased by 50 percent, the change in the slope factor b value is small and this will

produce a very small change in the location of the economic curve in the log-log scaled

FN chart.

Page 140: TARGET LEVELS OF RELIABILITY FOR DESIGN OF BRIDGE

116

Figure 5.46 Decrease in slope of the embankment probability of strength failure function

when reducing the cost by 50 percent (bottom)

Figure 5.47 Change in the probability of failure-cost function for spread footing strength

limit state when varying the load from 4000 psf (left) to 2000 psf (right).

A = -412ln(P) + 2,823

A50%cost = -206ln(P) + 1,411

0

2,000

4,000

6,000

8,000

10,000

12,000

1E-06 1E-05 1E-04 1E-03 1E-02 1E-01 1E+00

Co

st o

f fil

l a

nd

ge

ofo

am

em

ab

an

kme

nt,

do

llars

, (A

)

Probability of failure, (P)

ASu=4000psf = -412ln(P) + 2,823

ASu=2000psf = -544ln(x) + 3,464

0

2,000

4,000

6,000

8,000

10,000

12,000

1E-06 1E-05 1E-04 1E-03 1E-02 1E-01 1E+00

Co

st o

f fil

l a

nd

ge

ofo

am

em

ab

an

kme

nt,

do

llars

, (A

)

Probability of failure, (P)

Page 141: TARGET LEVELS OF RELIABILITY FOR DESIGN OF BRIDGE

117

The increase in the probability of failure is also displayed in Figure 5.48 where

the mean values of the distribution curves are displaced to lower factor of safety values.

This displacement is observed when comparing Figure 5.48 with Figure 5.24 in which the

undrained shear strength of the soil is 4000 psf and 2000 psf respectively. The

displacement of the distribution towards lower values of factor of safety increases the

areas under the curves that are lower than the limit factor of safety of 1.0 (F.S.=1.0)

Figure 5.48 Decrease in mean and spread of the embankment factor of safety distribution

(compare Figure 5.24) when decreasing load from 4000 kips to 3000 kips

Pfgeo=20ft = 0.0485 mgeo=20ft = 4.12

geo=20ft = 3.30

Pfgeo=24ft = 0.0250 mgeo=24ft = 5.11

geo=24ft = 4.10

0.E+00

1.E-01

2.E-01

3.E-01

0 5 10 15 20 25 30

PD

F

40 ft embankment, factor of safety

3.E-04

Page 142: TARGET LEVELS OF RELIABILITY FOR DESIGN OF BRIDGE

118

5.4 Summary

The establishment of the target probabilities of failure for the design of

geotechnical infrastructures from an economic perspective requires identifying and

understanding the relation (function) between the probability of failure of the

infrastructure and its cost. In this chapter, several functions were developed and presented

graphically for pile groups, drilled shafts, spread footings and approach embankments.

The relationship between the probabilities of failure and the costs were

established with the use of reliability analyses (Taylor Series Method).

The slope factor b of the probability of failure-cost function is described in this

chapter as an essential parameter to define, understand and compare functions. This

parameter is defined as the required cost to decrease the probability of failure by one

order of magnitude.

The slope factor b values established in this chapter for bridge foundations and

embankments were developed for the probability of exceeding the capacity (strength

limit state) and for the probability of exceeding the service limits established in Chapter

3. A summary of the slope factor b values are presented in Table 5.5 while the overall

slope factors b are presented in Table 5.6.

Page 143: TARGET LEVELS OF RELIABILITY FOR DESIGN OF BRIDGE

119

Table 5.5 Slope factors b for foundations and embankments considering strength and

service limits

Table 5.6 Upper and lower range values of the slope factors b for bridge foundations

Classification Piles Shafts Footing Embankments

Strength -1,352 -17,067 -8,989 -412

Serv A -12,581 -41,526 -47,701 -120

Serv B -6,996 -34,873 -31,373 -256

Serv C -2,553 -23,703 -17,277 -491

Classification

Strength -1,352 -17,067

Serv A -12,581 -41,526

Serv B -6,996 -34,873

Serv C -2,553 -23,703

Foundation Range

Page 144: TARGET LEVELS OF RELIABILITY FOR DESIGN OF BRIDGE

120

Sensitivity analysis was performed on the probability of failure-cost function. The

changes in the function were quantified through the change in the values of the slope

factor b. This chapter presented graphs and comments of the impact on the function

produced by the changes in the values of parameters such as costs, loads and soil

strength.

Results of the sensitivity analysis showed that the impact due to changes of

parameter values on the function were consistent for all foundation types and

embankments. The sensitivity analyses showed that (1) the changes in the log-log scaled

FN chart were small compared to the engineering precision or judgment when

establishing the target probability of failure and (2) the changes in the slope factors b fall

within the overall range of economic curves generated by the different foundation types.

The results of the sensitivity analyses for foundations are summarized in Table 5.7 while

Table 5.8 summarizes results of the sensitivity analysis performed on embankments.

Page 145: TARGET LEVELS OF RELIABILITY FOR DESIGN OF BRIDGE

121

Table 5.7 Change in foundation slope factor b values due to sensitivity analysis when

reducing costs, loads and c.o.v. of design parameters by 50 percent of their original value

Table 5.8 Change in embankment slope factor b values due to sensitivity analysis when

reducing costs, and soil strength parameters by 50 percent of their original value

Variable

Cost -412 -206

Su -412 -544

Embankments

Variable

Cost -1,352 -676 -17,067 -8,533 -8,989 -4,494

Load -1,352 -704 -17,067 -12,993 -8,989 -4,813

Load COV -1,352 -934 -17,067 -16,867 -8,989 -8,879

Pile Groups Drilled Shafts Spread Footing

Page 146: TARGET LEVELS OF RELIABILITY FOR DESIGN OF BRIDGE

122

6 DEVELOPMENT, ANALYSIS AND CALIBRATION OF

ECONOMIC CURVES

6.1 Introduction

In this chapter, the FN charts are developed with information obtained from the

probability of failure-cost functions developed in Chapter 5. The FN economic curves

that identify the optimum probability of failure for the design of bridge foundations and

approach embankments from an economic perspective are compared with the socially

acceptable risk. Comments on the results along with recommended target probability of

failure (or target reliabilities) are presented in accompanying tables.

6.2 FN Charts and Economic Curves

In the previous chapter, functions that relate the probability of failure and the cost

of bridge foundations and approach embankments were established with the use of

probability analysis. These functions along with the expected monetary value concept

allowed developing an equation to calculate the optimum probabilities of failure as a

function of the cost of failure (consequence costs) of bridges and approach embankments

(Figure 3.6). Points of optimum probabilities and their respective consequence cost are to

be plotted on FN charts.

FN charts are graphical representations of socially acceptability for the loss of

lives. The FN curves proposed by world government safety agencies on FN charts are

boundaries that define regions or levels of risk depending on the acceptability of society.

Page 147: TARGET LEVELS OF RELIABILITY FOR DESIGN OF BRIDGE

123

They are not curves that define the economically optimum acceptability of risk. However,

it is in this chart of regions of social acceptability that the optimum economical curves

are plotted. These optimal economic curves do not define regions of economic

acceptability. These curves represent a family of points of probabilities that are

economically optimum for different levels of consequence. Considering that economic

curves are dependent on the same parameters as socially acceptability (i.e. consequence

(X) and probability of failure (P)), they will be plotted on FN charts overlapping the

socially acceptance regions.

6.2.1 Pile Group FN Charts

The FN charts for pile groups were developed for the probability of exceeding the

capacity (strength limit state) and for the probability of exceeding the service limits

established in Chapter 4. These results were developed considering the assumptions listed

the section 5.2.3.1.

The economic curve displayed in Figure 6.1 for strength limit is located near the

ANCOLD and Hong Kong boundary for acceptable risk acceptance. The curve falls

within the region of social acceptability for civil works defined by Baecher and Christian

(2003). The economic curve displayed in Figure 6.2 for service limit A (3-inch

settlement) is located above the ANCOLD and Hong Kong boundaries were risk is

unacceptable. However, the curve still falls within the region of civil work acceptability.

The economic curve displayed in Figure 6.3 for service limit B (5-inch settlement) is also

located above but closer to the ANCOLD and Hong Kong boundaries were risk is

unacceptable. This curve also falls within the region of civil work acceptably.

Page 148: TARGET LEVELS OF RELIABILITY FOR DESIGN OF BRIDGE

124

Figure 6.1 FN chart for pile group strength limit.

Figure 6.2 FN chart for pile group service limit A.

Page 149: TARGET LEVELS OF RELIABILITY FOR DESIGN OF BRIDGE

125

Figure 6.3 FN chart for pile group service limit B.

Figure 6.4 FN chart for pile group service limit C.

Page 150: TARGET LEVELS OF RELIABILITY FOR DESIGN OF BRIDGE

126

The economic curve displayed in Figure 6.4 for service limit C (17-inch

settlement) is also located above but closer to the service limits of less settlement to the

ANCOLD and Hong Kong boundaries were risk is unacceptable. This curve also falls

within the region of civil work acceptably.

As the magnitudes of settlement of service limits increase, the location of their

economic curves approaches the location of the economic curve for strength limit or

collapse. Therefore as the magnitudes of settlement of a bridge increase, the target

probability of failure level approaches that of collapse.

6.2.2 Drilled Shafts FN Charts

The FN charts for drilled shafts were developed for the probability of exceeding

the capacity (strength limit state) and for the probability of exceeding the service limits

established in Chapter 4. These results were developed considering the assumptions listed

the section 5.2.4.1.

The economic curve displayed in Figure 6.5 for strength limit is located above the

ANCOLD and Hong Kong boundary for risk acceptance. The curve falls within the

region of social acceptability for civil works. The economic curve displayed in Figure 6.6

for service limit A (3-inch settlement) is located above the ANCOLD and Hong Kong

boundaries were risk is socially unacceptable. However, the curve still falls within the

region of civil work acceptability. The economic curve displayed in Figure 6.7 for service

limit B (5-inch settlement) is also located above but closer to the strength limit state

economic curve. This curve also falls within the region of civil work acceptably.

Page 151: TARGET LEVELS OF RELIABILITY FOR DESIGN OF BRIDGE

127

Figure 6.5 FN chart for drilled shaft strength limit state.

Figure 6.6 FN chart for drilled shaft service limit A.

Page 152: TARGET LEVELS OF RELIABILITY FOR DESIGN OF BRIDGE

128

Figure 6.7 FN chart for drilled shaft service limit B.

Figure 6.8 FN chart for drilled shaft service limit C.

Page 153: TARGET LEVELS OF RELIABILITY FOR DESIGN OF BRIDGE

129

The economic curve displayed in Figure 6.8 for service limit C (17-inch

settlement) is also located above but closer to the service limits of less settlement to the

ANCOLD and Hong Kong boundaries. This curve also falls within the region of civil

work acceptably. Therefore, as the magnitudes of settlement of a bridge increase, the

target probability of failure level approaches that of collapse.

In general, the economic curves of drilled shafts are located at higher risk levels

than pile group economic curves. Drilled shafts slope factors b are larger in magnitude

than pile group factors therefore it is more costly to decrease the probability of failure of

drilled shafts. The target level of probability of failure for the design of drilled shafts

from an economic perspective is larger than for pile groups.

6.2.3 Spread Footing FN Charts

The FN charts for spread footing were developed for the probability of exceeding

the capacity (strength limit state) and for the probability of exceeding the service limits

established in Chapter 3. These results were developed considering the assumptions listed

the section 5.2.5.1.

The economic curve displayed in Figure 6.9 for strength limit is located above the

ANCOLD and Hong Kong boundary for risk acceptance. The curve falls within the

region of social acceptability for civil works. The economic curve displayed in Figure

6.10 for service limit A (3-inch settlement) is located above the ANCOLD and Hong

Kong boundaries were risk is socially unacceptable. However, the curve still falls within

the region of civil work acceptability.

Page 154: TARGET LEVELS OF RELIABILITY FOR DESIGN OF BRIDGE

130

Figure 6.9 FN chart for spread footing strength limit state.

Figure 6.10 FN chart for spread footing service limit A.

Page 155: TARGET LEVELS OF RELIABILITY FOR DESIGN OF BRIDGE

131

Figure 6.11 FN chart for spread footing service limit B.

Figure 6.12 FN chart for spread footing service limit C.

Page 156: TARGET LEVELS OF RELIABILITY FOR DESIGN OF BRIDGE

132

The economic curve displayed in Figure 6.11 for service limit B (5-inch

settlement) is also located above but closer to the strength limit state economic curve.

This curve also falls within the region of civil work acceptably. The economic curve

displayed in Figure 6.12 for service limit C (17-inch settlement) is also located above but

closer to the service limits of less settlement to the ANCOLD and Hong Kong boundaries

were risk is unacceptable. This curve also falls within the region of civil work acceptably.

As the magnitudes of settlement of a bridge increase, the target probability of failure

level approaches that of collapse.

In general, the economic curves of drilled shafts are located at higher probability

levels than pile group economic curves. Spread footing slope factors b are larger in

magnitude than pile group factors therefore it is more costly to decrease the probability of

failure of spread footing. The target level of probability of failure for the design of spread

footing from an economic perspective is larger than for pile groups.

6.2.4 Bridge Approach Embankment FN Charts

The FN charts for bridge approach embankments were developed for the

probability of exceeding the capacity (strength limit state) and for the probability of

exceeding the service limits established in Chapter 3. These results were developed

considering the assumptions listed the section 5.2.6.1.

The economic curve displayed in Figure 6.13 for strength limit is located below

the ANCOLD and Hong Kong boundary for risk acceptance. The curve falls within the

region of social acceptability of ANCOLD, Hong Kong and civil works.

Page 157: TARGET LEVELS OF RELIABILITY FOR DESIGN OF BRIDGE

133

Figure 6.13 FN chart for approach embankment strength limit state.

Figure 6.14 FN chart for approach embankment service limit A.

Page 158: TARGET LEVELS OF RELIABILITY FOR DESIGN OF BRIDGE

134

Figure 6.15 FN chart for approach embankment service limit B.

Figure 6.16 FN chart for approach embankment service limit C.

Page 159: TARGET LEVELS OF RELIABILITY FOR DESIGN OF BRIDGE

135

The economic curve displayed in Figure 6.14 for service limit A (3-inch

settlement) is located below the ANCOLD and Hong Kong boundaries were risk is

socially acceptable. In addition the curve also falls within the region of civil work

acceptability. The economic curve displayed in Figure 6.15 for service limit B (5-inch

settlement) is below the strength limit state economic curve and below the ANCOLD and

Hong Kong risk boundaries. The curve also falls within the region of civil work

acceptably. The economic curve displayed in Figure 6.16 for service limit C (17-inch

settlement) is also located below the strength limit and closer to the ANCOLD and Hong

Kong boundaries. This curve also falls within the region of civil work acceptably.

Approach embankment economic curves are located at risk levels below bridge

foundation (pile group, drilled shaft and spread footings) economic curves. Therefore the

cost of trying to decrease the probability of failure of embankments is lower than to

decrease the probability of failure of the bridge foundations. The target probability of

failure of approach embankments is lower than for bridge foundations. Economically, it

is worth designing approach embankments at high risk of failure or unsatisfactory

performance because the low consequence cost (cheep fix). From an economic

perspective, the target levels of probability of failure for approach embankments for both

strength and service limits are lower than the target levels of probabilities of failure for

bridge foundations.

Page 160: TARGET LEVELS OF RELIABILITY FOR DESIGN OF BRIDGE

136

6.3 FN charts from Sensitivity Analysis

The bridge foundations and approach embankment economic curves shown in the

previous section were developed considering assumed mean and coefficient of variation

values for their design parameters. This section will address the impact (sensitivity) on

the location of the strength limit state economic curves on FN charts when varying

selected bridge foundation and approach embankment parameters.

The design parameter values used to develop probability of failure-cost functions

were obtained from the literature while the costs of material were estimated based on the

Missouri Department of Transportation (MoDOT) 2010 pay reports. The probability of

failure-costs functions were observed to change when varying the values of the design

variables. These changes were evaluated through the changes produced on the values of

the slope factor b of each function. Description of the changes are found in section 5.3

while summary of slope factors b are reported in tables shown in section 5.4 of Chapter 4.

The changes in the probability of failure-cost functions when performing the

sensitivity analysis produced changes in the expected monetary value equations which

produced changes in the values of the optimum probabilities of failure (Popt). The

changes in the values of the optimum probabilities of failure produced different economic

curves on the FN charts. In the case of pile groups, a decrease in unit cost to 50 percent

(Figure 6.17) resulted in a small displacement of the economic curve towards smaller

probabilities of failure. Similar behavior was observed when decreasing the magnitude of

load to 50 percent of the assumed value (Figure 6.18). Less sensitivity was observed

when decreasing the coefficient of variation of the load to 50 percent (Figure 6.19).

Page 161: TARGET LEVELS OF RELIABILITY FOR DESIGN OF BRIDGE

137

Figure 6.17 Pile group economic curve sensitivity to 50 percent change (decrease) in

cost.

Figure 6.18 Pile group economic curve sensitivity to 50 percent change in load.

1E-08

1E-07

1E-06

1E-05

1E-04

1E-03

1E-02

1E-01

1E+00

1E+4 1E+5 1E+6 1E+7 1E+8 1E+9 1E+10 1E+11 1E+12

Pro

b o

f fa

ilure

pe

r ye

ar (

Po

ptim

um

)

Failure/repair cost, dollars (X)

covCOST = 0.50

Fatalities, N10-2 10-1 100 10+1 10+2 10+3 10+4 10+5 10+6

Foundations

Dams

Commercial

Aviation

Mine

PitSlopes

Estimated US Dams

1E-08

1E-07

1E-06

1E-05

1E-04

1E-03

1E-02

1E-01

1E+00

1E+4 1E+5 1E+6 1E+7 1E+8 1E+9 1E+10 1E+11 1E+12

Pro

b o

f fa

ilure

pe

r ye

ar (

Po

ptim

um

)

Failure/repair cost, dollars (X)

covLOAD = 0.50

Fatalities, N10-2 10-1 100 10+1 10+2 10+3 10+4 10+5 10+6

Foundations

Dams

Commercial

Aviation

Mine

PitSlopes

Estimated US Dams

Page 162: TARGET LEVELS OF RELIABILITY FOR DESIGN OF BRIDGE

138

Figure 6.19 Pile group economic curve sensitivity to 50 percent change in load cov.

In the case of drilled shafts, a small displacement of the economic curve towards

smaller probabilities of failure also occurred when decreasing the price or unit cost of

shaft to 50 percent (Figure 6.20) of its original value. However, when decreasing the load

to 50 percent, drilled shafts showed to be less sensitive to change than pile groups (Figure

6.21). A similar behavior was observed when decreasing the variability of the load to 50

percent its original value (c.o.v. from 0.12 to 0.06). The impact is observed in Figure 6.22

where the modified economic curve overlaps the original economic curve showing

evidence of no sensitivity to the decrease in variability of the loads.

1E-08

1E-07

1E-06

1E-05

1E-04

1E-03

1E-02

1E-01

1E+00

1E+4 1E+5 1E+6 1E+7 1E+8 1E+9 1E+10 1E+11 1E+12

Pro

b o

f fa

ilure

pe

r ye

ar (

Po

ptim

um

)

Failure/repair cost, dollars (X)

covLOAD COV = 0.50

Fatalities, N10-2 10-1 100 10+1 10+2 10+3 10+4 10+5 10+6

Foundations

Dams

Commercial

Aviation

Mine

PitSlopes

Estimated US Dams

Page 163: TARGET LEVELS OF RELIABILITY FOR DESIGN OF BRIDGE

139

Figure 6.20 Drilled shaft economic curve sensitivity to 50 percent change (decrease) in

cost.

Figure 6.21 Drilled shaft economic curve sensitivity to 50 percent change in load.

1E-08

1E-07

1E-06

1E-05

1E-04

1E-03

1E-02

1E-01

1E+00

1E+4 1E+5 1E+6 1E+7 1E+8 1E+9 1E+10 1E+11 1E+12

Pro

b o

f fa

ilure

pe

r ye

ar (

Po

ptim

um

)

Failure/repair cost, dollars (X)

covLOAD = 0.50

Fatalities, N10-2 10-1 100 10+1 10+2 10+3 10+4 10+5 10+6

Foundations

Dams

Commercial

Aviation

Mine

PitSlopes

Estimated US Dams

1E-08

1E-07

1E-06

1E-05

1E-04

1E-03

1E-02

1E-01

1E+00

1E+4 1E+5 1E+6 1E+7 1E+8 1E+9 1E+10 1E+11 1E+12

Pro

b o

f fa

ilure

pe

r ye

ar (

Po

ptim

um

)

Failure/repair cost, dollars (X)

covCOST = 0.50

Fatalities, N10-2 10-1 100 10+1 10+2 10+3 10+4 10+5 10+6

Foundations

Dams

Commercial

Aviation

Mine

PitSlopes

Estimated US Dams

Page 164: TARGET LEVELS OF RELIABILITY FOR DESIGN OF BRIDGE

140

Figure 6.22 Drilled shaft economic curve sensitivity to 50 percent change in load cov.

Spread footing economic curves exhibit displacements when decreasing the unit

price or cost to 50 percent of its original value (Figure 6.23). The magnitude of

displacement shows that the economic curve is sensitive to the change in load. However

the magnitude of change in cost to produce the displacement is not likely to occur. Spread

footings economic curves also show evidence of being sensitive to change in load (Figure

6.24). However the change in loading that would produce the magnitude of displacement

shown in Figure 6.24 would have probably required a different foundation design that

would produce less or no displacement of the economic curve. The overlap of economic

curves shown in Figure 6.25 shows that spread footings are not sensitive to changes in the

variability of the load.

1E-08

1E-07

1E-06

1E-05

1E-04

1E-03

1E-02

1E-01

1E+00

1E+4 1E+5 1E+6 1E+7 1E+8 1E+9 1E+10 1E+11 1E+12

Pro

b o

f fa

ilure

pe

r ye

ar (

Po

ptim

um

)

Failure/repair cost, dollars (X)

covLOAD COV = 0.50

Fatalities, N10-2 10-1 100 10+1 10+2 10+3 10+4 10+5 10+6

Foundations

Dams

Commercial

Aviation

Mine

PitSlopes

Estimated US Dams

Page 165: TARGET LEVELS OF RELIABILITY FOR DESIGN OF BRIDGE

141

.

Figure 6.23 Spread footing economic curve sensitivity to 50 percent change (decrease) in

cost.

Figure 6.24 Spread footing economic curve sensitivity to 50 percent change in load.

1E-08

1E-07

1E-06

1E-05

1E-04

1E-03

1E-02

1E-01

1E+00

1E+4 1E+5 1E+6 1E+7 1E+8 1E+9 1E+10 1E+11 1E+12

Pro

b o

f fa

ilure

pe

r ye

ar (

Po

ptim

um

)

Failure/repair cost, dollars (X)

covCOST = 0.50

Fatalities, N10-2 10-1 100 10+1 10+2 10+3 10+4 10+5 10+6

Foundations

Dams

Commercial

Aviation

Mine

PitSlopes

Estimated US Dams

1E-08

1E-07

1E-06

1E-05

1E-04

1E-03

1E-02

1E-01

1E+00

1E+4 1E+5 1E+6 1E+7 1E+8 1E+9 1E+10 1E+11 1E+12

Pro

b o

f fa

ilure

pe

r ye

ar (

Po

ptim

um

)

Failure/repair cost, dollars (X)

covLOAD = 0.50

Fatalities, N10-2 10-1 100 10+1 10+2 10+3 10+4 10+5 10+6

Foundations

Dams

Commercial

Aviation

Mine

PitSlopes

Estimated US Dams

Page 166: TARGET LEVELS OF RELIABILITY FOR DESIGN OF BRIDGE

142

Figure 6.25 Spread footing economic curve sensitivity to 50 percent change in load cov.

The behavior due to change in cost of the approach embankments economic curve

is similar to those of bridge foundations (Figure 6.26). The change in cost affects directly

the value of the slope factor b. The location of the economic curve in the FN chart

depends on magnitudes of the optimum probability, Popt (which depends on the slope

factor b) and the consequences of failure cost, X (Figure 3.6). If the numerical magnitude

of cost would change dramatically (for example if using a different currency), then the

economic curve would shift towards the right or left of the original economic curve

depending on if there is an increase or decrease of the costs respectively. In this case, the

target probabilities value would not change. The change will be of the range of interest of

the consequence cost, X in the FN chart will shift to the right or to the left along with the

horizontal displacement of the economic curve.

Approach embankments are less sensitive to change in soil strength (Figure 6.27).

1E-08

1E-07

1E-06

1E-05

1E-04

1E-03

1E-02

1E-01

1E+00

1E+4 1E+5 1E+6 1E+7 1E+8 1E+9 1E+10 1E+11 1E+12

Pro

b o

f fa

ilure

pe

r ye

ar (

Po

ptim

um

)

Failure/repair cost, dollars (X)

covLOAD COV = 0.50

Fatalities, N10-2 10-1 100 10+1 10+2 10+3 10+4 10+5 10+6

Foundations

Dams

Commercial

Aviation

Mine

PitSlopes

Estimated US Dams

Page 167: TARGET LEVELS OF RELIABILITY FOR DESIGN OF BRIDGE

143

Figure 6.26 Approach embankment economic curve sensitivity to 50 percent change

(decrease) in cost.

Figure 6.27 Approach embankment economic curve sensitivity to 50 percent change in

undrained shear strength Su.

1E-08

1E-07

1E-06

1E-05

1E-04

1E-03

1E-02

1E-01

1E+00

1E+4 1E+5 1E+6 1E+7 1E+8 1E+9 1E+10 1E+11 1E+12

Pro

b o

f fa

ilure

pe

r ye

ar (

Po

ptim

um

)

Failure/repair cost, dollars (X)

covCOST = 0.50

Fatalities, N10-2 10-1 100 10+1 10+2 10+3 10+4 10+5 10+6

Foundations

Dams

Commercial

Aviation

Mine

PitSlopes

Estimated US Dams

1E-08

1E-07

1E-06

1E-05

1E-04

1E-03

1E-02

1E-01

1E+00

1E+4 1E+5 1E+6 1E+7 1E+8 1E+9 1E+10 1E+11 1E+12

Pro

b o

f fa

ilure

pe

r ye

ar (

Po

ptim

um

)

Failure/repair cost, dollars (X)

covSu = 0.50

Fatalities, N10-2 10-1 100 10+1 10+2 10+3 10+4 10+5 10+6

Foundations

Dams

Commercial

Aviation

Mine

PitSlopes

Estimated US Dams

Page 168: TARGET LEVELS OF RELIABILITY FOR DESIGN OF BRIDGE

144

6.4 Suggested Target Levels of Probabilities of Failure

Two steps are required to establish the suggested levels of probabilities of failure

for the design of bridge foundations and approach embankments. The first step is to

identify and plot the lateral (left and right) boundaries of risk for strength and service

limits for foundations (as a group) and embankments. The second step is to identify the

range of consequence cost for each bridge type and assign a probability of failure value

for each range of consequence.

Missouri bridges are classified in four groups or bridge types. There are two

major bridge types subdivided in those that exceed or not exceed 100 million dollars.

Then there is a third bridge type with bridges valued over 5 million dollars on major

roads and finally a forth bridge type with values of about one million dollars on minor

roads.

In section 5.2 of Chapter 5, the cost of consequence of bridge failure or

unacceptable performance was shown to be correlated to the initial cost of bridges. This

correlation is shown for example in Figure 5.4. The ranges of consequence cost are

established by identifying the consequence cost in Figure 5.4 when knowing the initial

cost ranges of Missouri bridges.

The lateral economic curves boundaries for strength and service limits for

foundations were developed using the slope factor b ranges shown in Table 5.6. There are

no lateral boundaries for embankments because only one “stability” method was

analyzed. Economic curves for strength and service limits for embankments were

developed using the slope factor b ranges shown in Table 5.5.

Page 169: TARGET LEVELS OF RELIABILITY FOR DESIGN OF BRIDGE

145

Engineering judgment is used to establish the suggested design probabilities of

failure within the intersection of the range of consequence costs and the lateral economic

curve boundaries. Figure 6.28 shows that suggested design probabilities of failure for

foundation strength limit state which is shown as a step function descending within the

economic curve boundaries.

The suggested design probability of failure for bridge foundations considering

service limit A (approximately 3 inch settlement) is identified in Figure 6.29 as a

horizontal line. This line falls to the left of the range of lateral economic curve range. The

suggested design probability of failure identified by the horizontal line is 4 percent or 1 in

25 bridges. The line is horizontal because the cost of repairing 3-inch settlements

(consequence cost) is almost constant regardless of the size (initial cost) of Missouri

bridges (Figure 4.4).

The optimum probability of failure for design is approximately 1 in 5 or 1 in 10

bridges. However, the horizontal line was located conservatively below the economic

curve range because of logistics and political reasons. A frequency of failure larger than 1

in 25 would probably require an increase in personnel and equipment to constantly search

and repair settlements. It could be considered a political decision because having more

than 1 in 25 bridges settle 3 inches could diminish the image and trust of the DOT. It

would also decrease the speed of travel producing a social impact difficult to quantify.

The suggested probability of failure for foundation service limit B (approximately

5 or 6 inches of settlement) was established by a step function located conservatively

below the economic curve range shown in Figure 6.30.

Page 170: TARGET LEVELS OF RELIABILITY FOR DESIGN OF BRIDGE

146

Figure 6.28 Suggested foundation probabilities of failure for strength limit state.

Figure 6.29 Suggested foundation probabilities of failure for service limit state A.

Page 171: TARGET LEVELS OF RELIABILITY FOR DESIGN OF BRIDGE

147

The step function was located conservatively below the economic curve range for

the same logistical and political reasons considered for service limit A. Although the step

function could be located closer to the true economic curve because of the smaller true

optimum probability of failure values that result in the consequence range (approximately

1 in 100), the social (political) impact of having 5 or 6-inch settlement in a bridge pier

would be too important.

The graphical representation of the suggested probabilities of failure for

foundation service limit C is shown in Figure 6.31. The step function was established

within the range between the lateral economic curve boundaries. Considering the low true

optimum probabilities of failure within the range of consequence, there was no need to

locate the probability step function conservatively below the economic curve range.

However within the economic curve range, the probability step function is located on the

conservative side.

Page 172: TARGET LEVELS OF RELIABILITY FOR DESIGN OF BRIDGE

148

Figure 6.30 Suggested foundation probabilities of failure for service limit state B.

Figure 6.31 Suggested foundation probabilities of failure for service limit state C.

Page 173: TARGET LEVELS OF RELIABILITY FOR DESIGN OF BRIDGE

149

The graphical representation of the suggested probabilities of failure for approach

embankment strength limit is shown in Figure 6.32. The horizontal line that defines the

suggested probability of failure is located conservatively at the low (left) side of the

economic curve. The suggested design probability of failure is 1 in 1000. The suggested

probability of failure is decreased to avoid a loss in confidence from a political

perspective of the department of transportation if having more than 1 in 1000

embankments collapse.

A similar criterion was considered when establishing the suggested design

probability of failure considering service limit A for embankments (Figure 6.33) and

service limit B (Figure 6.34). Their suggested design probabilities of failure are 1 in 500

and 1 in 2000 respectively.

Figure 6.32 Suggested embankment probabilities of failure for strength limit state.

Page 174: TARGET LEVELS OF RELIABILITY FOR DESIGN OF BRIDGE

150

Figure 6.33 Suggested embankment probabilities of failure for service limit state A.

Figure 6.34 Suggested embankment probabilities of failure for service limit state B.

Page 175: TARGET LEVELS OF RELIABILITY FOR DESIGN OF BRIDGE

151

The suggested target probabilities, expressed in fractions corresponding to

strength and service limit states (settlement limits) of bridge foundations and approach

embankments are summarized in Table 6.1. Conversely, the recommended target

reliabilities (1–Pf) are presented in Table 6.2. In both tables, bridge foundations are

divided into four categories while embankments are classified by short-term or long-term

stability. The recommended target probabilities of failure (Table 6.1) or reliabilities

(Table 6.2) include considerations of both economic optimum probability of failure and

the acceptable society level of risk.

MoDOT modified the target probabilities of failure to be implemented in their

design of bridge foundations and approach embankments (July, 2010). The modified

design probabilities of failure and the target reliabilities are presented in Table 6.3 and

Table 6.4, respectively. The major differences between the suggested and the modified

probabilities of failure are found in MoDOT’s acceptance to design bridge foundations at

high probabilities of failure (1 in 25 bridges) when considering service limit A (3-inch

settlements).

Page 176: TARGET LEVELS OF RELIABILITY FOR DESIGN OF BRIDGE

152

Table 6.1 Suggested target probability of failure, Pf for the design of bridge foundations

and embankments.

Table 6.2 Suggested target reliabilities R = (1- Pf) for the design of bridge foundations

and embankments.

Strength Service A Service B Service C

Major Bridges

(> $100M)1 in 10,000 1 in 25 1 in 750 1 in 2,500

Major Bridges

(< $100M)1 in 5,000 1 in 25 1 in 500 1 in 1,500

Bridges on Major Roads 1 in 1,500 1 in 25 1 in 300 1 in 1,000

Bridges on Minor Roads 1 in 300 1 in 25 1 in 200 1 in 500

Short-term Stability - - - -

Long-term Stability 1 in 1000 1 in 500 1 in 2,000 -

Application Classification

Recommended Target Probability of Failure

Bridge Foundations

Embankments

Strength Service A Service B Service C

Major Bridges

(> $100M)0.99990 0.96000 0.99867 0.99960

Major Bridges

(< $100M)0.99800 0.96000 0.99800 0.99933

Bridges on Major Roads 0.99933 0.96000 0.99667 0.99900

Bridges on Minor Roads 0.99667 0.96000 0.99500 0.99800

Short-term Stability - - - -

Long-term Stability 0.99900 0.99800 0.99950 -

Bridge Foundations

Embankments

Application Classification

Recommended Target Levels of Reliability

Page 177: TARGET LEVELS OF RELIABILITY FOR DESIGN OF BRIDGE

153

Table 6.3 Target probability of failure, Pf for the design of bridge foundations and

embankments (modified by MoDOT, July 2010).

Table 6.4 Target reliabilities R = (1- Pf) for the design of bridge foundations and

embankments (modified by MoDOT), July 2010).

Strength Service A Service B Service C

Major Bridges

(> $100M)1 in 10,000 1 in 100 1 in 750 1 in 2,000

Major Bridges

(< $100M)1 in 5,000 1 in 75 1 in 500 1 in 1,500

Bridges on Major Roads 1 in 1,500 1 in 50 1 in 250 1 in 1,000

Bridges on Minor Roads 1 in 300 1 in 25 1 in 150 1 in 750

Short-term Stability 1 in 2,000 - - -

Long-term Stability 1 in 400 1 in 150 1 in 2,000 -

Bridge Foundations

Embankments

Application Classification

Recommended Target Probability of Failure

Strength Service A Service B Service C

Major Bridges

(> $100M)0.99990 0.99000 0.99867 0.99950

Major Bridges

(< $100M)0.99980 0.98667 0.99800 0.99933

Bridges on Major Roads 0.99933 0.98000 0.99600 0.99900

Bridges on Minor Roads 0.99667 0.96000 0.99333 0.99867

Short-term Stability 0.99950 - - -

Long-term Stability 0.99750 0.99333 0.99950 -

Application Classification

Recommended Target Levels of Reliability

Bridge Foundations

Embankments

Page 178: TARGET LEVELS OF RELIABILITY FOR DESIGN OF BRIDGE

154

6.5 LRFD Application

Load and Resistance Factor Design method (LRFD) is an engineering designing

method developed to consider the variability and the uncertainty of the design parameters

in a probabilistic way. The LRFD method consists of applying factors to increase the load

parameters and factors to decrease the resistance parameters. The values of these factors

depend on the variability or uncertainty of a load or resistance parameter and depend on a

desired target probability of failure.

The suggested probabilities of failure presented in Table 6.1 are the socially

accepted and economic optimum target probabilities of failure for the design of bridge

foundations and approach embankments. Resistance factor can be established with the

use of these target probabilities and with the knowledge of the variability or uncertainty

of resistance parameters. An example of the relationship between parameter variability,

probability of failure and resistance factors is shown in Figure 3.1 of Chapter 3.

6.6 FN Chart Considerations

The optimum probability of failure curves (also referred in this study as economic

curves) are generated by identifying points of optimum economic probabilities of failure

(Popt) for different consequence failure cost of bridge and approach embankments (X).

The location of these curves in the FN chart allowed comparing them with the socially

acceptable levels of risk to establish suggested targets of failure.

The location of the economic curves in the FN chart depends of the value of the

slope factor b which is obtained from the probability of failure-cost function. This factor

Page 179: TARGET LEVELS OF RELIABILITY FOR DESIGN OF BRIDGE

155

represents the cost required to decrease the probability of failure of the infrastructure

(bridge foundation and/or approach embankment) by one order of magnitude. A large

slope factor b would indicate that it is very expensive to decrease the probability of

failure by one order of magnitude.

Large slope factors b locate economic curves towards the right at higher

consequence costs in the FN chart. This effect would also seem to locate the economic

curve at a higher position where the probabilities of failure are larger. In this case, to

lower the design target probability of failure of a economic curve that is located at high

probability of failure region on the FN chart requires a larger investment than to lower

design target probability of failure of a economic curve that is located at low probability

of failure region. For example, it is more expensive to reduce the probability of failure for

service limit A which economic curves are located at high probabilities of failure in the

FN chart (socially unaccepted) than it is to reduce the probability of failure of strength

limit which economic curves are located at lower possibilities of failure levels in the

chart.

In the case of foundation service limit A, the cost of selecting a smaller than 1 in

25 design probability of failure is expensive (Figure 6.29). To choose a smaller

probability of failure would not agree with the purpose of designing for the optimum

economic probability of failure. For the economic curve developed for approach

embankments considering service limit A (Figure 6.33), to decrease the design target

probability of failure will cost less than to decrease the design target probability of failure

of bridge foundations considering service limit A (Figure 6.29).

Page 180: TARGET LEVELS OF RELIABILITY FOR DESIGN OF BRIDGE

156

6.7 Summary

In this chapter, economic curves for pile groups, drilled shafts, spread footings

and approach embankments were developed based the probability of failure-cost

functions presented in Chapter 5. The locations of these economic curves in the FN charts

were evaluated with respect to their proximity to socially acceptable risk boundaries and

regions.

Sensitivity analysis was performed to evaluate the changes in the probability of

failure-cost functions and the changes of location of the economic curves in the FN charts

when varying costs, loads and load variability. Results showed through the impact on the

value of the slope factor b, that the functions were sensitive to the changes. However the

changes in the function did not produce important changes in the location of the

economic curves due to the fact that these curves were plotted on log-log scaled charts

(FN charts).

In the case of the sensitivity to changes in cost, the changes affected directly the

value of the slope factor b producing a horizontal shift of the economic curve in the FN

chart. The direction of the shift depended on the increase or decrease of cost. This shift

would not modify the design target probabilities of failure (Popt), as long as the range of

consequence cost (X) (horizontal axis of the FN chart) shifts accordantly to the change in

cost.

The results of the sensitivity analysis performed considering the change in load

show that this parameter also impacted the probability of failure-cost function through the

change produced in the slope factor b. The impact was observed to be less important in

Page 181: TARGET LEVELS OF RELIABILITY FOR DESIGN OF BRIDGE

157

the location of the economic curves due to the fact that these curves were plotted on log-

log scaled charts (FN charts). A significant change (increase) in the mean working load

of a bridge is expected to be foreseen by designers. In this case it is likely that an

appropriate foundation type and size would be selected and a different probability cost

function would be generated.

The process to establish the suggested target probabilities of failure consisted in

developing step functions in FN charts between the intersection of the ranges of

consequence costs of geotechnical infrastructures and the region located between upper

and lower economic curves for each level of failure (i.e. strength and three service

limits). The upper and lower economic curves boundaries were developed considering the

envelope of slope factor b (upper and lower extreme values) of all foundation types for

each level of failure. Refinement of the location of the step function to establish the

suggested probability of failure was based on judgment taking into account the societal

and political acceptance of failure.

The suggested target probabilities of failure (or reliabilities), expressed as

fractions corresponding to strength and service limit states (settlement limits) of bridge

foundations and approach embankments and the recommended target reliabilities (1–Pf)

were summarized and presented in tables. Tables showing MoDOT’s modified design

probability values are also presented for comparison.

The suggested target probabilities of failure were explained to be useful along

with the knowledge of the variability or uncertainty of a resistance parameter to establish

resistance factors in the LRFD method. Finally, consideration of the understanding of the

Page 182: TARGET LEVELS OF RELIABILITY FOR DESIGN OF BRIDGE

158

location of the economic curves on the FN chart and the economic limitation of selecting

more conservative target probabilities of failure based on its location was described.

Page 183: TARGET LEVELS OF RELIABILITY FOR DESIGN OF BRIDGE

159

7 PRACTICAL IMPLICATIONS

7.1 Introduction

The suggested target levels of probability of failure, or conversely, reliability to

be used to develop resistance factors for the design of bridge foundations and

embankments are presented in this chapter. Details of the development of the values were

presented in previous chapters. Several considerations for implementing the suggested

target probabilities of failure are addressed.

7.2 Acceptable Probabilities of Failure and FN Charts

The suggested levels of target probabilities of failure, Pf were established by

comparing and combining economic optimization and societal acceptance of risk. In this

study, risk is considered as the probability of failure multiplied by the consequence.

While the societal acceptance of risk is based on the societal acceptability of loss of life

(expressed in terms of money), the economic optimization is based on the identification

of the probability of failure that minimizes the life cycle cost of a geotechnical

infrastructure.

Societal acceptance is generally reported through FN charts which are

logarithmic-scaled plots that show the frequency F of an event against the number of

fatalities N. The curves of these plots (Figure 7.1) define regions or level of risks that are

generally dependent on the societal acceptability for the loss of life or some other

Page 184: TARGET LEVELS OF RELIABILITY FOR DESIGN OF BRIDGE

160

undesired consequence. Three areas of risk are distinguished in Figure 7.1: the acceptable

level of risk where permissible activities lie, the unacceptable levels of risk, and an

intermediate range of risk or as low as reasonably possibly (ALARP) where reduction of

risk is desirable.

Figure 7.1 Regions of acceptable, “as low as reasonably possibly” (ALARP) and

unacceptable levels of risk on FN curves (after Hong Kong Government Planning

Department, 1994)

FN curves are developed and used by several international agencies to quantify

risk and to make policy decisions as objective as possible. A plot of the average annual

probabilities of failure of traditional civil facilities and large structures (Baecher &

Christian, 2003) overlying the FN curves developed by the Australian National

1E-9

1E-8

1E-7

1E-6

1E-5

1E-4

1E-3

1E-2

1 10 100 1000 10000

Fre

qu

ency

of

acci

den

ts, F

(an

nual

pro

bab

ilit

y o

f fa

ilu

re,

Pf)

Number of fatalities, N (consequence costs)

ALARPregion

UNACCEPTABLE

ACCEPTABLE

Page 185: TARGET LEVELS OF RELIABILITY FOR DESIGN OF BRIDGE

161

Committee on Large Dams, ANCOLD (1994) and by the Hong Kong Government

Planning Department (1994) is shown in Figure 7.2.

Figure 7.2. FN chart: Average annual probabilities for traditional civil facilities overlying

ANCOLD and Hong Kong societal based risk limits (after: Baecher & Christian, 2003,

ANCOLD, 1994, and Hong Kong Government Planning Department, 1994).

The probabilities of failure established by economic analysis involve the

evaluation of the potential costs of failure (consequences, X) and the required investment

(initial cost, A) to reduce the consequences. Conceptually, the investment and

consequence costs are balanced. Mathematically, they are established by identifying the

optimum probability that results in the minimum life-cycle cost of the geotechnical

Ann

ual P

roba

bilit

y of

Fai

lure

, p f

$ Dollars

10-2 10-010-1 10+2 10+310+1

104 105 106 107 108 109 1010

Fatalities, N

104 105 106 107 108 109 1010

100

10-1

10-2

10-3

10-4

10-5

10-6

10-7

CommercialAviation

MinePit

Slopes

Foundations

Dams

Marginally Accepted

Accepted

Hong Kong

ANCOLD

Consequence (failure/repair) cost – U.S. dollars (X)

Page 186: TARGET LEVELS OF RELIABILITY FOR DESIGN OF BRIDGE

162

infrastructure. The life-cycle cost is expressed through the expected monetary value, E

equation (Equation 7.1):

𝐸 = 𝐴 + 𝑃 ∙ 𝑋

Equation 7.1

Where,

E = expected monetary value

A = geotechnical infrastructure initial cost

P = probability of failure

X = consequence/repair cost

Several curves developed for different consequence costs (X) are shown in Figure

7.3 in which the optimum probabilities of failure are identified at the minimum cost value

of the infrastructure.

Figure 7.3. Life-cycle cost curves for specific values of infrastructure consequence of

failure costs, X. Circles denote optimum probability of failure.

-50,000

-25,000

0

25,000

50,000

75,000

100,000

125,000

150,000

1E-07 1E-06 1E-05 1E-04 1E-03 1E-02 1E-01 1E+00 1E+01 1E+02

Exp

ect

ed

mo

ne

tary

va

lue

-d

olla

rs

Probability of failure, P

Popt (X=1E4)

Popt (X=1E6)

Popt (X=1E7)

Popt (X=1E5)

Popt (X=1E8)

X=1E8

X=1E7

X=1E6

X=1E5

X=1E4

Page 187: TARGET LEVELS OF RELIABILITY FOR DESIGN OF BRIDGE

163

The suggested probabilities of failure are established by overlapping or

intersecting the economic and societal probability regions on an FN chart. Additional

engineering judgment is applied to select the probabilities depending on the size (cost) of

the infrastructure and the variability of the design parameters. Two economic probability

curves for the design of drilled shaft capacity super-imposed on the socially acceptable

probability of failure curves are shown in Figure 7.4. These probability curves (economic

curves) correspond to different levels of variability (coefficient of variation, c.o.v.) of

design parameters.

Figure 7.4. Economic probabilities for the design of drilled shafts overlapping the

socially acceptable probabilities on an FN chart. Coefficient of variation, c.o.v.,

represents different levels of uncertainty in design parameters.

1E-08

1E-07

1E-06

1E-05

1E-04

1E-03

1E-02

1E-01

1E+00

1E+4 1E+5 1E+6 1E+7 1E+8 1E+9 1E+10 1E+11 1E+12

Pro

b o

f fa

ilure

pe

r ye

ar (

P)

Consequence (failure/repair) cost, U.S. dollars (X)

cov = 0.40

cov = 0.80

Fatalities, N10-2 10-1 100 10+1 10+2 10+3 10+4 10+5 10+6

Foundations

Dams

Commercial

Aviation

Mine

PitSlopes

Estimated US Dams

Page 188: TARGET LEVELS OF RELIABILITY FOR DESIGN OF BRIDGE

164

7.3 Suggested Target Probabilities of Failure (Pf) and Reliabilities (R)

The suggested target probabilities, expressed in fractions corresponding to

capacity strength and service limit states (settlement limits) of bridge foundations and

approach embankments are given in Table 7.1. Conversely, the suggested target

reliabilities (1–Pf) are presented in Table 7.2. In both tables, bridge foundations are

divided into four categories while embankments are classified by short-term or long-term

stability. The suggested target probabilities of failure or reliabilities in Table 7.1 and

Table 7.2 respectively include considerations of both economic optimum probability of

failure and the socially acceptable probability of failure.

The suggested target probabilities of failure and reliabilities for the service levels

for bridge foundations were developed considering Service Level A corresponds to minor

damage, Service Level B corresponds to intermediate damage and Service Level C

corresponds to major damage. Minor damage was defined to be caused by values of

differential settlement that would produce angular distortions on the order of 0.0021.

Intermediate damage was defined as the limit for a bridge to suffer structural damage

(angular distortion at about 0.004). Major damage was defined as the limit to produce

extreme stress (overstress) in the superstructure. The three service limits will not

necessarily be implemented in the final specification but are necessary as an intermediate

step to ensure that serviceability issues do not begin to control when strength limit state

design checks are improved. For approach embankments, Service Level A corresponds to

a 3-inch settlement at the bridge abutment while Service Level B corresponds to a 12-

inch settlement at the bridge abutment.

Page 189: TARGET LEVELS OF RELIABILITY FOR DESIGN OF BRIDGE

165

Table 7.1 Suggested target probability of failure, Pf for the design of bridge foundations

and embankments

Table 7.2 Suggested target reliabilities R = (1- Pf) for the design of bridge foundations

and embankments

Strength Service A Service B Service C

Major Bridges

(> $100M)1 in 10,000 1 in 25 1 in 750 1 in 2,500

Major Bridges

(< $100M)1 in 5,000 1 in 25 1 in 500 1 in 1,500

Bridges on Major Roads 1 in 1,500 1 in 25 1 in 300 1 in 1,000

Bridges on Minor Roads 1 in 300 1 in 25 1 in 200 1 in 500

Short-term Stability - - - -

Long-term Stability 1 in 1000 1 in 500 1 in 2,000 -

Application Classification

Recommended Target Probability of Failure

Bridge Foundations

Embankments

Strength Service A Service B Service C

Major Bridges

(> $100M)0.99990 0.96000 0.99867 0.99960

Major Bridges

(< $100M)0.99800 0.96000 0.99800 0.99933

Bridges on Major Roads 0.99933 0.96000 0.99667 0.99900

Bridges on Minor Roads 0.99667 0.96000 0.99500 0.99800

Short-term Stability - - - -

Long-term Stability 0.99900 0.99800 0.99950 -

Bridge Foundations

Embankments

Application Classification

Recommended Target Levels of Reliability

Page 190: TARGET LEVELS OF RELIABILITY FOR DESIGN OF BRIDGE

166

The suggested target probabilities of failure and probabilities of reaching a service

limit for bridge foundations increase as bridge size decreases. This behavior follows the

FN curves in which the optimum target probability of failure increases as the

consequence of failure decreases. The suggested target probabilities of failure for

embankments follow similar behavior.

The suggested target probabilities for reaching a specific service limit state (A, B,

C) decrease as the magnitude of the service limit (A<B<C) increases for any size of

bridge. At low consequences produced by small distortions (or settlements), the optimum

probability of settlement is large following the risk and FN curves.

While the calculated probabilities of failure represent a continuous function (a

line/curve), the suggested probabilities of failure are discrete values that can be used over

a range of consequence costs, or initial costs, depending on the bridge size. The

suggested probability step function produced by the combination of economic and

societal probabilities versus the initial cost of the bridge is shown in Figure 7.5. Each step

of the function identifies target probability of failure for strength for the four classified

bridge sizes (major bridges for more than $100M, major bridges less than $100M,

bridges on major roads and bridges on minor roads).

Similar target probability of failure step functions were developed to establish the

probability of failure for service limit states. The discrete probabilities of reaching the

service limit states versus consequence (repair) cost are shown in Figure 7.6.

Page 191: TARGET LEVELS OF RELIABILITY FOR DESIGN OF BRIDGE

167

Figure 7.5. Suggested discrete probabilities of failure versus initial cost of a bridge for the

design of the capacity (strength limit state, LS) of bridge foundations.

Figure 7.6. Suggested discrete probabilities of reaching a specific service limit state

versus repair cost of the bridge for design foundations.

Ann

ual P

roba

bilit

y of

Fai

lure

, p f

Repair Cost ($)

104 105 106 107 108 109 1010

Fatalities, N

10-2 10-010-1 10+2 10+310+1

104 105 106 107 108 109 1010

100

10-1

10-2

10-3

10-4

10-5

10-6

10-7

CommercialAviation

MinePit

Slopes

Foundations

Dams

Marginally Accepted

Accepted

Hong Kong

ANCOLD

Service C(Major)

Service B(Intermediate)

Service A(Minor)

Consequence (failure/repair) cost – U.S. dollars (X)

Ann

ual P

roba

bilit

y of

Fai

lure

, p f

Initial Bridge Cost ($)

Foundations

104 105 106 107 108 109 1010

Fatalities, N

10-2 10-010-1 10+2 10+310+1

104 105 106 107 108 109 1010

100

10-1

10-2

10-3

10-4

10-5

10-6

10-7

CommercialAviation

MinePit

Slopes

Dams

Marginally Accepted

Accepted

Hong Kong

ANCOLD

Strength LS Spec.

Page 192: TARGET LEVELS OF RELIABILITY FOR DESIGN OF BRIDGE

168

7.4 Considerations for the Suggested Probabilities of Failure

The suggested probabilities of failure although expressed in fractions with large

denominators are independent of the number of bridges an agency may build. Each

probability has been identified as the optimum probability of failure from an economic

perspective that balances the initial bridge infrastructure with the potential consequence

cost of failure. The suggested target probabilities of failure can be used to calculate

resistance factors for the design of bridge foundations and approach embankments using

the LRFD method. In general the LRFD method consists of increasing the load and

decreasing the resistance with the use of factors. Normally, one factor is used for each

design parameter. The values of these factors depend on the uncertainty or variability of

the parameters and the target probability of failure. In 2005 Loehr et al. developed

relationships (curves) that related resistance factors with the variability of soil parameters

(soil resistance) and the target probability of failure for the design of earth slopes. An

example of this relationship is shown in Figure 7.7.

Page 193: TARGET LEVELS OF RELIABILITY FOR DESIGN OF BRIDGE

169

Figure 7.7. Resistance factor relations for undrained shear strength for probabilities of

failure of 0.1, 0.01, 0.001, with respect to stability analyses of slopes (Loehr et al. 2005).

In Figure 7.7, different curves are shown for different targets of probability of

slope failure. The range of the resistance factors varies between 0.0 and 1.0. They are a

function of the variability of the soil parameter (expressed in terms of the coefficient of

variation, COV) and are dependent on a selected probability of failure. This dissertation

research suggests the use of the target probability of failure presented in Table 7.1 for the

design of bridge foundations and approach embankment using LRFD.

0.00

0.10

0.20

0.30

0.40

0.50

0.60

0.70

0.80

0.90

1.00

0.00 0.10 0.20 0.30 0.40 0.50 0.60 0.70 0.80 0.90 1.00

Res

ista

nce

Fact

or,

(Y

cf)

Coefficient of Variation for Undrained Shear Strength, (COV)

Pf = 0.100

Pf = 0.010

Pf = 0.001

Page 194: TARGET LEVELS OF RELIABILITY FOR DESIGN OF BRIDGE

170

7.5 Summary

Suggested target levels of probability of failure (reliability) to be used to develop

resistance factors for the design of bridge foundations and approach embankments were

presented. The suggested probabilities of failure were established by comparing socially

acceptable risk levels with economic optimization of probability of failure (or reliability).

Target levels are established by identifying the optimum probability that minimizes the

life cycle cost of the geotechnical infrastructure. Probabilities of failure for ultimate

strength and service limit states were classified by bridge size and type. The probabilities

of failure for strength limit states range from 1 in 10,000 to 1 in 300 for bridges greater

than 100 million dollars to bridges on minor roads. The probabilities of failure for service

limit states range from 1 in 2000 to 1 in 25 for bridges greater than 100 million dollars to

bridges on minor roads. The probability of reaching a service limit state decreases as the

magnitude of the limit state increases.

Page 195: TARGET LEVELS OF RELIABILITY FOR DESIGN OF BRIDGE

171

8 SUMMARY, CONCLUSIONS AND RECOMMENDATIONS

This chapter provides a summary of the dissertation, followed by a series of major

conclusions reached based on the results of this work. In addition, a series of

recommendations are provided to facilitate the implementation of the levels of risk for

the design of bridge foundations and approach embankments.

8.1 Summary

Traditionally, the factor of safety (F.S.) for the design of slopes and foundations

was calculated through the method Allowable Stress Design (ASD). The factor of safety

calculated with this method accounted for all the variability and uncertainties in the loads

and resistance. Although this empirical method has been used successfully for many

years, it lacked the capability of assigning consistent levels of safety (reliability) to

different sites that had different variability and uncertainty of resistance values.

Currently the level of reliability, which is also expressed as the probability of

failure or risk (probability of failure multiplied by the consequence) is mainly established

by an AASHTO specification committee. In the AASHTO specifications (2004), the

design risk is established at one ten thousandth (or 0.0001). The disadvantage of

establishing a single target level of safety for all structures is that it does not consider the

increase in cost required to achieve this reliability.

In some cases, the level of risk is established using the Load and Resistance

Factor Design (LRFD) method as a function of the variability of the loads and

Page 196: TARGET LEVELS OF RELIABILITY FOR DESIGN OF BRIDGE

172

resistances. According to the approach, a low level of risk would be established where the

uncertainty or load and resistance variability are low. This approach goes against the

philosophy of LRFD because the level of risk is adjusted for the variability of the

parameters instead of adjusting load and resistance factors to achieve a target level of

risk.

The objective of this study is to determine the target levels of reliability (or levels

of safety) for the design of bridge foundations and approach embankments using LRFD.

According to the hypothesis, these levels of reliability can be established by combining

societal acceptance of risk and economic analysis.

Normally societal acceptance is expressed in terms of tolerable limits of risk and

generally reported through FN curves, which summarize the relation between frequencies

of failure (F) and number of lives lost (N). Although the consequences of failure in FN

charts are normally expressed in terms of the number of losses of human lives, it is

possible to assign a value to human life and express the losses in terms of monetary

value. In this case, the FN curves would constitute boundaries between regions on the

plot that define the acceptance or non-acceptance of probabilities of failure for a potential

amount of loss. From an economic perspective, an FN curve (economic curve) constitutes

a curve developed by a family of points that represent the “optimum” probability of

failure for a given loss.

The life-cycle cost of a geotechnical infrastructure was expressed through an

expected monetary value equation, E. Based on decision theory, the E was considered a

measure of the value or utility expected to result from a given strategy (decision), equal

Page 197: TARGET LEVELS OF RELIABILITY FOR DESIGN OF BRIDGE

173

to the sum of the initial investment cost of the infrastructure plus the probability of

incurring in a consequence cost.

The mathematical expression to denote the expected monetary value was:

𝐸 = 𝐴 + 𝑃 ∙ 𝑋

Where,

E = expected monetary value

A = initial cost of the civil work

P = the probability of failure

X = consequential cost of failure

The number of unknown variables of the EMV equation was simplified by

obtaining a relation between the initial costs A and the probability of failure P:

𝐸 = (𝑏 ∙ 𝐿𝑛𝑃 + 𝑑) + 𝑃 ∙ 𝑋

Where,

b = the slope factor , and

d = the vertical intercept at Pf = 1.0

The optimum probability of failure has been defined as the probability of failure that

makes the expected monetary value the minimum (tangent slope is zero). This was

calculated by deriving expected monetary value (E) with respect to the probability of

failure (P). The probability (P) at which the expected monetary value was found

minimum was defined as the optimum probability of failure (Popt).

Page 198: TARGET LEVELS OF RELIABILITY FOR DESIGN OF BRIDGE

174

𝑃𝑜𝑝𝑡 =−𝑏

𝑋

The value of the slope factor b (slope of the probability of failure versus cost

function) was obtained from the relation generated between the initial cost A and the

probability of failure of the geotechnical infrastructure X. The slope factor b represents

the cost required to decrease the probability of failure by one order of magnitude. The

relations between the probabilities of failure and the costs were established with the use

of reliability analyses (Taylor Series Method).

Different values of consequence costs X produced families of optimum

probability points Popt generating continuous curves (economic curves) when plotted on

FN-charts. Sensitivity analysis was performed on the function between the cost and the

probability of failure by varying the assumed values of the variables that defined stability

of the infrastructure. The impact on the economic curves when changing the variable

values was also analyzed.

Optimum economic socially acceptable bands were identified between envelopes

of economic curves generated for all foundation types (pile group, drilled shafts and

spread footing). Step functions were developed within the envelopes of economic curves

to identify the recommended probability of failure of bridges according to their

consequence cost (Figure 8.1).

Page 199: TARGET LEVELS OF RELIABILITY FOR DESIGN OF BRIDGE

175

Figure 8.1 Example of probability of failure (risk) step function generated within

foundation economic curve envelope according to the consequence of bridge failure.

The risk functions were compared with the societal tolerance of risk. Comments

regarding the judgments used to establish the recommended target levels of risk

(probabilities of failure) are presented for different types of bridge failure (collapse, and

three levels of settlement). A final table of recommended probabilities of failure and

reliability are presented in the study. Finally, a general procedure is presented on the

application of the recommended probabilities of failure to obtain reducing factor for the

design of bridges and approach embankment using LRFD.

1E-08

1E-07

1E-06

1E-05

1E-04

1E-03

1E-02

1E-01

1E+00

1E+4 1E+5 1E+6 1E+7 1E+8 1E+9 1E+10 1E+11 1E+12

Pro

b o

f fa

ilure

pe

r ye

ar (

Po

ptim

um

)

Failure/repair cost, dollars (X)

Fatalities, N10-2 10-1 100 10+1 10+2 10+3 10+4 10+5 10+6

Foundations

Dams

Commercial

Aviation

Mine

PitSlopes

Marginally Accepted

Accepted

ANCOLD

Hong Kong

1E-08

1E-07

1E-06

1E-05

1E-04

1E-03

1E-02

1E-01

1E+00

1E+4 1E+5 1E+6 1E+7 1E+8 1E+9 1E+10 1E+11 1E+12

Pro

b o

f fa

ilure

pe

r ye

ar (

Po

ptim

um

)

Failure/repair cost, dollars (X)

Fatalities, N10-2 10-1 100 10+1 10+2 10+3 10+4 10+5 10+6

Foundations

Dams

Commercial

Aviation

Mine

PitSlopes

Marginally Accepted

Accepted

ANCOLD

Hong Kong

Page 200: TARGET LEVELS OF RELIABILITY FOR DESIGN OF BRIDGE

176

8.2 Conclusions

The hypothesis underlying this research effort was that the target levels of

reliability (or levels of safety) for the design of geotechnical infrastructure using LRFD

can be established through a combination of the economic optimization of their life cycle

cost through probabilistic analysis of failure and the identification and incorporation of

societal tolerance to risk.

The following conclusions were drawn based on the findings:

1. As an answer to the hypothesis, the results of this dissertation research

show that it is possible to develop target levels of reliability (or

probabilities of failure) for the design of geotechnical infrastructure and

approach embankments based on a combination of cost analysis and

societal acceptance of failure.

2. The significance of the procedure proposed is that the levels of reliability

obtained from the optimization of cost and risk, allows decreasing the

costs of infrastructures while designing to a consistent known level of

safety.

3. The engineering procedure proposed is robust and can be applied to

develop target reliabilities for the design of other civil works.

4. The suggested target probabilities of failure are to be used to calculate

resistance factors for the design of bridge foundations and approach

embankments using the LRFD method. The results of this work are

already being implemented to develop new design specifications for piles,

Page 201: TARGET LEVELS OF RELIABILITY FOR DESIGN OF BRIDGE

177

drilled shafts, shallow foundations and approach embankments for the

Missouri Department of Transportation (MoDOT).

5. Social considerations control the establishment of target levels of

reliability for bridge foundations at strength limit state. Conversely,

economic considerations control the establishment of target levels of

reliability for bridge foundation for service limit states.

6. The proposed procedure allows updating the target levels of reliability for

the design of geotechnical infrastructure if costs were to change.

8.3 Recommendations

The following recommendations were drawn based on the results of analyses:

1. The procedure proposed in this dissertation research should now be

extended to be implemented to other civil infrastructure.

2. The consequence costs of bridge failure did not include the social impact

due to traffic. Considering that the true extent of the social impact on

business is very difficult to quantify and that these costs are not paid by

the Departments of Transportation, it is recommended not to include these

values in the consequence costs of bridge or approach embankment

failures.

Page 202: TARGET LEVELS OF RELIABILITY FOR DESIGN OF BRIDGE

178

APPENDIX

Page 203: TARGET LEVELS OF RELIABILITY FOR DESIGN OF BRIDGE

179

Table A 1. Format of the bridge cost information answer sheet for the questionnaire filled

by the Missouri Department of Transportation, MoDOT.

Table A 2. Characteristics and costs of selected Missouri bridges (MoDOT).

Deck Crack Structural Severe

Settlement (in) 3 6 12

MoD

OT

's R

ecom

men

ded

Rep

air

Estimate cost

Estimated

economic

impact

Year Built

Bidding Cost

Bridge: MoDOT A3101 (Fed ID 2664)

Damage Level

Bridge TypeNumber of

SpansLengths (ft)

Critical Span

Length (ft)

Deck

CrackingStructural Severe

Year of

ConstructionInitial Cost

Present

Initial Cost

A3390 C.C. 4 48 - 60 - 48 - 35 35 2.0 4.0 8.0 1981 206,548 491,557

A4824 PS. C 4 82 - 82 - 82 - 82 82 2.5 4.0 18.0 2005 758,505 840,181

A3101 C.C., SP 2 120 - 120 120 3.0 6.0 12.0 1987 544,144 1,036,221

A6248 C.C., SP 6 120 - 179 - 132 - 107.5 - 135 - 107.5 107.5 3.0 6.0 30.0 2001 4,259,949 5,206,524

A5054 C.C., SP 26

(85, 85, 170, 105, 640, 220, 220, 220,

220, 220, 220, 130.5, 130.5, 130.5,

130.5, 130.5, 130.5, 130.5, 130.5,

130.5, 130.5, 130.5, 130.5, 151, 218,

85 2.5 5.0 18.0 1996 22,534,581 31,070,146

Damage Level (Settlement inches)

Page 204: TARGET LEVELS OF RELIABILITY FOR DESIGN OF BRIDGE

180

Table A 3. Repair costs for 5 Missouri bridges considering 3 service limit states.

Table A 4. Missouri bridge costs for Service Limit State A (minor damage).

A3390 A3101 A4824 A6248 A5054

Inspection 2,000 2,000 2,000 2,000 2,000 2,000 2,000 2,000 2,000 2,000 2,000 2,000 2,000 2,000 2,000

Wedge approach 1,200 1,200 3,400 1,800 5,900 5,900

Seal cracked areas. 2,000 3,000 2,000 3,000 2,000 2,000 3,000 4,000 4,000

Chip seal entire deck 800 800 120,000 1,400 1,400 80,000 1,200 7,000 7,000 1,900 1,900 200,000

Replace deck 1,200,000

Replace spans 140,000 140,000 1,000,000

New bearings 6,000

Strengthen foundation 40,000 100,000

Deep foundation 200,000 200,000 250,000 250,000 250,000 250,000 350,000 350,000 600,000 600,000

Replace 2nd series of spans 200,000 950,000 950,000 3,000,000 1,500,000

Replace partial approach slab 15,000 30,000 15,000 30,000 30,000 40,000 80,000

Estimated Cost 6,000 222,000 552,000 8,800 271,400 1,312,000 7,000 432,000 1,372,000 17,000 462,000 5,552,000 13,800 653,800 2,382,000

Est. Economic Impact 90,000 90,000 90,000 10,500 45,000 45,000 10,500 67,500 67,500 94,000 252,000 720,000 35,000 150,000 200,000

Repairing the cause 50,000 100,000 50,000 100,000 50,000 100,000 0 50,000 100,000 0 80,000 250,000

Investigation cause 15,000 30,000 50,000 15,000 30,000 50,000 15,000 30,000 50,000 15,000 30,000 50,000 15,000 60,000 100,000

Bridge TypeEstimate

Cost

Economic

Impact

Cause

Repair

Cause

Investigati

on

Total

A3390 C.C. 6,000 21,000 - 15,000 21,000

A4824 PS. C 7,000 10,500 - 15,000 22,000

A3101 C.C., SP 8,800 10,500 - 15,000 23,800

A6248 C.C., SP 17,000 94,000 - 15,000 32,000

A5054 C.C., SP 13,800 35,000 - 15,000 28,800

Deck Cracking - Costs

Page 205: TARGET LEVELS OF RELIABILITY FOR DESIGN OF BRIDGE

181

Table A 5. Missouri bridge costs for Service Limit State B (intermediate damage)

Table A 6. Missouri bridge costs for Service Limit State C (major damage)

Bridge TypeEstimate

Cost

Economic

Impact

Cause

Repair

Cause

InvestigatiTotal

A3390 C.C. 222,000 90,000 50,000 30,000 302,000

A4824 PS. C 432,000 67,500 50,000 30,000 512,000

A3101 C.C., SP 271,400 45,000 50,000 30,000 351,400

A6248 C.C., SP 462,000 252,000 50,000 30,000 542,000

A5054 C.C., SP 653,800 150,000 80,000 60,000 793,800

Structural Damage - Costs

Bridge TypeEstimate

Cost

Economic

Impact

Cause

Repair

Cause

InvestigatiTotal

A3390 C.C. 552,000 90,000 100,000 50,000 702,000

A4824 PS. C 1,372,000 67,500 100,000 50,000 1,522,000

A3101 C.C., SP 1,312,000 45,000 100,000 50,000 1,462,000

A6248 C.C., SP 5,552,000 720,000 100,000 50,000 5,702,000

A5054 C.C., SP 2,382,000 200,000 250,000 100,000 2,732,000

Severe Damage - Costs

Page 206: TARGET LEVELS OF RELIABILITY FOR DESIGN OF BRIDGE

182

Table A 7. Bridge settlement repair costs for 3 service limit states.

Table A 8. Calculations of different settlement limits for three levels of bridge damage

using angular distortion method.

BridgeYear of

Construction

Past

Initial Cost

Year 2010

Initial Cost

Service A

Repair Cost

Service B

Repair Cost

Service C

Repair Cost

A3390 1981 206,548 491,557 21,000 302,000 702,000

A4824 2005 758,505 840,181 22,000 512,000 1,522,000

A3101 1987 544,144 1,036,221 23,800 351,400 1,462,000

A6248 2001 4,259,949 5,206,524 32,000 542,000 5,702,000

A5054 1996 22,534,581 31,070,146 28,800 793,800 2,732,000

BridgeNumber

of SpansLengths

Critica

l Span

Length

t (ft)Angular

Distortion

Differential

Settlement

(in)

Angular

Distortion

Differential

Settlement

(in)

Num of

Spans

Dist

outer

fiber C

fo/fa oC/fo

Differential

Settlement

(in)A3101 2 120 - 120 120 0.71 0.0021 3.0 0.004 5.8 2 15 3.6 45 10.8

A6248 6 120 - 179 - 132 - 107.5 - 135 - 107.5 107.5 0.71 0.0021 2.7 0.004 5.2 6 15 3.6 120 28.8

A5054 26

(85, 85, 170, 105, 640, 220, 220,

220, 220, 220, 220, 130.5, 130.5,

130.5, 130.5, 130.5, 130.5, 130.5,

130.5, 130.5, 130.5, 130.5, 130.5,

151, 218, 145)

85 0.71 0.0021 2.1 0.004 4.1 26 15 3.6 70 16.8

A4824 4 82 - 82 - 82 - 82 82 0.71 0.0021 2.1 0.004 3.9 4 15 3.6 70 16.8

A3390 4 48 - 60 - 48 - 35 35 0.71 0.0021 0.9 0.004 1.7 4 9 3.6 19 7.6

Theoretical Bearn/Girder YieldTheoretical Deck Cracking Observered Structural

Structure Analysis Settlement Criteria Maximum Stress Criteria

Page 207: TARGET LEVELS OF RELIABILITY FOR DESIGN OF BRIDGE

183

Figure A.1 Elevation view of Bridge MoDOT A6248 (Fed ID 12126) located in Jackson

County, NB I-435 over Ramp N(71)-E, Ramp N(435)-E, Ramp N(435)-S, and U.S. 71. It

is a concrete continuous deck with steel plate girders bridge type, with 6 spans, (120, 179,

132, 107.5, 135, 107.5) ft.

Figure A.2 Elevation view of Bridge MoDOT 4824 located in McDonald County, over

Big Sugar Creek, State Road from Rte. KK to Barry CO Line about 0.2 miles N.E. of Rte

KK. It is a prestressed Concrete I-Girders spans bridge type, with 4 spans, (82, 82, 82,

82) ft.

Page 208: TARGET LEVELS OF RELIABILITY FOR DESIGN OF BRIDGE

184

Figure A.3 Elevation view of Bridge MoDOT 3101 (Fed ID 2664) located in Jefferson

County, Bridge Rock Creek Road Underpass, State Road 21, about 4 miles south of

Route 141. It is a continuous deck composite with steel plate girders bridge type with 2

spans, (120, 120) ft.

Figure A.4 Elevation view of Bridge MoDOT 3390 (Fed ID 2856) located in Clay

County, Ramp 2 over Ramp 9, State Road from Rte. I-35 to Rte. 210 at I-35 & I-435

Interchange. It is a concrete continuous bridge type with 4 spans, (48, 60, 48, 35) ft.

Page 209: TARGET LEVELS OF RELIABILITY FOR DESIGN OF BRIDGE

185

REFERENCES

AGS, (2000). “Landslide Risk Management Concepts and Guidelines. Australian

Geomechanics Society, Sub-Committee on Landslide Risk Management.

Australian Geomechanics, Volume 35, N°3, pages 49-92, 3 September 2000

7

ANCOLD (1994). "Guidelines on Risk Assessment 1994." Australia-New Zealand

Committee on Large Dams. Guidelines on Dam Safety Management.

8

AASHTO (2004), AASHTO LRFD Bridge Design Specifications, AASHTO, Customary

U.S. Units, Third edition, 2004. Washington, D.C.

Bedford, T. and Cooke, R (2001). Probabilistic Risk Analysis: Foundations and Methods.

Cambridge, Cambridge University Press.

9

Baecher, G.B. (1982b). "Statistical methods in site characterization." Updating

Subsurface Samplings of Soils and Rocks and their In-Situ Testing, Santa Barbara,

Engineering Foundation: 463-492.

10

Baecher, G.B., J.T. Christian (2003). Reliability and Statistics in Geotechnical

Engineering, Chichester, England ; Hoboken, NJ : Wiley.

Baecher, G.B. (1982a). Simplified Geotechnical Data Analysis, Reliability Theory and Its

Application in Structural and Soil Engineering. The Hague: Martinus Nijhoff

Publishers.

Baecher, G.B. (1982b). Statistical Methods in Site Characterization. Updating Subsurface

Sampling of Soils and Rocks and Their In-Situ Testing, Santa Barbara, Engineering

Foundation: 463-492.

Baecher, G.B. (1983a). Professional Judgement and Prior Probabilities in Engineering

Risk Assessment. Proceedings, 4th

International Conference on Applications of

Statistics and Probability to Structural and Geotechnical Engineering, Florence,

Pitagora Editrice, Bologna: 635-650.

Baecher G. (1983). Applied Geotechnical reliability Analysis - Reliability Theory and Its

Applications in Structural and Soil Mechanics. In: Thoft-Christensen P. (ed.),

NATO Series 70 ASI, 237-270.

Baecher, G.B., Pate, E.M. and de Neufville, R. (1980). Risk of Dam Failure in Benefit-

Cost Analysis. Water Resources Research. 16(3): 449-456.

Ball, D.J., Floyd, P.J. (1998). “Societal Risks”, Final Report. Report Commissioned by

the Health and Safety Executive, United Kingdom.

Page 210: TARGET LEVELS OF RELIABILITY FOR DESIGN OF BRIDGE

186

Barker, R. M., J. M. Duncan, K. B. Rojiani, P. S. K. Ooi, C. K. Tan, and S. G. Kim. 1991

“Manuals for the Design of Bridge Foundations.” NCHRP Report 343. TRB,

National Research Council, Washington, DC.

Chang, Nien-Yin. (2006). Report No. CDOT-DTD-R-2006-7. CDOT Foundation Design

Practice and LRFD Strategic Plan. Colorado Department of transportation –

Reseach Branch. February 2006.

Chau, K.T., Sse, Y.L., Fung, M.K., Wong, W.Y., Fong, E.L., Chan, L.C.P. (2002).

Lanslide Hazard Analysis for Hong Kong using Landslide Inventory and GIS.

Elsevier Ltd. DOI: 10.1016/j.cageo.2003.08.013.

11

Diamantidis, D., Duzgun, S., Nadim, F. Wöhrle, M. (2006). “On the Acceptable Risk for

Structures Subjected to Geohazards”. 2006 ECI Conference on Geohazards,

Lillehammer, Norway. Paper 32.

12

Duncan, J.M., Tan, C.K. (1991). Part 5 – Engineering Manual for Estimating Tolerable

Movements of Bridges. NCHRP RPT 343, December 1991. Manual for Design of

Bridge Foundations.

Duncan, J.M., Navin, M., Patterson, K. (1999). Manual for Geotechnical Engineering

Reliability Calculations. Virginia Polytechnic Institute and State University.

Dupont, B., Allen, D. (2002). Movements and Settlements of Highway Bridge

Approaches. Research Report KTC-02-18/PR-220-00-1F. DOT 1700.7 (8-72).

Contractor of Grant No. KYSPR-00-220.

Duval, T.D., Gribbin, D.J. (2008). Re: Memorandum: Treatment of Value of Life and

Injuries in Preparing Economic Evaluations. U.S. Department of Transportation.

Office of the Secretary of Transportation. Date: Feb. 5, 2008

Ellingwood, B.R. (2001). Acceptable Risk Bases for Design of Structures. Prog. Struct.

Engng Mater. 2001; 3: 170-179 (DOI: 10.1002/pse.78). John Wiley & Sons, Ltd.

Engert, P.A., Lansdowne, Z. F. (1999). Risk Matrix User’s Guide. Version 2.2. The

MITRE Corporation.

Evans, A.W., (2003). Transport Fatal Accidents and FN Curves 1967-2001. Research

Report 073. HSE Books, ISBN 0 7176 2623 7.

Falcon Geofoam. Price for geofoam retrieved in March, 2010.

http://www.falcongeofoam.com/

FHWA-TS-85-228 (1986). Tolerable Movement Criteria for Highway Bridges. Final

Report. U.S. Department of Transportation. Federal Highway Administration.

Page 211: TARGET LEVELS OF RELIABILITY FOR DESIGN OF BRIDGE

187

13

Haldar, A., Mahadevan, S. (2000). Probability, Reliability and Statistical Methods in

Engineering Design. John Wiley & Sons, 605 Third Ave., New York, NY 10158-

0012.

HDR Engineering, Inc (2007). Capital Cost Technical Report. State Highway 82.

Entrance to Aspen Environmental Reevaluation. Colorado Department of

Transportation, Region, 3 and Federal Highway Administration, Colorado Division.

HM Treasury United Kingdom (1996). The Setting of Safety Standards, a report by an

interdepartamental group and esternal advisers, June.

14

Hong Kong Government Planning Department (1994). "Hong Kong Planning Standards

and Guidelines, Chapter 11, Potentially Hazardous Installations." Hong Kong.

Hoppe, E.J. (1999). Guidelines for the Use, Design, and Construction of Bridge

Approach Slabs. Final Report. Virginia Transportation Research Council. VTRC

00-R4.

Inflationdata.com. Historical inflation rate retrieved in September 2009.

http://inflationdata.com/inflation/inflation_rate/historicalinflation.aspx?dsinflation_

currentpage=8

15

Kenkel, Donald (2003). Using Estimates of the Value of a Statistical Life in Evaluating

Consumer Policy Regulations, 26 J. Consumer policy 1. (surveying agency

practice). http://www.ers.usda.gov/publications/mp1570/mp1570d.pdf.

Kwon, O., Lim, E, Orton, S. (2010). Calibration of the live load factor in LRFD bridge

design specifications based on state-specific traffic environments.

Kulicki, J. M. (1999). “Chapter 5: Design Philosophies for Highway Bridges,” Bridge

Engineering Handbook, Edited by Chen, W.F. and Duan, L., CRC Press, Boca

Raton, FL.

Kulicki, J.M., Prucz, Z., Clancy, C.M., Mertz, D.R., Nowak, A.S. (2007). Updating the

Calibration Report for AASHTO LRFD Code. Final Report. Project No. NCHRP

20-7/186. National Cooperative Highway Research Program. Transportation

Research Board (TRB).

16

Lambe, T. W. (1985). “Amuay landslides.” XIth International Conference on Soil

Mechanics and Foundation Engineering, San Francisco, CA, A. A. Balkema: 137-

158.

17

Page 212: TARGET LEVELS OF RELIABILITY FOR DESIGN OF BRIDGE

188

Lambe, T. W., Silva, F. and Lambe, P. C. (1988). “Expressing the level of stability of a

slope.” The Art and Science of Geotechnical Engineering at the Dawn of the

Twenty-First Century: A Volume Honoring Ralph B. Peck, Prentice-Hall: 558-588.

18

Lichtenstein, S., B. Fischhoff & L. Phillips (1982), “Calibration of probabilities: The

state of the art to 1980,” in Kahneman, D., P. Slovic & A. Tversky (eds), Judgment

Under Uncertainty: Heuristics and Biases. New York: Cambridge University

Press.

Loehr, J.E., Finley, C.A., Huaco, D.R. (2005). Procedures for Design of Earth Slopes

Using LRFD. Final Report No. 103-030. Missouri Department of Transportation,

Research, Development and Technology Division.

Loehr, J.E., Huaco, D.R. (2009). “Probabilistic Calibration of Resistance Factors for

Slope Stability,” Contemporary Topics in In Situ Testing, Analysis, and Reliability

of Foundations, Proceedings of the 2009 International Foundation Congress and

Equipment Expo, ASCE, GSP 186, pp. 466-473.

Long, J.H. Olson, S.M., Stark, T.D., Samara, E.A. (1998). “Differential Movement at

Embankment-Bridge Structural Interface in Illinois.” Transportation Research

Record No. 1633, Liquefaction, Differential Settlement, and Foundation

Engineering, Transportation Research Board, National Research Council, Paper No.

98-1575, p. 53-60.

Luna, R., Robinson, J.L., Wilding, A.J. (2004). “Evaluation of Bridge Approach Slabs,

Performance and Design.” Final Project Report No. RDT 04-010. Research

Investigation RI 02-033.

19

Lund, Jay R. (2008). “A Risk Analysis of Risk Analysis”. Journal of Contemporary

Water Research & Education, Issue 140, pages 53-60.

Marsden, J., McDonald, L., Bowles, D.S., Davidson, R., Nathan, R. (2007). Dam safety,

economic regulation and society’s need to prioritise health and safety expenditures.

In Proceedings of the NZSOLD/ANCOLD Workshop on “Promoting and Ensuring

the Culture of Dam Safety”, Queenstown, New Zealand. November 2007.

McCormick, W.B., Shane, J.N. (1993). Memorandum: Treatment of Value of Life and

Injuries in Preparing Economic Evaluations. U.S. Department of Transportation.

Office of the Secretary of Transportation. Date: Jan 8, 1993.

McVay, M.C., Ellis, R.D., Birgisson, B., Conzolazio, G.R. Putcha, S., Min Lee, S. (2003)

Load and Resistance Factor Design, Cost and Risk. Designing a Drilled-Shaft Load

Test Program in Florida Limestone. Transportation Research Record 1849. Paper

No. 03-3189. p. 98-106.

Page 213: TARGET LEVELS OF RELIABILITY FOR DESIGN OF BRIDGE

189

Meyerhof, G. 1970. Safety Factors in Soul Mechanics. Canadian Geotechnical Journal,

Vol. 7, No. 4, pp. 349-355.

Miyamoto, N., Matsushita, H., Enomoto, M., Katsura, K. (2006). A Study on Optimum

Life Cycle Cost Focusing Bridge Maitenance for Japanese Local Governments – A

Case Study in Fukuoka City, Japan.

20

Moulton, L.K., (1985). Tolerable Movement Criteria for Highway Bridges. Report N°

FHWA-RD-85/107, Federal Highway Administration, Washington D.C. 20590.

21

Moulton, L.K., (1986). Tolerable Movement Criteria for Highway Bridges. Report N°

FHWA-TS-85-228, Federal Highway Administration, Washington D.C. 20590.

NCHRP (2004). Load and Resistance Factor Design (LRFD) for Deep Foundations.

Report 507. National Cooperative Highway Research Program. Transportation

Research Board (TRB).

NCHRP (2008). Costing Asset Protection: An All Hazards Guide for Transportation

Agencies (CAPTA). Report 525. Surface Transportation Security. Volume 15.

Transportation Research Board (TRB).

Nowak, A. (1995). “Calibration of LRFD Bridge Code.” Journal of Structural

Engineering, Vol. 121, No. 8, pp. 1245-1251.

Orr, T. L. (2005). Serviceability in the design of Bridge Foundations, Proceedings of the

International Workshop on the Evaluation of Eurocode 7. ERTC 10 of the

International Society for Soil Mechanics and Geotechnical Engineering and

Department of Civil, Structural and Environmental Engineering, Trinity College,

Dublin. March 31 and April 1, 2005.

Paikowsky, S.G., "Serviceability in the Design of Bridge Foundations", Proceedings of

International Workshop on the Evaluation of Eurocode 7, Trinity College Dublin,

March 31 - April 1, 2005, pp.251-261.

Paikowsky, S.G. (2004). NCHRP Report 507. Load and Resistance Factor Design

(LRFD) for Deep Foundations. Transportation Research Board (TRB).

Randolf, M.F., Dolwin, J. Beck, R. (1994). Design of Driven Piles in Sand. Geotechnique

44, No. 3, 427-448.

Sanders, G. (2010). Foundation Unit Pricing, Missouri Pay Item Report. Missouri

Department of Transportation, MoDOT. February 2010.

Schmidt, B.J., Bartlett F.M. (2002). Review of Resistance Factor for Steel: Data

Collection. Can. J. Civ. Eng. 29: 98-108. DOI: 10.1139/L01-081. NRC Canada.

Page 214: TARGET LEVELS OF RELIABILITY FOR DESIGN OF BRIDGE

190

Starr, C. (1969) “Social benefit versus technology risk.” Science 165: 1232-1238.

Stein, S., Sedmera K. (2006). NCHRP Web-Only Document 107: Risk-Based

Management Guidelines for Scour at Bridges with Unknown Foundations.

Contractor’s Final Report for NCHRP Project 24-25. National Cooperative

Highway Research Program. Transportation Research Board (TRB). GKY &

Associates, Inc.

22

Stern, P. C., Fineberg, H. V. and National Research Council (U.S.). Committee on Risk

Characterization (1996). Understanding Risk: Informing Decisions in a Democratic

Society. Washington, D.C., National Academy Press.

URS (2003). Thames Coast Flood Risk Assessment. Final Report. Environment Waikato

and Thames-Coromandel District Council. 48305-027-573/R001-E.DOC.

U.S. Army Corps of Engineers (1998). “Risk Based Analysis in Geotechnical

Engineering for Support of Planning Studies,” Engineering Circular No. 1110-2-

554, Department of the Army U.S. Army Corps of Engineers, Washington D.C., 27

February 1998. (Available online at www.usace.army.mil/usace-docs).

Van Westen, C.J., Van Asch, T.W.J., Soeters, R. (2005). Landslide Hazard and Risk

Zonation-Why Is It Still So Difficult?

Versteeg, M. (1987). "External Safety Policy in the Netherlands: An Approach to Risk

Management." Journal of Hazardous Material 17: 215-221.

Vicente, E.E., Diaz, G.M., Yourman, A.M. (1994). Settlement of Deep Compacted Fills

in California, Settlement 94, College Station, Texas. Foundations and

Embankments Deformations - Deep Compacted Fills, p. 1124-1134.

23

Viscusi, W. K., (1998). "The Social Costs of Punitive Damages against Corporations in

Environmental and Safety Cases”, 87 Georgetown L. J. 285-345.

24

Viscusi, W. K., (2003). The Value Of Life: Estimates With Risks By Occupation And

Industry. Discussion Paper No. 422. Harvard Law School. The Social Science

Research Network Electronic Paper Collection:

http://www.law.harvard.edu/programs/olin_center/papers/pdf/422.pdf

25

Viscusi, W. K., (2005). The Value of Life. Discussion Paper No. 517. Harvard Law

School. The Social Science Research Network Electronic Paper Collection:

http://www.law.harvard.edu/programs/olin_center/papers/pdf/Viscusi_517.pdf

26

Von Thun, J.L. (1996). "Risk assessment of Nambe Falls Dam." Uncertainty in the

Geologic Environment, Madison, ASCE: 604-635.

Page 215: TARGET LEVELS OF RELIABILITY FOR DESIGN OF BRIDGE

191

27

VROM (2006). “Societal Risk”. The Netherlands Ministry of Housing, Spatial Planning

and the Environment. http://www.vrom.nl/international.

Xanthakos, P.P. (1996). Bridge Substructure and Foundation Design. Prentice Hall. 1st

edition. ISBN-10: 0-13-300617-4. ISBN-13: 978-0-13-300617-9

Zhang, L.M., Tang, W.H. (2008). Calibration of Models for Pil Settlement Analysis using

64 Field Load Tests. Can Geotech. J. Vol 45, page 59-73. NRC Research Press

Web site at cgj.nrc.ca

Page 216: TARGET LEVELS OF RELIABILITY FOR DESIGN OF BRIDGE

192

VITA

Daniel R. Huaco was born in Lima, Peru. He graduated with a Bachelor’s degree

in Civil Engineering from the Universidad Ricardo Palma in December, 1994, after

which he obtained in Peru his professional license in Civil Engineering. He continued his

graduate studies in Applied Mathematics completing the academic requirements for the

Master’s degree in 1998. In 2001, he joined the University of Missouri perusing his

second Master’s degree in Geotechnical Engineering. In the fall of 2003, he was accepted

into the doctoral program where he was given the opportunity to work on two doctoral

projects with his advisor Dr. Erik Loehr. In the spring of 2011, he was ready to defend his

doctoral dissertation. During his years at the University of Missouri, he taught

engineering courses while creating, participating in, and enhancing various student

organizations. He is married to Sara Ysabel Vela and they are the parents of Daniel

Alberto and Sara Daniela.