Owned and operated as a joint venture by a consortium of Canadian universities via a contribution through the National Research Council Canada Propriété d’un consortium d’universités canadiennes, géré en co-entreprise à partir d’une contribution administrée par le Conseil national de recherches Canada
Canada’s national laboratory for particle and nuclear physics Laboratoire national canadien pour la recherche en physique nucléaire
et en physique des particules
Accelerating Science for Canada Un accélérateur de la démarche scientifique canadienne
ISAC Target Reliability from Design to Implementation to
Long Term Service
Violeta Toma WAO 2012
• Introduction to ISAC • Past: Phase I – on-line testing
• one target module • more target modules
• Present: Phase II – off line testing • ISAC target life cycle
• Future: Phase III – remote connect & disconnect
Overview
August 2012 Violeta Toma WAO 2012
2
ISAC = Isotope Separation and Acceleration
ISAC
August 2012 Violeta Toma WAO 2012
3
Phase one
August 2012
Violeta Toma WAO 2012
4
•Two target stations •One target module
Machine shop 6 -12 months
ISAC Target Life Cycle
August 2012 Violeta Toma WAO 2012
5
Machine shop 6 -12 months
Target (material) 1 – 8 weeks
ISAC Target Life Cycle
August 2012 Violeta Toma\ WAO 2012
6
Target and target tube
ISAC Target
August 2012 Violeta Toma WAO 2012
7
Machine shop 6 – 12 months
Target material 1-8 weeks
Target assembly and baking
5 days
ISAC Target Life Cycle
August 2012 Violeta Toma WAOP 2012
8
• In house made target 1 -8 weeks
• Target assembly &baking 5 days
ISAC Target
August 2012 Violeta Toma WAO 2012
9
Machine shop 6 -12 months
Target material 1 – 8 weeks
Target assembly and baking
5 days
Test stand 1 week
ISAC Target Life Cycle
August 2012 Violeta Toma WAO 2012
10
ISAC Target
August 2012 Violeta Toma WAO 2012
11
ISAC Target Life Cycle
August 2012 Violeta Toma WAO 2012
12
Target assembly goes to the Test stand.
Test stand
August 2012 Violeta Toma WAO 2012
13
Machine shop 6 -12 months
Target material 1 – 8 weeks
Target assembly and baking
5 days
Test stand 1 week
Target installed in Target Module
2 days
ISAC Target Life Cycle
August 2012 Violeta Toma WAO 2012
14
Hot Cell (HC) – Target remote installation into the Target Module (TM)
ISAC Target
August 2012 Violeta Toma WAO 2012
15
ISAC Target Module
August 2012 Violeta Toma WAO 2012
16
Machine shop 6 -12 months
Target material 1 – 8 weeks
Target assembly and baking
5 days
Test stand 1 week
Target installed in Target Module
2 days
Conditioning Station 2 days
ISAC Target Life Cycle
August 2012 Violeta Toma WAO 2012
17
Conditioning station
August 2012 Violeta Toma WAO 2012
18
Machine shop 6 -12 months
Target material 1 – 8 weeks
Target assembly and baking
5 days
Test stand 1 week
Target installed in Target Module
2 days
Conditioning Station 2 days
Target preparations for production
2 days
Beam Delivery 2-4 weeks
Post mortem analysis and storage
ISAC Target Life Cycle
August 2012 Violeta Toma WAO 2012
19
Target tube Ionizer tube Proton beam
Beam on Target
August 2012 Violeta Toma WAO 2012
20
Machine shop 6 -12 months
Target material 1 – 8 weeks
Target assembly and baking
5 days
Test stand 1 week
Target installed in Target Module
2 days
Conditioning Station 2 days
Target preparations for production
2 days
Beam Delivery 2-4 weeks
Post mortem analysis and storage
Phase I & II
August 2012 Violeta Toma WAO 2012
21
• Target travel document • Learn from failures • Learn from success
• Standardized parts • Dedicated target reliability engineer
Documenting & Improving
August 2012 Violeta Toma WAO 2012
22
• Present: manual connect/disconnect • Cool- down for one week after beam off • Beam off during manual dis/re-connect • Personnel dose
• Future: remote connect/disconnect • No cool-down necessary • Dis/Re-connect can be done while delivering
beam from the other station • No dose to personnel
Phase III
August 2012 Violeta Toma WAO 2012
23
Manual Target Disconnect/Connect
August 2012 Violeta Toma WAO 2012
24
Machine shop 6 -12 months
Target material 1 – 8 weeks
Target assembly and baking
5 days
Test stand 1 week
TRG installed in Target Module
2 days
Conditioning Station 2 days
Target preparations for production
2 days
Beam Delivery 2-3 weeks
Post mortem analysis and storage
Beam Availability
August 2012 Violeta Toma WAO 2012
25
ISAC Target
August 2012 Violeta Toma WAO 2012
26
• Problems: • Manufacturing problems • During baking:
• Target legs warping • Target tube warping
• During conditioning • Electrical short • Vacuum leaks • Water leaks
• Phase I => II • Gain: ~ 9 days beam
availability and improved reliability
• Phase II => III • Gain: ~11 days beam
availability and further improved reliability
Summary
August 2012 Violeta Toma WAO 2012
27
Owned and operated as a joint venture by a consortium of Canadian universities via a contribution through the National Research Council Canada
Propriété d’un consortium d’universités canadiennes, géré en co-entreprise à partir d’une contribution administrée par le Conseil national de recherches Canada
Canada’s national laboratory for particle and nuclear physics Laboratoire national canadien pour la recherche en physique nucléaire
et en physique des particules
Thank you! Merci!