55
Strategies and incentives for integration of renewable generation using distributed energy resources CSI RD&D Round 3 Project Hosted by UCSD July 10, 2013 Eric Cutter Priya Sreedharan, PhD, PE Jamil Farbes

Strategies and incentives for integration of renewable ...€¦ · 10/07/2013  · integration of distributed generation is essential 8 . PROJECT APPROACH 9 . ... 15-minute power

  • Upload
    others

  • View
    3

  • Download
    0

Embed Size (px)

Citation preview

Page 1: Strategies and incentives for integration of renewable ...€¦ · 10/07/2013  · integration of distributed generation is essential 8 . PROJECT APPROACH 9 . ... 15-minute power

Strategies and incentives for integration of renewable generation using distributed energy resources

CSI RD&D Round 3 Project

Hosted by UCSD

July 10, 2013

Eric Cutter

Priya Sreedharan, PhD, PE

Jamil Farbes

Page 2: Strategies and incentives for integration of renewable ...€¦ · 10/07/2013  · integration of distributed generation is essential 8 . PROJECT APPROACH 9 . ... 15-minute power

Using UCSD Microgrid for Renewable Integration

Page 3: Strategies and incentives for integration of renewable ...€¦ · 10/07/2013  · integration of distributed generation is essential 8 . PROJECT APPROACH 9 . ... 15-minute power

Acknowledgements

UCSD

• Byron Washom, John Dilliott and Jan Kleissl

Viridity

• Nancy Miller, Chuck Richter, Laura Manz

Itron

• Ann Peterson and Jonathan Wanjiru

3

Page 4: Strategies and incentives for integration of renewable ...€¦ · 10/07/2013  · integration of distributed generation is essential 8 . PROJECT APPROACH 9 . ... 15-minute power

Policy Context

The Million Solar Roofs initiative, net energy metering (NEM) and zero net-energy (ZNE) goals encourage high penetration PV

California’s Energy Action Plan places distributed energy resources (DER) at the top of the ‘loading’ order

Distribution system challenges a key barrier to increased penetration of renewable DG.

4

Page 5: Strategies and incentives for integration of renewable ...€¦ · 10/07/2013  · integration of distributed generation is essential 8 . PROJECT APPROACH 9 . ... 15-minute power

Potential Grid Problems from Increased Renewables

Focus of UCSD project

Not intended to be comprehensive. 5

Page 6: Strategies and incentives for integration of renewable ...€¦ · 10/07/2013  · integration of distributed generation is essential 8 . PROJECT APPROACH 9 . ... 15-minute power

Research Questions

Does integrating additional resources in dispatch decisions reduce costs/increase flexibility

Can integrated dispatch strategies

• Increase peak load shifting?

• Balance campus resources?

• Balance grid resources?

Are strategies cost-effective at current rates/prices?

If not, what incentives and policies are needed to encourage participation?

6

Yes

Yes

Marginally so

Page 7: Strategies and incentives for integration of renewable ...€¦ · 10/07/2013  · integration of distributed generation is essential 8 . PROJECT APPROACH 9 . ... 15-minute power

Contribution of This Study

1. Documents potential to engage existing DER for renewable integration

2. Develops an optimization framework to model the dispatch, costs and benefits of microgrid to

• Provide customer and utility grid benefits.

• Optimize electric and thermal resources

3. Compares costs and benefits over a full year with high resolution, validated historical data.

7

Page 8: Strategies and incentives for integration of renewable ...€¦ · 10/07/2013  · integration of distributed generation is essential 8 . PROJECT APPROACH 9 . ... 15-minute power

Key Findings

Accurately representing thermal resources is critical for developing accurate microgrid optimization strategies

Existing tariffs can significantly inhibit otherwise beneficial DER dispatch

Direct participation in energy and AS markets is cost-effective, but unlikely to mobilize DER on its own

Payments for flexible capacity can help if designed to include and enable DER

Establishing local avoided cost benefits for integration of distributed generation is essential

8

Page 9: Strategies and incentives for integration of renewable ...€¦ · 10/07/2013  · integration of distributed generation is essential 8 . PROJECT APPROACH 9 . ... 15-minute power

PROJECT APPROACH

9

Page 10: Strategies and incentives for integration of renewable ...€¦ · 10/07/2013  · integration of distributed generation is essential 8 . PROJECT APPROACH 9 . ... 15-minute power

Overview of Key UCSD Resources

The central plant is rich with dispatchable resources

• Two 13 MW natural gas generators

• One 3 MW steam generator

• Three steam driven chillers (~ 10,000 tons capacity)

• Eight electric driven chillers (~ 7800 tons capacity)

• 3.8 million gal thermal storage tank

• Backup diesel generation

>1 MW of solar PV

~ 1.4 MW of DR-ready reducible building load

Visibility at the building level

Chilled water tank at UCSD

campus

10

Page 11: Strategies and incentives for integration of renewable ...€¦ · 10/07/2013  · integration of distributed generation is essential 8 . PROJECT APPROACH 9 . ... 15-minute power

UCSD Data Resources

MSCADA system: 15-minute power data

Johnson Control Metasys System: thermal storage tank data

‘BOP’ System: steam data for boilers, generators

‘Efftrack’ chiller diagnostic system: chiller data

Daily central plant logs: gas usage

UCSD expert knowledge; especially John Dilliott, Energy Manager

Solar data from Prof. Jan Kleissl

11

Page 12: Strategies and incentives for integration of renewable ...€¦ · 10/07/2013  · integration of distributed generation is essential 8 . PROJECT APPROACH 9 . ... 15-minute power

UCSD Dispatch Optimization Tool

E3 developed an engineering and economics dispatch tool in the Analytical modeling platform

The tool determines which resources to dispatch on an hourly basis in order to minimize daily and monthly energy costs

Main thermal & electrical systems of the central plant are modeled (see next slide)

Model determines the least cost dispatch that satisfies campus thermal and electrical demand, subject to equipment operating constraints

12

Page 13: Strategies and incentives for integration of renewable ...€¦ · 10/07/2013  · integration of distributed generation is essential 8 . PROJECT APPROACH 9 . ... 15-minute power

Analytical Framework: How the Resources Fit Together

13

Page 14: Strategies and incentives for integration of renewable ...€¦ · 10/07/2013  · integration of distributed generation is essential 8 . PROJECT APPROACH 9 . ... 15-minute power

Campus Electric and Thermal Dispatch Optimization Model

14

Page 15: Strategies and incentives for integration of renewable ...€¦ · 10/07/2013  · integration of distributed generation is essential 8 . PROJECT APPROACH 9 . ... 15-minute power

Dispatch Example

The next slide shows how the chilled water needs are met under three different scenarios

• Imports only: all electrical needs are forced to be met through imported electricity (no onsite generation)

• Cogeneration: electrical needs can be met through either onsite generation or imported electricity

• Cogeneration and thermal energy storage: all flexible resources in the microgrid are permitted to operate

15

Page 16: Strategies and incentives for integration of renewable ...€¦ · 10/07/2013  · integration of distributed generation is essential 8 . PROJECT APPROACH 9 . ... 15-minute power

Chilled Water Provision

16

0

20

40

60

80

100

MM

Btu

of

CH

W

Cogeneration

0

20

40

60

80

100

MM

Btu

of

CH

W

Imports Only

0

20

40

60

80

100

7/13 h08 7/13 h16 7/14 h00 7/14 h08 7/14 h16 7/15 h00 7/15 h08 7/15 h16 7/16 h00 7/16 h08 7/16 h16 7/17 h00 7/17 h08 7/17 h16 7/18 h00

MM

Btu

of

CH

W

Cogeneration with TES

Steam Chiller WC 1 Production Steam Chiller WC 2 Production Steam Chiller WC 8 Production Electric Chiller WC 3 Production

Electric Chiller WC 5 Production Electric Chiller WC 6 Production Electric Chiller WC 7 Production Electric Chiller WC 9 Production

TES Discharge - Production Campus Chilled Water Demand

Page 17: Strategies and incentives for integration of renewable ...€¦ · 10/07/2013  · integration of distributed generation is essential 8 . PROJECT APPROACH 9 . ... 15-minute power

Broad Strategies Investigated

Peak load shifting (PLS)

• Reducing peak load is a primary motivation for DER

• Investigated tariff changes to increase potential/reduce cost of PLS

PV firming strategies

• PV variability imposes costs, but ‘leaning on the grid’ is currently free

• Investigated scenarios with higher PV penetration and with penalty for deviations from day-ahead schedule

Grid support

• Can DER compete with grid resources in providing ancillary services to integrate renewable generation?

• Used 2011 frequency regulation prices for illustrative case study

17

Page 18: Strategies and incentives for integration of renewable ...€¦ · 10/07/2013  · integration of distributed generation is essential 8 . PROJECT APPROACH 9 . ... 15-minute power

Criteria for Evaluating the Strategy

Does the strategy save UCSD money, relative to their baseline operations?

Is the strategy cost-effective today?

• If not, is the strategy likely to be cost-effective in the future?

• What policies would make it cost effective?

Net costs = scenario cost minus base case cost

18

Page 19: Strategies and incentives for integration of renewable ...€¦ · 10/07/2013  · integration of distributed generation is essential 8 . PROJECT APPROACH 9 . ... 15-minute power

PEAK LOAD SHIFTING

19

Page 20: Strategies and incentives for integration of renewable ...€¦ · 10/07/2013  · integration of distributed generation is essential 8 . PROJECT APPROACH 9 . ... 15-minute power

Peak Load Shifting Description

UCSD already shifts substantial portion of peak load with thermal energy storage

Can peak loads or campus costs be reduced further?

Do existing tariffs sufficiently promote (or inhibit) peak load shifting?

20

Source: www.cyp-res.com

Page 21: Strategies and incentives for integration of renewable ...€¦ · 10/07/2013  · integration of distributed generation is essential 8 . PROJECT APPROACH 9 . ... 15-minute power

Peak Load Shifting: Comparison of Scenario Costs to Base Case, 2011-8

21

~5% savings by removing all hours

demand charge

Positive = Cost Increase

Negative = Cost Savings

Page 22: Strategies and incentives for integration of renewable ...€¦ · 10/07/2013  · integration of distributed generation is essential 8 . PROJECT APPROACH 9 . ... 15-minute power

Peak Load Shifting: Peak Load Reductions

Peak demand is reduced significantly with all hours demand charge removed

Reduction of 0.5 MW on average, as high as 1 MW

22

Page 23: Strategies and incentives for integration of renewable ...€¦ · 10/07/2013  · integration of distributed generation is essential 8 . PROJECT APPROACH 9 . ... 15-minute power

Restructuring All-Hours Demand Charge

All-hours demand charge designed to recover fixed distribution costs regardless of when peak occurs

Individual customer classes all peak between 10 am and 7 pm

PLS is a specialized case where load can be shifted to super off-peak hours

GRC Phase 2 testimony supports excluding super off-peak period from fixed cost recovery1

23 1. Doc #254237, CY-7, http://www.sdge.com/sites/default/files/regulatory/Ch-1-Yunker.pdf

Page 24: Strategies and incentives for integration of renewable ...€¦ · 10/07/2013  · integration of distributed generation is essential 8 . PROJECT APPROACH 9 . ... 15-minute power

PV FIRMING

24

Page 25: Strategies and incentives for integration of renewable ...€¦ · 10/07/2013  · integration of distributed generation is essential 8 . PROJECT APPROACH 9 . ... 15-minute power

PV Firming: Description

Managing day-ahead (DA) forecast error

• Relatively small at existing penetration, greater issue at high levels of penetration

PV Firming counter balances forecast error to match day-ahead schedule

25

Page 26: Strategies and incentives for integration of renewable ...€¦ · 10/07/2013  · integration of distributed generation is essential 8 . PROJECT APPROACH 9 . ... 15-minute power

PV Firming: Strategies

Base case (today) no cost for forecast error

• No incentive to firm PV

Two-part rate

• Base rate for DA schedule, ‘penalty’ rate for deviations

• Imposes cost to lean on grid

• $8/MWh of production $31/MWh of forecast error

PV firming using natural gas and steam generators

• Offset forecast error with natural gas generation alone

• Offset forecast error with natural gas and steam generation

Investigated scenarios with higher PV penetration; 200% results shown

26

Page 27: Strategies and incentives for integration of renewable ...€¦ · 10/07/2013  · integration of distributed generation is essential 8 . PROJECT APPROACH 9 . ... 15-minute power

PV Firming 200%: Comparison of Scenario Costs

27

-2.0%

-1.5%

-1.0%

-0.5%

0.0%

0.5%

1.0%

1.5%

2.0%

Electricity Imports Natural Gas Total Cost Electricity Imports Natural Gas Total Cost

2011-8 2012-1

Perc

en

tag

e c

han

ge i

n c

ost

realt

ive t

o

base c

ase

Perfect Foresight Two Part Tariff NG Gen Support NG & Stm Gen Support

Two-part tariff (lean on grid) cheaper than firming with campus resources in most months

Two-part tariff (lean on grid)

Camus firming

Page 28: Strategies and incentives for integration of renewable ...€¦ · 10/07/2013  · integration of distributed generation is essential 8 . PROJECT APPROACH 9 . ... 15-minute power

PV Firming 200%: Implied Cost of PV Firming by PV Production

28

Difference in cost per MWh of production

$0

$2

$4

$6

$8

$10

$12

$14

$16

2011-8 2012-1

Co

sts

of

Fir

min

g P

V E

rro

r($

/MW

h o

f P

rod

uc

tio

n)

Firming w/ Grid ($31/MWh Penalty) NG Turbine Firming NG Turbine & Stm Turbine Firming

Page 29: Strategies and incentives for integration of renewable ...€¦ · 10/07/2013  · integration of distributed generation is essential 8 . PROJECT APPROACH 9 . ... 15-minute power

PV Firming: Summary

Using grid level estimates of integration costs, it appears more cost-effective to lean on grid

• Differences in total costs relatively small

However - local distribution costs for integration costs could be higher

Using additional campus resources could reduce costs of PV firming

As penetration increases, so does costs to firm using microgrid

29

Page 30: Strategies and incentives for integration of renewable ...€¦ · 10/07/2013  · integration of distributed generation is essential 8 . PROJECT APPROACH 9 . ... 15-minute power

GRID SUPPORT

30

Page 31: Strategies and incentives for integration of renewable ...€¦ · 10/07/2013  · integration of distributed generation is essential 8 . PROJECT APPROACH 9 . ... 15-minute power

Grid Support: Description

Use campus resources to support grid operations

Bid into CAISO frequency regulation market

• Used historical 2011 market prices for frequency regulation

• No pay-for-performance or flexi-ramp

Use frequency regulation as illustrative case study for DER providing flexible resources to grid

• Methodology applicable for load following and ramp

31

Page 32: Strategies and incentives for integration of renewable ...€¦ · 10/07/2013  · integration of distributed generation is essential 8 . PROJECT APPROACH 9 . ... 15-minute power

Grid Support: Scenarios

Base case

• Establishes resource schedule, no regulation bids

Fixed, simple regulation

• Use natural gas generator to bid 3.3 MW of Reg Up and Reg Down

Simple regulation

• Use natural gas generator to bid 0-3.3 MW of Reg Up and Reg Down

NG generator only regulation

• Bid 0-6.6 MW for either Reg Up or Reg Down separately

All campus resources regulation

• Add steam turbine and electric chillers to bid 0-13.5 MW of Reg Up or Reg Down separately

32

Incre

asin

g fle

xib

ility

Page 33: Strategies and incentives for integration of renewable ...€¦ · 10/07/2013  · integration of distributed generation is essential 8 . PROJECT APPROACH 9 . ... 15-minute power

Grid Support: Scenario Net Costs

33

Base Case Total Cost:

$1,116k $864k

Negative = Cost Savings/ Increased Revenue

Page 34: Strategies and incentives for integration of renewable ...€¦ · 10/07/2013  · integration of distributed generation is essential 8 . PROJECT APPROACH 9 . ... 15-minute power

Grid Support: Scenario Costs by Component, 2011-8

34

Increase generation

Decrease imports

Decrease generation

Increase imports Increase

revenue

Page 35: Strategies and incentives for integration of renewable ...€¦ · 10/07/2013  · integration of distributed generation is essential 8 . PROJECT APPROACH 9 . ... 15-minute power

Grid Support: Summary

Results suggest it is possible for UCSD to offer grid services at today’s prices for a net profit

• But profit is relatively small: ~ 1-2% of total energy costs

• Profit significantly increases with additional resources and greater flexibility in bidding strategy

Results in perspective

• Market may be small for regulation but larger for load following and ramp

Again, local distribution avoided costs may be needed to encourage DER participation

35

Page 36: Strategies and incentives for integration of renewable ...€¦ · 10/07/2013  · integration of distributed generation is essential 8 . PROJECT APPROACH 9 . ... 15-minute power

CONCLUSIONS

36

Page 37: Strategies and incentives for integration of renewable ...€¦ · 10/07/2013  · integration of distributed generation is essential 8 . PROJECT APPROACH 9 . ... 15-minute power

Conclusions

Integrated optimization and dispatch of campus resources can reduce costs while providing flexibility

Removing all-hours demand charge increases peak load shifting potential

Leaning on grid is marginally more cost-effective than PV firming with campus resources

Current prices for regulation provide net revenue, but it is small relative to total campus costs

37

Page 38: Strategies and incentives for integration of renewable ...€¦ · 10/07/2013  · integration of distributed generation is essential 8 . PROJECT APPROACH 9 . ... 15-minute power

Conclusions (con’t)

Incorporating load (non-generator) resources reduces campus costs of providing flexibility for renewable integration

Tariffs and incentives to encourage integration of renewables with DER are both feasible and cost-effective (based on TRC)

However, additional incentives based on local, distributed avoided costs and value of flexible capacity will be needed to encourage adoption

38

Page 39: Strategies and incentives for integration of renewable ...€¦ · 10/07/2013  · integration of distributed generation is essential 8 . PROJECT APPROACH 9 . ... 15-minute power

How will grid needs evolve over time?

39

Regulation

Ramp

Time Shift

2013 2050

Load Following

What are the size, probability and duration of capacity and ramping needs?

Page 40: Strategies and incentives for integration of renewable ...€¦ · 10/07/2013  · integration of distributed generation is essential 8 . PROJECT APPROACH 9 . ... 15-minute power

What the grid needs

What DERs do best

What grid resources do best

Which needs do DERs fill best?

Page 41: Strategies and incentives for integration of renewable ...€¦ · 10/07/2013  · integration of distributed generation is essential 8 . PROJECT APPROACH 9 . ... 15-minute power

41

How do DERs get a seat at the table?

Page 42: Strategies and incentives for integration of renewable ...€¦ · 10/07/2013  · integration of distributed generation is essential 8 . PROJECT APPROACH 9 . ... 15-minute power

APPENDIX SLIDES

Page 43: Strategies and incentives for integration of renewable ...€¦ · 10/07/2013  · integration of distributed generation is essential 8 . PROJECT APPROACH 9 . ... 15-minute power

Additional Resources

http://calsolarresearch.ca.gov/Funded-Projects/second-solicitation-funded-projects.html

• Tasks 6-8 report: Strategies and incentives for integration of renewable generation using distributed energy resources

• Additional reports found on the website

https://solarhighpen.energy.gov/2013_doe_cpuc_high_penetration_solar_forum

Later in 2013

• E3 update to NEM cost-effectiveness report

• E3 update to technical potential of high penetration distributed generation report

43

Page 44: Strategies and incentives for integration of renewable ...€¦ · 10/07/2013  · integration of distributed generation is essential 8 . PROJECT APPROACH 9 . ... 15-minute power

PV Firming – Levels of PV, Magnitude of Forecast Error

44

18

20

22

24

26

28

30

32

34

6-Jul-11 7-Jul-11 8-Jul-11 9-Jul-11 10-Jul-11

MW

400% More PV

10th - 90th %-tile 25th - 75th %-tile

Gross Load Load Net of PV

18

20

22

24

26

28

30

32

34

MW

200% More PV

10th - 90th %-tile 25th - 75th %-tile

Gross Load Load Net of PV

18

20

22

24

26

28

30

32

34

MW

Existing Level of PV

10th - 90th %-tile 25th - 75th %-tile

Gross Load Load Net of PV

Page 45: Strategies and incentives for integration of renewable ...€¦ · 10/07/2013  · integration of distributed generation is essential 8 . PROJECT APPROACH 9 . ... 15-minute power

PV Firming – Addressing Day Ahead Forecast Error

45

19

21

23

25

27

29

31

6/9 h08 6/9 h12 6/9 h16 6/9 h20 6/10 h00 6/10 h04 6/10 h08 6/10 h12 6/10 h16 6/10 h20 6/11 h00 6/11 h04

MW

Example Energy Dispatch with DA Forecast Error

NG Turbine Setpoint MW Steam Turbine Production MWh Imports to Campus MWh

Electric Chiller Consumption MWh DA Forecast Error to Balance MWh DA Forecast Net Load MWh

Actual Net Load MWh

Page 46: Strategies and incentives for integration of renewable ...€¦ · 10/07/2013  · integration of distributed generation is essential 8 . PROJECT APPROACH 9 . ... 15-minute power

PV Firming – NG Turbine Firming Explained

46

NG & Steam Turbine Firming is the same concept, where total flexible reserve is made up of both NG and steam turbine capacity

20

21

22

23

24

25

26

27

6/9 h08 6/9 h12 6/9 h16 6/9 h20 6/10 h00 6/10 h04 6/10 h08 6/10 h12 6/10 h16 6/10 h20 6/11 h00 6/11 h04

MW

Example NG Turbine Dispatch for PV Firming

Forecast error firmed Constrained range of turbine setpoint Reserved turbine flexibility

Turbine dispatch to firm PV Turbine setpoint

Page 47: Strategies and incentives for integration of renewable ...€¦ · 10/07/2013  · integration of distributed generation is essential 8 . PROJECT APPROACH 9 . ... 15-minute power

Regulation Dispatch

47

0

10

20

30

40

MW

Simple Regulation Energy Dispatch

0

10

20

30

40

8/2

h0

88

/2 h

12

8/2

h1

68

/2 h

20

8/3

h0

08

/3 h

04

8/3

h0

88

/3 h

12

8/3

h1

68

/3 h

20

8/4

h0

08

/4 h

04

8/4

h0

88

/4 h

12

8/4

h1

68

/4 h

20

8/5

h0

08

/5 h

04

8/5

h0

88

/5 h

12

8/5

h1

68

/5 h

20

8/6

h0

08

/6 h

04

8/6

h0

88

/6 h

12

8/6

h1

68

/6 h

20

8/7

h0

08

/7 h

04

8/7

h0

88

/7 h

12

8/7

h1

68

/7 h

20

8/8

h0

08

/8 h

04

8/8

h0

88

/8 h

12

8/8

h1

68

/8 h

20

8/9

h0

08

/9 h

04

8/9

h0

88

/9 h

12

8/9

h1

68

/9 h

20

8/1

0 h

00

8/1

0 h

04

MW

Whole Campus Regulation Energy Dispatch

NG Turbine 1 Production MWh NG Turbine 2 Production MWh Steam Turbine Production MWh

Imports to Campus MWh Electric Chiller Consumption MWh Campus Electric Demand MWh

Page 48: Strategies and incentives for integration of renewable ...€¦ · 10/07/2013  · integration of distributed generation is essential 8 . PROJECT APPROACH 9 . ... 15-minute power

Peak Load Shifting: Change in Dispatch

48

0

5

10

15

20

25

30

35

40

MW

Base Case Energy Dispatch

0

5

10

15

20

25

30

35

40

7/1

h0

1

7/1

h0

9

7/1

h1

7

7/2

h0

1

7/2

h0

9

7/2

h1

7

7/3

h0

1

7/3

h0

9

7/3

h1

7

7/4

h0

1

7/4

h0

9

7/4

h1

7

7/5

h0

1

7/5

h0

9

7/5

h1

7

7/6

h0

1

7/6

h0

9

7/6

h1

7

7/7

h0

1

7/7

h0

9

7/7

h1

7

7/8

h0

1

7/8

h0

9

7/8

h1

7

7/9

h0

1

7/9

h0

9

7/9

h1

7

7/1

0 h

01

7/1

0 h

09

7/1

0 h

17

7/1

1 h

01

7/1

1 h

09

7/1

1 h

17

7/1

2 h

01

7/1

2 h

09

7/1

2 h

17

MW

No All Hrs Charge, Higher On-Peak Demand Rate Energy Dispatch

NG Turbine 1 Production MWh NG Turbine 2 Production MWh Steam Turbine Production MWh

Imports to Campus MWh Electric Chiller Power Consumption MWh Campus Electric Demand MWh

Page 49: Strategies and incentives for integration of renewable ...€¦ · 10/07/2013  · integration of distributed generation is essential 8 . PROJECT APPROACH 9 . ... 15-minute power

Chiller Optimization

49

Page 50: Strategies and incentives for integration of renewable ...€¦ · 10/07/2013  · integration of distributed generation is essential 8 . PROJECT APPROACH 9 . ... 15-minute power

Change in Energy Imports for Full Year

50

Page 51: Strategies and incentives for integration of renewable ...€¦ · 10/07/2013  · integration of distributed generation is essential 8 . PROJECT APPROACH 9 . ... 15-minute power

Daily Output by Resource for Full Year

51

Page 52: Strategies and incentives for integration of renewable ...€¦ · 10/07/2013  · integration of distributed generation is essential 8 . PROJECT APPROACH 9 . ... 15-minute power

Cost-effectiveness: TRC Costs

UCSD energy costs are a mix of wholesale costs and retail rates

Retail rates are (almost) always higher than wholesale (TRC) costs

• We assume that the actual TRC cost will be less than or equal to the UCSD costs of implementing strategies

Capital cost of the existing resources are considered sunk

• Only the variable operating costs are included as TRC cost

52

Page 53: Strategies and incentives for integration of renewable ...€¦ · 10/07/2013  · integration of distributed generation is essential 8 . PROJECT APPROACH 9 . ... 15-minute power

Cost-effectiveness: TRC benefits

TRC benefits for each strategy are quantified based on alternative resources or established avoided costs

• PLS: resource adequacy or residual capacity value

• PV Firming: estimates of grid integration costs

• Frequency regulation: CAISO AS prices

PV Firming: not quite cost-effective based on grid level integration costs

Frequency regulation cost-effective, but small percentage of total campus energy costs

53

Page 54: Strategies and incentives for integration of renewable ...€¦ · 10/07/2013  · integration of distributed generation is essential 8 . PROJECT APPROACH 9 . ... 15-minute power

Peak Load Shifting TRC Details

“Cost” of increased peak load shifting is:

• Increase in electricity imports: $8/kW shifted

• Decrease in natural gas consumption $9/kW shifted

• In our illustrative case SDG&E demand charge revenue remains unchanged

Benefits (for month of August)

• Energy costs alone: $38/kW shifted

• E3 avoided costs: $85/kW shifted

• Includes system and T&D capacity value

TRC benefits much greater than cost

• RIM benefits also greater (for Direct Access customer)

54

Page 55: Strategies and incentives for integration of renewable ...€¦ · 10/07/2013  · integration of distributed generation is essential 8 . PROJECT APPROACH 9 . ... 15-minute power

Research for Policy Makers

What additional steps needed to access technical potential of existing DER

• 500 MW of college campus load

• 2,000 MW of flexible industrial load

• 8,500 MW of CHP at 1,200 sites in California

Overcoming ‘soft’ barriers for DER

• Data quality and management

• Operational costs, risks and uncertainty

Beyond dynamic pricing – what else is needed

• Sub-metering, flexible capacity payments, two-part rates

55