25
STFC Technology Helical Undulator Status and 2009 Progress Dr Owen Taylor On behalf of the Helical collaboration Collaboration members ASTEC: J.A. Clarke, O.B. Malyshev, D.J. Scott, B. Todd, N Ryder RAL: E. Baynham, T. Bradshaw, J. Rochford, O. Taylor, A Brummit, G Burton, C Dabinett, S. Carr, A Lintern University of Liverpool: I.R. Bailey, J.B. Dainton, P. Cooke, T. Greenshaw, L. Malysheva DESY: D.P. Barber University of Durham: G.A. Moortgat-Pick Argonne: Y. Ivansuhenkov

STFC Technology Helical Undulator Status and 2009 Progress Dr Owen Taylor On behalf of the Helical collaboration Collaboration members ASTEC: J.A. Clarke,

Embed Size (px)

Citation preview

Page 1: STFC Technology Helical Undulator Status and 2009 Progress Dr Owen Taylor On behalf of the Helical collaboration Collaboration members ASTEC: J.A. Clarke,

STFC Technology

Helical Undulator Status and 2009

ProgressDr Owen Taylor

On behalf of the Helical collaboration

Collaboration membersASTEC: J.A. Clarke, O.B. Malyshev, D.J. Scott, B. Todd, N RyderRAL: E. Baynham, T. Bradshaw, J. Rochford, O. Taylor, A Brummit, G Burton, C Dabinett, S. Carr, A LinternUniversity of Liverpool: I.R. Bailey, J.B. Dainton, P. Cooke, T. Greenshaw, L. Malysheva DESY: D.P. BarberUniversity of Durham: G.A. Moortgat-Pick Argonne: Y. Ivansuhenkov

Page 2: STFC Technology Helical Undulator Status and 2009 Progress Dr Owen Taylor On behalf of the Helical collaboration Collaboration members ASTEC: J.A. Clarke,

2

Slide titleScope of Presentation

•Magnet alignment

•Recap

• Cryogenic leak

• Magnet test

•Introduction

• Undulator requirements and specification

• 4 metre module prototype manufactured

•Excessive heat loads

• Effects of heat load

• Attempts to fix heat load

•Future plans

• Show magnet working in cryostat with re-condensation

• Investigate beam heating effects

Page 3: STFC Technology Helical Undulator Status and 2009 Progress Dr Owen Taylor On behalf of the Helical collaboration Collaboration members ASTEC: J.A. Clarke,

3

Slide titleILC requirements

Undulator :

To produce a circularly polarised positron beam

•High energy electron beam through helical undulator

•emission of polarised photons.

•Downstream high Z target, pair production

•Positrons stripped off to produce polarised positron beam.

Page 4: STFC Technology Helical Undulator Status and 2009 Progress Dr Owen Taylor On behalf of the Helical collaboration Collaboration members ASTEC: J.A. Clarke,

4

Slide titleIntro: Magnet Specification

Following a pretty extensive R&D programme and modelling study the following specification was developed for the undulators:

Undulator Period 11.5 mm Field on Axis 0.86 TPeak field homogeneity <1%Winding bore >6mmUndulator Length 147 mNominal current 215ACritical current ~270A Manufacturing tolerances

winding concentricity 20µmwinding tolerances 100µmstraightness 100µm

NbTi wire Cu:Sc ratio 0.9 Winding block 9 layers

7 wire ribbon This defines the shortest period undulator we could build with a realistic operating margin.

Page 5: STFC Technology Helical Undulator Status and 2009 Progress Dr Owen Taylor On behalf of the Helical collaboration Collaboration members ASTEC: J.A. Clarke,

5

Slide titleIntro: 4 m Prototype

•150 m of undulator•Module length

• Vacuum considerations < 4 m• Collimation < 4 m• Magnet R&D 2 m section

realistic•Minimise number of modules

• 2 magnet sections per moduleCryogenic system

•Magnets cooled in liquid helium bath

•Re-condensing system utilising a thermo siphon

Page 6: STFC Technology Helical Undulator Status and 2009 Progress Dr Owen Taylor On behalf of the Helical collaboration Collaboration members ASTEC: J.A. Clarke,

6

Slide titleRecap: Cryogenic Leak

Created a large open Liquid nitrogen bath

Found a leak at the indium seal between magnets

Fixed this by modifying the clamp arrangement

More worryingly - leak through the magnet structure

Leak fix with a silver soldered copper-iron Bi metal ring

Implemented this solution on some test pieces and it has survived 20 thermal cycles.

Each magnet joint then thermally cycled and tested 10+ times

Final leak check: <1e-12mb/ls in the beam tube vessel at temps <77K

Leak path

Page 7: STFC Technology Helical Undulator Status and 2009 Progress Dr Owen Taylor On behalf of the Helical collaboration Collaboration members ASTEC: J.A. Clarke,

7

Slide titleRecap: Magnet Testing

Field maps along the

length of the undulator

Current leads

LHe

undulator

Stepper motor

Screw mechanism

Bx

By

Quench testing both magnets deliver nominal field

Magnet rigidity – iron yoke

Page 8: STFC Technology Helical Undulator Status and 2009 Progress Dr Owen Taylor On behalf of the Helical collaboration Collaboration members ASTEC: J.A. Clarke,

8

Slide titleActive alignment system

Axis alignment

1mm

Magnet straightness

•Prototype alignment

+/-200 µm in X

+/-170 µm in Y

•Not adequate to deliver a straightness of +/-50 µm

•Developed an active alignment Yoke

•Allows the straightness of the magnet to be aligned to better than 50 µm.

•In principle the proto type can be retrofitted with this system at a later date.

M2 X horizontal M1

-0.25-0.20-0.15-0.10-0.050.000.050.100.150.200.25

0 500 1000 1500 2000 2500 3000 3500 4000axial position (mm)

Dis

plac

emen

t (m

m)

M2 Y vertical M1

-0.25-0.20-0.15-0.10-0.050.000.050.100.150.200.25

0 500 1000 1500 2000 2500 3000 3500 4000axial position (mm)

Dis

plac

emen

t (m

m)

Page 9: STFC Technology Helical Undulator Status and 2009 Progress Dr Owen Taylor On behalf of the Helical collaboration Collaboration members ASTEC: J.A. Clarke,

9

Slide titleActive alignment system

Active alignment system

Relies on the flexibility of the magnet

Over sized yoke aperture for the magnet allowing 100 μm clearance

Periodically placed adjustors allowing adjustment in X and Y

After adjustment actuators locked off, a small spring maintains alignment and takes up the thermal contraction when cold

Small contact pads around the magnet to spread contact pressure and avoid damage to winding

All components are magnetic steel to minimise any losses in the iron circuit

Manufactured 1/2 metre long test section

Getting some metrology data with this at the moment

Our initial tests shows we can position the magnet to within +/- 10 μm at the actuator point

Page 10: STFC Technology Helical Undulator Status and 2009 Progress Dr Owen Taylor On behalf of the Helical collaboration Collaboration members ASTEC: J.A. Clarke,

10

Slide titleHeat Load

There has been an excessive heat load on the helium bath

• This has caused a large boil off of liquid helium – should be no boil off in re-condensing system

• Low temperature superconductor section of current lead too hot

There have been many attempts to identify and remove unwanted heat loads

So far, these modifications have made little effect

Current lead

Page 11: STFC Technology Helical Undulator Status and 2009 Progress Dr Owen Taylor On behalf of the Helical collaboration Collaboration members ASTEC: J.A. Clarke,

11

Slide titleHeat load audit

Heat Loads

77KSupports Bellows Current Leads Radiation Radiation turretload 130 kg id 0.01 m number 4 diameter 0.3 m diameter 0.3 m

1300 N od 0.02 m Q/lead 12 Length 4 m Length 0.5 mstress 30 Mpa convolution 0.004 m Lead opt 216 Area 3.77 m 2̂ Area 0.47 m 2̂area 43.3 mm 2̂ L 0.03 mlength 0.1 m Leff 0.105 m q 1 W/m 2̂ q 1 W/m 2̂Int kdt 100 W/m/K t 0.0005 m# supports 4 A 2.36E-05 m 2̂dia 3.71 mm 2̂ Int kdt 2800 W/m/K

# bellows 2Q 0.04 W Q 1.26 Q 48 Q 3.77 W Q 0.47 W

total53.5 W

4.5K

Supports Bellows Current Leads feed thros J oints turret Radiation Radiation turretload 130 kg id 0.01 number 4 rho 300K 1.6E-08 resistance 1E-07 diameter 0.2 m diameter 0.2 m

1300 N od 0.02 Q/lead 0.065 RRR 100 I 250 Length 4 m Length 0.5 mstress 10 Mpa convolution 0.004 Lead 500 rho 4K 1.6E-10 Area 2.51 m 2̂ Area 0.31 m 2̂area 130 mm 2̂ L 0.03 rod dia 0.006 mlength 0.25 m Leff 0.105 m rod length 0.04 m q 0.2 W/m 2̂ q 0.2 W/m 2̂Int kdt 110 W/m/K t 0.0005 R 2.3E-07 Ohm# supports 4 A 2.36E-05 m 2̂ I 250 Adia 6.43 mm 2̂ Int kdt 300 W/m/K number 4 number 8

# bellows 2Q 0.06 W Q 0.13 Q 0.26 P 0.05659 W P 0.05 W Q 0.50 W Q 0.06 W

totalno intercept 1.1 W

Cryogenic system

•Magnets cooled in liquid helium bath

•Re-condensing system with Sumitomo RDK4150

•Weak thermal link between bath and condenser

•Final stage charge system with liquid

Heat load inventory

•50 W on rad shield

•1 W helium bath

He Fill Thermal anchor

HTS lead

Ln2 pre-cooling

He vent

0.5 W contingency

Page 12: STFC Technology Helical Undulator Status and 2009 Progress Dr Owen Taylor On behalf of the Helical collaboration Collaboration members ASTEC: J.A. Clarke,

12

Slide titleApril 2009 Cool Down

0

20

40

60

80

100

120

-3.5

-3

-2.5

-2

-1.5

-1

0 5 10 15 20 25 30

04.24 Helium level [litres]

04.24 Heat load [W]

Hel

ium

leve

l [li

tres

]

Heat load [W

]

Time [hours]

2009.04.24 Heat loadSystem cooled down in April 2009

2 big issues• Large liquid helium boil off• Low Temperature

Superconductor (LTS) section of current lead suspected to be at 6 K, not 4 K

• LTS tail would have been normal, damage to tails of both magnets

Fixes• Ensure HTS ends ~4.2 K• Implement a shunt to protect

LTS lead when normal• Add some thermometry

~2.5 W heat load!If 1.5 W re-

condensing is working, total heat load = 4 W

Page 13: STFC Technology Helical Undulator Status and 2009 Progress Dr Owen Taylor On behalf of the Helical collaboration Collaboration members ASTEC: J.A. Clarke,

13

Slide titleApril 2009 - Copper shunts added to

LTS cooling improved

AB temperature sensor - all HTS 4K ends

LTS cooling and shunt

Before April 2009 cool down

LTS straight from vacuum feed through to HTS

HTS cooled by braid as shown

Page 14: STFC Technology Helical Undulator Status and 2009 Progress Dr Owen Taylor On behalf of the Helical collaboration Collaboration members ASTEC: J.A. Clarke,

14

Slide titleJune 2009 - Helium Vent pipe repair

During re-build it was noticed that Helium vent pipe incorrectly manufactured

The ‘Anti-Oscillation Damper’ (ATO) was fitted upside-down!

Allows large convective path from 300 K into 4 K liquid

This was cut out and re-welded

Page 15: STFC Technology Helical Undulator Status and 2009 Progress Dr Owen Taylor On behalf of the Helical collaboration Collaboration members ASTEC: J.A. Clarke,

15

Slide titleJune 2009 - Liquid Nitrogen Pre-Cooling

Lines Removed

Thigh 66Tlow 4.2Outer Diam 0.012Inner Diam 0.006Length 0.05

x-sect area 8.5E-05Number 2

Total area 1.70E-04Int Hi SS 232.640Int lo SS 0.242Difference 232.397

Load W 0.79

conduction intoplate 0.79

Liquid n2 line

Does not include conduction down N2 ice

During the subsequent re-build it was decided to disconnect the nitrogen pre-cooling lines

Could potentially add 0.8 W heat load

Page 16: STFC Technology Helical Undulator Status and 2009 Progress Dr Owen Taylor On behalf of the Helical collaboration Collaboration members ASTEC: J.A. Clarke,

16

Slide titleJuly 2009 Cool Down

0

20

40

60

80

100

120

140

-2.6

-2.4

-2.2

-2

-1.8

-1.6

-1.4

0 5 10 15 20 25 30 35 40

Helium level Heat load

Hel

ium

leve

l [li

tres

] Heat load [W

]

Time zero [hours]

2009.07.09 - 2009.07.22 Heat Load

System cooled down in July 2009

Re-condensation does not work - system pressurizing rapidly

Still ~2 W (3.5 W total) heat load!

•All voltage developed was across LTS •Temp of LTS shunt was 7 K plus•Helium bath top plate also 7 K plus•LTS damaged again

Page 17: STFC Technology Helical Undulator Status and 2009 Progress Dr Owen Taylor On behalf of the Helical collaboration Collaboration members ASTEC: J.A. Clarke,

17

Slide titleAugust - 2009 Heat load on helium bath top plate

For equilibrium the load through the bolts and knife edge must = 260 mW

For this to happen temp of top plate is ~7 K. Very similar to that seen by A-Bradleys

260mW in

Helium at 4.2K

260mW out

Thigh 60 Thigh 60 Thigh 6.8 Thigh 6.8Tlow 6 Tlow 6 Tlow 4.2 Tlow 4.2op current (A) 215 Outer Diam 0.04 Outer Diam 0.222 Outer Diam 0.008

Inner Diam 0.036 Inner Diam 0.216 Inner Diam 0Number 4 Length 0.659 Length 0.0065 Length 0.024

x-sect area 2.4E-04 x-sect area 2.1E-03 x-sect area 5.0E-05Number 1 Number 1 Number 24

Cond @ 215A 0.039 degradation for touching contact 1 degradation for touching contact1Joule heat @215A 0.009 Total area 2.39E-04

Int Hi SS 193.508 Total area 2.06E-03 Total area 1.21E-03Int lo SS 0.667 Int Hi SS 0.951 Int Hi SS 0.951Difference 192.841 Int lo SS 0.242 Int lo SS 0.242

Cond @ 320A 0.058 Difference 0.709 Difference 0.709Joule heat @320A 0.022

Load W 0.19 Load W 0.07 Load W 0.23 Load W 0.04

conduction intoplate 0.26 conduction outofplate 0.26

StSt boltsStSt knife edgeCurrent leads Liquid He vent (60k-4k)

depth of

knife edge

Knife edge Id=216 mm , od=222mm

Conduction Length of

bolt

24 mm

Q via

4 current leads 156mW static conduction

190mw with joule heating at 215A

Q via Vent

Pipe 70mW

Page 18: STFC Technology Helical Undulator Status and 2009 Progress Dr Owen Taylor On behalf of the Helical collaboration Collaboration members ASTEC: J.A. Clarke,

18

Slide titleAugust 2009 - Copper ‘C’clamps added to top plate

With copper ‘C’ clamps, top plate should be no more than 4.3 K

Page 19: STFC Technology Helical Undulator Status and 2009 Progress Dr Owen Taylor On behalf of the Helical collaboration Collaboration members ASTEC: J.A. Clarke,

19

Slide titleSeptember 2009 Cool Down

0

2

4

6

8

10

12

14

16

0

20

40

60

80

100

120

140

250 260 270 280 290 300

31-aug-2009 to 10-sept-2009 12:20:48 05/10/2009

HTS 4.2 K endHe-Vess Topplate

Helium level [litres]

Tem

pera

ture

[K

]

Helium

level [litres]

Time [hours]

90 litres

13.6 K

9.6 K

0

2

4

6

8

10

12

14

16

0

20

40

60

80

100

120

140

124 128 132 136 140

9th july 2009 to 15 july 2009 14:29:27 05/10/2009

HTS 4.2 K endHelium-Vess Topplate

Helium level [litres]

Tem

pera

ture

[K

]

Helium

level [litres]

Time [hours]

90 litres

10.8 K

13.4 K

0

20

40

60

80

100

120

-3.5

-3

-2.5

-2

-1.5

-1

0 5 10 15 20 25 30 35 40

2009.04.242009.07.212009.09.10

2009.04.242009.07.212009.09.10

Hel

ium

leve

l [lit

res] H

eat load [W]

Time [hours]

Heat loads at different times

No Difference!Top plate and LTS shunt at

same temperatureKnife edge theory not correct

July Cool Down

SeptemberCool Down

• Boil off has not been altered• Always ~ 2 W above that of

the cold heat re-condensation

Page 20: STFC Technology Helical Undulator Status and 2009 Progress Dr Owen Taylor On behalf of the Helical collaboration Collaboration members ASTEC: J.A. Clarke,

20

Slide titleWhere is the heat leak?Helium bath location pins

To minimise heat leak into helium bath, the helium bath location pins were removed

The heat load from radiation through two 7 cm x 3 cm holes at300 K amounts to ~2.0 W

The thermal conductivity ~1 W worst case

Page 21: STFC Technology Helical Undulator Status and 2009 Progress Dr Owen Taylor On behalf of the Helical collaboration Collaboration members ASTEC: J.A. Clarke,

21

Slide titleOctober 2009 Cool Down Different methods of pre-cooling

0

50

100

150

200

250

300

0 0.5 1 1.5 2

Mag

net T

empe

ratu

re [

K]

Time [days]

29-sept-2009

70 litres of LN2 pre-cool

70 litres of LN2 pre-cool

Some LN2 still present

Magnet warmed with bore heater

Cooled with 100 litres of LHe

0

50

100

150

200

250

300

0 2 4 6 8

Mag

net T

empe

ratu

re [

K]

Time [days]

31-aug-2009

Cooled with 100 litres of LHe

Cooled with a further 50 litres LHe

Cold head turned on

Boil off from LHe dewar admitted

LHe dewar empty

The magnet was pre-cooled with the re-condensing cold head

9 days to cool magnet to 4 K150 litres of liquid helium used to

reach 4 K

The magnet was pre-cooled with liquid nitrogen

2.5 days to cool magnet to 4 K100 litres of liquid helium used to

reach 4 K

September Cool Down

OctoberCool Down

However, due to re-condensing design, difficult to remove nitrogen and a blockage occurred – system had to be warmed again

Page 22: STFC Technology Helical Undulator Status and 2009 Progress Dr Owen Taylor On behalf of the Helical collaboration Collaboration members ASTEC: J.A. Clarke,

22

Slide titleCurrent status

Pre production rods were tested to >1.5 kN at 77 K

Carbon magnet support rods have failedOne end of magnet dropped by ~15 mm -

Bonded joints on both CF rods had failed at 4 K end.

Once carbon rods are fixed, will cool down againCheck boil off (i.e. heat load)Test magnetInvestigate bore heating effects

Page 23: STFC Technology Helical Undulator Status and 2009 Progress Dr Owen Taylor On behalf of the Helical collaboration Collaboration members ASTEC: J.A. Clarke,

23

Slide titleWhere is the heat leak?Other Concerns

0

10

20

30

40

50

60

70

0

5

10

15

20

25

30

0 8 16 24 32 40 48 56

Temperature

Width

Tem

pera

ture

[K

] Width [m

m]

Length [mm]

He Bath (4 K)

Rad shield (70 K)

Some worry, radiation shield supports from helium bath may have a larger heat load than originally calculated

~0.13 W each~1.5 W for 12 in totalThis is worst case scenario,

probably much less – MLI barrier

Outer can (300 K)

G10 Supports

G10 Ring at 70 K ??

Stainless steel at 4 K

Thermal contact

unknown

Central support ring has an unknown heat load

Page 24: STFC Technology Helical Undulator Status and 2009 Progress Dr Owen Taylor On behalf of the Helical collaboration Collaboration members ASTEC: J.A. Clarke,

24

Slide titleFuture plans - “Beam heating” test

“Beam heating” test planned

Chain of resistors in evacuated bore to simulate beam heating effects

From Duncan’s thesis the calculated heat loads span range 0.1 W to 1.4 W per module

Current experiment can apply 0 to 2.5 W inside the bore of the magnet

The intention is to run the magnets at their nominal field wind up the power in steps until the magnet quenches

This gives a measure of the peak power the magnets can sustain

Page 25: STFC Technology Helical Undulator Status and 2009 Progress Dr Owen Taylor On behalf of the Helical collaboration Collaboration members ASTEC: J.A. Clarke,

25

Slide titleSummary

4 metre prototype has been builtEach 2 metre magnet reaches beyond design fieldThe magnets have a straightness of +/-200 µmThis is greater than the +/-50 µm requiredWith an active alignment system, +/-10 µm achievable

Future workShow magnet running in cryostat with re-condensationBore heater tests to simulate beam heating effects

Cryogenic issues There have been ‘cryogenic’ leaks that have now been fixed There is a heat leak greater than originally expected causing

-High helium boil off-Low temperature superconductor too warm to pass operating currentFixes

Many attempts to fix heat leakNone successful so far – latest ideas seem more plausible