14
Rodd Pope, SLAC Undulator System Assembly [email protected]. edu April 20-21, 2006 FAC Meeting 1 Undulator System Assembly Plans Rodd Pope, SLAC In collaboration with Catherine LeCocq, SLAC Metrology & Geoff Pile, ANL

Undulator System Assembly Plans

  • Upload
    samara

  • View
    24

  • Download
    0

Embed Size (px)

DESCRIPTION

Undulator System Assembly Plans. Rodd Pope, SLAC In collaboration with Catherine LeCocq, SLAC Metrology & Geoff Pile, ANL. Outline. Roles and Responsibilities ANL, SLAC Metrology, SLAC Undulator Assembly System Design & Requirements Assembly Plan Outline Facility Space Management Schedule - PowerPoint PPT Presentation

Citation preview

Page 1: Undulator System Assembly Plans

Rodd Pope, SLAC

Undulator System Assembly [email protected]

April 20-21, 2006 FAC Meeting1

Undulator System Assembly Plans

Rodd Pope, SLAC

In collaboration with Catherine LeCocq, SLAC Metrology & Geoff Pile, ANL

Page 2: Undulator System Assembly Plans

Rodd Pope, SLAC

Undulator System Assembly [email protected]

April 20-21, 2006 FAC Meeting2

Outline

Roles and ResponsibilitiesANL, SLAC Metrology, SLAC Undulator Assembly

System Design & RequirementsAssembly Plan OutlineFacility Space ManagementScheduleMoving Forward

Page 3: Undulator System Assembly Plans

Rodd Pope, SLAC

Undulator System Assembly [email protected]

April 20-21, 2006 FAC Meeting3

SLACMetrology

ANL

Areas of Expertise Working in Collaboration

October 2005 April 2006

SLACMetrology

ANL

SLAC Assy & Install

Collaboration requires trust. Trust requires effort.

Page 4: Undulator System Assembly Plans

Rodd Pope, SLAC

Undulator System Assembly [email protected]

April 20-21, 2006 FAC Meeting4

Collaboration Roles and Responsibilities(abridged)

ANLDesign the System and Sub-assemblies minus WPM/HLSSupply Designed Sub-assembliesProvide Expertise

SLAC MetrologyDesign and Supply WPM/HLS SystemDevelop and Test Fiducialization ProceduresProvide Expertise

SLAC Assembly & InstallationGirder Assembly PlanSystem Installation PlanMaterial Handling and StorageProvide Expertise

Page 5: Undulator System Assembly Plans

Rodd Pope, SLAC

Undulator System Assembly [email protected]

April 20-21, 2006 FAC Meeting5

SLAC Assembly Supervisor

Requisition postedInterviews are nearly completeAn offer should be extended the week of April 24th

Responsibilities will include:Material handling and assembly planning and executionAssembly and QA documentationSpace and personnel resource planning

Page 6: Undulator System Assembly Plans

Rodd Pope, SLAC

Undulator System Assembly [email protected]

April 20-21, 2006 FAC Meeting6

Undulator System Girder Assembly

Field Installation

Precise/Vacuum Assembly performed in a control environment

Page 7: Undulator System Assembly Plans

Rodd Pope, SLAC

Undulator System Assembly [email protected]

April 20-21, 2006 FAC Meeting7

Intra-girder Component Alignment

PRD 1.4-001 r3

Page 8: Undulator System Assembly Plans

Rodd Pope, SLAC

Undulator System Assembly [email protected]

April 20-21, 2006 FAC Meeting8

Girder Assembly

PrerequisiteAll necessary components fiducialized

Stands aligned in all staging areas

Outside MMF (possibly in Building 750) following the SPEAR3 Approach as suggested by Richard M. Boyce

Station 1 Prepare Girder: Mount CAM wedges under girder

Station 2 Component Installation, part 1

roll-away slides, component supports

HLS & WPM components

undulator vacuum chamber

Station 3 Component Installation, part 2

quadrupole, BFW and BPM

Station 4 Wiring / Plumbing

In the Controlled Environment of the MMF Station 1 Optical Alignment

Station 2 CMM

Storage LeCocq, Catherine, October 27-28,

2005, FAC Meeting, Slide 13

Page 9: Undulator System Assembly Plans

Rodd Pope, SLAC

Undulator System Assembly [email protected]

April 20-21, 2006 FAC Meeting9

Girder Assembly Flow

Page 10: Undulator System Assembly Plans

Rodd Pope, SLAC

Undulator System Assembly [email protected]

April 20-21, 2006 FAC Meeting10

Possible Assembly & Storage Spaces

B033 - GLAST B006 – SSRL/ILC Requires Cleanout ($)

B750 – Access may be limited by construction

B081 - MMF

Page 11: Undulator System Assembly Plans

Rodd Pope, SLAC

Undulator System Assembly [email protected]

April 20-21, 2006 FAC Meeting11

SLAC Magnetic Measurement FacilityWolf, Zachary, LCLS Management Presentation, April 11, 2006, Slide 3

Floor plan divided into three functional areasMagnetic Measurements (± 0.1º C)Fiducialization and Assembly (± 1º C)Storage (± 2.5º C)

Assembly Area

Storage and Queuing

LCLS-TN-04-1

Page 12: Undulator System Assembly Plans

Rodd Pope, SLAC

Undulator System Assembly [email protected]

April 20-21, 2006 FAC Meeting12

Undulator Magnet Storage

All 40 undulator magnets could be stored in the MMF storage area.

Page 13: Undulator System Assembly Plans

Rodd Pope, SLAC

Undulator System Assembly [email protected]

April 20-21, 2006 FAC Meeting13

Component Delivery & Assembly Schedule

Page 14: Undulator System Assembly Plans

Rodd Pope, SLAC

Undulator System Assembly [email protected]

April 20-21, 2006 FAC Meeting14

Moving Forward

Solidify Component Delivery Dates

Refine Assembly Process with SUT Experience

The activities and logic in the P3 assembly plan are reasonable.

The resources assigned to the tasks are being reviewed.

Secure Assembly and Storage Space

Material handling equipment design and procurement is behind schedule

Addition of SLAC Assembly Supervisor