23
GROUPE 3 1 Example 3: Detention Pond Design

Soutenance 3AGC2.pptx

Embed Size (px)

Citation preview

Page 1: Soutenance 3AGC2.pptx

GROUPE 3

1

Example 3: Detention Pond Design

Page 2: Soutenance 3AGC2.pptx

Plan

1. Problem Statement

2. System Representation

3. Model Setup

4. Model Results

5. Summary

6. Conclusion 2

Page 3: Soutenance 3AGC2.pptx

Problem statement This example illustrates how to define, design, and evaluate a

detention pond using SWMM.

Detention pond for the post-development site3

Page 4: Soutenance 3AGC2.pptx

System Representation • Defining the site after development (the designation of areas

representing the seven sub catchments). • Identifying the location of the pond and the network in which water

runoffs.

Study area map with storage unit SU14

Page 5: Soutenance 3AGC2.pptx

System Representation

• The main elements used to design detention ponds in SWMM are:

Storage Units: described by a Storage Curve, an Evaporation Factor can be specified, and a Maximum Depth of storage must be defined.

Orifices: can be used to represent the opening along the side or bottom of the storage unit that serves as an outlet

Weirs: represent the opening at the top of the storage unit that serves as an overflow structure.

5

Page 6: Soutenance 3AGC2.pptx

Model SetupRunoff will be detained in

separate sections of the detention pond. Both sections will have the shape of a trapezoidal prism.

The upper prism will control the major storms (return periods: 10 years and 100-yr) while the lower prism will control the minor storms (WQCV and 2-yr). 6

Schematic Representation of a detention Pond

Page 7: Soutenance 3AGC2.pptx

Model SetupConception Steps:

– Calculating the site’s average percent imperviousness.

– Determining the WQCV in watershed inches.– Identifying Pond dimensions.

7Geometry of the pond’s WQCV

Page 8: Soutenance 3AGC2.pptx

Model Setup Conception Steps:

– Add a Storage Unit to the Model

• Size the WQCV Orifice “the entire WQCV is released within 40 hours” , so we

simulate that in 4 iterations. 8

Page 9: Soutenance 3AGC2.pptx

Personal Work

9

Page 10: Soutenance 3AGC2.pptx

Personal Work

10

Page 11: Soutenance 3AGC2.pptx

Personal Work

11

Page 12: Soutenance 3AGC2.pptx

Personal Work

12

Results from SWMMFigure from QA

Comparison of Flow Through the Bottom Orifice of Example

EXTRAN3

Page 13: Soutenance 3AGC2.pptx

Personal Work

13

Page 14: Soutenance 3AGC2.pptx

Personal Work

14

Figure from QA Results from SWMM

Comparison of Water Depth at the Inlet Node of the Orifice inExample EXTRAN3

Page 15: Soutenance 3AGC2.pptx

Personal Work

15

Page 16: Soutenance 3AGC2.pptx

Personal Work

16

Figure from QA Results from SWMM

Flow Comparison for Link 1570 of Example EXTRAN3

Page 17: Soutenance 3AGC2.pptx

Personal Work

17

Page 18: Soutenance 3AGC2.pptx

Personal Work

18

Figure from QA Results from SWMM

Flow Comparison for Link 1570 of Example EXTRAN3

Page 19: Soutenance 3AGC2.pptx

Model SetupConception Steps:

– So after doing the 4

iterations we obtain

a curve which shows

the change in water

depth upstream of

the storage unit.

19

WQCV drainage time for the 4 iterations

Page 20: Soutenance 3AGC2.pptx

Model Setup

Outlet hydrographs for the 10-yr storm

Outlet hydrographs for the 100-yr storm

20Impact of urbanisation

Page 21: Soutenance 3AGC2.pptx

Model Results

• The final SWMM model for the post-development site with the detention pond is shown in this picture.

21Details of the outlet structure

Page 22: Soutenance 3AGC2.pptx

Summary

This table summarizes the characteristics of the different discharge elements included in the pond’s outlet.

Characteristics of the pond’s outlet structure 22

Page 23: Soutenance 3AGC2.pptx

Conclusion

This example showed how SWMM could be used to design a

detention pond and its outlet structure to provide both a

water quality capture volume (WQCV) and peak runoff control.

The WQCV was designed to provide a 40 hour drawdown time

to satisfy water quality treatment requirements while the peak

runoff goal was to limit the maximum post-development

discharges for the 2-, 10- and 100-yr storms to their pre-

development values.

23