Introduction

Project System is part of SAP‘ssolution for Project and PortfolioManagement. Project Systemhelps you manage the projectthrough its entire life cycle, fromsetting up a structure, to drawingup detailed plans, to execute andcompleting the project.

Because of its tight integrationinto financial and logistic coreenterprise processes ProjectSystem can especially be usedfor large and complex projectssuch as construction, production,maintenance, investment, orcosts projects in all industries.

Project Builder and Project Planning Board

Page 3: SAP Project System - Overview.pdf

Project Structuring

In Project System you can use WorkBreakdown Structures (WBS) andNetworks to structure your projectshierarchical and/or using networktechniques. Milestones anddocuments help you to mark projectevents of particular interest anddocument your project appropriate.

You can set up project structuresmanually or based on templates.Project structures can also becreated automatically from salesdocuments or cProjects projects forexample.

Using access control lists, partnerdata and persons responsible youcan easily define authorizations andresponsibilities for project elements.

Graphical Display of WBS and Networks

Page 4: SAP Project System - Overview.pdf

Project Scheduling

Project System provide various dateplanning functions. Flexible schedulingtechniques can be used to calculateearliest/latest dates, floats or criticalpaths within projects.

Dependent dates, such as requirementdates of materials, services orcapacities, billing dates or periods ofplanned costs can automatically bederived from planned dates.

Comparing forecasted, planned andactual dates you can easily identifydeviations from your project plan.

Additional tools such as ProgressTracking, Subnetwork Monitor,Simulations or Milestone TrendAnalysis enables you to manage thedates of your projects efficiently. Progress Tracking and Project Planning Board

Page 5: SAP Project System - Overview.pdf

Capacity and Workforce Planning

Networks in Project System enablesyou to plan, analyze and level workcenter based capacity requirementsof your project.

You can use simulation versions forwhat-If analysis of your projectschedules and capacity requirements.

For detailed workforce planning youcan assign organizational units orindividual personel resources to workpackages of your project.

Because of the tight integration ofProject System to Human CapitalManagement you can directly accessthe availability or even qualificationsof employes if required duringworkfore planning.

Capacity Leveling and Workforce Planning

Page 6: SAP Project System - Overview.pdf

Material and External Service Planning

If you assign material components toNetworks you can plan materialrequirements based on your projectschedule, check the materialavailability and trigger the materialprocurement and delivery later on.

Functions such as project specific billsof material, bill of material transfer, theopen catalog interface or integrationsto Integrated Product and ProcessEngineering (iPPE) helps you to planmaterials efficiently in Project System.

In order to plan external services youcan directly use purchasing inforecords, outline agreements or servicespecifications from MaterialsManagement in Project System. Theopen catalog interface allows you toselect services also from internal orexternal service catalogs. Material Components in the Project Builder

and Service Specification

Page 7: SAP Project System - Overview.pdf

Financial Planning

You can use various techniques forplanning costs and revenues in ProjectSystem depending on your financialplanning requirements.

So the cost planning capabilities forexample range from overall costplanning to Easy Cost Planning ordetailed network costing.

Sales Pricing helps you to createquotations for customer projects basedon the planned costs.

Project milestones can be used to derivebilling dates automatically from theproject schedule.

Project System cash management alsoallows you to plan and monitor incomingand outgoing payments for projects.

Overall Cost Planning and Easy Cost Planning

Page 8: SAP Project System - Overview.pdf

Budget Management

Budget is the approved coststructure for a project. You canallocate budget to projects inInvestment Management ordirectly in Project System.

Budgets can be distributedhierarchically within the projectstructure. If required you cansuccessively release budgetsand post updates, such asbudget supplements or returns.

Budget availability controlenables you to control costsactively by issuing warnings anderror messages when tolerancelimits of the budget are exceededbecause of assigned values.

Allocation and Mass Release of Project Budgets

Page 9: SAP Project System - Overview.pdf

Confirmations

In the execution phase of projectsconfirmations can be used todocument the actual workperformed and the progress ofindividual work packages.

Using confirmations you can alsoenter forecast information such asthe remaining work or duration.

Because of confirmations thedates and capacity requirementsof your project will be adapted andactual costs are postedautomatically to the project.

Project System provides variousconfirmation options includingindividual and collectiveconfirmations, integration to theCross Application Time Sheet(CATS) or external interfaces. CATS and Individual Confirmation

Page 10: SAP Project System - Overview.pdf

Project Related Procurement

Reservations or purchaserequisitions can automatically becreated for a project based on yourmaterial and external serviceplanning.

You can easily track all follow up in-house production and purchasingprocesses related to your project forexample using the ProMan orProgress Tracking.

Commitments and actual costsbecause of purchasing documents,material movements or invoices areautomatically posted to the project.

Valuated project stock helps you tomanage and valuate material in yourproject independently if required.

ProMan and Progress Tracking

Page 11: SAP Project System - Overview.pdf

Cost Integration and Billing

Costs actually incurred are posteddirectly to your project by accountassignment of documents inFinanical Accounting, Controllingor Materials Management forexample.

Using Execution Services you canalso directly post variousdocuments in Easy Cost Planningbased on planned values.

Costs of orders assigned to yourproject can be analyzed in projectreporting and will be checkedagainst the project budget.

Milestone billing and resourcerelated billing can be used incustomer projects to control billingprocesses based on the projectprogress. Execution Services and Resource Related Billing

Page 12: SAP Project System - Overview.pdf

Claim Management and Workflows

Project System supports ClaimManagement using a notification typecalled "claim". You can use claims todocument variances from your projectplan, name the person responsible,and initiate follow-up activities.

Costs that are caused by a deviationcan be planned using claims andintegrated into your project plan.

Standard workflows can be used inClaim Management for approvalprocesses.

Other standard workflows areavailable in Project System in order tonotify persons responsible in case ofdeviations affecting purchase ordersor project capacity and date planning. Workflow because of Network Changes Affecting

Purchase Orders and Claim Management

Page 13: SAP Project System - Overview.pdf

Project Progress

Milestone trend analysis andProgress Tracking can be used toeffectively monitor the projectschedule.

Progress Analysis in ProjectSystem provides several methodsand interfaces to derive andanalyze the POC and other projectprogress values of your project orindividual work packages.

Using the Progress AnalysisWorkbench you can easily monitorand enter all progress related datafor several projectssimultaneously.

Forecast values can be calculatedor entered manually using theForecast Workbench for example. Progress Analysis Workbench and

Milestone Trend Analysis

Page 14: SAP Project System - Overview.pdf

Period-End Closing

You can perform various period-end closing procedures on yourproject to ensure that all projectdata belonging to a period isdetermined and available forpurposes of enterprise control.

Typical period-end closingprocedures for projects are:

Overhead calculationTemplate allocationProject interest calculationProgress and results analysisProject related incoming orderanalysisSettlement

You can use the ScheduleManager to easily plan, carry outand control your period-endclosing procedures. Overhead Calculation and Schedule Manager

Page 15: SAP Project System - Overview.pdf

Project Reporting

Project System provides variousstandard reports for realtimereporting of financial and logisticproject data as well as predefined BIcontent.

Using report-report interfaces youcan directly navigate from one reportto other more detailed reports.

You can also define your own reportsand queries depending on yourreporting requirements.

Project System reports include:Project and individual structure reportsResource and material reportsHierarchy, cost element and line itemreportsClaim and project progress reports Hierarchy Report and Project Structure Overview

Page 16: SAP Project System - Overview.pdf

Interfaces

Project System provides several optionsto exchange project data with externalsystems. For example you can usevarious BAPIs to export, import ormaintain project data.

Based on the BAPI technology theOpenPS interface allows you tointerchange project data with MicrsosoftProject Client based on predefinedmapping rules.

As of SAP ERP 6.0 EnhancementPackage 3 more than 50 EnterpriseServices are available to interchangeproject data with other systems too.More information on Enterprise Servicesfor Projects can be found on theEnterprise Services Workplace:www.sdn.sap.com/irj/sdn/esworkplace

BAPI Explorer and Enterprise Services Workplace

Page 17: SAP Project System - Overview.pdf

Copyright 2008 SAP AGAll rights reserved

No part of this publication may be reproduced or transmitted in any form or for any purpose without the express permission of SAP AG. The information contained herein may be changedwithout prior notice.Some software products marketed by SAP AG and its distributors contain proprietary software components of other software vendors.SAP, R/3, mySAP, mySAP.com, xApps, xApp, SAP NetWeaver, Duet, Business ByDesign, ByDesign, PartnerEdge and other SAP products and services mentioned herein as well as theirrespective logos are trademarks or registered trademarks of SAP AG in Germany and in several other countries all over the world. All other product and service names mentioned andassociated logos displayed are the trademarks of their respective companies. Data contained in this document serves informational purposes only. National product specifications may vary.

The information in this document is proprietary to SAP. This document is a preliminary version and not subject to your license agreement or any other agreement with SAP. This documentcontains only intended strategies, developments, and functionalities of the SAP® product and is not intended to be binding upon SAP to any particular course of business, product strategy,and/or development. SAP assumes no responsibility for errors or omissions in this document. SAP does not warrant the accuracy or completeness of the information, text, graphics, links, orother items contained within this material. This document is provided without a warranty of any kind, either express or implied, including but not limited to the implied warranties ofmerchantability, fitness for a particular purpose, or non-infringement.

SAP shall have no liability for damages of any kind including without limitation direct, special, indirect, or consequential damages that may result from the use of these materials. This limitationshall not apply in cases of intent or gross negligence.The statutory liability for personal injury and defective products is not affected. SAP has no control over the information that you may access through the use of hot links contained in thesematerials and does not endorse your use of third-party Web pages nor provide any warranty whatsoever relating to third-party Web pages

Weitergabe und Vervielfältigung dieser Publikation oder von Teilen daraus sind, zu welchem Zweck und in welcher Form auch immer, ohne die ausdrückliche schriftliche Genehmigung durchSAP AG nicht gestattet. In dieser Publikation enthaltene Informationen können ohne vorherige Ankündigung geändert werden.Einige von der SAP AG und deren Vertriebspartnern vertriebene Softwareprodukte können Softwarekomponenten umfassen, die Eigentum anderer Softwarehersteller sind.SAP, R/3, mySAP, mySAP.com, xApps, xApp, SAP NetWeaver, Duet, Business ByDesign, ByDesign, PartnerEdge und andere in diesem Dokument erwähnte SAP-Produkte und Servicessowie die dazugehörigen Logos sind Marken oder eingetragene Marken der SAP AG in Deutschland und in mehreren anderen Ländern weltweit. Alle anderen in diesem Dokument erwähntenNamen von Produkten und Services sowie die damit verbundenen Firmenlogos sind Marken der jeweiligen Unternehmen. Die Angaben im Text sind unverbindlich und dienen lediglich zuInformationszwecken. Produkte können länderspezifische Unterschiede aufweisen.

Die in diesem Dokument enthaltenen Informationen sind Eigentum von SAP. Dieses Dokument ist eine Vorabversion und unterliegt nicht Ihrer Lizenzvereinbarung oder einer anderenVereinbarung mit SAP. Dieses Dokument enthält nur vorgesehene Strategien, Entwicklungen und Funktionen des SAP®-Produkts und ist für SAP nicht bindend, einen bestimmtenGeschäftsweg, eine Produktstrategie bzw. -entwicklung einzuschlagen. SAP übernimmt keine Verantwortung für Fehler oder Auslassungen in diesen Materialien. SAP garantiert nicht dieRichtigkeit oder Vollständigkeit der Informationen, Texte, Grafiken, Links oder anderer in diesen Materialien enthaltenen Elemente. Diese Publikation wird ohne jegliche Gewähr, wederausdrücklich noch stillschweigend, bereitgestellt. Dies gilt u. a., aber nicht ausschließlich, hinsichtlich der Gewährleistung der Marktgängigkeit und der Eignung für einen bestimmten Zwecksowie für die Gewährleistung der Nichtverletzung geltenden Rechts.

SAP übernimmt keine Haftung für Schäden jeglicher Art, einschließlich und ohne Einschränkung für direkte, spezielle, indirekte oder Folgeschäden im Zusammenhang mit der Verwendungdieser Unterlagen. Diese Einschränkung gilt nicht bei Vorsatz oder grober Fahrlässigkeit.Die gesetzliche Haftung bei Personenschäden oder die Produkthaftung bleibt unberührt. Die Informationen, auf die Sie möglicherweise über die in diesem Material enthaltenen Hotlinkszugreifen, unterliegen nicht dem Einfluss von SAP, und SAP unterstützt nicht die Nutzung von Internetseiten Dritter durch Sie und gibt keinerlei Gewährleistungen oder Zusagen überInternetseiten Dritter ab.

Alle Rechte vorbehalten.