75
Implementation of modular manufacturing system in garment industry BY B.SUDARSHAN REGD. NO.:120505MEP001 BATCH:2012-13 DEPARTMENT OF MECHANICAL ENGINEERING Under the supervision/guidance of Dr.D. Nageswara Rao Vice chancellor, CUTM. [email protected]

REVIEW-1-6-15 PPT

Embed Size (px)

DESCRIPTION

modular manufacturing

Citation preview

PowerPoint Presentation

Implementation of modular manufacturing system in garment industryby B.SudarshanRegd. No.:120505MEP001Batch:2012-13Department of Mechanical Engineering

Under the supervision/guidance ofDr.D. Nageswara RaoVice chancellor, [email protected]

1 INTRODUCTION:Due to the increasing labor wage in developed countries, the apparel manufacturing has-been migrating from the high wage developed world to low wage developing countries(Bheda, Narag and Singla, 2003). Even though the labor cost is cheaper than in developed countries; due to the specific market nature of the garment industries for example: the short production life cycle, high volatility, low predictability, high level of impulse purchase, the quick market response; garment industries are facing the greatest challenges these days (Lucy Daly and Towers, 2004).This volatility of styles can be addressed only by flexibility in manufacturing. The best way to cope with all these challenges is the implementation of Modular manufacturing. This will serve our purpose of flexibility and save a lot of money by reducing production lead time, reducing the inventory, increasing productivity, training operators for multiple works, and by reducing rework.

Research Problems:Firstly, High WIP in traditional type of batch production is the major problem faced by industries. Due to high WIP the throughput time as well as rework is very high.Secondly, in batch processing flexibility cannot be achieved easily; which is the current demand of garment industry. This is obstructed by the decreasing order size and increasing number of styles. So to meet this requirement production layout should be designed such that it should hold minimum WIP and should be flexible enough to the changing of order.Thirdly, in batch process operators are given specific jobs, so the operator knows one or a few more operations only. Though he (she) may have good skill and can work more efficiently on one (allocated job only) operation; he (she) cannot work immediately on some other operation.This is another need of todays world, because the fashion is changing frequently and the work force should be capable enough to cope with this change. To achieve this operator should be multi-skilled; which can be served by regular training and converting long assembly lines into small manufacturing cells.Research ObjectiveModular manufacturing is an operational strategy oriented towards achieving the shortest possible cycle time by eliminating wastes. The term lean manufacturing is coined tore present half the human effort in the company, half the manufacturing space, half the investment in tools and half the engineering hours to develop a new product in half the time.To meet customer demand on time by eliminating non value added work from the process To minimize the work in process inventory To create flexibility of style changeover To reduce rework percentage To create a pool of multi-skilled operators who can respond quickly for changing style

Research Approach:The initial step in this research is to systematically study and define the history of the Modular manufacturing concept and its different tools and techniques. It will then examine some most used Modular manufacturing tools and techniques. This will be followed by the study of the existing production system of the case company for example the existing production layouts, inventory movement systems, work balancing methods and other different variables which needs to be improved for the betterment of the existing system.To address the current issues of the industry, the researcher tries to find out the standard operation time for each operation by using time study techniques and will try to standardize all the operations. Once the standard operation time is obtained work will be done to find out the best suitable production layout and WIP movement methods, which will help to get flexibility in style changeover, should reduce the production lead time, create operator multi-skilling etc.Basically, this is quantitative research where the researcher is a part of the organization during the study. Kind of WastesAccording to David Magee, (Magee, 2007, p. 67) different kinds of wastes in a process can be categorized in following categories. These wastes reduce production efficiency, quality of work as well as increase production lead time.1. Overproduction Producing items more than required at given point of time i.e. producing items without actual orders creating the excess of inventories which needs excess staffs, storage area as well as transportation etc.2. Waiting Workers waiting for raw material, the machine or information etc. is known as waiting and is the waste of productive time. The waiting can occur in various ways for example; due to unmatched worker/machine performance, machine breakdowns, lack of work knowledge, stock outs etc.3. Unnecessary Transport Carrying of work in process (WIP) a long distance, insufficient transport, moving material from one place to another place is known as the unnecessary transport.4. Over processing Working on a product more than the actual requirements is termed as over processing. The over processing may be due to improper tools or improper procedures etc. The over processing is the waste of time and machines which does not add any value to the final product.5. Excess Raw Material - This includes excess raw material, WIP, or finished goods causing longer lead times, obsolescence, damaged goods, transportation and storage costs, and delay. Also, the extra inventory hides problems such as production imbalances, late deliveries from suppliers, defects, equipment downtime, and long setup times.6. Unnecessary Movement Any wasted motion that the workers have to perform during their work is termed as unnecessary movement. For example movement during searching for tools, shifting WIP etc.7. Defects Defects in the processed parts is termed as waste. Repairing defective parts or producing defective parts or replacing the parts due to poor quality etc.is the waste of time and effort.8. Unused Employee Creativity Loosing of getting better ideas, improvement, skills and learning opportunities by avoiding the presence of employee is termed as unused employee creativity (Liker, 2003, p. 29).Modular Manufacturing Tools and TechniquesSome of the tools areCellular Manufacturing Continuous Improvement Just in Time Total Productive Maintenance Work Standardization Waste Reduction Techniques Value Stream mapping

1.Cellular Manufacturing

A cell/module/unit is a combination of people, equipment and workstations organized in the order of process to flow, to manufacture all or part of a production unit. Following are the characteristics of effective cellular manufacturing practice.1. Should have one-piece or very small lot of flow.2. The equipment should be right-sized and very specific for the cell operations.3. Is usually arranged in a C or U shape so the incoming raw materials and outgoing finished goods are easily monitored.4. Should have cross-trained people within the cell for flexibility of operation.5. Generally, the cell is arranged in C or U shape and covers less space than the long assembly lines.2.Continuous ImprovementAccording to (Gerstein and Rises, 2002, p. 41) Continuous improvement (CI) can be defined as the planned, organized and systematic process of ongoing, incremental and company-wide change of existing practices aimed at improving company performance.Activities and behaviors that facilitate and enable the development of CI include problem-solving, plan-do-check-act (PDCA) and other CI tools, policy deployment, cross-functional teams, a formal CI planning and management group, and formal systems for evaluating CI activities.PDCA cycleThe short description of PDCA cycle is given belowPlan: Identify an opportunity and plan for change.Do: Implement the change on a small scale.Check: Use data to analyze the results of the change and determine whether it made a difference.Act: If the change was successful, implement it on a wider scale and continuously assess the results. If the change did not work, begin the cycle again.3.Just in Time

Just in time is an integrated set of activities designed to achieve high volume production using the minimal inventories of raw materials, work in process and finished goods. Just-in-time manufacturing is a Japanese management philosophy applied in manufacturing. It involves having the right items with the right quality and quantity in the right place at the right time.Pull and Push SystemIn push system, when work is finished at a workstation, the output is pushed to the next station; or, in the case of the final operation, it is pushed on to the final inventory. In this system, work is pushed on as it is completed, with no regard for whether the next station is ready for the work or not. In this way, the WIP is unbalanced in all operations throughout the shop floor (Roy, 2005, p. 174).The push system is also known as the Materials Requirements Planning (MRP) system. This system is based on the planning department setting up a long-term production schedule, which is then dissected to give a detailed schedule for making or buying parts.4. Total Productive MaintenanceMachine breakdown is one of the major headaches for people related to production. There liability of the equipment on the shop floor is very important because if any one of the machines is down the entire shop floor productivity may be nil. The tool that takes care of these sudden breakdowns and awakes maintenance as well as production workers to minimize these unplanned breakdowns is called total productive maintenance.The goal of the TPM program is to increase production, increase employee morale and job satisfaction. (Bisen and Srivastava, 2009, p. 175)Total Productive Maintenance contd.,TPM is set of tools, which when implemented in an organization as a whole gives the best utilization of machines with least disruption of production. The set of tools are called pillars of TPM5S:The first pillar of TPM is called 5S, which organize and cleans work place; this helps to make problems visible and attracts the attentions of everyone. Brief description of 5Selements are as follows:Sort: The first step in making things cleaned up and organized.Set In Order: Organize, identify and arrange everything in a work area.Shine: Regular cleaning and maintenance.Standardize: Make it easy to maintain, simplify and standardize.Sustain: Maintain what has been achieved.Total Productive Maintenance contd.,Autonomous maintenanceThis is about the involvement of production workers in the day to day general maintenance of machines like cleaning, lubricating etc. which saves the time of skilled maintenance person at the same time the production workers are made more responsible to their machines.KaizenKaizen is for small improvements, but carried out on a continual basis and involve all people in the organization. Kaizen requires no or little investment. The principle behind is that a very large number of small improvements are more effective in an organizational environment than a few improvements of large value.Total Productive Maintenance contd.,Planned maintenanceIt addresses the proactive approach of maintenance activities. This involves four types of maintenance namely preventive maintenance, breakdown maintenance, corrective maintenance, and maintenance prevention.Quality MaintenanceIt is aimed towards customer delight through the highest quality and defect free manufacturing. In this system, one has to take care of parts which affect product quality and try to eliminate or modify them to give customer superior quality.TrainingFor this employee need continuous training, ultimately; the entire employee should be multi-skilled and should solve the problem in their area by themselves.5 .Work Standardization

A very important principle of waste reduction is the standardization of work. Standardized work basically ensures that each job is organized and carried out in the same manner; irrespective of the people working on it. In this way if the work is standardized the same quality output will be received even if the worker is changed in process.6 .Waste Reduction TechniquesSome of the waste reduction tools include zero defects, setup time reduction, and line balancing. The goal of zero defects is to ensure that products are fault free all the way, through continuous improvement of the manufacturing process.7. Value Stream mappingOnce waste is identified, then it is easier to make plan to eliminate it. The purpose of VSM is process improvement at the system level. Value stream maps show the process in a normal flow format. However, in addition to the information normally found on a process flow diagram, value stream maps show the information flow necessary to plan and meet the customers normal demands. Other process information includes cycle times, inventories, changeover times, staffing and modes of transportation etc.8. Method StudyMethod study focuses on how a task can (should) be accomplished. Whether controlling a machine or making or assembling components, how a task is done makes a difference in performance, safety, and quality. Using knowledge from ergonomics and methods analysis, methods engineers are charged with ensuring quality and quantity standards are achieved efficiently and safely.Methods techniques are used to analyze the following (Heizer et al., 2000, p. 394-396):1. Movement of individuals or material. Analysis for this is performed using flow diagrams and process charts with varying amounts of detail.2. Activity of human and machine and crew activity. Analysis for this is performed using activity charts (also known as man-machine charts and crew charts).3. Body movement (primarily arms and hands). Analysis for this is performed using micro-motion charts.9.Labor Standards and Work MeasurementsEffective operations management requires meaningful standards that can help a firm to determine the following (Heizer et al., 2000, p. 408-420)1. Amount of labor contribution for any product (the labor cost).2. Staffing needs (how many people it will take to meet required production).3. Cost and time estimates prior to production (to assist in a variety of decisions, from cost estimates to make or buy decisions).4. Crew size and work balance (who does what in a group activity or on an assembly line).5. Expected production (so that both manager and worker know what constitutes a fair days work).6. Basis of wage-incentive plan (what provides a reasonable incentive).10.Time StudiesThe classical stopwatch study, or time study, originally proposed by Federic W. Taylor in 1881, is still the most widely used time study method. The time study procedure involves the timing of a sample of workers performance and using it to set a standard.1. Define the task to be studied (after methods analysis has been conducted).2. Divide the task into precise elements (parts of a task that often takes no more than a few seconds).3. Decide how many times to measure the task (the number of cycles of samples needed).4. Record elemental times and rating of performance.Time Studies contd.5. Compute the average observed cycle time. The average observed cycle time is the arithmetic mean of the times for each element measured, adjusted forunusual influence for each element:

6. Determine performance rating and then compute the normal time for eachelement.Normal Time = (average observed cycle time) x (performance rating factor).7. Add the normal times for each element to develop a total normal time for each task.8. Compute the standard time. This adjustment to the total normal time provides allowances such as personal needs, unavoidable work delays and worker fatigue. Personal time allowances are often established in the range of 4% to 7% of total time, depending upon nearness to rest rooms, water fountains, and other facilities. Delay allowances are often set as a result of the actual studies of the delay that occurs. Fatigue allowances are based on our growing knowledge of human energy expenditure under various physical and environmental conditions.

11.Predetermined Time Standards

To estimate the time for a particular task, the time factors for each basic element of that task are added together. The most common predetermined time standard is methods time measurement (MTM), which is the product of the MTM association (Heizer et al.,2000 p. 415-416).Predetermined time standards are an outgrowth of basic motions called therblings. The term "therblig" was coined by Frank Gilbreth. Therbligs include such activities as select, grasp, position, assemble, reach, hold, rest and inspect. These activities are stated in terms of time measurement units (TMUs), which are each equal to only 0.00001 hour or 0.0006 minutes. MTM values for various therbligs are specified with the help of detailed tables.12.Work Sampling

It is an estimate of the percentage of time that a worker spends on particular work by using random sampling of various workers.This can be conducted by the following procedures1. Take a preliminary sample to obtain an estimate of the parameter value (such as percent of time worker is busy).2. Compute the sample size required.3. Prepare a schedule for observing the worker at appropriate times. The concept of random numbers is used to provide for random observation. For example, let's say we draw the following 5 random numbers from a table: 07, 12, 22, 25, and49. These can then be used to create and observation schedules of 9:07 AM,9:12, 9:22, 9:25, and 9:49 AM.4. Observe and record worker activities.5. Determine how workers spend their time (usually as percentage).13.Layout DesignLayout is one of the key decisions that determine the long-run efficiency of operations. Layout has numerous strategic implications because it establishes an organization's competitive priorities in regard to the capacity, processes, flexibility and cost as well as quality of work life, customer contact and image.The layout must consider how to achieve the following:1. Higher utilization of space, equipment, and people.2. Improved flow of information, material or people.3. Improved employee morale and safer working conditions.4. Improved customer/client interaction.5. Flexibility (whatever the layout is now, it will need to change).14 .Assembly Line BalancingLine balancing is usually undertaken to minimize imbalance between machines or personnel while meeting a required output from the line. The production rate is indicated as cycle time to produce one unit of the product, the optimum utilization of work force depends on the basis of output norms. The actual output of the individual may be different from the output norms.The assembly line needs to balance so that there is minimum waiting of the line due to different operation time at each workstation. The sequencing is therefore, not only the allocation of men and machines to operating activities, but also the optimal utilization of facilities by the proper balancing of the assembly lineAssembly Line Balancing contd.The process of assembly line balancing involves three steps1. Take the units required (demand or production rate) per day and divide it into the productive time available per day (in minutes or seconds). This operation gives us what is called the cycle time. Namely, the maximum time that the product is available at each workstation if the production rate is to be achieved.Cycle time = production time available per day / units required per day2. Calculate the theoretical minimum number of workstations. This is the total task duration time (the time it takes to make the product) divided by the cycle time. Fractions are rounded to the next higher whole number.

Where n is the number of assembly tasks.3. Balance the line by assigning specific assembly tasks to each workstation. An efficient balance is one that will complete the required assembly, follow the specified sequence, and keep the idle time at each work stations to a minimum.

15. Takt Time

Takt is German word for a pace or beat, often linked to conductors baton. Takt time is a reference number that is used to help match the rate of production in a pacemaker process to the rate of sales. This can be formulated as below

Takt timeworks better when customer demand is steady and clearly known; but if the customer demand varies on the daily basis then it is difficult to calculate the takt time as well as balance the production facility according to varying takt time.16.Cycle Time

Cycle time is defined as how frequently a finished product comes out of our production facility. Cycle time includes all types of delays occurred while completing a job. So cycle time can be calculated by the following formula.Total Cycle Time = processing time + set up time + waiting time + moving time +inspection time + rework time + other delays to complete the jobTo meet customer demand or monitor productivity the cycle time and takt time should be balanced in parallel.Garment manufacturing process:

TOTAL TEXTILE PROCESS AT A GLANCE

Modular manufacturing systemProduction system: Modular manufacturing systemModular manufacturing groups operators into teams, or modules. The team works on one/a few garment at a time instead of a bundle of garments. The operators stand /sit at their stations and rotate to different machines as they work, becoming familiar with multiple steps in producing the garment.

Sewing department

Sewing process flowSewing departmentProduction system: Make through system It is the traditional method of manufacture in which an operator makes right through one garment at a time.

Sewing departmentSource: ApparelKey.comProduction system: Conventional bundle system Sewing machines are arranged in lines.The work flows from the central (store) area to the first machine, from the first machine back to the store, and then on to the next machine, and so forth.A distributor stationed at the store is responsible for receiving and dispatching the work. The work in progress is in the form of bundles. These bundles may be put on to a tray, a box, or a bag, or the garment parts may be wrapped and tied.

Sewing department

Production system: Clump system A worker collects a clump of materials from the worktable and carries out the first operation. After he has completed his part of the work, he returns it to the table. A worker for the second operation then continues the work and so on. The process is ' collection - work -return' continues until the whole garment has been assembled.

Sewing department

Production system: Progressive bundle systemSewing operations are laid out in sequence. Each operator receives a bundle, does his work, reties the bundle and passes it to the next operator. There is a storage facility such as rack, bin or table for storing the inter-process work between each operation. The work is routed by means of tickets. This system is the most widely used system in the garment industry today. It is used in shirt factories, jeans factories, jacket factories, etc.

Sewing department

Production system: Flexible flow systemA section of sewing operators, each with a supply of work in a rack at the side, work at an engineered work place.The machines are laid out in such a way that a flow of work can be planned using the correct number of operators in sequence. For style A garments, the work distributed after operation 1 can be distributed to the two operators performing operation 2. On completion, the work from both workers is then sent to operator 3. After operation 3, the work is continued by the two operators performing operation 4 and so on. When a new style is to be loaded on to the system, the number of operators needed for each operation must be planned in detail to ensure a balanced output.

Sewing department

Production system: Straight line systemThe manufacturing process is broken down into several operations, which take the same time to complete. Groups of operators are required to handle only individual garments. The garment parts pass from one operator to the next, until the garment has been completely made up by one group of operators. The central distribution unit may be a fixed table or a a conveyor belt (its speed will be set to suit the cycle time).

Sewing department

Production system: Synchro flow systemGarment parts of the same size and color are processed separately. Different garment parts can be processed simultaneously for assembling. At the same time, collars, sleeves, cuffs, pockets, etc., from other lines also go down a central line. The different garment parts are then processed together to form completed garments.

Sewing department

Production system: Unit production systemA unit production system (UPS) is a computer-controlled production line. It is a type of line layout that uses an overhead transport system to move individual units from work-station to work station for assembly. All the parts for a single garment are advanced through the production line together by means of a hanging carrier that travels along an overhead conveyor. Production operations are completed without removing the parts from the carrier. Automated materials handling replaces the traditional system of bundling, tying and untying, and manually moving garment parts. Electronic data can be collected from workstations, which provides payroll and inventory data, immediate tracking of styles, and costing and performance data for prompt decision.

Sewing departmentLINE BALANCING (Process Organization)The Line Balancing is to design a smooth production flow by allotting processes to workers so as to allow each worker to complete the allotted workload within an even time It is a system where we meet the production expectations and we can find the same amount of work in process in every operation at any point in the day.

Reasons to have balance the production line (1) Keeping inventory costs low results in higher net income.(2) Keeping normal inventory levels lets the operator work all day long giving him/her the opportunity to earn more money by increasing his/her efficiency. (3)Keeping the line balanced lets the supervisors improve other areas because they can use their time better.(4) Balanced production keeps prices low which turns into repeat sales.(5) Balanced production means better production planning.Balancing MethodThe most basic methods are the Time Study,Bottle Neck Process Theory and Data Collection and Analysis.How do we start balancing the production line?Well we can start by determining how many operators for each operation are needed for a determined level of production. After this we need to determine how much WIP we need to anticipate production problems. Recommended WIP is 1-hour inventory level for each operation. A good range would be from 30 min to 120 min inventory level. There are 3 rules for balancing(1)To Have at least hour of WIP foreach operation

(2) To Solve problems before they become any larger

(3) Meet production goals by keeping every operator working at their maximum capacityTime StudyWhat is time study?

Time study is a work measurement technique for recording the time of performing a certain specific job or its element carried out under specific condition and for analyzing the data so as to obtain the time necessary for an operator to carry out at a defined rate of performance

Time study is a method of direct observation. A trained observer watches the job and records data as the job is being performed over a number of cycles.Time study equipmentthe stop watch in general, two types of watch are used for time study.Fly back ContinuousThese watches may be used any of the following time scalesSeconds Decimal minutesDecimal hoursTime StudySMVSMV time that is allowed to perform the job satisfactory.SMV = Basic time + AllowancesStandard Minute ValueSMV = B.T + AllowancesBasic Time The basic time for the operation is found by applying concept of rating to relate the observed to that of a standard place of working.Calculated as follows:Basic time = observed time * observed rating 100 (BT = Observed time * Observed Rating= A constant) 100Example..Rating 5075 100 125 Observed time1.20.80.60.5 Basic Time 1.2*500.8*750.6*100 0.5*125 100 100 100 100 = 0.6 0.6 0.6 0.6 Ex.SMV calculationElement descriptionObser ratingObser. timeBasic TimeFreq.Basic Time/GmtGet bundle and sort parts950.320.3041/300.010Match pocket flap to lining1050.110.1161/10.116Sew round flap1000.480.4801/10.480Trim threads and turn out flap580.350.2981/10.298Top stitch flap900.560.5041/10.504Close bundle and place aside1100.230.2531/300.008Total1.416Total basic time/garment (brought forward) 1.416 Add machine attention allowances 7%7% of (0.480 + 0.504) = 0.07 x 0.984 = 0.0690.069Basic time + MAA (1.416 + 0.069)1.485Add personal needs and relaxation allowances 14%14% of 1.485 = 0.14 x 1.485 = 0.2080.028Standard minute Value (SMV) = Basic time + all allowances = 1.485 + 0.208 = 1.693 (SMV)Production Planning Load and capacity PlanningSuccessful planning requires knowledge of two variables to determine the time required to manufacture a contract.Load How much work we are putting on a sectionCapacity How much work a section is capable of completing In an ideal situation >> Load = Capacity

Load and capacityLOAD Contract size x Work content

Capacity The amount of work the factory or section is capable of doing.

The scheduling ruleBalance load and capacity

Arrange the programmed of work so that the load can be achieved Use common units standard minutesBalancing & CapacityLoadUncertainty about the number of garments to be sold Demand?Speculation?Prediction?Uncertainty about work contentStandard minute value MeasuredEstimatedCapacityUncertainty about the number of operators and performanceTotal numbersAttendance hoursAbsenteeismPerformanceLearning curveUncertainty about the equipment Availability ReliabilityPitch TimeReference value for synchronization in the division of labor is called Pitch Time (PT). Pitch Time provides average time allotted to each worker.Bottleneck Process:The time at which the longest time is required is called bottleneck Process The state of line organization should be evaluated as Organization Efficiency Using the pitch time and Bottleneck Process Time. Pitch Time Organization Efficiency (%) = ________________________ x 100 Bottleneck Process Time

100 = ______ X 100 140 = 71.4 % (For the case study)

How to reduce the number of bottleneck processes (1) Investigate the relation between the bottleneck process and its previous and subsequent processes to correct the line organization. (2) Investigate whether it is possible to further divide the process.(3) Conduct the motion study for work improvement.(4) Make improvements to equipment, jig and tools.(5) Mechanize the manual work.(6) Change the positions of workers.(7) Investigate the modification to the machining specifications.(8) Make it a rule to lend the worker in charge of the bottleneck process a helping handControl limit Pitch Time Upper Limit = _________________________ X 100 Target organization efficiency = 0.85 = 117.6 Seconds

Lower Limit = 2 x Pitch Time Upper Limit = 2 x 100 117.6 = 82.4 Seconds

Data CollectionApparel &textile production center cum learning Lab.Cutm,bhubaneswar,odhisa,indiaCapacity check sheet U-1 (Line: 1,2,3,4)

Style no: 29694 Target: Buyer: quantity: Description: womans top Type: BasicONE PART DIVIDED INTO DIFFERENT CUT PARTS AND ASSIGNED TO EACH WORKER ON17-04-2015SLOperation NameOperator Name & IDM/C type(electrical power -ZUKI)1Shoulder join-1Roman17371O/L2Shoulder join-2Tuni19021O/L3Neck rib folding & servicingJohura20568O/L4Neck rib edge jointMukul20918P/M5Neck jointSajida3357O/L6Piping shoulder to shoulder-1Taslima2199F/L7Piping shoulder to shoulder-2Arif19799F/L8Piping top stitch shoulder to shoulder-1Rekha20954F/L9Piping top stitch shoulder to shoulder-2Alal3011F/L10Sleeve joint-1Hasina850O/L11Sleeve joint-2Shapla19930O/L12Arm hole position zigzag top stitch-1Helena18332F/L13Arm hole position zigzag top stitch-2Afsana20922F/L14Side seam-1Laboni20145O/L15Side seam-2Ashiq19659O/L16Side seam-3Parvin3360O/LTime study-1:16 workers and i6 jobsSLoperatorOperation(Stiching)Starting (H:Min) Finishing(H:Min) Time (min)1P-12.393.07282P-22.393.15363P-32.393.16374P-42.393.16375P-52.393.23446P-62.393.28597P-72.393.45668P-82.393.50719P-92.393.557610P-102.394.028311P-112.394.109112P-122.394.139413P-132.394.159514P-142.394.189815P-152.394.2010116P-162.394.25106For individual person the average time for finishing task= 70min.,(or)1.10hr.Time study-2:4-modules16 workers and 4 jobsSLOperator/moduleModule-1Operation(Stiching)Starting (H:Min) Finishing(H:Min) Time (min)1P-14.305.03332P-24.305.03333P-34.305.03334P-44.305.0333Module-25P-54.305.02326P-64.305.02327P-74.305.02328P-84.305.0232Module-39P-94.305.073710P-104.305.073711P-114.305.073712P-124.305.0737Module-413P-134.305.104014P-144.305.104015P-154.305.104016P-164.305.1040For all modules the average time taken for finishing task= 35.5min.,.Time study-3:4-modules12 workers and 4 jobsSLOperator/moduleModule-1Operation(Stiching)Starting (H:Min) Finishing(H:Min) Time (min)1P-15.125.37252P-25.125.37253P-35.125.3725Module-24P-45.125.39275P-55.125.39276P-65.125.3927Module-37P-75.125.39278P-85.125.39279P-95.125.3927Module-410P-105.125.392711P-115.125.392712P-125.125.3927For all modules the average time taken for finishing task= 26.5min.,.Time study-4:4-modules 8 workers and 4 jobsSLOperator/moduleModule-1Operation(Stiching)Starting (H:Min) Finishing(H:Min) Time (min)1P-15.426.03212P-25.426.0321Module-23P-35.426.05234P-45.426.0523Module-35P-55.426.04226P-65.426.0422Module-47P-75.426.07258P-85.426.0725For all modules the average time taken for finishing task= 22.8min.,.Time study-5:4-modules 4 workers and 4 jobsSLOperator/moduleModule-1Operation(Stiching)Starting (H:Min) Finishing(H:Min) Time (min)1P-16.106.3020Module-22P-26.106.3222Module-33P-36.106.3121Module-44P-46.106.3323For all modules the average time taken for finishing task= 21.5min.,.Time study-6:1-modules 4 Skilled workers and 4 jobsSLOperator/moduleModule-1Operation(Stiching)Starting (H:Min) Finishing(H:Min) Time (min)1P-16.356.55202P-26.356.52173P-36.356.53184P-46.356.5621Module-2Module-3Module-4in one module the time taken for finishing task at earliest = 17min.,.Result and discussions:The above data clearly determines the bottlenecks avoided for completing task in each moduleIn the work flow process eliminating the idle time and idle person.Finally by using time study method for implementing modular manufacturing system in garment industries, we got the optimized time, and the optimizing time is 17min.,In modular system mainly focusing reducing production cost. Especially in garment industries increasing productivity.Conclusions:Firstly, the problem of low flexibility is eliminated by cellular manufacturing, because there is very low WIP inside the process, so the line can be changed immediately if needed. This helps to make different kinds of products in the same production line depending upon requirements, whereas in case of old production layout this cannot be implemented.Secondly, all stitching operations were standardized by means of time and working procedures, this will help management to know the production target per line and can make the production plan before loading actual products in the shop floor.Similarly, allocation of workers in different work cells is as per the standard operation time. This motivates operators towards their work, because everybody is given equal work load by this system. At the same time each operator inside the cell should have to work on multiple operations. This eliminates accusing to supervisors for inappropriate allocations of operators in difficult operations.REFERENCES:Bheda, R., Narag, A.S. and Singla, M.L. Apparel Manufacturing a Strategy forP roductivity Improvement, Journal of Fashion Marketing and Management, Volume 7.No1, pp12-22, MCB up limited, 2003. [available at: http://www.emeraldinsight.com/journals.htm?articleid=858534&show=pdf] [viewed on: 04.10.2011].Banks, J., J. Carson, and B. Nelson, 1996: Discrete-Event System Simulation, Prentice Hall, Upper Saddle River, NJ.Schroer, B., and J. Wang, 1992: Simulation Support Environment for Modular ManufacturingSystems SSE5, UAH Reseamh Report 92-03, University of Alabama in Huntsville, October.Schroer, B.,1992: Manufacturing's New Crystal Ball, Bobbin, Three-part series in August pages 60-64, September pages100-104, and October pages 44-48.Cole, W., 1987: "The Ups and Downs of UPS," Bobbin, pages 70-74, December.Dewitt, J., 1991: "Computer Simulation," Aparel Industry Magazine, pages 42-48, February.Fralix, M., J. Langford, C. Carrere, and T. Little, 1990: "Reflections on Modular," Bobbin, pages 60-66, April.Gilbert, C., 1988: "Tracking Modular Production," Apparel Industry Magazine, April.Gilbert, C., 1989: "Modular Manufacturing, Sizzle or Steak," Apparel Research Notes, AmericanApparel Manufacturers Association, Arlington, VA, Vol. 8, No. 5, September.Kron, P., 1987: "Pondering Modular," Apparel Industry Magazine, pages 70-80, August.Kulers, B. and J. Dewitt, 1990: "Modular Goes Mainstream," Apparel Industry Magazine, pages 44-52, May.