Miami‐Dade County, Florida Request for Qualifications (Step 1) South Miami Heights Water Treatment Plant Program December 2014 DRAFT – FOR PUBLIC COMMENT ONLY
NOT A PROCUREMENT SOLICITATION i ORL.JKC.PW_XM1.6430.101067.04.15.07.40.01CDAM003_DRAFT‐RFQ_SMHWTP_121714
REQUEST FOR QUALIFICATIONS (STEP 1)
ISD Project No. 14‐DBFO‐WASD‐01
Design‐Build‐Finance‐Operate‐Maintain Services
For
South Miami Heights Water Treatment Plant Program
Submittal Deadline: 3:30 PM, Local Time, [_________]
Issued Date: [_________]
Miami‐Dade County, Florida
111 NW 1st Street, 17th Floor, Suite 202
Miami, Florida 33128
Miami‐Dade County, Florida Request for Qualifications (Step 1) South Miami Heights Water Treatment Plant Program December 2014 DRAFT – FOR PUBLIC COMMENT ONLY
NOT A PROCUREMENT SOLICITATION ii ORL.JKC.PW_XM1.6430.101067.04.15.07.40.01CDAM003_DRAFT‐RFQ_SMHWTP_121714
Table of Contents
Section1 Background...............................................................................................................................................1‐1 1.1Introduction..................................................................................................................................................................1‐1 1.2TheProject....................................................................................................................................................................1‐1 1.3DefinedTerms.............................................................................................................................................................1‐2
Section2 GeneralRequirementsandInstructions.........................................................................................2‐1 2.1EffectofSubmittal......................................................................................................................................................2‐1 2.2StatusofTeamFirms................................................................................................................................................2‐1 2.3OrganizationalConflictsofInterestandAdvanceRestrictions.............................................................2‐2
2.3.1Policy...................................................................................................................................................................2‐2 2.3.2AdvanceRestrictions....................................................................................................................................2‐4
2.4TeamingRestrictions................................................................................................................................................2‐4 2.5ContractMeasures.....................................................................................................................................................2‐4 2.6VendorRegistration..................................................................................................................................................2‐5 2.7Prequalification...........................................................................................................................................................2‐5 2.8RequestsforAdditionalInformation;Addenda...........................................................................................2‐5 2.9WorkHistoryDisclosure.........................................................................................................................................2‐6 2.10ConfidentialInformation......................................................................................................................................2‐6 2.11Withdrawals...............................................................................................................................................................2‐6 2.12CostsIncurred...........................................................................................................................................................2‐6 2.13ConflictofInterestRelatedtoSection2‐11.1oftheCodeofMiami‐DadeCounty.....................2‐6 2.14Postponement/Cancellation...............................................................................................................................2‐6 2.15ContractAward........................................................................................................................................................2‐7 2.16RightsofProtest.......................................................................................................................................................2‐72.17Miami‐DadeWaterandSewerDepartmentAccelerationOrdinance..............................................2‐7
Section3 SubmittalRequirements.......................................................................................................................3‐1 3.1InstructionsforRespondents...............................................................................................................................3‐1 3.2RequiredFormat........................................................................................................................................................3‐2 3.3RequiredContents.....................................................................................................................................................3‐2
Section4 EvaluationofSubmittals.......................................................................................................................4‐1 4.1OverallProcess............................................................................................................................................................4‐1 4.2Qualifications...............................................................................................................................................................4‐1 4.3ComparativeEvaluationCriteria.........................................................................................................................4‐4 4.3ShortListNotification..............................................................................................................................................4‐6 4.5RequestforProposals,RFP(Step2)..................................................................................................................4‐6
List of Tables
Table1‐1ScheduleofCriticalEvents.......................................................................................................................................1‐1 Table4‐1Step1ComparativeEvaluationCriteria.............................................................................................................4‐4
Miami‐Dade County, Florida Request for Qualifications (Step 1) South Miami Heights Water Treatment Plant Program December 2014 DRAFT – FOR PUBLIC COMMENT ONLY
NOT A PROCUREMENT SOLICITATION iii ORL.JKC.PW_XM1.6430.101067.04.15.07.40.01CDAM003_DRAFT‐RFQ_SMHWTP_121714
Appendices
AppendixA DescriptionoftheProjectAppendixB AffidavitFormsAppendixC CertificateofAuthorizationAppendixD PreliminaryTermSheetforServiceContractAppendixESummaryofApplicableLawsAppendixF CountyPre‐QualificationofA/EFirms
[EndofTableofContents]
Miami‐Dade County, Florida Request for Qualifications (Step 1) South Miami Heights Water Treatment Plant Program December 2014 DRAFT – FOR PUBLIC COMMENT ONLY
NOT A PROCUREMENT SOLICITATION 1‐1 ORL.JKC.PW_XM1.6430.101067.04.15.07.40.01CDAM003_DRAFT‐RFQ_SMHWTP_121714
Section 1
Background
1.1 Introduction ThisRequestforQualifications(RFQ),isthefirststepinatwo‐stepselectionprocess,andisintendedtoobtainstatementsofqualificationsfromRespondentsinterestedinbeingconsideredforinclusiononapre‐qualifiedshort‐listofnofewerthanthreeresponsiveandresponsibleProjectTeams(the“AdvancingFirms”).UponcompletingthisStep1‐EvaluationofQualifications,theAdvancingFirmswouldbeinvitedinStep2–EvaluationofProposalstosubmitProposalsforthedesign,construction,financing,operationandmaintenance(includingrenewalandreplacement)servicesrequiredbytheMiami‐DadeWaterandSewerDepartment(WASD)fortheSouthMiamiHeightsWaterTreatmentPlantProgram(Project).SuchProposalswouldbeinresponsetoaRequestforProposals(RFP)beingpreparedbytheCountywithassistancefromCDMSmithInc.astheDesignCriteriaProfessional.OnlytheAdvancingFirmswillbeeligibletosubmitProposals.AtentativescheduleofcriticaleventsisincludedinTable1‐1belowandsubjecttochangeatanytimeatthesolediscretionoftheCounty.
Table 1‐1 Schedule of Critical Events
Event Date
1. Step 1 RFQ Issued TBD
2. Step 1 RFQ Pre‐Submittal Project Briefing TBD
3. Step 1 RFQ Deadline for Receipt of Questions TBD
4. Step 1 RFQ Submittal Due TBD
5. Step 1 RFQ Advancing Firms Notified TBD
6. Step 2 Request for Proposals (RFP) Issued TBD
7. Step 2 RFP Pre‐Submittal Project Briefing and Site Visit TBD
8. Step 2 RFP Deadline for Receipt of Questions TBD
9. Step 2 RFP Submittal Due TBD
TheCountyhasdeterminedthattheprojectisaQualifyingProjectasthattermisdefinedunderSection287.05712oftheFloridaStatutes,and,initssolediscretionandsubjecttotheprocessesforcompetition,selection,evaluationandnegotiationsetforthinthelawandinthesedocuments,planstoenterintoacomprehensiveagreementforthedesign,permitting,financing,construction,operationandmaintenanceoftheProjectinaccordancewiththatSection.PleasenotethatthissolicitationhasbeenissuedthroughtheCounty’sBidSyncElectronicBiddingSystem,requiringSubmittalselectronically.(PotentialRespondentshouldberegisteredwithBidSync.)
1.2 The Project AdescriptionoftheProject,includingadescriptionofCountyassumptionsandexpectationsforthecomprehensiveagreement,issetforthinAppendixA.
Miami‐Dade County, Florida Request for Qualifications (Step 1) South Miami Heights Water Treatment Plant Program December 2014 DRAFT – FOR PUBLIC COMMENT ONLY
NOT A PROCUREMENT SOLICITATION 1‐2 ORL.JKC.PW_XM1.6430.101067.04.15.07.40.01CDAM003_DRAFT‐RFQ_SMHWTP_121714
AdditionalinformationconcerningtheProject,includingengineeringreportscanbeobtainedatthefollowingFTPsite:[_____________].RespondentsareresponsibleforobtaininganyadditionalinformationthatmaybeperiodicallyaddedbytheCountytotheFTPsite.
1.3 Defined Terms ThefollowingcapitalizedwordsandtermsusedinthisRFQhavethefollowingmeanings:
“A/E”meansarchitecturalandengineeringfirmcertifiedasavendorcapableoftransactingbusinessinMiamiDadeCountyandhavingavalidMiamiDadePre‐QualificationCertification.
“Affiliate”meansanyperson,corporationorotherentitydirectlyorindirectlycontrollingorcontrolledbyanotherperson,corporationorotherentityorunderdirectorindirectcommoncontrolwithsuchperson,corporationorotherentity.
“AdvancingFirms”meanstheshort‐listofProjectTeamsselectedbytheCompetitiveSelectionCommitteetoadvancetoStep2basedupontheevaluationoftheSubmittalspursuanttothisStep1RequestforQualifications.(“AdvancingFirm”meansanindividualProjectTeamincludedamongtheAdvancingFirms.)
“Company”meansthelegalentitythatwouldbeauthorizedandcontractuallyresponsibleforperformingtheScopeofServicesfortheProjectandwouldenterintotheServiceContractwiththeCounty.
“ComparativeEvaluationCriteria”meansthecriteriasetforthinthisRFQthatwillbeutilizedbytheCompetitiveSelectionCommitteetoevaluateandranktheSubmittals.
“CompetitiveSelectionCommittee”or“CSC”asdefinedinSection2‐10.4(5)oftheMiami‐DadeCountyCode,meansthecommitteeappointedbytheCountyMayororCountyMayor’sdesigneetoevaluatequalificationsandperformanceofthefirmsrequestingconsiderationforthespecificprojectandselectthemostqualifiedfirm(s)toperformtheservices.
“County”or“Owner”meansMiami‐DadeCounty,apoliticalsubdivisionoftheStateofFlorida.
“CountyTechnicalAdvisor”meansthefirm,CDMSmithInc.,thatisprovidingengineeringandrelatedprofessionalservicestosupporttheCountyintheprocurementprocessandistheDesignCriteriaProfessionalfortheProject.
“County’sA/ECoordinator”meansthepersondesignatedbytheCountyastheprimarycontactforthissolicitation.
“Days”or“days”meancalendardays,unlessotherwiseexpresslystated.
“DesignCriteriaProfessional”meansanindividualorfirmwhoholdsacurrentcertificateofregistrationunderChapter481ofFloridaStatutestopracticearchitectureorlandscapearchitectureorafirmwhoholdsacurrentcertificateasaregisteredengineerunderChapter471ofFloridaStatutestopracticeengineeringandwhoisemployedbyorundercontractwiththeCountyfortheprovisionofprofessionalarchitectureservicesorengineeringservicesinconnectionwiththepreparationofthedesigncriteriapackage.
“Design‐Builder”meansafirmthatwouldberesponsibleforperformanceofbothdesignandconstructionofalloraportionoftheProject.
“Director”meanstheDirectoroftheMiami‐DadeWater&SewerDepartment.
“Guarantor”meanstheentitythatwouldprovideanunconditionalguaranteeoftheCompany’sperformanceoftheServiceContract.
“GeneralManager”meanstheindividualemployeeoftheCompanyresponsibletotheCountyfortheCompany’sperformanceofitsobligationsundertheServiceContract.
Miami‐Dade County, Florida Request for Qualifications (Step 1) South Miami Heights Water Treatment Plant Program December 2014 DRAFT – FOR PUBLIC COMMENT ONLY
NOT A PROCUREMENT SOLICITATION 1‐3 ORL.JKC.PW_XM1.6430.101067.04.15.07.40.01CDAM003_DRAFT‐RFQ_SMHWTP_121714
“InternalServicesDepartment”meanstheCountyDepartmentwhichcombinestheformerAmericanwithDisabilityActCoordination,OfficeofCapitalImprovements,GeneralServicesAdministration,HumanResources,andProcurementManagementDepartments.
“KeyPersonnel”meanstheindividualsincludedintheSubmittalwhowillmanageorperformsignificantportionsoftheServicesfortheContractorandshouldincludetheGeneralManagerandindividualsinresponsiblechargeofdesign(DesignManager),hydrogeologicstudies,welldesignandconstruction(Hydrogeologist),financing(FinanceArranger),construction(ConstructionManager),operationandmaintenance(O&MManager),qualitymanagement(QA/QCManager),permitsandapprovals(PermittingManager)andotherindividualsandpositionsthatmaybesetforthintheSubmittaltosupplementorotherwiseaddressspecificareasofresponsibility.
“LeadConstructor”meansafirmthatwouldbethegeneralcontractorfortheperformanceofconstructionworkforalloraportionoftheProject.(TheLeadConstructormayalsobedesignatedastheDesign‐Builder.)
“LeadDesigner”meansafirmthatwouldbetheEngineerofRecorddulyregisteredunderChapter481oftheFloridaStatuteswithresponsibilityforpreparationofthedetailedplansandspecificationsfortheconstructionofalloraportionoftheProject.(TheLeadDesignermayalsobedesignatedastheDesign‐Builder.)
“LeadOperator”meansafirmthatwouldberesponsibleforoperationandmaintenanceofalloraportionoftheProject.
“MDWASD”meanstheMiami‐DadeWater&SewerDepartment.
“Owner”meansMiami‐DadeCounty,apoliticalsubdivisionoftheStateofFlorida.
“Project”meanstheSouthMiamiHeightsWaterTreatmentPlantProgramdescribedinthisRFQ.
“ProjectTeam”means,collectively,allofthefirmssetforthintheSubmittal(includingsubconsultants,subcontractors,theRespondent,theCompany,andmembers,partners,andAffiliates)andKeyPersonnel.
“ProjectTeamMember”meansafirmincludedintheProjectTeam.
“Proposal”meansaproposalsubmittedinresponsetotheRequestforProposalsissuedbytheCountyintheStep2ofthisprocurementprocess.
“Proposer”meansanAdvancingFirmthatsubmitsaproposalinresponsetotheStep2RequestForProposals.
“Respondent”meanstheparty(orparties)submittingtheSubmittal,executingthecoverletterandForm[_____],asalegalpersonorpersonscapableoftransactingbusinessinMiamiDadeCounty.
“Responsible”meansaRespondent,CompanyorotherProjectTeamMemberwhotheCountyaffirmativelydetermines:hastheability,capacityandskilltoperformunderthetermsoftheServiceContract;doesnothaveanunsatisfactoryrecordofpastperformanceinCountycontracting;includingabidingbyapplicableordinances,resolutions,andotherpoliciesoftheCounty;andhasasatisfactoryrecordofintegrityandbusinessethics.
“Responsive”meansaRespondentwhointheCounty’ssolediscretionhascompliedwithallofthematerialrequirementsoutlinedinthissolicitation,asapplicable.
“RFP”meanstheRequestforProposalsandaddendaissuedbytheCountyinStep2toobtainproposalsfortheProjectfromtheAdvancingFirms.
Miami‐Dade County, Florida Request for Qualifications (Step 1) South Miami Heights Water Treatment Plant Program December 2014 DRAFT – FOR PUBLIC COMMENT ONLY
NOT A PROCUREMENT SOLICITATION 1‐4 ORL.JKC.PW_XM1.6430.101067.04.15.07.40.01CDAM003_DRAFT‐RFQ_SMHWTP_121714
“RFQ”meansthisStep1RequestforQualificationsandalladdenda.
“ScopeofServices”meanstheworkandservicestobeprovidedbytheCompanyinthedesign,permitting,financing,construction,andoperationandmaintenanceoftheProjectundertheServiceContract.
“ServiceContract”meansthecontractbetweentheCountyandtheCompanysettingforththeobligationsofthepartieswithrespecttothedesign,permitting,financing,construction,operationandmaintenanceoftheProject,whichcontractmaybecomprisedofoneormorelegaldocumentscapturingthewholeorpartsoftheProjectasappropriate.
“Submittal”meansthedocumentationdeliveredbyaRespondentinresponsetothisStep1RequestforQualifications.”
“SubmittalDeadline”or“SubmissionDeadline”meansthedeadlinefordeliveryoftheSubmittaltotheCounty.
[EndofSection1]
Miami‐Dade County, Florida Request for Qualifications (Step 1) South Miami Heights Water Treatment Plant Program December 2014 DRAFT – FOR PUBLIC COMMENT ONLY
NOT A PROCUREMENT SOLICITATION 2‐1 ORL.JKC.PW_XM1.6430.101067.04.15.07.40.01CDAM003_DRAFT‐RFQ_SMHWTP_121714
Section 2
General Requirements and Instructions
2.1 Effect of Submittal SubmittingaproposalinresponsetothisRFQshallconstitutetheirrevocablecommitmentoftheRespondent,ifselectedtodosopursuanttotheprocessdescribedinthisRFQ,toundertakethegood‐faithnegotiationofaServiceAgreementwiththeCountyfortheworkrequiredtocompletetheProjectwiththeTeamandpersonnelidentifiedintheSubmittal.TheRespondentmustcompleteForm[_______],attachedheretoidentifyingtheRespondent.TheRespondentshallbealegalperson,capableofenteringintolegallyenforceablecontractualcommitments,andotherwiseauthorizedtodobusinessintheStateofFlorida.TheRespondentshallbeexpresslyauthorizedtomaketherepresentationsmadetotheCountyintheSubmittal,includingbutnotlimitedtotherepresentationthattheCompany,theTeamandpersonsidentifiedintheSubmittalare,oruponformationwillbe,ready,willingandabletoperformtheworkrequiredtocompletetheProject.TheRespondentmaybe,butshallnotberequiredtobe,theCompanyidentifiedintheSubmittal.
FailuretoprovidetheinformationrequiredbyMiami‐DadeCountymayresultinthenegativeevaluationoftheProjectTeamoratMiami‐DadeCounty’ssolediscretion,disqualificationoftheProjectTeam.
TheCountyMayormayimposethelossofeligibilitytoparticipateinCountycontractsforaspecifiedperiodoftime,nottoexceedfiveyearsforanapplicant,itsindividualofficers,itsshareholderswithsignificantinterests,anditsaffiliatedbusinessesforviolationsofornon‐compliancewithAdministrativeOrder3‐39,includingthefalsificationofinformationprovidedintheSubmittal,proposaland/orotherdocumentssubmittedbytheRespondentinsupportofitsoffer.
2.2 Status of Team Firms ExceptfortheRespondent,whoshallbegovernedbytheprovisionsofSection2.1aboveandmustbeapersoninlegalexistenceatthetimeofSubmittal,unlessotherwisespecificallyprovidedinthisRFQortheServiceAgreement,personsandentitiesidentifiedintheSubmittalmustbeinexistence,anddulyauthorizedandlicensedtoperformtherequiredservices,notlaterthanthetimetheMayororMayor’sdesigneerecommendsanawardofaServiceContract.InapplyingtheselectioncriteriasetforthinthisRFQ,theCompetitiveSelectionCommitteeshallbeauthorizedtoinquirefromproposerswithrespecttotheexistence,legalstatus,contractualcommitmenttotheProject,licensingandqualificationsofanyoftheproposedmembersorpersonnelofaTeam,andtoconsiderasanegativefactorintheevaluationofaRespondenttheRespondent’sinabilitytodemonstrateexistence,contractualcommitmenttotheProject,activestatus,licensingorqualificationsofanyofthefirmsorpersonnelproposedaspartofaTeamatthetimeofsubmittal.Asubmittalidentifyingfirmsnotinexistence,notcontractuallycommittedtotheProject,orwhichdonothavetherequisitestatus,licensing,orqualifications,maybeconsideredtopresentagreaterrisktotheCountyandscoredaccordingly.
Miami‐Dade County, Florida Request for Qualifications (Step 1) South Miami Heights Water Treatment Plant Program December 2014 DRAFT – FOR PUBLIC COMMENT ONLY
NOT A PROCUREMENT SOLICITATION 2‐2 ORL.JKC.PW_XM1.6430.101067.04.15.07.40.01CDAM003_DRAFT‐RFQ_SMHWTP_121714
2.3 Organizational Conflicts of Interest and Advance Restrictions 2.3.1 Policy TheCOUNTY,throughMDWASD,adoptstheprovisionsofthisSectiontogovernpotential
conflictsofinterest.ItisthepolicyoftheCOUNTY,implementedthroughthisSection,toidentify,analyzeandaddressorganizationalconflictsofinterestthatmightotherwiseexistinordertomaintainthepublic’strustintheintegrityandfairnessoftheCOUNTY’ScontractingfortheProjectandtoprotectthebusinessinterestsoftheCOUNTYtherebysafeguardingpublicdollars.Thispolicyshallbesupplementaltoandnotinderogationoftherequirementsoflawrelatingtoconflictsofinterestincluding,butnotlimitedto,theCounty’sCodeofEthics.
Anorganizationalconflictofinterestisasituationinwhichaperson:(a)undertheContract,oranypartthereof,includingaparticularworkorderordefinedtask,isrequiredtoexercisejudgmenttoassisttheCOUNTYinamatter(suchasindraftingspecificationsorassessinganotherconsultant’sorcontractor’sproposalorperformance)andthepersonhasadirectorindirectfinancialorotherinterestatstakeinthematter,sothatareasonablepersonmighthaveconcernthatwhenperformingWorkundertheServiceContract,thepersonmaybeimproperlyinfluencedbyitsowninterestsratherthanthebestinterestoftheCOUNTY,or(b)wouldhaveanunfaircompetitiveadvantageinaCOUNTYcompetitivesolicitationasaresultofhavingperformedworkonaCOUNTYcontractthatputthepersoninapositiontoinfluencetheresultofthesolicitation.
Anyperson’s:(a)executionofthecomprehensiveagreementsolicitedunderthisprocess,ortheagreementtoperformanyportionoftheworkthereunderor(b)makinganyclaimforpaymentthereunder,constitutessuchperson’scertificationtotheCOUNTYthatthepersondoesnothaveknowledgeofanyorganizationalconflictsofinteresttoexistinperformingtheworkundertheServiceContract.FalsecertificationsmaybeconsideredamaterialbreachoftheServiceContractandthepersonmaybeliabletotheCOUNTYforafalseclaimundertheCOUNTY’Sfalseclaimordinance.AtanytimeinanticipationofawardingtheServiceContract,orduringtheperformanceoftheServiceContract,theCOUNTYmayrequirethepersontoexecuteanexpresswrittencertificationthatafterdiligentinquirythepersondoesnothaveknowledgeofanyorganizationalconflictofinterest.TheCOUNTYmayalsorequirethepersontosetforthinwritingthescopeoftheinquiryconductedtomaketheexpresscertification.Failuretomakediligentinquiry,todiscloseaknownconflictorpotentialconflict,ortoexecutethedocumentsrequiredtobeproducedmaybeconsidered,ifpre‐award,areasonfordisqualificationoftheproposal,andfollowingaward,amaterialbreachoftheServiceContract.
Identificationoforganizationalconflictofinterest.ThepersonshallbeobligatedtodisclosetotheCOUNTYanyorganizationalconflictofinterest,orthepotentialforthesametooccur,immediatelyuponitsdiscovery.Thedisclosureshallbeinwriting,addressedtotheContractManageridentifiedintheServiceContractspecifications.ThedisclosureshallidentifytheorganizationalconflictofinterestwithsufficientdetailfortheCOUNTY’sanalysisandshallproposeamethodtoaddressthesame.SuchdisclosureshallalsobereportedtotheOfficeoftheInspectorGeneral(OIG)ortotheCommissiononEthicsandPublicTrust(COE).Theperson’sfailuretoidentifyanorganizationalconflictofinterest,ortodisclosethesametotheCOUNTYinthemannersetforthinthisSection,maybeconsideredamaterialbreachoftheServiceContract.Eachsolicitationshallalsorequirerespondentstoaddressthemethodologyproposedtoidentifyandaddressanypotentialorganizationalconflictofinterest,particularlyin
Miami‐Dade County, Florida Request for Qualifications (Step 1) South Miami Heights Water Treatment Plant Program December 2014 DRAFT – FOR PUBLIC COMMENT ONLY
NOT A PROCUREMENT SOLICITATION 2‐3 ORL.JKC.PW_XM1.6430.101067.04.15.07.40.01CDAM003_DRAFT‐RFQ_SMHWTP_121714
thoseinstanceswherethepersonofferstousethesamesubcontractorsorsubconsultantswhichfirmsareengagedinothercontractsrelatedtotheProjectwheresuchuseisnotspecificallyprohibitedbytheadvancerestrictionssetforthbelow.Thepotentialfororganizationalconflictsofinterest,andthemethodologyofferedtopreventorganizationalconflictsofinterest,maybeevaluatedbytheCOUNTYasacriterionforselectionassetforthintheapplicablecompetitivesolicitationdocuments.
Addressingorganizationalconflictsofinterest.TheCOUNTYwillanalyzeandaddressorganizationalconflictsofinterestonacase‐by‐casebasis,becausesuchconflictsariseinvarious,andoftenunique,factualsettings.TheDirector,withtheassistanceofsuchotherpersonsashemaydeemappropriate,shallmakethefinaldecisionastohowtoaddressanorganizationalconflictofinterest.TheCOUNTYshallconsiderthespecificfactsandcircumstancesofthecontractingsituationandthenatureandpotentialextentoftherisksassociatedwithanorganizationalconflictofinterestwhendeterminingwhatmethodormethodsofaddressingtheconflictwillbeappropriate.WhenanorganizationalconflictofinterestissuchthatitrisksimpairingtheintegrityoftheProject,thentheCOUNTYmusttakeactiontosubstantiallyreduceoreliminatethoserisks.IftheonlyriskcreatedbyanorganizationalconflictofinterestisaperformanceriskrelatingtotheCOUNTY’Sbusinessinterests,thentheCOUNTYshallhavebroaderdiscretioninacceptingsomeoralloftheperformancerisk,butonlywhenthepotentialharmtotheCOUNTY’SinterestisoutweighedbytheexpectedbenefitfromhavingtheconflictedpersonperformtheContract.
Measurestoaddressorganizationalconflictsofinterest:Themeasure,orcombinationofmeasures,whichmaybeappropriatetoaddressanorganizationalconflictofinterest,ifany,shallbedecidedbytheDirectorandinclude,butarenotlimitedto:(a)avoidanceofriskthroughreductionofsubjectivityintheanalysisorbydefiningworktasksanddeliverableswithspecificity,(b)requiringthepersonoritssubcontractorsorsubconsultantstoimplementstructuralbarriers(firewalls)andinternalcorporatecontrols,(c)limitingthesubcontractor,subconsultantorpersonneltobeinvolvedinaworkassignment,(d)employingspecifichourlylimitsondefinedtasks,(e)limitingorprohibitingcertainpassthroughfeesandmarkups,(f)executingamitigationplanwhichwilldefinespecificdutiestomitigateorganizationalconflictsofinterest,(g)requiringpersonswhoareconflictfreetoperformidentifiedareasofwork,(h)requiringthepersontoadopt,disseminateandinstructstaffonconflictofinterestidentificationandremediationproceduresand(i)relyingonmorethanonesourceoronobjectiveorverifiabledataorinformation.
Documentationandevaluation:TheDirectorwillsetforthintheServiceContractfileawrittenexplanationofthemethodologyusedtoaddressanidentifiedorganizationalconflictofinterest.TheCOUNTYshallperiodicallyevaluatetheeffectivenessofthemethodologyintheprotectionoftheProject.Upontherenderingofadecisionregardingtheresolutionofareportedconflictofinterest,acopyofsuchfindingshallbeforwardedtotheOIGorCOE.
Organizationalconflictsofinterestwhicharenotremedied:IfinthesolediscretionoftheCOUNTYthereisnomeasureorcombinationofmeasureswhichprotecttheCOUNTYagainsttheorganizationalconflictofinterest,andthenthepersonmaynotperformthesubjectwork.TheCOUNTYmayinitsdiscretion,ifpre‐award,decidenottoawardtheServiceContracttotheaffectedperson,andfollowingaward,terminatetheServiceContract,orportionoftheServiceContract,whichthepersonhasmateriallybreachedbecauseofsuchinabilitytoperform.
Miami‐Dade County, Florida Request for Qualifications (Step 1) South Miami Heights Water Treatment Plant Program December 2014 DRAFT – FOR PUBLIC COMMENT ONLY
NOT A PROCUREMENT SOLICITATION 2‐4 ORL.JKC.PW_XM1.6430.101067.04.15.07.40.01CDAM003_DRAFT‐RFQ_SMHWTP_121714
2.3.2 Advance Restrictions CDMSmithInc.,theDesignCriteriaProfessionalfortheProject,isnoteligibleforinclusiononaProjectTeamorforotherwiseperforminganyservicesfortheProject,RespondentorotherProjectTeamMember.Inaddition,thefollowingfirmshavebeenretainedbytheDesignCriteriaProfessionalandlikewisearenoteligibleforinclusiononaProjectTeamorforotherwiseperforminganyservicesfortheProject,RespondentorotherProjectTeamMember:
ArchitectsInternational,Inc.
AylwardEngineeringandSurveying,Inc.
FragaEngineers
HazenandSawyer,P.C.
NovaConsulting,Inc.
LauraLlerenaandAssociates,Inc.
EBSEngineering,Inc.
2.4 Teaming Restrictions FirmsmustselectbetweensubmittingasaRespondentorsubcontractor/subconsultantwhenrespondingtoaspecificsolicitation.AllaffectedSubmittalsandproposals,whereinafirmisinviolationofthiscondition,shallnotbeconsidered.
Respondentselectingtosubmitasaprimemayonlyrespondoncetoasolicitation,limitedtoparticipationonasingleteam.Ifsubmittingasaprime,saidfirmmaynotparticipateasasubconsultantonthesamesolicitation.Intheeventofspecificindustryrequirements,theCountyMayororCountyMayor’sdesigneemaymakeexceptions.
DuetotheavailabilityoffirmsineachofthespecifiedA/Etechnicalcertificationcategories,A/EsubconsultantsmayonlyparticipateonthreeProjectTeamswhenrespondingtoasolicitation.
Therearenoteamingrestrictionsforthefollowingtechnicalcertificationcategories:
- 9.01:Soils,FoundationsandMaterialsTesting–Drilling,SubsurfaceInvestigationsandSeismographicServices
- 9.02:Soils,FoundationsandMaterialsTesting–GeotechnicalandMaterialsEngineeringServices
- 9.03:Soils,FoundationsandMaterialsTesting–ConcreteandAsphaltTestingServices
- 9.04:Soils,FoundationsandMaterialsTesting–Non‐DestructiveTestingandInspections
Pleasebeadvisedthatintheeventafirmfailstoadheretotherestrictionsstatedhereinandparticipatesinmorethantheoutlinedmaximums,thenallaffectedSubmittalsandproposalsshallbefoundnon‐responsive.
2.5 Contract Measures ItisanticipatedthattheMiami‐DadeCountyCommunityBusinessEnterprises(CBE)andCommunitySmallBusinessEnterprises(CSBE)goalsfortheProjectshallbeasfollows:
[____]%CBEsub‐consultantgoal(A/EPortiononly)–RefertoExhibitA–CBEImplementingOrder3‐32
[____]%CSBEgoal,2nd,3rd,4thTier(ConstructionPortiononly).RefertoExhibitB–CSBEImplementingOrder3‐22
Miami‐Dade County, Florida Request for Qualifications (Step 1) South Miami Heights Water Treatment Plant Program December 2014 DRAFT – FOR PUBLIC COMMENT ONLY
NOT A PROCUREMENT SOLICITATION 2‐5 ORL.JKC.PW_XM1.6430.101067.04.15.07.40.01CDAM003_DRAFT‐RFQ_SMHWTP_121714
ProposedparticipatingCBE/CSBEfirmsmusthaveavalidMiami‐DadeCountyCBE/CSBEcertificationbytheStep1SubmittalDeadlineofthissolicitation.Ifselected,participatingCBE/CSBEfirmsmusthaveavalidCBE/CSBEcertificationatthetimeofawardofthecontractandthroughoutthecontractterm.RespondentsareadvisedthattheCBE/CSBEcertificationprocesstakesaminimumofeightweekstocomplete.RespondentsshallrefertothemostcurrentRERCSBECertificationlistavailableatthefollowinglink:http://www.miamidade.gov/business/reports‐certification‐lists.asp.
PursuanttoSection10‐33.02oftheCodeofMiami‐DadeCounty,Florida,“acontractorwhofailstomeetanestablishedCSBEgoalshallsubmitaCSBEMake‐upPlanforapprovalofthe[RegulatoryandEconomicResources(“RER”)]Director.AMake‐upPlanandacorrespondingScheduleofIntentAffidavitmustbesubmittedaspartofanybidorproposalsubmittal.”FailuretoincludetherequiredScheduleofAffidavitwithbidsorproposalsforanyfuturecontractsshallresultinthesubmittalbeingdeemednonresponsive.ToverifywhetheryourcompanyhasaCSBEmake‐uprequirement,pleaserefertotheRERwebpageathttp://www.miamidade.gov/business/reports‐certification‐lists.asp.Forquestionsregardingthisrequirement,contactRERat(305)375‐3131.
2.6 Vendor Registration ToberecommendedforawardtheCountyrequiresthatvendorscompleteaMiami‐DadeCountyVendorRegistrationPackage.TheVendorRegistrationPackage,includingaUniformAffidavitPacket(Affidavitform),mustbecompletedbyvendorsandreturnedtotheInternalServicesDepartment(ISD),VendorAssistanceUnit,within14daysofnotificationoftheintenttorecommendforaward.IntheeventtheVendorRegistrationPackageisnotproperlycompletedandreturnedwithinthespecifiedtime,theCountymayinitssolediscretion,awardtothenextlowestresponsiveandresponsibleproposer.TheproposerrecommendedforawardisresponsibleforobtainingtheVendorRegistrationPackage,includingallaffidavitsbydownloadingfromtheISDwebsiteatwww.miamidade.govorfromtheVendorAssistanceUnitat111N.W.1stStreet,13thFloor,Miami,FL33128.
2.7 Prequalification Allfirmsprovidingarchitectural,engineering,landscapearchitectural,landsurveyingandmappingprofessionalservicespursuanttoMiami‐DadeCountyprofessionalservicesagreementsmustbeprequalifiedinMiami‐DadeCounty.Pre‐qualificationcertificationistheconsolidationofthevariouscertificationprocessesintoonestreamlinedprocessandincludes,butmaynotbelimitedto,technicalcertification,affirmativeactionplanverification,vendorregistrationandexecutionofthebasicMiami‐DadeCountyaffidavits,asapplicable.Thepre‐qualificationcertificationprogramisadministeredbytheInternalServicesDepartment(ISD).Pre‐QualificationapprovalisgrantedtofirmswhohavereceivedapprovalfromISDonalltherequiredcertificationprocessesoutlinedabove.TheCounty’sprequalificationcertificationprocessisdescribedinmoredetailinExhibitF.
2.8 Requests for Additional Information; Addenda RequestsforadditionalinformationorinquiriesmustbemadeinwritingandreceivedbytheCounty’sA/ECoordinator,withacopyfiledwiththeClerkoftheBoard.RequestsforcopiesofallpublicdocumentsmaybeobtainedfromtheCounty’sA/ECoordinator.TheCountywillissueresponsestoinquiriesandanychangestothissolicitationitdeemsnecessaryinwrittenAddendaissuedtoallpartieswhohavedownloadedthisRFQpriortotheSubmittalDeadline.
Miami‐Dade County, Florida Request for Qualifications (Step 1) South Miami Heights Water Treatment Plant Program December 2014 DRAFT – FOR PUBLIC COMMENT ONLY
NOT A PROCUREMENT SOLICITATION 2‐6 ORL.JKC.PW_XM1.6430.101067.04.15.07.40.01CDAM003_DRAFT‐RFQ_SMHWTP_121714
2.9 Work History Disclosure AnyfirmincludedontheProjectTeamwhohasnotpreviouslysubmittedaWorkHistoryDisclosure(WHD)isrequiredtosubmitWHDformspriortotheSubmittalDeadlinetoMs.PatriceKing,RegulatoryandEconomicResourcesDepartment(RER),111N.W.1stStreet,19thFloor,Miami,FL33128,telephonenumber(305)375‐3103.Newfirmsrequestingpre‐qualificationcertificationwithMiami‐DadeCountytoprovideengineering,architectural,landscapearchitectural,landsurveyingand,mappingservicesarerequiredtosubmitWHDformstoRER.
2.10 Confidential Information Respondentshallnotsubmitanyinformationinresponsetothissolicitation,whichtheRespondentorotherProjectTeamMemberconsiderstobeatradesecretorconfidential.ThesubmissionofanyinformationtotheCountyinconnectionwiththissolicitationshallbedeemedconclusivelytobeawaiverofanytradesecretorotherprotection,whichwouldotherwisebeavailable.IntheeventthattheRespondentsubmitsinformationtotheCountyinviolationofthisrestrictionandclearlyidentifiesthatinformationintheSubmittalasprotectedorconfidential,theCountyshallendeavortoredactandreturnthatinformationtotheRespondentasquicklyaspossible,andifappropriate.TheCountywillthenevaluatethebalanceoftheSubmittal.TheredactionorreturnofinformationpursuanttothisclausemayrenderaSubmittalnon‐responsive.
2.11 Withdrawals ThepersonorrepresentativesigningtheStep1SubmittalshallbetheonlypersonorrepresentativeeligibletowithdrawsaidSubmittalinwritingbeforetheStep1SubmittalDeadline.
2.12 Costs Incurred AllexpensesinvolvedwiththepreparationandsubmissionofSubmittalsandotherinformationtotheCounty,oranyworkperformedinconnectiontherewith,shallbebornebytheRespondent.NopaymentwillbemadeforanySubmittalsorresponsesreceived,norforanyothereffortrequiredoformadebytheRespondentorotherProjectTeamMemberpriortocommencementofworkasdefinedbyacontractapprovedbytheBoardofCountyCommissioners.
2.13 Conflict of Interest Related to Section 2‐11.1 of the Code of Miami‐Dade County AnyquestionsregardingconflictofinterestrelatedtoSection2‐11.1oftheCodeofMiami‐DadeCountyshallbesubmittedbytheRespondentpriortotheStep1SubmittalDeadline,totheMiami‐DadeCountyCommissiononEthicsandPublicTrust(EthicsCommission),19WestFlaglerStreet,Suite820,Miami,FL33130,Attn:JosephCentorino,ExecutiveDirector,forevaluationastoanypossibleconflictofinterest,andcopiedtotheCounty’sA/ECoordinatorande‐mailfty@miamidade.gov.DeterminationsbytheEthicsCommissionshallbedeemedfinal.
2.14 Postponement/Cancellation TheCountymay,atitssoleandabsolutediscretion,rejectanyandall,orpartsofanyandallSubmittalsorproposals;re‐advertisethissolicitation;postponeorcancel,atanytime,thissolicitationprocess;orwaiveanyirregularitiesinthissolicitationorintheSubmittalsorproposalsreceivedasaresultofthissolicitation.
Miami‐Dade County, Florida Request for Qualifications (Step 1) South Miami Heights Water Treatment Plant Program December 2014 DRAFT – FOR PUBLIC COMMENT ONLY
NOT A PROCUREMENT SOLICITATION 2‐7 ORL.JKC.PW_XM1.6430.101067.04.15.07.40.01CDAM003_DRAFT‐RFQ_SMHWTP_121714
2.15 Contract Award Anycontract,resultingfromthissolicitation,willbesubmittedtotheCountyMayororCountyMayor’sdesigneeforapproval.AllproposerswillbenotifiedinwritingwhentheCountyMayororCountyMayor’sdesigneemakesanawardrecommendation.TheServiceContractaward,ifany,shallbemadetotheproposerwhoseproposalshallbedeemedbytheCountytobeinthebestinterestoftheCounty.Notwithstandingtherightsofprotestlistedbelow,theCounty'sdecisionofwhethertomaketheawardandtowhichproposershallbefinal.
2.16 Rights of Protest ArecommendationforcontractawardorrejectionofproposalsmaybeprotestedbyaRespondentinaccordancewiththeprocedurescontainedinSections2‐8.3and2‐8.4oftheCountyCode,asamended,andasestablishedinImplementingOrderNo.3‐21.
2.17 Miami‐Dade Water and Sewer Department Acceleration Ordinance ThisProjectisgovernedbytheproceduresandrequirementsoftheMiami‐DadeWaterandSewerDepartmentAccelerationOrdinanceassetforthinMiami‐DadeCountyCode§2‐8.2.11.
[EndofSection2]
Miami‐Dade County, Florida Request for Qualifications (Step 1) South Miami Heights Water Treatment Plant Program December 2014 DRAFT – FOR PUBLIC COMMENT ONLY
NOT A PROCUREMENT SOLICITATION 3‐1 ORL.JKC.PW_XM1.6430.101067.04.15.07.40.01CDAM003_DRAFT‐RFQ_SMHWTP_121714
Section 3
Submittal Requirements
3.1 Instructions for Respondents Communications Respondentsmustsubmitallquestions,requestsforadditionalinformationandothercommunicationsregardingSubmittalsandthisRFQinwritingtotheCounty’sA/ECoordinatordesignatedbelowandmustcomplywithotherCountyrequirementsconcerningcommunications,notlimitedtoSection2.7ofthisRFQ:
[________]111N.W.1stStreet,Suite1300
Miami,FL33128‐1974[_______]@miamidade.gov
EachpotentialRespondentshouldutilizeasingleindividualforcommunicationswiththeCounty’sA/ECoordinator.ThesubmissionofquestionsorrequestsforadditionalinformationfrommultiplepartiesassociatedwithapotentialRespondentshouldbeavoided.TelephonecommunicationswiththeCounty’sA/ECoordinatorareprohibited.EmailisthepreferredformofcommunicationwiththeCounty’sA/ECoordinator.ResponsestocommunicationsfrompotentialRespondentswillbeprovidedinwritingandmadeavailabletoallpotentialRespondents.
Submission Deadline ThecompleteSubmittalmustbesubmittedelectronicallythroughtheCounty’sBidSyncElectronicBiddingSystemnolaterthan3:00PM,localMiamitime[__________________](SubmissionDeadline).AnySubmittalreceivedaftertheSubmissionDeadlinewillnotbeconsidered.NoinformationorsupplementalmaterialwillbeacceptedaftertheSubmissionDeadline,exceptforinformationandmaterialsthatmayberequestedinwritingbytheCountyaspartoftheSubmittalreviewandevaluationprocess.
Delivery of Hard Copies Within48‐hoursoftheSubmissionDeadline,tenhardcopiesoftheelectronicSubmittal(witheachhardcopyalsocontainingaCDelectroniccopyoftheSubmittalinsearchablepdfformat)mustbeaddressedanddeliveredinsealedboxesorenvelopesto:
Miami‐DadeCounty,ClerkoftheBoardStephenP.ClarkCenter
111N.W.1stStreet,17thFloor,Suite202Miami,Florida33128Attention:[________]
Re:ISDProjectNo.14‐DBFO‐WASD‐01
ThesealedboxesorenvelopesmusthavetheRespondentnameandaddressandthefollowinginformationclearlymarkedandvisibleontheexterior:“SouthMiamiHeightsWaterTreatmentPlantProgram–RFQSubmission.”TheClerkoftheBoardwillstampthehardcopiesofeachSubmittalwiththedateofreceipt.Thisstampwillconstitutedefiniteevidenceofsuchdateandtime.Failureto
Miami‐Dade County, Florida Request for Qualifications (Step 1) South Miami Heights Water Treatment Plant Program December 2014 DRAFT – FOR PUBLIC COMMENT ONLY
NOT A PROCUREMENT SOLICITATION 3‐2 ORL.JKC.PW_XM1.6430.101067.04.15.07.40.01CDAM003_DRAFT‐RFQ_SMHWTP_121714
delivertherequiredhardcopiesinaccordancewiththeaboverequirementsmayresultinaSubmittalbeingdeemednon‐responsive.
TheresponsibilityfordeliveringhardcopiesoftheSubmittalandforsubmissionelectronicallythroughtheCounty’sBidSyncElectronicBiddingSystemonorbeforethestatedtimesanddatesissolelyandstrictlytheresponsibilityoftheRespondent.TheCountyisnotresponsiblefordelayscausedbyanymail,packageorcouriersservice,includingtheU.S.mail,orcausedbyanyotheroccurrence.
Changes in the Project Team ChangestotheProjectTeamsetforthinaSubmittal,suchasadding,deletingorreplacingafirm(s)orindividual(s)aftertheSubmittalDeadline,willonlybeallowedatthediscretionoftheCounty.
RFQ Ambiguity, Conflict or Error Ifanyambiguity,conflictorerrorisfoundinthisRFQ,thepotentialRespondentmustprovideimmediatewrittennotificationofsuchambiguity,conflictorerrortotheCounty’sA/ECoordinatoratleastfive(5)dayspriortotheSubmissionDeadline.
3.2 Required Format Respondentsareencouragedtobeconcise,factualandcompleteinrespondingasdirectlyaspossibletotherequirementssetforthinthisRFQ.Notincludingtheappendices,theSubmittalshouldnotexceed75pages.Themarginsoneachpagemustnotbelessthan1‐inchandfontsizemustnotbelessthan11point.Eachpagemustbe8‐1/2inchesby11inchesandthehardcopiesmustbeboundintoasingledocumentandtabbedwiththeinformationbelow,providedthattheappendicesmaybepresentedasoneormoreseparatedocumentsorvolumes.RespondentsareadvisedthatrequiredformstobesubmittedwiththeRFQwillnotbecountedtowardsanypagelimitations.
TheStep1Submittalmustbeorganizedasfollows:
1. TransmittalLetter
2. ExecutiveSummary
3. QualificationsSummary
4. OrganizationandManagement
5. ProjectExperienceandCapabilities
6. FinancialCondition
7. PastPerformance
8. AppendixA–Resumes(maximum2pageseach)
9. AppendixB–ContractorLicenses
10. AppendixC–FinancialStatements
11. AppendixD–Affidavits
Marketingbrochures,genericnarrativesandaudiovisualmaterials,suchasaudiorecordingsorvideorecordingsortapes,shallnotbeincluded.
3.3 Required Contents TherequirementsoutlinedinthissectionrepresenttheminimumcontentthatmustbeincludedintheSubmittalandarenotintendedtolimitsubstantivecontent(unlessexpresslystatedotherwise).TheSubmittalmustdemonstratethattheProjectTeampossessestheexpertise,experience,capabilities
Miami‐Dade County, Florida Request for Qualifications (Step 1) South Miami Heights Water Treatment Plant Program December 2014 DRAFT – FOR PUBLIC COMMENT ONLY
NOT A PROCUREMENT SOLICITATION 3‐3 ORL.JKC.PW_XM1.6430.101067.04.15.07.40.01CDAM003_DRAFT‐RFQ_SMHWTP_121714
andresourcesrequiredforthedesign,permitting,construction,financing,andoperationandmaintenanceoftheProject.ItistheRespondent’sresponsibilitytoincludeinformationintheSubmittalthatsatisfiesthecontentrequirementssetforthinthisSection3.3aswellasanyadditionalinformationthatfurtherdemonstratesrelevantqualificationsandcapabilities.Amaterialfailuretoprovidetherequestedinformation,whichintheCounty’ssolediscretionimpedestheCounty’sabilitytounderstandtheSubmittalorcomparetheSubmittaltoothers,deprivestheCountyoftheassurancethatifawardedthecontractwouldbeenteredintoandperformedinaccordancewithitsmaterialterms,orotherwiseplacestheRespondentoritsProjectTeaminamaterialadvantageoverotherrespondents,mayresultinaSubmittalbeingdeemednon‐responsive.
Transmittal Letter ThetransmittallettermustbesignedbyarepresentativeoftheRespondentwhoisauthorizedtosignsuchmaterialandtocommittheRespondenttotheProjectobligationsandmustinclude:(a)name,title,address,telephoneandfaxnumbers,andemailaddressfortheRespondent’scontactpersonregardingallmattershavingtodowiththisRFQandtheSubmittal,(b)thenameofeachProjectTeamMember,and(c)confirmationofreceiptofallRFQaddenda.TheCertificateofAuthorization(Attachment1totheCoverLetter)attestingtosuchauthorizationmustalsobesubmittedwiththeCoverLetter.IftheRespondentisapartnership,theCoverLettershallbesignedbyoneormoreofthegeneralpartners.IftheRespondentisacorporation,anauthorizedofficershallsignhisorhernameandindicatehisorhertitlebeneaththefullcorporatename.IftheRespondentisajointventure,anauthorizedrepresentativeofeachfirminthejointventureshallsigntheCoverLetter.Anyonesigningasanagentmustfilewithitlegalevidenceofhisorherauthoritytoexecuteassuch.AllformsthatrequirethesignatureoftheRespondentshallbesignedbytheRespondent’sauthorizedrepresentative.ThetransmittallettermustalsoclearlyindicateRespondent’scommitmenttotimelydeliveryoftheProjectandintenttoparticipateintheStep2RFPprocessifincludedontheshort‐listofAdvancingFirms.
Executive Summary ThissectionshouldnotexceedthreepagesandmustsummarizetheSubmittal,brieflydescribetherole,officelocation,andqualificationsofeachProjectTeamMemberandKeyPersonnel,experienceinperformingDBOprojectsandhighlightthosequalificationsthatrelatemostdirectlytotheScopeofServicesfortheProjecttakingintoaccounttheComparativeEvaluationCriteriasetforthinTable4.1below
Qualifications Summary ThissectionmustsummarizeandrefertotheinformationpresentedelsewhereintheSubmittalthatdemonstratestheexperienceandqualificationsoftheProjectTeam.
Organization and Management ThissectionmustdescribetheCompanyandtheorganization,managementandintegrationoftheProjectTeam,ProjectTeamMembersandtheKeyPersonnelforexecutionoftheProjectinatimelyandeffectivemanner.Thesectionshallalsodescribetherelationship,contractualorotherwise,betweentheProjectTeamMembersandtheCompany.Thefollowinginformationmustbeprovided,asapplicable,fortheexistingorproposedCompany(and,ifincluded,theGuarantor):
Legalformofentity;
Dateandplace(state)offormation;
Briefhistoryofbusinessandprojects;
Listofallofficersandbriefworkhistory;
Miami‐Dade County, Florida Request for Qualifications (Step 1) South Miami Heights Water Treatment Plant Program December 2014 DRAFT – FOR PUBLIC COMMENT ONLY
NOT A PROCUREMENT SOLICITATION 3‐4 ORL.JKC.PW_XM1.6430.101067.04.15.07.40.01CDAM003_DRAFT‐RFQ_SMHWTP_121714
ListofallAffiliates;
Ifacorporation,namesoftheboardofdirectors,listofallstockholdersholdingtenpercentormoreofoutstandingshares,andgenerallydescribetheownershipofsharesnotincludedintenpercentormoreblocks;
Ifalimitedliabilitycompany,namesofallmembersalongwithrespectivepercentageofmembershipinterest,namesofallmanagersandofficers;or
Ifapartnership,namesofallpartnersindicatingstatusasgeneralorlimited.
Foreachcorporatememberofalimitedliabilitycompanyoreachgeneralandlimitedpartnerofageneralorlimitedpartnership,theinformationrequiredaboveforacorporationmustbeprovided.Furthermore,theroleandauthorityofeachshareholder,memberorpartnerinmanagementandcontroloftheCompanymustbeclearlydescribed.
Forallcontractors,subcontractors,consultants,subconsultantsandKeyPersonnelcomprisingtheProjectTeam,theSubmittalshalldescribewhetherawrittenagreementorothervalidcontractualcommitmentexiststoperformtheworkrequiredundertheProject.Ifnoagreementexists,theSubmittalshalldescribethecontingenciesorotherassumptionswhichmustbesatisfiedforsuchagreementtoexistandthelikelihoodthatthesamewillbesatisfied.
ThefollowinginformationmustbeincludedinthissectionoftheSubmittaltodescribetheorganizationandmanagementoftheProjectTeamMembersandtheKeyPersonnel:
Adescriptionofprojectmanagement,ProjectTeamorganizationstrategy,decision‐makingprocesses,andoverallmanagementphilosophy;
AfirmorganizationchartdepictingthereportingandcontrolstructurefortheProjectTeam,adescriptionoftheroleandscopeofworkofeachProjectTeamMember,andthecontractualandaccountabilityrelationships;
ApersonnelorganizationchartshowingthereportingandcontrolstructureforKeyPersonnel;
Adescriptionofthesafetyandthequalityassurance/qualitycontrolprogramfortheProject;
AdescriptionofprojectswhereProjectTeamMembershaveworkedtogether;and
AdescriptionoftheRespondent’sapproachandphilosophytowardsachievingacooperative,partnershipenvironmentamongtheProjectTeamMembersandtheCompanyandProjectTeam’sabilitytointerfacesuccessfullywiththeCountyandtheDesignCriteriaProfessional.
ThissectionmustalsodescribehowtheCompanywillcomplywiththecontractmeasuressetforthinSection2.5ofthisRFQconcerningtheparticipationofCommunityBusinessEnterprises(CBE)andCommunitySmallBusinessEnterprises(CSBE)intheProjectandmustincludetheSBDUtilizationandAssuranceFormdulyexecutedbytheRespondent.
Project Experience and Capabilities ThissectionmustdescribedirectlyrelevantprojectssuccessfullycompletedinthepasttenyearsbyProjectTeamMembersandKeyPersonnel,describethecapabilitiesofProjectTeamMemberswithrespecttoassignedrolesontheProject,anddescribetheavailabilityandrelevantcapabilitiesofKeyPersonnelandotherpersonnel.
Foreachsuchreferenceproject,include:
Projectname,location,andtype;capitalandO&Mcostvalues,andprojectstatus(startandcompletiondates);
Nameofclientandcontactinformation;
Miami‐Dade County, Florida Request for Qualifications (Step 1) South Miami Heights Water Treatment Plant Program December 2014 DRAFT – FOR PUBLIC COMMENT ONLY
NOT A PROCUREMENT SOLICITATION 3‐5 ORL.JKC.PW_XM1.6430.101067.04.15.07.40.01CDAM003_DRAFT‐RFQ_SMHWTP_121714
Projectdescription,relevancytotheProject,andspecificscopeofservicesbyProjectTeamMember(s);
RoleofProjectTeamMember(s)andKeyPersonnel;and
Discussionofhowunanticipatedcircumstancesandchallengeswereaddressed.
ResumesforKeyPersonnelandotherpersonnelshouldbeincludedinAppendixAtotheSubmittalandmustidentifyprofessionalregistrations,certificationsandlicenses,asapplicable,forperformingarchitectural,designandplantoperationsservicesintheStateofFlorida.Eachresumemustnotexceedtwopages.
CopiesofthecertifiedorregisteredgeneralcontractororbuildingcontractorlicensesfortheDesign‐BuilderandLeadConstructor(s),asapplicable,oranydesign‐buildorconstructionjointventureagreementandstatementsofauthorityapprovalbytheStateofFloridaDepartmentofProfessionalRegulationConstructionLicensingBoard(CILB)orproofofsubmittaltotheCILBofthejointventureagreementandstatementsofauthoritymustbeincludedinAppendixBtotheSubmittal.
Inaddition,aone‐pagetablemustbeincludedtocross‐referenceeachreferenceprojectwithProjectTeamMembersandKeyPersonnel.
Financial Condition ThissectionandAppendixCtotheSubmittalmustincludefinancialandrelatedinformationfortheCompany,Guarantor(ifproposed),Design‐Builder(ortheLeadDesignerandLeadConstructor,ifnotintendingtoutilizedesign‐builddelivery),andtheLeadOperator.PleasenotethattheCountyisseekingsingle‐pointresponsibilityforthefullScopeofServicesandisnotinterestedinanarrangementwherebyfinancialresponsibilitywouldbedividedamongmultipleGuarantorsorotherparties.Also,itistheCounty’spreferencethattheCompanyorGuarantorbeasufficientlycapitalizedUnitedStatesentity.IftheCompanyorGuarantorwouldnotbeaUnitedStatesentity,RespondentmustdescribeanyandallproceduralandsubstantivelimitationsontheabilityoftheCountytoenforcetheServiceContractagainsttheCompanyortheGuarantor.
IftheRespondentisunableorunwillingtoprovidetheinformationrequested,theRespondentshallprovideawrittenexplanationforsuchomission.TheCountyshallbeentitledtoconsidersuchabsenceofinformationascreatinganadditionalrisktotheCountyandmaygradetheProposalaccordingly.TheCountyreservestherighttorequestfinancialstatementsandinformationfromanyotherProjectTeamMember.
FinancialStatements.FortheCompany,Guarantor(ifproposed),Design‐Builder(orLeadDesignerandLeadConstructor),andLeadOperator,AppendixCtotheSubmittalmustinclude:
- Auditedfinancialstatements(income,balancesheet,andcashflow;andauditor’sreport,opinionandallrelevantnotes)forthepastthreeyearspreparedinaccordancewithgenerally‐acceptedaccountingprinciples.Quarterlyfinancialstatements,whichmaybeunauditedbutmustbecertifiedbytheChiefExecutiveOfficer,forthecurrentfiscalyear.
- ThemostrecentForm10‐KandForm10‐QfiledwiththeSecuritiesandExchangeCommission(SEC),ifregulatedbytheSEC.
- Allcreditreports,creditbulletins,ratingsorotherstatementspublishedwithinthepastthreeyearsbyrecognizedratingagencies(includingStandard&Poor’sRatingServices,Moody’sInvestorServices,andDun&Bradstreet).
- Anyadditionalinformationtofullycharacterizefinancialcondition,includinganyoff‐balancesheetobligationsorguaranteesnotfullydescribedintheauditedfinancial
Miami‐Dade County, Florida Request for Qualifications (Step 1) South Miami Heights Water Treatment Plant Program December 2014 DRAFT – FOR PUBLIC COMMENT ONLY
NOT A PROCUREMENT SOLICITATION 3‐6 ORL.JKC.PW_XM1.6430.101067.04.15.07.40.01CDAM003_DRAFT‐RFQ_SMHWTP_121714
statements.Forexample,theprospectusorofferingstatementforrecentdebtorequityofferings,ifavailable,shouldbeincluded.
BondsandInsurance.ThissectionmustincludethefollowingdocumentationtodemonstratetheabilitytosatisfythebondandinsurancerequirementsoftheMinimumQualificationRequirements:
- Respondentsmustdemonstrateitscapabilitytoprovideadesign‐buildperformanceandpaymentbondandanannualoperationandmaintenanceperformanceandpaymentbondinaccordancewiththerequirementsforthisProjectbyincludinginitsSubmittalaletterfromitssuretycompanyindicatingtheRespondent’sbondingcapacity.ThesuretycompanymustbeauthorizedtodobusinessintheStateofFloridaandthebondsandSuretyCompanymustcomplywiththerequirementsofthisRFQ,includingthesuretycompanyratingsastomanagementandstrength.Thelettermustindicatethat,basedontheinformationavailableasofsuchdateoftheletter,thereisnoreasontobelievethatthesuretywouldnotprovideperformanceandpaymentbondsfortheProject(subjecttoreviewofthetermsoftheServiceContract)andthatthatRespondenthassufficientbondingcapacityavailabletomeettherequirementssetforthinthisRFQfortheProject.
- RespondentsmustacknowledgethatifselectedinStep2,theCompanywillcomplywiththeinsurancerequirementssetforthinthisRFQ(subjecttomodificationintheStep2RFP)andmustdemonstrateitscapacitytoprovideinsuranceinaccordancewiththerequirementsfortheProjectbyincludinginitsSubmittalaletterfromarecognizedinsurancebrokerorinsurancecompaniesauthorizedtodobusinessintheStateofFloridathatinsurancecoverageisorwouldbeavailabletotheCompanymeetingtherequirementssetforthinthisRFQ.
FinancialQuestions.ThissectionmustincluderesponsestothequestionslistedbelowwithrespecttotheCompany(andanyGuarantor).Ifanyofthesequestionsareansweredinanunfavorablemanner,RespondentmustdescribeindetailtheunfavorablefactororeventandmustdemonstratethattheunfavorablefactororeventwillnotadverselyimpacttheCompany’sabilitytoperformtheProject.
- MaterialChangesinFinancialPosition–Arethereanyrecent(past3years),existingoranticipatedmaterialchangesinfinancialposition,includingmaterialchangesinthemodeofconductingbusiness,mergers,acquisitions,takeovers,jointventures,and/ordivestitures?
- Bankruptcy–Inthelasttenyears,hastherebeenavoluntaryorinvoluntaryfilingforbankruptcy?
CreditReferences.ThissectionmustincludeatleasttworeferencesforlendinginstitutionsthathaveextendedsignificantcredittotheCompany(andanyGuarantor)withinthepasttwoyears.
ClaimsandLitigation.ListandbrieflydescribetheclaimsduringthepastfiveyearsandthemeritsofallpendingandthreatenedlitigationandcontingentliabilitiesfortheCompany(and,ifprovided,Guarantor).Arethereanythreatened,pendingorpastlegalproceedingsorjudgments,oranycontingentliabilitiesthatcouldadverselyaffecttheabilityoftheCompanytoperformtheProject?Ifyes,pleasedescribe.IsanyProjectTeamMemberinvolvedwithanyclaims,litigationoradministrativeactionagainsttheCountyortheStateofFlorida?Ifyes,pleasedescribe.
Miami‐Dade County, Florida Request for Qualifications (Step 1) South Miami Heights Water Treatment Plant Program December 2014 DRAFT – FOR PUBLIC COMMENT ONLY
NOT A PROCUREMENT SOLICITATION 3‐7 ORL.JKC.PW_XM1.6430.101067.04.15.07.40.01CDAM003_DRAFT‐RFQ_SMHWTP_121714
Past Performance ThissectionmustdescribeanyinstanceduringthepasttenyearswhereaProjectTeamMemberoranyKeyPersonnelhas(a)failedtocompleteacontractorhasbeenterminatedonthegroundsofallegedbreach,default,ornonperformance,(b)beenconvictedofanycriminalconductorbeenfoundinviolationofanylawconcerningantitrust,publiccontracting,discrimination,orprevailingwages,or(c)beenbarredfrombiddingbythefederalgovernmentoranystategovernmentonpubliccontracts.
SafetyRecord.ThissectionmustincludetheExperienceModificationRate(EMR)dataforeachProjectTeamMemberforeachofthepastthreefullcalendaryears(2013,2012and2011or2010if2013dataarenotavailableasoftheSubmissionDeadline)onafirm‐widebasisandshallalsoprovidethethree‐yearaveragevaluesforeachfirm.SuchEMRdatamustbedocumentedbyaletterwithcontactinformationfromtheProjectTeamMember’sinsurancecarrierortheinsurancecarrier’srepresentative.ThissectionmustalsoincludeOccupationalSafetyHealthAct(OSHA)forms300and300AforeachProjectTeamMemberforthepastthreefullcalendaryearsindicatingOSHAsubmittedaccidentdata.
ClientReferences.ThissectionmustincludethreeclientreferencesfortheRespondentorCompany,theDesign‐Builder,theLeadConstructor(s),theLeadDesign(s),andtheLeadOperator,andtwoforeachoftheotherProjectTeamMembersandeachoftheKeyPersonnel.Inallcases,thereferencesmustbeforcurrentprojectsorforprojectscompletedwithinthepastfiveyears.PleasebesurethateachoneoftheclientreferencesprovidedhasbeenadvisedthattheymaybecontactedbyCountystafforotherdesignee.
PursuanttoaCommissiononEthicsandPublicTrustopiniondatedMarch15,2005,potentialRespondentsrequestingprofessionalreferencesfromCountyemployeesmustsubmitsaidrequestinwritingtotheattentionofthesubjectCountyemployeeandcopytheClerkoftheBoard(COB).NotethattheCOBmaybereachedeitherviaemailatclerkbcc@miamidade.govorfacsimileat(305)375‐2484.Beadvisedthatpursuanttosection2‐11.1(p)oftheMiami‐DadeCountyCode,Countyemployeesmaynotprovidepersonallettersofrecommendationsforprofessionalservicesforanypersonorfirmforthesubjectproject.
ClientDisputes.ThissectionmustdiscussCompanyandRespondentdisputeswithclientsthathaverequiredsettlementagreementsorthirdpartyresolution(mediation,independentexpert,disputepanel,arbitrationorcourt)onprojectsunderwayorcompletedinthepasttenyearsandmustdescribeallsettledclaims,disputesorlawsuitswithanownerofaprojectduringsuchtenyearperiod.
Miscellaneous.ThissectionmustdescribeallOSHAviolationsandallworkers’compensationandsafetyclaims,aswellasprovideadetaileddescriptionofthesafetyrecord,insuranceclaimandlossrecord,andcompliancewithapplicableDavis‐BaconActrequirements,duringthepastfiveyearsfortheRespondentorCompany,theDesign‐Builder,theLeadConstructor(s)andotherProjectTeamMembersthatwouldperformconstructionwork.ThissectionmustdescribeanystatelicensingviolationbyanyProjectTeamMemberallegedordeterminedduringthepasttenyearsandmustcertifythatnocommercialbankruptcy,debarment,disqualification,default,orearlycontractterminationoftheRespondent,theCompany,orProjectTeamMemberhasoccurredinthepastfiveyears.
Required Affidavits RespondentsmustincludeinAppendixDofitsSubmittalthefollowingaffidavitsdulyexecutedbyanauthorizedrepresentativeoftheRespondent(seeAppendixBtothisRFQfortherequiredformsofaffidavits):
Miami‐Dade County, Florida Request for Qualifications (Step 1) South Miami Heights Water Treatment Plant Program December 2014 DRAFT – FOR PUBLIC COMMENT ONLY
NOT A PROCUREMENT SOLICITATION 3‐8 ORL.JKC.PW_XM1.6430.101067.04.15.07.40.01CDAM003_DRAFT‐RFQ_SMHWTP_121714
LocalBusinessPreferenceAffidavit–ifclaimingalocalofficeinMiami‐DadeCounty
Respondent’sAffidavit
DebarmentDisclosureAffidavit
CriminalRecordAffidavit
CollusionAffidavit
PublicEntityCrimesSwornStatement
[EndofSection3]
Miami‐Dade County, Florida Request for Qualifications (Step 1) South Miami Heights Water Treatment Plant Program December 2014 DRAFT – FOR PUBLIC COMMENT ONLY
NOT A PROCUREMENT SOLICITATION 4‐1 ORL.JKC.PW_XM1.6430.101067.04.15.07.40.01CDAM003_DRAFT‐RFQ_SMHWTP_121714
Section 4
Evaluation of Submittals
4.1 Overall Process TheSubmittalswillbereviewedandevaluatedbytheCompetitiveSelectionCommittee(CSC)appointedbytheCountyMayororCountyMayor’sdesigneewithassistanceprovidedbytheDesignCriteriaProfessionalandotheroutsideconsultantsandadvisorsutilizingtherequirementsandcriteriaoutlinedinthisSection4andinothersectionsofthisRFQ.TheCSCappointedbytheCountyMayororCountyMayor’sdesigneewillbecomprisedofappropriateCountypersonnelfrommultipledepartmentsandmembersofthecommunity,asdeemednecessary.CSCmemberswillbeappointedbasedonappropriateexperienceand/orknowledge,strivingtoensurethattheCommitteeisbalancedwithregardtobothethnicityandgender.TheCSCistaskedwithevaluatingRespondentqualificationsanddeterminingashortlistofaminimumofthreeofthehighestqualifiedRespondentstoproceedtotheStep2.
TheStep1SubmittalwillinitiallydeterminetheresponsivenessoftheSubmittal.EachSubmittalthatisdeterminedtoberesponsivewillbeevaluatedandrankedbytheCSCusingtheComparativeEvaluationCriteria.ThisRFQprocesswillconcludewiththeCSC’sissuanceofashortlistoftheAdvancingFirmstoStep2.
AtanytimeduringtheRFQevaluationprocess,theCSC,otherCountyemployeesorrepresentatives,includingtheDesignCriteriaProfessionalandotheroutsideconsultantsandadvisors,may(a)submitwrittenquestionsorrequestsforclarificationstoaRespondentregardingitsSubmittalorrelatedmatters,(b)contactreferencesincludedintheSubmittalandotherthirdpartiesnotincludedasreferencesintheSubmittaltoobtaininformationregardinganyProjectTeamMemberorKeyPersonnel,and(c)visitfacilitiesandclientsassociatedwithanyProjectTeamMemberorKeyPersonnel(whetherornotsuchfacilityorclientisincludedintheSubmittal).FailuretorespondinatimelymannertoanysuchquestionsorrequestsmaybegroundsforeliminationoftheRespondentfromfurtherconsideration.TheCountymayrequirethatalloralimitednumberofRespondentsparticipateininterviews.
TheCSCmay,atitsdiscretion,waiveanyfailureofaSubmittaltosatisfytherequirementsofthisRFQifitdeterminesthatsuchwaiverisinthebestinterestoftheCountyormayrequestclarificationoradditionalinformationfromaRespondenttocureanysuchfailure.
4.2 Qualifications ThefollowingisastatementoftheCounty’sexpectationswithrespecttothequalificationofthepersonscontractingwiththeCountyandperformingthework.IntheeventthattheProjectTeamdoesnotmeetthequalificationssetforthbelow,theSubmittalshalldescribeindetailhowtheproposerwouldprovidetheCountywithprotectionsthatmeetorexceedtheprotectionsaffordedbythestatedqualifications.FailuretomeetthestatedqualificationsmaybeconsideredbytheCountytopresentagreaterrisktotheCountyandrankedaccordingly.Inaddition,theCountymayatanytimedecidethatthelackofqualificationsinanySubmittalpresentssuchriskstotheCountythattheSubmittalshouldberejected.Insuchinstance,theSubmittalmayberejectedatanytimeintheCounty’ssolediscretion.
Miami‐Dade County, Florida Request for Qualifications (Step 1) South Miami Heights Water Treatment Plant Program December 2014 DRAFT – FOR PUBLIC COMMENT ONLY
NOT A PROCUREMENT SOLICITATION 4‐2 ORL.JKC.PW_XM1.6430.101067.04.15.07.40.01CDAM003_DRAFT‐RFQ_SMHWTP_121714
Financial Requirements TheSubmittalshouldevidencetheProjectTeam’sabilitytocomplywiththefollowingfinancialrequirements:
PerformanceandPaymentBonds.Abilitytoprovidedesign‐buildperformanceandpaymentbondsinanamountnotlessthan[________]millionfortheCompany’sdesign,constructionandperformancetestingobligationsfortheProjectundertheServiceContractandperformanceandpaymentbondsinanamountnotlessthan[________]millionfortheCompany’sannualoperationandmaintenanceobligationsfortheProjectundertheServiceContract.
Insurance.AbilitytoprovidethefollowingcoveragefortheProject:(a)GeneralLiabilityonstandardoccurrenceformwithminimumlimitsof$1,000,000peroccurrence,$2,000,000intheaggregate,and$2,000,000productscompletedoperations;(b)AutomobileLiabilitywithminimumlimitsof$1,000,000peraccident;(c)Employer’sLiabilityandWorkers’Compensationmeetingstatutoryrequirements;(d)EnvironmentalLiabilitywithminimumlimitsof$10,000,000perclaimand$20,000,000annualaggregate;(e)Builder’sRiskwithaminimumlimitof$40,000,000;and(g)ProfessionalLiabilitywithminimumlimitsof$10,000,000perclaimand$20,000,000annualaggregate;and(h)Umbrella/ExcessLiabilityofatleast$50,000,000peroccurrenceandintheaggregate.Respondentmustdemonstratethatadequateself‐insurancereservesexistforanydeductibleamountgreaterthan$50,000.
SufficientFinancialStrength.ThefinancialstatementsandotherfinancialinformationsetforthintheSubmittalmustdemonstratesufficientfinancialstrengthtoundertaketheobligationsandrisksassociatedwithdesign,permitting,construction,financingandlong‐termoperationandmaintenanceoftheProject.TheCompany,GuarantorandProjectTeamMembersmaynotbesubjecttoamaterialadversecondition,suchaspendinglitigation,insufficientliquidity,insufficienttangiblenetworth,insufficientnetincome,orexcessiveleverage,thatcouldgiverisetoreasonabledoubtconcerningitsabilitytocontinuetooperateasanongoingconcern,toproviderequiredperformanceandpaymentbondsorinsurance,ortomaintainsufficientfinancialstrengthtoundertakeobligationsandrisksassociatedwithdesign,permitting,construction,financingandlong‐termoperationandmaintenanceoftheProject.
Licensing and Authorizations ProjectTeamMembersandKeyPersonnelmustholdtheapplicablelicenses,registrations,authorizationsorcertificationsrequiredbylawfortheperformanceoftheirrespectivedisciplines,scopesofworkorservices.TheSubmittalmustdemonstratesatisfactionofallapplicablerequirementsoftheCountyandtheStateofFloridawithrespecttotheworkorservicesthatwouldbeperformedfortheProjectbyeachProjectTeamMemberandKeyPersonnel,including(butnotlimitedto)aStateofFloridaregisteredProfessionalEngineer(s)whowillsignandsealconstructionplansandspecifications.
A/EfirmsincludedonaProjectTeam,asapplicable,mustsatisfytheCounty’spre‐qualificationrequirementssetforthinAppendixE(CountyPre‐QualificationofA/EFirms).FailureofanyfirmsdenotedontheProjectTeamsasanA/Edesignfirmtobetechnicallycertified,asapplicable,atthetimeStep1SubmissionDeadlinemayrendertheSubmittalnon‐responsive.AlldesignA/EfirmsofrecordmustbeRegisteredProfessionalArchitectsorEngineersintheStateofFloridaintheirrespectivedisciplines.
Design‐BuildersincludedonaProjectTeammust,notlaterthantheStep1SubmissionDeadlineandatalltimesthereafter,includingtheevaluationandselectionprocess,timeofaward,andthroughoutthedurationofthecontract,meettherequirementsstatedbelow.PursuanttoFloridaStateStatutes287.055,aDesign‐Builderisdefinedasapartnership,corporation,orotherlegalentitythat:
Miami‐Dade County, Florida Request for Qualifications (Step 1) South Miami Heights Water Treatment Plant Program December 2014 DRAFT – FOR PUBLIC COMMENT ONLY
NOT A PROCUREMENT SOLICITATION 4‐3 ORL.JKC.PW_XM1.6430.101067.04.15.07.40.01CDAM003_DRAFT‐RFQ_SMHWTP_121714
IscertifiedunderSection489.119,FloridaStatutes,toengageincontractingthroughacertifiedorregisteredgeneralcontractororacertifiedorregisteredbuildingcontractorasthequalifyingagent;or
IscertifiedunderSection471.023,FloridaStatutes,topracticeengineering;certifiedunderSection481.219topracticearchitecture;orcertifiedunderSection481.319topracticelandscapearchitecture.
ThoseDesign‐BuildersorganizedasaJointVenturemustprovidedocumentationforeachentityparticipatingintheJointVenturetoincludethelegalnameofthecompaniesparticipatingintheJointVentureasregisteredwiththeStateofFloridatogetherwithcopiesoftheJointVentureagreementandstatementsofauthorityassubmittedtotheStateofFloridaDepartmentofProfessionalRegulationConstructionIndustryLicensingBoard(CILB).CopiesofthejointventureagreementandstatementsofauthorityandproofofsubmissiontotheCILBfromthosefirmssubmittingasaJointVenturemustbesubmittedtoandreceivedbytheCILBpriortotheStep1SubmissionDeadline.TheJointVentureagreementandstatementsofauthoritymustbeapprovedbytheCILBBoardOfficepriortotheStep2ProposalDeadlineforthoseAdvancingFirms.
FailureforaDesign‐Buildertoholdacurrentvalidcertificate,asindicatedabove,orfailureforthoseJointVenturefirmstosubmittherequireddocumentationtotheCILBbytheStep1SubmissionDeadlinemayrendertheSubmittalnon‐responsive.TheJointVenturemustbequalifiedbytheCILB.
Safety Record Thethree‐yearaverageforthelastthreefullyearsofExperienceModificationRate(EMR)fortheLeadConstructor(s)mustnotexceed1.10.
Project Experience TheSubmittalshouldidentifyeachofthefollowingpersons,andforeachprovidesufficientinformationfortheCountytoperformanevaluationofhowsuchpersonsatisfiesthestatedrequirementorequivalent.TheSubmittalshouldevidencetheProjectTeam’sabilitytocomplywiththefollowingprojectexperiencerequirements:
WaterTreatmentPlantLeadDesigner.TheLeadDesignerforthemembranewatertreatmentplantshouldhavesuccessfullycompleted,withinthepasttenyears(includingprojectsatleast50%completeasoftheSubmissionDeadline),thedesignofatleasttwomembranetreatmentplantsthattreatbrackishgroundwaterforpotableuse,withaminimumtreatedwaterproductioncapacityof5mgdeach.
RawWaterSupplyLeadDesigner.TheLeadDesignerforthewatersupplywellsshouldhavesuccessfullycompleted,withinthepasttenyears(includingprojectsatleast50%completeasoftheSubmissionDeadline),thedesignofatleastthreerawwatersupplysystemsthatextractgroundwaterfortreatmentforpotableuse,withaminimumrawwatersupplyproductioncapacityof10mgdeach.AtleastonewellfieldmustbeinthesurficialBiscayneAquifer(unconfined)andonewellfieldintheUpperFloridanAquifer(confined).
DeepWellInjectionLeadDesigner.TheLeadDesignerforthedeepwellinjectionsystemshouldhavesuccessfullycompleted,withinthepasttenyears(includingprojectsatleast50%completeasoftheSubmissionDeadline),thedesignofatleastonedeepwellinjectionsystemsthatdisposeofconcentratefrommembranetreatmentfacilitiesintotheFloridanAquifer“BoulderZone”,withaminimumconcentratedisposalcapacityof2mgdeach.
LeadConstructor(s).TheLeadConstructor(s)shouldhavesuccessfullycompleted,withinthepasttenyears(includingprojectsatleast50%completeasoftheSubmissionDeadline),theconstructionofatleast(a)twodrinkingwatertreatmentplantsorwastewatertreatment
Miami‐Dade County, Florida Request for Qualifications (Step 1) South Miami Heights Water Treatment Plant Program December 2014 DRAFT – FOR PUBLIC COMMENT ONLY
NOT A PROCUREMENT SOLICITATION 4‐4 ORL.JKC.PW_XM1.6430.101067.04.15.07.40.01CDAM003_DRAFT‐RFQ_SMHWTP_121714
plants,eachwithaminimumconstructionvalueof$25million,and(b)twogroundwaterwellfieldswithtransmissionmains,eachwithaminimumconstructionvalueof$10million,(c)nolessthanonemileinlength,preferablyof24‐inchorlargerdiameterpipeand(d)onemembranewatertreatmentplant.
LeadOperator(s).TheLeadOperatorshouldhavesuccessfullyperformedorbesuccessfullyperforming,withinthepasttenyearsorcurrently,theoperationandmaintenanceofatleast(a)twodrinkingwatertreatmentplantsproducingpotablewaterforpublicuse,eachwithaminimumproductioncapacityof5mgd,and(b)onerawwatersupplysystemutilizinggroundwaterwellsandtransmissionmainswithaminimumrawwaterproductioncapacityof10mgd.ExperiencewithbrackishgroundwaterROtreatmentinFloridaisdesirable.
GeneralManager.ShouldhaveatleasttenyearsrelevantprofessionalexperienceinresponsiblechargeandmanagementofwaterorwastewaterprojectsofsimilarincomplexitytotheProject.
ConstructionManager.Shouldhaveatleastfifteenyearsrelevantprofessionalexperienceinresponsiblechargeandmanagementoftheconstructionoflarge(minimum$20millionconstructionvalue)waterorwastewaterprojects.
DesignManager.Shouldhaveatleastfifteenyearsrelevantprofessionalexperienceinresponsiblechargeandmanagementofthedesignofdrinkingwatertreatmentplantprojects.
Hydrogeologist.Shouldhaveatleastfifteenyearsrelevantprofessionalexperienceinresponsiblechargeandmanagementofthedesignofdeepwellinjectionsystems,wellsinthesurficialBiscayneAquifer(unconfined)andtheUpperFloridanAquifer.
Failuretoidentifyanyofthepersonsstatedabove,ortheabsenceofavalidandexistingcontractualcommitmentbetweentheRespondentandsuchpersontoprovidetheworkrequiredbytheProjectmaybeconsideredtopresentagreaterrisktotheCountyandtheSubmittalscoredaccordingly.ThevaluesforprojectexperiencearebasedonJanuary,2015dollars.
4.3 Comparative Evaluation Criteria TheCSC,withtheassistanceoftheDesignCriteriaProfessionalandotherconsultantsandadvisors,willevaluateeachSubmittalbyapplyingtheComparativeEvaluationCriteriasetforthinTable4‐1furtherdescribedbelow.
Table 4‐1 Step 1 Comparative Evaluation Criteria
Criterion Maximum Points
1A. Project Team Experience, Capabilities and Past Performance [35]
2A. Key Personnel Experience, Capabilities and Past Performance [35]
3A. Safety Record [10]
4A. Organization and Management [10]
5A. Amount of work awarded and paid by the County [5]
6A. Ability of Project Team Members to interface with the County [5]
Criteria1ApointvaluewillbeappliedbasedontheapplicabilityoftheProjectTeamdemonstratedprojectexperience,capabilitiesandpastperformance(withapreferenceonpastperformanceintheUnitedStates)withregardtothepermitting,design,construction,financing,andoperationandmaintenanceoffacilitiessimilartotheProjectintypeandsize.Florida,
Miami‐Dade County, Florida Request for Qualifications (Step 1) South Miami Heights Water Treatment Plant Program December 2014 DRAFT – FOR PUBLIC COMMENT ONLY
NOT A PROCUREMENT SOLICITATION 4‐5 ORL.JKC.PW_XM1.6430.101067.04.15.07.40.01CDAM003_DRAFT‐RFQ_SMHWTP_121714
design‐build,anddesign‐build‐operateexperiencearedesirable.HydrogeologictestingexperienceinFloridabyaProfessionalGeologistorHydrogeologistispreferred.
Criteria2Apointvaluewillbeappliedbasedonthelevelofexperience,capabilitiesandpastperformance(withapreferenceonpastperformanceintheUnitedStates)ofKeyPersonnelspecificallywithrespecttosimilartypeandsizeprojectsandtheirrolesonpreviousprojectsversestheirproposedrolesforthisProject.Florida,design‐buildanddesign‐build‐operateexperiencearedesirable.
Criteria3ApointvaluewillbeappliedbasedonathreeyearaverageforthelastthreepreviousfullyearsoftheExperienceModificationRate(EMR)andthefrequencyandseverityofOSHAsubmittedaccidentdataoverthelastthreefullcalendaryearsforeachProjectTeamMember.
Criteria4ApointvaluewillbeappliedbasedontheeffectivenessdemonstratedfortheCompanyandProjectTeamorganizationandmanagementtoperformtheScopeofServicesinatimelyandcompliantmanner.
Criteria5ApointvaluewillbeappliedbasedontheamountofdollarsawardedandpaidtotheProjectTeamMembers.
Criteria6ApointvaluewillbeappliedbasedontheCompetitiveSelectionCommittee’sevaluationoftheabilityoftheProjectTeamMemberstoefficientlyinterfacewiththeCountyandMDWASDinatimelyandeffectivemannerwithrespecttoitemssuchasregularandemergencycommunications,submittals,meetingattendance,commercialissuesandotherprojectrelatedactivities.
AttheStep1meeting,theCSCwillsubmittheirscoresforStep1totheCounty’sA/ECoordinator.TheCounty’sA/ECoordinatorwillrecordthescoresforeachRespondentandreadtheinformationintotherecord.Thescoreswillbetotaled,andifapplicable,localcertifiedservicedisabledveteranpreference;localpreferenceandtiebreakerswillbeappliedtodeterminethefinalranking.
Thetiebreakersareasfollows:
TotalqualitativepointsforCriteria1A;
TotalqualitativepointsforCriteria2A;
TotalqualitativepointsforCriteria3A;
TotalqualitativepointsforCriteria4A;
TotalqualitativepointsforCriteria5A;and
TotalqualitativepointsforCriteria6A.
TheCSCshallshort‐listnofewerthanthreeresponsiveandresponsibleRespondents.
Step1scoreswillnotbeutilizednortransferredtotheStep2RFPEvaluation/Selectionprocess.
IntheeventthattheCountyreceivesfewerthanthreeSubmittalsorfewerthanthreeRespondentsdeterminedtobeResponsiveandResponsibletoperformtherequiredservices,theCountymayproceedwiththenumberofSubmittalsreceivedwhicharedeterminedtobeResponsiveandResponsible,providedthattheCountyhasconductedananalysisofmarketavailabilityforsubjectservicesanddeterminedinitssolediscretionthatthereisnofurthermarketavailabilityorimmediateinteresttoprovidesubjectservices.Furthermore,intheeventthattheCountyreceivesfewerthanthreeSubmittals,theCountyinitssolediscretionmayextendtheStep1SubmissionDeadline,providedthatSubmittalsreceivedhavenotbeenopened.
OnlytheAdvancingFirmswillbeeligibletoofferaresponsiveandresponsibletechnicalandpriceproposalintheStep2‐EvaluationofTechnicalandPriceProposalprocess.
Miami‐Dade County, Florida Request for Qualifications (Step 1) South Miami Heights Water Treatment Plant Program December 2014 DRAFT – FOR PUBLIC COMMENT ONLY
NOT A PROCUREMENT SOLICITATION 4‐6 ORL.JKC.PW_XM1.6430.101067.04.15.07.40.01CDAM003_DRAFT‐RFQ_SMHWTP_121714
4.4 Short List Notification TheCSCwillnotifyinwritingeachRespondentoftheshortlistuponcompletionofitsevaluationoftheSubmittals.
4.5 Request for Proposals, RFP (Step 2) TheRFPforStep2willbeavailabletotheAdvancingFirmsafternotificationoftheshort‐list.
[EndofSection4]
Miami‐Dade County, Florida Request for Qualifications (Step 1) South Miami Heights Water Treatment Plant Program December 2014 DRAFT – FOR PUBLIC COMMENT ONLY
NOT A PROCUREMENT SOLICITATION .
.
Appendix A
Description of the Project
TheMiami‐DadeWaterandSewerDepartment(MDWASD)isthelargestwaterandsewerutilityinthesoutheasternUnitedStates,servingnearly2.3millionresidents,employingnearly2,500workers,andprovidingdirectservicetomorethan440,000customerswithannualoperatingrevenuesofmorethan$528million.MDWASDprovideswaterandwastewaterservicetotheunincorporatedareasofMiami‐DadeCounty,wholesalewaterserviceto14municipalities,andwholesalewastewaterserviceto11municipalities.TheSouthMiamiHeightsWaterTreatmentPlant(SMHWTP)seekstoimprovereliabilityinwaterserviceandqualitybyallowingforthedecommissioningofsatelliteplantswithover40yearsofservice.ConstructionoftheplantwillbenefittheconsumersinthesouthMiami‐Dadeareaandwillbolsterwatertreatmentproductioncapacity.Theplantislocatedat11800SW208StreetinCountyCommissionDistrict9.
In2006,anInterimConsumptiveUseAuthorizationandAgreementwasreachedbetweenMDWASDandtheSouthFloridaWaterManagementDistrict(SFWMD).AspartofthisAgreement,MDWASDagreedtoincorporatetheuseoftheUpperFloridanAquifer(UFA)rawwaterintoMiami‐DadeCounty’swatersupplyportfolio.OnJuly16,2012,SFWMDissuedamodificationtoMDWASD’sWaterUsePermit(WUP),whichlimitstherawwaterwithdrawalratefromtheBiscayneAquifer(BA)to3milliongallonsperday(mgd),withthebalanceoftherawwaterbeingwithdrawnfromtheUFA.
Water Treatment Plant Process ThedesigncriteriadraftfortheSMHWTP,whichwhenreadytobepublished,canbeviewedatwww.miamidade.gov/waterinclude,butisnotlimitedtoallofthefollowing:
Amembranetreatmentplantandassociatedfacilitiesandbuildingstoproduce20mgd(maxday)finishedwaterusingrawwatermeetingalldrinkingwaterstandardsfromacombinationoftheUFAandBArawwatersupplies.
RawwatersupplywellsintheUpperFloridanAquifer(UFA)andtheBiscayneAquifer(BA)alongwithtransmissionmainsfromsuchwellfieldstothewatertreatmentplantsite.RawwaterwithdrawalfromtheBAislimitedto1,095milliongallonsduringany12‐monthconsecutiveperiod.(Assume3.0milliongallonsperday(mgd)).
RawwaterfromtheBAwouldbetreatedusingnanofiltration(NF)orultralowpressure(ULP)reverseosmosis(RO)membranes.
RawwaterfromtheUFAwouldbetreatedusingROmembranes.
BAandUFAstreamsaretreatedviaseparatemembraneskids.
Finishedwaterstabilizationwouldbeachievedusinghydratedlimeandcarbondioxideaddition.
FinishedwaterfromtheSMHWTPwillmeetallPrimaryandSecondaryDrinkingWaterStandardswithpost‐treatmentforstabilized,non‐corrosivewater.ItisanticipatedthatpHadjustmentandcalciumhardnessadditionusinghydratedlimeinconjunctionwithcarbondioxideadditionforcarbonatealkalinityaugmentationwillbenecessaryforfinishedwaterstabilization.
TherecommendedconfigurationalternativeproposestheuseofoneNF/ULPmembraneskidtotreatthe3mgdofrawwaterallocatedfromtheBAandsevenROmembraneskidstreatingrawwaterallocatedfromtheUFAtoproducethedesired20mgdoffinishedwater(maxday).Thisoptionhasthe
Miami‐DadeSouth Miam
flexibilityfinishedw
Water TrWatertreprocessinwellsandflowdiagr
Sand Stra
Strainers w
UFA and B
mixing of t
additional
microns. T
filters.
Pre‐Trea
Sulfuric ac
accommod
larger volu
UFA syste
for precipit
system wil
BA and UF
e County, Floridami Heights Water
ytobeexpandwater.Aprop
reatment CoeatmentatthengrawwatertheBAwellsramfortheS
ainers, Pretr
will be installed
BA raw water.
these chemical
protection to th
The cartridge fi
tment Chem
cid will be used
dates either 93%
umes associated
ms. Antiscalan
tation of sparin
ll be configured
FA systems.
a r Treatment Plan
N
dedbytheadosedsiteplan
omponents eSMHWTPwcomingintotswillenterthMHWTP.
reatment, a
d to remove san
A total of four
ls in the raw w
he membranes
lter vessels acc
micals
d to adjust the p
% or 98% sulfu
d with 93% aci
nt (scale inhibit
ngly soluble sa
d similarly to t
nt Program
NOT A PROCUR
ditionoftwonisshownbe
willbeachievtheplant.Twhemembrane
nd Cartridge
nd ahead of the
r 316 stainless
ater line prior t
. Five filter car
commodate eit
pH of the raw w
uric acid. Dosin
id. A day tank
tor) will be use
alts and thus as
the sulfuric aci
Dece
REMENT SOLIC
moreROmeelow.
edthroughthoseparateraprocessbuild
e Filters
e cartridge filte
steel static mix
to the cartridge
rtridges are bei
ther string-wou
water prior to m
ng equipment s
will feed separ
ed in the memb
sist in the prev
d dosing system
ember 2014 DRA
CITATION
embraneskid
heoperationawwaterlineding.Figure 3
ers and membr
xers will be ins
e filters. Cartri
ing proposed w
und cartridge fi
membrane trea
sizes and stora
rate sets of me
brane treatmen
vention of mem
m with separat
Request for QuAFT – FOR PUBL
stoproduce
ofspecializedsoriginating
3illustratesth
rane treatment
stalled to provi
idge filters will
with a nominal
ilters or rigid-s
atment. The ac
age capacities a
etering pumps f
nt process to red
mbrane fouling
te sets of meter
ualifications (SteLIC COMMENT O
25mgdof
dequipmentfromtheUFAheproposed
units for both
ide thorough
l provide
pore size of 5
structure cartrid
id system desig
are based on th
for the BA and
duce the poten
. The antiscala
ring pumps for
ep 1) ONLY
A
dge
gn
he
d
ntial
ant
r the
Miami‐Dade County, Florida Request for Qualifications (Step 1) South Miami Heights Water Treatment Plant Program December 2014 DRAFT – FOR PUBLIC COMMENT ONLY
NOT A PROCUREMENT SOLICITATION .
.
Membrane Feed Pumps and UFA Interstage Boost Pumps ThemembranefeedpumpsfortheBAandUFAsystemswillbelocateddownstreamoftheirrespectivecartridgefiltrationsystems.Onededicatedverticalturbinecannedmembranefeedpumpcontrolledbyavariablefrequencydrive(VFD)willbelocatedimmediatelyadjacenttoeachmembraneunit.Atotalof8membranefeedpumpsareproposed.Toreducetheoverallimpactonenergyconsumption,seventurbochargertypeenergyrecoverydevices(ERDs)havebeenincludedinthedesignfortheUFAunits.
Membrane Units: NF/ULP and RO Theproposedmembranearrayconfigurationconsistsof48vesselsinthefirststageand24vesselsinthesecondstage,resultinginanaveragepermeatedesignfluxof12.4gfd.Themembranesystemdesignisbasedonpermeatewaterrecoveryratesof85%fortheBAunitsand75%fortheUFAunits.
Degasification and Odor Control Facilities Hydrogensulfideconcentrationsareexpectedinthe3.5to5.0mg/LrangefortheUFAwaterrequiringtheprovisionofadegasifierandodorcontrolscrubbersystem.Atotalofthreedegasifiersareproposedforplantdesignflow.Anodorcontrolsystemwillbeprovidedtoremovehydrogensulfidefromtheoff‐gasofthedegasificationsystemtoavoidodorcomplaintsfromnearbyresidentsandtominimizecorrosionofmetallicequipmentorstructures.Twoscrubbersystemsareproposedforthe20‐mgdplantflow,witheachscrubbersystemhavingtwostages.
Contact Basin and Transfer Pumps Thecontactbasinisdesignedtoprovideachlorinecontacttime(CT)sufficientfor99.99%(4‐log)inactivationofvirusesatatemperatureof22oCwithaminimumfreechlorineresidualof3.0mg/l.TheCTvaluefortargetedvirusinactivationandtemperaturebetweenapHof6.5and7is2.6mg/L‐min.Thetransferpumpswillconsistoffourunits(threeactive/onestandby),allVFD,verticalturbinetypepumps.
Post‐Treatment Chemical Feed Systems Post‐treatmentchemicalswillbeusedforthedisinfectionofthetreatedprocesswater(bulksodiumhypochloriteforprimarydisinfectionandammoniaadditionformonochloramineformationforsecondarydisinfection)aswellastostabilizethefinishedwaterbyaddingcalciumhardnessandalkalinity,whichhelpstoprotectthedistributionsystem(hydratedlime,carbondioxide,andcorrosioninhibitor).Fluoridewillbealsoaddedtothefinishedwaterfordentalhygiene.
Membrane Concentrate Disposal Concentratewillbedisposedofusinginjectionwells(onedutyandoneredundantwell)locatedonsite.Theproposedinjectionwellswillhavecementfilledannulusforan18.18‐inchoutsidediameterFiberglassReinforcedPlastic(FRP)injectiontubingand30‐inchoutsidediametersteelinjectioncasing,andadesigncapacityofapproximately9.44mgd.Eachinjectionwellwillbecasedtoatleast2,500feetbelowlandsurface(ftbls)andatotaldepthofapproximately3,500ftblspenetratingthroughtheFloridaAquiferBoulderZone.Itisanticipatedthattherewillbeatotaldynamicheadof120ft(52psi).
TheanticipatedtermsandconditionsoftheServiceContractaresummarizedinaPreliminaryTermSheetforServiceContractsetforthinAppendixD.ThePreliminaryTermSheetshouldnotbeconsideredasallinclusiveordefinitiveastotheformorsubstanceoftheactualServiceContractprovisions.TheCountyreservestherighttoamend,modifyordeleteanyofthesetermsandconditionssetforthinthePreliminaryTermSheetforServiceContract.
Miami‐Dade County, Florida Request for Qualifications (Step 1) South Miami Heights Water Treatment Plant Program December 2014 DRAFT – FOR PUBLIC COMMENT ONLY
NOT A PROCUREMENT SOLICITATION .
.
Appendix B
Affidavit Forms
Miami‐Dade County, Florida Request for Qualifications (Step 1) South Miami Heights Water Treatment Plant Program December 2014 DRAFT – FOR PUBLIC COMMENT ONLY
NOT A PROCUREMENT SOLICITATION .
.
Appendix C
Certificate of Authorization
Attachment 1 to Transmittal Letter
CERTIFICATE OF AUTHORIZATION*
I,____________________,aresidentof_____________________intheStateof______________________,DO
HEREBYCERTIFYthatIamtheClerk/Secretaryof_________________________________,acorporation
dulyorganizedandexistingunderandbyvirtueofthelawsof_______________________;thatIhave
custodyoftherecordsofthecorporation;andthatasofthedateofthiscertification,
___________________holdsthetitleof___________________ofthecorporation,andisauthorizedto
executeanddeliverinthenameandonbehalfofthecorporationtheRequestforQualifications
(“RFQ”)submittedbythecorporationinresponsetotheRequestforQualificationsforthe
Design‐Build‐Finance‐Operate‐MaintainServiceContractfortheSouthMiamiHeightsWater
TreatmentPlantProgram,issuedbytheMiamiDadeCounty,Floridaon____________________as
amended;andalldocuments,letters,certificatesandotherinstrumentswhichhavebeen
executedbysuchofficeronbehalfofthecorporationinconnectiontherewith.
INWITNESSWHEREOF,Ihavehereuntosetmyhandandaffixedthecorporatesealofthe
corporationthis____________________dayof__________,20_______.
(AffixSealHere)
____________________________________
Clerk/Secretary
*Note:SeparatecertificationsshallbesubmittedifmorethanonecorporateofficerhasexecuteddocumentsaspartoftheRFQ.RespondentsshallmakeappropriateconformingmodificationstothisCertificateintheeventthatthesignatory’saddressisoutsideoftheUnitedStates.
Miami‐Dade County, Florida Request for Qualifications (Step 1) South Miami Heights Water Treatment Plant Program December 2014 DRAFT – FOR PUBLIC COMMENT ONLY
NOT A PROCUREMENT SOLICITATION .
.
Appendix D
Preliminary Term Sheet for Service Contract
Project: AnewwatersupplysystembeingimplementedbytheMiami‐DadeCountyWaterandSewerDepartment(WASD)toimprovethereliabilityandqualityofpotablewaterinSouthMiami‐DadeCounty.ThesystemgenerallywillconsistofrawwatersupplywellsintheUpperFloridanAquifer(UFA)andtheBiscayneAquifer(BA),rawwatertransmissionmains,atwenty(20)milliongallonperday(maximumday)finishedwatercapacitymembranewatertreatmentplant(withassociatedfacilitiesandbuildings),afive(5)milliongallonreservoir,anddeepwellinjectionfacilitiesfordisposalofconcentrate(Project).
AUFAtestwellprogramtoobtainrawwaterproductionflow
rateandwaterqualitydataandwellsitingdevelopedbyWASDiscurrentlyinprocurementandscheduledforinitiationin[_____].TestwelldataandhydraulicmodelingthatcanbeutilizedfordesignoftheUFAwatersupplywellsandtransmissionmainsshouldbeavailableonorabout[_____].
Parties: TheCountyofMiami‐Dade,Florida(County)andaspecial
purposevehicleorganizedtoperformthedesign,permitting,construction,financingandlong‐termoperationandmaintenanceoftheProject(Company).
CountyRepresentatives: Engineeringfirmswillprovideconsultingservicestoassist
theCountywithprocurementandimplementationoftheProject,includingpreparationofadesigncriteriapackage,permitting,life‐cyclecostdevelopment,scheduling,designreviewandconstructioninspection.
Term: Initialtermoftwenty(20)yearsfromthedatewhenthe
Projectisplacedintoservice(ServiceDate),subjecttoCountyrenewaloptionsforanaggregateofuptotwenty(20)additionalyears.
PerformanceSecurity: Asofthedateofexecution(ContractDate),theCompanywill
provide:(a)third‐partyguaranteeoftheCompany’scontractualobligationstotheCounty(GuarantyAgreement);(b)performanceandpaymentbondsfortheDesign‐BuildWorkinamountsequaltoone‐hundredpercent(100%)oftheDesign‐BuildPrice;and(c)letterofcreditinanamountequaltofivepercent(5%)oftheDesign‐BuildPrice.
Miami‐Dade County, Florida Request for Qualifications (Step 1) South Miami Heights Water Treatment Plant Program December 2014 DRAFT – FOR PUBLIC COMMENT ONLY
NOT A PROCUREMENT SOLICITATION .
.
AsoftheServiceDate,theCompanyshallprovideanannually‐renewableperformancebondforoperation,maintenanceandotherCompanyobligationsotherthantheDesign‐BuildWork(Services)inanamountequaltoone‐hundredandfiftypercent(150%)oftheServiceFee.
PropertyRights: TheCountyownsthelandwherethewatertreatmentplant
andconcentratedisposalwellwillbelocated(PlantSite)andsuchlandwillbemadeavailabletoCompany.TheCountywillobtainagreementsforthepubliclandswheretheUFAandBArawwatersupplywells,ancillaryfacilities,andtherawwatertransmissionmainswillbelocatedandsuchlandswillbemadeavailabletoCompany.
Ownership: TheCompanywillnotowntheProject,norhaveany
ownershiprightstotheraworfinishedwater.TheProjectwillbeownedbytheCounty.
CompanyObligations: TheCompanywillgenerallybeobligatedtoarrangefinancing
andachievefinancialclose,preparefinaldesign,obtainpermitsandgovernmentapprovals,performconstruction,conductperformancetesting,andperformoperation,maintenance,repair,renewalandreplacementservicesfortheProject.
CBE/CSBEGoals: GoalsforCommunityBusinessEnterprise(CBE)and
CommunitySmallBusinessEnterprise(CSBE)participationwillbeprovided.
FinancialClose: TheCompanymustachievefinancialcloseforthefullamount
ofprivatefinancingnecessaryfortheProjectnolaterthanninety(90)calendardaysfromtheContractDate.FailuretoachievefinancialclosewithinsuchtimewillentitletheCountytoterminatetheServiceContractfordefault.ItisanticipatedthattheFixedAvailabilityChargecomponentoftheServiceFeewillbeestablished,basedonapre‐agreedformulatotakeintoaccountmarketinterestratesasofthedateoffinancialclose.
Design‐BuildWork: TheCompanyshallperformalltheworkandrelatedactivities
necessarytocompletedesignandconstructionandplacetheProjectintoservice,including(butnotlimitedto)preparingthefinaldesign(subjecttoreviewandcommentbytheCounty);applyingfor,obtainingandmaintainingallnecessarypermitsandapprovals;procureallsubcontractors,materialsandequipment;complywithreportingrequirements;undertakedesignandconstructionqualitymanagement;
Miami‐Dade County, Florida Request for Qualifications (Step 1) South Miami Heights Water Treatment Plant Program December 2014 DRAFT – FOR PUBLIC COMMENT ONLY
NOT A PROCUREMENT SOLICITATION .
.
employsafeandeffectiveconstructionmeansandmethods;promptlycompleteforallnecessarycorrectionofconstructionwork;achievesubstantialcompletionofconstruction;conductstart‐upandcommissioning;successfullycompleteperformancetesting;andarrangeforanynecessarytemporaryconstructioneasementsandalltemporaryfacilitiesthatmaybenecessary(Design‐BuildWork).
DesignandPermitting: TheCompanyshallhavesoleresponsibilityandliabilityfor
designandpermittingoftheProject,providedthattheCountyshallhavetherighttoreviewandcommentonalldesigndocumentationpreparedbytheCompanyforthepurposeofcomparingtheconsistencyofdesigndocumentationwiththedesignrequirementssetforthintheServiceContract(DesignRequirements).TheCountymay,initssolediscretion,acceptorrejectanychangetotheDesignRequirementsproposedbytheCompany.TheCompanywillimplementchangestotheDesignRequirementsthatmayberequestedbytheCountytotheextentthatsuchchangesdonotimpairtheCompany’sabilitytoperformitsobligationsorifadditionalcostsarereimbursedbytheCounty.ImpactsonCompanyobligationscausedbychangestotheDesignRequirementsnecessitatedbyUncontrollableCircumstancesmayentitleCompanytocost,timeandperformancerelief.
Design‐BuildCosts: TheCompanyshallpayallcostsincurredfortheDesign‐Build
WorkwithoutreimbursementfromtheCounty(otherthanthroughpaymentoftheServiceFee).TheamountofsuchcostsfortheDesign‐BuildWorkreflectedintheServiceFeewillbebasedonafixedpriceasoftheContractDatethatmaybeadjustedtoaccountfor(a)UncontrollableCircumstances,(b)changesintheunitpricesforcertaincommodities;and(c)changesindesignorconstructionrequestedbytheCounty.
PerformanceTesting: AftersubstantialcompletionoftheProject,theCompanywill
berequiredtoconductandpassperformancetestingasaconditionofachievingtheServiceDate.Suchperformancetestingmustdemonstrate(amongotherthings)theProject’scapabilitytoproducepotablewateraccordingtoagreed‐tooperatingconditionsandcriteriaincludingrawwaterqualityandquantities,hydraulictransients,maximumelectricalpowerutilization,andfinishedwaterqualityandquantities.
Schedule: TheCompanymustachievetheServiceDatenotlaterthan
[_____________________]calendardaysaftertheContractDate(ScheduledServiceDate),subjecttoadjustmentofthe
Miami‐Dade County, Florida Request for Qualifications (Step 1) South Miami Heights Water Treatment Plant Program December 2014 DRAFT – FOR PUBLIC COMMENT ONLY
NOT A PROCUREMENT SOLICITATION .
.
ScheduledServiceDateduetoUncontrollableCircumstancesorchangesrequestedbytheCounty.
DelayLiquidatedDamages: IftheServiceDateoccursaftertheScheduledServiceDate,
theCompanywillpay[_______________]dollarsperdaytotheCountyasliquidateddamagesforsuchdelay.
EarlyCompletionBonus: IftheServiceDateoccursbeforetheScheduledServiceDate,
theCountywillpay[_______________]dollarsperdaytotheCompanyasanearlycompletionbonusuptothemaximumamountof[_______________]dollars.
OperationandMaintenance: StartingontheServiceDate,theCompanyshalloperateand
maintaintheProjectona24‐hourperday,7‐dayperweekbasis.TheCompanyshallcontinuouslyproducepotablewaterinsuchquantitiesasrequiredbytheOperatingProtocolinconformancewiththePerformanceStandardsandwiththemaintenance,repair,renewal,replacementandotherrequirementsoftheServiceContract.TheCompanymayalsoberesponsibleforoperationandmaintenanceofexistingfacilitieslocatedatthePlantSite,includingHighServicePumpStationandReservoir,butsubjecttoWASDdailyinstructionsconcerningratesofpumpingandstorage.
PerformanceStandards: SpecificstandardsapplicabletoCompanyprovisionofthe
Serviceswillbeprovided,including(butnotlimitedto)standardsforrawwaterdeliverytothePlantSite(subjecttotheCounty’swaterusepermitissuedbytheSouthFloridaWaterManagementDistrict),finishedwaterquality(inclusiveofallcurrentfederalandstateregulatorystandards),finishedwaterproductionflowrates,concentratedisposal,andhydraulictransients.Company’sobligationtocomplywithfinishedwaterqualitystandardsandproductionflowrateswillbesubjecttoreliefunderagreed‐toconditions(butnotincludingCompanyfault)concerningthequalityandflowratesofrawwaterproducedbytheUFAandBAwellfields.
ElectricalPower: TheCountywillpaytheelectricutilitydirectlyforelectrical
powerconsumedintheoperationoftheProject,subjecttomaximumamountsofelectricalusageanddemandguaranteedbytheCompany.NoCompanymarkupwillbeallowedforthecostsofelectricalpowerfortheProject.
Repair,RenewalandReplacement: TheCompanywillberesponsibleforallrepairs,renewalsand
replacementsrequiredduringthetermoftheServiceContract.
Miami‐Dade County, Florida Request for Qualifications (Step 1) South Miami Heights Water Treatment Plant Program December 2014 DRAFT – FOR PUBLIC COMMENT ONLY
NOT A PROCUREMENT SOLICITATION .
.
CapitalImprovements: TheCompanywillberesponsibleforcapitalimprovementsthatmayberequiredduringtheterm,subjecttoanadjustmentoftheServiceFeetoreimbursethecostsincurred.TheCompanywillarrangeprivatefinancingforcapitalimprovements,unlessotherwisedirectedbytheCounty.
ServiceFee: StartingontheServiceDateandsubjecttoadjustmentfor
non‐performancebytheCompany,theCountywillpayamonthlyfeefortheCompany’sprovisionoftheServices(ServiceFee).TheServiceFeewillincludethefollowingcomponents:(a) AvailabilityChargeinafixedamounttopaytheCompany
foritsfinancingoftheProject(including,asapplicable,debtserviceandreturnonequity);
(b) FixedO&MChargeinanamounttopaytheCompanyforitsfixedcostsandrelatedoverheadandprofitforoperationandmaintenanceoftheProject;
(c) FixedR&RChargeinanamounttopaytheCompanyforitscostsandrelatedoverheadandprofitforrepair,renewalandreplacementoftheProject(excludingmembranereplacement);
(d) FixedMembraneReplacementChargeinanamounttopaytheCompanyforitscostsandrelatedoverheadandprofitforperiodicreplacementofmembranes;
(e) ProductionChargeinanamounttopaytheCompanyforitsvariablecostsandrelatedoverheadandprofitcalculatedbymultiplyingthemilliongallons(mg)offinishedwaterproducedduringthemonthtimes[$fromproposal]amountpermg.(TheProductionChargemaybefurtherbrokendownintoseparatechargesforutilizationofBAandUFAsupplies.TheProductionChargemaytakeintoaccountvariationsinoneormorerawwaterqualityparameters,suchassalinity.)
ServiceFeeAdjustments: TheServiceFeewillbeincreasedordecreasedduringthe
termtoaccountforthefollowing:(a) Inflationbasedonchangesinanagreed‐toeconomic
indexorindices,butexcludingtheFixedAvailabilityCharge;
(b) UncontrollableCircumstances;(c) CapitalimprovementsrequestedbytheCounty;(d) ElectricalpowercreditsbasedonCompanyelectrical
powerconsumptionaboveguaranteedmaximumamounts;
Miami‐Dade County, Florida Request for Qualifications (Step 1) South Miami Heights Water Treatment Plant Program December 2014 DRAFT – FOR PUBLIC COMMENT ONLY
NOT A PROCUREMENT SOLICITATION .
.
(e) Electricalpowerefficiencypaymentsbasedon[fifteenpercent(15%)]ofCompanyelectricalpowerconsumptionbelowguaranteedmaximumamounts;and
(f) NonperformancecreditsduetoCompanyfailuretoachievePerformanceStandardsfortheServices,includingrequirementsforProjectavailabilityandforoperation,maintenance,renewalandreplacements.
UncontrollableCircumstances: EventsandconditionsthatmayentitleCompanytocost,time
and/orperformancereliefwillincludedifferingsiteconditions,changeinlaw,variationsinthequalityofrawwaterextractedfromUFAandBAwellsoutsideagreed‐toranges,variationsintheflowratesofrawwaterextractedfromUFAandBAwellsbelowagreed‐toamounts,uninsurableforcemajeure,abnormalweather,labordisputesnotlimitedtoProjectemployees,andcertainothereventsandconditions.ThescopeofsuchreliefavailabletotheCompanymaybelimitedtocost‐onlyortime‐onlyforcertaineventsorconditions.
NoreliefwillprovidedintheeventofCompanyor
subcontractorfaultinthedesign,construction,operationormaintenanceoftheProjectorfailuretocomplywithobligationssetforthintheServiceContract.
ApplicableLaw: Companyatalltimesshallcomplywithalllaws(including
federal,state,Countyandmunicipallaws,ordinances,ordinances,procedures,etc.)applicabletotheProjectandtheServices.Additionally,Section2‐1076oftheCodeofMiami‐DadeCounty,whichpertainstotheOfficeoftheInspectorGeneral,shallapplytothisServiceContract.
Indemnification: CompanyshallindemnifyCountyandrelatedentitiesand
individualsfromlossesandclaimsarisingfromnegligence,omissions,intentionalmisconduct,andfailuretoperformorcomplywithcontractualobligationsandasalsoprovidedforspecificcircumstances.Company’sindemnificationshallnotbelimitedbyavailabilityorunavailabilityofinsurancecoverage.
LimitationofLiability: Company’saggregateliabilityundertheServiceContractasa
consequenceofaclaimorsuitinitiatedbytheCountyshallbelimitedtothe[_______________]fromtheContractDatethroughthedatetwoyearsaftertheServiceDate.StartingtwoyearsaftertheServiceDate,suchaggregateliabilityshallbelimitedtoanamountequalto[_______________].Suchlimitationsof
Miami‐Dade County, Florida Request for Qualifications (Step 1) South Miami Heights Water Treatment Plant Program December 2014 DRAFT – FOR PUBLIC COMMENT ONLY
NOT A PROCUREMENT SOLICITATION .
.
liabilitydonotapplytoCompanyindemnificationofclaimsbythirdparties.
ConsequentialDamages: Neitherpartywillbeliabletotheotherforspecial,incidental,
consequential,punitiveorsimilardamagesarisingoutofclaimsordisputesbetweentheparties.SuchwaiverdoesnotapplytoCompanyindemnificationofclaimsbythirdparties.
RequiredInsurance: Minimumlimitsofcoveragewillbeprovidedforinsurance
policiesthatmustbecarriedbytheCompany(includingcommercialgeneralliability,workers’compensationandemployer’sliability,commercialautomobileliability,umbrellaliability,professionalliability,contractor’spollutionliability,builder’sriskduringconstruction,andproperty,boilerandmachineryandbusinessinterruptionduringoperation).Companywillberesponsiblefordeductibles.
County“Step‐In”Rights: IntheeventofCompany’snon‐performanceofamaterial
obligationornon‐conformancewithamaterialrequirementsetforthintheagreement,theCountymayelect(thoughtheuseofCountyforcesorthird‐partycontractors)toundertakeperformanceofsuchobligationorrequirementonatemporaryorpermanentbasis.
ConvenienceTermination: StartingontheServiceDateanduponsixty(60)days’written
noticeandwithoutcause,theCountyforitsconveniencemayterminatetheServiceContractandwillpayCompany(a)allServiceFeeamountsdueasofsuchdateoftermination(b)aterminationfeeassetforthintheServiceContractthatwillautomaticallydecreaseeachmonthaftertheServiceDate,and(c)acapitalpaymentamountcalculatedaccordingtoanagreed‐toformulatoreimburseCompanyfortheoutstandingbalanceoftheprivatefinancingdueasofsuchdateofterminationandrelatedcostsandfees,ifany,necessarilyincurredinconnectionwiththeredemptionofsuchfinancing.
StartingontheContractDatethroughtheServiceDateanduponsixty(60)days’writtennoticeandwithoutcause,theCountyforitsconveniencemayterminatetheServiceContractandwillpayCompany(a)allamountsdueasofsuchdateoftermination,and(b)acapitalpaymentamountcalculatedaccordingtoanagreed‐toformulatoreimburseCompanyfortheoutstandingbalanceoftheprivatefinancingdueasofsuchdateofterminationandrelatedcostsandfees,ifany,necessarilyincurredinconnectionwiththeredemptionofsuchfinancing.
Miami‐Dade County, Florida Request for Qualifications (Step 1) South Miami Heights Water Treatment Plant Program December 2014 DRAFT – FOR PUBLIC COMMENT ONLY
NOT A PROCUREMENT SOLICITATION .
.
DefaultTermination: Uponthirty(30)days’writtennoticeandsubjecttocure,eitherpartymayterminatetheServiceContractuponamaterialbreachbytheotherpartyandupontheoccurrenceofotherdefinedeventsofdefault.Theterminatedpartywillbeliablefordirectdamagesincurredbytheotherpartyintheeventofsuchbreachandtermination.Certaineventsofdefaultwillalsobeprovidedforterminationwithoutcure.
LenderRights: LendersincludedaspartofprivatefinancingfortheProject
willhavecustomaryrightstostepinandcureCompanydefaultpriortoterminationbytheCounty.
TurnoverCondition: PriortotransferofProjectoperationsresponsibilitytothe
County,CompanywillberequiredtocomplywithrequirementspertainingtotheconditionofProjectassets.AprocesswillbeincludedforanindependentengineeringassessmentandforCountyinspectionandassessment.
Miscellaneous: Provisionswillbeincludedregardingprogressschedules,raw
andfinishedwaterqualitytestingandreporting,keypersonnel,periodicinspectionandaudit,booksandrecords,refinancingofprivatefinancing,restorationofdamageordestruction,disputeresolution,representationsandwarranties,laborpractices,useofsubcontractors,operatingprotocols,assignmentandchangesincontrol,contractadministration,andthelike.
Miami‐Dade County, Florida Request for Qualifications (Step 1) South Miami Heights Water Treatment Plant Program December 2014 DRAFT – FOR PUBLIC COMMENT ONLY
NOT A PROCUREMENT SOLICITATION .
.
Appendix E
Summary of Applicable Legislation
TheProjectTeamisrequiredtoabidebyallapplicablefederal,stateandlocallawsandordinances,asamended.Amongtheapplicablelocallawsandordinancesare:Ordinances
_77‐13‐FinancialDisclosure
_90‐133‐DisclosureofOwnership,CollectiveBargainingAgreement,andEmployeeWages,HealthCareBenefits,Race,NationalOriginandGender
_97‐35‐PolicyofFairSubcontractingPractices
_97‐67‐AmendingChapter11AProhibitingDiscriminationinContracting,Procurement,BondingandFinancialServices
_97‐215‐OfficeoftheInspectorGeneral
_99‐152‐FalseClaimOrdinance
_01‐105‐AmendingSection2‐10.4oftheMiami‐DadeCountyCodefortheacquisitionofprofessionalarchitectural,engineering,landscapearchitectureorlandsurveyingandmappingservices
_03‐107‐OrdinanceAmendingSection2‐11.1(s)oftheConflictofInterestandCodeofEthics
_07‐65‐SustainableBuildingsProgram
_08‐92‐EconomicStimulusOrdinance
_08‐113‐OrdinanceAmendingSections2‐8.1.1and10‐33.1oftheMiami‐DadeCountyCoderelatingtobidsfromrelatedpartiestoincludeaprohibitiononcollusivebidding
_09‐41‐OrdinanceamendingSection10‐33.02oftheCodepertainingtotheCommunitySmallBusinessEnterprise(CSBE)Program
_09‐68‐LocalCertifiedServiceDisabledVeteransPreference
_11‐22‐CommunitySmallBusinessEnterprise
_11‐24‐CommunityBusinessEnterprise
_11‐90‐OrdinanceRelatingtotheCollectionofDataforaDisparityStudy
Miami‐Dade County, Florida Request for Qualifications (Step 1) South Miami Heights Water Treatment Plant Program December 2014 DRAFT – FOR PUBLIC COMMENT ONLY
NOT A PROCUREMENT SOLICITATION .
.
Resolutions
_R‐1049‐93‐AffirmativeActionPlanFurtheranceandCompliance
_R‐385‐95‐PolicyprohibitingcontractswithfirmsviolatingtheAmericanwithDisabilitiesAct(ADA)andotherlawsprohibitingdiscriminationonthebasisofdisabilityADArequirements,areaconditionofaward,asamendedbyResolutionR‐182‐00
R‐531‐00‐ProhibitionofcontractingwithindividualsandentitieswhileinarrearswiththeCounty
_R‐894‐05‐IndependentPrivateSectorInspectorGeneral(IPSIG)Services
_R‐744‐00‐Requiringthecontinuedengagementofcriticalpersonnelincontractsforprofessionalservicesforthedurationoftheproject
_R‐183‐00‐FamilyLeaveRequirements
_R‐185‐00‐DomesticViolenceLeave
_R‐1386‐09‐CommunitySmallBusinessDevelopmentProgram;directingCountyMayortoincludeadditionalsubcontractorprovisionsinallfuturecontracts,whereapplicableunlesswaivedbytheBoardofCountyCommissioners
_R‐138‐10‐ResolutionrequiringthatconstructioncontractsincludelanguagemandatingthatthescopeofworkofCSBEsbeseparatelystatedandaccountedforinscheduleofvalues
AdministrativeOrders
_3‐20‐IndependentPrivateSectorInspectorGeneral(IPSIG)Services
_3‐26‐OrdinanceamendingSection2‐10.4requiringcertainagreementsforProfessionalArchitecturalandEngineeringServicestoincludeValueAnalysisasapartofthebasescopeofservices.
_3‐37‐CommunityWorkforceProgram(CWP)
_3‐39‐StandardProcessforConstructionofCapitalImprovements,AcquisitionofProfessionalServices,ConstructionContracting,ChangeOrdersandReporting
_10‐10‐DutiesandResponsibilitiesofCountyDepartmentsforCompliancewiththeAmericanswithDisabilitiesAct(ADA)
ImplementingOrders
_3‐21‐BidProtestProcedure
Miami‐Dade County, Florida Request for Qualifications (Step 1) South Miami Heights Water Treatment Plant Program December 2014 DRAFT – FOR PUBLIC COMMENT ONLY
NOT A PROCUREMENT SOLICITATION .
.
_3‐22‐CommunitySmallBusinessEnterprise
_3‐32‐CommunityBusinessEnterprise
_3‐34‐FormationandPerformanceofSelectionCommittees
Miami‐DadeCountyCode
_Section2‐1076‐OfficeoftheInspectorGeneral
_Section2‐8.1‐ContractsandPurchases
_Section2‐8.4‐ProtestProcedures
_Section2‐8.5‐LocalPreference
Section2‐8.5.1‐LocalCertifiedService‐DisabledVeteranBusinessEnterprise
_Section2‐8.8‐FairSubcontractingPractices
_Section2‐10.4‐AcquisitionofProfessionalArchitectural,Engineering,LandscapeArchitecturalorLandSurveyingandMappingServices
_Section2.11.1‐ConflictofInterestandCodeofEthics
_Section10‐34‐ListingofSubcontractorsRequired
CopiesoftheaforementionedOrdinancesandResolutionsmaybeobtainedattheClerkoftheBoard'sOffice.
Miami‐Dade County, Florida Request for Qualifications (Step 1) South Miami Heights Water Treatment Plant Program December 2014 DRAFT – FOR PUBLIC COMMENT ONLY
NOT A PROCUREMENT SOLICITATION .
.
Appendix F
County Pre‐Qualification of A/E Firms
A/EFirms.Allproperlylicensedfirmsand/orindividualsincludedontheProjectTeamforprovidingengineering,architectural,landscapearchitectural,landsurveyingandmappingservices,regardlessoftheirindividualassignmentsinconnectionwiththisProject,andrespondingtothissolicitationmusthavefiledwithISDapre‐qualificationpackageandhaveapprovedpre‐qualificationstatusfromISD,inaccordancewithChapter2,Section2‐10.4andAdministrativeOrder3‐39ofMiami‐DadeCounty,priortotheSubmittalDeadline.Firmsand/orindividualsarerequiredtomaintainactivepre‐qualificationstatusatthetimeoftheStep1SubmissionDeadline,solicitationevaluationandselectionprocess,and,ifselectedattimeofaward,andthroughoutthedurationoftheServiceContract.
InterestedA/Efirmsand/orindividualsmustsecuretherequiredpre‐qualificationcertificationwhichincludes,butmaynotbelimitedtotechnicalcertifications,affirmativeactionplanverification,vendorregistrationandexecutionofthebasicMiami‐DadeCountyaffidavits,asapplicable,priortotheStep1SubmissionDeadline.TheA/Epre‐qualificationrequirementisalsoapplicabletoanyfirmthatmaybelaterselectedtoperformworkasasubstituteforapreviouslyselectedfirm,ortoperformadditionalworkonthisProject.
JointVenturefirmsmaybepre‐qualifiedinthesamemannerasotherfirms.Inthealternative,ifaJointVenturefirmoptstosatisfythetechnicalcertificationrequirementsofthissolicitationthroughtheA/EfirmcomprisingtheJointVenture,theJointVentureshallataminimumcomplywiththefollowingadditionalrequirements:
1. TheJointVentureshallinitsownnameobtainanapprovedaffirmativeactionplan.
2. TheJointVentureshallinitsownnamesubmitacompletedvendorregistrationpackage,includingapplicableaffidavits.
3. TheA/Eentityshallinitsownnamebepre‐qualifiedpriortotheStep1SubmissionDeadline.
TheaboverequirementsmustbecompletedbytheJointVentureinitsownnamenolaterthantheStep1SubmissionDeadline.FailureofanyfirmsdenotedontheDesign‐Builder’sA/Edesignteamtobepre‐qualifiedattheStep1SubmissionDeadlinemayrendertheSubmittalnon‐responsive.
A/ETechnicalCertificationRequirementsfortheA/EdesignmembersoftheProjectTeam:
6.01‐WaterandSanitarySewerSystems–WaterDistributionandSanitarySewageCollectionandTransmissionSystems(LeadDesigner)
6.02‐WaterandSanitarySewerSystems‐MajorWaterandSanitarySewagePumpingFacilities(LeadDesigner)
6.03–WaterandSanitarySewerSystems–WaterandSanitarySewageTreatmentPlants(LeadDesigner)
9.01‐Soils,FoundationsandMaterialsTesting–Drilling,SubsurfaceInvestigationsandSeismographicServices
Miami‐Dade County, Florida Request for Qualifications (Step 1) South Miami Heights Water Treatment Plant Program December 2014 DRAFT – FOR PUBLIC COMMENT ONLY
NOT A PROCUREMENT SOLICITATION .
.
9.02‐Soils,FoundationsandMaterialsTesting–GeotechnicalandMaterialsEngineeringServices
9.03‐Soils,FoundationsandMaterialsTesting–ConcreteandAsphaltTestingServices
9.04‐Soils,FoundationsandMaterialsTesting–Non‐DestructiveTestingandInspections
10.01‐EnvironmentalEngineering–StormwaterDrainageDesignEngineeringServices
10.02‐EnvironmentalEngineering–GeologyServices(LeadDesigner)
10.05–EnvironmentalEngineering–ContaminationAssessmentandMonitoring
10.09‐EnvironmentalEngineering–Wellfield,Groundwater,andSurfaceWaterProtectionandManagement(LeadDesigner)
11.00‐GeneralStructuralEngineering
12.00‐GeneralMechanicalEngineering
13.00‐GeneralElectricalEngineering
14.00‐Architecture
15.01‐SurveyingandMapping–LandSurveying
15.03‐UndergroundUtilityLocation
16.00‐GeneralCivilEngineering(LeadDesigner)
17.00‐EngineeringConstructionManagement(LeadDesigner)
18.00‐ArchitecturalConstructionManagement(LeadDesigner)
20.00‐LandscapeArchitecture
Tosatisfythetechnicalcertificationrequirementsfortherequestedservices,validtechnicalcertificationinalloftheabove‐specifiedarea(s)ofworkmustbeheldbyafirmrespondingasasoleRespondent,orateamoffirms.Furthermore,ifanindividualisprovidingservicesthatrequiretechnicalcertificationbyMiami‐DadeCounty,theindividualisrequiredtohavetherelevantcertification(s).Individualswhoarenottechnicallycertifiedwillnotbe“allowed”toperformworkforthosescopesofworkrequiringtechnicalcertification.Additionally,firmsthatlistotherareasofworkassupplementstotherequiredtechnicalcertificationsmustalsobecertifiedforthosesupplementalareas.
ForquestionsregardingMiami‐DadeCounty'sA/ETechnicalCertification,thatarenotrelatedtothisprojectandCertificationCommitteemeetingdates,pleasecontactNubiaJarquin,InternalServicesDepartment(ISD),at(305)375‐5637.TechnicalCertificationapplicationsubmissiondeadlinedatesandTechnicalCertificationmeetingdatesmaybeaccessedviathefollowingwebsite:http://www.miamidade.gov/internalservices/technical‐certification.asp.
IntheeventthattheRespondentisaJointVenture,theA/EtechnicalcertificationrequirementsofthisRFQmaybesatisfiedbytheJointVentureorbytheA/EindividualfirmcomprisingtheJointVenture.FailuretosatisfytherequirementsshallresultinthedisqualificationoftheJointVenture.
[ENDRFQ]