Upload
keon
View
34
Download
0
Embed Size (px)
DESCRIPTION
Rapid Frac Material Handling. Beth Nowacki SCMP Intern Final Presentation B.U.M: Thomas Sweeney PGL: Kaci Cook August 4, 2011. About Me- Elizabeth (Beth) Nowacki. Tables of Contents. HSE project Rapid Frac Material Handling Lessons Learned Thank you!. - PowerPoint PPT Presentation
Citation preview
Rapid Frac Material Handling
Beth NowackiSCMP Intern Final Presentation
B.U.M: Thomas SweeneyPGL: Kaci CookAugust 4, 2011
2FOR INTERNAL USE ONLY
About Me- Elizabeth (Beth) Nowacki
B.S. Industrial Engineering, Minor in
Mathematics
LSU- GEAUX TIGERS!!
Dallas Native
3FOR INTERNAL USE ONLY
Tables of Contents
HSE project
Rapid Frac Material Handling
Lessons Learned
Thank you!
4FOR INTERNAL USE ONLY
HSE: Recommendations to improve Ergonomics in the Send Out Crating Area
Ergonomic Issues:
Back StrainKnee Problems
5FOR INTERNAL USE ONLY
JSA/ RISK ASSESSMENT FORM
• Kneepads• Lifting Table
6FOR INTERNAL USE ONLY
Rapid Frac
Enables continuous pumping of multi-zone treatments
Helps reduce completion cycle time and improve production
7FOR INTERNAL USE ONLY
-Field estimates 1200 assemblies per month
- Takt rate of 72 assemblies per day.
Project Statement: Improve the overall logistics of
handling rapid frac material.
Rapid Frac
8FOR INTERNAL USE ONLY
Introduction to Halliburton Introduction to Rapid Frac
Data Collection Basic Analysis
Weeks 1-6
9FOR INTERNAL USE ONLY
Saws
Crating
Receiving
Warehouse
QM Lot
TRT
Inspection
Manufacturing
Assembly
RF
RF
RF
External Vendor
- In house production only
- In house production, with external finishing's
- External production
10FOR INTERNAL USE ONLY
Saws
Crating
Staging
QM Lot
External Vendor
Staging
Send Out
Organize
Staging
Receiving Dock
1
2
45
78
9
6
WarehouseRF
1110
3
Areas of Improvement Crating (1.5 hours) Receiving (10 days)
Re-palletize (15 mins) Saw Area
Initial State
11FOR INTERNAL USE ONLY
Saws
Crating
Staging
External Vendor
Staging
Send Out
Organize
Staging
Receiving Dock
2
WarehouseRF
3
5
Long Bar Send Out
Pallet Pull System
1
4
6
Ideal Future State
QM Lot
Crating: Before: 1.5 hours After: NONE
Receiving Before: 10 days After: 3 days
Re-palletize Before: 15 mins After: NONE
12FOR INTERNAL USE ONLY
ROI- Receiving Current State (150-300 Assemblies)
Average Number of Pallets Received per day– 5.6 pallets
Time spent Re-palletizing per day (15 min/pallet)– 84 min or 1.4 hours per day– 285 hours per year
Indirect Labor Cost (Labor Burn Rate $56/hour)– $78.40/day– $15,993.80/year
13FOR INTERNAL USE ONLY
ROI- Receiving Future State with Current Pallet System
Average Number of Pallets Received per day– 22.4 pallets
Time spent Re-palletizing per day– 336 min or 5.6 hours per day– 1,442 hours per year
Indirect Labor Cost (Labor Burn Rate $56/hour)– $313/day– $63,974 /year
14FOR INTERNAL USE ONLY
Implementing a standardize pallet will be the most efficient way to improve overall logistics of Rapid Frac.
• Reduce the number of Touches• Reduce time in Receiving
• Reduce time in Crating• Integrate into the Pull Systems• Ergonomically and Cost Effect
Introduction to Halliburton
Introduction to Rapid Frac
Data Collection Basic Analysis
Research Solutions
Ergonomic Assessment
Container Comparisons Action Plan
Weeks 1-6 Weeks 7-12
15FOR INTERNAL USE ONLY
Requirements For Standardize PalletGood
Ergonomics: Lifting
Good Ergonomics: Transportation
Under $350 each
Reduce Time in Receiving
Reduce Time in Crating
Forklift Accessible
Weight Capacity of 2000 lbs
Ability to stack at least 3 high
Pallets
Wire Basket
Steel Corrugated
Bin
Metal Pallet with
Removable Doors
16FOR INTERNAL USE ONLY
Metal Pallet (Wooden Replica)
Good Ergonomics: both Transporting and Lifting
$276 2000 lbs static load Stackable (3) Forklift Accessible 2 Removable Doors Lined with cardboard or
corrugated plastic
17FOR INTERNAL USE ONLY
Sustainability
Management of Change
Standard Work
10 metal pallets on order– 3 week lead time
Jason Besly- EPIC Project Manager - Rapid Frac
18FOR INTERNAL USE ONLY
Initial State Future State
# of Touches (Specifically in the Send out Process) 11 touches 6 touches
Reducing time in Crating 1.5 hours None
Waiting time in Receiving 10 days15 min
3 daysNone
Integrate into Pull System 0 2
By Implementing a the metal pallet with two removable doors:
$63,974 ROI
19FOR INTERNAL USE ONLY
Lessons Learned
Ask Questions!
Don’t wait for something to happen, make it happen yourself!!
Network!!!!
Good communication is essential!
20FOR INTERNAL USE ONLY
Thank You! Ryan Arrington Jason Besly Mark Bregenzer Kaci Cook David Dockweiler Gary Freet Joe Haddad Bryan Hensley Dean Wynia Jimilee McCleskey Susan Price Lynsey Ritchie
Cheri Rogers Shannon Sixkiller Tom Sweeney Dan Swofford Donna Willis Chad Woodward Carrollton Interns
– Austin Baltes– Kimberly Caleon– Haley Helweg– Lee Smiley– Javier Penaflor– Aditya Mittal
21FOR INTERNAL USE ONLY
Questions?
22FOR INTERNAL USE ONLY
Action Plan People
– Overall Manager: Jason– To finish ergonomic testing of metal samples: (Epic: Jason or Dean)– Updating Vendors on how to properly load parts (Jim Gilmore with Standard
Work from Beth)– Inform Receiving and Crating on new pallets (Mark Bregenzer)– Pallet included in PO (Joy)
6 star documents (SOP) standard work– Instructions put parts in bin/pallet– MOC– ROI(completed)
23FOR INTERNAL USE ONLY
Saws
Crating
Receiving
Warehouse
QM Lot
TRT
Inspection
Manufacturing
Assembly
RF
RF
RF
External Vendor
11 touches
24FOR INTERNAL USE ONLY
Saws
Crating
Receiving
Warehouse
QM Lot
TRT
Inspection
Manufacturing
Assembly
RF
RF
RF
External Vendor Long Bar
Send Out
Bin Pull
6 touches
25FOR INTERNAL USE ONLY
Saws
Crating
Receiving
Warehouse
QM Lot
TRT
Inspection
Manufacturing
Assembly
RF
RF
RF
External Vendor
23 touches
26FOR INTERNAL USE ONLY
Saws
Crating
Receiving
Warehouse
QM Lot
TRT
Inspection
Manufacturing
Assembly
RF
RF
RF
External Vendor
22 touches
27FOR INTERNAL USE ONLY
Saws
Crating
Receiving
Warehouse
QM Lot
TRT
Inspection
Manufacturing
Assembly
RF
RF
RF
External Vendor
16 touches
28FOR INTERNAL USE ONLY
Manufacturing Process