Talk Outline
• Proton Source Overview• Proton Source Operations and Previous Upgrades
Operational Past Operational Current Operational Planned
• Current Upgrades in progress• Task Force Report & Review• Proton Source Improvement Report & Effort
Report Review• Systems• Costs• Timetable
William Pellico, FRA Visiting Committee Meeting, March 14-15, 20112
Proton SourcePre-Accelerator Linac Booster
William Pellico, FRA Visiting Committee Meeting, March 14-15, 20113
Pre - Accelerator
William Pellico, FRA Visiting Committee Meeting, March 14-15, 20115
H-
I-
Inside H- Dome
Pre-Acc
Region
I- Dome
H-
LINAC
William Pellico, FRA Visiting Committee Meeting, March 14-15, 20116
200 MHz Alvarez LE
Accelerating Cavity
5 MW 7835
Power Amp
800 MHz Klystron
High Energy Linac
Booster
William Pellico, FRA Visiting Committee Meeting, March 14-15, 20117
RF Cavities
Magnets
(Inside)
Booster Facts:
15 Hz Synchrotron
400 MeV to 8 GeV
24 Cell Lattice - Harmonic = 84
Beam
Input
MI-8
8 GeV
Historic Operations
First 30 years of operations Averaged about 1E19 Protons/Year Users
• Fixed Target • Pbar Production (Starting in 1985)
Booster Duty Cycle was much less than 1 Hz Booster Efficiency was under 70% Major Upgrade - Doubling Linac Energy
• Installation of Klystron System in 1995
William Pellico, FRA Visiting Committee Meeting, March 14-15, 20118
Start Neutrino Program and Run II RequirementsFY2000
• Requested Rep rate increased by about a factor of 10• Requested Proton throughput increased by about a factor of 10• Beam quality required significant improvements
MI Slip Stacking Requirements Booster Activation Issues Protons for collider program
• Reduced Scheduled Repair/Study Periods
HEP requests greater than Proton Source could deliver!
William Pellico, FRA Visiting Committee Meeting, March 14-15, 20119
Completed Proton Source Upgrades
• Improved Beam Quality New Booster Correctors
• Orbit Control• Corrected Harmonics
Removal of an extraction region• Aperture restriction
Added damping New injection region
• Increased Proton Throughput Added shielding Collimation System
• Controlled loss point• Reduced Component Activation
Improved Low Level control – Cogging/Notching
William Pellico, FRA Visiting Committee Meeting, March 14-15, 201110
Beam Plot - Efficiency Improvements - 2000 to 2010
William Pellico, FRA Visiting Committee Meeting, March 14-15, 201111
Beam Acceleration Cycle in Booster90% Efficiency
72% Efficiency
Proton Throughput History
William Pellico, FRA Visiting Committee Meeting, March 14-15, 201112
1974
1977
1980
1983
1986
1989
1992
1995
1998
2001
2004
2007
2010
2013
2016
2019
2022
2025
0
50
100
150
200
250
300
350
400
0
10
20
30
40
50
60
70
Proton Source Yearly and Integrated Output (E19)Integrated Protons
Yearly Protons
Year
Inte
gra
ted
E1
9
Record Year FY10 6.1E20
Current Proton Source Projects
• Pre-Accelerator New RFQ injector*
• Linac Linac Dump Repair Line Power Regulation (PLC Based Controls)
• Booster Short Kicker (20 ns goal ) Low Level Upgrade Lattice and Aperture studies (Magnet Moves) Transverse Dampers Beam Dynamics Correction – New Correctors Booster Solid State*
* Projects included in Proton Task Force report and PIP
William Pellico, FRA Visiting Committee Meeting, March 14-15, 201113
Pre Accelerator Project
Remove Cockcroft-Waltons and 750 KeV line Two Round Slit Magnetron H- 35 KeV Sources (June Delivery) New Transport Line
• 750 KeV Radio Frequency Quadrupole (RFQ) (May Delivery)• New Transport Lines
• LEBT• Solenoids (Completed)• Trims (June Delivery)
• MEBT• New Buncher Cavity (March Delivery)• New High Gradient Quadrupoles (Oct. Delivery)
Scheduled Installation - 2012 Shutdown
William Pellico, FRA Visiting Committee Meeting, March 14-15, 201114
Pre-Accelerator Upgrade 2009 to 2012
William Pellico, FRA Visiting Committee Meeting, March 14-15, 201115
Beam Testing
End of Summer
RFQ arrives by May
Proton Task Force Report (Submitted 2010)
Task charge: Reliable operation for 15 yearsAreas of Concern
Pre-Accelerator • Continue With RFQ Project
Linac• Low Energy RF Drive System• Low Energy DTL
Booster• High Level RF Systems (Solid State and More)• Combined Function Magnets• Radiation/Activation
Utilities• LCW• Transformers and Switch Gear
William Pellico, FRA Visiting Committee Meeting, March 14-15, 201116
Proton Improvement Plan (PIP)
• Maintains viable and reliable operation of the Linac and Booster through 2025 +
TASK FORCE REPORT
• Increases the Booster RF pulse repetition rate (From ~8 Hz to 15 Hz)
TASK FORCE REPORT
• Doubles the proton flux “delivering 2.25E17 protons/hour (at 15 Hz) by January 1, 2016”
William Pellico, FRA Visiting Committee Meeting, March 14-15, 201117
The Fermilab Associate Director for Accelerators and the Fermilab Accelerator Division Head have established a charge for developing a plan that.....
PIP - Proton Goals
William Pellico, FRA Visiting Committee Meeting, March 14-15, 201118
Present Flux
PIP – Cycle Rate Goals
William Pellico, FRA Visiting Committee Meeting, March 14-15, 201119
Present Rate
Proton Improvement Plan Efforts
• Workshop (Dec.2010) Identify Physics Issues Identify Personnel Review Proton Force Task Force Report Review Required Resources
• Meetings to discuss details of workshop Working groups started to address critical issues
• Create project funding profile – using guidance M&S funding Manpower Timetable
• Submitted plan to management February 2011
William Pellico, FRA Visiting Committee Meeting, March 14-15, 201120
PIP Summary• Task M&S K$ FTEs• Project Management 9.0• Modulator /Drive System Only 10,000 49• RFQ 750.0 10.0• New Booster Cavities 18,000.0 25.0• Beam physics studies etc 12.0• Collimators 1,500.0 12.0• Instrumentation 500.0 15.0• BRF Anode and Bias supplies & test stand 1,710.0 3.0• Controls 1,000.0 10.0• Booster Solid state systems 3,700.0 8.0• Booster LCW 465.0 0.8• Booster Vacuum 124.0 3.0• Linac Vacuum 255.0 3.0• Power distribution 1,816.0 3.5• Booster gradient magnets 80.0 1.5• TOTALS (Modulators Only) 39,900.0 164.8
William Pellico, FRA Visiting Committee Meeting, March 14-15, 201121
PIP cost profile for FY2012 and 20113Proton Source Improvement Plan M&S Cost Profile by Calendar Quarter
Fixed Cost
Year QuarterPROTON SOURCE
IMPROVEMENT PLAN2011 Q1 700,000
Q2 0Q3 0Q4 6,200,000
2011 Total 6,900,0002012 Q1 1,200,000
Q2 600,000Q3 0Q4 2,574,000
2012 Total 6,374,0002013 Q1 1,126,000
Q2 0Q3 0Q4 0
2013 Total 3,426,000Grand Total 12,400,000
William Pellico, FRA Visiting Committee Meeting, March 14-15, 201122
Conclusion
William Pellico, FRA Visiting Committee Meeting, March 14-15, 201123
The domestic accelerator High Energy Physics program for the next 15 years is dependent on the viability and vitality of the Fermilab Linac and Booster.
The Fermilab Associate Director for Accelerators and the Fermilab Accelerator Division Head have established a charge for developing a plan to assure this viability and vitality.
Execution of the plan requires a commitment of significant resources. It is important to move quickly and the support of FRA is essential.
Critical Items in PIP
William Pellico, FRA Visiting Committee Meeting, March 14-15, 201126
• Linac RFQ project. This program is now effectively underway, but the project might benefit from a constructive advice from a wider group with a range of relevant experiences. Both a conceptual design review by independent experts and an internal technical design and implementation plan review are appropriate at this stage.
• Booster RF Solid State Program. This and the other Booster RF efforts are presently guided by one individual able to devote an inadequate fraction of his time to each. Undivided attention is required to be prepared for the 2012 shutdown.
• Booster RF Cavities, Tuners, Anode Supplies, and Bias Supplies. Each of these elements cries for, undivided attention for there to be any chance of supporting 12 Hz operation in 2013.
• The entire “Doubling the 8 GeV Beam Flux” category. This range of elements requires one dedicated and informed scientific staff person to serve as a focal point. That person shall provide the oversight and guide the planning of investigations and beam studies necessary to achieve sufficient understanding of the issues. The time scale should be such as to enable proper preparation for effective use of the 2012 shutdown.
• 200 MHz Linac RF Power Systems backup Plans B and C. Especially Plan C to design a “SNS-like” 400 MHz Linac compatible with the present high energy section of the Fermilab Linac should be addressed.
• Linac and Booster Power Distribution Equipment. Items within this category that will be replaced must be prioritized and pre-procurement activities such as specification development and installation planning need to begin in order to effectively procure the equipment in a timely manner when funds become available.
• Booster Spare RF Cavity Program. This effort is in immediate need of skilled mechanical technician labor.