26
Proton Improvement Plan William Pellico FRA Visiting Committee Meeting March 14-15, 2011

Proton Improvement Plan William Pellico FRA Visiting Committee Meeting March 14-15, 2011

Embed Size (px)

Citation preview

Proton Improvement Plan

William PellicoFRA Visiting Committee Meeting

March 14-15, 2011

Talk Outline

• Proton Source Overview• Proton Source Operations and Previous Upgrades

Operational Past Operational Current Operational Planned

• Current Upgrades in progress• Task Force Report & Review• Proton Source Improvement Report & Effort

Report Review• Systems• Costs• Timetable

William Pellico, FRA Visiting Committee Meeting, March 14-15, 20112

Proton SourcePre-Accelerator Linac Booster

William Pellico, FRA Visiting Committee Meeting, March 14-15, 20113

Proton Source Overview

William Pellico, FRA Visiting Committee Meeting, March 14-15, 20114

Pre - Accelerator

William Pellico, FRA Visiting Committee Meeting, March 14-15, 20115

H-

I-

Inside H- Dome

Pre-Acc

Region

I- Dome

H-

LINAC

William Pellico, FRA Visiting Committee Meeting, March 14-15, 20116

200 MHz Alvarez LE

Accelerating Cavity

5 MW 7835

Power Amp

800 MHz Klystron

High Energy Linac

Booster

William Pellico, FRA Visiting Committee Meeting, March 14-15, 20117

RF Cavities

Magnets

(Inside)

Booster Facts:

15 Hz Synchrotron

400 MeV to 8 GeV

24 Cell Lattice - Harmonic = 84

Beam

Input

MI-8

8 GeV

Historic Operations

First 30 years of operations Averaged about 1E19 Protons/Year Users

• Fixed Target • Pbar Production (Starting in 1985)

Booster Duty Cycle was much less than 1 Hz Booster Efficiency was under 70% Major Upgrade - Doubling Linac Energy

• Installation of Klystron System in 1995

William Pellico, FRA Visiting Committee Meeting, March 14-15, 20118

Start Neutrino Program and Run II RequirementsFY2000

• Requested Rep rate increased by about a factor of 10• Requested Proton throughput increased by about a factor of 10• Beam quality required significant improvements

MI Slip Stacking Requirements Booster Activation Issues Protons for collider program

• Reduced Scheduled Repair/Study Periods

HEP requests greater than Proton Source could deliver!

William Pellico, FRA Visiting Committee Meeting, March 14-15, 20119

Completed Proton Source Upgrades

• Improved Beam Quality New Booster Correctors

• Orbit Control• Corrected Harmonics

Removal of an extraction region• Aperture restriction

Added damping New injection region

• Increased Proton Throughput Added shielding Collimation System

• Controlled loss point• Reduced Component Activation

Improved Low Level control – Cogging/Notching

William Pellico, FRA Visiting Committee Meeting, March 14-15, 201110

Beam Plot - Efficiency Improvements - 2000 to 2010

William Pellico, FRA Visiting Committee Meeting, March 14-15, 201111

Beam Acceleration Cycle in Booster90% Efficiency

72% Efficiency

Proton Throughput History

William Pellico, FRA Visiting Committee Meeting, March 14-15, 201112

1974

1977

1980

1983

1986

1989

1992

1995

1998

2001

2004

2007

2010

2013

2016

2019

2022

2025

0

50

100

150

200

250

300

350

400

0

10

20

30

40

50

60

70

Proton Source Yearly and Integrated Output (E19)Integrated Protons

Yearly Protons

Year

Inte

gra

ted

E1

9

Record Year FY10 6.1E20

Current Proton Source Projects

• Pre-Accelerator New RFQ injector*

• Linac Linac Dump Repair Line Power Regulation (PLC Based Controls)

• Booster Short Kicker (20 ns goal ) Low Level Upgrade Lattice and Aperture studies (Magnet Moves) Transverse Dampers Beam Dynamics Correction – New Correctors Booster Solid State*

* Projects included in Proton Task Force report and PIP

William Pellico, FRA Visiting Committee Meeting, March 14-15, 201113

Pre Accelerator Project

Remove Cockcroft-Waltons and 750 KeV line Two Round Slit Magnetron H- 35 KeV Sources (June Delivery) New Transport Line

• 750 KeV Radio Frequency Quadrupole (RFQ) (May Delivery)• New Transport Lines

• LEBT• Solenoids (Completed)• Trims (June Delivery)

• MEBT• New Buncher Cavity (March Delivery)• New High Gradient Quadrupoles (Oct. Delivery)

Scheduled Installation - 2012 Shutdown

William Pellico, FRA Visiting Committee Meeting, March 14-15, 201114

Pre-Accelerator Upgrade 2009 to 2012

William Pellico, FRA Visiting Committee Meeting, March 14-15, 201115

Beam Testing

End of Summer

RFQ arrives by May

Proton Task Force Report (Submitted 2010)

Task charge: Reliable operation for 15 yearsAreas of Concern

Pre-Accelerator • Continue With RFQ Project

Linac• Low Energy RF Drive System• Low Energy DTL

Booster• High Level RF Systems (Solid State and More)• Combined Function Magnets• Radiation/Activation

Utilities• LCW• Transformers and Switch Gear

William Pellico, FRA Visiting Committee Meeting, March 14-15, 201116

Proton Improvement Plan (PIP)

• Maintains viable and reliable operation of the Linac and Booster through 2025 +

TASK FORCE REPORT

• Increases the Booster RF pulse repetition rate (From ~8 Hz to 15 Hz)

TASK FORCE REPORT

• Doubles the proton flux “delivering 2.25E17 protons/hour (at 15 Hz) by January 1, 2016”

William Pellico, FRA Visiting Committee Meeting, March 14-15, 201117

The Fermilab Associate Director for Accelerators and the Fermilab Accelerator Division Head have established a charge for developing a plan that.....

PIP - Proton Goals

William Pellico, FRA Visiting Committee Meeting, March 14-15, 201118

Present Flux

PIP – Cycle Rate Goals

William Pellico, FRA Visiting Committee Meeting, March 14-15, 201119

Present Rate

Proton Improvement Plan Efforts

• Workshop (Dec.2010) Identify Physics Issues Identify Personnel Review Proton Force Task Force Report Review Required Resources

• Meetings to discuss details of workshop Working groups started to address critical issues

• Create project funding profile – using guidance M&S funding Manpower Timetable

• Submitted plan to management February 2011

William Pellico, FRA Visiting Committee Meeting, March 14-15, 201120

PIP Summary• Task M&S K$ FTEs• Project Management 9.0• Modulator /Drive System Only 10,000 49• RFQ 750.0 10.0• New Booster Cavities 18,000.0 25.0• Beam physics studies etc 12.0• Collimators 1,500.0 12.0• Instrumentation 500.0 15.0• BRF Anode and Bias supplies & test stand 1,710.0 3.0• Controls 1,000.0 10.0• Booster Solid state systems 3,700.0 8.0• Booster LCW 465.0 0.8• Booster Vacuum 124.0 3.0• Linac Vacuum 255.0 3.0• Power distribution 1,816.0 3.5• Booster gradient magnets 80.0 1.5• TOTALS (Modulators Only) 39,900.0 164.8

William Pellico, FRA Visiting Committee Meeting, March 14-15, 201121

PIP cost profile for FY2012 and 20113Proton Source Improvement Plan M&S Cost Profile by Calendar Quarter

Fixed Cost

Year QuarterPROTON SOURCE

IMPROVEMENT PLAN2011 Q1 700,000

Q2 0Q3 0Q4 6,200,000

2011 Total 6,900,0002012 Q1 1,200,000

Q2 600,000Q3 0Q4 2,574,000

2012 Total 6,374,0002013 Q1 1,126,000

Q2 0Q3 0Q4 0

2013 Total 3,426,000Grand Total 12,400,000

William Pellico, FRA Visiting Committee Meeting, March 14-15, 201122

Conclusion

William Pellico, FRA Visiting Committee Meeting, March 14-15, 201123

The domestic accelerator High Energy Physics program for the next 15 years is dependent on the viability and vitality of the Fermilab Linac and Booster.

The Fermilab Associate Director for Accelerators and the Fermilab Accelerator Division Head have established a charge for developing a plan to assure this viability and vitality.

Execution of the plan requires a commitment of significant resources. It is important to move quickly and the support of FRA is essential.

Extra Slides

William Pellico, FRA Visiting Committee Meeting, March 14-15, 201124

William Pellico, FRA Visiting Committee Meeting, March 14-15, 201125

Critical Items in PIP

William Pellico, FRA Visiting Committee Meeting, March 14-15, 201126

• Linac RFQ project. This program is now effectively underway, but the project might benefit from a constructive advice from a wider group with a range of relevant experiences. Both a conceptual design review by independent experts and an internal technical design and implementation plan review are appropriate at this stage.

• Booster RF Solid State Program. This and the other Booster RF efforts are presently guided by one individual able to devote an inadequate fraction of his time to each. Undivided attention is required to be prepared for the 2012 shutdown.

• Booster RF Cavities, Tuners, Anode Supplies, and Bias Supplies. Each of these elements cries for, undivided attention for there to be any chance of supporting 12 Hz operation in 2013.

• The entire “Doubling the 8 GeV Beam Flux” category. This range of elements requires one dedicated and informed scientific staff person to serve as a focal point. That person shall provide the oversight and guide the planning of investigations and beam studies necessary to achieve sufficient understanding of the issues. The time scale should be such as to enable proper preparation for effective use of the 2012 shutdown.

• 200 MHz Linac RF Power Systems backup Plans B and C. Especially Plan C to design a “SNS-like” 400 MHz Linac compatible with the present high energy section of the Fermilab Linac should be addressed.

• Linac and Booster Power Distribution Equipment. Items within this category that will be replaced must be prioritized and pre-procurement activities such as specification development and installation planning need to begin in order to effectively procure the equipment in a timely manner when funds become available.

• Booster Spare RF Cavity Program. This effort is in immediate need of skilled mechanical technician labor.