Upload
ophrah
View
30
Download
0
Tags:
Embed Size (px)
DESCRIPTION
Proton Improvement Plan Bill Pellico April 19, 2013 NOvA collaboration Meeting. PIP Work Update. Injector (RFQ) RFQ injector installed Nov FY13 Operations Dec FY13 Hardware/ Beam Studies Continue Linac Beam established Nov FY13 Beam physics – matching Match to RFQ injector - PowerPoint PPT Presentation
Citation preview
Proton Improvement Plan
Bill Pellico
April 19, 2013NOvA collaboration Meeting
Bill Pellico NOvA
PIP Work Update
• Injector (RFQ)– RFQ injector installed
• Nov FY13• Operations Dec FY13• Hardware/ Beam Studies
Continue
• Linac– Beam established Nov FY13– Beam physics – matching
• Match to RFQ injector• Working on lattice/software
– New BPM/Toroid electronics– Upgraded vacuum systems
• Booster– New beam absorber
• 19,000 lbs of steel & concrete for dump of notched beam
• 3 kicker systems configured
– Solid State Completed• New Modulators• New Power Amplifiers (PA)• New Solid State drivers• Controls and Cabling
– Magnet/orbit Corrections– Beam physics - Lattice
Corrections– Upgraded LCW system– Refurbishment of RF Cavities
• 6 of 19 completedBill Pellico NOvA
Bill Pellico NOvA
Beam Status • RFQ injector largely in operations mode
– Still adjusting new sources • Beam current at ~ 30ma but design is for 35ma
– Second Source – with some improved hardware/design being tested– Additional trim package being added in May - should help increase beam current
• Linac Commissioning continues – Efficiency improved with new injector– Still lower current then before shutdown – but improving– Before MI starts ups – will have to work on two week stations (saving tubes)
• Booster beam up and running– Beam at half of desired (pre-shutdown) levels
• Work on RF systems (Refurbishment) limits beam current due to lower voltage
– New orbits/operating point being studied– Still working on RF systems – commissioning – debugging
• Refurbishment continues and will require stations out of the tunnel for repair – two more years
– Beam shielding assessment still being worked on – should not prevent operations
Booster RF Upgrade(s)• Solid State, Cavity Refurbishment, Alignment, LCW
systems, New cabling, Passive Damper Work
Booster Cavity WorkRefurbished (15Hz)
SS Prototype SS Upgraded
Cavity Removed
Bill Pellico NOvA
Bill Pellico NOvA
Booster Solid State RF Station Booster Aperture Scan
Solid State PA Booster Notch Beam Absorber
Bill Pellico NOvA
Near Term Plans• RFQ injector – Will be adding a new trim package (improve transmission)
• Installing Booster Utility Transformers• Installing Linac Roof access • Booster Magnet Moves continue• Booster Cogging studies• Booster Lattice Studies• Booster Cavity Refurbishment
• Operations:– Higher Intensity Tune-up– Address shielding assessment issues to allow for higher flux
Bill Pellico NOvA
PIP - issues• Beam operational goals vs. Refurbishment
– Having station(s) out of the tunnel will be a vulnerability • Get done faster or perhaps more downtime
• Labor– Need people to work on RF
• Skilled work that takes training• Low dose rates – but long hours creates radiological issues
• Funding– Big items just getting started
• Klystrons for low energy linac• New Booster Cavity• New Booster Tuners
– Need to adjust to changing laboratory priorities/funding
Bill Pellico NOvA
Proton Source/PIP – FY13 Calendar
NTFLinac
Booster
RFQMI Startup
High Intensity Tuning
Beam StudiesCoggingMagnet/Aperture MovesInjector Tune-upDampersLattice studies/corrections
Proton Source Throughput Goals (Base lined timetable/goals FY12)
g-2 Mu2e8 GeV
120 GeV NOvA Shutdown
LBNE
• We are currently on a ~ 10weeks/cavity• Labor
• Use contract help • Lots of training• Labor intensive job
• Radiation• Low doses – but long jobs
Bill Pellico NOvA
Required for 12 Hz Required for flux Required for 15 Hz Required for reliability
Com
pleti
on D
ate
Base
Lin
ed P
IP
Bill Pellico NOvA
FY13 Q1 Milestones and Goals look good Q2 through Q4 start to see budget impacts on some base lined milestones.
PIP Gant (Using FY13 Estimates)
Removed
Bill Pellico NOvA
PIP Support• We set up a model for participation• We put together a spreadsheet of potential jobs• The jobs are organized in areas of scientific, technical, and
machining• We had a meeting for all spokespersons to discuss• The request went out for help from all the experiments• We had four volunteer institutions from MicroBooNE -
none from elsewhere (Therefore they will get the best Protons!)
• We are in the process of putting out a first machining job– Other jobs are in the process of being screened
• Keep talking to directorate – defend labor and funding