Project Monitoring (Tung)

Embed Size (px)

Citation preview

  • 7/31/2019 Project Monitoring (Tung)

    1/20

    Topics for Today

    Cycle of planning-monitoring-control

    Report process

    The concept of earned value (EV) EV, PV, AC

    CPI, SPI

    Purposes and types of control Practice of project control

  • 7/31/2019 Project Monitoring (Tung)

    2/20

    The basic feedback loop ofcontrol

    PLAN ACTUAL

    Find

    cause

    Corrective action

    VARIANCE?

    New Plan

    Forecast to

    complete

    yesno

  • 7/31/2019 Project Monitoring (Tung)

    3/20

    Control SystemExample

    1. Periodic status checking will be performed monthly2. Labor costs will be collected manually and estimated where

    necessary from discussion with Group engineeringmanagement.

    3. Out-of-pocket costs will be collected through commitments

    and/or invoice payment records.4. Monthly status reports will be issued by the PM&C Program

    project manager including:a. Cost to date summariesb. Cost variances.

    c. Schedule performance relative to schedule in Ganttformat.d. Changes in scope or other modifications to plan.

    5. Informal control will be exercised through milestoneanticipation in the PM&C Program project manager

  • 7/31/2019 Project Monitoring (Tung)

    4/20

    Gantt Schedule Chart

    Example

    Figure 15.4

    JobDay

    1Day

    2Day

    3Day

    4Day

    5Day

    6Day

    7Day

    8

    A

    B

    C

    Now

    Maintenance

    Start of anactivity

    End of anactivity

    Scheduledactivity timeallowed

    Actual workprogress

    Nonproductiontime

    Point in timewhen chart isreviewed

  • 7/31/2019 Project Monitoring (Tung)

    5/20

  • 7/31/2019 Project Monitoring (Tung)

    6/20

  • 7/31/2019 Project Monitoring (Tung)

    7/20

    Earned Value (EV or BCWP) is thebudgeted value of work performed.

    Planned Value (PV) is also called BCWS budgeted cost of work scheduled.

    Actual Cost (AC) is also called ACWP actual cost of work performed.

  • 7/31/2019 Project Monitoring (Tung)

    8/20

    SV (schedule variance) = EV PV a negative value isbad (behind schedule)

    SPI (schedule performance index) = EV/PV a value less

    than 1 is bad

    CV (cost variance) = EV-AC a negative value is bad(over cost)

    CPI (cost performance index) = EV/AC a value less than1 is bad; equal to 1 suggests being on target; over 1says under budget.

  • 7/31/2019 Project Monitoring (Tung)

    9/20

    The Earned Value Calculations

    50-50 rule

    0-100 percent rule

    Critical input use rule The proportionality rule

  • 7/31/2019 Project Monitoring (Tung)

    10/20

    Management Information System

  • 7/31/2019 Project Monitoring (Tung)

    11/20

    Designing the MonitoringSystem

    1. Identify key factors to be controlled

    Performance

    Cost

    Time

    2. Information to be collected must beidentified

  • 7/31/2019 Project Monitoring (Tung)

    12/20

  • 7/31/2019 Project Monitoring (Tung)

    13/20

  • 7/31/2019 Project Monitoring (Tung)

    14/20

    Test your knowledge

    1. What does a cost performance index(CPI) of 1.0 suggest?

  • 7/31/2019 Project Monitoring (Tung)

    15/20

    That the project is on budget

  • 7/31/2019 Project Monitoring (Tung)

    16/20

    2. What does a schedule Performance Index(SPI) of 0.80 mean?

  • 7/31/2019 Project Monitoring (Tung)

    17/20

    We are only progressing at 80% of theschedule.

  • 7/31/2019 Project Monitoring (Tung)

    18/20

    How do you interpret the CPI (costperformance index) = 0.7?

  • 7/31/2019 Project Monitoring (Tung)

    19/20

    CPI = EV/AC = 0.7

    It means that for each $1 actually spent,only $0.7 worth of work has beencompleted cost inefficient.

  • 7/31/2019 Project Monitoring (Tung)

    20/20

    Group Discussion Assignments

    G1&2: Discuss the benefits of timely, appropriate, detailed information. Howcan a value be assigned to these characteristics?

    G3&4: What are the advantages for a PM of having a computerized systemover a manual one? The disadvantages?

    G5&6: A project is usually a one-time activity with a well-defined purpose.What is the justification of setting up a PMIS for such a project?

    G7&8: The earned value chart is an attempt to put the three-dimensionalconcept of Figure 1.1 (see Chap 1) into a two-dimensional format. Is itsuccessful?What is missing?

    G9&10: How might a variance be traced back to its source?