Upload
others
View
0
Download
0
Embed Size (px)
Citation preview
Ministry of Federal Affairs and Local Development
Department of Local Infrastructure Development and Agricultural Roads
Project Coordination Unit
Rural Reconstruction and Rehabilitation Sector Development Program, Phase 2 (RRRSDP-2)
Contract No. PCU/QCBS/01/2013
Survey, Design &Cost Estimate of Shankhu - Paluwari - Nagarkot Road
CH: 0+000 – 10+046.48 Km Kathmandu District
Volume – I MAIN REPORT
March, 2016 Submitted by
ERMC (P.) Ltd. (Environment & Resource Management Consultant) New Baneshwor, Kathmandu, Nepal P. O. Box: 12419, Kathmandu Tel.: 977-01-4483064, 4465863 Fax: 977-01-4479361 Email:[email protected], Website: www.ermcnepal.com
RRRSDP-2 i
ACKNOWLEDGEMENT
ERMC would like to extend special gratitude to all the concerned RRRSDP central Project coordination
Unit and district team, officials of DDC, DTO and especially the local people of the project area who
guided, advised, and cooperated ERMC and joined the survey team and guided/assisted during
conduction of detailed engineering survey work. We also appreciate the contribution of all the individuals
involved in this project works for their kind co-operation and help at every step of Detail Engineering
Survey and Design of Shankhu-Palubari-Nagarkot Road in Kathmandu District.
.
RRRSDP-2 ii
Table of Contents Abbreviation Salient
Feature Executive
Summary
CHAPTER-I: INTRODUCTION ..................................................................................................... 1
1.1 RRRSDP Districts for Implementation .......................................................................................... 1
1.2. OBJECTIVES ................................................................................................................................ 2
1.3. SCOPE OF WORKS ..................................................................................................................... 2
CHAPTER-II: METHODOLOGY ................................................................................................... 4
2.1 THE STUDY TEAM ....................................................................................................................... 4
2.2 Desk study..................................................................................................................................... 4
2.3 Identification and Selection of Roads............................................................................................ 4
2.4 Meetings ........................................................................................................................................ 4
2.5 Meeting with Local Level Stakeholders......................................................................................... 5
2.6 Detailed Engineering Survey, Design and Cost Estimate............................................................. 6
2.7 Field Verification of Design / Estimate .......................................................................................... 8
CHAPTER-III: THE PROJECT ...................................................................................................... 9
3.1 Project District ............................................................................................................................... 9 3.2 Description of Alignment ............................................................................................................. 10 3.3 Population Served & Traffic Data: .............................................................................................. 10 3.4 Potential Area & Growth Centers................................................................................................ 11 3.5 Project Rationale......................................................................................................................... 11
CHAPTER-IV: GEOLOGY AND GEOMORPHOLOGY .............................................................. 13
4.1 Geological Study......................................................................................................................... 13 4.1.1 Introduction ................................................................................................................................. 13 4.1.2 Regional Geology and Geomorphology...................................................................................... 13 4.1.3 Surface Geology ......................................................................................................................... 13 4.1.4 Slope Stability Condition ............................................................................................................. 14 4.1.5 Engineering Geological Mapping ................................................................................................ 14 4.1.6 Geological Hazard Mapping ....................................................................................................... 15
4.2 Construction Material Survey...................................................................................................... 15 4.3 Land Use Pattern / VDC & Settlements...................................................................................... 15 4.4 Conclusions ................................................................................................................................ 15
CHAPTER-V: HYDROLOGY AND METEOROLOGY ................................................................ 16
5.1 General........................................................................................................................................ 16
5.2 Rainfall ........................................................................................................................................ 16
5.3 Design Discharge ........................................................................................................................ 16
5.4 Cross Drains............................................................................................................................... 17
RRRSDP-2 iii
5.5 Side Drains .................................................................................................................................. 18
5.6 Selection of Cross-drainage Structures Type ............................................................................. 18
CHAPTER-VI: GEOMETRIC STANDARDS & DESIGN ............................................................. 20
6.1. Road Classification ..................................................................................................................... 20
6.2. Design Standard ......................................................................................................................... 20
6.2.1. Design Speed............................................................................................................................. . 20
6.2.2. Geometric Design ....................................................................................................................... 20
6.2.3. Horizontal Curvature ................................................................................................................... 20
6.2.4. Super Elevation ........................................................................................................................... 20
6.2.5. Minimum Radius of Curvature..................................................................................................... 21
6.2.6. Widening on Curves .................................................................................................................... 21
6.2.7. Stopping Sight Distance Sight Distance ..................................................................................... 22
6.2.8. Gradient....................................................................................................................................... 23
6.2.9. Summit Curves............................................................................................................................ 24
6.2.10. Valley Curves .............................................................................................................................. 24
6.3. ROAD CROSS- SECTION .......................................................................................................... 25
6.3.1. Cross Section Design.................................................................................................................. 26
6.3.2. Shoulder Width............................................................................................................................ 26
6.3.3. Carriageway Width ...................................................................................................................... 26
6.3.4. Formation Width .......................................................................................................................... 26
6.3.5. Right of Way................................................................................................................................ 26
6.3.6. Camber........................................................................................................................................ 26
6.3.7. Pass Bay ..................................................................................................................................... 27
6.3.8. Carriageway width at culvert/ bridge ........................................................................................... 27
6.3.9. Level of road embankment above hfl .......................................................................................... 27
6.3.10. Lateral Clearance ........................................................................................................................ 27
6.3.11. Vertical Clearance ....................................................................................................................... 27
6.4. Cut / Fill Batter Slopes ................................................................................................................ 27
CHAPTER-VII: ENVIRONMENTAL MITIGATION MEASURES ................................................. 28
7.1. Consideration Made in Alignment Selection, Survey and Design Phase ................................... 28
7.2. Drainage Outlet Protection Works............................................................................................... 28
RRRSDP-2 iv
7.3. Selection of Slope Protection Work............................................................................................. 29
7.4. LIST OF SOME ENVIRONMENT PROTECTION WORKS: ....................................................... 29
DETAILED ENGINEERING DESIGN ......................................................................................... 30
8.1 Design Method ............................................................................................................................ 30 8.2 Review & Redesign..................................................................................................................... 30 8.3 Design & Drawings ..................................................................................................................... 30 8.4 Horizontal Curve Design ............................................................................................................. 30 8.5 Design of Structures and other geometric Features ................................................................... 30 8.6 Pavement Proposed .................................................................................................................. 30 8.7 Field Verification of Design / Estimate ........................................................................................ 36
CHAPTER-IX: COST ESTIMATE ............................................................................................... 37
9.1. Summary ..................................................................................................................................... 37
9.2. Quantity Estimate ........................................................................................................................ 37
9.3. Rate Analysis .............................................................................................................................. 37
9.4. Cost estimate .............................................................................................................................. 37
9.5. Conclusion................................................................................................................................... 37
CHAPTER-X: CONCLUSION & RECOMMENDATIONS ........................................................... 38
Annexes
Annex1: DCP Test
Annex 2: Horizontal Curve Data
Annex 3: Bench Marks List
Annex 4: Photographs
RRRSDP-2 v
ACRONYMS
ADB ADDI BCR BG BS
Asian Development Bank Appraisal Document for Donor Investment Benefit Cost Ratio Building Group Baseline Survey
CE Community Empowerment DDC District Development Committee DFID Department for International Development (UK) DoLIDAR Department of Local Infrastructure Development and Agricultural Roads
DoR DoS DPR DRCN
Department of Roads Description of Services Detailed Subproject Report District Road Core Network
DTMP District Transport Master Plan DTO District Technical Office
EIA Environmental Impact Assessment EIRR Economic Internal Rate of Return ERMC Environment Resource Management Consultant (the consultant of RRRSDP-2) GDP Gross Domestic Product GoN Government of Nepal
ICD Institutional Capacity Development
IEE IPDP IRR
Initial Environmental Examination Indigenous People Development Plan Improved Rural Roads
LBFAR Local Body Financial Administrative Regulation LEP Labor-based, Environmentally-friendly, and Participatory (approach) LSGA Local Self-Governance Act MoFALD Ministry of Federal Affairs and Local Development
MYRP NGO
Multi Year Rolling Plan
Non Government Organization
NPV net present value O&M Operation & Maintenance
OFID PCR PCU PFP
PIP
OPEC Countries for International Development Subproject Completion Report Subproject Coordination Unit Program Financing Plan Subproject Program Investment Plan
Subproject PMS Program Monitoring System Subproject
PPTA Subproject Preparatory Technical Assistance
RES RFP RIRR RoW
Rapid Environmental Screening Request for Proposal Rural Infrastructure Rehabilitation & Reconstruction Investment Plan of GoN Right of Way
RP Resettlement Plan
RRMC Rural Road Maintenance Committee
RRMFC RRMMS RRRSDP SDC
Rural Road Maintenance Fund Committee Rural Road Maintenance Management System Rural Reconstruction and Rehabilitation Sector Development Program
Swiss Agency for Development and Cooperation SRN Strategic Road Network ToR Terms of Reference VDC Village Development Committee VOC Vehicle Operation Cost ZoI Zone of Influence
Detail Engineering Survey and Design of Sankhu - Palubari - Nagarkot Road
RRRSDP-2 vi
(Kathmandu)
SALIENT – FEATURES OF THE PROJECT
1. Name of Project : Shankhu – Paluwari - Nagarkot Road
2. Location
Region : Central Development
Zone : Bagmati
District : Kathmandu
VDC : Bajrayogini and Suntol VDC 3 Major Settlements : Sankhu/Bajrayogini, Palubari, Kattike and
Nagarkot
4 Population served : 4819
5 Terrain : Rolling & Hilly
6 Classification of Road
Classification : District Core Road Network
Existing Surface : partially graveled, earthen
Proposed Surfacing Surface : Blacktopped
7 Road Alignment
Starting Point : Shankhu of BajrayoginiVDC#6
Ending Point : Baluwapati - Deupur VDC#8, Kavre
Length : 10.046 km
DTMP Code : 27DR037
8 Cross Section
Right of Way : 10m either Side
Formation Width 6.25 m including drain
Roadway width : 5.25 m
Carriageway Width : 3.75 m
Shoulder Width : 0.75 m either Side
9 Earthwork
Cut Volume (Cum) : 48,736.91 cu.m
Fill Volume (Cum) : 34735.42 cu.m
10 Retaining Structure
Gabion Wall (Cum) : 2660 cum
Cement Masonry Wall : 1855.56 cum
11 Drainage
Drain 8533.24 R m Pipe culvert : 23Nos
Slab Culvert : 4Nos
Outlet Protection Works 32Nos
12 Project Cost
Overall Total Cost including
Contingency and VAT : NRs.232,716,449.2
Overall Total Cost excluding
Contingency and VAT : NRs. 200,617,628.6
Cost per Km excluding
Contingency and VAT : NRs. 19,968,311.16
Detail Engineering Survey and Design of Sankhu - Palubari - Nagarkot Road
RRRSDP-2 vii
(Kathmandu)
EXECUTIVE SUMMARY
This report is the findings of detailed engineering survey and design of District Road Sankhu - Palubari -
Nagarkot Road (Kathmandu)”that was carried out for upgrading of road stretch that connects the different
settlements of Bajrayogini and Suntol VDCs of Kathmandu and Deupur VDC of Kavre with core city area of
Kathmandu Metropolitan City and different strategic road networks. The road is located in the north - east
part of Kathmandu district.
This road is designed for upgrading to blacktopped standard and the proposed intervention comprises:
Widening of narrow section to NRRS 2055 standard
Improvement of steep gradient
Provision of passing bays
Improved drainage system with lined drain and adequate cross-drainage structures
Upgrade the road geometry to minimum design standard of DoLIDAR; and
Minimizing Environmental hazards
The total length of road is 10.046 km. The road alignment starts from Shankharapur Municipality Ward #11
and passes through Sankhu, Palubari, Kattike and finally reaches to Nagarkot and Baluwapat - Deupur
VDC Ward #8 of Kavre district.
This road will provide access to market, education institutions, and Health centre and government service
offices. In addition it is also a potential heritage route to religious places of Sankhu and Bajrayogini and
tourist route to Nagarkot.
The Consultant has conducted the detail survey work of proposed road with total station using digital
terrain model. Walkover survey has been conducted to confirm the feasibility of road. Local peoples
including district technical office (DTO) team are consulted prior to commencement of work.
Existing road has been followed as far as possible while fixing the alignment; however these will be shifted
in some places especially at hair-pin-bends to maintain the geometric design parameters and at
problematic areas of steep gradient where locals allowed doing so. As far as the topography allows the
ruling longitudinal gradient has been followed. Only in exceptional cases where the alternative alignment
is difficult and not justifiable, the gradient is adopted to 12% and even more keeping view of resettlement
limitation and other social reasons and to escape from unfeasible cut/fill and possible damage to houses.
The road is designed to all weather type of District Core Road Network standard of general width of 5.25 m
with 3.75 m carriageway including 0.75 m shoulder on either side and with vehicle-passing zone at
intervals as proposed in the design standard.
In order to manage the surface run-off lined drain is proposed with cross-drainages at frequent interval
focusing to be located at vertical intersection valley points. Consideration is given to safe discharge of the
drainage outlets in natural gullies. Type of crossings has been determined keeping view of nature and
characteristics of gullies, river, stream and spring.
Unnecessary heavy cut/fill has been avoided as far as possible; however this could happen to some extent
especially in hair-pin bends, where the combined effect of design grade limitation and abrupt change of
topography contour could induce such consequences and at sections with steep existing gradients.
Nepal Rural Road Standard (2055) with Second revision of December 2014 of MoFALD and DOLIDAR has
been followed during detailed engineering survey and design. So far, the construction concerns,
environment–friendly approach adopted in design.
The Consultant has tried their best knowledge, lesson learnt and expertise to cover all aspects of best
practices in road design in mountainous terrain and to produce a quality design report with optimal
economical and environmental consideration.
Detail Engineering Survey and Design of Sankhu - Palubari - Nagarkot Road
RRRSDP-2 viii
(Kathmandu)
After the submission of design/cost estimate to PCU/DTO a joint field visit verification from DTO and
Consultant of design/drawing have been made to assess adequateness and appropriateness of proposed
geometric design, retaining and cross drainage structures and other protection works with existing ground
reality need. The findings from field verification and comments & suggestions from DTO have been
incorporated in design/estimate.
Detail Engineering Survey and Design of Sankhu - Palubari - Nagarkot Road
RRRSDP-2 1
Kathmandu
1. CHAPTER-I: INTRODUCTION
The Rural Reconstruction and Rehabilitation Sector Development Program, Phase 2 (RRRSDP-2) is
the follow-on program of RRRSDP-1 which was successfully completed in June 2013. The
Government of Nepal is financing for the current preparatory stage of RRRSDP-2 with a purpose to
carry on this Program into physical construction stage later after securing funds from bilateral and
multilateral development partners after accomplishing the preparation of all specific designs and
documents. So this Program preparation modality of DoLIDAR is considered to be rather unique due
to the fact that it is commissioned without any external or donor‟s PPTA support and funding
assistance.
The agreement for consultancy services for this preparatory phase was signed on July 10, 2013
between PCU/ DoLIDAR and ERMC (who is the successful bidder) for carrying out feasibility, detailed
engineering surveys and design works of some 1087 km of roads and feasibility studies of 35 bridges
inclusive of other field surveys/ studies of allied components related to geological, geotechnical,
environmental, social and resettlement prerequisites in the 20 districts (same RRRSDP-1 districts).
DDC selected the list of roads and bridges from DTMPs/DRCNs and forwarded to the PCU for
inclusion in RRRSDP-2. After thorough review of the DTMP roads or selected roads of districts and
other relevant documents and data, the Consultant made discussions with the Client at the central
level concerning candidate roads to be included for feasibility study and detailed engineering toward
preparation of Detailed Project report.
This detailed engineering survey, design and cost estimate report has been produced as result of field
investigation, topographical survey along with the geological, hydrological study of road alignment and
review of relevant maps, reports and documents.
1.1 RRRSDP Districts for Implementation
The RRRSDP-2 implementation proposed to be continued in the same 20 districts of RRRSDP-1
listed below in the table and map:
Table: Names of Districts for RRRSDP-2 Implementation
Eastern Development Region: Panchthar, Ilam, Jhapa, Morang, Sunsari, Dhankuta,
Central Development Region: Sindhuli, Sindhupalchowk, Kathmandu, Lalitpur, Bhaktapur, Kavre, Dolakha, Chitwan,
Western Development Region: Parbat, Manang, Mustang,
Mid Western Development Region: Rolpa, Rukum,
Far western Development Region: Dadeldhura
Detail Engineering Survey and Design of Sankhu - Palubari - Nagarkot Road
RRRSDP-2 2
Kathmandu
1.2. OBJECTIVES
To achieve the program goal of reduce the poverty the program will continue and strengthen the
overall objectives of RRRSDP-1 to improve connectivity, enhanced economic and employment
opportunities and to ensure increased access to markets and social services for rural communities.
1.3. SCOPE OF WORKS
The consultant shall prepare Detailed Project Reports (DPR) of the each Road Subprojects.
Preparation of Detailed Engineering Survey, Design and Cost Estimate of Individual Road
Subprojects is one of major part of Detailed Project Report Preparation (under Part A of 2.2 of Scope
of Consulting Services). Following are the task under engineering report:
(i) Detailed field investigation including topographical survey, geological observation,
hydrological study &incorporating meteorological secondary information, slope stabilization
features, drainages patterns, and other features for road design..
(ii) Cross-drainage requirements will be assessed for proposing new structures for bridges,
culverts, and causeways as appropriate or improvements will be recommended for
structurally unsound structures.
(iii) Engineering surveys will be done following the standard engineering practices with horizontal
and vertical controls and benchmarking with all details necessary for a detailed design of
roads.
(iv) Material availability surveys will also be conducted for record. Local rates for construction, of
various items, local and imported materials, transportation charges, etc., will be enquired and
established as per the prevailing market rates and labour wage rates are to be confirmed from
district rates for cost estimating purpose.
Detail Engineering Survey and Design of Sankhu - Palubari - Nagarkot Road
RRRSDP-2 3
Kathmandu
(v) Computer aided software designs will be done for road designing. However manual designs
in some cases can be done.
(vi) The detailed designs will be done or prepared by the Consultant following the DoLIDAR‟s
Rural Road Design Standards.
(vii) Detailed and standard drawings will be also prepared as mentioned in the DoLIDAR
Technical Guidelines.
(viii) The designs and drawings will consist of the location map and layout, design profile, design
cross-section plan, other structural detailing and drawings and standard/typical drawings.
(ix) Engineering technical specifications for each work item will be written taking into account
relevant standard specifications in use in the country and elsewhere for similar works and in
accordance with the Codes of Practices.
(x) The detailed cost estimate will be prepared using the calculated quantities and unit rates,
derived from standard applicable District Rates and DoLIDAR Work Norms.
(xi) Detailed Subproject Report (DPR) will be prepared following the agreed Table of Content.
(xii) Detailed economic analysis of individual road subprojects will be carried out and presented in
the DPR.
(xiii) Contract packaging will be suitably done as agreed with the Client for all subprojects, and
respective bidding documents will be prepared following the DoLIDAR practices and
frameworks.
(xiv) Similarly engineering subproject implementation schedules will be prepared.
Detail Engineering Survey and Design of Sankhu - Palubari - Nagarkot Road
RRRSDP-2 4
Kathmandu
2. CHAPTER-II: METHODOLOGY
2.1 THE STUDY TEAM
The study team of Consultants for detailed engineering comprised a Road Expert (Team Leader), one
Social Specialist, one Environmental Specialist, one Resettlement Specialist, Road Engineer, one
Bridge Engineer, one Geo-technical Engineer, one Geologist, one Hydrologist and one Transport
Economist.
In addition to the above mentioned core team, the Consultants had fielded special survey team for
conduction of detailed engineering survey and design of road sub-projects. Furthermore other
necessary human resource and all required logistics was mobilized for the study of road in terms of
engineering feasibility, social viability, environmental sustainability and economically beneficial.
2.2 Desk study
The Consultant collected documents, drawings, study reports, maps, walkover survey report and
existing DTMP to acquire and extract key information for conduction of detail engineering study of the
selected alignment route. The Consultant had studied all these documents prior to field movement to
perform detail alignment survey.
Following activities were carried out during desk study:
- Studied the maps and previous reports that indicated the route alignment.
- Collected all relevant guidelines, norms, handout, specification and maps required for desk
study.
- Nepal Rural Road Standard (NRSS 2055) and DoLIDAR Norms & Specification has been
studied and referred for adoption of design standard and specification.
- Collected and referred existing DTMP of district road core network and its priority ranking.
- Collected relevant geological map to acquire geological/geotechnical feature of road
alignment.
- Study has been made to find out the possible environmentally sensitive areas from where the
alignment passes through
2.3 Identification and Selection of Roads
DDC selected and provided the road lists to the PCU for inclusion in RRRSDP-2 before
commencement of Consultant's services. After thorough review of the DTMP roads or selected roads
the Consultant made discussions with the Client for the selection of candidate roads.
.A candidate new road has been identified which is technically feasible, economically viable; environmentally and socially responsible
2.4 Meetings
Meeting – I: Prior to commencement of feasibility/detailed engineering study a meeting was organized
on August 1, 2013, in the Project Coordination Unit (PCU) Office at DoLIDAR. Discussions were held
on work delivery, understanding of program requirements and responsibilities of the Consultant‟s
team members in general, and procedures and time frame management in particular.
Detail Engineering Survey and Design of Sankhu - Palubari - Nagarkot Road
RRRSDP-2 5
Kathmandu
Meeting – II: Likewise, on August 5, 2013, orientation meeting as a kick-off point for feasibility/detailed
engineering was held among the team members of the Consultant. Discussion on how to move
forward to accomplish the task in a systematic manner keeping in view of the limited time was done.
Also, the Team Leader drew attention of the individual professionals for carrying out the duties and
responsibilities as prescribed by the ToR of the Program Agreement for consultancy services. A need
of management support system, communication, and coordination was expressed. The participants in
this meeting were:
Meeting – III:A Meeting was arranged by ERMC on December 08, 2013. The following points were
highlighted for action:
o Collect information about household, family/settlement and water supply along the road
alignment.
o For the environmental part, only IEE can be done (no need to do EIA being rural roads).
o It should be differentiated beforehand what costs to put in IEE part and what in contractor
part.
o Include bio-engineering, demand of the community infrastructures and their costs in the
BoQ.
o Only genuine works that can be achieved should be included in the report. No
exaggeration will be entertained.
o Since all kinds of implementation plans (like Social Action Plan, Resettlement Plan,
Environmental Plan, Indigenous People Development Plan) are done for the same road
(and naturally it belongs to the same groups of people), utmost care should be taken so
that there is no duplication.
o Endangered human groups should be addressed more than the other groups.
o Utmost care must be taken while analyzing survey data and reports should be attractive,
meaningful and precise.
Orientation to Field Detailed Engineering survey Team
On November 24 an orientation and interaction session was organized at RRRSDP Office of the
Consultant by the TL in presence of PD and other senior road designers and all road and bridge
survey teams being mobilized in 18 districts. They were thoroughly briefed about survey works with
specially prepared ToR for field works for uniformity, accuracy and quality outputs.
Key points discussed:
Topography Survey and Details, Survey Codes, D-Cards, Total Station Closing & Error Distribution,
National Grids, GPS, DTM, CAD, DoLIDAR Norms, Recommended Gradients, First Meeting with
DTO/DDC and Local Concerned, Records and Report, Meeting Minuting, DoLIDAR's Letter of Jestha
1, 2070 and Letter from RRRSDP Consultant to DDCs, ID Cards, Information from Field, etc.
2.5 Meeting with Local Level Stakeholders
Local people were contacted prior to conduction of detailed engineering survey. Meeting with
DTO/DDC was also held regarding the plan of the team for the study of road sub-projects selected by
districts.
Detail Engineering Survey and Design of Sankhu - Palubari - Nagarkot Road
RRRSDP-2 6
Kathmandu
2.6 Detailed Engineering Survey, Design and Cost Estimate
I Field Team Mobilization:
Engineering team comprising of highway Engineer, geologist, Environmentalist and sub-
engineer/senior surveyor and local supervisor with other sector specialists had been mobilized in field
for detailed survey works equipped with necessary survey equipment and accessories.
Prior to conduction of detail survey Results of previous feasibility/walkover surveys were verified
FIELD SURVEY TEAM COMPOSITION
Following are the member of survey team:
1. Ravindra Thapa Team Leader/Civil engineer (9849026213)
2. Anil Aryal Surveyor
II Topographic Survey
Strip survey method was used in the field which included fixing of the base stations and taking details
15m either side for preparing a topographic map of the road strip.
Topography survey is carried out in adequate details and accuracy to prepare exact DTM of the road
alignment in 1:1000 scales. Horizontal and vertical control points are established by monument of
concrete pillar at an interval of 500m.
Initially traverse survey was carried out with high accuracy (1:70,000 to 1:148,000) to establish traverse
station and other permanent control points. Topographical details were carried out from these traverse
station to attain accuracy at higher level.
Close traverse method was applied for horizontal traversing.
1. Establishment of Control Points / Benchmarks: Permanent monument has been installed as
benchmarks (approx. size 15 cm x 15 cm x 60 cm) with 1:2:4 cement concrete nails embedded as
per the DoLIDAR standards at intervals not exceeding 500 m according to site condition. The
Control point (size 10 cm x 10 cm x 45 cm) with 1:2:4 concrete are installed at 250 m interval on
an average. Description cards are prepared for each benchmark / control point with three
reference points.
2. Traverse and Fly Leveling
The coordinates of control points is presented in NEZD (Northing, Easting, Elevation and
Description) format along with point number and remark. Closed traverse survey is carried out
to confirm the control point coordinates. All traverse angles and distances shall be double
checked with reciprocal observations. Traverse and level shall be calculated at the site
itself for accuracy and quality control and data validation. If reasonable accuracy
(1:10,000) is not achieved, the traverse shall be repeated.
3. Centerline and Cross Section Survey
a. Centerline of road is marked using Abney level by the method of chaining and pegging which
Detail Engineering Survey and Design of Sankhu - Palubari - Nagarkot Road
RRRSDP-2 7
Kathmandu
then followed by Total station survey.
b. Cross sections survey has been carried out at intervals not exceeding 10 m. Where
topographic features such as ridges and valleys are encountered, additional cross sections
taken.
c. The cross sections generally extend to 15 m either side of road centerline and extended
further whenever site demands.
d. Enough points taken at each cross-section or for each string to cover full width of the road
including roadside feature, side drain, toe of cut/fill slope retaining wall, cross drainage
structure etc.
e. Topographical survey also included individual building, utilities (water supply, electricity,
telephone poles etc.), landslides, canals, footpaths, temples, Kushmas, drainages, cross
structures, retaining structures, land use patterns and other information such as fences etc.
f. At bridge side the bank lines, lowest water level HFL, direction and distribution of flow taken.
4. Digital Terrain Model
DTM (a digital representation of ground surface topography or terrain) has been carried out using
SW–DTM or other acceptable software and verified in field. All feature lines and configurations of
existing features shall be completed in AutoCAD compatible maps. D-Cards of BM and BL, field
sketches and raw downloaded data shall be submitted together with DTM. Check of data
consistency, error distribution and adjustments shall be clearly documented. All data and records
have been submitted in digital format.
III. Hydrological study / Cross drainage Survey
Cross-drainage requirements has been assessed with identification of type requires such as bridges,
culverts, and causeways as appropriate
IV Geological Studies:
Geological observation inclusive of soil type, geology and geomorphology, slope stabilization,
vegetation, land erosion situation, landslide prone areas, gully formation, and other features have
been conducted for proper design of road.
V. Alignment Description / Inventory of Land use/Public Infrastructures
Alignment descriptions for road and other necessary features are properly recorded in detail.
Inventory of public infrastructure and land use pattern were taken with locations
VI. Material availability surveys
Material availability survey has been conducted to acquire the information on construction material.
Local rates for construction, of various items, local and imported materials, transportation charges,
etc., enquired and district rates collected for cost estimating purpose.
VII. Design drawings:
(i) The detailed engineering design and drawings is based on the data collected during detailed
engineering survey.
Detail Engineering Survey and Design of Sankhu - Palubari - Nagarkot Road
RRRSDP-2 8
Kathmandu
(ii) The detailed designs has been done or prepared by the Consultant following the DoLIDAR‟s
Nepal Rural Road Design Standards 2055 and detailed and standard drawings are prepared
as mentioned in the DoLIDAR Technical Guidelines.
(iii) The designs and drawings consist of the design profile, design cross-section plan, and other
standard/typical drawings.
(iv) Engineering technical specifications for each work item will be written taking into account
relevant standard specifications.
VIII Detailed Cost Estimate:
(i) The detailed cost estimate has been prepared using the calculated quantities and unit rates,
derived from standard applicable District Rates and DoLIDAR Work Norms.
(ii) Contract packaging will be suitably done for all subprojects, and respective bidding
documents will be prepared following the DoLIDAR practices and frameworks.
2.7 Field Verification of Design / Estimate
After the production of design drawings and cost estimate of road sub-project, joint field
verification from DTO and Consultant representative have been done to verify the result of
survey, design works with the existing ground reality and to assess whether the proposed
retaining and drainage structures are appropriate as per the field condition
Detail Engineering Survey and Design of Sankhu - Palubari - Nagarkot Road
RRRSDP-2 9
Kathmandu
3. CHAPTER-III: THE PROJECT
3.1 Project District
Kathmandu District is located in middle of Bagmati Zone of the Central Development Region of Nepal.
It borders with Bhaktapur and Kavrepalanchowk district to the East, Dhading and Nuwakot district to
the West, Nuwakot and Sindhupalchowk district to the north, Lalitpur and Makwanpur district to the
South.
According to the National Census 2011 projection, the total population of the district is 1744240
comprising 831239 female (48%) and 913001 male (52%) residing in 436344 households. Kathmandu
district has an average population density of around 4415.8 people per square km. The average
family size is 4. The average literacy rate is about 86.3%.
Kathmandu district is multi caste society where the people belong to different caste live in. The
different castes found in the district are Newar, Brahmin, Chhetri, Gurung, Tamang, Malla, Thakuri,
Damai, Kami, Sarki, etc. The common language is Nepali followed by Newari.
The district has one metropolitan city, one municipality and fifty-seven VDCs, ten constituency areas.
The total area of the district is 395 sq.kM. The district lies partly in the plain and partly in the hills. The
lowest elevation point is 1262 meter and the highest elevation point is 2732 meter from mean sea
level. The maximum temperature of the district is 32°C and minimum 2°C, annual rainfall of the district
is 176 mm. Kathmandu is the capital city of Nepal where most of the corporate offices and industries
are located. Tourism is one of the main industries of the district.
Transportation Scenario
The district has major access to the Tribhuvan Rajpath (Highway) in west part and Araniko Highway
in east part. Total 267.79 km (228.24 km Feeder and 89.55 km Highway) connects to the different part
of the district and adjoining districts. The Kathmandu outer Ring Road (39km) and Kathmandu-Terai
Detail Engineering Survey and Design of Sankhu - Palubari - Nagarkot Road
RRRSDP-2 10
Kathmandu
Fast-track (11km section) is on the planning, which will pass through majority VDCs of Kathmandu
and also linking them to the district headquarter and to other districts respectively.
The district inventory identified just over 1078.29 km of roads, including 267.79 km of strategic roads
and 713.24 km of rural roads. In coordination with the DTICC and DDC, 39 rural roads with a length of
209.52 km (excluding new construction roads of length 2.54 km) were identified as making up the
district road core network (DRCN), and the remaining 503.72 km were classified as village roads. The
existing SRN roads link up 22 VDC headquarters and existing DRCN roads connects remaining 28
VDC headquarters. The DRCN road of 82.51 km black top, 57.70 km gravel and 69.31 km earthen is
identified, which is as shown in table below:
Road Class Total Length Black Top Gravel Earthen
Strategic road networks 267.79 171.09 25.4 71.3
Urban roads 97.26 79.30 1 16.96
District road core networks 209.52 82.51 57.7 69.31
Village roads 503.72 91.25 113.62 298.85 Total 1078.29 424.15 197.72 456.42
3.2 Description of Alignment
Shankhu - Paluwari - Nagarkot Road Sector (CH: 0+000 to 10+046) is located in north-east part of
Kathmandu District. The road alignment starts from Bajrayogini VDC Ward#6, Sankhu and passes
through Sankhu, Palubari, Kattike of Suntol VDC and finally reaches to Nagarkot and Baluwapati-
Deupur VDC Ward#8 of Kavre district.
The DTMP code of this road is 27DR037.
The total length of this road is 10.046 km. The road is graveled and partially blacktopped at initial
section 0+000 km – 3+000 km and end section of 9+900 km -10+046 km and earthen surface at
3+000 km – 9+900 km. The average existing width of road is 5.50 m at ch 0+000 – ch 2+600 and
3.00 m from 2+600 to onward.
This road connects the different settlements of Bajrayogini and Suntol VDCs of Kathmandu and
Baluwapati- Deupur VDC of Kavre with core city area of Kathmandu Metropolitan City and different
strategic road networks of feeder roads.
The road is designed with a number of switch-backs to connect the river valley of Salinadi with
Nagarkot peak.
Most of the alignment passes through cultivated land with few bushes and forest areas in between.
Sankhu/Bajrayogini, Palubari, Kattike and Nagarkot are the major settlements of this road corridor.
The road starts at Sankhu, Bajrayogini#6 – historical religious place of Nepal. Initially the road follows
paddy field up to 3+300km and meets forest at 3+300km – 3+600km. The road again passes through
cultivated land at 3+600km – 4+000km and forest at 4+800km – 7+200km and meets Kattike village
at 7+200km – 7+600km and finally reaches to Nagarkot Hotel area at 7+600km – 10+046km.
3.3 Population Served & Traffic Data:
Presently the total population served by this road is 4819 benefitting people of Shankhu, Palubari and
Nagarkot. The traffic number is 125 PCU with 115 VPD.
Detail Engineering Survey and Design of Sankhu - Palubari - Nagarkot Road
RRRSDP-2 11
Kathmandu
Proposed Road
Figure 2: Showing proposed Road
3.4 Potential Area & Growth Centers
Sankhu located at Bajrayogini VDC ward no 6 is one of the most popular historical and religious place
of Nepal. Similarly, Nagarkot is well-known view point and tourist centre of Kathmandu district. The
fertile land of this hinterland can be developed as pocket area of cash crop, green vegetable and diary
production.
3.5 Project Rationale
The rationale for construction of road is as followings:
This road to joins large settlements of Bajrayogini and Suntol VDCs of Kathmandu and
Baluwapati- Deupur VDC of Kavre with core city area of Kathmandu Metropolitan City and
different strategic road networks of feeder roads.
The road will play a vital role to increase cash crop production and dairy farming in the zone of
influence area by improving access to densely populated Kathmandu Metropolitan city.
Construction of the road is expected to help the people of the area to receive better education
and quick access to medical facilities. Government‟s other services will also be delivered better
as the road will encourage government employees to visit the area and its vicinity more
frequently, or extend the duration of their stay.
It is expected to reduce the travel time considerably and thus people can utilize the saved time
for other productive works.
RRRSDP-2 12
Detail Engineering Survey and Design of Sankhu - Palubari - Nagarkot Road
Kathmandu
This will promote religious and other tourism as being located in such historical and view point
area.
The proposed road is expected not only to be an excellent facility to link several ecological,
cultural and demographic zones of the district but it will also open new possibilities for
entrepreneurs with new visions and plans. Furthermore, the road upgrading will use local
labor that will generate employment to local people and minimize emigration to other major
cities and abroad for search of work. Consequently, local people will get long-term benefit,
which will boost up their economic status within the road corridor and adjoining area
RRRSDP-2 13
4. CHAPTER-IV: GEOLOGY AND GEOMORPHOLOGY
4.1 Geological Study
4.1.1 Introduction
A geological survey has been carried out along the 10.046 km long alignment of the Sankhu –
Palubari – Katike - Nagarkot Road. Geologically the road alignment belongs to the Lesser
Himalayan rocks.
4.1.2 Regional Geology and Geomorphology
This road follows the rocks of the Sarung Khola Formation of the Lesser Himalaya. The Sarung
Khola Formation is composed of gneiss and schist. Some part of the road alignment in the valley
sediments and some part of the road alignment passes through the Lesser Himalayan rocks. There
are no any geological structures like fault and thrust along and nearby the road alignment. The road
alignment starts from Sankhu and passes through Palubari and ends at Nagarkot. There are no
major tributaries along the road alignment. The topography of along the road alignment is flat slope
to gentle slope, passes through valley sediments, residual soil, colluvial deposits after then some
part of the road alignment follows the rocky terrain of the Lesser Himalaya. The road alignment
passes through bushes and forest as well as settlements and cultivated land.
4.1.3 Surface Geology
Along the road section, the rocks of the gneiss and schist of the Sarung Khola Formation is
exposed and also covered by the residual soil with thick colluvial deposits as well as and valley
sediments.
Figure 1: Regional Geological Map of Kathmandu Area (Stocklin and Bhattarai, 1977)
RRRSDP-2 14
Kathmandu
4.1.4 Slope Stability Condition
a. Landslide and Cut Slope Failures
Less than five cut slope failures are observed which are mostly in residual and colluvial soils
deposits. The main causes of slides are precipitation, surface water condition, and undercutting
slope by road cutting. Almost all failures are occurred after opening of the road alignment. These
instabilities are found between the chainage 8+600+10+000 on hill slope. These slides are shallow
depth and can be mitigated by the arrangement of the surface drain as well as trimming of the slope
and applying the bioengineering works in the barren land on the slope. Remaining of the length of
road has good stability, because of low height cut slope. So there are no anymore failures along the
road.
b. Rock Slope Stability
Most of places in the rocky area, the orientation of the bedding plane is opposite to dipping of the
hill slope so the rocks have good slope stability.
4.1.5 Engineering Geological Mapping
The road alignment passes through slightly limestone and colluvial, residual soil deposits.
Thickness of colluvial and residual soil deposits range from 1 to more than 3 m. The natural hill
slope ranges from 5 to 65 degrees.
Figure : Stereographic Protection of the Rock Mass along Road section
The road alignment between this chainage is on residual soil and alluvial deposits and some part
on rocks of limestone. The hydrological condition of the road alignment is wet and some places wet
to dry and also seepage. The land use pattern is forest, cultivated land and settlements. After
widening of the road, there is very less chance to meet the cut slope failure due to low height cut
slope and land use pattern. The bedrocks of the Shivpuri Gneiss are exposed along the road
alignment.
RRRSDP-2 15
Kathmandu
4.1.6 Geological Hazard Mapping
Along the road, soil and rock are found low to medium hazard. The low hazardous soil covers 90%
length of the road comparing with area of the medium hazardous of soil and rock. The slope
stability of this section is good so necessity for realigning any of the subsection is not envisaged on
account of geological consideration
4.2 Construction Material Survey
Stone for structural works can be used from the places adjacent to the proposed road, within 5 km
distance in fewer quantities. Along with it existing stone soling at some sections of the road surface
can be used. For the construction purpose stone quarry is also available at Melamchi River, about
15 km far from Kattike bhanjyang. Considering these, 12 km lead is proposed for stone collection.
The excavated mass during construction can be used for filling.
Other construction materials such as GI wire, aggregates, cement and sand can be extracted,
procured or borrowed from Kathmandu valley as there are lots of crusher plant and sand collection
depot.
4.3 Land Use Pattern / VDC & Settlements
From To Land Use Pattern VDC Place
0+000 0+370 Paddy field / Sankhu bazaar Bajrayogini Sankhu
0+370 0+600 Bushes Suntol Palubari
0+600 3+300 Cultivated land Suntol Palubari
3+300 3+600 Forest Suntol Palubari
3+600 4+000 Cultivated land Suntol Palubari
4+000 4+220 Forest Suntol Palubari
4+220 4+800 Cultivated land Suntol Palubari
4+800 7+200 Forest Suntol Palubari
7+200 7+600 Settlement Suntol Kattike
7+600 10+046 Settlement Suntol Nagarkot Hotel area
4.4 Conclusions
1. About 80% road alignment passing on colluvial and residual soil deposits but 20% of the
alignment on the rocks of gneiss.
2. In the colluvial/residual soil deposits, the road alignment is influenced by the seepage and
considered high possibilities of failures. So recommended to manage the surface drain.
3. Stability condition is good in rock, but unstable area can be seen only in colluvial and
residual soil deposits, these unstable can be mitigated by simple engineering structures,
arrangement of surface drain, trimming slope and using bioengineering works.
4. The road has low soil and rocks hazard.
RRRSDP-2 16
Kathmandu
5. CHAPTER-V: HYDROLOGY AND METEOROLOGY
5.1 General
The main purpose of the hydrological studies is to evaluate the discharge across and along the proposed
road alignment due to monsoon rainfall so that appropriate drainage structures can be selected and
designed. The type, size, span and shape of cross and side drains are then fixed according to the
corresponding design discharge.
5.2 Rainfall
The proposed road lies in Kathmandu District. Rainfall stations located in this district are presented in
Table 5.1. Mean Annual Rainfall (MAR) and Monsoon Wetness Index (MWI) at these stations are obtained
from “Hydrological Estimations in Nepal”, DHM, 2004. About 80% of rainfall occurs in monsoon, which
starts around the middle of June and continues until the end of August.
Table 5.1: Summary of Rainfall Stations
Station Name
Index
No.
Latitude
Longitude
Elevation
(m)
MAR
(mm)
MWI
(mm)
THANKOT 1015 2741 8512 1630 2005 1594
KATHMANDU AIRPORT 1030 2742 8522 1337 1402 1096
SANKHU 1035 2745 8529 1449 2019 1664
PANIPOKHARI(KATHMANDU) 1039 2744 8520 1335 1504 1172
BUDDHANILAKANTHA 1071 2747 8522 1350 1962 1576
SUNDARIJAL 1074 2746 8525 1490 2894 2563
NAIKAP 1076 2741 8515 1520 DNA DNA
SUNDARIJAL 1077 2745 8525 1360 DNA DNA
NAGARJUN 1079 2745 8515 1690 DNA DNA
JETPURPHEDHI 1081 2747 8517 1320 DNA DNA
Hourly rainfall design intensities of different return periods at these rainfall stations are obtained from
“Maximum storm flood for the design of road structures of Nepal”, Prem Chandra Jha, Ph.D. Dissertation,
Moscow, 1996 and presented in Table 5.2.
Table 5.2: Hourly Rainfall Design Intensities for the proposed road
Return Period, T (years) 2 5 10 20 50 100
Hourly Rainfall Design Intensity (mm/min) 0.64 0.72 0.79 0.85 0.94 1.00
5.3 Design Discharge
The design discharge for the hydraulic design of cross and side drains of this road has been estimated by
“PCJ 1996” [Maximum storm flood for the design of road structures of Nepal]. PCJ 1996 uses hourly rainfall
design intensity (Table 5.2). Flood discharges from unit area (1 sq.km) for different return periods,
estimated by this method are presented in Table 5.3.
Table 5.3: Design Floods of different return periods by PCJ 1996
Return Period, T (years) 2 5 10 20 50 100
Design Floods by PCJ 1996 (m3/sec/km
2) 0.9 2.9 4.4 6.0 8.0 9.6
RRRSDP-2 17
Kathmandu
5.4 Cross Drains
Cross drains are mainly designed to pass the stream flows. However in some cases the cross drains are
provided to divert the flows coming from side drains. Following steps are followed for locating cross drains:
Identifying stream points and valley curves in topographical map
Verifying these locations during field visit and survey
Locating finally after study of designed plan and profile of the road
Following design criteria are adopted for the design of cross drains after hydrological analysis:
Design flood frequency: 20 years
Design intensity: 0.85 mm/min
Design flood: 6.0 m3/sec/km
2
The design discharge for a cross drain is a high flow corresponding to the selected return period. In order to
economize on construction costs, frequency of flood is selected for return periods, depending upon the
importance of the structure. For this road, it is recommended to design the cross drains for 20 years return
period flood.
The drain size varies based on the design discharge. The design discharge for each drain is different. It
means there will be many sizes of cross drains in a road. For crossing of small streams, rivulet and springs
not carrying debris pipe culvert is good option. It is not practicable even not economical to construct pipe
culvert of many sizes. Hence it is decided to use pipe culverts of 60, 90 and 120 cm for crossing the drains.
By experience, the 60 cm diameter pipe is not recommended for cross drains because of choking and
clogging by sediment and debris coming from upslope of mountain catchments. However it can be used for
crossing of irrigation channel, road intersection and flow with low discharges. The 120 cm diameter pipe
should also be avoided due to the difficulties of handling and transporting. In most of the places where
seasonal waterways occur in the monsoon and for flash flood, stone or concrete causeways are
recommended.
The hydraulics of pipe culverts is worked out in Table 5.4. Maximum flow capacity and velocity are
determined at a suitable head. The design discharge of a crossing is compared with flow capacity of a pipe
and then size is fixed from standard pipe sizes.
Table 5.4: Hydraulics of proposed cross drains (pipe culverts)
CD type
Size
(m)
Full
flowing
area, m2
Max.
design
slope, %
Length
of
CD, m
Max.
Head
loss, m
Friction
coeff.(f)
Max.
Velocity,
m/sec
Max.
flow,
m3/sec
Pipe culvert 0.60 0.28 3 6 0.18 0.05 2.66 0.74
Pipe culvert 0.90 0.63 3 6 0.18 0.05 3.26 2.05
Pipe culvert 1.20 1.12 3 6 0.18 0.05 3.76 4.21
Table 5.4 gives an idea of maximum flow capacity and velocity of proposed pipe culverts so as to define the
proper size of the culvert based on design discharge coming to a culvert. The maximum design slope for
these culverts is assumed as 3% so as to create self flushing velocity. Table 5.4 shows the full flow
capacities, head losses and the design slopes for different pipes. Head losses are calculated by Darcy -
Weisbach formula for pipe flow. The coefficient of friction (f) for concrete pipe in this formula is assumed as
0.05. The maximum velocity at exit point for all size of pipes shall be maintained by providing an apron. The
length of pipe in average is assumed to be 6 m.
For medium size streams where flow more and carrying boulders, pebbles and gravels and span is up to 6
m, box or slab culvert are recommended. The actual span of these culverts is fixed according to field
survey. For larger streams bridges of suitable span based on field survey are recommended.
RRRSDP-2 18
Kathmandu
The list of proposed cross drains is provided in Annex 4.
5.5 Side Drains
Side drains are recommended for catching the flows from road surface and upside adjoining areas. In some
stretches side drains exist but most of the side drains will be occupied by new design width of the road and
hence new side drains are proposed along the full length of this road. The design discharge for a side drain
is a high flow corresponding to the selected return period. In order to economize on construction costs,
frequency of flood is selected for return periods, depending upon the importance of the structure. For this
road, it is recommended to design the longitudinal side drains for 5 years return period flood. Following
design criteria are adopted for the design of side drains after hydrological analysis:
Design flood frequency: 5 years
Design intensity: 0.72 mm/min
Design discharge: 2.9 m3/sec/km
2
Table 5.5 shows the maximum flow capacity and velocity of side drains at maximum longitudinal slope of
10% and having full flowing area. The side drains must follow the longitudinal slope of the road and in most
of the cases hill road has a maximum slope of 12%. Cross sections of proposed side drains types (A, B &
C) are presented in Figure 5.1.
Table 5.5: Flow capacity of proposed side drains at maximum slope of 10%
Drain Type b, m d, m A, m2 P, m R, m n S V, m/s Q, m
3/s
Tick Drain [A] 0.8 0.3 0.12 1.154 0.104 0.016 0.10 4.34 0.52
Tick Drain [B] 0.8 0.45 0.18 1.368 0.131 0.016 0.10 5.07 0.91
Trapezoidal Drain [C] 0.45 0.45 0.2025 1.31 0.155 0.016 0.10 5.66 1.15
As the design discharge is less than 1.5 m3/sec/km
2with medium intensity of rainfall, tick type drain of
concrete masonry [Type B] having medium draining capacity is recommended for this road. It is also
recommended that the length of side drain should not be more than 300 m. Hence a cross drain of 90 cm
diameter is proposed to cater the discharge of side drain at 300 m interval.
Figure 5.1 Proposed types of Side Drains
5.6 Selection of Cross-drainage Structures Type
Pipe culverts:
RRRSDP-2 19
Detail Engineering Survey and Design of Sankhu - Palubari - Nagarkot Road
Kathmandu
Pipe culverts are proposed in areas where the discharge is concentrated and at intersection points
of vertical gradients. Vehicular access to the construction site is necessary for transportation of the
pipe.
The minimum culvert size proposed is 600 mm diameter. The minimum size was selected to lessen
the risk of the blockage and make it easier to clear blockages once they occur. The maximum size
was selected in consideration of the difficulties of handling and transporting larger size pipes during
construction.
Floodway
In consideration to the road design standards floodways will be preferred over large culverts.
Floodways will be cheaper to construct and will be more likely to accommodate flood events outside
the 10-year design period without damage.
Slab culverts
Slab culverts will be preferred for cases where the topography would make construction of a
floodway difficult.
RRRSDP-2 20
6. CHAPTER-VI: GEOMETRIC STANDARDS & DESIGN
Geometric design standard of Nepal Rural Road Standard (2055) with 1st
revision of September 2012 with
District Road Core Network class have been followed while carrying out detailed engineering survey and
design of RRRSDP-2 roads proposed for improvement, upgrading and new construction. Work Norms and
specification of DoLIDAR in general and Norms for Rate Analysis as per Standard Specification for Road
and Bridge Works for specific items is followed for cost analysis of sub-projects and preparation of contract
packages.
6.1. Road Classification
Project roads fall under the category of District Road Core Network as per Nepal Rural Road Standard -
2055 (Revised-2071, December 2014) as it connects village headquarter with strategic road network and
District headquarter. 6.2. Design Standard
6.2.1. Design Speed
The sight distance, radius of horizontal curve, super elevation, extra widening of pavement, length of
horizontal curve and the length of vertical curve (summit and valley) depend on the design speed, which in
turn depends on class of road and nature of terrain. According to the design standards, the design speed
for hill terrain is 25 km/hr and minimum is 20 km/hr.
6.2.2. Geometric Design
The technical standards are set considering minimum initial investments with the scope for gradual
upgrading. The roads can be upgraded in a compatible manner as the traffic volume increases and
availability of resources justify additional inputs.
The design standards / parameters adopted for the sub-project follow DoLIDAR Rural Road Design
Standards, DRCN.
HORIZONTAL ALIGNMENT
6.2.3. Horizontal Curvature
The purpose of introducing curves is to deflect a vehicle traveling along one of the straight, safely and
comfortably, through the angle (deflection angle), to enable it to continue its journey along the other
straight.
A horizontal curve serves for change in direction to the centerline of a road and safe turning to the vehicles
in horizontal plane.
6.2.4. Super Elevation
Super elevation is provided to maintain the design traffic speed at a given radius.
Coefficient of Lateral Friction (f)
RRRSDP-2 21
Design Speed kM/hr Recommended Minimum Radius ,m Super elevation e =10% Super elevation e = 7 %
15 10 20 12.5 25 20 30 30
Kathmandu
The value of the coefficient of lateral force depends basically upon vehicle speed, type and condition of
road type and surface as well as the condition of tyresThe factor affecting the coefficient(I) 'f' is adopted as
per IRC recommendation i.e. if the value of 'f' = 0.15,is adopted, the passenger shall not feel discomfort.
Maximum Super Elevation Value
In plain terrain, non-motorized vehicles travel with high centre of gravity, so the maximum value of super elevation shall be limited to the following values;
Terai 7%
Hill 10%
The designer should aim at providing flatter super elevation but it should not be less than the camber.
Super-elevation is defined as the raising of the outer edge of the road or track along curves. It will reduce
effect of radial force on the vehicle.
6.2.5. Minimum Radius of Curvature
On a horizontal curve, the centrifugal force is balanced by the effects of super elevationand side friction. The following formula fulfils the condition of equilibrium:
e + f = V2/127R
or
R= V2/127(e + f)
Where,
V = Vehicle Design Speed, km/hr
R = Radius, m
e = Super elevation ratio, meter per meter.
f = Coefficient of side (lateral) friction between the vehicle tyres and pavement. A constant value of coefficient
of side friction is adopted at 0.15.
The recommended minimum radius value is tabulated in Table 10.1
The recommended minimum radius value is tabulated in Table below:
Table Minimum Radius for Horizontal Curve
For the section of the road where difficult site conditions are in predominance, the minimum radius of
horizontal curves adopted are ruling minimum of 15 m and absolute minimum radius of 12.5 m is provided.
6.2.6. Widening on Curves
At sharp horizontal curves, it is necessary to widen the carriageway to provide safe passage of vehicles.
Widening is dependent on curve radius, width of carriageway and type of vehicle (length and
RRRSDP-2 22
e
Kathmandu
width).Widening has two components: (1) mechanical widening to compensate for the extra width occupied
by the vehicle on the curve due to tracing of the rear wheels, and (ii) psychological widening vehicles in a
lane tend to wander more on a curve than on a straight reach.
In single lane roads the outer wheels of vehicles use the shoulders whether on the straight or on a curve.
Therefore use of the mechanical component of widening should be sufficient on its own.
For single lane roads, only mechanical widening is required for low traffic speed.
W = (L2/ 2R)
Where, We= extra widening
N= number of traffic lanes
L= length of wheel base (6.1 m)
R= radius of curve
The recommended increase in width is given in Table below
Table: Recommended Minimum Widening for Single Lane Road
Curve Radius (m) Up to 20 21-60 Above 60
Increase in width ( for 3 m carriageway),(m)
1.5
0.6
Nil
Increase in width ( for 3.75 m
carriageway),(m)
0.9
0.6
Nil
6.2.7. Stopping Sight Distance (SSD)
Visibility is an important requirement for the safety of travel on the roads. For this it is necessary that sight
distance of adequate length should be available in different situations to permit drivers enough time and
distance to control their vehicles so that the chances of accident are minimized. The stopping sight
distance is the clear distance ahead needed by a driver to bring his vehicle to a stop before collision with a
stationary object in his path and is calculated as the sum of braking distance required at a particular speed
plus the distance travelled by the vehicle during perception and brake reaction time (lag distance).Total
reaction time of drivers depends on a variety of factors and a value of 2.5 seconds and coefficient of
longitudinal friction varying from 0.40 for 20 km/hr to 0.35 for 100
km/hr. Stopping Sight Distance (Ds) shall be:
Ds = 0.278Vt+ V2/254f
Where,
Ds = Stopping Sight Distance, m
V = Speed, km/hr
t= Perception and Brake Reaction Time, seconds (2.5 seconds)
f = Coefficient of Longitudinal Friction (Varies as speed varies)
RRRSDP-2 23
Kathmandu
The Safe Stopping Site Distance is provided in Table below.
Table :Safe Stopping Site Distance
Speed, kM/hr Perception and Brake Reaction Time, t (Sec)
Coefficient of Longitudinal Friction
Safe Stopping Sight Distance ,m
15 2.5 0.40 15 20 2.5 0.40 20 25 2.5 0.40 25 30 2.5 0.40 30 40 2.5 0.38 45
VERTICAL ALIGNMENT
All vertical curves are suggested simple parabolas according to the Nepal Road standards. Vertical curves
are unavoidable due to drainage problems and topography of project area. This road project is located in
hilly terrain so vertical curves are designed according to the Nepal Road standards.
6.2.8. Gradient
The selection of ruling gradient depends on several factors such as type of terrain, length of the grade,
speed, pulling power of vehicles and presence of horizontal curves.
Recommended gradient for different terrain conditions are given in Table below:
S.No
Design Standard
District Road (Core
Network)
Hill
Terai
1
Ruling gradient (%)
7
5
2
Limiting gradient (%)
10
6
3
Exceptional gradient (%)
12
7
4
Limitation of maximum gradient length (m) above
average gradient of 7%
300
-
5
Maximum recovery gradient (%) to be applied after
gradient in excess of 7% for a minimum recovery
length of 150 m
4
-
6
Maximum gradient at bridge approach (%)
6
5
7
Minimum gradient on hill roads (for better drainage)
(%)
0.5 (max 1%)
-
However in case of existing roads it is very difficult to maintain the longitudinal gradient within the design
limit throughout because of several factors. Among them following are some examples:
There can be unnecessarily heavy box cutting for very long stretch if we don't escape from
keeping the design grade for short stretch in some sections. This means adopting more
gradient in some short section will save heavy cut/ fill for long stretch.
RRRSDP-2 24
Case Length of Summit curve (m)
For safe stopping sight distance
When the length of curve exceed the required L = (N*S2)/(1.5 + 0.035 S)
Kathmandu
Changing the existing alignment may not prove practical every time for the improvement of
gradient. Hence, keeping high gradient for short stretch may resolve the issue of
resettlement and other social dispute that may result from realignment
Most of the existing roads are found non engineered road in terms of gradient. Hence,
some section need steeper gradient, also because to maintain the relief gradient in hair-
pin-bend and other structures.
It is not wise to destroy or ruin the stable and normal road sections in the cost of improving
problematic part without logical justification.
The problems that consultant faced during survey and design of road is to maintain the design gradient as
the existing road was with steep gradient. The consultant has tried to realign the road wherever possible. A
separate investigation had been made to explore the possibility of grade improvement after that carried out
re-survey in some sections also.
Vertical curve
Vertical curves are introduced for smooth transition at grade changes. Both summit curve and valley curve
should be designed as parabolas. The length of vertical curves is controlled by sight distance
requirements, but curves with greater lengths are aesthetically better.
6.2.9. Summit Curves
The length of summit curves is governed by the choice of sight distance. The length is calculated on the
basis of the following formulae
Case Length of Summit curve (m)
For safe stopping sight distance
When the length of curve exceed the required
sight distance (i.e., L>S ) L = (N*S
2)/(4.4)
When the length of curve is less than the required
sight distance (i.e., L< S )
L = 2S – (4.4)/N
N = deviation angle, i.e. the algebraic difference between the two grade
L = Length of parabolic vertical curve (m)
S = stopping sight distance (m)
The above formula has been derived based on the following assumption
Height of driver's eye (H) = 1.2 m (above the pavement surface)
Height of subject above the pavement surface = 0.15 m
6.2.10. Valley Curves
The length of valley curves should be such that for night travel, the headlight beam distance is equal to the
stopping sight distance. The length of curve may be calculated as follows:
RRRSDP-2 25
Kathmandu
sight distance (i.e., L>S ) When the length of curve is less than the required
sight distance (i.e., L< S )
L = 2S – (1.5 + 0.035 S)/N
Where,
N = deviation angle, i.e the algebraic difference between the two grade
L = Length of parabolic vertical curve (m)
S = stopping sight distance (m)
The above formula has been derived based on following assumption
Head light height = 0.75 m
The beam angle = 10
6.3. ROAD CROSS- SECTION
Following road width and other cross-sectional features have been adopted in design of RRRSDP-2 roads.
Figure: Single Lane Road with drain in Hill area of District Road – Core Network
Carriage way width in passing bays = 5.5 m
Roadway width in passing bays = 7 m
RRRSDP-2 26
Kathmandu
Fig District Road - Core Network, Single Lane Road in Terai
6.3.1. Cross Section Design
The cross section design was carried out taking plan and profile under consideration. For embankment
areas, the side slopes of 1.5 H : 1 V are adopted and side slopes in cutting varies based on soil
classification.
6.3.2. Shoulder Width
According to the DoLIDAR Standard the Shoulder Width is 0.75 m either side adopted.
6.3.3. Carriageway Width
According to the NRRS this road adopted carriageway width 3.75 m.
6.3.4. Formation Width
Roadway width of 5.25 m which includes carriageway and its shoulder width and formation width of 6.25 m
including drain has been proposed..
6.3.5. Right of Way
Total right of way for this road section is 20 m (10 m either side of the road).
6.3.6. Camber
Recommended camber cross slope on straight road sections is given in Table below.
Camber
District Road (Core Network)
Village Road
Hill
Terai
Hill
Terai
Carriage way cross slope
Earthen (existing)
5
5
5
5
RRRSDP-2 27
Kathmandu
(%)
Gravel
4
4
4
4
Bituminous Seal Coat
3
3
-
-
Unpaved shoulders on paved carriageway should be at least 0.5 per cent steeper than the cross fall of the
carriageway. However, 1 per cent more slope than the carriageway is desirable.
6.3.7. Pass Bay
The increased width at passing zones should allow two trucks (2 axles) to pass. The width of carriage way
should be 5.5 m and length about 12 m along the outside edge and 30 m along inside. This means that
passing zones and lay bys should be tapered gradually towards the carriageway so that vehicles can leave
or join the traffic stream safely. At passing places, vehicles would be expected to stop or slow to a very low
speed.
Normally, passing place should be located every 300 m for Hill and 500 m for Terai. The location of
passing place depends on the sight distance and should be provided at or near blind and sharp summit
curves; where the likelihood of vehicles meeting between passing places is high and where reversing
would be difficult. In general passing places should be constructed at the most economic location as
determined by the terrain and ground condition, such as at transitions from cut to fill, rather than at precise
intervals.
6.3.8. Carriageway width at culvert/ bridge
The recommended carriageway width at culverts and for Single lane is 4.25 m and Intermediate lane 6m.
Width is measured from between parapet walls or Kerbs and additional width for footpath can be
considered as per site requirement and volume of pedestrian flow.
6.3.9. Level of road embankment above HFL
In flat terrain the road embankment should be high enough so that the level of sub grade is above the
highest flood level (HFL). HFL at site can be found from inspecting the site and local enquiry. Minimum
recommended level of sub grades are given below for district road (core network) 1 m desirable but
minimum is 0.5 m for village road 0.5 m (minimum)
6.3.10. Lateral Clearance
Lateral clearance between roadside objects and the edge of the shoulder should normally be as given below: Hill road - normally 1.0 m but may be reduced to minimum 0.5 m in steep and difficult areas and where the cost of providing the full clearance is high.
6.3.11. Vertical Clearance
A vertical clearance of 5 m should be ensured over the full width of roadway at all underpasses, and
similarly at overhanging cliffs. The vertical clearance should be measured with reference to the highest
point of the carriageway i.e. the crown or super elevated edge of the carriageway. However, in the case of
overhead wires, poles etc. clearance shall be at least 7.0 m above the road surface.
6.4. Cut / Fill Batter Slopes
Cut/fill slope designs are normally based on geo-technical parameters, such as soil and rock properties,
terrain slope, water tables and height of cut slope.
RRRSDP-2 28
Kathmandu
The cut slope gradient should be between 1:0.3 (V: H) and 1:1.5 depending on subsurface conditions and
other characteristics. Attention shall be paid to the geological condition of the slope prior to cutting of the
slope.
As a rule, cutting and removal of soil mass should be performed from upper to lower portion to maintain
the slope stability. Cutting work should be carried out during dry season. The final cut slopes should be
treated with adequate drainages, slope protection works and/or bioengineering works to increase stability
against effects of rainfall and infiltration of water.
7. CHAPTER-VII: ENVIRONMENTAL MITIGATION MEASURES
As per Environmental Protection Act 2053 and Environmental Protection Regulation 2054 Initial
Environment Examination (IEE) is mandatory for all kind of District and Rural roads and hence IEE are
conducted for each sub-project to investigate the possible environmental impacts during and after
implementation of project in socio-economic & cultural aspects, biological and physical sectors of proposed
road influence zone.
Detailed Cost estimate of environment management plan to mitigate and safeguard the adverse impacts
will be prepared separately and be incorporated as civil works item in Bill of Quantity of bidding document.
In general the provision of bioengineering is made in this estimate. In order to discourage uncontrolled cut
and throw of spoil mass a separate item of transportation of excess mass from roadwork has been
introduced in detailed estimate for mass management. EMP will cover rehabilitation of public
infrastructures and will address to slope stabilization work. However mitigation of adverse environmental
impact should be began right from feasibility, alignment study and design phase. Following are some
attempts that the consultant has tried to address to minimize environmental impact during its planning
phase.
7.1. Consideration Made in Alignment Selection, Survey and Design Phase
Following attempts and considerations have been made during detailed engineering as part of
environmental mitigation measures in planning phase:
i. Road alignment selection that avoids landslide-prone and geological unstable areas, sensitive
ecosystems, and important cultural and religious sites;
ii. Road alignment selection that avoids large scale cutting and filling and that is based on mass
balancing;
iii. Proper design of cut slopes to minimize possibility of destabilization;
iv. Provision of suitable drainage facilities utilizing discharge to natural drainage channels;
7.2. Drainage Outlet Protection Works
Construction of side drain and culverts and other drainage work (for quick drain out the surface run-off)
alone is not always enough for water management. The possible erosion and gulley formation inclusive of
damage of cultivated land and other private property is common at outlet of culverts. That is why there is
always dispute with local farmers regarding the location of cross-drain during construction works. Keeping
RRRSDP-2 29
Kathmandu
view of these, different types of outlet protection works have been designed and proposed in the cost
estimate as one of the mitigation matter of adverse environmental impact.
7.3. Selection of Slope Protection Work
In general, following points are considered while planning a slope protection work:
Use of bio-engineering on all exposed cut and fill slopes, weak and fragile zone and on completed
spoil tips to minimize subsequent erosion. Tentative cost estimate for the bio engineering work has been
calculated and provisioned this report but now it is excluded from the current contract package.
Implementation of Bio engineering works will be carried out after detailed field verification during the
implementation of project. The site in which bioengineering application is required will be identified then
priority to implement will be given to local Users Committees mobilizing forest groups and Mothers Groups
(if available). Small Contractor having specific experience of bio engineering works will be another option.
Water management structures as an essential factor for quick and effective drainage of surface
run-off have been introduced. Side drain and other cross drainage structures have been selected and
determined keeping view of nature and characteristics of gullies, stream and spring.
Restrain measures such as retaining wall and structures like gabion wall and stone masonry have
been provided to retain the fill mass and for prevention of toe failure.
7.4. LIST OF SOME ENVIRONMENT PROTECTION WORKS:
As per findings of field investigations following environmental protection measures have been proposed in
design and estimate of roadwork.
S. No. ENVIRONMENT PROTECTION MEASURES 1 Provision of spoil mass transportation up to nearby tipping sites
2 Shifting of Electric poles, water supply pipelines etc from roadway to safe sites
3 Bioengineering works along with small slope protection civil structures
4 Rehabilitation and reconstruction of irrigation canals
5 Inlet and outlet protection works of cross drainages, culverts to mitigate the damage to
cultivated land, private property etc
6 Provision of breast walls in potential and existing landslide area
7 Proper drainage management to protect the road and roadside slope from adverse effect of
accumulated water
Detail Engineering Survey and Design of Sankhu - Palubari - Nagarkot Road
RRRSDP-2 30
Kathmandu
8. DETAILED ENGINEERING DESIGN
8.1 Design Method
Design of the road was carried out by SW_ROAD 2006 and SW_DTM 2006 computer software developed by SOFTWEL (P) Ltd, Nepal. Design was carried out using strip survey method so that alignment could be optimized as per requirement. The design works are based on the Digital Terrain Model created from the 3D points captured through the detailed survey.
Centerline was generated using the design environment and accordingly the profile and cross- sections were generated. Through an interactive design environment, the centerline (plan and profile) is optimized by adjusting the cross-sections.
8.2 Review & Redesign
Attempts have been made to minimize the cut/fill volume of earthwork and unnecessary stuff of structures.
Once the computer designed plan and profiles printed, the profiles were thoroughly reviewed and
redesigned wherever necessary to optimize the design and to keep it in right track within the norms and
standard. Necessary adjustment has been made in difficult areas where to follow the design standard is
likely not justifiable and impractical.
8.3 Design & Drawings
(v) The detailed engineering design and drawings is based on the data collected during detailed
engineering survey.
(vi) The detailed designs has been done or prepared by the Consultant following the DoLIDAR‟s Nepal
Rural Road Design Standards 2055 (with 2nd Revision of December 2014) and detailed and
standard drawings are prepared as mentioned in the DoLIDAR Technical Guidelines.
(vii) The designs and drawings consist of the design profile, design cross-section, plan and other
standard/typical drawings.
8.4 Horizontal Curve Design
The horizontal curve design table along with different features and parameters of horizontal alignment has
been presented in annex and in drawings.
8.5 Design of Structures and other geometric Features
The list of retaining and cross drainage structures extracted from detailed design output is presented in
annexes. Similarly, the standard drawing represents the adopted design standard of road cross-sections.
The list of passing bays is also attached in annex.
8.6 Pavement Proposed
The pavement is based on CBR values taken from DCP-CBR correlation chart. This Sankhu– Paluwari-
Nagarkot Road is proposed with blacktopping with gravel sub-base and base of graded crushed stone
aggregate materials. The road pavement structure is designed as follows:
Detail Engineering Survey and Design of Sankhu - Palubari - Nagarkot Road
RRRSDP-2 31
Kathmandu
Road Pavement Structure Design Calculation for the Sankhu - Paluwari - Nagarkot Road
under RRRSDP-2
Traffic growth rate(r) = 5% (assumed for rural road)
The accuracy of design will also depend very largely on the accuracy of traffic prediction over the chosen
life of 15 years. According to IRC and Road Note 29, it suggests to take a normal traffic growth rate of 4%,
but in Nepal from its past trends traffic growth rate of 5% for rural roads is appropriate though „Flexible
Pavement Design Manual- 2070‟ by DoR suggests to use a traffic growth of 7% for strategic (SRN) roads.
And the type of pavement selection will depend on not only projected traffic volume but also economic
considerations as well.
Design period (n) = 15yrs
The projected traffic volume of 15 years includes the construction years (the road being upgraded traffic
growth will continue to grow during construction as well and the road cannot be fully closed during
construction).
LDF (Load Distribution Factor) = 0.75 (for 2 lane road)
According to latest traffic count done by RRRSDP-2 on Sankhu - Paluwari – Nagarkot Road the recorded
traffic volume per day is 115 VPD and this value converted to Passenger Car Unit (PCU) shows only 125
PCU only. Equivalency factor used for converting the commercial vehicles (bus, trucks, tractors) to PCU
Is 3 for Bus up to 40 passengers & Minibus and similarly for Truck up to 10 tones gross weight is also 3.
Since the values of VDP and PCU are closer we can assume 17~ 20% of PCU as number of buses and
mini buses and 8~10% of PCU as trucks plying on the road. Because the loads imposed by cars and light
vehicles do not contribute significantly to the structural damage caused to road pavements by traffic. For
the purpose of structural design, therefore, only the numbers of commercial vehicles having unladen
weight exceeding 1500 kg and their axle loading are considered.
Now, assume number of buses (8ton) =25, say (@20%of125PCU)
Assume number of trucks (10ton)=13,say(@10% of 125 PCU)
Cumulative Equivalent Standard Axles (ESA) at base year= (A*VDF) = (Number of traffic x vehicle
Damage factor, which taken as 0.91for bus and 2.5for truck as per Overseas Road Note (ORN) 31.
NB: It can be calculated using, VDF = (Axle load (kg)/8160) ^4.5)
A*VDF =25x0.91+13x2.5=22.75+32.5=55.25 ESA/ day
So, the cumulative number of 8160kg (82KN) equivalent standard axle over design life is calculated as
Detail Engineering Survey and Design of Sankhu - Palubari - Nagarkot Road
RRRSDP-2 32
Kathmandu
follows:
Numerically, Ns = [365*[(1+r)^n-1] *(A*VDF)*LDF]/r
VDF = Vehicle damage factor = multiplier to convert the number of commercial vehicles of different axle
loads & configuration to the number of standard axles load repetitions. It is defined as the equivalence
factor of standard axles per commercial vehicle.
Ns= [{365*{(1+0.05)^15-1}*(55.25)*0.75}]/0.05=[{365*1.079*55.25*0.75}]/0.05=326390.76 ESA =
0.326,391 Million Standard Axle (msa). However with the upgrading of roads the additional traffic may be
attracted or diverted on this road from other ends coming from Bhaktapur and Sindhupalchok districts. In
absence of traffic count data, it is proposed to increase the above value by 50%.This makes the design
traffic value as 1.5*0.326391= 0.4896 msa. See Map below to have an idea of traffic diversion or attraction
possibility.
Hence as per ORN 31, this traffic falls into ClassT2 (0.3msa to 0.7msa).
RRRSDP-2 33
Detail Engineering Survey and Design of Sankhu - Palubari - Nagarkot Road
Kathmandu
Sankhu –Palubari–Nagarkot Section
Detail Engineering Survey and Design of Sankhu - Palubari - Nagarkot Road
RRRSDP-2 34
Kathmandu
Therefore, referring to ORN 31 again the pavement thicknesses for granular road-base materials
with this traffic class T2 and sub grade strength classes based on the range of CBR values as
shown below in the Table in different sections figure out to as follows:
Table: Summary of the Dynamic Cone Penetration Test (DCP) Test Results Showing CBR Values in Different Sections of Sankhu- Paluwari- Nagarkot Road under RRRSDP-2
S.N. Chainage Depth of Layers in cm CBR
Valu e in
%
Sub-grade Strength Classes for Design as per ORN31
Granular Base
Course (BC) and
Sub-base Course
(SC)Thicknesses in
mm with Surface
Dressing (SD)
Refined** &
Recommended
Thicknesses of
BC
& SC***In mm
Remarks
1
0+000
0.0-13.9
17.8
S4
BC=150
SC=175
BC=100
SC=175
30 mm
Asphalt
Concrete
(structural
surface)=@ 50 mm of BC
13.9-59.5
7.8
59.5-62.7
Very
high due
to rock soling
BC=100
SC=150
BC=100
SC=150
Provided
minimum
Thicknesses
of BC&SC
2
0+500
0.0-33.0 6.8
S3
BC=150
SC=250
BC=150
SC=250
50 mm BC
reduced to
take
Care by 30
mm strength
contributing
33.0-38.4 6.1 38.4-71.6 4.8
71.6-100.0
10.8
3
1+000
0.0-44.0 7
S3
BC=150
SC=250
BC=100
SC=250
44.0-49.0
9.5
49.0-97.3 4.2
4
1+500
0-23.4 7.8
S3 (For
getting very high value)
BC=150
SC=250
BC=100
SC=250
23.4-28.0 53.4
28.0-100.0 4.4
5
2+000
0.0-12.0 23.3
S5
BC=150
SC=100
BC=100
SC=150
Minimum
thickness of
SC should be
150 mm as
per ORN.
12.0-28.1 76.7 28.1-36.1 29.9
36.1-63.5
26.3
6
2+500
0.0-30.5 33.9
S4
BC=150
SC=175
BC=100
SC=175
30.5-43.5 16.1 43.5-100 4.8
7
3+000
0.0-21.0 8.1
S4
BC=150
SC=175
BC=150
SC=175
21.0-33.3 24.1 33.3-42.6 15.6
42.6-100.0 6.2
8
3+500
0.0-32.5 8.8
S4
BC=150
SC=175
BC=150
SC=175
32.5-53.5 19.8
53.5-100.0 6.7
9
4+000
0.0-16.9 70.3 BC=100
SC=150
BC=100
SC=150
Provide
minimum
thickness of
16.9 to Below
High due
to rock
Detail Engineering Survey and Design of Sankhu - Palubari - Nagarkot Road
RRRSDP-2 35
Kathmandu
soling BC and SC
10
4+500
0.0-19.6 109.2
BC=100
SC=150
BC=100
SC=150
Provide
minimum
thickness of
BC and SC
19.6 below
High due
to rock
soling
11
5+000
0.0-12.5 37.8
BC=100
SC=150
BC=100
SC=150
Provide
minimum
thickness of
BC and SC
12.5-13.0 54.6 13.0-44.1 56.6
44.1 below
High due
to rock
12
5+500
0.0-27.0 46.6
BC=100
SC=150
37.0-31.3 85.3
31.3 below
High due
to rock
13
6+000
0.0-12.2 11.2
S3
BC=150
SC=250
BC=100
SC=250
12.2-68.6 3.1
68.6-100.0 5.2
14
6+500
0-11.0 71.1
S5
BC=150
SC=100
BC=100
SC=150
11.0-24.0 30.2 24.0-100.0 6
15
7+000
0.0-20.6 15 S4
BC=150
SC=175 BC=100
SC=175
20.6-98.9 5.5
16
7+500 0.0-23.6 28.6
S5 BC=150
SC=100 BC=100
SC=150
23.6-96.9 6.6
17
8+000 0.0-28.0
29.1 S5
BC=150
SC=100
BC=100
SC=150
28.0-39.6 54
18
8+500 0.0-17.1 31.1
S5 BC=150
SC=100 BC=100
SC=150
17.1-49.0 14.8
19
9+000
0.0-100.0
7.7
S4 BC=1500
SC=175 BC=100
SC=175
20
9+500
0.0-27.0
21.6
S3 for 4.1
CBR and S6 for higher
values shown
BC=150
SC=250
BC=100
SC=250
27.0-34.5 4.1 BC=100
SC=150
for higher CBR
34.5-46.9
36.2
21
10+000
0.0-10.7 58.2
S5
BC=150
SC=100
BC=100
SC=150
10.7-43.6 41.4 43.6-63.3 15.9
NB1: *SD=Surface Dressing= a wearing coat like 30 mm thick open graded Premix or Asphalt Concrete or single /double bituminous surface treatment (SBST/DBST).So it is basically meant for protection of road surface from changes in moisture and abrasion by traffic and pavement under layers and it is not normally taken into account when determining the structural thickness of the pavement.
NB2:** BC =It is to be noted that in all RRRSDP-2 roads 30 mm thick closely graded aggregates (max. nominal size should be little less than half of the total compacted design thickness) blacktopped premix carpet is provided. So, it cannot only protect but also add structural strength to take load and disburse traffic loads down to sub grade. So its thickness is additional strength and plus point and can be included as structural thickness. We propose to substitute 30 mm of Asphalt Concrete in 100 mm of base course.
NB3:***SC= According to IRC Flexible Design Procedure or Road Note 29 & 31,it is recommended that the minimum thickness of sub-base should be 150mm (15cm) for design traffic less than 1.0 msa.
Detail Engineering Survey and Design of Sankhu - Palubari - Nagarkot Road
RRRSDP-2 36
Kathmandu
Asphalt Concrete Plants are easily available in Kathmandu; diverted traffic to this road will be increased significantly after
completion of this road, Construction Procedure and Quality Control for Asphalt Concrete work will be comfortable
30 mm thick Asphalt Concrete pavement to Sankhu- Palubari- Nagarkot road has been proposed due to following reasons
diverted traffic to this road will be increased significantly after completion of this road,
Asphalt Concrete Plants are easily available in Kathmandu
Construction Procedure and Quality Control for Asphalt Concrete work will be more comfortable to DTO
since DTO technicians have considerable experience of premix carpeting during RRRSDP phase 1
implementation.
The cost of DBST per km is calculated about 2.2 million while the cost of asphalt concrete of 30 mm thickness is about 2.6
million. Though cost of Asphalt Concrete is slightly high than DBST, considering the benefits listed above, Asphalt
Concrete for wearing course is recommended.
8.7 Field Verification of Design / Estimate
After the production of draft/design drawing a field visit have been made to review and explore the possibility of
improvement of existing steep gradient.
Similarly, after the production of revised design drawings and cost estimate of road sub-project, joint field
verification from DTO and Consultant representative have been done to verify the result of survey, design
works with the existing ground reality and to assess whether the proposed retaining and drainage structures
are appropriate as per the field condition.
Detail Engineering Survey and Design of Sankhu - Palubari - Nagarkot Road
RRRSDP-2 37
Kathmandu
9. CHAPTER-IX: COST ESTIMATE
9.1. Summary
The total estimated construction cost for upgrading of Sankhu – Palubari - Nagarkot road is summarized
in the Table below, which does not, include compensation for building and land.
S. No.
Road Name Length Km
Cost Estimate NRs
Cost per km
1 Sankhu – Palubari -
Nagarkot road
10.046 NRs. 232,716,449.2
Includes contingency
and VAT
NRs. 19,968,311.16
Excludes Contingency and VAT
The details of the cost estimation are provided in Volume II of this report
9.2. Quantity Estimate
Quantity estimates are based on the cross-section designs and number & types of cross drainage structures.
The quantity of different items of work like earthwork excavation, filling etc. is calculated by using the Design
software and on the basis of standard engineering formulae. However, some minor adjustment might be
needed which would be verified during the construction phase.
9.3. Rate Analysis
During the calculation of unit rates, three major components labor, material and equipment were considered.
Unit quantities for all these three components were taken from the DoLIDAR and DoR Work Norms and
Specifications. Similarly, the cost of labor and construction materials, are based on the district rate 2072/73 of
DDC. The rate of labor, material and equipment is then increased by adding VAT of 13%.
9.4. Cost estimate
The detailed cost estimate has been prepared using the calculated quantities and unit rates,
derived from standard applicable District Rates and DoLIDAR Work Norms and DoR Norms.
Contract packaging will be suitably done for all subprojects, and respective bidding documents will
be prepared following the Standard bidding documents of PPMO and DoLIDAR practices and
frameworks.
9.5. Conclusion
Due to adaptation of higher standard road width than previous design standard (road width from 5.00 m to
6.25 m) it is rational to increase the volume of earthwork and retaining structures, which along with raised
daily wages obviously increased the per kilometer cost of road. Similarly, due to presence of high and
steep gradient and hair-pin-bends the quantity of structures increased while trying to bring it within
permissible design standard and thus resulting in per kilometer cost
Detail Engineering Survey and Design of Sankhu - Palubari - Nagarkot Road
RRRSDP-2 38
Kathmandu
10. CHAPTER-X: CONCLUSION & RECOMMENDATIONS
The RRRDSP-2 has proposed to upgrade this Sankhu – Palubari – Nagarkot Road to all weather blacktopped
standard. Other intervention includes widening of narrow track and improvement of longitudinal gradient to
bring it within geometric standard road of District Road Core Network. Furthermore provision of passing bays,
construction of proper drainage system including lined drain, box & pipe culverts and causeways have also
been proposed following DoLIDAR guidelines and geometric standard of Nepal Rural Road Standards.
Upgrading and improvement of this district road will improve access and mobility of large settlements of
Sankhu, Palubari and Nagarkot to market, education and service centre, health and other economic activities.
The road will play a vital role to increase cash crops, horticulture and dairy & poultry farming in the zone of
influence area by providing access to these hinterlands to dense populated market of capital. As Nagarkot is a
tourist spot and Sankhu is famous historical religious place, this road will promote and enhance internal
tourism as well.
Upgrading of the road will help the people of the area to receive better education and quick access to medical
facilities. Government‟s other services will also be delivered better as the road will encourage government
employees to visit the area and its vicinity more frequently, or extend the duration of their stay. It is expected
to reduce the travel time further after the implementation of this project inspiring to use the saved time in
income generating activities.
The total cost of the project is estimated as NRs. 232,716,449.2 for 10.046 Km of length. The unit cost per Km
is estimated at NRs. 19,968,311.16.
CONSTRAINTS:
Due to the lengthy holidays of Dashain, Tihar and Chhat festivals and also because of election of the
Constituency Assembly on November 2013, the progress of assigned detailed engineering survey, design and
estimate of this road has been severely affected. Similarly the delay in timely delivery of output happened for
following reasons:
Due to need of joint field verification of design/drawing of each road sub-project than that was in
original contract
Delayed responses and repeated comments and suggestions from districts on submitted reports it
took double time to finalize the detail design report.
Another matter that delayed the timely delivery of output is need of concentration in 20 priority roads
up to tendering process. This has interrupted in smooth progress of gross work which could be done in
mass as most time was expended in preparing, correcting, re-correcting BoQ and bid documents of 20
district.
Furthermore, there was lack of consistency in review of submitted Detailed Design Report. Each and
every district reviewed DDR in own way and shown altering and varying requirement. The late and
frequent and even day by day changing comments / demands from each district extremely consumed
lots of time in addressing such issues.
Detail Engineering Survey and Design of Sankhu - Palubari - Nagarkot Road
RRRSDP-2 39
Kathmandu
And the devastating earthquake that took place on 4th week of April and 2nd week of May has off course
hampered the work progress severely. However, the consultant has tried their best for timely delivery of
outputs despite of such unavoidable circumstances.
CONCLUSION
Improvement and upgrading of this road to all weather standard will enhance the increased access to markets
and social services; provide opportunity to use saved travel time for productive income generating works;
development horticulture, cash crop, diary production and other agro based industry etc, which eventually pave
the way to achieve the program goal of reduce the poverty through creating employment generation