Date: August 8th, 2016 L&M Project: 1146-12
Community Meeting Summary Report
Meeting Date: August 3rd, 2016
Meeting Location: Northwood Motor Inn (2280 Hart Highway)
Meeting Duration: 7:00pm – 8:00pm
Number of Neighbours in Attendance: 6
City Representatives: Mandy Stanker (Planner), Katy Fabris
(Planner)
Background
The subject property is approximately 2.93 hectares (ha) in size and is located within the municipal boundaries of the City of Prince George at the intersection of the Hart Highway and Monterey Road. The property is presently split-zoned (RS2M: Single Residential, Z17: Monterey Road Commercial and C5: Visitor Commercial) and is currently vacant.
The following existing uses are located around the subject property:
North: AG: Greenbelt; RS2: Single Residential (Vacant; Hart Highway) East: Z17: Monterey Road Commercial (Vacant) South: RS2m: Single Residential (Residential) West: RS2: Single Residential (Residential)
Description of Project
The rezoning proposal includes rezoning approximately 1.06 ha of the subject property from
RS2m: Single Family to Z17: Monterey Road Commercial. The intent of this rezoning application
is to expand the existing Z17 zone to facilitate the development of an expanded commercial
node at this underutilized intersection. In 2013, the Z17: Monterey Road Commercial zone was
created to include commercial mini storage as a permitted use as part of a larger commercial
City of Prince George 1100 Patricia Boulevard Prince George BC V2L 3V9
ENGINEERING LIMITED
1210 Fourth Avenue Prince Gecrge, B.C. V2L 3J4 Tel. (250) 562-1977 Fax (250) 562-1967
Summary of Community Meeting Date: August 8th
, 2016 L&M Engineering Limited L&M Project No: 1146-12
L&M Engineering Limited Page | 2
node. The subject property is envisioned to provide a low-impact mini storage facility that will
be orientated to the rear of the property away from Highway 97 with the higher trip generating
commercial development located directly at the intersection ultimately promoting the most
visibility for vehicles passing by. This proposed site layout will ultimately help to meet the
original intent of the Z17 zone. Approximately 0.09 ha of the subject property is proposed to
remain RS2m: Single Residential. This portion of the property is not proposed for development
and can be retained for future residential land uses.
Community Meeting
The Community Meeting was advertised by hand delivered invitation to homes surrounding the
subject property. The area included homes on Monterey Road, as well as those homes located
on Cook Crescent, Erickson Street, Lehman Street, Hartway Drive and Ridge Cove Point which is
directly across from the subject property. The City of Prince George’s standard for delivery of
notices to the public is 30 metres and in this case, we delivered invitations to residents in
excess of 500 metres from the subject property. A total of 110 invitations were hand delivered
to residents.
Present at the Community Meeting were two L&M Engineering Limited staff members as well
as Mandy Stanker (Planner) and Katy Fabris (Planner) to represent the City of Prince George.
Neighbours were invited to view poster board displays and to ask any questions or enter into
conversation with any of the representatives at the meeting.
The Community Meeting was attended by 6 neighbours. Attendees began to arrive shortly after
6:45pm and were offered coffee and donuts from Tim Hortons. Attendees were presented with
five poster boards illustrating relevant information and conceptual site plans of the proposed
rezoning and were invited to review the boards and ask questions in a personal one-on-one
format. The meeting lasted until roughly 8:00pm for a total duration of 1 hour.
All of the neighbourhood questions and comments were documented have been provided with
this summary. We encouraged residents to provide their email on the sign-in-sheet so that we
could create a group email as a means of providing application updates and so that residents
could remain in contact with L&M Engineering throughout the process and future development
phases.
The feedback received from the community was largely inquisitive in nature, with neighbours
inquiring about more information regarding the following reoccurring issues: Traffic, new
development concerns and landscaping. These three topics have been described in greater
detail below.
Summary of Community Meeting Date: August 8th
, 2016 L&M Engineering Limited L&M Project No: 1146-12
L&M Engineering Limited Page | 3
Traffic
Neighbours in attendance cited traffic concerns with respect to the proposed development.
One main area of concern was regarding traffic access for the proposed development via
Lehman Street. We explained a Traffic Impact Study had been completed and that the subject
property is proposed to feature one point of access via Monterey Road. This driveway access
will be engineered to be located a safe distance from the Highway intersection and will feature
excellent visibility and maneuverability. The remainder residential lot would be accessed via
Lehman Street. We also stated that the portion of the subject property proposed to remain
RS2m could also be rezoned in the future to AG: Greenbelt to ensure that this lot would not
become a point of access for the proposed commercial development. Further, a Covenant may
be placed on the subject property preventing access to Lehman Street.
New Development Concerns
A concern about the safety and security of the surrounding neighbourhood was identified by
those in attendance. Neighbours were concerned that the proposed commercial mini-storage
facility would attract opportunities for crime and vandalism during the evening and cause light
pollution to the surrounding residential neighbours. To address these concerns we explained
that a security operator suite is proposed to be developed as a secondary use to the
commercial mini-storage facility so that someone would be living onsite 24 hours per day. The
decision to locate an operator suite onsite would be in an effort to further reduce the
opportunities for crime and vandalism as well as to keep the behavior of the unit tenants
mindful of the surrounding residential neighbours with respect to noise and traffic. The
commercial mini-storage facility will also provide a quiet, non-invasive, attractive development
which will promote Crime Prevention Through Environmental Design principals due to the high
visibility, street lighting, and the lack of activity during the evening hours. Directional, “dark
sky” lighting is proposed to be utilized onsite to prevent any night time light pollution from
impacting the surrounding neighbours.
Some neighbours expressed concerns with Vehicle Sales being a permitted principal use of the
Z17 zone. They felt that vehicle sales would not be very compatible with the site and would like
it removed from the zone. We explained that this use was approved by Council in 2013 for the
portion of the subject property already zoned Z17, however the Applicant is willing to discuss
this permitted use with the City and come to an agreement on where uses would be most
appropriately located for the surrounding neighbourhood.
Summary of Community Meeting Date: August 8th
, 2016 L&M Engineering Limited L&M Project No: 1146-12
L&M Engineering Limited Page | 4
Landscaping
Many neighbours expressed concerns regarding the aesthetic of the neighbourhood and were
inquiring about what was proposed on the subject property in terms of landscaping. We
explained that the subject property will be appropriately landscaped as per the City of Prince
George Zoning Bylaw No. 7850, 2007 standards. We further went on to explain that the
landscape plan will take into consideration the adjacency of the residential subdivision and will
create a landscape buffer and any fencing requirements to ensure that the residential
subdivision is adequate buffered from the expanded commercial use.
Comment Forms
We encouraged neighbours to fill out the comment forms provided so that they could be
included in this summary report. Following the completion of the meeting, no comment forms
were received. We have provided photographs of the interactive comment board which was
available at the meeting. The coloured dots on the map represent the location of a raised
concern and are colour coded to the adjacent comment page.
Summary
Overall, this voluntary meeting met its intended goal of sharing project information with the
neighbours and collecting valuable feedback. By the end of the meeting residents felt satisfied
that their concerns had been documented and considered. Further, many neighbours in
attendance expressed favor with the proposal so long as there is aesthetic control over the
future design and access is prevented from being granted onto Lehman Street.
Final negotiations for this application will continue until a mutually beneficial revision to the
Z17 zone is achieved. At such time, an update will be provided via email to all neighbours who
attended and provided their email address.
If you have any additional questions or concerns please do not hesitate to contact the
undersigned at your convenience.
Yours Very Truly,
L&M ENGINEERING LIMITED
Ashley Elliott, BPl
Community Planner
Summary of Community Meeting Date: August 8th
, 2016 L&M Engineering Limited L&M Project No: 1146-12
L&M Engineering Limited Page | 5
Copies To: Chris Matte, Matte Brothers & Sons Construction Ltd.
Terry Fjellstrom, President L&M Engineering Limited
Enclosures: As Noted
Monterey Road Community Meeting Summary
Meeting Date: August 3rd, 2016 Meeting Location: Northwood Motor Inn (2280 Hart Highway) Meeting Duration: 7:00pm – 8:00pm Number of Neighbours in Attendance: 6 neighbours City Representatives: Mandy Stanker (Planner) & Katy Fabris (Planner)
Comments:
There needs to be a landscaping buffer to reduce the noise
Once the intersection was put in on Lehman Street there was an increase of residential traffic
What type of security will be on-site for mini-storage? I do not want to have homeless people in the neighbourhood
Couldn’t care less about what type of development is on the property, just came to inquire about what was going on
Worried about the aesthetic of the neighbourhood
Not happy with vehicle sale as a principal use on the zone, and also not happy with recycling centre being a principal use
A storage facility would be a nice fit for the neighbourhood
Happy to have development on the property because it will block noise from the highway
This seems very dirty and noisy and we are not having this in our backyard
What will happen to our property taxes?
We want more residential development NOT commercial development
Concerned about potential access onto Lehman Street
Noise, traffic, pollution
A storage container should not be in my backyard
It is clear that the portion of the property that is on Lehman Street is going to be used as a driveway access into the commercial development
Our neighbours will move because of this
Already have industrial development across the highway, why can’t this development go somewhere else?
Control site coverage of mini storage
Does not want to have residences within the mini storage
Just want it to look nice
• I-Cl)
z <(
~ I w _J
MONTEREY ROAD REZONING
It ..
I .... I .... I I I I
.. --- -- -- -- -- -- -- -- -- -- -- -- --I I
• I • ' I
• 10 '
: • • ' • I -- -- ---- -- -- --1 ~
•
# ,#
# ~~ #
# ~~ #
~#
# #
• ##
# #
# #
# #
# #
# #
-- LEGEND
• SUBJECT BOUNDARY
' & !:::I \
-:ff
• • ~
• • G,
• • • 10
~o ?\ctt.SS 0N\0 L1c.\-\lY'\t1N ¥'...."E"E'? \1 RcS\t:tNT\'f\ L
?~?E.~,I.\ "-!l\LUt:.$
ffiW-.E. ,R~ rr,c_ \\\\-\-cN L\6ITTS ¼ ENT \N tol\tT{2.a__ ~,11:. C..O\J~C:ie: or m \ N, ST~& E.
f\\...R~f\t:'.)L\ \N't::;JST~ \f\L 'fl.L~oss \-\'N~
LX)ESN~ Wf\N1 RES,\~&JU:~ "'1 / I \'(\~ \ 51bMGtE
4 Su,\)'(\-\'\ ~o___--\ur Su.\-\ e o .'{...
S\\r8~ \ ~~c..,vtrt'-{
NO \Jc.\-\\ClE Sf\U:.s LPiN'DSCf\\)INGi.
t:v I L-t)l NG S ¼\LL tSLCe,K \-\\i-.l '{ NO\SE
Just V\\t\N"T \T \0 LcbK ~\CE