MANUFACTURING PROCESS IN NWK

• JOINTLY MAKE THE MONTHLY PLAN WITH PLANNING CONSIDERING MACHINE LOADING AND URGENCY AS REQUIRED BY MARKETING

• AFTER FINALISATION OF MONTHLY PLAN DEVIDED INTO WEEKLY PLAN

• THEN MAKE DAY AND SHIFT WISE MICRO PLAN

• MAKE JOB CARDS WITH THE HELP OF PLANNING

• RAW MATERIAL ISSUE FROM STORE DAILY BASIS

• MONITORING PRODUCTION AND RAW MATERIAL CONSUMTION SHIFT WISE

• REVIEW OF MACHINE MAN METHOD AND METERIAL PROBLES IN MORNING MEETING

• OUTPUT MONITORING IN EVENNING PRODUCTION REVIEW MEETNG.

2

Page 3: Presentation in Trainning

FLOW CHART (LT XLPE / PVC CONTROL CABLE)

WIRE DRAWING INT. WIRE DRAWING BUNCHING ( RE) (RM) CORE EXTRUSION

CORE LAYING UP

INNER SHEATHING

TESTING REWINDING OUTER SHEATHING ARMOURING

3

Page 4: Presentation in Trainning

FLOW CHART (LT XLPE / PVC POWER CABLE)

WIRE DRAWING COND. STRAND. CORE EXTRUSION

CORE LAYING UP TAPE (EXTR. INSH) INER SHEATH INNER SHEATHING

TESTING REWINDING OUTER SHEATHING ARMOURING

4

Page 5: Presentation in Trainning

FLOW CHART (HT XLPE CABLE)

WIRE DRAWING COND. STRAND. TAPPING CORE EXTRUSION CURRING

CU TAPPING CORE LAYING UP TAPE (EXTR. INSH) INER SHEATH INNER SHEATHING

TESTING REWINDING OUTER SHEATHING ARMOURING

5

Page 6: Presentation in Trainning

WIRE DRAWING

• AL DRAWING PROCESS• AL ROD – 9.5MM

• USE OIL MEDIA AS LUBRICANT

• 9 DIE MACHINES – 2 NOS

• CAN DRAW 2MM IN ONE GO AND CAN DRAW MIN 1.32 IN 2 GO

• CU DRAWING PROCESS• CU ROD – 8MM

• USE DRAWMED MIX WITH WATER AS LUBRICANT

• 15 DIE MACHINE WITH INLINE AANNEALING CAN DRAW 1.38 IN ONE GO

• INTERMIDIADE DRAWING WITH INLINE ANNEALER CAN DRAW MIN 0.3MM IN ONE GO

6

Page 7: Presentation in Trainning

WIRE DRAWING

7

Page 8: Presentation in Trainning

BUNCHING

• AL BUNCHING PROCESS

• AL WIRE – 3 WIRE FOR 4 SQ. MM. AND 6 SQ. MM. RM CONDUCTOR

• NWK HAS 2 BUNCHING MACHINE FOR BOTH AL AND CU

• CU BUNCHING PROCESS

• CU WIRE – 7 WIRE FOR ALL 1.5 SQ.MM TO 6 SQMM RM CONDUCTOR

• NWK HAS 2 BUNCHING MACHINE FOR BOTH AL AND CU

8

Page 9: Presentation in Trainning

CONDUCTOR STRANDING

• TYPE OF CONDUCTOR• PLAIN ROUND CONDUCTOR (RE)

• STRANDED ROUND CONDUCTOR (RM)

• STRANDED AND SECTOR SHAPED CONDUCTOR.

• STRANDED AND ROUND COMPACED CONDUCTOR (RM/V)

SECTOR SHAPED CONDUCTOR IS EITHER PLAIN STRAIGHT SECTOR ( FOR SMALLER CROSS SECTION ) AND PRETWISTED (FOR BIGGER CROSS – SECTION)

NWK HAS ONE 19 BOBIN ,TWO 37 BOBIN AND ONE 61BOBIN CONDUCTOR STRANDING MACHINES

9

Page 10: Presentation in Trainning

CONDUCTOR STRANDING

10

Page 11: Presentation in Trainning

CORE INSULATION

• CORE INSULATION PROCESS FOR LT CABLES AND HT CABLES

• INSULATION TYPE – PVC INSULATION AND XLPE INSULATION

• INSULATION PROCESS – SINGLE EXTRUSION AND TRIPPLE EXTRUSION

• CONTROL CABLES INSULATION

XLPE AND PVC INSULATION DONE IN 80 MM NOKIA MAILLRFER EXTRUSION LINE

• POWER CABLE INSULATION

XLPE AND PVC INSULATION DONE IN 150 MM NOKIA MAILLRFER EXTRUSION LINE

• HT CABLE INSULATION

XLPE TRIPPLE EXTRUSION DONE IN 65MM/150MM/100MM ROYALE EXTRUSION LINE

11

Page 12: Presentation in Trainning

CORE INSULATION

12

Page 13: Presentation in Trainning

CORE TAPPING & SCREENING

• TAPPING MEANS APPLICATION OF TAPE EITHER HELICALLY OR LONGITUDINALLY

• VARIOUS TAPES USED :• SEMICONDUCTING TERENE TAPE

• COPPER TAPE

• IDENTIFICATION COL OUR POLY TAPE

SCREENING IS A PROCESS OF APPLYING A LAYER OF SEMICONDUCTING TAPE AND VERNISH ( FOR PVC ONLY) , SCREENING COPPER TAPE AND COLOUR IDENTIFICATION TAPE OVER XLPE INSULATED CONDUCTOR (FOR HT XLPE CABLE)

13

Page 14: Presentation in Trainning

CORE STRANDING

• INSULATED OR CU SCREENED CORES ARE STARNDED TOGETHER TO FORM A CABLE.

• CORES ARE IDENTIFIED BY COLOUR , NUMBERING OR TAPING WITH COLOUR TAPE.

• THESE CORES ARE THEN WRAPPED WITH A COMON COVERING OF PVC/LDPE TAPE – FOR TAPED INNESHEATH CABLE & RCC/POLYESTER TAPE FOR PVC EXTRUDED INNER SHEATH CABLES

) 14

Page 15: Presentation in Trainning

CORE STRANDING

15

Page 16: Presentation in Trainning

ARMOURING

ARMOURING IS A PROCESS OF PROVIDING PROTECTION TO THE CABLE BY CONSTRUCTION OF AN ARMOUR ARROUND

• TYPE OF ARMOURING

1. GI WIRE ARMOUR

2. GI FLAT STRIP ARMOUR

16

Page 17: Presentation in Trainning

SHEATHING

SHEATHING IS A PROCESS WHICH GIVES PROTECTION (LIKE JACKET) OVER ARMOUR

• TYPE OF SHEATHING

1. PVC – ST-2

2. PVC - FRLS

17

Page 18: Presentation in Trainning

Rewinding

• CHECKING AND CUTTING OF

1) CONTROL CABLE

2) POWER CABLE

3) HT CABLE

• AS PER STD LENGTH MENTIONED IN CUTTING INSTRUCTIONS

• DELIVER TO TEST FIELD FOR FINAL TESTING