Upload
nuriman-k-mon
View
331
Download
7
Embed Size (px)
Citation preview
7/30/2019 Pgb Internship 2012
1/33
1
Industrial training report
1. Executive summaryThis report focuses on the significant progress done during the 10 weeks internship period at Kuantan
Compressor Station (KTNCS).The objective of the industrial training program is to integrate theories
learned in university with on-hand experience in order to get clearer understanding of learning process.
Being assigned to one of the world class oil and gas company, this will be the perfect chance to do so.
Kuantan Compressor Station is one of the stations managed by Transmission Operation Department
(TOD), and owned by PETRONAS Gas Berhad (PGB), which is one of the subsidiaries of Petroliam
Nasional Berhad (PETRONAS). KTNCS main objective is to increase the pressure of the natural gas
flowing from Kertih to Segamat with normal operational reliability of 99.90%. During 10 weeks of intern,
Mr Ahmad Naim, Executive of Compressor Maintenance KTNCS, has been assigned as my supervisor. His
wide experience in the company and serious approach to work has been exemplary to me. Others
colleague has been a huge help too, I managed to blend well with them and able to gain much
knowledge from them. I was tasked with an individual project and able to join their activities without
any problem. Conclusively, the experience acquired during this industrial training especially in
compressor, turbine and natural gas transmission is a lifetime opportunity.
7/30/2019 Pgb Internship 2012
2/33
2
Industrial training report
2. AcknowledgementFirst and foremost, I would like to thank to Allah S.W.T, The Almighty for giving the strength and
patience in completing 10 weeks Industrial Internship program, which starts from 9 July 2012 until 14September 2012. Besides, thank God for giving me the chance to complete this final report.
A special thank goes to my family and members who has been given a lot of support during my
internship program. All of their efforts in ensuring me have been successfully undergone the program
are really appreciated.
Besides that, I would like to express my utmost gratitude and appreciation to PETRONAS Gas Berhad
(PGB), for giving me an opportunity to do industrial training, great experience and knowledge in doing
the internship program. Special thanks especially to my supervisor, Mr Ahmad Naim who has been an
exemplary leader and mentor to me. Also I want to reserve special thanks for other KTNCS staffs for
their guidance and cooperation in teaching me a lot of technical stuffs within these 10 weeks of practical
training program.
Last but not least, I would like to express my appreciation to my visiting lecturer, Miss Sitinoor Adieb
Binti Idris for her continues support and efforts either directly or indirectly in helping me to successfully
complete the internship program. The experiences obtained, be it sweet or bitter, will always become a
guidance for me in pursuit of an ubiquitous oil and gas engineering student goal, which is to become an
excellent engineer with full of integrity.
7/30/2019 Pgb Internship 2012
3/33
3
Industrial training report
3. Contents1. Executive summary 1
2. Acknowledgement 2
4. Introduction 4
5. Process 9
6. Projects and activities
6.1 The safety valve project 11
6.2 Activities involved
6.2.1 Unit 4k and 8k running maintenance 23
6.2.2 Jom Sembang program 24
6.2.3 Site visit for new lube sampling point 25
6.2.4 Site visit schedule waste 28
6.2.5 Site visit to PETRONAS CUF Gebeng to collect
Demineralized water 30
7. Problem encountered and ways overcoming it 31
8. Lesson learned 32
9. Suggestion 32
10. Conclusion 33
11. Reference 33
12. List of Appendices 33
7/30/2019 Pgb Internship 2012
4/33
4
Industrial training report
4. Introduction
Figure 1 Petroliam Nasional Berhad
Figure 2 PETRONAS Gas Berhad (PGB) logo
PETRONAS
PETRONAS GasBerhad
Plant OperationDivision
TransmissionOperation Division
Facilities
Metering
Pipeline Compressor
Technical Maintenance
Centralised UtilitiyFacilities
Technical andFacilities
DevelopmentDivision
RegasificationTerminal Division
PETRONASCarigali
PETRONASDagangan
7/30/2019 Pgb Internship 2012
5/33
5
Industrial training report
PETRONAS Gas Berhad (PGB) is a subsidiary of Petroliam Nasional Berhad (PETRONAS). There are five
department under PGB, mainly known as Plant Operation Division (POD), Transmission Operation
Division (TOD), Centralized Utilities Facilities (CUF), Technical and Facilities Development Division (TFDD)
and Regasification Terminal Division (RGTD).
Table 1 Departments in PGB
Department Task
Plant Operations Division (POD) POD operates the six gas processing plants in the
state of Terengganu. The plants are divided into
two complexes Gas Processing Plant A in Kertih
and Gas Processing Plant B in Paka. With total
combined sales gas processing capacity of over
2000 million standard cubic per day, these gas
processing plants process natural gas into sales gas
and other by-products such as ethane, propane
and butane to be transmitted to PETRONAS
customers in power and non-power sectors via
PGBs Peninsular Gas Utilization pipeline network.
Transmission Operation Division (TOD) TOD operates the Peninsular Gas utilization
pipeline network by managing the supply of gas to
PETRONAS customers throughout Malaysia and
ensuring the reliability, safety and efficiency of
operations. The Segamat Operation Center which
houses the PETRONAS Gas Control Center acts as a
mission control for the entire PGU network.
Centralised Utility Facilities (CUF) CUF supplies a range of industrial utilities to the
petrochemical business in Kertih Integrated
Petrochemical Complex in Terengganu and Gebeng
Industrial Area in Pahang. The industrial utilities
include electricity, steam, industrial gases and
other by-products such as liquid oxygen, liquid
nitrogen, demineralized water, raw water, cooling
water and boiler feed water, as well as effluent
treatment.
Technical and Facilities Development Division
(TFDD)
TFDD is the engineering and project management
arm of PETRONAS Gas Berhad. Having in place asolid technical resume, TFDD also provides services
to other companies within the PETRONAS Group
such as PETRONAS Carigali Sdn. Bhd for the
Sabah-Sarawak Pipeline project.
7/30/2019 Pgb Internship 2012
6/33
6
Industrial training report
Regasification Terminal Division (RGTD) The newly-formed RGTD is testimony to PGBs
serious endeavor in transcending beyond its
conventional business parameters. RGTD is
currently responsible in overseeing the
engineering, construction and commissioning ofMalaysias first ever Liquefied Natural Gas (LNG)
Regasification facilities in Sungai Udang, Melaka as
well as the operations and maintenance of the
facilities upon completion in August 2012. Three
new subsidiaries under PGB Group, namely Regas
Terminal (Sg. Udang) Sdn. Bhd., Regas Terminal
(Pengerang) Sdn. Bhd., and Regas Terminal (Lahad
Datu) Sdn. Bhd., under the purview of RGTD.
Kuantan Compressor Station (KTNCS)
Managed by TOD PGB, KTNCS is located at Kg. Mahkota, KM19, Jalan Gambang, 26070, Kuantan.
Figure 3 KTNCS top view
Station A
Station B
7/30/2019 Pgb Internship 2012
7/33
7
Industrial training report
The main purpose of KTNCS is to increase the pressure of the natural gas flowing from Kerteh to
Segamat. There are two stations, station A and B. Their differences are mainly on the operating
conditions:
Table 2 Stations operating conditions
Station A Station B
Unit 1,2,3 4,5
Capacity (mmscfd) 700 500
Conversion ratio 1:1.35 1:1.48
KTNCS has the flexibility of running either Station A or Station B or combination of them. Natural gas
arrived from Kerteh at pressure between 3000-6000kPag and temperatures between 20 to 30C.It is
boosted up to 6895 kPag maximum as export pressure.
During 10 weeks of internship here, I was assigned to Mr. Ahmad Naim, Executive of Compressor
Maintenance KTNCS and was trained as trainee engineer. Project that was assigned to me is The Safety
Valve Studies, which is explained in details in project and activities section. The project is an individual
assignment, it was done for the further reference of the station and I have carried it out successfully.
7/30/2019 Pgb Internship 2012
8/33
8
Industrial training report
Figure 4 KTNCS organization chart
Ismail b. Othman
Kuantan Regional Operation
Mohd Faiz b.Mohd Mustafa
Executive CompressorOperation
Fazley Zulfikar b.Ismai
Technician (MT - OperationCompression)
Matsaliniah b.Yusof
Technician (MT - OperationCompression
Mohammad Faris
b. M ZayadiTechnician (MT - OperationCompression
Mat Ghani b.Mohd Salleh
Technician (MT - Process)
Mohammad Faizalb. M. Noor
Technician (MT - Process)
Mohd Hashim b.
EmbongTechnician (MT - Process)
Norli b. Yajid
Technician (MT - Process)
Ahmad TawfikFathir b.
MuhammadTechnician (MT - Process)
Khairul Anuar b.
MamatTechnician (MT - Process)
Ahmad Naim Abd.Rahman
Executive CompressorMaintenance
Azmi b. Mamat
Technician (MT- Electrical)
Azizul b. Hosma
Technician (MT- Electrical
Mohd Fauzi b.Mamat
Technician (MT - Mechanical)
Tahir b. Shariff
Technician (MT - Mechanical
Zamri b. Embong
Technician (MT - Mechanical
Azanmudin b.Deraman
Technician ( MT - MechanicalCompression)
Nik Mohd Fauzib. Sapian
Technician ( MT - MechanicalCompression
Ariffin b. Sulaiman
Supervisor Administrator
MohammadHusni
Muhammad SaniExecutive Compressor
Maintenance Mechanical
7/30/2019 Pgb Internship 2012
9/33
9
Industrial training report
5. ProcessKuantan Compressor station (KTNCS) was opened on 1993 with initial three units, 1,2 and 3. This is
known as Station A. Further renovation to the station occurs with addition of Station B with 2 new units,
4 and 5, effective in 2010. Overall, KTNCS undergoes clean process flow with no reaction occur. Natural
gas flow only undergoes increase in pressure through the compressor. The gas is a composition of
nitrogen, CO2, methane, ethane, propane, i-Butane, n-butane, i-pentane, n-pentane, n-hexane, n-
heptane and water. The composition is constant throughout the system as the process is at steady state
with no reaction occurring. The summary of composition is stated in the table below:
Table 3 Composition natural gas
Material Composition Lean Composition 80% isentropic
Nitrogen 0.004049 0.008720
CO2 0.040647 0.022521
Methane 0.910743 0.869046
Propane 0.028511 0.069902
i-Butane 0.009277 0.020331
n-Butane 0.002939 0.003100
i-Pentane 0.000880 0.001450
n-Pentane 0.000440 0.000730
n-Hexane 0.000420 0.000320
n-Heptane 0.000190 0.000060
Water 0.000316 0.000000
Relate with Component Continuity Equation, with its general equation and taking methane as subject:
Moles of methane
flow into the
systemMoles of methane
flow out of the
systemRate of
formation
due to
reactions
Time rate of change
of mole of methane
in the system- + =
7/30/2019 Pgb Internship 2012
10/33
10
Industrial training report
Then, knowing that:
No reaction occur Process at steady state
Cancellation causes the equation to become:
This applied throughout the system, so the composition of methane is constant throughout the system.
Moles of methane
flow into the system
Moles of methane
flow out of the
system
=
7/30/2019 Pgb Internship 2012
11/33
11
Industrial training report
6. Project and activities6.1The safety valve studya) Introduction
The project was handed out by supervisor, Mr. Ahmad Naim, on 28 July 2012. Scope ofthe project includes:
i. Gathers required data regarding PSV and PRV at KTNCSii. Locate each safety valves in the drawings
After lengthy discussion, it is known that the safety valves can be found at station A,
station B and Fire Water Pump. Station A and B is located at the process area and Fire
water Pump is at non-process area.
Heres a closer look at the safety valve. A safety valve is a valve mechanism which
automatically releases a substance from a boiler, pressure vessel, or other system when
the pressure or temperature exceeds limit. It is one of set of pressure safety valves (PSV)
or pressure relief valve (PRV) which also includes relief valves, safety relief valves, pilot-
operated relief valves, low pressure safety valves and vacuum pressure safety valves.
PSV and PRV differ from each other, PSV have manual lever that open valves in case of
emergency.
Pressure relief valve is an auto system actuated by the static pressure in a liquid-filled
vessel. It specifically opens proportionally with increasing pressure. Pressure safety
valve in the other hand is an auto system that relieves the static pressure on a gas.
Usually open completely with popping sound. KTNCS safety valves consist mainly of PSVtype.
One of the PSV model used is Farris Series 3800 by Farris Engineering. Its operating
principles can be summarized in four sentences below:
i. Pressure in the protected vessel is sensed through a pressure tap (remotelyconnected or to the main valve body). The pressure tap is piped to the pilot
control sensing line port. The vessel pressure is transmitted to the dome
from the pilot control dome port.
ii. When vessel pressure is below pilot control set pressure, the relief seat ofthe pilot control is closed. Inlet pressure of the main valve is equal to the
dome pressure (smaller) and the dome area (larger) guarantees the main
valve to be closed.
iii. When the vessel pressure reaches set pressure, the pilot control relief seatopens instantaneously with the closing of lower seat. The pilot control
7/30/2019 Pgb Internship 2012
12/33
12
Industrial training report
relieves the dome pressure to the atmosphere. The force of the pressure in
the inlet of main valve causes the piston to lift from its closed position to
relieve excess vessel pressure. The relationship between the down ward
force on the main valve and vessel pressure is illustrated in Figure 1.
iv. When vessel pressure reaches re-seat pressure (typically 95% of the setpressure), the spring forces overcomes the pressure force on the lower seat
of the pilot control. The relief seat closes instantaneously with the opening
of the lower seat. Pressure re-enters the dome and develops the force to
move the main piston down and close the main valve. In Figure 2, the lift of
the main valve piston is plotted against vessel pressure.
Figure 5 Main valve close
Figure 6 Main valve open
dome
Main valve
Piston
Pilot
Pilot discharge
Relief seat
7/30/2019 Pgb Internship 2012
13/33
13
Industrial training report
b) FindingsStudies on plant station A, station B and also Fire Water Pump system is conducted. First, the
manual documents of each station need to be found. The manual contains data provided by the
manufacturer earlier during the design and building of the plant. Fortunately, all the manuals
are placed in tidily on shelves, so finding the right ones is not a tough job. The manual
documents are very specific, and it helps a lot as most of the data can be found there.
Next, related P&IDs are analyzed in detail in order to determine the valves locations. The P&IDsare quite complicated at first, but with the help of experienced colleague, understanding the
piping and instrumentation flow become easier. We then go to the site to check out each valve
and also visit fire water pump. The Fire Water Pump uses PSV on its diesel engine, to relieve the
excessive head on the pipe. Another PSV found is PCV-2120. Although the tagging indicates it is
Figure 8 Main valve piston lift
Fi ure 7 Downward Force on Main Valve Piston
7/30/2019 Pgb Internship 2012
14/33
14
Industrial training report
regulator valve (pressure control valve), but its function resembles safety valve. Thus it is
regarded as one of the safety valve.
The findings can be summarized below:
7/30/2019 Pgb Internship 2012
15/33
15
Industrial training report
Table 4 Pressure Safety Valve Station A
No
Tag
no. Equipment
Serial
no.
Manufactur
er Model Inlet Outlet Type
Orifice
(in)
Set Pressure
(KPAG)
Relieve
temperature
(C) Drawing no.
1
PSV
1011
FILTER SEP.
V1010
VA
004779
2 CROSBY 2H3-JOS-45-A
2'' X 600 #
ANSI RF
3" X 150 #
ANSI RF
CONVENTI
ONAL 0.785 7585 64.3
CM202-020-D-
0006 (1)
2
PSV
1021
FILTER SEP.
V1020
VA
004779
2 CROSBY 2H3-JOS-45-A
2'' X 600 #
ANSI RF
3" X 150 #
ANSI RF
CONVENTI
ONAL 0.785 7585 64.3
CM202-020-D-
0006 (2)
3
PSV
1031
FILTER SEP.
V1031
98/3870
6 ANDERSON
D050HS120AK
S1100
2'' X 600 #
ANSI RF
3" X 150 #
ANSI RF
CONVENTI
ONAL 0.785 7585 64.3 2223-110-001
4
PSV
1051
FUEL GAS
FILTER
VA
004703
1 CROSBY ID2-JOS-45-A
1" X 600 #
ANSI RF
2" X 150 #
ANSI RF
CONVENTI
ONAL 0.11 7585 64.3
CM202-020-D-
0013 (1)
5
PSV
1061
FUEL GAS
FILTER
VA
004702
5 CROSBY ID2-JOS-45-A
1" X 600 #
ANSI RF
2" X 150 #
ANSI RF
CONVENTI
ONAL 0.11 7585 64.3
CM202-020-D-
0013 (1)
6
PSV
1081 AIR RECEIVER
VA
004702
6 CROSBY 3L4-JOS-15-A
3" X 150 #
ANSI RF
4" X 150 #
ANSI RF
CONVENTI
ONAL 2.853 1380 85.7
CM202-020-D-
0015 (1)
7
PSV
1019
POWR GAS
DEHYDRATOR
VA
004702
8 CROSBY ID2-JOS-45-A
1" X 150 #
ANSI RF
2" X 150 #
ANSI RF
CONVENTI
ONAL 0.11 7585 64.3
CM202-020-D-
0019
8
PSV
1013 FUEL GAS SKID
VA
004703
1 CROSBY
11/2 G 2 1/2-
JOS-35-A
11/2" X 150 #
ANSI RF
21/2" X 150 #
ANSI RF
CONVENTI
ONAL 0.503 3272 35
CM202-020-D-
0013 (2)
9
PSV
FUEL GAS SKID
VA
CROSBY
11/2 G 2 1/2- 11/2" X 150 # 21/2" X 150 # CONVENTI
0.503 3272 35
CM202-020-D-
7/30/2019 Pgb Internship 2012
16/33
16
Industrial training report
1014 004703
1
JOS-35-A ANSI RF ANSI RF ONAL 0013 (2)
10
PSV
1015 FUEL GAS SKID
VA
004703
1 CROSBY
11/2 G 2 1/2-
JOS-35-A
11/2" X 150 #
ANSI RF
21/2" X 150 #
ANSI RF
CONVENTI
ONAL 0.503 3272 35
CM202-020-D-
0013 (2)
11
PSV
1023
UTILITY GAS
SKID
VA
004703
4 CROSBY 1E2-JOS-15-A
1" X 150 #
ANSI RF
2" X 150 #
ANSI RF
CONVENTI
ONAL 0.196 825 46
CM202-020-D-
0014
12
PSV
1024
UTILITY GAS
SKID
VA
004703
4 CROSBY 1E2-JOS-15-A
1" X 150 #
ANSI RF
2" X 150 #
ANSI RF
CONVENTI
ONAL 0.196 825 46
CM202-020-D-
0014
13
PSV
1025
UTILITY GAS
SKID
VA
004703
6 CROSBY
11/2F2-JOS-
15-A
11/2" X 150 #
ANSI RF
2" X 150 #
ANSI RF
CONVENTI
ONAL 0.307 250 21
CM202-020-D-
0014
14
PSV
1071
ODOURIZER
POT
VA
004703
8 CROSBY 1E2-JOS-15-A
1" X 150 #
ANSI RF
2" X 150 #
ANSI RF
CONVENTI
ONAL 0.196 690 21
CM202-020-D-
0014
15
PSV
1001
STN DISCH
HEADER
93E
00079 FARRIS
47312-
81010/SI
8" X 600 #
ANSI RF
10" X 150 #
ANSI RF PILOT N/A 7240 50
CM202-020-D-
0006(1)
16
PSV
112-1
PIPELINE
RECEIVER
KA2319
3
FISCHER
(FARRIS)
26 GC 13-140-
A10
11/2" X 600 #
ANSI RF
21/2" X 150 #
ANSI RF
CONVENTI
ONAL N/A 6895 N/A 0516-33-008
17
PSV
112-2
PIPELINE
LAUNCHER
KA2318
4
FISCHER
(FARRIS)
26 FC 13-140-
A-10
11/2" X 600 #
ANSI RF
2" X 150 #
ANSI RF
CONVENTI
ONAL N/A 6895 N/A 0516-33-008
18
PSV
112S
RL
PIPELINE
RECEIVER
328896-
1-A10/R
TELEDYNE
(FARRIS) 26 GC 13-130
1.5" X 600 #
ANSI RF
2" X 150 #
ANSI RF
CONVENTI
ONAL N/A 6895 N/A 0516-33-008
19
PSV
112SIL
PIPELINE
LAUNCHER
328896-
2-A10/R
TELEDYNE
(FARRIS) 26 FC 13-130
1.5" X 600 #
ANSI RF
2" X 150 #
ANSI RF
CONVENTI
ONAL N/A 6895 N/A 0516-33-008
7/30/2019 Pgb Internship 2012
17/33
17
Industrial training report
Table 5 Pressure Safety Valve Station B
No Tag no. Equipment
Serial
no.
Manufactu
rer Model Inlet Outlet Type
Orifice
(in)
Set Pressure
(KPAG)
Relieve
temperature
(C) Drawing no.
1PSV-2010 FILTER SEP V-2010
06-40359 CROSBY
1D2-JOS-E-45-J
1" x
600#
ANSIRF
2" x
150#
ANSI RF
CONVENTIO
NAL0.11
7585 311.36
8022-KN-DR-PR-007(1)
2
PSV-
2016 DISCHARGE SIDE
VALVE
06-
40378 CROSBY
44312T810/
S1
8" X
600#
ANSI
RF
10'' X
150#
ANSI RF
PILOT
26
7240 508022-KN-DR-PR-
007(1)
3
PSV-
2020
FILTER SEP V-2020
06-
40360 CROSBY
1D2-JOS-E-
45-J
1" x
600#
ANSI
RF
2" x
150#
ANSI RF
CONVENTIO
NAL
0.11
7585 311.368022-KN-DR-PR-
007(2)
4
PSV-
2030 FUEL GAS FILTER SEP V-
2030
06-
40361 CROSBY
1D2-JOS-E-
45-J
1" x
600#
ANSI
RF
2" x
150#
ANSI RF
CONVENTIO
NAL
0.11
7585 313.198022-KN-DR-PR-
011
5
PSV-
2040 FUEL GAS FILTER SEP V-
2040
06-
40362 CROSBY
1D2-JOS-E-
45-J
1" x600#
ANSI
RF
2" x
150#
ANSI RF
CONVENTIO
NAL
0.11
7585 313.198022-KN-DR-PR-
011
6
PSV-
2061
UTILITY GAS
06-
40363 CROSBY
1D2-JOS-E-
15-J
1" X
150#
ANSI
RF
2" x
150#
ANSI RF
CONVENTIO
NAL
0.11
825 258022-KN-DR-PR-
012
7/30/2019 Pgb Internship 2012
18/33
18
Industrial training report
7
PSV-
2062
UTILITY GAS
06-
40364 CROSBY
1D2-JOS-E-
15-J
1" X
150#
ANSI
RF
2" x
150#
ANSI RF
CONVENTIO
NAL
0.11
825 258022-KN-DR-PR-
012
8
PSV-
2070 INST. AIR RECEIVER V-
2070
06-
40365 CROSBY
1E2-JOS-E-
15-J
1" X
150#
ANSI
RF
2" x
150#
ANSI RF
CONVENTIO
NAL
0.196
1380 441.38022-KN-DR-PR-
013
9
PSV-
2080 BUFFER AIR RECEIVER
V-2080
06-
40366 CROSBY
1E2-JOS-E-
15-J
1" X
150#
ANSI
RF
2" x150#
ANSI RF
CONVENTIO
NAL
0.196
1380 441.38022-KN-DR-PR-
013
10
PSV-
2090 UTILITY AIR RECEIVER
V-2090
06-
40367 CROSBY
1E2-JOS-E-
15-J
1" X
150#
ANSI
RF
2" x
150#
ANSI RF
CONVENTIO
NAL
0.196
1380 441.38022-KN-DR-PR-
013
11
PSV-
2101
FUEL GAS
06-
40368 CROSBY
2H3-JOS-E-
35-J
2" X
300#
ANSI
RF
3.2" X
150#
ANSI RF
CONVENTIO
NAL
0.785
3450 308022-KN-DR-PR-
011
12
PSV-
2201
FUEL GAS
06-
40369 CROSBY
2H3-JOS-E-
35-J
2" X
300#
ANSI
RF
3.2" X
150#
ANSI RF
CONVENTIO
NAL
0.785
3450 308022-KN-DR-PR-
011
13
PSV-
1080
FUEL GAS SEP. V-1080
06-
40370 CROSBY
1D2-JOS-E-
45-J
1" X
600#
ANSI
RF
2" X
150#
ANSI RF
CONVENTIO
NAL
0.11
7585 64.3CM202-020-D-
0013(1)
7/30/2019 Pgb Internship 2012
19/33
19
Industrial training report
Table 6 Pressure Relieve Valve for Fire Water Pump
N
o Tag no. Equipment Serial no. Manufacturer Model Inlet Outlet Type
Orifice
(in)
Set Pressure
(KPAG)
Relieve
temperature
(C) Drawing no.
1
PSV-
2120 DIESEL ENGINE 07-20505
ANDERSON
GREENWOOD CROSBY
324JLT-JOS-EOR-
15-J N/A N/A N/A N/A 1600 N/A
8022-KN-DR-PR-
019
2
PCV-
2120
RECYCLE TO
TANK 705-108-3 SINGER VALVE INC 106-XX-PR N/A N/A N/A N/A 1100 N/A
8022-KN-DR-PR-
019
7/30/2019 Pgb Internship 2012
20/33
20
Industrial training report
c) ConclusionBy referring all the tables, station A, statin B and Fire Water Pump contains 19, 13 and 2
pressure safety valves respectively. Type of valves varies with each position and requirement
and model used were Crosby, Anderson, and Farris. The safety valves mainly can be separated
into two types, pilot and conventional. Pilot typed valves usually found at the station discharge
header and for others, conventional valves are usually used. All PSV locations can be spotted on
its individual P&ID by referring the drawing number provided. The drawings are compiled in the
appendix section. The project was completed on 25th July, one week after.
Figure 9 Farris safety valve, pilot typed valve
7/30/2019 Pgb Internship 2012
21/33
21
Industrial training report
Figure 10 Conventional safety valve
6.2Activities involvedThroughout the internship period, a lot of activities are planned at KTNCS. By joining these
activities, a lot of experience and knowledge regarding PETRONAS Gas Berhad and KTNCS
were gained. Being friendly and freely volunteer is important remarks in joining these
activities. Among the activities are:
6.2.1 Units 4k and 8k running hour maintenanceAs the unit has continuously running for about 4000 and 8000 hours, a routine
maintenance needs to be done. These maintenance standard procedures in
ensuring the turbine well serviced and detect any abnormalities in its process.
The procedure includes:
a) Filter change for lube oil system and dry gas seal systemChange of filter in the oil that acts as both lubricant and coolant for the
turbine. Routine maintenance is done by the mechanical technician in order
to enhance turbine operating life. The turbine uses duplex filter system,
where one run and the other are on standby. The filter has capability of
filtering component up to 5 micron. Steps during filter change include
isolate, drain line, change filter, online with control system, and perform
bleeding.
Figure 11 Lube oil sequence
Compressor is connected to turbine by coupling, radial bearing, thrust
bearing, radial bearing and gas seal. All of them are connected with each
TankFin fan (lube oil cooler) Duplex filter Engine beari
Pump:
Backup
Pre/post
Main line
7/30/2019 Pgb Internship 2012
22/33
22
Industrial training report
other on a shaft. Bearing main objective is to support the shaft. It requires
lube oil to operate smoothly and if not isolated properly, it will mix with the
gas flowing through the compressor. This is where gas seal work. The dry
gas seal contains two inlet (refer appendix), buffer air and gas. The buffer air
reduces oil from bearing side enter the compressor and gas on the gas
flowing side. Both use labyrinth, a mechanical seal that provides a tortuous
path to help prevent leakage. The dry gas is the most important part in
ensuring quality of the gas discharged.
Figure 12 Bleeding process
b) Turbine blade washThe turbine can be regarded as the core element in the gas process
here. The complex structure of the turbine itself requires professionalhandling and regular maintenance. Its efficiency highly depends on the
blade condition. So, routine cleaning is required for each unit of
turbines in order to maintain the turbine performance and condition.
The cleaning process also provides opportunity for the maintenance
team to observe whether any part has worn out and needs attention.
7/30/2019 Pgb Internship 2012
23/33
23
Industrial training report
Figure 13 Turbine blade
Figure 14 Turbine blade
c) Air intake pre-filter changeIn addition to normal 4k maintenance procedure, the 8k requires
operator to check unit control panel any determine any abnormality on
its process. If any abnormalities occur, the technician needs to open the
related parts and fix it. If the turbine is well maintained, these
abnormalities will be a rare case. Air intake filter consist of two parts,
pre and final. Pre-filter is a component made of fiber-glass, placed
before final filter. The final filter is component that is box-typed; contain
series of alternating aluminum sheet and fiber sheet. The change is
done by Salutary Avenue, the company that provides the filter to PGB
itself. This is convenient as they have expertise in their own product.
7/30/2019 Pgb Internship 2012
24/33
24
Industrial training report
6.2.2 Jom Sembang program at Kuantan Regional Office (RO)Program initiated by TOD of PETRONAS Gas to help close gaps between top
management and staff. This program provides opportunity for staff to issue any
problem regarding their department to the top management. Besides, the
program also provide platform for both parties to mingle with each other. Theagenda includes briefing of current performance of TOD and interactive games.
The briefing was conducted by Mr Noranizar B. Ali Amran, the Senior Manager
(SM) of TOD. Briefing section create chances for staff to forward any questions
regarding PETRONAS and TOD especially. All of the questions were answered
directly by SM. Among the question raised was the staffs pay system, about the
incentives given by PETRONAS to its loyal workers. The interactive part was
even better, the staff and the top management combines and form groups to
play the classic snakes checkers (dam ular). The game turns out to be interesting
and funny, as all of the eager to finish first. All of the players enjoy quality time
together, and in turn help release their daily working stress.
7/30/2019 Pgb Internship 2012
25/33
25
Industrial training report
Figure 15 Game winners
Figure 16 snake checkers on floor tiles
6.2.3 Site visit for new lube oil sampling pointIn addition to existing sampling point, new lube oil sampling point is needed to
monitor and maintain lube oil quality. Existing lube oil tapping sample is taken
before the oil enters it filter. By consulting its very own Group Technical
Solutions (GTS), they wanted to know where other samplings can be made. Dr.
Chew has been assigned to this task. He has conducted studies on the Segamat
Operation Center first prior coming to KTNCS. The assessment take two days,
first day is entirely briefing regarding the choices that available for sampling andthe discussions with responsible engineers and technician. Here he explained
that there are four choices available:
7/30/2019 Pgb Internship 2012
26/33
26
Industrial training report
a) First is just maintaining the current sampling point (tapping) and addedtapping point to the return line. This option is simple but the result will be
unsatisfactory and seems lazy.
b) Second option is to maintain current tapping, add another tapping afterfilter at the feed line and another at the return line. This seems reasonable
and will make the job easier.
c) The third choice is same as the second, but for the return line, each bearing(five all of them) will have its lube oil sampled. This is more accurate and
better but depends on accessibility.
d) The final option is to have sampling at all equipment that lube oils passed.This will be the most accurate method, but the sampler will have a torrid
time collecting all the sample and it will be time consuming.
It is agreed that the sampling will be either between options two and three,
depending on the accessibility at the turbine. That takes us to the second day,
where the line tracing is done. Line tracing using P&ID of lube oil will help the teamto have far better view of the situation. Station A and B have different arrangement,
so line tracing will be conducted at each one of units of the station. For station A,
the team takes quite long time to determine the sampling point as the accessibility
and the turbine arrangement is quite complicated. But for station B, which are more
modern in design, the line tracing and the decision is made in short time. The line
tracing only reveal possible sampling points but the final decision is at the hand of
GTS. The result will come in after about one week.
Figure 17 return line for lube oil (station A)
7/30/2019 Pgb Internship 2012
27/33
27
Industrial training report
Figure 18 Line tracing
Figure 19 Existing sampling point
7/30/2019 Pgb Internship 2012
28/33
28
Industrial training report
6.2.4 Site visit schedule wasteSelection for contractor for schedule waste management is subject to open
bidding. The contractors that present for the site visit were from Hiap Huat
Chemicals and Kualiti Alam. The intent for the site visit is to clarify scope of work
for the contractor. One of the key points of the 14 pages document is the safety
rule set by PGB. They must submit a proposal that includes nine basic points:
a) Company policy on safetyb) Detail method statement and other standard documentationc) Certificate of competencyd) List of manpower with their I/C and contact no.e) Schedule of workf) Job Safety Analysis (JSA), where highlight of potential hazard and its
preventive method
g) List of vehicle to be used inclusive of copy drivers license and PuspakomInspection Certification
h) Copy of Worker Protection Scheme (SOCSO) for all workers involvedi) PETRONAS-NIOSH Safety Passport (NPSP) for all workers
After the meeting, technician, Mr Fazley led the contractors to visit schedule waste
site. The present schedule waste includes:
a) Spent filter/contaminated rag (SW410) 2000b)
Oil residue from oil and grease interceptor (SW 312) 48000kg
All the schedule waste should be disposed by Kualiti Alam or recycle by authorized
company. By interviewing the contractors, it is found that Hiap Huat Chemicals
intended to recycle the oil residue to second grade oil. The second grade oil can be
used as combustion fuel or basic component in paint. Kualiti Alam in the other hand
focuses on dispose the chemical.
7/30/2019 Pgb Internship 2012
29/33
29
Industrial training report
Figure 20 Schedule waste shed
Figure 21 Spent filter flammable label
7/30/2019 Pgb Internship 2012
30/33
30
Industrial training report
Figure 22 mixture of oil residue and water sample
6.2.5 Site visit to PETRONAS CUF Gebeng to collect demineralized waterCollecting demineralized water (demin water) at PETRONAS Centralized Utilities
Facilities (CUF) in Gebeng have given me the chance to see others PETRONAS
plant. demin water is exclusively used for turbine engine cleanup procedure.
Also known as deionized water, it is a water type that has its mineral ions
removed, such as cations from sodium, calcium, iron, copper and anions such as
chloride and bromide. With four others, we travelled by pickup truck to Gebeng.
The PETRONAS CUF provided PETRONAS and others plants utilities for everyday
operation. Examples of utilities are electricity, steam, nitrogen, oxygen,
dematerialized water, cooling water, boiler feed water and raw water. Although
it is not quite what engineers are expected to do, but travelling with work
colleague is essential experience and it open chances to get to know them
better.
CUF plants at Kerteh and Gebeng have successfully commenced operations and
the supplying of utilities to the intergrated Petrochemical Complexes (IPCs) in
stages since November 1999. The plants first came on-operation with the first
delivery of electricity on 19 November 1999 for Gebeng and 27 January 2000 for
Kertih. The Heat Recovery Steam Generator system was brought online in Ketih
in June 2000 and Gebeng in August 2000. This was followed by the Air
Separation Unit (ASU 1) plant which produces gases low pressure nitrogen and
oxygen to the IPC customers. The dematerialized Water and Waste Water
Treatment plants were commissioned in July 2000 and August 2000
respectively.
7/30/2019 Pgb Internship 2012
31/33
31
Industrial training report
4 main units to produce respective utilities includes, Co generation unit (steam,
electricity), Air Separation Unit (oxygen, nitrogen, argon), Waste Treatment Unit
(Demineralized, cooling, potable and boiler feed water) and Waste Water
Treatment Unit (treatment of waste water).
7. Problem encountered and ways overcoming itThere are many problems that we faced in everyday life and whats important is how we tackle it.
Settling in as new staff at KTNCS is the first problem that I faced here. Since I didnt know anybody and
relatively fresh in the engineering world, I have to prove to everyone and most importantly my
supervisor that I really am interested in this field. Overcoming the problem is really are simple, being
friendly, show respect and other positive attitudes are the key. First impression is important, and make
sure they get the right one. Besides, always volunteer and make ourselves available to work, this
attitude helps greatly to promote ourselves and gain experiences. Another problem is the work scope
that I should be involved during these 10 weeks internship period. Not having program planned for me is
one thing, and the fact that the station concentrate mainly on the mechanical and electrical work is the
other. A discussion between me and my supervisor help to encounter this problem. To me, I did not
have any problem learning all these mechanical equipment, such as turbine and compressor parts again
as I think its going to help me big time in the future. The compressor and turbine are also important
equipments in oil and gas industry, and by having knowledge regarding it, Im going to have a big
advantage. For my supervisor, he wants me to take this chance to learn as many things as I can here.
The internship period is also a problem. 10 weeks is a short period, compared to some universities that
sent their student for 8 months, so hard work is needed to make sure that the time is used wisely. All
these problem arises before I even started the internship. Overcoming all these, I started joining the
activities and gain some experiences. Other problems also arises, such as during mechanical
maintenance. Not knowing the parts and even how it operates makes maintenance work confusing and
hard to me. To overcome this, I make sure that I asked the technician all the things that I didnt know
and make effort to study its manual book. The Solar Turbine, Dresser-Rand Compressor looks
complicated at first but studying it, everything became simpler. Besides that, during project progress,
some problem also arises. I have no knowledge at all regarding pressure safety valve. The pressure
safety valve could be understood easily by using Wikipedia on the internet, but to locate it at the site, I
need help from my colleagues. Luckily, they all are very helpful and I managed to finish the project
ahead of schedule.
7/30/2019 Pgb Internship 2012
32/33
32
Industrial training report
8. Lessons learnedThere are too many lessons that I learned from the first day I reported to duty. From activities that I
joined, I was able to gain knowledge of performing engineering tasks. Being able to compliment many ofthe theories that I learned before, such as valves, piping, and control system was amazingly fun and
challenging. The newly acquired knowledge was also a big plus for me as a fresh member in this field.
Being actively involved in the activities also helps improve my personal soft skills. Being able to
communicate with contractors, colleague and organizing event helps me greatly in planting self belief
and interaction skills. Respecting older colleague was also valuable lesson that I learned. Having a
positive relationship with them trough this internship period helps me greatly. I made them aware of my
hunger for knowledge and theyre more than happy to share theirs. Respecting others opinion is
important although sometimes we didnt share the same view on things.
Besides that, through the project assigned, I learn to bear responsibility and handle pressure. To make
sure that the project finish on time, it is important to make sure that proper planning is made. I needed
to make sure that the project is in progress although I wanted to involve in other activity. This is the
responsibility that I need to take in order to make the project a success. The project sometimes having
its rough patch, easiest example is when sometimes reference is needed and the required data is not
there. There are also others, such as the exact location of the valves, where to look for further
reference, and whats needed in the data. Thankfully all of these were sorted out by the help of my
colleague. Each of my questions is answered easily, thanks to their wide experience at the station.
Last but not least, by undergoing internship here, I was treated to a grand introduction of natural gas
transmission industry. The flow of PETRONAS gas transmission which is so distant before has become
crystal clear to me.
9. SuggestionsHere are some suggestions that can be useful in the future. First and foremost, being friendly, show
respect and other positive attitudes are important if you really serious to learn. Always volunteer and
make ourselves available to work whenever the opportunities come, dont expect others to ask you. In
reality, the only person that can help us is ourselves. Besides that, I think that the student progress
during internship is time constrained. The time provided is too short, and not much progress can be
made. The student knowledge might be wider, but theres not much activity and task that they can join
because of this. I suggest that the internship period for the students in the future should be longer,approximately six to eight months.
7/30/2019 Pgb Internship 2012
33/33
33
10.ConclusionThis internship period has been a successful and enjoyment journey for me. Many positive points have
been taken from my first taste working in this engineering field. Many of these outcomes surely will be
useful tools for me to perform the final year project next semester. Although the period is too short, the
experience gained is vastly big and invaluable for me. Furthermore these experiences will also act useful
guide for me in determining my direction after completing my degree.
11.ReferencesDresser-Rand Service Manual, Solar Turbines, Inc./Brown&Root Eng. PETRONAS Kuantan Station,
Malaysia
Operation and Routine Maintenance Course, Mars Gas Turbine Mechanical-Drive Set, Solar Turbines
Anonymous, history, Retrieved online fromhttp://www.petronasgas.com/Pages/History.aspx, Jult 17th
,
2012
12.List of AppendicesAppendix A Relevant Figures
A.1 - KTNCS layout
A.2 - Inner gas seal diagram
A.3 - Piping symbols
A.4 - Letter designations
A.5 - P&ID dry gas seal
A.6 - Dresser-rand 50PDI
http://www.petronasgas.com/Pages/History.aspxhttp://www.petronasgas.com/Pages/History.aspxhttp://www.petronasgas.com/Pages/History.aspxhttp://www.petronasgas.com/Pages/History.aspx