Upload
voduong
View
219
Download
1
Embed Size (px)
Citation preview
M/S. BELLFIELD POWER INCEPTION PRIVATE LIMITED
Pre-Feasibility Report requiring Environmental Clearance for New 23 MW Power Plant at Survey No. 1382/1, 1382/2, 1383/1, 1383/2, & 1413/1P, Village: Naika, Taluka & Dist: Kheda (Gujarat).
MARCH, 2017
Kadam Environmental Consultants w w w . ka d a m en v i r o . c o m
Envi ronment for Deve lopment
M/S. BPIPL PFR – NEW POWER PLANT OF 23 MW AT VILLAGE: NAIKA, TALUKA &
DIST: KHEDA (GUJARAT) QUALITY CONTROL
SHEET
KADAM ENVIRONMENTAL CONSULTANTS | MARCH, 2017 II
M/S. BELLFIELD POWER INCEPTION PRIVATE LIMITED
Pre-Feasibility Report requiring Environmental Clearance for New 23 MW Power Plant at Survey No. 1382/1, 1382/2, 1383/1, 1383/2, & 1413/1P, Village: Naika, Taluka & Dist: Kheda (Gujarat). © Kadam Environmental Consultants (‘Kadam’), March, 2017.
This report is released for the use of the M/s. Bellfield Power Inception Private Limited (BPIPL),
Regulators and relevant stakeholders solely as part of the subject project’s Environmental
Clearance process. Information provided (unless attributed to referenced third parties) is
otherwise copyrighted and shall not be used for any other purpose without the written consent of
Kadam.
PROJECT DETAILS
Name of
Publication
Pre-Feasibility Report requiring Environmental Clearance for new 23 MW Power Plant at Survey No. 1382/1, 1382/2, 1383/1, 1383/2, & 1413/1P, Village: Naika, Taluka & Dist:
Kheda (Gujarat). Project
Number 1727721906 Report No. 1 Version 1 Released
March,
2017
Prepared &
Managed By
Bhavin Jambucha, Vaibhav
Rana & BPIPL Representatives Released By Sangram Kadam
CONTACT DETAILS
Vadodara (Head Office)
871/B/3, GIDC Makarpura, Vadodara, India – 390 010.
E: [email protected]; T:+91-265-3001000; F: +91-265-3001069
Delhi / NCR
Spaze IT Park, Unit No. 1124, IIth Floor, Tower B3, Sector 49, Near Omaxe City Centre Mall, Sohna Road,
Gurgaon, Haryana, INDIA - 122002.
E: [email protected]; T: +91-124-4242430 to 436; F:+91-124-4242433
DISCLAIMER
Kadam has taken all reasonable precautions in the preparation of this report as per its auditable quality
plan. Kadam also believes that the facts presented in the report are accurate as on the date it was written.
However, it is impossible to dismiss absolutely, the possibility of errors or omissions. Kadam therefore
specifically disclaims any liability resulting from the use or application of the information contained in this
report. The information is not intended to serve as legal advice related to the individual situation.
M/S. BPIPL PFR – NEW POWER PLANT OF 23 MW AT VILLAGE: NAIKA, TALUKA &
DIST: KHEDA (GUJARAT) TABLE OF CONTENT
KADAM ENVIRONMENTAL CONSULTANTS | MARCH, 2017 III
CONTENTS
1 EXECUTIVE SUMMARY ............................................................................ 1
1.1 PLANT FEATURES AND PRODUCTION CAPACITY ..................................................... 1
1.2 INFRASTRUCTURE ................................................................................... 1
1.3 UTILITY ............................................................................................. 1
1.4 ENVIRONMENT ....................................................................................... 2
1.5 SENSITIVITY ......................................................................................... 2
1.6 CONCLUSION ........................................................................................ 2
2 INTRODUCTION ..................................................................................... 3
2.1 IDENTIFICATION OF PROJECT PROPONENT & PROJECT ............................................. 3
2.1.1 Project Proponent ........................................................................... 3
2.1.2 Proposed Project ............................................................................ 3
2.2 BRIEF DESCRIPTION OF NATURE OF THE PROJECT .................................................. 3
2.3 NEED FOR THE PROJECT AND ITS IMPORTANCE TO THE COUNTRY & REGION ...................... 3
2.4 DEMAND & SUPPLY GAP ............................................................................. 3
2.5 EXPORT POSSIBILITY ................................................................................ 3
2.5.1 Domestic / Export Market ................................................................. 3
2.6 EMPLOYMENT GENERATION (DIRECT & INDIRECT) DUE TO THE PROJECT .......................... 4
3 PROJECT DESCRIPTION .......................................................................... 5
3.1 TYPE OF PROJECT ................................................................................... 5
3.2 LOCATION OF THE PROJECT ......................................................................... 5
3.3 DETAILS OF ALTERNATE SITES CONSIDERED ........................................................ 6
3.3.1 Alternate Fuel ................................................................................ 7
3.4 SIZE OR MAGNITUDE OF OPERATION................................................................ 7
3.5 PROJECT DESCRIPTION WITH PROCESS DETAILS – 23 MW POWER PLANT ........................ 8
3.6 RESOURCE OPTIMIZATION/ RECYCLING AND REUSE ................................................ 9
3.7 UTILITIES ........................................................................................... 9
3.7.1 Power Requirement ......................................................................... 9
3.7.2 Fuel Requirement ........................................................................... 9
3.7.3 Water Requirement ......................................................................... 9
3.7.4 Storage Details ............................................................................. 10
3.8 POLLUTION LOAD ON ENVIRONMENT DUE TO PROJECT ............................................ 10
3.8.1 Air Emissions & Control ................................................................... 10
3.8.2 Noise Generation ........................................................................... 12
3.8.3 Waste Water Generation .................................................................. 12
3.8.4 Hazardous Waste and Other Solid Waste .............................................. 12
4 SITE ANALYSIS .................................................................................... 13
4.1 CONNECTIVITY ..................................................................................... 13
4.1.1 By Road ...................................................................................... 13
4.1.2 By Rail ....................................................................................... 13
4.1.3 By Air ........................................................................................ 13
4.2 LAND FORM, LAND USE & LAND OWNERSHIP ...................................................... 13
4.3 TOPOGRAPHY ....................................................................................... 13
4.4 EXISTING LANDUSE PATTERN WITH SENSITIVITY TABLE ........................................... 13
M/S. BPIPL PFR – NEW POWER PLANT OF 23 MW AT VILLAGE: NAIKA, TALUKA &
DIST: KHEDA (GUJARAT) TABLE OF CONTENT
KADAM ENVIRONMENTAL CONSULTANTS | MARCH, 2017 IV
4.5 EXISTING INFRASTRUCTURE ........................................................................ 15
4.6 SOIL CLASSIFICATION, GEOLOGY, DRAINAGE, TOPOGRAPHY ...................................... 15
4.6.1 Soil Classification ........................................................................... 15
4.6.2 Geology ...................................................................................... 15
4.6.3 Drainage ..................................................................................... 16
4.6.4 Topography ................................................................................. 17
4.7 CLIMATIC DATA FROM SECONDARY SOURCES ....................................................... 17
4.8 SOCIAL INFRASTRUCTURE AVAILABLE .............................................................. 19
5 PLANNING BRIEF ................................................................................. 20
5.1 PLANNING CONCEPT ................................................................................ 20
5.2 POPULATION PROJECTION .......................................................................... 20
5.3 LAND USE PLANNING ............................................................................... 20
5.4 ASSESSMENT OF INFRASTRUCTURE DEMAND (PHYSICAL & SOCIAL) ............................... 20
5.5 AMENITIES/FACILITIES ............................................................................. 20
6 PROPOSED INFRASTRUCTURE ............................................................... 21
6.1 INDUSTRIAL AREA (PROCESSING AREA)............................................................ 21
6.2 NON-PROCESSING AREA ........................................................................... 21
6.3 GREEN BELT ........................................................................................ 21
6.4 SOCIAL INFRASTRUCTURE .......................................................................... 21
6.5 CONNECTIVITY ..................................................................................... 21
6.6 DRINKING WATER MANAGEMENT .................................................................. 21
6.7 SEWAGE SYSTEM ................................................................................... 21
6.8 INDUSTRIAL WASTE & SOLID WASTE MANAGEMENT .............................................. 21
6.9 POWER REQUIREMENT & SUPPLY / SOURCE ....................................................... 21
7 REHABILITATION AND RESETTLEMENTS (R& R) PLAN .............................. 22
8 PROJECT SCHEDULE AND COST ESTIMATE ............................................... 23
8.1 LIKELY DATE OF START OF CONSTRUCTION AND LIKELY DATA OF COMPLETION .................... 23
8.2 ESTIMATED PROJECT COST ........................................................................ 23
8.2.1 Profitability .................................................................................. 24
9 ANALYSIS OF PROPOSAL ...................................................................... 25
9.1 FINANCIAL AND SOCIAL BENEFITS.................................................................. 25
M/S. BPIPL PFR – NEW POWER PLANT OF 23 MW AT VILLAGE: NAIKA, TALUKA &
DIST: KHEDA (GUJARAT) TABLE OF CONTENT
KADAM ENVIRONMENTAL CONSULTANTS | MARCH, 2017 V
ANNEXURES
Annexure 1: Willingness Letters – Rice Mills ............................................................................ 27
Annexure 2: Site Layout Map ................................................................................................. 34
Annexure 3: Project Site Located on Toposheet No. F43G5, F43G6, F43G569 & F43G10............. 35
Annexure 4: Draft Landuse Map ............................................................................................. 36
Annexure 5: Long Term Meteorological Data – IMD Ahmedabad ............................................... 37
LIST OF TABLES
Table 2-1: List of Directors and Their Designations .................................................................... 3
Table 3-1: Co-ordinates of Site Boundary .................................................................................. 6
Table 3-2: Availability of Rice Husk in Three Districts ................................................................. 7
Table 3-3: Availability of Rice Husk in Nearby Vicinity ................................................................ 7
Table 3-4: Tentative Area Breakup ........................................................................................... 7
Table 3-5: Details of Main Raw Material Quantity and Means of Storage ...................................... 9
Table 3-6: Details of Stacks, Fuel Used and APCM attached to Flue Gas Stacks .......................... 11
Table 4-1: Details of Nearby Ponds/River ................................................................................ 13
Table 4-2: Details of Nearby Villages/Town ............................................................................. 13
Table 4-3: Nearest Sensitive Ecological Features ..................................................................... 14
Table 4-4: Geology of Kheda District ...................................................................................... 15
Table 4-5: Geology of Ahmedabad District .............................................................................. 16
Table 4-6: Predominant Wind Direction IMD Ahmedabad ......................................................... 17
Table 4-7: Average Meteorological Condition at IMD Ahmedabad (1961-1990) .......................... 18
Table 8-1: Tentative Project Time Schedule ............................................................................ 23
Table 8-2: Cost Break-up ....................................................................................................... 23
LIST OF FIGURES
Figure 3-1: General Location of Proposed Project Site ................................................................ 5
Figure 3-2: Specific Location Showing Proposed Project ............................................................. 6
Figure 3-3: Process Flow Diagram – Proposed Power Plant ......................................................... 8
M/S. BPIPL PFR – NEW POWER PLANT OF 23 MW AT VILLAGE: NAIKA, TALUKA &
DIST: KHEDA (GUJARAT) EXECUTIVE SUMMARY
KADAM ENVIRONMENTAL CONSULTANTS | MARCH, 2017 1
1 EXECUTIVE SUMMARY
Bellfield Power Inception Private Limited (BPIPL) proposes to set up a new 23 MW power plant at
Survey No. 1382/1, 1382/2, 1383/1, 1383/2, & 1413/1P, Village: Naika, Taluka & Dist: Kheda in
Gujarat. Promoter of the proposed project are Mr. Kailash Agrawal & Mr. Jitendra Agrawal.
Plot area of the proposed project consists of 16,844 m2. Around 33.6 % (~5,665 m2) of total plot
area will be developed as greenbelt. The project cost is estimated to be around INR 73.9 Crore.
As per the EIA notification dated 14th September, 2006, as amended till date, the proposed
products falls in category including Project / Activity: 1(d) – Thermal Power Plant. This project
shall be treated as Category “B”.
1.1 Plant Features and Production Capacity
The Imported Coal & Rice Husk will be fed to furnace of the AFBC Boilers (2 x 55 TPH). The fuel
mix (Ratio 70:30) will be fired in the furnace. The saturated steam is generated in the Boiler drum
and passed to the Primary, Secondary & In-bed super heaters to get the superheated steam from
the Boilers. The superheated steam is fed to the Steam Turbine and it rotates the steam Turbine.
The steam Turbine is coupled with Reduction gears and Alternators. The power of 23 MW will be
generated in the Alternators and distributed to the nearby industries and textile units.
Coal & husk will have the separate storage area. Fly ash & bottom ash generated shall be
disposed off as per the fly ash notification as amended till date. Plant will have no effluent
discharge, hence meeting Zero Liquid Discharge norms. Flue gas shall meet the statutory norms.
Design of ESPs will be as per the state government norms.
1.2 Infrastructure
The proposed power plant will mainly comprise of Boiler House consisting of AFBC Boilers, Steam
Turbine, Alternator / Generator, Fuel storage area, Utility Area consisting of cooling tower,
compressors, ESP section, ETP (RO & MEE) area & Fly ash & Hazardous waste storage area.
1.3 Utility
Power: Auxiliary Power requirement of ~ 1.5 MW will be sourced from DG Sets / UGVCL and will
be used as standby back-up supply for emergency conditions & safe shutdown of power plant in
case of main power failure.
Steam: Steam requirement of 20-40 Tons in adjoining industries and textile units shall be met.
Fuel: For startup purposes, HSD will be used as fuel. During operation phase, Rice Husk based on
availability & imported coal and will be used. Maximum blending ratio of coal to husk shall be
maintained to 70:30, as per the availability of Husk. In such case, 365 TPD Indonesian coal & 200
TPD rice husk will be required.
Raw Water: Water requirement of 384 KLD will be met from existing bore wells (2 Nos).
Manpower: During the construction phase around 100 workers will be hired. During operation
phase, project will generate direct employment for more than 50 people and indirect employment
for approximately 25 people.
M/S. BPIPL PFR – NEW POWER PLANT OF 23 MW AT VILLAGE: NAIKA, TALUKA &
DIST: KHEDA (GUJARAT) EXECUTIVE SUMMARY
KADAM ENVIRONMENTAL CONSULTANTS | MARCH, 2017 2
1.4 Environment
Environmental issues associated with proposed units are:
Air Emissions: As, point source emissions, likely air pollutants from proposed project are
SPM, SO2 & NOx from flue gas stack attached to boilers. Adequate APC equipment like ESP will
be provided. Adequate stack height will be provided.
Wastewater: Waste water generation will be 137 KLD which will be fully recycled and
reutilized to achieve zero liquid discharge.
Solid & Hazardous Waste: Fly ash & bottom ash (~21,000 TPA) will be generated from
burning of fuel in boilers, which shall be stored in closed storage silos and sold to brick
manufacturers and cement industry.
1.5 Sensitivity
There are around 7 water bodies including 2 rivers namely Sabarmati & Vatrak river within 10 Km
of the project site. There are around 24 villages in the surround of 10 Km from the project site.
There are no National Park/Wildlife Sanctuary, Tiger Reserve/Elephant Reserve / Turtle Nesting
Ground, Core Zone of Biosphere Reserve, Habitat for migratory birds, Estuary/Sea/Mangroves,
Mountains/Hills, Reserve Forest, Defense Installations, Airports, Railway Lines within 10 Km of the
project site.
Site is well connected to Ahmedabad via SH-140 which is 0.15 Km in E Direction from site. Major
railway station for public transportation is Nadiyad Railway Station located at an aerial distance of
~30 Km in ESE direction from the project site. Other nearest railway station is Kheda Railway
Station at ~11.5 Km from the project site in E Direction. Nearest airport from project site is
Ahmedabad Airport located at an aerial distance of ~ 34 Km in NNE direction, which operate
flights to most of the large cities in India.
1.6 Conclusion
Demand of power and steam in nearby industries and textile units is envisaged. No power plant is
available in the region and these units have to rely on the grid power and own small boilers.
During the lean period, husk will be used as per its availability. Currently it is being used by many
nearby brick manufacturers for burning purpose. In such small scale industries, APCM are
generally not available. In case, if the same fuel (if used) in the proposed power plant, the
emissions from the stack will be controlled and shall meet the GPCB norms easily, with online
reporting of emissions.
Thus, if this project comes up, it will have social, financial benefits and will be environmentally
sustainable.
Pre-feasibility study confirm the viability of the project.
M/S. BPIPL PFR – NEW POWER PLANT OF 23 MW AT VILLAGE: NAIKA, TALUKA &
DIST: KHEDA (GUJARAT) INTRODUCTION
KADAM ENVIRONMENTAL CONSULTANTS | MARCH, 2017 3
2 INTRODUCTION
2.1 Identification of Project Proponent & Project
2.1.1 Project Proponent
Promoter of the proposed project are Mr. Kailash Agrawal & Mr. Jitendra Agrawal. List of directors
along with their designation is given in Table 2-1.
Table 2-1: List of Directors and Their Designations
S. No. Name Designation
1 Kailash Tarachand Agrawal Director
2 Jitendra Tarachand Agrawal Director
Mr. Kailash Agrawal is the key founder of the company. His experience in business management
runs more than 30 years, giving the maturity to the group from the initial stage. His visions and
his principles lay the foundation for this company. He is on the panel of various leading business
organizations.
Mr. Jitendra Agrawal has been involved in various projects for product conceptualization, Brand
perception & positioning. He is an active member of various reputed committees. He helps in
formulating the company’s sales and marketing strategy as well as overseas operations.
2.1.2 Proposed Project
The proposed project is for new power plant of 23 MW. It will be based on state-of-the-art,
environment friendly blending of fuel namely rice husk and imported coal.
2.2 Brief Description of nature of the Project
Proposed project is for development of new Power Plant.
2.3 Need for the Project and its Importance to the Country & Region
The proposed power plant is required to carter the power requirement of nearby industries and
textile units.
2.4 Demand & Supply Gap
Demand of power and steam in nearby industries and textile units is envisaged. No power plant is
available in the region and they have to rely on the grid power and own small boilers. Hence, to
fulfill their requirement, this power plant is proposed.
2.5 Export Possibility
Not envisaged.
2.5.1 Domestic / Export Market
Requirement of nearby industries and textile units will be fulfilled by this proposed power plant.
M/S. BPIPL PFR – NEW POWER PLANT OF 23 MW AT VILLAGE: NAIKA, TALUKA &
DIST: KHEDA (GUJARAT) INTRODUCTION
KADAM ENVIRONMENTAL CONSULTANTS | MARCH, 2017 4
2.6 Employment Generation (Direct & Indirect) due to the Project
During the construction phase around 100 workers will be hired. During operation phase, project
will generate direct employment for more than 50 people and indirect employment for
approximately 25 people.
M/S. BPIPL PFR – NEW POWER PLANT OF 23 MW AT VILLAGE: NAIKA, TALUKA &
DIST: KHEDA (GUJARAT) PROJECT DESCRIPTION
KADAM ENVIRONMENTAL CONSULTANTS | MARCH, 2017 5
3 PROJECT DESCRIPTION
3.1 Type of Project
As per the EIA notification dated 14th September, 2006, as amended till date, the proposed
products falls in category including Project / Activity: 1(d) – Thermal Power Plant. This project
shall be treated as Category “B”.
3.2 Location of the Project
Proposed project is located at Survey No. 1382/1, 1382/2, 1383/1, 1383/2, & 1413/1P, Village:
Naika, Taluka & Dist: Kheda in Gujarat. Land was purchased for thermal power plant from farmers
as per the market price. Change is landuse is envisaged from agriculture use to industrial use.
Location map showing general location of proposed project is given in Figure 3-1. Specific Map
showing project boundary is given in Figure 3-2. The co-ordinates of the project site are given in
Table 3-1.
Figure 3-1: General Location of Proposed Project Site
M/S. BPIPL PFR – NEW POWER PLANT OF 23 MW AT VILLAGE: NAIKA, TALUKA &
DIST: KHEDA (GUJARAT) PROJECT DESCRIPTION
KADAM ENVIRONMENTAL CONSULTANTS | MARCH, 2017 6
Figure 3-2: Specific Location Showing Proposed Project
Table 3-1: Co-ordinates of Site Boundary
POINT LATITUDE LONGITUDE
A 22°45'55.16"N 72°34'12.89"E
B 22°45'55.76"N 72°34'15.55"E
C 22°45'55.38"N 72°34'16.40"E
D 22°45'55.59"N 72°34'20.57"E
E 22°45'54.31"N 72°34'19.67"E
F 22°45'54.57"N 72°34'18.71"E
G 22°45'53.21"N 72°34'18.15"E
H 22°45'53.25"N 72°34'17.73"E
I 22°45'52.10"N 72°34'17.25"E
J 22°45'52.28"N 72°34'15.95"E
K 22°45'51.62"N 72°34'15.77"E
L 22°45'51.36"N 72°34'16.84"E
M 22°45'51.21"N 72°34'16.79"E
N 22°45'51.06"N 72°34'14.05"E
O 22°45'52.62"N 72°34'14.02"E
3.3 Details of Alternate Sites Considered
No alternative sites were assessed, since the power & steam requirement is envisaged in the
nearby industries and textile units.
M/S. BPIPL PFR – NEW POWER PLANT OF 23 MW AT VILLAGE: NAIKA, TALUKA &
DIST: KHEDA (GUJARAT) PROJECT DESCRIPTION
KADAM ENVIRONMENTAL CONSULTANTS | MARCH, 2017 7
3.3.1 Alternate Fuel
Since the project site is being surrounded by agricultural fields, a study was conducted to identify
the possibilities of using rice husk as an alternate fuel.
Based on production and productivity of rice in the surrounding area of the project data up to year
2011 and considering 20% husk of total grain weight, the area, production and husk potentiality is
given in Table 3-2.
Table 3-2: Availability of Rice Husk in Three Districts
S.
No. District Area in Ha.
Production of
Paddy in TPA
Production Potential of
Husk in TPA
1 Ahmedabad 1,03,500 2,73,600 54,720
2 Kheda 87,700 1,85,200 37,040
3 Anand 86,200 2,09,800 41,960
Total 2,77,400 4,85,252 1,33,720
In the surrounding area paddy (kharif)-paddy (summer) and paddy (kharif)-wheat (winter) crop
rotations are taken. The exact location of the Power Plant is in western corner of the Textile Park.
The cultivated area surrounding the Power Plant is about 250-300m in West & North; 500m in
East and 100m in South (surrounded by ONGC Godown and main road).
Rice mills in nearby vicinity are willing to supply rice husk to the proposed project. Details of the
same is tabulated in Table 3-3. Willingness letters are attached as Annexure 1.
Table 3-3: Availability of Rice Husk in Nearby Vicinity
S.
No. Name of Mill Village
Distance in Km / Direction
from Project Site
Likely Capacity
(TPM)
1 Kedar Nath Rice Mill Naz NA 700
2 A M Agro Jetalpur 13.0 / N 800
3 Akshar Rice Mill Jetalpur 13.0 / N 650
4 Baldev Krupa Rice Mill Jetalpur 13.0 / N 900
5 Jagatnath Agro Umiyapur 13.5 / NNE 750
6 Anarbath Rice Mill Jetalpur 13.0 / N 500
7 Keshav Laxmi Rice Mill Jetalpur 13.0 / N 800
Many such owners will be further met and this will fulfill the requirement of total rice husk in the
project. Excess quantity of rice husk will be stored during the lean period of four to five months
(March-July) by the individual rice mill owners.
3.4 Size or Magnitude of Operation
Plot area of the proposed project consists of 16,844 m2. It is proposed to set up 23 MW of power
plant. Site layout plant is shown in Annexure 2. Tentative area breakup of the site is as per
Table 3-4.
Table 3-4: Tentative Area Breakup
S. No. Description Area (m2) Percentage of Total Area
1 TG Building 798 4.7%
2 Coal & Husk Storage Yard 1,727 10.3%
3 Road 2,773 16.5%
4 Green Belt 5,665 33.6%
5 ACC 990 5.9%
M/S. BPIPL PFR – NEW POWER PLANT OF 23 MW AT VILLAGE: NAIKA, TALUKA &
DIST: KHEDA (GUJARAT) PROJECT DESCRIPTION
KADAM ENVIRONMENTAL CONSULTANTS | MARCH, 2017 8
S. No. Description Area (m2) Percentage of Total Area
6 ETP 209 1.2%
7 Water Treatment Plant 197 1.2%
8 Boiler 1,534 9.1%
9 Open Space 2,951 17.5%
Total 16,844
3.5 Project Description with Process Details – 23 MW Power Plant
The Imported Coal (4,200 GCV) & Rice Husk (3,000 GCV) will be fed to furnace of the AFBC
Boilers (2 x 55 TPH) through RAV & DCF from the Coal Bunker & Rice husk storage. The fuel mix
(Ratio 70:30) will be fired in the furnace by means of FD-Fan air. The saturated steam is
generated in the Boiler drum and passed to the Primary, Secondary & In-bed super heaters to get
the superheated steam @ 510°C & 89 kg/cm2 from the Boilers. The superheated steam is fed to
the Steam Turbine and it rotates the steam Turbine at the speed of ~7,000 rpm. The steam
Turbine is coupled with Reduction gears and Alternators. The power of 23 MW will be generated in
the Alternators and distributed to the nearby industries and textile units. Flue gas shall meet the
statutory norms. Design of ESPs will be as per the state government norms. General process flow
diagram of power plant is given in Figure 3-3.
Figure 3-3: Process Flow Diagram – Proposed Power Plant
Coal Handling System
Coal from the coal wagons will be unloaded by Tipplers in the coal handling plant. This coal will be
transported up to the coal storage bunkers through conveyor belts. Coal will be then transported
to the Crush house by conveyor belts where it will be crushed to small pieces and light dust will be
separated. The crushed coal will be then transported to the bowl mill by coal feeders. In the bowl
mill, coal will be grounded to a powder form. The mill consists of a round metallic table on which
coal particles fall. The crushed coal will be then taken to the Boiler through coal pipes with the
M/S. BPIPL PFR – NEW POWER PLANT OF 23 MW AT VILLAGE: NAIKA, TALUKA &
DIST: KHEDA (GUJARAT) PROJECT DESCRIPTION
KADAM ENVIRONMENTAL CONSULTANTS | MARCH, 2017 9
help of hot and cold air mixture. Ducon systems are custom engineered solutions, utilizing its
advanced equipment components, that provide low maintenance and operating costs.
Ash Handling System
The fly ash produced from combustion will be collected at various locations such as economizer,
air preheater, electrostatic precipitators, etc. along with bottom ash and shall be transported
pneumatically with the help of dense phase pneumatic pumps to closed storage silos. The Fly Ash
shall be sold to brick manufacturers and cement industry. Bottom Ash is partly recycled after
screening and balance will be sold to the cement industry. RCC silos will be provided having
storage capacity of 200 m3 (for 3 days of storage) to store Fly Ash.
Dust collection system will be installed at transfer tower, crusher house, top of silo & bunker
tower. Adequate capacities of bag filters will be provided to avoid dusting.
3.6 Resource Optimization/ Recycling and Reuse
Steam condensate will be recycled back into the process. There will not be any generation of
process effluent. About 90% cooling tower blow down would be recycled back to the process by
installing RO & MEE. Thus water consumption will be minimal Details of the same shall be shall be
provided in EIA report.
3.7 Utilities
The estimated list of utilities required for the project is as given below:
3.7.1 Power Requirement
Auxiliary Power requirement of ~ 1.5 MW will be sourced from DG Sets / UGVCL and will be used
as standby back-up supply for emergency conditions & safe shutdown of power plant in case of
main power failure.
3.7.2 Fuel Requirement
For startup purposes, HSD will be used as fuel. During operation phase, Rice Husk based on
availability & imported coal and will be used.
Details of fuel along with the quantity and means of storage is given in Table 3-5.
Table 3-5: Details of Main Raw Material Quantity and Means of Storage
S.
No. Name of Fuel
Consumption
MTPD
Physical
State Source
Means of
Transportation
1 Imported Coal (Indonesian) 365 Solid Local Supplier Trucks
2 Rice Husk 200 Solid Local Rice Mill
Suppliers Tractors (2 Tons)
3 HSD 400 LPH Liquid Local -
3.7.3 Water Requirement
Water requirement of 384 KLD will be met from existing bore wells (2 Nos). Prior permission from
CGWA will be taken. Application of the same is ready and shall be submitted after receiving TOR
for the project.
M/S. BPIPL PFR – NEW POWER PLANT OF 23 MW AT VILLAGE: NAIKA, TALUKA &
DIST: KHEDA (GUJARAT) PROJECT DESCRIPTION
KADAM ENVIRONMENTAL CONSULTANTS | MARCH, 2017 10
3.7.4 Storage Details
Coal & Husk Storage
Storage space of 1,260 m2 will be provided to store Coal & Rice Husk.
HSD Storage
HSD will be stored in drums placed near to DG sets.
Fly Ash Storage
RCC silos will be provided having storage capacity of 200 m3 (for 3 days of storage) to store Fly
Ash.
3.8 Pollution Load on Environment due to Project
Environmental issues associated with power plants include:
Air emissions;
Wastewater;
Solid Wastes.
3.8.1 Air Emissions & Control
Volume Source
SPM emission from coal & husk storage yard is envisaged as volume source emissions.
Fugitive Emissions
No fugitive emissions envisaged in the project.
Line Source Emissions
During construction phase, vehicular emissions like CO & HC’s will be generated as line source
emissions. Other emissions will be from use of construction machinery. Apart from it, application
of heavy machinery and earth movers will generate emissions. Suitable dust suppression
techniques such as water sprinkling will be taken at these times as relevant.
During operation phase, vehicular emissions due to transportation of raw materials and local travel
of employees are envisaged. Approximately, 30 trucks per day & 20 tractors per day carrying coal
& rice husk shall be using the SH – 140 connecting Ahmedabad & Kheda. Direct Freight Corridor is
also proposed near the site, which will be used to transport Coal in future.
Point Source
As, point source emissions, likely air pollutants from proposed project are SPM, SO2 & NOx from
flue gas stack attached to boilers. Adequate APC equipment like ESP will be provided. Adequate
stack height will be provided. Details of proposed stacks with fuel consumption and attached Air
Pollution Control Equipment are tabulated in Table 3-6.
The ambient air quality & stack emissions will be maintained as per GPCB/CPCB norms.
M/S. BPIPL PFR – NEW POWER PLANT OF 23 MW AT VILLAGE: NAIKA, TALUKA & DIST: KHEDA (GUJARAT) PROJECT DESCRIPTION
KADAM ENVIRONMENTAL CONSULTANTS | MARCH, 2017 11
Table 3-6: Details of Stacks, Fuel Used and APCM attached to Flue Gas Stacks
S.
No. Stack Attached to Fuel Used
Quantity
of Fuel APCM
Expected
Pollutants
Efficiency
of APCE
Stack
Height
(m)
Stack
Top Dia.
(m)
Exit
Temp.
(°C)
Exit
Velocity
(m/s)
1 Boiler 1 (55 TPH) Imported Coal & Husk 282.5 TPD* ESP SPM, SO2 & NOx 99.9 % 53 1.85 170 12.5
2 Boiler 2 (55 TPH) Imported Coal & Husk 282.5 TPD* ESP SPM, SO2 & NOx 99.9 % 53 1.83 170 12.5
3 DG Set – 1.5 MW (for
Emergency Purpose only) HSD 400 LPH
Adequate
Stack Height SPM, SO2 & NOx - 15 0.3 150 15
* Maximum blending ratio of coal to husk shall be maintained to 70:30, as per the availability of Husk.
M/S. BPIPL PFR – NEW POWER PLANT OF 23 MW AT VILLAGE: NAIKA, TALUKA &
DIST: KHEDA (GUJARAT) PROJECT DESCRIPTION
KADAM ENVIRONMENTAL CONSULTANTS | MARCH, 2017 12
3.8.2 Noise Generation
From the proposed project, noise shall be generated from the various activities. Source of noise
generation are:
The heavy machinery like crane, dumper, roller, bulldozers etc. will be used during daytime
during construction phase;
Operation of generators, compressors, pumps, blowers etc.;
Vehicle movement for transportation of raw material.
3.8.3 Waste Water Generation
Waste water generation will be 137 KLD which will be fully recycled and reutilized to achieve zero
liquid discharge. Capacities along with technical details of ROs & MEE shall be detailed out in EIA
report.
3.8.4 Hazardous Waste and Other Solid Waste
Fly ash & bottom ash will be generated from burning of fuel in boilers. The fly ash (~21,000 TPA)
shall be pneumatically collected with the help of dense phase pneumatic pumps to closed storage
silos and sold to brick manufacturers and cement industry. Bottom ash is partly recycled after
screening and balance will be sold to the cement industry. No other hazardous waste will be
generated from proposed power plant.
Facility for storage of hazardous waste having area of 50 m2 will be provided.
Other inorganic waste like:
Used paper and waste wood shall be recycled or reused through recyclers.
Waste metal shall be sold as scrap.
Waste plastic shall be sold to recyclers.
M/S. BPIPL PFR – NEW POWER PLANT OF 23 MW AT VILLAGE: NAIKA,
TALUKA & DIST: KHEDA (GUJARAT) SITE ANALYSIS
KADAM ENVIRONMENTAL CONSULTANTS | MARCH, 2017 13
4 SITE ANALYSIS
4.1 Connectivity
4.1.1 By Road
Site is well connected to Ahmedabad via SH-140 which is 0.15 Km in E Direction from site.
4.1.2 By Rail
Major railway station for public transportation is Nadiyad Railway Station located at an aerial
distance of ~30 Km in ESE direction from the project site. Other nearest railway station is Kheda
Railway Station at ~11.5 Km from the project site in E Direction.
4.1.3 By Air
Nearest airport from project site is Ahmedabad Airport located at an aerial distance of ~ 34 Km in
NNE direction, which operate flights to most of the large cities in India.
4.2 Land Form, Land use & Land Ownership
Land was purchased for thermal power plant from farmers as per the market price. Change is land
use is envisaged from agriculture use to industrial use.
4.3 Topography
Project site shown on Toposheet No. F43G5, F43G6, F43G9 & F43G10 is provided in Annexure 3.
4.4 Existing Landuse pattern with Sensitivity Table
Details of nearby water bodies is given in Table 4-1. Details of nearby villages/town is given in
Table 4-2.
Table 4-1: Details of Nearby Ponds/River
S. No. Rivers / Pond Distance in Km Direction From Site
1 Nayka Talav 1.9 W
2 Bherai Talav 2.9 E
3 Kathvada Talav 3.8 NNW
4 Phui Talav 7.4 ENE
5 Bareja Lake 9.5 NNE
6 Sabrmati River 3.8 W
7 Vatrak River 7.8 SSE
Table 4-2: Details of Nearby Villages/Town
S. No. Villages/ Town Distance in km Direction From Site
1 Nayka 1.8 SW
2 Shrijipura 1.9 S
3 Bherai 3.0 E
4 Navagam 3.1 NNE
M/S. BPIPL PFR – NEW POWER PLANT OF 23 MW AT VILLAGE: NAIKA,
TALUKA & DIST: KHEDA (GUJARAT) SITE ANALYSIS
KADAM ENVIRONMENTAL CONSULTANTS | MARCH, 2017 14
S. No. Villages/ Town Distance in km Direction From Site
5 Chitrasar 3.7 W
6 Damri 3.7 ESE
7 Dhathal 3.8 E
8 Kathvada 3.8 NNW
9 Dharoda 4.0 WNW
10 Kaloli 4.1 SW
11 Adsar 4.6 NNW
12 Pinglaj 5.3 ENE
13 Vadala 5.4 E
14 Kanera 6.8 NE
15 Mahijda 7.2 NNW
16 Radhu 7.3 S
17 Ambaliala 7.5 W
18 Sathal 8.2 WSW
19 Rasikpura 8.7 SW
20 Samadra 8.8 ENE
21 Bareja 8.9 NNE
22 Chandisar 9.0 WNW
23 Sarsa 9.1 NE
24 Vasai 9.4 NNW
Details of the important features along with other sensitive ecological locations from BPIPL in the
study area are provided in Table 4-3.
Table 4-3: Nearest Sensitive Ecological Features
S. No. Sensitive Ecological Features Location Distance (km) Direction
1. National Park/Wildlife Sanctuary - - -
2. Tiger Reserve/Elephant Reserve /
Turtle Nesting Ground - - -
3. Core Zone of Biosphere Reserve - - -
4. Habitat for migratory birds - - -
5. Lakes/Reservoir/Dams
Bherai Talav 2.9 E
Phui Talav 7.4 ENE
Bareja Lake 9.5 NNE
6. Stream/Rivers/Drains Sabrmati River 3.8 W
Vatrak River 7.8 SSE
7. Estuary/Sea/Mangroves - - -
8. Mountains/Hills - - -
9. Reserve Forest - - -
10. Defense Installations - - -
11. Airports - - -
12. Railway Lines - - -
13. National / State Highways NH-8 7.2 ENE
SH-140 0.15 E
M/S. BPIPL PFR – NEW POWER PLANT OF 23 MW AT VILLAGE: NAIKA,
TALUKA & DIST: KHEDA (GUJARAT) SITE ANALYSIS
KADAM ENVIRONMENTAL CONSULTANTS | MARCH, 2017 15
4.5 Existing Infrastructure
Site is well connected with the roads. Photographs of proposed site is given in Photographs 4-1.
Photographs 4-1: Photographs of Proposed Site
4.6 Soil Classification, Geology, Drainage, Topography
4.6.1 Soil Classification
The project area covers Ahmedabad & Kheda district of North Gujarat Agro-Climatic Zone-IV. These
zone districts fall under Agro-Ecological Zones 19 A (Ahmedabad) and 25 C (Kheda). The entire
project area is characterized by 70-80 cm rainfall, 1-3 % slope and soil depth is >100cm. The texture
of soil varies from loamy sand to loam and sporadically clay loam soils are seen especially in the
project area, the soils are having mainly illitic clay mineral and taxonomically these soils are classified
as Inceptisols of recent alluvium.
4.6.2 Geology
Geology of Kheda District is given in Table 4-4. Geology of Ahmedabad District Table 4-5.
Table 4-4: Geology of Kheda District1
Age Formations equivalent to Thickness in meters Lithology
HOLOCENE
Gujarat Alluvium Consisting;
Nal Sarovar Formation,
Jantral formation,
Varahi formation,
Mahuva formation,
Akhaj Formation,
Katpur formation and
Rann Clay formation
100
Soil, Alluvium, Brown
Sand, Flood Plan
deposits, Tidal Flat
deposits, delta and levee
deposits
POST MIOCENE
Jambusar formation 100 Coarse grained sand
with clay
Broach formation 125 Grayish brown clays
Jhagadia formation 300 Greenish grey Claystone
with minor coal
MIOCENE Kand formation 200 Claystone with sand
1
1 District Resource Map, Kheda District
M/S. BPIPL PFR – NEW POWER PLANT OF 23 MW AT VILLAGE: NAIKA,
TALUKA & DIST: KHEDA (GUJARAT) SITE ANALYSIS
KADAM ENVIRONMENTAL CONSULTANTS | MARCH, 2017 16
Age Formations equivalent to Thickness in meters Lithology
Babaguru formation 125 Clay stone with shale
with minor sandstone
Tarakeshwar formation 125 Shale with sand
UNCONFORMITY
OLIGOCENE TO
UPPER EOCENE Tarapur Shale 175 Shale with sandstone
UPPER EOCENE TO
MIDDLE EOCENE Kalol formation 250
Grey shale with silty
Sandstone, siltstone
with minor coal beds.
UNCONFORMITY
LOWER EOCENE Cambay Shale (Vagadkhol
formation) More than 1500 m
Dark Grey carbonaceous
shale which changes to
trap conglomerate
UNCONFORMITY
LOWER EOCENE
TO UPPER
CRETACEOS
Deccan Traps - Deccan Traps with inter
Trappean beds
Table 4-5: Geology of Ahmedabad District2
Lithology Formation/Group Age
Lacustrine, Channel fill, flood plain, tidal flat, spit
bar, tidal marsh deposits
Nal Sarovar, Jantral, Varahi,
Mahuva, katpur etc Holocene
Variegated Clay, Siltstone and marl Vend
formation Porbandar
Group Pleistocene
Oolitic to Sandy limestone with intercalated grit
and sandstone
Miliolite
formation
Unconformity
Basalt flow Deccan Volcanics Eocene to Upper
Cretaceous
4.6.3 Drainage
River in the South –East part is Vatrak arise from Dungerpur hills and meets Sabarmati at Vautha.
River in North-West Part is Sabarmati originates in the southwestern spurs of the Aravalli hills and
traverses a distance of 400 km through the districts of Sabarkantha, Ahmedabad and Kheda
before meeting the Gulf of Khambhat Interestingly, the river has in its upper reaches cliffy banks
rising up to 50 m. In its lower reaches, the river is seen to have frequently changed its course.
The Vatrak & Mesvo and Khari rivers are tributaries of Sabarmati. These different types of
drainage pattern mainly depend on the local geography, geology, structures and tectonics and
also it depends on the slope of the area. The area is under the influence of these river being the
main recharging source & controlling the drainage pattern.
1
2 District Resource Map, Ahmedabad and Gandhinagar Districts
M/S. BPIPL PFR – NEW POWER PLANT OF 23 MW AT VILLAGE: NAIKA,
TALUKA & DIST: KHEDA (GUJARAT) SITE ANALYSIS
KADAM ENVIRONMENTAL CONSULTANTS | MARCH, 2017 17
4.6.4 Topography
Ahmedabad District
Ahmedabad district as whole forms a level plain gradually rising towards the north and east where
the elevation varies between 17 m and 100 m above MSL. The southern portion of the district is
low lying area with the altitude ranging 12m to 22m above MSL, the mining leases falls in northern
part of the district in Detroj Rampura and Mandal Taluks.
Kheda District
The district is mostly occupied by Holocene sediments. These sediments are of marine, fluvial and
Aeolian origin. The marine sediments include the older tidal flats and tidal marsh of Rann Clay
formation and shoal, tidal flat and marsh of younger Mahuva Formation. The Fluvial sediments
include flood plain and delta of Katpur Formation and Channel-fill and flood plain of younger
Varahi Formation. The Aeolian sediments include stabilized sand sheet and sand dune of Akhaj
Formation and Sand sheet of Younger Jantarl Formation.
4.7 Climatic data from secondary sources
The climatic data is based on the long-term climatological tables (1961 – 1990) published by
Indian Meteorological Department (IMD) for Ahmedabad. A copy of the long-term climatological
data is enclosed as Annexure 5.
Temperature
The period from March to May is one of continuous increase in temperatures. May is generally the
hottest month with a mean daily maximum temperature of about 41.7°C and mean daily minimum
of about 26.2°C. The weather is intensely hot in summer and on some days the day temperature
may reach up to 45°C. The highest temperature recorded is 47.8°C on 27th May 1916.
From November, both day and night temperatures begin to decrease rapidly. January is generally
the coldest month with the mean daily maximum temperature at about 28.3°C and mean daily
minimum at about 11.9°C. Cold waves sometimes affect the region in association with the passage
of western disturbances across North India. On such occasions, the minimum temperature
sometimes drops down to 6-7°C. The lowest temperature recorded at Ahmedabad is 2.2°C on 6th
February 1920.
Wind
Long term wind direction data is presented in Table 4-6. During June to September, that is
during the monsoon season wind blows mostly from south-west. During the period from October
to February, both the morning and evening winds are mostly from northeast. During March to May
wind mostly blows from north-west predominantly.
Table 4-6: Predominant Wind Direction IMD Ahmedabad
Month
Predominant Wind
First Second Third
Morning Evening Morning Evening Morning Evening
January E N NE/ CLAM NW N NE
February CALM NW NE/E W NW NE
March NW NW CALM W E N
April NW NW W W CALM SW
M/S. BPIPL PFR – NEW POWER PLANT OF 23 MW AT VILLAGE: NAIKA,
TALUKA & DIST: KHEDA (GUJARAT) SITE ANALYSIS
KADAM ENVIRONMENTAL CONSULTANTS | MARCH, 2017 18
Month
Predominant Wind
First Second Third
Morning Evening Morning Evening Morning Evening
May W W NW SW SW NW
June SW SW W S S W
July SW SW W W S S
August SW SW W W NW/CALM S
September NW SW W W SW NW
October CALM CALM NW NW E N
November E CALM CALM N NE E
December E N NE E CALM NE / NW
Rainfall
The distribution of rainfall in the region, which includes the study area, is uneven. Average rainfall
in the region is 762.7 mm. About 93 percent of the annual rainfall in the region is received during
the southwest monsoon months i.e. June to September. July is the rainiest month.
The annual average rainfall is about 762.7 mm. Maximum rainfall in any one month was recorded
in the month of July in year 1905 which was about 952.5 mm. July is having maximum number of
rainy days i.e. 11.2.
Cloud Cover
The area remains cloudy between June - September, which is the active period of the monsoon
season. During this time all clouds cover is between 4.3 to 6.6 Oktas during day time and 3.9 to
6.3 Oktas during night time.
Humidity
Most humid conditions are found in the monsoons, followed by post-monsoons, winter and
summer in that order. Mornings are more humid than evenings and humidity ranges from a high
of 74-87% in monsoon mornings to a low of 20-45% in summer evenings. During post-monsoon
season, in morning humidity remains between 55-64% and in the evening it remains between 35-
37%.
Table 4-7: Average Meteorological Condition at IMD Ahmedabad (1961-1990)
Month
Mean Daily Temperature Rainfall
(mm)
Monthly
Total
No. of
Rainy
days
Relative
Humidity
(%),
Morning
Relative
Humidity
(%),
Evening
Max Min
January 28.3 11.9 1.8 0.2 59 32
February 30.9 14.0 1.1 0.1 53 25
March 35.8 18.9 1.0 0.1 49 20
April 39.8 23.5 2.7 0.2 54 20
May 41.7 26.2 15.1 0.7 65 23
June 38.5 27.1 98.7 4.2 74 45
July 33.4 25.6 262.3 11.2 85 67
August 31.9 24.7 239.6 10.8 87 71
September 33.7 24.2 108.9 5.3 82 58
October 36.0 21.0 16.2 0.4 64 37
M/S. BPIPL PFR – NEW POWER PLANT OF 23 MW AT VILLAGE: NAIKA,
TALUKA & DIST: KHEDA (GUJARAT) SITE ANALYSIS
KADAM ENVIRONMENTAL CONSULTANTS | MARCH, 2017 19
Month
Mean Daily Temperature Rainfall
(mm)
Monthly
Total
No. of
Rainy
days
Relative
Humidity
(%),
Morning
Relative
Humidity
(%),
Evening
Max Min
November 33.1 16.6 11.5 0.6 55 35
December 29.6 13.2 3.8 0.2 60 35
Total - - 762.7 34.0 - -
Average 34.4 20.6 - - - -
4.8 Social Infrastructure Available
Availability of health facilities in the study area are very poor. There are 17 primary health centers,
106 primary health sub-centers, 25 maternity & child welfare centers, 51 family welfare centers
and 4 hospitals present in the study area. 109 registered Private Medical practitioners are available
for the visits to villages as and when required by the people. (This includes data for all three
districts Kheda, Gandhinagar, & Ahmedabad)3.
1
3 Primary census abstract 2011.
M/S. BPIPL PFR – NEW POWER PLANT OF 23 MW AT VILLAGE: NAIKA,
TALUKA & DIST: KHEDA (GUJARAT) PLANNING BRIEF
KADAM ENVIRONMENTAL CONSULTANTS | MARCH, 2017 20
5 PLANNING BRIEF
5.1 Planning Concept
Site falls under the seismic intensity Zone III, which is classified as Moderate Risk zone. Thus,
suitable seismic coefficients accordingly shall be adopted while designing the structures to make it
earthquake resistant.
Transportation of raw material will be carried out through existing SH-140.
5.2 Population Projection
Refer Chapter 2, Section 2.6, Pg. 4.
5.3 Land Use Planning
Land was purchased for thermal power plant from farmers as per the market price. Change is land
use is envisaged from agriculture use to industrial use. Draft Landuse map within 10 Km from the
project site is provided in Annexure 4.
5.4 Assessment of Infrastructure Demand (Physical & Social)
No additional infrastructure demand is required.
5.5 Amenities/Facilities
Refer Chapter 4, Section 4.8, Pg. 19.
M/S. BPIPL PFR – NEW POWER PLANT OF 23 MW AT VILLAGE: NAIKA, TALUKA &
DIST: KHEDA (GUJARAT) PROPOSED
INFRASTRUCTURE
KADAM ENVIRONMENTAL CONSULTANTS | MARCH, 2017 21
6 PROPOSED INFRASTRUCTURE
6.1 Industrial Area (Processing Area)
The proposed power plant will mainly comprise of following sections:
Boiler House consisting of AFBC Boilers – 2 Nos., Steam Turbine, Alternator / Generator;
Fuel storage area;
Utility Area consisting of cooling tower, compressors, ESP section, ETP (RO & MEE) area;
Fly Ash & Hazardous waste storage area.
6.2 Non-Processing Area
Non processing area will include weighbridge, administrative building, laboratory, security cabins,
workers restroom, vehicle shed, water reservoirs for raw water and fire hydrant system, temporary
storage sites, worksblock etc.
6.3 Green Belt
Around 33.6 % (~5,665 m2) of total plot area will be developed as greenbelt as shown in
Annexure 2.
6.4 Social Infrastructure
Refer Chapter 4, Section 4.8, Pg. 19.
6.5 Connectivity
Refer Chapter 4, Section 4.1, Pg. 13.
6.6 Drinking Water Management
The source of drinking water is either through borewell or water from nearest river which is
Sabarmati and Vatrak River. Water from rivers is being treated and make it suitable for drinking
purpose.
6.7 Sewage System
9 KLD of domestic waste water will be collected in Septic Tanks and disposed in Soak Pits.
6.8 Industrial Waste & Solid Waste Management
Solid waste as mentioned in Chapter 3, Section 3.8.4 shall be collected, stored, disposed off as
per the Fly Ash Notification, 2015, as amended till date.
6.9 Power Requirement & Supply / Source
Refer chapter 3, section 3.7.1.
M/S. BPIPL PFR – NEW POWER PLANT OF 23 MW AT VILLAGE: NAIKA, TALUKA &
DIST: KHEDA (GUJARAT) R & R ISSUES
KADAM ENVIRONMENTAL CONSULTANTS | MARCH, 2017 22
7 REHABILITATION AND RESETTLEMENTS (R& R)
PLAN
Land was purchased from farmers as per the market price. All the dues are settled and hence, R &
R issues are not envisaged.
M/S. BPIPL PFR – NEW POWER PLANT OF 23 MW AT VILLAGE: NAIKA, TALUKA &
DIST: KHEDA (GUJARAT) PROJECT SCHEDULE &
COST ESTIMATE
KADAM ENVIRONMENTAL CONSULTANTS | MARCH, 2017 23
8 PROJECT SCHEDULE AND COST ESTIMATE
8.1 Likely date of start of construction and likely data of completion
The construction is likely to start after getting Environmental Clearance and NOC/CTE from the
authorized committee. Tentative schedule for the project to be completed is given in Table 8-1.
Table 8-1: Tentative Project Time Schedule
S. No. Activities Start Finish
1 EC Approval March, 2017 March, 2018
2 Detailed Engineering January 2018 January 2019
3 Procurement and Delivery January 2019 August 2019
4 Construction at Site (Buildings, Mech., Piping, Elec. etc.) January 2019 May 2019
5 Pre Commissioning August 2019 September 2019
6 CTO Approval August 2019 September 2019
7 Process Startup and Stabilization September 2019 October 2019
8.2 Estimated Project Cost
The project cost is estimated to be around INR 73.9 Crore. The breakup is given in Table 8-2.
Table 8-2: Cost Break-up
S. No. Particulars Amount (INR in Crores)
1 Boiler with Deaerator, Storage Tank, Chemical Dosing System 25.8
2 Steam piping and PRDS 0.6
3 Electro Static Precipitator (ESP) 3.0
4 Automation, Instrumentation 1.0
5 Supervision, Erection & Commissioning 2.2
6 Turbine with Auxiliaries & HT Alternator 10.2
7 Erection & Commissioning 0.6
8 Air cooled condenser 7.2
9 Erection & Commissioning 0.3
10 Water treatment plant, Transfer Pump & Storage Tank 0.7
11 Coal Handling System &Ash handling 4.0
12 Boiler, Turbine & All Civil Works including Chimney & RCC silo 9.3
13 Misc. like Fire Fighting, Air Conditioning, crane, Lab Equip,
Compressor, Aux cooling tower etc. 0.6
14 Power Plant Integral Electrical Works 0.7
15 Consultancy and other statutory expenses 0.4
A Contingencies 2% 0.8
Total Project Cost without taxes & duties 67.6
B Freight and Insurance @2% 0.8
Sub Total 68.4
C Excise duty @ 5.25% 2.0
D CST @ 2% 1.1
E Service tax 14.5% 2.4
Total Project Cost 73.9
M/S. BPIPL PFR – NEW POWER PLANT OF 23 MW AT VILLAGE: NAIKA, TALUKA &
DIST: KHEDA (GUJARAT) PROJECT SCHEDULE &
COST ESTIMATE
KADAM ENVIRONMENTAL CONSULTANTS | MARCH, 2017 24
8.2.1 Profitability
The project has been conceived assuming that there will be a demand for power in nearby
industries and textile units, leading to a reasonable rate of return in the medium term. The project
is thus considered ‘bankable’.
M/S. BPIPL PFR – NEW POWER PLANT OF 23 MW AT VILLAGE: NAIKA, TALUKA &
DIST: KHEDA (GUJARAT) ANALYSIS OF PROPOSAL
KADAM ENVIRONMENTAL CONSULTANTS | MARCH, 2017 25
9 ANALYSIS OF PROPOSAL
9.1 Financial and Social Benefits
Demand of power and steam in nearby industries and textile units is envisaged. No power plant is
available in the region and they have to rely on the grid power and own small boilers.
Requirement of nearby industries and textile units will be fulfilled by this proposed power plant.
During the lean period, husk will be used as per its availability. Currently it is being used by many
nearby brick manufacturers for burning purpose. In such small scale industries, no APCE is
attached generally. If it is used in proposed power plant, the emissions from the stack will be
controlled and shall meet the GPCB norms.
During the construction phase around 100 workers will be hired. During operation phase, project
will generate direct employment for more than 50 people and indirect employment for
approximately 25 people.
The positives impact include enhanced direct employment for technical/administrative works and
indirect employment opportunities for transporters of raw material like Coal & Husk.
If this project comes up, it will have social, financial and environmental benefits. There will be
indirect development of small market for various aspects around the site.
Pre-feasibility study confirms viability of the project.
M/S. BPIPL PFR – NEW POWER PLANT OF 23 MW AT VILLAGE: NAIKA, TALUKA &
DIST: KHEDA (GUJARAT) ANNEXURES
KADAM ENVIRONMENTAL CONSULTANTS | MARCH, 2017 26
ANNEXURES
M/S. BPIPL PFR – NEW POWER PLANT OF 23 MW AT VILLAGE: NAIKA, TALUKA &
DIST: KHEDA (GUJARAT) ANNEXURES
KADAM ENVIRONMENTAL CONSULTANTS | MARCH, 2017 27
Annexure 1: Willingness Letters – Rice Mills
Letter from Kedar Nath Rice Mill
M/S. BPIPL PFR – NEW POWER PLANT OF 23 MW AT VILLAGE: NAIKA, TALUKA &
DIST: KHEDA (GUJARAT) ANNEXURES
KADAM ENVIRONMENTAL CONSULTANTS | MARCH, 2017 28
Letter from A. M. Agro Pvt. Ltd.
M/S. BPIPL PFR – NEW POWER PLANT OF 23 MW AT VILLAGE: NAIKA, TALUKA &
DIST: KHEDA (GUJARAT) ANNEXURES
KADAM ENVIRONMENTAL CONSULTANTS | MARCH, 2017 29
Letter from Akshar Rice Mill
M/S. BPIPL PFR – NEW POWER PLANT OF 23 MW AT VILLAGE: NAIKA, TALUKA &
DIST: KHEDA (GUJARAT) ANNEXURES
KADAM ENVIRONMENTAL CONSULTANTS | MARCH, 2017 30
Letter from Baldev Krupa Rice Mill
M/S. BPIPL PFR – NEW POWER PLANT OF 23 MW AT VILLAGE: NAIKA, TALUKA &
DIST: KHEDA (GUJARAT) ANNEXURES
KADAM ENVIRONMENTAL CONSULTANTS | MARCH, 2017 31
Letter from Jagathnath Agro Pvt. Ltd.
M/S. BPIPL PFR – NEW POWER PLANT OF 23 MW AT VILLAGE: NAIKA, TALUKA &
DIST: KHEDA (GUJARAT) ANNEXURES
KADAM ENVIRONMENTAL CONSULTANTS | MARCH, 2017 32
Letter from Anarbath Rice Mill
M/S. BPIPL PFR – NEW POWER PLANT OF 23 MW AT VILLAGE: NAIKA, TALUKA &
DIST: KHEDA (GUJARAT) ANNEXURES
KADAM ENVIRONMENTAL CONSULTANTS | MARCH, 2017 33
Letter from Keshav Laxmi Rice Mill
M/S. BPIPL PFR – NEW POWER PLANT OF 23 MW AT VILLAGE: NAIKA, TALUKA & DIST: KHEDA (GUJARAT) ANNEXURES
KADAM ENVIRONMENTAL CONSULTANTS | MARCH, 2017 34
Annexure 2: Site Layout Map
M/S. BPIPL PFR – NEW POWER PLANT OF 23 MW AT VILLAGE: NAIKA, TALUKA & DIST: KHEDA (GUJARAT) ANNEXURES
KADAM ENVIRONMENTAL CONSULTANTS | MARCH, 2017 35
Annexure 3: Project Site Located on Toposheet No. F43G5, F43G6, F43G569 & F43G10
M/S. BPIPL PFR – NEW POWER PLANT OF 23 MW AT VILLAGE: NAIKA, TALUKA & DIST: KHEDA (GUJARAT) ANNEXURES
KADAM ENVIRONMENTAL CONSULTANTS | MARCH, 2017 36
Annexure 4: Draft Landuse Map
M/S. BPIPL PFR – NEW POWER PLANT OF 23 MW AT VILLAGE: NAIKA, TALUKA & DIST: KHEDA (GUJARAT) ANNEXURES
KADAM ENVIRONMENTAL CONSULTANTS | MARCH, 2017 37
Annexure 5: Long Term Meteorological Data – IMD Ahmedabad
M/S. BPIPL PFR – NEW POWER PLANT OF 23 MW AT VILLAGE: NAIKA, TALUKA & DIST: KHEDA (GUJARAT) ANNEXURES
KADAM ENVIRONMENTAL CONSULTANTS | MARCH, 2017 38
CONTACT DETAILS
Vadodara (Head Office)
871/B/3, GIDC Makarpura, Vadodara, India – 390 010.
E: [email protected]; T:+91-265-3001000; F: +91-265-3001069
Delhi / NCR
Spaze IT Park, Unit No. 1124, IIth Floor, Tower B3, Sector 49, Near Omaxe City Centre Mall, Sohna Road,
Gurgaon, Haryana, INDIA - 122002.
E: [email protected]; T: +91-124-4242430 to 436; F:+91-124-4242433
Kadam Environmental Consultants
w w w . ka d a m en v i r o . c o m
Envi ronment for Deve lopment