Upload
others
View
0
Download
0
Embed Size (px)
Citation preview
M/S. NIRMA LIMITED
Pre-Feasibility Report for Environmental Clearance for Proposed Expansion in Nirma Chemical Complex at Village – Kalatalav, Taluka & District Bhavnagar Gujarat.
NOVEMBER, 2017
Kadam Environmental Consultants w w w . ka d a m en v i r o . c o m
Envi ronment for Deve lopment
NIRMA LIMITED PFR – PROPOSED EXPANSION IN SODA ASH, CAUSTIC SODA PRODUCTION AND
CAPTIVE POWER PLANT IN EXISTING FACILITY AT KALATALAV, NEAR BHAVNAGAR QUALITY CONTROL SHEET
KADAM ENVIRONMENTAL CONSULTANTS | NOVEMBER, 2017 II
M/S. NIRMA LIMITED
Pre-Feasibility Report for Environmental Clearance for Proposed Expansion in Nirma Chemical Complex at Village – Kalatalav, Taluka & District Bhavnagar Gujarat. © Kadam Environmental Consultants (‘Kadam’), November, 2017
This report is released for the use of the M/s. NIRMA LIMITED., Regulators and relevant stakeholders solely as part
of the subject project’s Environmental Clearance process. Information provided (unless attributed to referenced
third parties) is otherwise copyrighted and shall not be used for any other purpose without the written consent of
Kadam.
PROJECT DETAILS
Name of
Publication
Pre-Feasibility Report for Environmental Clearance for Proposed Expansion in Nirma Chemical Complex
at Village – Kalatalav, Taluka & District Bhavnagar, Gujarat
Project Number 1730141406 Report No. 1 Version 1 Released November,
2017
Prepared &
Managed By
Tanu Prasad & Bhavin Jambucha, K.K
Antani Released By Sangram Kadam
CONTACT DETAILS
Vadodara (Head Office)
871/B/3, GIDC Makarpura, Vadodara, India – 390 010.
E: [email protected]; T:+91-265-6131000
Delhi / NCR
Spaze IT Park, Unit No. 1124, IIth Floor, Tower B3, Sector 49, Near Omaxe City Centre Mall, Sohna Road, Gurgaon, Haryana,
INDIA - 122002.
E: [email protected]; T: +91-124-4242430 to 436; F:+91-124-4242433
DISCLAIMER
Kadam has taken all reasonable precautions in the preparation of this report as per its auditable quality plan. Kadam also
believes that the facts presented in the report are accurate as on the date it was written. However, it is impossible to dismiss
absolutely, the possibility of errors or omissions. Kadam therefore specifically disclaims any liability resulting from the use or
application of the information contained in this report. The information is not intended to serve as legal advice related to the
individual situation.
NIRMA LIMITED PFR – PROPOSED EXPANSION IN SODA ASH, CAUSTIC SODA PRODUCTION AND
CAPTIVE POWER PLANT IN EXISTING FACILITY AT KALATALAV, NEAR BHAVNAGAR TABLE OF CONTENTS
KADAM ENVIRONMENTAL CONSULTANTS | NOVEMBER, 2017 III
CONTENTS
1 EXECUTIVE SUMMARY ................................................................................................ 1
1.1 PLANT FEATURES AND PRODUCTION CAPACITY ......................................................................... 1
1.2 INFRASTRUCTURE ....................................................................................................... 2
1.3 UTILITY ................................................................................................................. 2
1.4 ENVIRONMENT ........................................................................................................... 3
1.5 SENSITIVITY ............................................................................................................. 3
1.6 CONCLUSION ............................................................................................................ 3
2 INTRODUCTION ......................................................................................................... 4
2.1 IDENTIFICATION OF PROJECT PROPONENT & PROJECT ................................................................. 4
2.1.1 Project Proponent ............................................................................................... 4
2.1.2 Proposed Project ................................................................................................ 4
2.2 BRIEF DESCRIPTION OF NATURE OF THE PROJECT ...................................................................... 4
2.3 NEED FOR THE PROJECT AND ITS IMPORTANCE TO THE COUNTRY & REGION .......................................... 4
2.4 DEMAND & SUPPLY GAP ................................................................................................. 5
2.5 EXPORT POSSIBILITY .................................................................................................... 5
2.5.1 Domestic / Export Market ..................................................................................... 5
2.6 EMPLOYMENT GENERATION (DIRECT & INDIRECT) DUE TO THE PROJECT .............................................. 5
3 PROJECT DESCRIPTION .............................................................................................. 6
3.1 TYPE OF PROJECT ....................................................................................................... 6
3.2 LOCATION OF THE PROJECT ............................................................................................. 6
3.3 DETAILS OF ALTERNATE SITES CONSIDERED ............................................................................ 8
3.4 SIZE OR MAGNITUDE OF OPERATION.................................................................................... 8
3.5 PROJECT DESCRIPTION WITH PROCESS DETAILS ....................................................................... 9
3.5.1 Soda Ash (Existing + Expansion) ............................................................................. 9
3.5.2 Caustic Soda (Existing + Expansion) ....................................................................... 10
3.5.3 Captive Power Plant (Existing + Expansion) ............................................................... 12
3.6 UTILITIES .............................................................................................................. 13
3.6.1 Power Requirement ............................................................................................ 13
3.6.2 Fuel Requirement .............................................................................................. 13
3.6.3 Water Requirement ............................................................................................ 13
3.6.4 Storage Details ................................................................................................. 13
3.7 POLLUTION LOAD ON ENVIRONMENT DUE TO PROJECT................................................................. 13
3.7.1 Air Emissions & Control ....................................................................................... 13
3.7.2 Noise Generation ............................................................................................... 16
3.7.3 Waste Water Generation ...................................................................................... 16
3.7.4 Hazardous Waste & Other Solid Waste ..................................................................... 17
4 SITE ANALYSIS ........................................................................................................ 20
4.1 CONNECTIVITY ......................................................................................................... 20
4.1.1 By Road .......................................................................................................... 20
4.1.2 By Rail ........................................................................................................... 20
4.1.3 By Air ............................................................................................................ 20
4.2 LAND FORM, LAND USE & LAND OWNERSHIP .......................................................................... 20
NIRMA LIMITED PFR – PROPOSED EXPANSION IN SODA ASH, CAUSTIC SODA PRODUCTION AND
CAPTIVE POWER PLANT IN EXISTING FACILITY AT KALATALAV, NEAR BHAVNAGAR TABLE OF CONTENTS
KADAM ENVIRONMENTAL CONSULTANTS | NOVEMBER, 2017 IV
4.3 TOPOGRAPHY ........................................................................................................... 20
4.4 EXISTING INFRASTRUCTURE ............................................................................................ 20
4.5 SOIL CLASSIFICATION, GEOLOGY & DRAINAGE ........................................................................ 20
4.5.1 Soil Classification ............................................................................................... 20
4.5.2 Geology .......................................................................................................... 20
4.6 CLIMATIC DATA FROM SECONDARY SOURCES ........................................................................... 21
4.7 SOCIAL INFRASTRUCTURE AVAILABLE .................................................................................. 21
5 PLANNING BRIEF ..................................................................................................... 22
5.1 PLANNING CONCEPT .................................................................................................... 22
5.2 LANDUSE PLANNING .................................................................................................... 22
5.3 ASSESSMENT OF INFRASTRUCTURE DEMAND (PHYSICAL & SOCIAL) ................................................... 22
5.4 AMENITIES/FACILITIES ................................................................................................. 22
6 PROPOSED INFRASTRUCTURE ................................................................................... 23
6.1 INDUSTRIAL AREA (PROCESSING AREA)................................................................................ 23
6.2 NON- PROCESSING AREA ............................................................................................... 23
6.3 GREENBELT ............................................................................................................. 23
6.4 SOCIAL INFRASTRUCTURE .............................................................................................. 23
6.5 CONNECTIVITY ......................................................................................................... 23
6.6 DRINKING WATER MANAGEMENT ...................................................................................... 23
6.7 SEWAGE SYSTEM ....................................................................................................... 23
6.8 INDUSTRIAL WASTE & SOLID WASTE MANAGEMENT .................................................................. 23
6.9 POWER REQUIREMENT & SUPPLY / SOURCE ........................................................................... 24
7 REHABILITATION AND RESETTLEMENT (R&R) PLAN ..................................................... 25
8 PROJECT SCHEDULE AND COST ESTIMATE ................................................................... 26
8.1 LIKELY DATE OF START OF CONSTRUCTION AND LIKELY DATE OF COMPLETION......................................... 26
8.2 ESTIMATED PROJECT COST ............................................................................................ 26
8.2.1 Profitability ...................................................................................................... 26
9 ANALYSIS OF PROPOSAL .......................................................................................... 27
9.1 FINANCIAL AND SOCIAL BENEFITS...................................................................................... 27
NIRMA LIMITED PFR – PROPOSED EXPANSION IN SODA ASH, CAUSTIC SODA PRODUCTION AND
CAPTIVE POWER PLANT IN EXISTING FACILITY AT KALATALAV, NEAR BHAVNAGAR LIST OF ANNEXURES
KADAM ENVIRONMENTAL CONSULTANTS | NOVEMBER, 2017 V
ANNEXURES
Annexure 1: Preliminary Site Layout Map ......................................................................................................... 29
Annexure 2: Project Site Located on Toposheet showing 3, 5, 7 & 10 km Radii Circles ......................................... 30
Annexure 3: Long Term Meteorological Data for Bhavnagar City ........................................................................ 31
NIRMA LIMITED PFR – PROPOSED EXPANSION IN SODA ASH, CAUSTIC SODA PRODUCTION AND
CAPTIVE POWER PLANT IN EXISTING FACILITY AT KALATALAV, NEAR BHAVNAGAR LIST OF TABLES
KADAM ENVIRONMENTAL CONSULTANTS | NOVEMBER, 2017 VI
LIST OF TABLES
Table 1-1: Products Capacity (Existing & Proposed) ............................................................................................1
Table 2-1: Products Capacity .............................................................................................................................4
Table 3-1: Co-ordinates of Site Boundary ...........................................................................................................8
Table 3-2: Area Statement* ..............................................................................................................................8
Table 3-3: Details of Stack Emissions ............................................................................................................... 14
Table 3-4: Details of Process Emissions ............................................................................................................ 14
Table 3-5: Wastewater Generation Details ........................................................................................................ 16
Table 3-6: Solid Waste Generation & Disposal................................................................................................... 17
Table 3-7: Hazardous Waste Generation and Disposal ....................................................................................... 18
Table 6-1: Identification of Other Wastes ......................................................................................................... 24
Table 8-1: Tentative Project Time Schedule ...................................................................................................... 26
Table 8-2: Breakup of Project Cost .................................................................................................................. 26
LIST OF FIGURES
Figure 3-1: General Location of Proposed Project Site .........................................................................................6
Figure 3-2: Specific Map Showing Project Boundary ............................................................................................7
Figure 3-3: Process Flow Diagram - Soda Ash Manufacturing Process ................................................................. 10
Figure 3-4: Process Flow Diagram - Caustic Soda Manufacturing Process ............................................................ 12
NIRMA LIMITED PFR – PROPOSED EXPANSION IN SODA ASH, CAUSTIC SODA PRODUCTION AND
CAPTIVE POWER PLANT IN EXISTING FACILITY AT KALATALAV, NEAR BHAVNAGAR EXECUTIVE SUMMARY
KADAM ENVIRONMENTAL CONSULTANTS | NOVEMBER, 2017 1
1 EXECUTIVE SUMMARY
Nirma Ltd. is one of the leading soda ash producing company in India. The group has integrated backwards for the
production of detergents and toilet soaps by establishing industrial chemical manufacturing facilities of Linear Alkyl
Benzene, Alfa Olefin Sulfate, Soda Ash (light and dense), Caustic Soda, industrial salt and consumer salt to facilitate
quality production of their consumer products.
It is located at Survey No. 478/p, 447 – 453, 455 - 457, Village – Kalatalav, Taluka & District Bhavnagar, Gujarat.
Nirma Limited, Bhavnagar now proposes for modernization with expansion of their existing production plant
capacity.
As per the EIA notification dated 14th September, 2006, as amended till date, the proposed project falls in category
including Project / Activity: 4(d) - Caustic Soda Plant, 4(e) - Soda Ash Plant, 1(d) - Captive Power Plant and
categorized under “A”.
1.1 Plant Features and Production Capacity
Existing cost of project is INR 3,110 crores. The expected cost of the proposed expansion project will be around
INR 1,320 crores. Details of existing and proposed products are listed in Table 1-1.
Table 1-1: Products Capacity (Existing & Proposed)
Sr.
No. Products/By-Products Units
Existing
Capacity Proposed
Total Capacity after
Expansion
1 Soda Ash Plant
A Light Soda Ash TPD 2,800 1,500 4,300
B Dense Soda Ash TPD 1,800 600 2,400
C Refined Sodium Bicarbonate (RBC)
(NOC) TPD 400 0 400
D Pure Water Plant M3/D 6,720 0 6,720
E Vacuum Salt TPD 2,400 0 2,400
2 Caustic Soda Plant
A Product
Caustic Soda (100%) TPD 750 250 1,000
Hydrochloric Acid (100%) TPD 280 220 500
B By-Products
Chlorine Gas (100%) TPD 665.2 220.8 886
Hydrogen (100%) TPD 18.75 6.25 25
Sodium Hypo Chlorite (100%) TPD 12 3 15
3 Captive Power Plant
Power MW 197.18 152.82 350
4 Chlorine & Hydrogen Derivatives
A Hydrogen Peroxide (100%) TPD 84 0 84
B Epichlorohydrin (ECH) TPD 150 0 150
C Glycerin TPD 160 0 160
D Mono Chloro Acetic Acid (MCAA) TPD 120 0 120
By-Products
Hydrochloric Acid (100%) TPD 48 0 48
Mother Liquor of MCAA TPD 30 0 30
NIRMA LIMITED PFR – PROPOSED EXPANSION IN SODA ASH, CAUSTIC SODA PRODUCTION AND
CAPTIVE POWER PLANT IN EXISTING FACILITY AT KALATALAV, NEAR BHAVNAGAR EXECUTIVE SUMMARY
KADAM ENVIRONMENTAL CONSULTANTS | NOVEMBER, 2017 2
Sr.
No. Products/By-Products Units
Existing
Capacity Proposed
Total Capacity after
Expansion
Sodium Hypo Chlorite (100%) TPD 10 0 10
Product
E Tricolor Acetyl Chloride (TCAC) TPD 10 0 10
By-Product
Hydrochloric Acid (100%) TPD 9 0 9
Sodium Hypo Chlorite (100%) TPD 1 0 1
Sodium Bisulfite Solution (100%) TPD 3 0 3
F Calcium Chloride (100%) (NOC) TPD 152 0 152
Calcium Chloride Granules TPD 160 0 160
By-Product
CO2 Gas TPD 60 0 60
Solid CO2 (Dry Ice) & / or Liquid CO2 TPD 60 0 60
G Phosphoric Acid (61.5% P2O5) (NOC) TPD 100 0 100
5 Toilet Soap Plant
Toilet Soap TPD 200 0 200
Detergent Powder TPD 414.66 0 414.66
Detergent Cake TPD 414.66 0 414.66
Fatty Acid TPD 150 0 150
Glycerin TPD 167 0 167
6 Bromine Plant
Bromine TPD 20 0 20
1.2 Infrastructure
The proposed expansion would be implemented in Nirma Ltd.’s existing manufacturing facility at Kalatalav, near
Bhavnagar, Gujarat.
Main components of the existing project which includes Captive Power Plant, Soda Ash Plant, Caustic Soda Plant,
Chlorine and Hydrogen derivatives plant, , Toilet soap plant and Bromine Plant and their associated utilities /
components like Boiler House of CFBC Boilers, Steam Turbine, Generator, Utility Area consisting of cooling tower,
ESP section Fly ash storage area. Water & wastewater infrastructure like Effluent Treatment Plant (ETP), Air
compressors & Hazardous storage facility area are being used.
1.3 Utility
Power: The total additional power demand for the expansion has been estimated about 152.82 MW. The power
requirement will be met by installing additional coal / lignite / pet-coke based CFBC boiler (410 TPH & 130 TPH ,
total 540 TPH*) along with Turbo-alternator and utilizing some surplus steam from existing boilers.
* Capacity of proposed boilers may vary however total proposed capacity of steam generation will remain same as
540 TPH.
Arrangement has also been made for sourcing power through sub-station of Gujarat State Electricity Board.
Fuel: Coal: 240.25 T/hr. &/or Lignite: 245 T/hr. &/or Pet coke: 163 T/hr. (93 T/hr for proposed boilers + 70 T/hr
for existing boilers). Light Diesel Oil (LDO) shall be required for start-up of CFBC boiler.
Raw Water: Existing Seawater intake facility i.e. from Sonarai Creek, near village Gundala. Existing seawater
intake – 14 x 105 m3/day. Additional seawater intake - 3.6 x 105 m3/day.
NIRMA LIMITED PFR – PROPOSED EXPANSION IN SODA ASH, CAUSTIC SODA PRODUCTION AND
CAPTIVE POWER PLANT IN EXISTING FACILITY AT KALATALAV, NEAR BHAVNAGAR EXECUTIVE SUMMARY
KADAM ENVIRONMENTAL CONSULTANTS | NOVEMBER, 2017 3
Manpower: Existing manpower at the operational site is 1,630 nos. Manpower during Construction phase would
be 150 nos. The manpower for operation phase of Expansion plants would be 100 nos. Thus, the total manpower
during full operation phase of Nirma-Kalatalav complex will be approximately 1,730 nos.
1.4 Environment
Environmental issues associated with proposed units are:
Air Emissions: These would be due to presence of various Flue Gas stacks and process vents.
Wastewater: The wastewater generated from the proposed activities would be treated in Effluent treatment
plant. The treated effluent would be discharged into the Gulf of Khambhat through existing outfall equipped
with diffuser system.
Solid & Hazardous Waste: Hazardous waste generated from the proposed project would be managed as per
the Hazardous and Other Wastes (Management and Transboundary Movement) Rules, 2016.
1.5 Sensitivity
Project boundary is well beyond minimum distance of 500 m from CRZ boundary. About 6.5 km in North (Gundala
Creek), 6.0 km East side (Malcolm Channel), and 3.0 km in the South direction (Bhavnagar Creek). Project site falls
in Zone-III of Seismicity. Civil and Structures shall be designed according to applicable code. It is 6.0 km from
Malcolm Channel (Gulf of Khambhat) thus susceptible to natural hazards like cyclone/storm etc.
1.6 Conclusion
There is no adverse impact on the water environment due to the operation of the project. The air environment has
negligible effect due to the activities related to the operation of the project.
After implementation of pollution control measures there will be no emission from the plant beyond the norms
specified by Gujarat Pollution Control Board (GPCB). The project is not contributing to any adverse impact on the
surrounding soil, as the pollutants emitted are of the negligible amount.
Project intends to generate employment for local people and unskilled / semiskilled workers during construction
phase. If this project comes up, it will have social, financial benefits and will be environmentally sustainable.
Pre-feasibility study confirms viability of the project.
NIRMA LIMITED PFR – PROPOSED EXPANSION IN SODA ASH, CAUSTIC SODA PRODUCTION AND
CAPTIVE POWER PLANT IN EXISTING FACILITY AT KALATALAV, NEAR BHAVNAGAR INTRODUCTION
KADAM ENVIRONMENTAL CONSULTANTS | NOVEMBER, 2017 4
2 INTRODUCTION
2.1 Identification of Project Proponent & Project
2.1.1 Project Proponent
Nirma is one of the few names - which is instantly recognized as a true Indian brand, which took on mighty
multinationals and rewrote the marketing rules to win the heart of princess, i.e. the consumer.
Nirma, the proverbial ‘Rags to Riches’ saga of Dr. Karsanbhai Patel, is a classic example of the success of Indian
entrepreneurship in the face of stiff competition. Starting as a one-man operation in 1969, today, it has about
15,000+ employee-base and annual turnover is more than 10,000 Crores INR.
Nirma Ltd. is one of the leading soda ash producing company in India. The group has integrated backwards for the
production of detergents and toilet soaps by establishing industrial chemical manufacturing facilities of Linear Alkyl
Benzene, Alfa Olefin Sulfate, Soda Ash (light and dense), Caustic Soda, industrial salt, Cement and consumer salt to
facilitate quality production of their consumer products.
2.1.2 Proposed Project
Proposed project is for expansion in Existing Production Capacity.
2.2 Brief Description of nature of the Project
Details of existing and proposed products for which expansion is proposed are listed in Table 2-1.
Table 2-1: Products Capacity
Sr.
No. Project or activity
Capacity (TPD)
Existing Proposed Total
Soda Ash Plant (Area = 2,61,548.33 m2)
1. Light Soda Ash Plant 2,800 1,500 4,300
2. Dense Soda Ash* 1,800 600 2,400
Ash * Dense Soda is conversion of Light Soda Ash
Caustic Soda Plant (Area = 2,88,945.55 m2)
1. Caustic Soda (100%) 750 250 1,000
2. Hydrochloric Acid (100%) 280 220 500
Caustic Soda Plant – By Products
1. Chlorine Gas (100%) 665.2 220.8 886
2. Hydrogen (100%) 18.75 6.25 25
3. Sodium Hypo Chlorite (100%) 12 3 15
Captive Thermal Power Plant (Area = 69,100 m2)
1. Captive thermal Power Plant 197.18 MW 152.82 MW 350 MW
2.3 Need for the Project and its Importance to the Country & Region
There is regular use of these products and has demand in local market as well as in export. This will meet the local
demand and generate employment.
NIRMA LIMITED PFR – PROPOSED EXPANSION IN SODA ASH, CAUSTIC SODA PRODUCTION AND
CAPTIVE POWER PLANT IN EXISTING FACILITY AT KALATALAV, NEAR BHAVNAGAR INTRODUCTION
KADAM ENVIRONMENTAL CONSULTANTS | NOVEMBER, 2017 5
2.4 Demand & Supply Gap
Limestone requirement is approximate 5,050 TPD for existing Soda Ash Plant.
Additional approximate 3,964 TPD (2,705 TPD for SA + 1,259 TPD for CPP) is required for proposed Soda Ash
Expansion and desulphurization in Captive Power Plant. Limestone requirement will be met from the limestone
mines located in Junagadh & Porbandar districts as well as imports.
2.5 Export Possibility
2.5.1 Domestic / Export Market
There is regular use of these products and has demand in local market as well as in export. This will meet the local demand, generate employment and generate revenue for government.
2.6 Employment Generation (Direct & Indirect) due to the project
During the construction phase around 150 workers and existing manpower is sufficient to operate proposed
expansion units. Local skilled and semi-skilled workers will be engaged during construction phase.
NIRMA LIMITED PFR – PROPOSED EXPANSION IN SODA ASH, CAUSTIC SODA PRODUCTION AND
CAPTIVE POWER PLANT IN EXISTING FACILITY AT KALATALAV, NEAR BHAVNAGAR PROJECT DESCRIPTION
KADAM ENVIRONMENTAL CONSULTANTS | NOVEMBER, 2017 6
3 PROJECT DESCRIPTION
3.1 Type of Project
As per the EIA notification dated 14th September, 2006, as amended till date, the proposed project falls in category
including Project / Activity: 4(d) - Caustic Soda Plant, 4(e) - Soda Ash Plant, 1(d) - Captive Power Plant and
categorized under “A”.
3.2 Location of the Project
Proposed project is located at Survey No. 478/p, 447 – 453, 455 - 457, Village – Kalatalav, Taluka & District
Bhavnagar, Gujarat.
Location map showing general location of proposed project is given in Figure 3-1. Specific Map showing project
boundary is given in Figure 3-2. The co-ordinates of the project site are given in Table 3-1.
Figure 3-1: General Location of Proposed Project Site
NIRMA LIMITED PFR – PROPOSED EXPANSION IN SODA ASH, CAUSTIC SODA PRODUCTION AND CAPTIVE POWER PLANT IN EXISTING FACILITY
AT KALATALAV, NEAR BHAVNAGAR PROJECT DESCRIPTION
KADAM ENVIRONMENTAL CONSULTANTS | NOVEMBER, 2017 7
Figure 3-2: Specific Map Showing Project Boundary
Red highlighted boundary shows boundary of Plant. No extra land is required.
NIRMA LIMITED PFR – PROPOSED EXPANSION IN SODA ASH, CAUSTIC SODA PRODUCTION AND
CAPTIVE POWER PLANT IN EXISTING FACILITY AT KALATALAV, NEAR BHAVNAGAR PROJECT DESCRIPTION
KADAM ENVIRONMENTAL CONSULTANTS | NOVEMBER, 2017 8
Table 3-1: Co-ordinates of Site Boundary
POINT LATITUDE LONGITUDE
A 21°51'56.83"N 72° 9'30.48"E
B 21°51'46.15"N 72°10'17.76"E
C 21°51'42.81"N 72° 9'23.53"E
D 21°51'39.12"N 72° 9'28.14"E
E 21°51'33.87"N 72° 9'27.12"E
F 21°51'32.87"N 72° 9'25.35"E
G 21°51'31.17"N 72° 9'25.11"E
H 21°51'30.23"N 72° 9'20.84"E
I 21°51'24.09"N 72° 9'20.45"E
J 21°51'23.82"N 72° 9'25.64"E
K 21°51'13.96"N 72° 9'26.98"E
L 21°51'12.59"N 72° 9'17.77"E
M 21°51'7.73"N 72° 9'13.03"E
N 21°50'51.17"N 72° 9'8.71"E
O 21°50'52.41"N 72°10'8.26"E
P 21°51'16.70"N 72°10'10.47"E
Q 21°51'23.75"N 72°10'15.83"E
3.3 Details of Alternate Sites Considered
The expansion and set-up of new project is within the existing chemical complex. Hence no alternative sites were
explored.
3.4 Size or Magnitude of Operation
Total plot area is 22,49,458 m2. The details of area calculations are given in Table 3-2. Site layout is provided as
Annexure 1.
Table 3-2: Area Statement*
S. No. Particular Area (Acre) Area (m2)
1 Plant facilities 84.0 3,39,825
2 Storage (Raw Material & Finished Products) 23.0 92,930
3 Storage (Fuel) 107.2 4,33,940
4 Storage (Water) 7.5 30,400
5 Storage (Others) 22.3 90,286
6 Utilities 16.9 68,250
7 Laboratory 0.9 3,600
8 Approach Road(s) 3.2 13,000
9 Green Belt 183.4 7,42,321
10 ETP 3.1 12,500
11 Office + Parking + Security 3.6 14,500
12 Open area 100.8 4,07,906
Total 555.8 22,49,458
* Area given are tentative and are subjected to changes, which will be clearly demarcated in the EIA study report.
NIRMA LIMITED PFR – PROPOSED EXPANSION IN SODA ASH, CAUSTIC SODA PRODUCTION AND
CAPTIVE POWER PLANT IN EXISTING FACILITY AT KALATALAV, NEAR BHAVNAGAR PROJECT DESCRIPTION
KADAM ENVIRONMENTAL CONSULTANTS | NOVEMBER, 2017 9
3.5 Project Description with Process Details
3.5.1 Soda Ash (Existing + Expansion)
The global theoretical equation for the production of soda ash, involving sodium chloride and calcium carbonate is
as follows;
2 NaCl + CaCO3 Na2CO3 + CaCl2
In practice the reaction is not possible and needs the participation of other substances and many different process
steps to get the final product. The first reaction involves absorption of ammonia in salt solution, followed by
reaction of ammoniated brine with carbon dioxide to obtain ammonium carbonate followed by ammonium
carbonate. The continuous introduction of carbon dioxide injection and cooling the solution, precipitation of sodium
bicarbonate is achieved and ammonium chloride is formed. The chemical reactions of the process are given below:
NaCl + H2O + NH3 NaCl + NH4OH
2 NH4OH + CO2 (NH4)2 CO3 + H2O
(NH4)2CO3 + CO2 + H2O 2 NH4HCO3
2 NH4HCO3 + 2 NaCl 2 NaHCO3 + 2 NH4Cl
Sodium Bicarbonate crystals are separated from the mother liquor by filtration, followed by thermal decomposition
to obtain sodium carbonate, water and carbon dioxide. Sodium carbonate, thus formed is called “light soda ash”
because its bulk density is approximately 0.5 t/m3.
2 NaHCO3 Na2CO3 + H2O + CO2
CO2 is recovered in the carbonation step. The mother liquor is treated to recover ammonia, by reacting with dry lime
followed by steam stripping to recover free gaseous ammonia, which is recycled to absorption step.
2 NH4Cl + H2O+CaO CaCl2 + 2 NH3 + 2 H2O
Carbon dioxide and Calcium oxide originate from limestone calcinations CaCO3 CaO + CO2. Calcium and
magnesium which are impurities in the brine are removed by reacting with alkali and carbon dioxide to produce
insoluble salts. Brine purification reactions are described in the following equations:
Ca2+ + CO32- CaCO3
Mg2+ + 2 OH- Mg (OH)2
The difference between Light and Dense Soda ash is bulk density & the size of particles. Dense Soda ash is produced
via the monohydrate process. The hot light soda ash discharge from Calciner is transported via chain conveyors and
bucket elevator to Hydrator. In hydrator Light Soda ash is mixed with water to form monohydrate according to the
exothermic reaction:
Na2CO3 + H2O Na2CO3.H2O
The next step is dehydration and drying of the monohydrate in Fluid Bed Dryer according to endothermic reaction:
Na2CO3.H2O Na2CO3 + H2O
The Dense Soda Ash is cooled and transported to storage to packing plant. The block diagram of the Soda Ash
Manufacturing unit is given in Figure 3-3.
NIRMA LIMITED PFR – PROPOSED EXPANSION IN SODA ASH, CAUSTIC SODA PRODUCTION AND
CAPTIVE POWER PLANT IN EXISTING FACILITY AT KALATALAV, NEAR BHAVNAGAR PROJECT DESCRIPTION
KADAM ENVIRONMENTAL CONSULTANTS | NOVEMBER, 2017 10
Figure 3-3: Process Flow Diagram - Soda Ash Manufacturing Process
3.5.2 Caustic Soda (Existing + Expansion)
The Caustic soda manufacturing technology being used i.e. membrane technology is completely environment
friendly. The by products are hydrogen, chlorine & sodium hypo chlorite. Hydrochloric acid is manufactured using
H2 and Cl2 (produced from cell house).
Manufacturing process of Caustic Soda involves the following key steps:
Brine Saturation: Desirable circulating rate of brine in saturator is attained by dissolving salt from solar salt works
and depleted brine from the process. The water loss by membrane is compensated by supply of demineralized
water.
Chemical Preparation: In precipitation tanks saturated brine is treated to remove Ca, Mg & Sulphates by adding
Na2CO3, NaOH and Barium Chloride.
Clarification: Flocculants are added to enhance the settling. Impurities are removed in clarifier. Main impurities
are solids which are pumped to sludge filtration unit. Filtrate is recycled to clarifier.
Filtration: Anthracite filters are used to remove suspended solids.
Secondary Brine Purification: Polishing candle filters and ion exchange system is used for this process. The
objective of producing ultra-pure brine required for membrane cell operation is achieved. Polished brine after
heating through brine heater is passed through two ion exchange columns connected in series. The columns have
cation exchange resin, which provides active sites for adsorption of residual calcium and magnesium salts still
present in brine. Brine is passed through heat exchanger for achieving the temperature required at cell inlet.
Electrolysis: Brine flows into the anode chamber. Cl2 is liberated at the anode surface with depleted brine left
behind. Cl2 and depleted brine overflows from the anode chambers into the anolyte header. Weak caustic flows
SALT
BRINE PREPARATION
RO / RAIN WATER LIME STONE COKE
LIME KILNS
ABSORPTION
CARBONATION
CALCINATION
DENSIFICATION
STORAGE
WASTE TREATMENT
DISTILLATION
COMPRESSION
GAS CONDENSATION
PACKING
FILTERATION
FINAL PRODUCTS
CLEAR LIQ. TO SALT WORKS
AIR
STEAM 38-40% CO2
80-90% CO2
PURIFIED BRINE CaCl2 Waste
CRUDE BICARBONATE
STEAM
LSA
DSA
LSA
LSA & DSA
MOTHER LIQUOR
NH4Cl
AMMONIA GAS
AMMONIA MAKE UP
LIME
CO2 + H2O
STEAM
ZERO
DISCHARGE
NIRMA LIMITED PFR – PROPOSED EXPANSION IN SODA ASH, CAUSTIC SODA PRODUCTION AND
CAPTIVE POWER PLANT IN EXISTING FACILITY AT KALATALAV, NEAR BHAVNAGAR PROJECT DESCRIPTION
KADAM ENVIRONMENTAL CONSULTANTS | NOVEMBER, 2017 11
into the cathode chamber. H2 is generated at the cathode surface and OH ions combine with the Na+ ions diffusing
through the membrane. A two-phase mixture of 32% NaOH and hydrogen overflows into the catholyte header.
Anode Reaction: 2NaCl 2Na+ + Cl2 + 2 e –
Cathode Reaction: 2H2O + 2 e – 2OH– +H2
Overall Reaction: 2NaCl + 2H2O 2NaOH + Cl2 + H2
Catholyte System: In the catholyte header the two-phase mixture of NaOH and Hydrogen gets separated. This
catholyte stream is tapped as “Product” and fed to the caustic evaporation unit. Whole stream is not tapped and
some part is sent for internal consumption.
Anolyte Dechlorination: Depleted brine containing dissolved chlorine (called anolyte) is dechlorinated in two
stages: Vacuum dechlorination and chemical dechlorination. A part stream of chemically dechlorinated brine is be
purged out of the system to keep the sulphate within the desired levels.
Caustic Evaporation Unit: Here the incoming 32% Caustic is concentrated to 50%. The 50% caustic coming
from this unit can be stored in 50% storage tank.
Chlorine Treatment: The water vapor is removed, from the saturated chlorine, using series of coolers. The gas is
then passed through the moist chlorine filter to remove the entrained brine aerosol. In drying towers 98% H2SO4 is
used to dry moist chlorine.
The dried chlorine gas is compressed to the required pressure and then liquefied. Liquid chlorine from the liquefiers
is sent to liquid chlorine storage tanks. Sniff gas from the liquefier containing inlets and chlorine gas is sent to the
HCl synthesis unit. Excess sniff gas, is diverted to the waste air system.
Hydrogen Treatment: Hydrogen gas leaving the cells saturated with water vapor is cooled. The cooled gas is
passed through filters to remove the NaOH aerosols. Some amount of hydrogen is required for HCl synthesis and a
part of the gas is sent to caustic flaking unit to be used as fuel and a part is sent to hydrogen bottling through
hydrogen compressors as per requirement and the balance hydrogen is vented through with flame arrestor.
HCl Synthesis Unit
Hydrogen is burnt in Chlorine atmosphere and the combustion gases are absorbed in water to yield a 32% HCl
solution. HCl produced is pumped to HCl head tank from HCl receiver for internal consumption within plant. The
Block diagram showing the Caustic Soda Manufacturing Process is shown in Figure 3-4.
NIRMA LIMITED PFR – PROPOSED EXPANSION IN SODA ASH, CAUSTIC SODA PRODUCTION AND
CAPTIVE POWER PLANT IN EXISTING FACILITY AT KALATALAV, NEAR BHAVNAGAR PROJECT DESCRIPTION
KADAM ENVIRONMENTAL CONSULTANTS | NOVEMBER, 2017 12
Figure 3-4: Process Flow Diagram - Caustic Soda Manufacturing Process
3.5.3 Captive Power Plant (Existing + Expansion)
In the case of lignite/coal-fired boilers, steam generation with any of following firing technology is technically
feasible:
Circulating fluidized bed combustion (CFBC)
Pressurized Fluidized Bed Combustion (PFBC)
Integrated Gasification Combined Cycle (IGCC)
Pulverized Fuel Firing (PF)
Circulating fluidized bed combustion (CFBC) technology is adopted for the proposed captive power plant. A 100 MW
captive power plant turbo-alternator and 350 TPH + 350 TPH (standby) lignite / coal / petcoke based CFBC Boilers,
along with captive power plant machineries will be installed in order to meet internal steam and power requirement
for the proposed expansion.
The steam generator units proposed for the plant will be compact, semi-outdoor, natural/assisted circulation,
balanced draft, single drum, water tube type provided with Circulating Fluidized Bed Combustion system using pan-
leg furnace configuration. In a typical Circulating Fluidized Bed furnace, the lignite fed on a bed of suitable inert
material with addition of a sorbent material (such as lime stone) is burnt in suspension through the action of
primary air distributed below the combustor floor. In addition, secondary air is introduced at suitable points in the
combustion zone to ensure controlled and complete combustion of the fuel. Suitable lignite feeding and limestone
feeding arrangements are provided in the typical Circulating Fluidized Bed Combustion systems and is commonly
used as bed material for initial start-up of the boiler. The steam generators will be designed for satisfactory
continuous operation with the range of lignite/coal expected for this plant without any need for auxiliary fuel oil for
fire stabilization etc. Lignite and Coal are used as fuel after mixing in appropriate ratio.
VENT
CAUSTIC TO STORAGE AND
FILLINGSALT SATURATION
BRINE PRECIPITATION
CHLORATE DESTRUCTION
CATHOLYTE SYSTEM
DM WATER/CONDENSATE
CHEMICALS Na2CO3,NaOH SALT
FLOCCULANT
NaHSO3, NaOH 32% SOLUTION
DM WATER
FLAKES STORAGEAND BAGGING
HYDROGEN BOTTLING
FLAKING UNIT
CAUSTIC EVAPORATION
CHLORINE LIQUEFICATION
HYDROGEN TREATMENT
LIQUID CHLORINE STORAGE
CHLORINE FILLING
48.5 / 50%NaOH SOLUTION
BRINE PURIFICATION
(ION EXCHANGE)
BRINE FILTRATION
SLUDGE FILTRATION
BRINE CLARIFICATION
ANOLYTE DECHLORINATION
SLUDGE
CHLORINE COOLING &
DRYING
98% H2SO4
CHLORINE COMPRESSION
ANODE CATHODE+ -
78% H2SO4
H2 TO STACK
HCL FILLING
HCL STORAGE
HCL SYNTHESIS UNIT
HYPO FILLING
HYPOCHLORITE STORAGE
WASTE GAS DECHLORINATION
VENT
SALT SATURATION
BRINE PRECIPITATION
CATHOLYTE SYSTEM
NIRMA LIMITED PFR – PROPOSED EXPANSION IN SODA ASH, CAUSTIC SODA PRODUCTION AND
CAPTIVE POWER PLANT IN EXISTING FACILITY AT KALATALAV, NEAR BHAVNAGAR PROJECT DESCRIPTION
KADAM ENVIRONMENTAL CONSULTANTS | NOVEMBER, 2017 13
Steam generating unit would be provided with electrostatic precipitator in the flue gas path. The overall efficiency
of ESP will be around 99.70% with one field remaining as operational standby. The ESP would have adequate
number of ash hoppers provided with electric heaters. The design of ESP will be such that the dust burden at the
outlet of chimney with one field out of service doesn’t exceed 50 mg/Nm3 at 100 % BMCR with worst fuel.
Common chimney for boiler G and H will be constructed. The NOx emission from the steam generator is least in
case of CFBC steam generator design in view of low combustion temperature maintained in the furnace. The steam
generator and auxiliaries will perform continuously within noise limits as per relevant standard specification but not
more than 85 dB (A) at 1.0 meter from any equipment or sub equipment. The steam from the boiler will go to back
pressure turbo generators. The extracted back pressure steam will be used in process.
3.6 Utilities
The estimated list of utilities required for the new project is as given below:
3.6.1 Power Requirement
The total additional power demand for the expansion has been estimated about 152.82 MW. The power
requirement will be met by installing additional coal / lignite / pet-coke based CFBC boiler (410 TPH & 130 TPH,
total 540 TPH*) along with Turbo-alternator and utilizing some surplus steam from existing boilers.
* Capacity of proposed boilers may vary however total proposed capacity of steam generation will remain same as
540 TPH.
Arrangement has also been made for sourcing power through sub-station of Gujarat State Electricity Board.
3.6.2 Fuel Requirement
Coal: 240.25 T/hr. &/or Lignite: 245 T/hr. &/or Pet coke: 163 T/hr. (93 T/hr for proposed boilers + 70 T/hr for
existing boilers). Light Diesel Oil (LDO) shall be required for start-up of CFBC boiler.
3.6.3 Water Requirement
Existing Seawater intake facility i.e. from Sonarai Creek, near village Gundala. Existing seawater intake – 14 x 105
m3/day. Additional seawater intake - 3.6 x 105 m3/day.
3.6.4 Storage Details
Unit will create additional storage facilities for products, raw materials as per the MSIHC rules.
3.7 Pollution Load on Environment due to project
Environmental issues include:
Air emissions;
Wastewater;
Solid Wastes.
3.7.1 Air Emissions & Control
Point Source
Likely air pollutants from proposed project shall be PM, SOx & NOx from flue gas stack, HCl, Cl2 & NH3 from process
stacks/vents as point source.
NIRMA LIMITED PFR – PROPOSED EXPANSION IN SODA ASH, CAUSTIC SODA PRODUCTION AND
CAPTIVE POWER PLANT IN EXISTING FACILITY AT KALATALAV, NEAR BHAVNAGAR PROJECT DESCRIPTION
KADAM ENVIRONMENTAL CONSULTANTS | NOVEMBER, 2017 14
Volume Source
PM emission from coal storage yard is envisaged as volume source emissions.
Fugitive Emissions
Line Source Emissions
The ambient air quality & stack emissions will be maintained as per GPCB/CPCB norms. Details of proposed stacks
with fuel consumption and attached Air Pollution Control Equipment details are tabulated in Table 3-3 & Table
3-4.
Table 3-3: Details of Stack Emissions
S. No. Stack Attached to Stack Height
(m)
Stack Top
Dia. (m) APCM
Expected
Pollutants*
Existing
Soda Ash Division
1 Boiler - A, B, C & D (100 TPH Each) 100 (Common
Stack) 5.04
ESP to Each
Boiler PM, SO2 & NOx
2 DG Set (1000 KVA)
2 No. 24 each 0.2 -- PM, SO2 & NOx
Caustic Soda & CPP Division
2 Boiler - E (200 TPH) 121 (Common
Stack) 4.5
ESP PM, SO2 & NOx
3 As per EC 2014 Boiler - F (200 TPH) –
Not Installed Yet ESP PM, SO2 & NOx
4
As per EC 2017 Boiler - G & H (350 TPH
each ) – Installed One boiler having
capacity 410 TPH
121 (Common
Stack) 4.5 ESP PM, SO2 & NOx
5 DG Set (1000 KVA) 30 0.32 - PM, SO2 & NOx
6 DG Set (1500 KVA) 30
0.32
-
PM, SO2 & NOx
7 DG Set (1500 KVA)
Toilet Soap plant
8 Thermic Fluid Heater
(3 No.) 45 0.4 PM, SO2 & NOx
Proposed
Soda Ash Division
1. DG Set (2000 KVA) 30 0.32 -- PM, SO2 & NOx
Caustic Soda & CPP Division
1 Boiler - I & J (410 TPH + 130 TPH) * 121 (Common
Stack) 4.5 ESP PM, SO2 & NOx
2 DG Set (1850 KVA) 30 0.32 -- PM, SO2 & NOx
* Capacity of proposed boilers may vary however total proposed capacity of steam generation will remain same as
540 TPH.
Table 3-4: Details of Process Emissions
Sr.
No. Vent Attached to
Stack
Height (m)
Stack Dia.
(m)
Air Pollution Control
System Pollutant
1
Soda Ash Plant – Existing & Proposed
Lime Kilns (A to H) – 8 nos. 68 (Common
Stack) 0.8
4 scrubbers and 3 ESP in
Series PM, SO2, NOx
Ammonia Recovery System (A
to E) 5 No.
56 (Common
Stack) 0.75 Brine Scrubbers (5 nos.) Ammonia
NIRMA LIMITED PFR – PROPOSED EXPANSION IN SODA ASH, CAUSTIC SODA PRODUCTION AND
CAPTIVE POWER PLANT IN EXISTING FACILITY AT KALATALAV, NEAR BHAVNAGAR PROJECT DESCRIPTION
KADAM ENVIRONMENTAL CONSULTANTS | NOVEMBER, 2017 15
Sr.
No. Vent Attached to
Stack
Height (m)
Stack Dia.
(m)
Air Pollution Control
System Pollutant
Lime Grinding System A to E
(5 nos.)
60
(each) 0.65 Bag Filter PM
Calcinations Vessel (A to D 4
nos) 29 (each) 0.7 Water Scrubber PM
Densification 1 40 1.37 Water Scrubber PM
Densification 2 51 1.37 Water Scrubber PM
Densification 3 51 1.37 Water Scrubber PM
Lime Kilns (I to L) – 4 nos.
(Proposed)
68 (Common
Stack) 0.8
Two scrubbers and two
ESP in Series PM, SO2, NOx
Ammonia Recovery System (F
& G) 2 nos. (Proposed)
56 (Common
Stack) 0.75 Brine Scrubbers (2 nos.) Ammonia
Lime Grinding System (F 1
nos.) (Proposed) 60 0.65 Bag Filter PM
Calcinations Vessel (E & F 2
nos) (Proposed)
29 (Common
vent) 0.7 Water Scrubber PM
Densification 4 (Proposed) 51 1.37 Water Scrubber PM
2
Caustic Soda and CPP - Existing & Proposed
HCl Synthesis Unit – 1 30 0.1 Water Scrubbers HCl & Cl2
HCl Synthesis Unit - 2 30 0.1 Water Scrubbers HCl & Cl2
HCl Synthesis Unit – 3 30 0.1 Water Scrubbers HCl & Cl2
HCl Synthesis Unit - 4 30 0.1 Water Scrubbers HCl & Cl2
HCl Synthesis Unit – 5
(Proposed) 30 0.1 Water Scrubbers HCl & Cl2
Waste Gas Dechlorination
System - 1 30 0.3 18% NaOH Scrubber Cl2
Waste Gas Dechlorination
System - 2 30 0.3 18% NaOH Scrubber Cl2
Waste Gas Dechlorination
System – 3 30 0.3 18% NaOH Scrubber Cl2
Hydrogen unit with Flame arrestor and steam snuffing –
1 30 -- -- --
Hydrogen unit with Flame
arrestor and steam snuffing –
2
30 -- -- --
Hydrogen unit with Flame
arrestor and steam snuffing –
3
30 -- -- --
3. Bromine Plant
De-bromination System 30 0.3 Alkali Scrubber Bromine
4.
Chlorine & Hydrogen Derivatives
Solvent Recovery 30 0.3 Ceramic + Activated
Carbon Filter Aromatic Solvent
Hydrogenation Plant (purge
gas) 30 0.3
Ceramic + Activated
Carbon Filter
H2 + Aromatic
Solvent
Incinerator & its scrubber 30 0.3 Water Scrubber PM, SO2, CO, NOx,
HCl, TOC
HCl Synthesis Unit 30 0.1 Water Scrubbers HCl
NIRMA LIMITED PFR – PROPOSED EXPANSION IN SODA ASH, CAUSTIC SODA PRODUCTION AND
CAPTIVE POWER PLANT IN EXISTING FACILITY AT KALATALAV, NEAR BHAVNAGAR PROJECT DESCRIPTION
KADAM ENVIRONMENTAL CONSULTANTS | NOVEMBER, 2017 16
Sr.
No. Vent Attached to
Stack
Height (m)
Stack Dia.
(m)
Air Pollution Control
System Pollutant
Chlorination Plant 30 0.3 Acidic/Water Scrubber (3
nos.) SO2, HCl, Cl2
Chlorination Plant 30 0.3 Alkali Scrubber (3 nos.) Cl2
Chlorination 30 0.3 Water Scrubber SO2, HCl, Cl2
Hydrogenation Plant (purge
gas) 30 0.3 ---- H2
3.7.2 Noise Generation
From the proposed project, noise shall be generated from the various activities. Source of noise generation are:
The heavy machinery like crane, dumper, roller, bulldozers etc. will be used during daytime during construction
phase;
Operation of plant machinery and diesel generator set;
Vehicle movement for transportation of raw material.
3.7.3 Waste Water Generation
The main source of the industrial wastewater generation will be from domestic, process, utilities, washing and
others. The total quantity of effluent will be increased from 5,86,445.2 KLD to 9,06,634.7 KLD. Entire quantity of
wastewater will be treated in existing treatment facilities. In existing scenario Treated effluent is partly reused /
recirculated in salt works and around 12000 m3/day of Soda Ash effluent and 6000 m3/day of Bittern is being
disposed off in to the sea at a discharge point suggested by National Institute of Oceanography (NIO).
In proposed expansion, Additional soda ash effluent, additional bittern & cooling water will be disposed in sea along
with existing effluent and bittern at point suggested by NIO. Return cooling water of 3,00,000 m3/day will be
disposed into deep sea at a discharge Point suggested by NIO on permanent basis and during emergency purpose /
monsoon 8,60,000 m3/day will be disposed into sea.
Details of Waste water generation is given in
Table 3-5: Wastewater Generation Details
Sr. No. Source Wastewater Generation (m3/day)
Existing Proposed Total
Soda Ash plant
1. Domestic 184 99 283
2. Process 32,547 17,436 49,983
3. Boiler 216 0 216
4. Cooling 4,73,571 2,86,840 7,60,411
5. Others 0 0 0
Total (I) 5,06,518 3,04,375 8,10,893
Toilet Soap plant
1. Domestic 48 0 48
2. Process 0 0 0
3. Washing 25 0 25
4. Cooling 275 0 275
Total (II) 348 0 348
Caustic Soda Plant & CPP
1. Domestic 11 3.5 14.5
2. Process 750 250 1,000
NIRMA LIMITED PFR – PROPOSED EXPANSION IN SODA ASH, CAUSTIC SODA PRODUCTION AND
CAPTIVE POWER PLANT IN EXISTING FACILITY AT KALATALAV, NEAR BHAVNAGAR PROJECT DESCRIPTION
KADAM ENVIRONMENTAL CONSULTANTS | NOVEMBER, 2017 17
Sr. No. Source Wastewater Generation (m3/day)
Existing Proposed Total
3. Boiler 1,340 447 1,787
4. Cooling 4,03,842 14,614 58,456
Total (III) 45,943 15,314.5 61,257.5
Salt works
1. Salt works 11,000 500 11,500
Total (IV) 11,000 500 11,500
Bromine plant
1. Cooling tower 1,000 0 1,000
2. Process 12,500 0 12,500
Total (V) 13,500 0 13,500
Chlorine & Hydrogen Derivatives
1. Domestic 6.6 0 6.6
2. Process + DM 1,595 0 1,595
3. Cooling + Chilling 2,977 0 2,977
4. Boiler 0 0 0
5. Washing/Others 41 0 41
Total (VI) 4,619.6 0 4,619.6
RBC Plant, Calcium Chloride plant & Phosphoric acid plant
1 Domestic 8.6 0 8.6
2 Process 4,250 0 4,250
3 Cooling 258 0 0
Total (VII) 4,516.6 0 4,516.6
Grand Total (I to VI) 5,86,445.2 3,20,189.5 9,06,634.7
3.7.4 Hazardous Waste & Other Solid Waste
The main source of hazardous waste generation will increase after proposed expansion. ETP sludge will be dispose
to TSDF site. Used oil will be sold to authorized recycler and discarded containers & plastic liners will be sold to
registered recyclers.
The details of Solid & hazardous waste are given in Table 3-6 & Table 3-7.
Table 3-6: Solid Waste Generation & Disposal
Sr.
No. Solid Waste
Quantity (TPD) Mode of Disposal
Existing Proposed After Expansion
1 Settling Pond Sludge 880 482 1,362 Shall be used in road construction,
salt works bund preparation
2 Lime stone rejects /under
size 700 375 1,075
Shall be used in boilers for
desulphurization in boilers
3 Brine Sludge 19 10 29 Non-hazardous; Shall be used
dumped in identified area
4 Fly ash/ Bottom ash 2,185 1,693 3,878 Brick manufacturing, bund
preparation, road making etc…
5 Incineration Ash --- 15 15 Brick manufacturing, bund
preparation, road making etc…
6 Saponification
Solid Waste 3 0 3
Non-hazardous; Shall be
dumped in identified area
NIRMA LIMITED PFR – PROPOSED EXPANSION IN SODA ASH, CAUSTIC SODA PRODUCTION AND
CAPTIVE POWER PLANT IN EXISTING FACILITY AT KALATALAV, NEAR BHAVNAGAR PROJECT DESCRIPTION
KADAM ENVIRONMENTAL CONSULTANTS | NOVEMBER, 2017 18
Table 3-7: Hazardous Waste Generation and Disposal
S No Hazardous Waste Category
Quantity (MTPA)
Mode of Disposal Existing Proposed
Total After
Expansion
1
Soda Ash Plant
Waste Oil/ Lub. Oil
from 5.1 10 5 15
Collection, Storage, Transportation &
disposal by selling to Registered
Recyclers
Spent ion exchange
resins 34.2
1,830
lt/year
980
lt/year 2,810 lt/year
Collection, Storage, Transportation,
Disposal by selling to authorized
recyclers or sent to NECL Nandesari
for Incineration.
Discarded
bags/drums/containers
etc…
33.3 3.5 2 5.5
Collection, Storage, Transportation,
Disposal by selling to authorized
recyclers
2
Caustic Soda Plant
Waste Oil/ Lub. Oil
from 5.1 30 kl 10 kl 40 kl
Collection, Storage, Transportation &
disposal by selling to Registered
Recyclers
Spent ion exchange
resins 34.2 2.56 1 3.56
Collection, Storage, Transportation,
Disposal by selling to authorized
recyclers or sent to NECL Nandesari
for Incineration.
Discarded
Bags / drums /
containers etc…
33.3 4.5 1.5 6
Collection, Storage, Transportation,
Disposal by selling to authorized
recyclers
Residue/ Sludge &
Filter sludge 16.2 6,526 2,175 8,701
Collection, Storage, Transportation,
Disposal at TSDF
ETP sludge 34.3 150 50 200 Collection, Storage, Transportation,
Disposal at TSDF
Spent Sulphuric Acid
(80%) D2 6,520 2,173 8,693
Collection, Storage, Transportation,
reuse as raw material for Nirma Ltd.
Moraiya and other end users.
3
Toilet Soap Plant
Waste Oil/ Lub. Oil
from 5.1 0.45 0 0.45
Collection, Storage, Transportation &
disposal by selling to Registered
Recyclers
ETP sludge 34.3 48 0 48 Collection, Storage, Transportation,
Disposal at TSDF
Glycerin foot D6-II 72 0 72
Collection, Storage, Transportation &
disposal by selling to M/s. Ultratech
Cement for Co- incineration in cement
kiln/NECL for Incineration.
Spent Sulphuric Acid
(80%) D2 24,000 0 24,000
Collection, Storage, Transportation,
reuse as raw material for Nirma Ltd.
Moraiya and other end users.
NIRMA LIMITED PFR – PROPOSED EXPANSION IN SODA ASH, CAUSTIC SODA PRODUCTION AND
CAPTIVE POWER PLANT IN EXISTING FACILITY AT KALATALAV, NEAR BHAVNAGAR PROJECT DESCRIPTION
KADAM ENVIRONMENTAL CONSULTANTS | NOVEMBER, 2017 19
S No Hazardous Waste Category
Quantity (MTPA)
Mode of Disposal Existing Proposed
Total After
Expansion
4
Chlorine & Hydrogen Derivatives
Waste Oil/ Lub. Oil 5.1 10 0 10
Collection, Storage, Transportation &
disposal by selling to Registered
Recyclers
Discarded containers/
Barrels/empty
drums/empty bags
33.3 10 0 10 Collection, Storage and disposal by
selling to authorized recyclers.
ETP sludge 34.3 120 0 120 Collection, Storage, Transportation,
Disposal at TSDF
Glycerin foot D6-II 5,356 0 5,356 Collection, Storage & incineration in
plant incinerator.
Catalyst from
regeneration 35.2 1.2 0 1.2
Collection, Storage, Transportation,
Disposal at Common Haz. Waste
incineration facility
Spent Carbon from
solvent recovery 35.3 3 0 3
Collection, Storage, Transportation,
Disposal at Common Haz. Waste
incineration facility
Spent Carbon from
ETP 34.3 3 0 3
Collection, Storage, Transportation,
Disposal at TSDF
Distillation Residue 36.4 550 0 550
Collection, Storage, Transportation,
Disposal at Common Haz. Waste
incineration facility.
NIRMA LIMITED PFR – PROPOSED EXPANSION IN SODA ASH, CAUSTIC SODA PRODUCTION AND
CAPTIVE POWER PLANT IN EXISTING FACILITY AT KALATALAV, NEAR BHAVNAGAR SITE ANALYSIS
KADAM ENVIRONMENTAL CONSULTANTS | NOVEMBER, 2017 20
4 SITE ANALYSIS
4.1 Connectivity
4.1.1 By Road
The nearest highway (Bhavnagar-Ahmedabad SH-6 Coastal highway) is about 14.0 kms away from the plant in the
West direction.
4.1.2 By Rail
Major railway station for public transportation is Bhavnagar Railway Station located at an aerial distance of ~10 Km
from the project site in the South-South West Direction.
4.1.3 By Air
Bhavnagar has its own airport, Bhavnagar Airport, which is at ~10 Km from project site.
4.2 Land Form, Land use & Land Ownership
There will be no change in landuse as the necessary expansion will be within the integrated complex of Nirma
Limited. Land Cover will be as per the Site Layout Map as shown in Annexure 1.
4.3 Topography
Project site is shown on Toposheet in Annexure 2.
4.4 Existing Infrastructure
Existing infrastructure like roads, power supply, water supply line, etc. are readily available at the site.
4.5 Soil Classification, Geology & Drainage
4.5.1 Soil Classification
Bhavnagar district is located in the south-eastern part of Saurashtra peninsula of Gujarat. The soil type is a mixture
of sand & gravel with intermediate golden colour laterites with clay as binder. The subsoil strata of the study area
consist of a mixture of sandy gravel with clay as binder in the top 10 m. Thereafter the strata of about 50 m is a
thick layer of Grayish-blue clay having very hard to stiff consistency tending to rock like formation. The topsoil
around Kalatalav is made up of coarse saline soil poor in nutrients.
Most of the 10 km radial zone around Kalatalav has alluvial deposits and consists of sandy soil, tidal mudflats,
raised beaches and freshwater alluvium. Clay (size < 0.002mm) amount in the soil samples ranges from 17% to
22%; Silt (size 0.002 to 0.075 mm) in the soil samples is 14% to 18% Sand (size 0.075 to 0.475mm) in the soil
samples is 50% to 58% and gravel (size > 4.75 mm) in soil samples is 10% to 14%.
4.5.2 Geology
The Bhavnagar district is located in the south-eastern part of Saurashtra peninsula of Gujarat. It falls in the seismic
zone-III as per IS 1893 (part -1) 2003. Peninsula is bounded by sea on all sides except northeast side where it is
flanked by alluvium plains of main land.
NIRMA LIMITED PFR – PROPOSED EXPANSION IN SODA ASH, CAUSTIC SODA PRODUCTION AND
CAPTIVE POWER PLANT IN EXISTING FACILITY AT KALATALAV, NEAR BHAVNAGAR SITE ANALYSIS
KADAM ENVIRONMENTAL CONSULTANTS | NOVEMBER, 2017 21
Bhavnagar district shows diverse features like uneven, rocky (basaltic) land surface traversed by mountain
ranges/ridges and trappean dykes. Most of the district is composed of Weathered to Hard & massive Deccan Trap
formation, which is impervious with low yield. Rocks with cracks, fractures and fissures provide some discharge and
potable water quality.
4.6 Climatic data from secondary sources
Information presented in subsequent paragraphs is from the Indian Meteorological Department (IMD), Long Term
Climatological Tables, 1981-2010, Bhavnagar (A). These tables give useful information about a region’s weather,
since they are collected over a 29-year period. Copy of the same is attached as Annexure 3.
Mean daily maximum temperature is recorded in the month of May at 40.0°C. From October to December, both day
and night temperatures begin to decrease rapidly. January is generally the coldest month, having minimum
morning temperature at 13.9°C. During the post-monsoon months of October, November, December day
temperatures remain between 17.8ºC - 26.7ºC. In winters, i.e. December, January and February, average day
temperatures remain between 16.2 – 18.8ºC.
The total rainfall in year is observed to be 655.9 mm. Distribution of rainfall by season is 2.4 mm in winter
(December, January, February), 5.2 mm in summer (March, April, May), 612.4 mm in monsoons (June, July,
August, September) and 35.9 mm in post-monsoons (October, November, December). Annual total heaviest rainfall
recorded in 24 hrs is observed to be 434.4 mm on 20th July, 1996.
An online weather logger was set up at Plant site. The co-ordinates for the same are 21051’14.1”N; 72010’32.8”E.
4.7 Social Infrastructure Available
Educational Facilities
As per 2001 census in all 5 villages, there are 4 primary schools & other educational facilities are in 10 km radius of
the study area.
Medical Facilities
Out of 4 villages in the study area, one has Primary Health Sub-Centers & other medical facilities are within 10 km
of the study area. Almost all medical facilities are available there.
Drinking Water Supply
All the villages in the study area have two or more sources of drinking water. All villages in study area have tap
water supply (almost all) with tank water supply. One village has well water facility.
Communication & Transport
The main mode of public transport available in the study area is by bus service. All villages are near Bhavnagar, so
almost all villages have approach to railway station as western railway meter gauge line is passing through nearby.
Post & Telegraph
There are 5 villages in study area, 2 villages have post office facility at doorstep & almost all have phone facility.
Power Supply
All the villages are getting power supply for domestic purposes.
NIRMA LIMITED PFR – PROPOSED EXPANSION IN SODA ASH, CAUSTIC SODA PRODUCTION AND
CAPTIVE POWER PLANT IN EXISTING FACILITY AT KALATALAV, NEAR BHAVNAGAR PLANNING BRIEF
KADAM ENVIRONMENTAL CONSULTANTS | NOVEMBER, 2017 22
5 PLANNING BRIEF
5.1 Planning Concept
Site falls under the seismic Zone III, which is classified as Low Risk zone (Area liable to shaking Intensity VI (and
lower). Thus, suitable seismic coefficients accordingly shall be adopted while designing the structures to make it
earthquake resistant.
Basic facilities of infrastructure like admin building, processing area, storage area, internal roads etc. are already
developed in the project site.
5.2 Landuse Planning
There will be no change in landuse as the necessary expansion will be within the integrated complex of Nirma Ltd.
5.3 Assessment of Infrastructure Demand (Physical & Social)
No additional infrastructure demand is required.
5.4 Amenities/Facilities
Within the study area (i.e. 10 kms) basic amenities/ facilities like there are 4 primary schools & other educational
facilities, is available in all the nearby villages. Out of 4 villages in the study area, one has Primary Health Sub-
Centres & other medical facilities are within 10 km of the study area. Bhavnagar is nearest city to the study area,
which is around 10 km away from project site. Almost all medical facilities are available there.
All the villages in the study area have two or more sources of drinking water. All villages in study area have tap
water supply (almost all) with tank water supply. One village has well water facility. The main mode of public
transport available in the study area is by bus service. All villages are near Bhavnagar, so almost all villages have
approach to railway station as western railway meter gauge line is passing through nearby. Majority of villages in
the study area is connected with pucca road. Out of 5 villages in study area, 2 villages have post office facility at
doorstep & almost all have phone facility. All the villages are getting power supply for domestic purposes.
NIRMA LIMITED PFR – PROPOSED EXPANSION IN SODA ASH, CAUSTIC SODA PRODUCTION AND
CAPTIVE POWER PLANT IN EXISTING FACILITY AT KALATALAV, NEAR BHAVNAGAR PROPOSED INFRASTRUCTURE
KADAM ENVIRONMENTAL CONSULTANTS | NOVEMBER, 2017 23
6 PROPOSED INFRASTRUCTURE
6.1 Industrial Area (Processing Area)
The existing unit comprises of following sections:
Boiler House consisting of CFBC Boilers – 2 Nos., Steam Turbine, Alternator / Generator;
Fuel storage area;
Utility Area consisting of cooling tower, compressors, ESP section, ETP area;
Fly Ash & Hazardous waste storage area.
Adequate storage space for fuel storage, hazardous and other solid waste is already available. Additional storage
space will be provided as per the requirement.
6.2 Non- Processing Area
Existing non processing area includes Weighbridge, Administrative Building, Laboratory, Security cabins, Workers
restroom, Vehicle Shed, Water reservoirs for raw water and fire hydrant system, Temporary storage sites, Works
block etc.
6.3 Greenbelt
Nirma has done extensive plantation in around 110 acres and spared total 183.4 acres for greenbelt development.
Unit is also taking interest to develop greenbelt peripheral outside of the factory premises
6.4 Social Infrastructure
Refer Chapter 4, Section 4.7.
6.5 Connectivity
Refer Chapter 4, Section 4.1.
6.6 Drinking Water Management
Drinking water source for the existing Nirma plant at Kalatalav is from RO plant.
6.7 Sewage System
Sewage would be generated from the various units within the manufacturing facility. The existing sewage quantity
generated is 258.2 m3/day. The sewage expected to be generated for proposed expansion would be 102.5 m3/day.
Thus, the total sewage generation would be 360.7 m3/day. The sewage would be disposed off in soak pits of
individual plants and the same is being used in greenbelt development.
6.8 Industrial Waste & Solid Waste Management
Solid and hazardous waste as mentioned in Chapter 3, Section 3.7.4 shall be collected, stored, disposed to
authorized vendors and sold to local suppliers as per it’s characterization and based on the prescribed Fly Ash
NIRMA LIMITED PFR – PROPOSED EXPANSION IN SODA ASH, CAUSTIC SODA PRODUCTION AND
CAPTIVE POWER PLANT IN EXISTING FACILITY AT KALATALAV, NEAR BHAVNAGAR PROPOSED INFRASTRUCTURE
KADAM ENVIRONMENTAL CONSULTANTS | NOVEMBER, 2017 24
Notification, 2015 & Hazardous Waste Rules, 2016 amended till date. Other wastes to be generated from the
project are tabulated in Table 6-1. Details will be provided in EIA report.
Table 6-1: Identification of Other Wastes
S. No. Type of Waste Constituents
1 Municipal Solid Waste Kitchen waste, cardboard, paper and garden wastes
2 Inorganic Waste Scraps, paper bags, cardboards and glassware’s etc.
3 Plastic Waste Plastic bags, plastic scraps etc.
4 E-waste CD’s, LAN Cables, Fuses, Data cables, circuit boards, etc.
5 Biomedical Waste Syringe, Bandages, used cotton, medicine etc.
6 Construction & Demolition waste Debris
6.9 Power Requirement & Supply / Source
Refer Chapter 3, Section 3.6.1.
NIRMA LIMITED PFR – PROPOSED EXPANSION IN SODA ASH, CAUSTIC SODA PRODUCTION AND
CAPTIVE POWER PLANT IN EXISTING FACILITY AT KALATALAV, NEAR BHAVNAGAR R&R PLAN
KADAM ENVIRONMENTAL CONSULTANTS | NOVEMBER, 2017 25
7 REHABILITATION AND RESETTLEMENT (R&R) PLAN
Since no additional land is acquired for the proposed expansion project, and all the proposed units will be inside the
existing plant premises, R & R issues are not envisaged.
NIRMA LIMITED PFR – PROPOSED EXPANSION IN SODA ASH, CAUSTIC SODA PRODUCTION AND
CAPTIVE POWER PLANT IN EXISTING FACILITY AT KALATALAV, NEAR BHAVNAGAR PROJECT SCHEDULE & COST
ESTIMATE
KADAM ENVIRONMENTAL CONSULTANTS | NOVEMBER, 2017 26
8 PROJECT SCHEDULE AND COST ESTIMATE
8.1 Likely date of start of construction and likely date of completion
The construction is likely to start after getting Environmental Clearance and NOC/CTE from the authorized
committee. Tentative schedule for the project to be completed is given in Table 8-1.
Table 8-1: Tentative Project Time Schedule
S. No. Activities Start Finish
1 EC Approval November, 2017 August, 2018
2 Detailed Engineering January, 2019 April, 2019
3 Procurement and Delivery June, 2019 Delivery start from
December, 2019
4 Construction at Site (Buildings, Mech., Piping, Elec., Inst etc.) June, 2019 December, 2020
5 Pre Commissioning January, 2021 June, 2021
6 CTO Approval July, 2021 January, 2022
7 Process Startup and Stabilization September, 2021 March, 2022
8.2 Estimated Project Cost
The proposed project cost is estimated to be INR 1,320 crores. The breakup of project cost is given in Table 8-2.
Table 8-2: Breakup of Project Cost
S. No. Particulars Amount (INR in Crores)
1 Soda Ash Plant 570
2 Caustic Soda and CPP 750
Total Project Cost 1,320
8.2.1 Profitability
The project has been conceived upgrading old inefficient sets with new efficient sets, hence increasing profitability.
Further capacity enhancement leads to a reasonable ROI, based on consuming plant expansion.
NIRMA LIMITED PFR – PROPOSED EXPANSION IN SODA ASH, CAUSTIC SODA PRODUCTION AND
CAPTIVE POWER PLANT IN EXISTING FACILITY AT KALATALAV, NEAR BHAVNAGAR ANALYSIS OF PROPOSAL
KADAM ENVIRONMENTAL CONSULTANTS | NOVEMBER, 2017 27
9 ANALYSIS OF PROPOSAL
9.1 Financial and Social Benefits
During the construction phase around 150 workers and existing manpower is sufficient to operate proposed
expansion units. Local skilled and semi-skilled workers will be engaged during construction phase.
NIRMA LIMITED PFR – PROPOSED EXPANSION IN SODA ASH, CAUSTIC SODA PRODUCTION AND
CAPTIVE POWER PLANT IN EXISTING FACILITY AT KALATALAV, NEAR BHAVNAGAR ANNEXURES
KADAM ENVIRONMENTAL CONSULTANTS | NOVEMBER, 2017 28
ANNEXURES
NIRMA LIMITED PFR – PROPOSED EXPANSION IN SODA ASH, CAUSTIC SODA PRODUCTION AND CAPTIVE POWER PLANT IN EXISTING FACILITY AT KALATALAV, NEAR BHAVNAGAR ANNEXURES
KADAM ENVIRONMENTAL CONSULTANTS | NOVEMBER, 2017 29
Annexure 1: Preliminary Site Layout Map
NIRMA LIMITED PFR – PROPOSED EXPANSION IN SODA ASH, CAUSTIC SODA PRODUCTION AND CAPTIVE POWER PLANT IN EXISTING FACILITY
AT KALATALAV, NEAR BHAVNAGAR ANNEXURES
KADAM ENVIRONMENTAL CONSULTANTS | NOVEMBER, 2017 30
Annexure 2: Project Site Located on Toposheet showing 3, 5, 7 & 10 km Radii Circles
NIRMA LIMITED PFR – PROPOSED EXPANSION IN SODA ASH, CAUSTIC SODA PRODUCTION AND CAPTIVE POWER PLANT IN EXISTING FACILITY
AT KALATALAV, NEAR BHAVNAGAR ANNEXURES
KADAM ENVIRONMENTAL CONSULTANTS | NOVEMBER, 2017 31
Annexure 3: Long Term Meteorological Data for Bhavnagar City
NIRMA LIMITED PFR – PROPOSED EXPANSION IN SODA ASH, CAUSTIC SODA PRODUCTION AND CAPTIVE POWER PLANT IN EXISTING FACILITY
AT KALATALAV, NEAR BHAVNAGAR ANNEXURES
KADAM ENVIRONMENTAL CONSULTANTS | NOVEMBER, 2017 32
CONTACT DETAILS
Vadodara (Head Office)
871/B/3, GIDC Makarpura, Vadodara, India – 390 010.
E: [email protected]; T:+91-265-3001000; F: +91-265-3001069
Delhi / NCR
Spaze IT Park, Unit No. 1124, IIth Floor, Tower B3, Sector 49, Near Omaxe City Centre Mall, Sohna Road, Gurgaon,
Haryana, INDIA - 122002.
E: [email protected]; T: +91-124-4242430 to 436; F:+91-124-4242433
Kadam Environmental Consultants w w w . ka d a m en v i r o . c o m
Envi ronment for Deve lopment