Task Name Duration Start Finish
Phase 1 - Strategic Plan 23 days Mon 1/3/00 Wed 2/2/00
Self-Assessment 3 days Mon 1/3/00 Wed 1/5/00
Define business vision 1 day Mon 1/3/00 Mon 1/3/00
Identify available skills, information and support 1 day Tue 1/4/00 Tue 1/4/00
Decide whether to proceed 1 day Wed 1/5/00 Wed 1/5/00
Define the Opportunity 10 days Thu 1/6/00 Wed 1/19/00
Research the market and competition 1 day Thu 1/6/00 Thu 1/6/00
Interview owners of similar businesses 5 days Fri 1/7/00 Thu 1/13/00
Identify needed resources 2 days Fri 1/14/00 Mon 1/17/00
Identify operating cost elements 2 days Tue 1/18/00 Wed 1/19/00
Evaluate Business Approach 4 days Thu 1/20/00 Tue 1/25/00
Define new entity requirements 1 day Thu 1/20/00 Thu 1/20/00
Identify on-going business purchase opportunities 1 day Fri 1/21/00 Fri 1/21/00
Research franchise possibilities 1 day Mon 1/24/00 Mon 1/24/00
Summarize business approach 1 day Tue 1/25/00 Tue 1/25/00
Evaluate Potential Risks and Rewards 7 days Fri 1/21/00 Mon 1/31/00Assess market size and stability 2 days Fri 1/21/00 Mon 1/24/00
Estimate the competition 1 day Tue 1/25/00 Tue 1/25/00
Assess needed resource availability 2 days Wed 1/26/00 Thu 1/27/00
Evaluate realistic initial market share 1 day Fri 1/28/00 Fri 1/28/00
Determine financial requirements 2 days Wed 1/26/00 Thu 1/27/00
Review personal suitability 1 day Fri 1/28/00 Fri 1/28/00
Evaluate initial profitability 1 day Mon 1/31/00 Mon 1/31/00
Review and modify the strategic plan 2 days Tue 2/1/00 Wed 2/2/00
Confirm decision to proceed 0 days Wed 2/2/00 Wed 2/2/00
Phase 2 - Define the Business Opportunity 27 days Thu 2/3/00 Fri 3/10/00
Define the Market 13 days Thu 2/3/00 Mon 2/21/00
Access available information 1 day Thu 2/3/00 Thu 2/3/00
Create market analysis plan 2 days Fri 2/4/00 Mon 2/7/00
Implement market analysis plan 5 days Tue 2/8/00 Mon 2/14/00
Identify competition 2 days Tue 2/15/00 Wed 2/16/00
Summarize the market 2 days Thu 2/17/00 Fri 2/18/00
Identify target market niche 1 day Mon 2/21/00 Mon 2/21/00
Identify Needed Materials and Supplies 7 days Tue 2/22/00 Wed 3/1/00
Select a business approach (from "Evaluate Business
Approach" above)2 days Tue 2/22/00 Wed 2/23/00
Identify management staff resources 1 day Thu 2/24/00 Thu 2/24/00
Identify staffing requirements 1 day Fri 2/25/00 Fri 2/25/00
Identify needed raw materials 1 day Mon 2/28/00 Mon 2/28/00
Identify needed utilities 1 day Tue 2/29/00 Tue 2/29/00
Summarize operating expenses and financial projections 1 day Wed 3/1/00 Wed 3/1/00
Evaluate Potential Risks and Rewards 6 days Thu 3/2/00 Thu 3/9/00
Assess market size and stability 2 days Thu 3/2/00 Fri 3/3/00
Assess needed resources availability 2 days Mon 3/6/00 Tue 3/7/00
8/2/2019 New Business Plan Project
2/7
Forecast financial returns 2 days Wed 3/8/00 Thu 3/9/00
Review and modify the business opportunity 1 day Fri 3/10/00 Fri 3/10/00
Confirm decision to proceed 0 days Fri 3/10/00 Fri 3/10/00
Phase 3 - Plan for Action 21 days Mon 3/13/00 Mon 4/10/00
Develop Detailed 5-Year Business Plan 21 days Mon 3/13/00 Mon 4/10/00
Describe the vision and opportunity 1 day Mon 3/13/00 Mon 3/13/00
List assumptions 1 day Tue 3/14/00 Tue 3/14/00
Describe the market 1 day Wed 3/15/00 Wed 3/15/00
Describe the new business 1 day Thu 3/16/00 Thu 3/16/00
Describe strengths, weaknesses, assets and threats 1 day Fri 3/17/00 Fri 3/17/00
Estimate sales volume during startup period 1 day Mon 3/20/00 Mon 3/20/00
Forecast operating costs 1 day Tue 3/21/00 Tue 3/21/00
Establish pricing strategy 1 day Wed 3/22/00 Wed 3/22/00
Forecast revenue 1 day Thu 3/23/00 Thu 3/23/00
Summarize pro-forma financial statement 2 days Fri 3/24/00 Mon 3/27/00
Develop break-even analysis 1 day Tue 3/28/00 Tue 3/28/00
Develop cash-flow projection 1 day Wed 3/29/00 Wed 3/29/00
Identify licensing and permitting requirements 1 day Thu 3/30/00 Thu 3/30/00
Develop startup plan 2 days Fri 3/31/00 Mon 4/3/00
Develop sales and marketing strategy 1 day Tue 4/4/00 Tue 4/4/00
Develop distribution structure 1 day Wed 4/5/00 Wed 4/5/00
Describe risks and opportunities 2 days Thu 4/6/00 Fri 4/7/00
Publish the business plan 1 day Mon 4/10/00 Mon 4/10/00
Confirm decision to proceed 0 days Mon 4/10/00 Mon 4/10/00
Phase 4 - Proceed With Startup Plan 53 days Tue 4/11/00 Thu 6/22/00
Choose a location 1 day Tue 4/11/00 Tue 4/11/00
Establish Business Structure 24 days Wed 4/12/00 Mon 5/15/00
Choose a Name 2 days Wed 4/12/00 Thu 4/13/00
Identify implications 1 day Wed 4/12/00 Wed 4/12/00
Research name availability 1 day Thu 4/13/00 Thu 4/13/00
Choose a Bank 5 days Fri 4/14/00 Thu 4/20/00
Establish accounts 4 days Fri 4/14/00 Wed 4/19/00
Establish line of credit 1 day Thu 4/20/00 Thu 4/20/00
Choose legal representation 1 day Fri 4/21/00 Fri 4/21/00
Select business tax-basis category 2 days Mon 4/24/00 Tue 4/25/00Choose capital funding source 2 days Wed 4/26/00 Thu 4/27/00
Commit capital funding 0 days Thu 4/27/00 Thu 4/27/00
Establish the Operating Control Base 12 days Fri 4/28/00 Mon 5/15/00
Choose and set up the accounting system 2 days Fri 4/28/00 Mon 5/1/00
Obtain required licenses and permits 4 days Tue 5/2/00 Fri 5/5/00
Obtain needed insurance 4 days Mon 5/8/00 Thu 5/11/00
Establish security plan 2 days Fri 5/12/00 Mon 5/15/00
Develop Marketing Program 4 days Thu 4/13/00 Tue 4/18/00
8/2/2019 New Business Plan Project
3/7
Establish an advertising program 2 days Thu 4/13/00 Fri 4/14/00
Develop a logo 1 day Mon 4/17/00 Mon 4/17/00
Order promotional materials 1 day Tue 4/18/00 Tue 4/18/00
Provide Physical Facilities 15 days Tue 5/16/00 Mon 6/5/00
Secure operation space 5 days Tue 5/16/00 Mon 5/22/00
Select computer network hardware 1 day Tue 5/23/00 Tue 5/23/00
Select computer software 1 day Wed 5/24/00 Wed 5/24/00Establish utilities 3 days Thu 5/25/00 Mon 5/29/00
Provide furniture and equipment 4 days Tue 5/30/00 Fri 6/2/00
Move in 1 day Mon 6/5/00 Mon 6/5/00
Provide Staffing 40 days Fri 4/28/00 Thu 6/22/00
Interview and test candidates 14 days Fri 4/28/00 Wed 5/17/00
Hire staff 10 days Thu 5/18/00 Wed 5/31/00
Train staff 16 days Thu 6/1/00 Thu 6/22/00
Start up the business 0 days Thu 6/22/00 Thu 6/22/00
8/2/2019 New Business Plan Project
4/7
Predecessors Resource Names Legends
owners
3 Business Advisor,Manager
4 owners
5 Business Advisor
7 owners
8 Business Advisor,Peers
9 Accountant
Start date
10 Manager End date
12 Manager
13 Manager Hours each day
14 Manager Total hours
Total days12 Business Advisor Total months
17 Business Advisor
18 Business Advisor interiors
19 Business Advisor equipments
15 Business Advisor rent per month
21 Manager
22 Manager
23
24
25 Business Advisor
28 Business Advisor
29 Business Advisor
30 Business Advisor
31 Business Advisor
32 Business Advisor
28SS,33 Manager
35 Manager
36 Manager
37 Manager
38 Manager
39 Manager
40 Manager
42 Manager
8/2/2019 New Business Plan Project
5/7
43 Accountant
44
45
Business
Advisor,Peers,Lawyer,Account
ant
46 Business Advisor
49 Business Advisor
50 Business Advisor
51 Business Advisor
52 Business Advisor
53 Business Advisor,Accountant
54 Business Advisor,Accountant
55 Business Advisor
56 Business Advisor
57 Business Advisor
58 Business Advisor
59 Business Advisor
60 Business Advisor
61 Business Advisor
62 Business Advisor
63 Business Advisor
64 Business Advisor
65 Business Advisor
66 Business Advisor
67
69 Lawyer
72 Lawyer
73 Banker
75 Banker
Lawyer
77 Lawyer,Accountant78 Manager
79 Manager
79,80 Accountant
82 Lawyer,Government Agency
83 Accountant
84 Business Advisor,Lawyer
8/2/2019 New Business Plan Project
6/7
Business Advisor
87 Business Advisor,Lawyer
88 Business Advisor
85,89 Lawyer
91 Information Services
92 Information Services93 Manager
94 Manager
95 Manager
79 Manager
98 Manager
99 Manager
96,100 Manager
8/2/2019 New Business Plan Project
7/7
Main phases or Work activity
Sub-activites under Main phases
Important work activity under sub-activites
Project details
1/3/2000
6/22/2000
11 hours
1368 hours
124 days4.1 months
2500000 rs
7000000 rs
100000 rs starts after start up plan