Narva city development overview Sofja Homjakova Vice-Mayor of Narva, ESTONIA Contribution to Estonian presentation, Session C03 Sevilla 22.03.2007

Embed Size (px)

Citation preview

Page 1: Narva city development overview Sofja Homjakova Vice-Mayor of Narva, ESTONIA Contribution to Estonian presentation, Session C03 Sevilla 22.03.2007

Narva Narva city developmentcity developmentoverviewoverview

Sofja HomjakovaSofja HomjakovaVice-Mayor of Vice-Mayor of Narva, ESTONIANarva, ESTONIA

Contribution to Estonian presentation, Session C03Contribution to Estonian presentation, Session C03Sevilla 22.03.2007Sevilla 22.03.2007

Page 2: Narva city development overview Sofja Homjakova Vice-Mayor of Narva, ESTONIA Contribution to Estonian presentation, Session C03 Sevilla 22.03.2007

General data

The city of Narva is located in North-Eastern Estonia at the border with Russia, at the distance of 212 km to the East from Tallinn and 150 km to the West from Saint-Petersburg.

Since 2004 Narva is the European Union border city.

The city lies on the left bank of the river Narva, 14 km away from the place of its flow into the Gulf of Finland, where a resort town Narva-Jõesuu is located.

Narva is the 3rd biggest city in Estonia. Its population (as of 2006) is 69 000 people, among them 47 000 are of labour age.

Page 3: Narva city development overview Sofja Homjakova Vice-Mayor of Narva, ESTONIA Contribution to Estonian presentation, Session C03 Sevilla 22.03.2007

The city of Narva – what is it?• Narva is a city on the Eastern border of Estonia, which has

two histories: (1) today’s Narva, with architecture and culture originating from the Soviet times and (2) baroque-style Old Narva, which perished in the World War II.

• Narva as an industrial city: in 1950-s Narva started to develop as an industrial and power engineering centre by rapid restoration of the Krenholm Manufacture, construction of huge plants, a hydro electric power station and two thermal electric power stations.

• Narva as a city of multiple ethnical groups and cultures.

• Narva as a tourism centre!

Page 4: Narva city development overview Sofja Homjakova Vice-Mayor of Narva, ESTONIA Contribution to Estonian presentation, Session C03 Sevilla 22.03.2007

In what situation are we today?• Continuing growth of investments into the city and the

region • Rapid development of trading centres• Removal of industrial enterprises from the city centre

into suburbs• Beginning of powerful development of dwelling sector• City authorities’ purposive work on creation of more

citizen-friendly and comfortable city environment

Page 5: Narva city development overview Sofja Homjakova Vice-Mayor of Narva, ESTONIA Contribution to Estonian presentation, Session C03 Sevilla 22.03.2007

Where are we going and what will the future bring to us?

• Big projects, which are going to change the outward appearance of the city: new traffic schemes, recreation zones, entertainment facilities, dwelling houses, etc.

• General plannings:(1) Old Town, (2) industry

Page 6: Narva city development overview Sofja Homjakova Vice-Mayor of Narva, ESTONIA Contribution to Estonian presentation, Session C03 Sevilla 22.03.2007

Projects aimed at development of fortifications as tourist products• Bastions route • Opening of the Narva Castle Northern Yard for tourists• EstRusFortTour • Compilation of Narva bastions development concept• Integrated development of the historical riverside protection area in Narva/Estonia and Ivangorod/Russia

Page 7: Narva city development overview Sofja Homjakova Vice-Mayor of Narva, ESTONIA Contribution to Estonian presentation, Session C03 Sevilla 22.03.2007

Bastions routeProject duration: January 2005- May 2006

Project budget: 5,6 mln Estonian kroons

Finance sources: 85%- Phare ESC 2003 Tourism Infrastructure Development Programme in Estonia, 15%- Narva City Government

Project main activities: • Investments into the infrastructure of the tourist

product “Bastions route” including construction of a drainage system at Victoria, Honor, Gloria bastions;

• Construction of illumination at Spes, Pax and Victoria bastions;

• Water and sewage system construction in the front yard of the Art Gallery for outdoor café erection;

• Installation of information board and stones at the bastions.

Page 8: Narva city development overview Sofja Homjakova Vice-Mayor of Narva, ESTONIA Contribution to Estonian presentation, Session C03 Sevilla 22.03.2007

Bastions route

Page 9: Narva city development overview Sofja Homjakova Vice-Mayor of Narva, ESTONIA Contribution to Estonian presentation, Session C03 Sevilla 22.03.2007

Opening of the Narva Castle Northern Yard for tourists

Project duration: 2005-2006Project budget: 11,7 mln Estonian kroonsFinance sources: 80%- Regional

Competitiveness Improvement Programme, 20%- Narva City Government

Project content: • New medieval interactive tourist product

“Northern Yard – handicraftsmen’s yard of Swedish period” along with traditional image events was developed and adjusted for functioning in the Narva Castle Northern Yard.

• Product development programme was developed as support measure for implementation in public private partnership.

Page 10: Narva city development overview Sofja Homjakova Vice-Mayor of Narva, ESTONIA Contribution to Estonian presentation, Session C03 Sevilla 22.03.2007

EstRusFortTour -"Unique Estonian-Russian fortresses ensemble development as a

single tourist product and conservation of cultural and historical heritage “, INTERREG III

A

Project duration: 01.07.2006-30.06.2008Project budget: 4 811 392 Estonian kroonsNarva City Government self-financing: 477 221 Estonian kroons, incl. Estonian Ministry of the Interior co-financing 176 135 Estonian kroons.Partners: Narva City, Ivangorodi City, Ivangorod Centre of Sustainable Development, Leningrad oblast Committee for Physical Culture, Sports, Tourism and Youth Policy, Leningrad oblast Museum Agency

Page 11: Narva city development overview Sofja Homjakova Vice-Mayor of Narva, ESTONIA Contribution to Estonian presentation, Session C03 Sevilla 22.03.2007

EstRusFortTour

Project outputs:• Narva and Ivangorod single tourist route around fortresses

developed• Network of tourist companies suggesting the tourist product

created• Tourist product PR (schemes, booklets, CD, web-site,

interactive game, articles in tourist magazines, familiarization tours, participation in tourist fairs)

• Documentary and archive studies for preparation of documentation of the unique ensemble of fortresses to UNESCO;

• Preservation plan of fortresses and development programme for conservation of cultural and historical heritage developed

Page 12: Narva city development overview Sofja Homjakova Vice-Mayor of Narva, ESTONIA Contribution to Estonian presentation, Session C03 Sevilla 22.03.2007

Project “Compilation of Narva bastions development concept”

Project duration: 01.07.2006 – 01.09.2007Project budget: 774 734 krooniProgramme for Planning Regional Development: 500 000

Estonian kroonsNarva City Government self-financing: 274 734 Estonian

kroonsProject activities:• Compilation of expert assessment of Viktoria, Honor and

Gloria bastions technical state• Bastions as attraction for tourists development programme

and compilation of feasibility study analysis

Page 13: Narva city development overview Sofja Homjakova Vice-Mayor of Narva, ESTONIA Contribution to Estonian presentation, Session C03 Sevilla 22.03.2007

Integrated development of the historical riverside protection area in Narva/Estonia and Ivangorod/Russia,

Interreg IIIA/Tacis programm

Project duration: 01.07.2007 – 30.06.2009Project budget: 4 700 000 Estonian kroonsNarva City Government self-financing: 235 000 Estonian kroonsPartners: Narva City and Ivangorod CityProject activities:1.Technical study including heritage protection, geological, geodesy, ecological and hydrological studies.2. Economical study including marketing studies, marketing plan compilation, recoupment analysis, practicability analysis and technical design project development.3. Study visit to an EU country4. Seminar for project partners and beneficiaries

Page 14: Narva city development overview Sofja Homjakova Vice-Mayor of Narva, ESTONIA Contribution to Estonian presentation, Session C03 Sevilla 22.03.2007

Development of the Narva river port infrastructure

Suggestions for investors in connection with the development of the riverside area

Page 15: Narva city development overview Sofja Homjakova Vice-Mayor of Narva, ESTONIA Contribution to Estonian presentation, Session C03 Sevilla 22.03.2007

• Compilation of the Narva Town Hall development vision and plan of activities• Narva Town Hall energy-saving project• Renovation of the Narva Town Hall facade• Elaboration of the “Mini Old Narva” tourist product development programme

Projects aimed at development of Narva Old Town

Page 16: Narva city development overview Sofja Homjakova Vice-Mayor of Narva, ESTONIA Contribution to Estonian presentation, Session C03 Sevilla 22.03.2007

Renovation of the Narva Town Hall facade (preparation stage)

Project duration: 2007-2008Project budget: ca. 2 000 000 Estonian kroonsProgramme for Small Projects for Developing Regional Competitiveness: 1 000 000 Estonian kroonsNarva City Government co-finance: 1 000 000 Estonian kroons

Project activities: • Facade renovation (walls, socle)• Construction of rainwater drain system

Page 17: Narva city development overview Sofja Homjakova Vice-Mayor of Narva, ESTONIA Contribution to Estonian presentation, Session C03 Sevilla 22.03.2007

Restaurant in old style

Possibilities of the Town Hall cellar use

Page 18: Narva city development overview Sofja Homjakova Vice-Mayor of Narva, ESTONIA Contribution to Estonian presentation, Session C03 Sevilla 22.03.2007

Workshops, workrooms

Possibilities of the Town Hall cellar use

Page 19: Narva city development overview Sofja Homjakova Vice-Mayor of Narva, ESTONIA Contribution to Estonian presentation, Session C03 Sevilla 22.03.2007

Souvenir and fancy-work shop

Possibilities of the Town Hall cellar use

Page 20: Narva city development overview Sofja Homjakova Vice-Mayor of Narva, ESTONIA Contribution to Estonian presentation, Session C03 Sevilla 22.03.2007

Shops (spices or nature products shop)

Possibilities of the Town Hall cellar use

Page 21: Narva city development overview Sofja Homjakova Vice-Mayor of Narva, ESTONIA Contribution to Estonian presentation, Session C03 Sevilla 22.03.2007

Handicraftsmen market at the Town Hall square

Possibilities of the Town Hall square use

Page 22: Narva city development overview Sofja Homjakova Vice-Mayor of Narva, ESTONIA Contribution to Estonian presentation, Session C03 Sevilla 22.03.2007

Elaboration of the “Mini Old Narva” tourist product development

programme (preparation stage)

Project duration: 2007-2008Project budget: about 700 000 Estonian kroonsProgramme for Planning Regional Development: 500 000 Estonian kroonsNarva City Government co-finance: 200 000 Estonian kroonsThe tourist product „Mini Old Narva” is a replica of the old town in miniature and maquette in the open air. Similar mini towns are created in Holland, England, Germany, Italy. About 15 mini towns from all over the world are members of the International Mini-parks Association. In Estonia there is no tourist product of this kind.Project activities: • Archive studies and questionnaires • Tourist product “Mini Old Narva” • Elaboration programme (incl. marketresearch), • Development plan, feasibility study, • Marketing plan.

Page 23: Narva city development overview Sofja Homjakova Vice-Mayor of Narva, ESTONIA Contribution to Estonian presentation, Session C03 Sevilla 22.03.2007

• Development of Joaoru beach• Narva River Water Routes• Chess Park• Preliminary works for construction of Äkkeküla and health path in Narva• Narva skate- park construction

Projects aimed at development of city physical living environment

Page 24: Narva city development overview Sofja Homjakova Vice-Mayor of Narva, ESTONIA Contribution to Estonian presentation, Session C03 Sevilla 22.03.2007

Development of Joaoru beach (preparation stage)

Project budget : 1 200 000 Estonian kroonsNarva City Government co-finance: 300 000 Estonian kroons

Project activities:Purchase of beach equipment for Joaoru beach (benches, changing cabins, bio toilets, equipment for sports grounds and children playgrounds, waste containers, catamarans, safety equipment)• Installation of equipment

Page 25: Narva city development overview Sofja Homjakova Vice-Mayor of Narva, ESTONIA Contribution to Estonian presentation, Session C03 Sevilla 22.03.2007

Narva River Water Routes, INTERREG III A

Project duration: 01.07.2006-30.06.2008Project budget: 6 167 727 Estonian kroonsNarva City Government self-financing: 639 042 Estonian

kroons, out of which 233 993 Estonian kroons covers the Estonian Ministry of the Interior co-financing

Partners: Narva City, Ivangorod City, Kingisepp Region, Ivangorod Centre of Sustainable Development

Project outputs:• Water tourist routes Narva – Narva-Jõesuu, Ivangorod –

Rosson – Luuga developed• Navigation and environmental impact studies in connection

with development of water tourism carried out• Feasibility study for creation a yacht marina on the Rosson

River implemented • Navigation projects for water tourist routes developed• Small ports infrastructure in Narva and the Rosson River

improved • Promotion of the tourist product (route schemes, brochures,

website, articles in tourist magazines)

Page 26: Narva city development overview Sofja Homjakova Vice-Mayor of Narva, ESTONIA Contribution to Estonian presentation, Session C03 Sevilla 22.03.2007

Preliminary works for creation of health path along the Narva River

Project duration: 14.06.2005-31.08.2006Project budget: 1 321 901 Estonian kroonsPhare EBI: 982 277 Estonian kroonsNarva City Government self-financing: 169 812

Estonian kroonsVaivara Borough co-finance: 84 906 Estonian kroons Narva-Jõesuu City co-finance: 84 906 Estonian kroons

Project outputs:• Feasibility study for the health path creation carried

out; path route defined, preliminary construction cost estimated; environmental study implemented.

• Design work implemented; all necessary approvals implemented.

Page 27: Narva city development overview Sofja Homjakova Vice-Mayor of Narva, ESTONIA Contribution to Estonian presentation, Session C03 Sevilla 22.03.2007

Preliminary works for Äkkeküla and health path construction in Narva (submitted)

Project duration: 01.07.2007 – 30.08.2009Project budget: 11 762 018 Estonian kroonsNorwegian and EEA Financial Mechanisms: 9 917 707

Estonian kroonsNarva City Government self-financing: 1 764 311 Estonian

kroons (out of which 100 000 Estonian kroons are in-kind contribution)

Partners’ co-financing, total: 80 000 Estonian kroons (in-kind). Project partners: Narva-Jõesuu Municipality, Vaivara Borough

Municipality, Midtre Gauldal Commune (Norway).Project activities:• Feasibility study of the Akkeküla sports centre implementation• Study visit to Norway winter sports centre• Development of the Äkkeküla sports centre construction project• Development of the health path project between Narva and

Narva-Jõesuu• Project application for construction of the Äkkeküla sports centre• Project application for the construction of the health path

between Narva and Narva-Jõesuu

Page 28: Narva city development overview Sofja Homjakova Vice-Mayor of Narva, ESTONIA Contribution to Estonian presentation, Session C03 Sevilla 22.03.2007

Construction of the Äkkeküla sports centre

Page 29: Narva city development overview Sofja Homjakova Vice-Mayor of Narva, ESTONIA Contribution to Estonian presentation, Session C03 Sevilla 22.03.2007

Narva skate-park construction

Project budget: 300 832 Estonian kroonsInvestments from the Gambling Tax Fund:

240 665 Estonian kroonsNarva City Government self-financing: 60 167

Estonian kroonsThe project envisages the construction of 600

square meters for the skate-park in the Pähklimäe part of Narva (Pähklimäe 3a).

Project activities:• Asphalt-concrete surface laying (implemented with the city self-financing)• skate-park construction

Page 30: Narva city development overview Sofja Homjakova Vice-Mayor of Narva, ESTONIA Contribution to Estonian presentation, Session C03 Sevilla 22.03.2007