61
Choose a building block. MOE FLS Reference Designs for 15 August 2016 Standard Classroom Upgrade - Revision: 0 Nelson Two Storey Block (Concrete Reference: 246313 Stairs) Structural Specification Ministry of Education

MOE FLS Reference Designs for 15 August 2016 Standard ... · PDF file4.9 Concrete Tests 22 . ... This Section of the Specification shall be read in conjunction with all other Sections

  • Upload
    hatuong

  • View
    214

  • Download
    2

Embed Size (px)

Citation preview

  • Choose a building block.

    MOE FLS Reference Designs for 15 August 2016

    Standard Classroom Upgrade Revision: 0

    Nelson Two Storey Block (Concrete Reference: 246313

    Stairs)

    Structural Specification

    Ministry of Education

    Jagnesh.MakwanaRectangle

  • Document control record

    Document prepared by:

    Aurecon New Zealand Limited

    Level 8, 42-52 Willis Street Wellington 6011

    PO Box 1591 Wellington 6140 New Zealand

    T +64 4 472 9589

    F +64 4 472 9922

    E [email protected]

    W aurecongroup.com

    A person using Aurecon documents or data accepts the risk of:

    a) Using the documents or data in electronic form without requesting and checking them for accuracy against the original hard copy version.

    b) Using the documents or data for any purpose not agreed to in writing by Aurecon.

    Document control

    Report title Structural Specification

    Document ID Project number 246313

    File path P:\246313\03 Project Delivery\Design\Nelson Block\Nelson Two Storey Block (Concrete Stairs) - FLS Upgrade Structural Specification - Rev 0.docx

    Client Ministry of Education Client contact

    Rev Date Revision details/status Prepared by

    Author Verifier Approver

    0 15 August 2016 Issue to Client JBM JBM LP JF

    Current revision 0

    Approval

    Author signature Approver signature

    Name Jagnesh Makwana Name John Finnegan

    Title Structural Engineer Title Technical Director

    Jagnesh.MakwanaImage

    Jagnesh.MakwanaImage

  • MOE FLS Reference Designs for Standard Classroom Upgrade -Nelson Two Storey Block (Concrete Stairs)

    Date 15 August 2016 Reference 246313 Revision 0

    Aurecon New Zealand Limited

    Level 8, 42-52 Willis Street Wellington 6011

    PO Box 1591 Wellington 6140 New Zealand

    T +64 4 472 9589 F +64 4 472 9922 E [email protected] W aurecongroup.com

    Project 246313 File Nelson Two Storey Block (Concrete Stairs) - FLS Upgrade Structural Specification - Rev 0.docx 15

    August 2016 Revision 0

    http:aurecongroup.commailto:[email protected]

  • Contents Ministry of Education 1

    1 Demolition 1

    1.1 Preliminary 1

    1.2 Scope 1

    1.3 Related Documents 1

    1.4 Safety 1

    1.5 Site Inspection Assessment 1

    1.6 Demolition Contractor 1

    1.7 Demolition Plan 2

    1.8 Compliance 2

    1.9 Existing Services 2

    1.10 Dust and Noise 2

    1.11 Protection of Adjacent Sites 2

    1.12 Explosives 3

    1.13 Foundations 3

    1.14 Removal of Support 3

    1.15 Separation from Existing Buildings 3

    1.16 Levelling the Site 3

    1.17 Fence the Site 3

    1.18 Salvage Materials 3

    1.19 Control of Debris 3

    1.20 Materials to be Carted Away 3

    1.21 Loading and Off-Loading Materials 4

    2 Excavation and Sitework 5

    2.1 Preliminary 5

    2.2 Scope 5

    2.3 Related Documents 5

    2.4 Safety 5

    2.5 Site Inspection Assessment 5

    2.6 Levels 5

    2.7 Setting Out 6

    2.8 Existing Services 6

    2.9 Dust and Noise 6

    2.10 Protection of Adjacent Sites 6

    2.11 Explosives 6

    2.12 Geotechnical Investigation 6

    2.13 Methods of Excavation 7

    Project 246313 File Nelson Two Storey Block (Concrete Stairs) - FLS Upgrade Structural Specification - Rev 0.docx 15

    August 2016 Revision 0 Page i

  • 2.14 Surplus Material 7

    2.15 Existing Soft Spots and Previously Filled Areas 7

    2.16 Excavations Too Deep 7

    2.17 Maintain Excavations 7

    2.18 Excavation for Services 7

    2.19 Dewatering 7

    2.20 Compaction 8

    2.21 Notice to Engineer 8

    2.22 Inspection 8

    2.23 Site Concrete 8

    2.24 Backfilling 8

    2.25 Hardfill 9

    2.26 Granular Hardfill Base for Capillary Break to Underside of Slabs on Grade 9

    2.27 Verification Testing 9

    2.28 Sand Blinding Beneath DPC 9

    2.29 Other Trades 9

    2.30 Hazardous and Contaminated Materials 9

    2.31 Drainage Material behind Retaining Walls 10

    3 Reinforcing Steel 11

    3.1 Preliminary 11

    3.2 Scope 11

    3.3 Related Documents 11

    3.4 Safety 11

    3.5 Quality Assurance 11

    3.6 Inspection 12

    3.7 Supervision 12

    3.8 Testing 12

    3.9 Producer Statements 12

    3.10 Materials and Workmanship 12

    3.11 Reinforcing Steel 12

    3.12 Galvanising of Bars 13

    3.13 Bending of Bars 13

    3.14 Bending of Galvanised Bars 13

    3.15 Bending Schedules 13

    3.16 Bend Diameters 14

    3.17 Bar Numbering 14

    3.18 Abbreviations 14

    3.19 Cover 15

    3.20 Tolerances 15

    3.21 Laps in Concrete 15

    Project 246313 File Nelson Two Storey Block (Concrete Stairs) - FLS Upgrade Structural Specification - Rev 0.docx 15

    August 2016 Revision 0 Page ii

  • 3.22 Splicing of Bars 16

    3.23 Fixing of Reinforcing Steel 16

    3.24 Concrete Slab Reinforcement 17

    3.25 Cleaning Steel 17

    3.26 Welding of Bars 17

    3.27 Welding Certificates 17

    3.28 Qualification of Welding Procedures and Personnel 18

    3.29 Welding Inspection and Testing 18

    3.30 Repair of Welding Defects 18

    4 Concrete 19

    4.1 Preliminary 19

    4.2 Scope 19

    4.3 Related Documents 19

    4.4 Safety 20

    4.5 Quality Assurance 20

    4.6 Erection and Temporary Works 21

    4.7 Inspection 21

    4.8 Producer Statement 22

    4.9 Concrete Tests 22

    4.10 Materials and Workmanship 22

    4.11 Concrete 22

    4.12 Reinforcement 23

    4.13 Formwork 23

    4.14 Concreting 24

    4.15 Vibrators 24

    4.16 Curing and Protection 24

    4.17 Tolerances 24

    4.18 Concrete Finishes 25

    4.19 Slab Finishes 25

    4.20 Formed Surfaces 25

    4.21 Schedule of Finishes 26

    4.22 Protection 26

    4.23 Repairs and Cleaning 26

    4.24 Structural Steelwork 26

    4.25 Dampcourse Membrane 27

    4.26 Foundations 27

    4.27 Epoxy Grouting of Reinforcing Bars 27

    4.28 Repair of Concrete 28

    4.29 Concrete Repair using Concrete or Drypack 29

    4.30 Concrete Repair using Epoxy Resin 29

    Project 246313 File Nelson Two Storey Block (Concrete Stairs) - FLS Upgrade Structural Specification - Rev 0.docx 15 August 2016 Revision 0 Page iii

  • 5 31Structural Steelwork

    5.1 Preliminary 31

    5.2 Scope 31

    5.3 Related Documents 31

    5.4 Safety 32

    5.5 Quality Assurance 32

    5.6 Drawings 33

    5.7 Shop Drawings 33

    5.8 Welding Certificates 34

    5.9 Producer Statements 34

    5.10 Rejection 34

    5.11 Inspection and Testing 34

    5.12 Materials 34

    5.13 Steel 35

    5.14 Alternative Sections 35

    5.15 Bolts 35

    5.16 Welding Consumables 36

    5.17 Fabrication 36

    5.18 Verification of Dimensions 37

    5.19 Cutting 37

    5.20 Repair of Cutting Defects 37

    5.21 Welding 37

    5.22 Qualification of Welding Procedures and Personnel 38

    5.23 Welding Inspection and Testing 38

    5.24 Repair of Welding Defects 39

    5.25 Holing 39

    5.26 Bolting 39

    5.27 Splices 40

    5.28 Bending 40

    5.29 Cold Bending of Plates and Flats 40

    5.30 Erection 41

    5.31 Storage, Handling and Delivery 41

    5.32 Assembly 41

    5.33 Seatings 42

    5.34 Temporary Bracing 42

    5.35 Existing Structure 42

    5.36 Re-tensioning of Bolts 42

    5.37 Erection Tolerances 42

    5.38 Holding Down Bolts 43

    5.39 Proprietary Fasteners 43

    Project 246313 File Nelson Two Storey Block (Concrete Stairs) - FLS Upgrade Structural Specification - Rev 0.docx 15 August 2016 Revision 0 Page iv

  • 5.40 Flowable Grout 43

    5.41 Drypack 43

    5.42 Corrosion Protection 43

    5.43 Galvanising 44

    5.44 Thermal Sprayed Metal Coatings 44

    5.45 Painting 45

    5.46 Painting Inspection 47

    6 Structural Timber 48

    6.1 Preliminary 48

    6.2 Scope 48

    6.3 Related Documents 48

    6.4 Safety 48

    6.5 Quality Assurance 49

    6.6 Producer Statements 49

    6.7 Timber 49

    6.8 Moisture Content 49

    6.9 Treatment 50

    6.10 Metalwork 50

    6.11 Bolts 50

    6.12 Screws and Nails 50

    6.13 Fixings to Bottom Plates 50

    6.14 Workmanship 50

    6.15 Protection 51

    6.16 Framing 51

    6.17 Damp Proofing 51

    6.18 Erection 51

    6.19 Proprietary Beam and Joist Assemblies 52

    6.20 Proprietary Sheet Bracing Systems 52

    Project 246313 File Nelson Two Storey Block (Concrete Stairs) - FLS Upgrade Structural Specification - Rev 0.docx 15 August 2016 Revision 0 Page v

  • 1 Demolition 1.1 Preliminary

    Refer to the Preliminary and General Clauses of this Specification and to the General Conditions of

    Contract, which are equally binding on all Trades. This Section of the Specification shall be read in

    conjunction with all other Sections as the requirements are interrelated.

    1.2 Scope

    This Section is for the demolition of the buildings on the site, including foundations and the removal

    and disposal of all demolished material and disturbed ground. It includes the provision of all

    precautionary safety measures, screens, scaffoldings, hoarding, covered walkways and the like for

    carrying out the demolition work.

    1.3 Related Documents

    In this Section of the Specification, reference is made to the latest revisions of the following

    documents:

    Health and Safety in Employment Act 1992 Approved Code of Practice for Demolition The New Zealand Buil