Click here to load reader
View
215
Download
0
Embed Size (px)
PROJECT MANAGEMENT HANDBOOK, PART 2 - PHASE SPECIFIC PROJECT MANAGEMENT ISSUES
Page 1 of 14 CHAPTER 5 CONSTRUCTION PROJECT MANAGEMENT________________________ Revised 03/02/2016
CHAPTER 5 - Construction Project Management
Contents Introduction ........................................................................................................... 2
Construction Contract Management ..................................................................... 2
CEI Contracts........................................................................................................ 3
Community Awareness Plan ................................................................................. 7
Alternative Contracting Methods ........................................................................... 8
Warranty Specifications ...................................................................................... 10
Plan Revisions .................................................................................................... 10
Permits and Other Commitments ........................................................................ 11
Alternate Designs ................................................................................................ 11
Coordination with the Engineer of Record .......................................................... 11
Construction Quality Control Testing .................................................................. 12
Coordination with the District Maintenance Office............................................... 13
Project Closeout.................................................................................................. 14
PROJECT MANAGEMENT HANDBOOK, PART 2 - PHASE SPECIFIC PROJECT MANAGEMENT ISSUES
Page 2 of 14 CHAPTER 5 CONSTRUCTION PROJECT MANAGEMENT________________________ Revised 03/02/2016
Introduction
The term Project Manager (PM) is a general term used throughout this chapter for the Florida
Department of Transportation (FDOT) employee responsible for managing a construction project.
Unless specifically indicated otherwise, PM refers to the FDOT Construction PM.
This chapter deals with project management from the perspective of the FDOT PM and
consultant Construction Engineering and Inspection (CEI) PM. Whether FDOT or consultant, the
PM must concentrate on the four goals of a successful project:
Fulfill project objectives
Complete the project within the time specified
Complete the project within the allocated funds
Complete the project to the level of quality specified by the contract documents
Of these goals, the one that lingers longest after job completion is the quality of construction, and
it should not be sacrificed for the sake of the other three.
Perhaps more so than for any other project phase, fiscal responsibility must have a high priority
on a construction project. PMs are responsible for very large expenditures of state and federal
money. Projects must be managed properly in every respect. Accurate and complete
documentation is imperative.
Construction Contract Management The PM manages construction contracts either directly or through a CEI consultant, who has
responsibility to manage the construction contract on behalf of the FDOT. The PM may be
responsible for more than one construction project. Following trends in other areas, the FDOT
now out-sources management of many of its construction contracts; however, it still manages a
select few with its own in-house staff. The FDOT competitively selects consultant firms to provide
CEI services on a specific construction project or group of construction projects. The CEI
consultant furnishes a team of engineers and inspectors fully qualified for and certified in all areas
related to their responsibilities, including sampling, testing and inspection. A Senior Project
Engineer oversees the CEI team effort and is responsible for coordination and monitoring
contract progress. The Senior Project Engineer may oversee more than one construction project.
PROJECT MANAGEMENT HANDBOOK, PART 2 - PHASE SPECIFIC PROJECT MANAGEMENT ISSUES
Page 3 of 14 CHAPTER 5 CONSTRUCTION PROJECT MANAGEMENT________________________ Revised 03/02/2016
It is important for both the Senior Project
Engineer and the PM to remember that the
contractor is ultimately in charge of the
construction effort. The contractor is obligated to
provide the means, methods, and resources
such as labor, equipment, materials and sub-
contract services and to complete the job as
specified in the contract documents. It is very
important to establish a positive working
relationship through a Partnering Program or
similar means at the very outset of the job. For
additional information on partnering, refer to the
Partnering Facilitators Manual.
Communications, trust, documentation and
coordination are just a few of the key ingredients
that go into managing a successful project, as
shown in Figure 1, Elements in Managing a Successful Project. Both the PM and the CEI
must work together to provide them.
There are many guidelines and manuals describing the relationships of the FDOT, CEI, and the
contractor. These relationships will differ slightly from job to job. Both the Senior Project
Engineer and the PM must be very familiar with all contract documents. Reading and
understanding them is essential. Two additional documents that must be thoroughly understood
are the FDOT Standard Specifications for Road and Bridge Construction, and Procedure
No. 700-000-000, Construction Project Administration Manual (CPAM). The FDOT
Specifications establish the relationship between the FDOT and the contractor. The CPAM
describes the relationship between the FDOT and the CEI firm; it also describes the CEI
management scope and procedures required on the job.
CEI Contracts A construction project normally has three entities working together to achieve the project
objectives of timely completion, within budget, and a quality product: the FDOT, the CEI and the
contractor. The roles and responsibilities of each must be clearly defined and understood. For a
project to run smoothly there must be clear leadership and coordination, without redundancy.
http://www.dot.state.fl.us/construction/ContractorIssues/Partnering/PartneringManual.pdfhttp://www.dot.state.fl.us/specificationsoffice/http://www.dot.state.fl.us/construction/Manuals/ManualsMain.shtm
PROJECT MANAGEMENT HANDBOOK, PART 2 - PHASE SPECIFIC PROJECT MANAGEMENT ISSUES
Page 4 of 14 CHAPTER 5 CONSTRUCTION PROJECT MANAGEMENT________________________ Revised 03/02/2016
The PM should concentrate on the performance of the CEI firm and its daily operations. The PM
should be personally involved in the selection process, defining the type and number of personnel
needed, qualifications required and other important selection criteria. The PM should see that the
selected CEI team is brought on board at the appropriate time and is fully familiar with the
requirements of the contract and the scope of services to be provided. The CPAM describes CEI
responsibilities in detail. In addition to monitoring CEI performance, the PM reviews invoices and
results of sampling and verification testing. It is particularly important that the PM track the
schedule and costs of the CEI and that the CEI track those of the construction contracts. The PM
should coordinate other FDOT resources that may be required and key decisions that may be
needed. The PM is the primary resource for decisions outside the CEI Scope. The CEI does not
have the authority over R/W or Utility conflict issues.
Both the CPAM and the CEI contract scope of services clearly define the responsibilities of the
Senior Project Engineer. The Senior Project Engineer is to be totally involved with the
construction contractor on a day-to-day basis, from pre-construction activities through project
completion and final acceptance. The Senior Project Engineer must monitor and document the
contractors activities.
Scheduling the CEI Contract. The appropriate time to bring the CEI on board will vary
according to the type of construction contract, i.e. design-build, unit price, lump sum, etc. The PM
should decide the appropriate level of involvement in any pre-letting activities such as plans
review and comments, determining contract duration and recommending appropriate alternative
contracting techniques. There are many good reasons to involve the CEI firm early in the
process. The CEI firms input in the early stages of a project can result in a more constructible
project and thus lower construction cost.
The Work Program establishes the bid-letting date well in advance. Following this date, the
contract is generally awarded within 20 days. The contractor executes the contract documents
within 10 days following award of the contract. Once the contractor returns the contract
documents, the FDOT has 5 days to execute them. The construction contractors Notice to
Proceed (NTP) is generally issued within 20 days following contract execution by both parties.
"...CEI firms shall be allowed to exercise their independent professional judgement...The role of the D