112
Contractor No. of Correction Executive Engineer MAHARASHTRA JEEVAN PRADHIKARAN MAHARASHTRA JEEVAN PRADHIKARAN WATER MANAGEMENT CIRCLE, NEW PANVEL MAHARASHTRA JEEVAN PRADHIKARAN WATER MANAGEMENT DIVISION, VIRAR Name of Work : Vasai-Virar Sub-Regional Water Supply Scheme (Surya) stage-II Part-I. Designing, Providing and constructing RCC ESR of capacity 1.25 ML @ Tulinj, Nallasopara (E). INDEX Sr. No. Description Page No. From To 1. Short Tender Notice 01 - 02 2. Check List - 03 - 3. Detailed Tender Notice 04 - 09 4. Form B-1 10 - 51 5. Material Schedule A - 52 - 6. Obligatory Technical condition 53 - 57 7. General Specification 58 - 68 8. Additional Condition of Contract 69 - 70 9. Work and Site Condition 71 - 72 10. Detailed Itemwise Specification 73 - 117 11. Declaration - 118 - 12. Undertaking for Guarantee - 119 -

MAHARASHTRA JEEVAN PRADHIKARANmjp.maharashtra.etenders.in/tpoimages/mjp/tender/Tender...Maharashtra Jeevan Pradhikaran, such specifications with designs and drawings shall form a part

  • Upload
    others

  • View
    6

  • Download
    0

Embed Size (px)

Citation preview

Page 1: MAHARASHTRA JEEVAN PRADHIKARANmjp.maharashtra.etenders.in/tpoimages/mjp/tender/Tender...Maharashtra Jeevan Pradhikaran, such specifications with designs and drawings shall form a part

Contractor No. of Correction Executive Engineer

MAHARASHTRA JEEVAN PRADHIKARAN MAHARASHTRA JEEVAN PRADHIKARAN WATER MANAGEMENT CIRCLE, NEW PANVEL

MAHARASHTRA JEEVAN PRADHIKARAN WATER MANAGEMENT DIVISION, VIRAR

Name of Work : Vasai-Virar Sub-Regional Water Supply Scheme

(Surya) stage-II Part-I.

Designing, Providing and constructing RCC ESR of

capacity 1.25 ML @ Tulinj, Nallasopara (E).

INDEX

Sr.

No. Description

Page No.

From To

1. Short Tender Notice 01 - 02

2. Check List - 03 -

3. Detailed Tender Notice 04 - 09

4. Form B-1 10 - 51

5. Material Schedule – A - 52 -

6. Obligatory Technical condition 53 - 57

7. General Specification 58 - 68

8. Additional Condition of Contract 69 - 70

9. Work and Site Condition 71 - 72

10. Detailed Itemwise Specification 73 - 117

11. Declaration - 118 -

12. Undertaking for Guarantee - 119 -

Page 2: MAHARASHTRA JEEVAN PRADHIKARANmjp.maharashtra.etenders.in/tpoimages/mjp/tender/Tender...Maharashtra Jeevan Pradhikaran, such specifications with designs and drawings shall form a part

Contractor No. of Correction Executive Engineer

MAHARASHTRA JEEVAN PRADHIKARAN

MAHARASHTRA JEEVAN PRADHIKARAN WATER MANAGEMENT CIRCLE, NEW PANVEL MAHARASHTRA JEEVAN PRADHIKARAN WATER MANAGEMENT DIVISION, VIRAR

Name of Work : Vasai-Virar Sub-Regional Water Supply Scheme

(Surya) stage-II Part-I.

Designing, Providing and constructing RCC ESR of

capacity 1.25 ML @ Tulinj, Nallasopara (E).

CHECK LIST

All required documents, forms, statements, specifications, conditions, schedules drawings

etc. are to be submitted with the tender.

The document shall contain the following particularly without which the tender may not

be finally decided.

1) Fixed Deposit Receipt valid upto a period not earlier than six months from

submission of tender of any Scheduled / Nationalised Bank, towards payment of

Earnest Money drawn in favour of Executive Engineer, Maharashtra Jeevan

Pradhikaran Water Management Division, Virar.

2) Copy of valid registration in MJP in Class V and above in Civil.

3) Brief details of the works of similar type and magnitude, carried out by the

tenderer.

4) Details of other works tendered for and the work in hand along with the value of

work remaining unfinished as on the date of submission of this tender.

5) Details of plant and machinery proposed to be immediately made available and

the manner in which it is proposed to be procured.

6) Details of technical personnel with tenderer.

7) Copies of certificate regarding registration with sales tax department.

8) Copy of VAT registration certificate.

9) Full name of all partners of the tenderer if offered by partnership deed and power

of attorney.

10) The Tenderer should sign on B-1 form at the appropriate place and mention his

address on B-1 form at appropriate place. Without which his offer will be treated

as non responsive and the offer shall not be read out by the tender opening

authority.

Contractor Executive Engineer

M.J.P. Water Management Div., Virar

Page 3: MAHARASHTRA JEEVAN PRADHIKARANmjp.maharashtra.etenders.in/tpoimages/mjp/tender/Tender...Maharashtra Jeevan Pradhikaran, such specifications with designs and drawings shall form a part

Contractor No. of Correction Executive Engineer

FORM B-1

MAHARASHTRA JEEVAN PRADHIKARAN

--------------------------------------------------------------

Percentage Rate Tender and Contract for work

---------------------------------------------------------------

DEPARTMENT : MAHARASHTRA JEEVAN PRADHIKARAN

CIRCLE : MAHARASHTRA JEEVAN PRADHIKARAN W.M.

CIRCLE, PANVEL

DIVISION : MAHARASHTRA JEEVAN PRADHIKARAN W.M. DIV.

VIRAR

GENERAL RULES AND DIRECTIONS FOR THE GUIDANCE OF

CONTRACTORS

1. All works, proposed to be executed by contract, shall be notified in a form of

invitation to tender, pasted on a notice board hung up in the office of the

Executive Engineer and signed by the Executive Engineer.

This form will state the work to be carried out as well as the date for submitting

and opening tenders, and the time allowed for carrying out the work, also the

amount of earnest money to be deposited with the tender, and the amount of the

security deposit to be deposited by the successful tenderer and the percentage, if

any, to be deducted from bills. It will also state whether refund or quarry fees,

royalties and ground rents will be granted. Copies of any other documents

required in the connection with the work shall be signed by the Executive

Engineer for the purpose of identification and shall also be open for inspection by

contractors at the office of the Executive Engineer during office hours.

Where the works are proposed to be executed according to the specifications

recommended to a contractor and approved by a competent authority on behalf of

Maharashtra Jeevan Pradhikaran, such specifications with designs and drawings

shall form a part of the accepted tender.

2. In the event of the tender, being submitted by a firm, it must be signed by partner

thereof, and in the event of the absence of any partner, it shall be signed on his

behalf by a person holding a power-of-attorney authorizing him to do so.

2(A) i) The Contractor shall pay along with the tender the sum of Rs.1,16,15,612/-

(Rupees One Crore Sixteen Lac Fifteen Thousand Six Hundred Twelve only) as and by way of earnest money, In the form of Fixed Deposit Receipt in the

name of Executive Engineer, Maharashtra Jeevan Pradhikaran, Water

Management Division, Virar, from any Nationalized /Scheduled Bank for

minimum 12 months period from the prescribed date of submission of the

Tender., the said amount of earnest money shall not carry any interest whatsoever.

Page 4: MAHARASHTRA JEEVAN PRADHIKARANmjp.maharashtra.etenders.in/tpoimages/mjp/tender/Tender...Maharashtra Jeevan Pradhikaran, such specifications with designs and drawings shall form a part

Contractor No. of Correction Executive Engineer

(ii) In the event of his tender being accepted, to the provision of sub-clause,

(iii) below, the said amount of earnest money shall be appropriated towards the

amount of security deposit payable by him under conditions of General

Conditions of Contract if the contractor request so in writing.

(iii) if, after submitting the tender, the contractor withdraws his offer or

modifies the same, or if after the acceptance of his tender, the contractor fails or

neglects to furnish the balance amount of Security Deposit, without prejudice to

any other rights and powers of the Pradhikaran hereunder, or in law Pradhikaran

shall be entitled to forfeit the full amount of the earnest money deposited by him.

(iv) In the event of his Tender not being accepted the amount of earnest money

deposited by the Contractor shall, unless it is prior there to forfeited under the

provisions of sub clause (iii) above, be refunded by him on his passing a receipt

therefore.

3. Receipt for payments made on account of any work, when executed by a firm,

should also be signed by all the partners except where the contractors are

described in their tender as a firm, in which case the receipt shall be signed in the

name of the firm by one of the partners, or by some other person have authority to

give effectual receipts of the firm.

4. Any person who submits a tender shall fill up the usual printed form stating to

what percentage above or below the rates specified in Schedule –B

(Memorandum showing item of work to be carried out ) he is willing to undertake

the work. Only one rates or such percentage on all estimated rates / scheduled

rates shall be named. tenders which propose any alterations in the work specified

in the said form of invitation to tender, or in the time allowed for carrying out the

work, or which contain separate percentage over estimated rates / schedule rates

for different sub work or item, or which contain any other conditions of any sort

which are not filled with the percentage as the space provided for the purpose and

not signed at proper place in the printed B-1 Tender Form will be liable to

rejection. No printed form of tender shall include tender for more than one work.

But, if the contractors who wish to tender for two or more works, they shall

submit a tender for each work separately. Tenders shall have the name and the

number of work to which they refer, written outside the envelopes.

5. The Superintending Engineer shall open tenders in the presence of contractors

who have submitted tenders or their representatives who may be present at the

time, and he will enter the amount of the several tenders in a comparative

statement in a suitable form. In the event of a tender being accepted, the

contractor shall for the purpose of identification, sign copies of the specifications

and other documents mentioned in Rule 1. In the event of a tender being rejected,

the Superintending Engineer shall arrange / authorized to refund the amount of

the earnest money deposited to the tenderer, on his giving a receipt for the return

of the money.

Page 5: MAHARASHTRA JEEVAN PRADHIKARANmjp.maharashtra.etenders.in/tpoimages/mjp/tender/Tender...Maharashtra Jeevan Pradhikaran, such specifications with designs and drawings shall form a part

Contractor No. of Correction Executive Engineer

6. The Competent Authority is the final authority to reject all or any of the tenders.

7 No receipt for any payment alleged to have been made by a contractor in regard to

any matter relating to this tender or the contract shall be valid and binding on

Pradhikaran unless it is signed by the Executive Engineer.

8 The memorandum of work to be tendered for the schedule of materials to be

supplied by the Maharashtra Jeevan Pradhikaran (herein before and after called as

MJP or Pradhikaran for brevity) and their rates shall be filled in and completed

by the office of the Executive Engineer before the tender form is issued if a form

issued to an intending Tenderer has not been so filled in and completed, he shall

request the said office to have done before he completes and delivers his tender.

9. All work shall be measured net by standard measure and according to the rules

and customs of the Maharashtra Jeevan Pradhikaran without reference to any

local custom.

10. All corrections and additions or pasted slips should be initialed.

11. The measurement of work will be taken according to the usual methods in use in

the Maharashtra Jeevan Pradhikaran and no proposal to adopt alternative methods

will be accepted. The Executive Engineer’s decision as to what is the usual

method in use in the Maharashtra Jeevan Pradhikaran will be final.

12. In view of the difficult position regarding the availability of foreign exchange, no

foreign exchange would be released by the Pradhikaran for the purchase of plant

and machinery or any other purpose for the execution of the work contracted for.

13. The contractor will have to construct shed for storing controlled and valuable

materials issued to him under Schedule ‘A’ of the agreement, at work site having

double locking arrangement with his own cost and it will not reimbursed. The

material will be taken for use in the presence of the Department person. No

materials will be allowed to be removed from the site of works without written

permission of the Engineer-in-Charge.

14. Successful tendered will have to produce to the satisfaction of the accepting

authority a valid and current license issued in his favour under the provision of

Contract Labour (Regulation and Abolition Act 1973) before starting work failing

which acceptance of the tender will be liable for withdrawal and earnest money /

Security Deposit will be forfeited to Pradhikaran.

15. The contractor shall comply with the provisions of Apprentices Act, 1961 and the

rules and orders issued there under from time to time. If he fails to do so, his

failure will be a breach of the contract and the Superintending Engineer may, in

his discretion, cancel the contract. The contractor shall also be liable, for any

pecuniary liability arising on account of any violation by him of the provisions of

the Act.

Page 6: MAHARASHTRA JEEVAN PRADHIKARANmjp.maharashtra.etenders.in/tpoimages/mjp/tender/Tender...Maharashtra Jeevan Pradhikaran, such specifications with designs and drawings shall form a part

Contractor No. of Correction Executive Engineer

I/We hereby tender for the execution, for the Maharashtra Jeevan

Pradhikaran (‘hereinbefore and hereinafter referred to as Pradhikaran or MJP’) of

the work specified in the under written memorandum within the time specified in

such memorandum at “--------------------------(--------------------------------------------

---------------------------------------------------------------------) (in figures as well as in

words) percent below/above the estimated rates entered in Schedule ‘B’

(memorandum showing items of work to be carried out) and in accordance with

all respects with the specifications, designs, drawings and instructions in writing

referred to in Rule 1 hereof and in Clause 12 of the annexed conditions of the

contract and agree that what materials for the work are provided by the

Pradhikaran, such materials and the rates to be paid for them shall be as provided

in Schedule ‘A’ here.

MEMORANDUM

1.(A) General Description:

Vasai-Virar Sub-Regional Water Supply Scheme

(Surya) stage-II Part-I.

Designing, Providing and constructing RCC ESR of

capacity 1.25 ML @ Tulinj, Nallasopara (E).

a)

If several sub works

are included, same

should be detailed in a

separate list.

B) Estimated cost : Rs.1,16,15,612/

C) Earnest money : Rs. 1,00,000/- c) The amount of earnest

money to be deposited

shall be in accordance

with the provision of

paras 206 and 207 of

the MPW Manual.

D) Security deposit: Total 4% of estimated cost OR

Contract value whichever is higher.

d) This deposit shall be

in accordance with the

paras 213 and 214 of

the MPW Manual,

instruction issued by

MJP from time to time

E) (i) ( 2% Initial Security Deposit shall be in form of FDR

from any Nationalized/Scheduled Bank.)

F) (i) Balance 2% amount of security deposit, will be

recovered through each Running Bill at 5% of the gross

amount till the required total amount of Security Deposit

is recovered.

G) Percentage if any, to be deducted from bills so as to

make up the total amount required as security deposit @

e

&

This percentage where

no security deposit is

Page 7: MAHARASHTRA JEEVAN PRADHIKARANmjp.maharashtra.etenders.in/tpoimages/mjp/tender/Tender...Maharashtra Jeevan Pradhikaran, such specifications with designs and drawings shall form a part

Contractor No. of Correction Executive Engineer

4 % percent. f) taken will vary from

5% to 10% .

H) Additional Security Deposit

If the tender is proposed to be accepted at the rate quoted

less than estimated costs put to tender, additional security

deposit over and above 4% in at the below rate shall have

to be paid by the tenderer.

a) For offer up to 10% below Nil

b) For offer up to 10% to 15% below 2 %

c) For offer more than 15% below 4 %

(Additional security deposit shall be based on estimated

cost put to tender)

The additional security deposit in full in the form of FDR

/ Bank Guarantee will have to deposited at the time of

agreement.

The additional S.D. will be refunded after completion of

work in all respect only.

h) If additional security

deposit

I) Time allowed for the work from date of written order to

commence 9 months (Nine calendar months including

monsoon.)

f) Give Schedule where

necessary showing

dates by which the

various items are to be

completed.

2. I/We agree that, the offer shall remain open for

acceptance for a minimum period of 180 days from the

date fixed for opening the same and thereafter until it is

withdrawn by me/us by notice in writing duly addressed

to the authority opening the tenders and sent by

registered post A.D. or otherwise delivered at the office

of such authority. Term deposit receipt No / Demand

Draft No ---------------------- dated ------------. And date in

respect of sum of Rs------------------- in wards ( Rs --------

---------------------------------------------------------------------

--------------------------------------------only) is enclosed.

The amount of earnest money shall be liable to be

forfeited to the Pradhikaran should I / We fail (i) abide

by the stipulations to keep the offer open for the period

mentioned above or (ii) sign and complete the contract

documents as required by the Engineer and furnish the

security deposit specified in item (d) of the memorandum

contained in paragraph (1) above within the time limit

laid down in clause (1) of the annexed General

Conditions of Contract, the amount of earnest money

may be adjusted towards the security deposit or refunded

to me/us if so desired by me/us in writing unless the

same or any part thereof has been forfeited as aforesaid.

Amount to be

specified in words and

figures.

Page 8: MAHARASHTRA JEEVAN PRADHIKARANmjp.maharashtra.etenders.in/tpoimages/mjp/tender/Tender...Maharashtra Jeevan Pradhikaran, such specifications with designs and drawings shall form a part

Contractor No. of Correction Executive Engineer

3. Deleted

4. Should this tender be accepted I/we agree to abide by

and fulfill all the terms and provisions of the Conditions

of Contract annexed hereto so far as applicable and in

default thereof to forfeit and pay to the Pradhikaran the

sums of money mentioned in the said conditions.

Name of the bank to

be specified.

Fixed Deposit Receipt No --------------------------------

dated ---------------- from the Bank

At -----------------------------------------------------------------

--------in respect of the sum of Rs ----------------------------

--------( Rupees--------------------------------------------------

---------------------------------------------------------------------

---------Only)

is herewith forwarded representing the earnest money (a)

the full value of which is to be absolutely forfeited to the

Pradhikaran should I/we do not deposit in full amount of

security deposit specified in the above memorandum in

accordance with (d) of clause (1) of the tender for works

shall be refunded.

Strike out (a) if no

such security deposit

is to be taken.

Contractor Signature of Contractor

before submission of

tender

Address

-------------- day of 19--

----

Witness Signature of Witness to

Contractor’s signature

Address

Occupation

The above tender is hereby accepted by me on behalf of

the Maharashtra Jeevan Pradhikaran.

Signature of the Officer

by whom accepted

Executive Engineer

(or his duly authorized Assistant)

Page 9: MAHARASHTRA JEEVAN PRADHIKARANmjp.maharashtra.etenders.in/tpoimages/mjp/tender/Tender...Maharashtra Jeevan Pradhikaran, such specifications with designs and drawings shall form a part

Contractor No. of Correction Executive Engineer

CONDITION OF CONTRACT

Clause 1 :

(Modification as per the G.R., P.W.D. No. CAT – 1047 / CR – 94 / Bldg

– 2. dt. 14.6.89) The person/Persons whose tender may be accepted

(hereinafter called the contractor, which expression shall unless

excluded by or repugnant to the context include his heirs, executors,

administrators and assignors) shall (A) within 10 days (which may be

extended by the Superintending Engineer concerned upto 15 days if the

Superintending Engineer thinks fit to do so) of the receipt by him of the

notification of the acceptance of his tender deposit with the Executive

Engineer in cash or Government securities endorsed to the Executive

Engineer (if deposited for more than 12 months) or Bank Guarantee

from Schedule Bank of Sum sufficient which will make up the 50 % of

the total full security deposit specified in the tender. Provided always

that in the event of the contractor depositing a lump sum by way of

security deposit as contemplated at (A) above then and in such case if

the sum so deposited shall not amount to 4% of the total estimated cost

of the work, it shall be lawful for Pradhikaran at the time of making any

payment to the contractor for work done under the contract to make up

the full amount of four percent by deducting a sufficient sum from

every such payment as last aforesaid until the full amount of the

security deposit is made up. All compensation or other sums of money

payable by the contractor to Pradhikaran under the terms of his

contract may be deducted from, or paid by the sale of sufficient part of

his security deposit or from the interest arising there from, or from any

sums which may be due or may become due by Pradhikaran to the

contractor under any other contract or transaction of any nature on any

account whatsoever and in the event of his security deposit being

reduced by reason of any such deduction or sale as aforesaid, the

contractor shall within ten days thereafter, make good in cash or

Government securities endorsed. Or Bank Guarantee issued by Bank

any sum or sums which may have been deducted from or raised by sale

of his security deposit or any part thereof.

Security

deposit

If the amount of the Security deposit to be paid in lump sum within the

period specified at (A) above is not paid the Tender/Contract already

accepted shall be considered as cancelled and legal steps taken against

the contractor for recovery of the amounts. The amount of the security

deposit lodged by a contractor shall be refunded along with the payment

of the final bill, If the date upto which the contractor has agreed to

maintain the work in good order, is over. If such date is not over only

90% amount of security deposit shall be refunded along with the

payment of the final bill. The amount of security deposit retained by the

Pradhikaran shall be released after expiry of period upto, which the

contractor has agreed to maintain the work in good order, is over. In the

event of the contractor failing or neglecting to complete rectification

work within the period upto which the contractor has agreed to maintain

Page 10: MAHARASHTRA JEEVAN PRADHIKARANmjp.maharashtra.etenders.in/tpoimages/mjp/tender/Tender...Maharashtra Jeevan Pradhikaran, such specifications with designs and drawings shall form a part

Contractor No. of Correction Executive Engineer

the work in good order, then, subject to provisions of clauses 17 and 20

hereof the amount of security deposit retained by Pradhikaran shall be

adjusted towards the excess cost incurred by the department on

rectification work.

Clause 2 :

The time allowed for carrying out the work as entered in the tender shall

be strictly observed by the contractor and shall be reckoned from the

date on which the order to commence work is given to the contractor.

The work shall throughout the stipulated period of the contract be

proceeded with, with all due diligence (time being deemed to be of the

essence of the as contract on the part of the contractor. And further to

ensure good progress during execution of the work, the contractor shall

be bound in all cases in which the time allowed for any work exceeds

one month to complete for complete minimum quantum of work as

compared to accepted tender cost as stated below: -

1/4 of the work in 1/4 of the time

1/2 of the work in 1/2 of the time.

3/4 of the work in 3/4 of the time.

And abide by the programme of detailed progress laid down by the

Executive Engineer. However, in case of ground water source adopted

for the scheme the work of development of source shall only be taken in

hand by the contractor first and only after ascertaining adequacy of the

yield through GSDA during the summer period, the remaining works

shall be undertaken for execution after obtaining written permission

from the Executive Engineer. No material shall be purchased till the

adequacy of the source is confirmed and written orders to proceed for

remaining works are obtained from the Executive Engineer. In case of

failure of the original source due to inadequate yield or any other reason

the contractor shall have to take up the work of other suitable source

suggested by GSDA and to ascertain its adequacy during summer. In

such case the Executive Engineer will ascertain the reasonable time

required for completion of remaining works included in the contract and

shall grant suitable extension to the Contractor the decision of the

engineer-in-charge regarding suitable extension shall be treated as final

an binding on the contractor. However, such extension shall not be less

than '1/2 of period of completion stated in the original contract. The

Contractor shall prepare revised programme of work based on extended

time limit granted and shall get the same approved from the executive

Engineer. Based on approved revised programme the progress of the

contractor shall be watched for imposing compensation by the

Executive Engineer. The Contractor shall prepare modified programme

on completion of successful yield test and get it approved from the

Engineer-in-charge and such approved and modified programme shall

be binding on the Contractor in case of all other schemes where ground

Compen-

sation delay

Page 11: MAHARASHTRA JEEVAN PRADHIKARANmjp.maharashtra.etenders.in/tpoimages/mjp/tender/Tender...Maharashtra Jeevan Pradhikaran, such specifications with designs and drawings shall form a part

Contractor No. of Correction Executive Engineer

water is not proposed as source and have other assured water source,

works of all the sub-works can be taken up by the contractor

simultaneously and for such scheme the time limit stated in the Contract

shall be treated as final and binding on the Contractor failing which the

compensation as stated in the clause shall be recoverable.

In the event of the contractor failing to comply with this condition he

shall be liable to pay as compensation an amount equal to 1% (one

percent) of the estimated cost put to tender or such smaller amount as

the Superintending Engineer (whose decision in writing shall be final)

may decide of the said estimated cost of the whole work for every day

that the due quantity of work remains incomplete provided always that

the total amount of compensation to be paid under the provisions of this

clause shall not exceed 10 percent of the estimated cost of the work as

shown in the tender. Superintending Engineer should be the final

authority in this respect irrespective of the feet that the tender is

accepted by Chief Engineer/ Superintending Engineer / Executive

Engineer.

Clause 3 : In any case in which under any clause or clauses of this contract the

contractor shall have rendered himself liable to pay compensation

amounting to the whole of his security deposit ( whether paid in one

sum or deducted by installments) or in the case of abandonment of the

work owning to serious illness or death of the contractor or any other

clause, the Executive Engineer on behalf of Pradhikaran, shall have

power to adopt any of the following courses as he may deem best suited

to the interest of Pradhikaran

Action when

whole of

security

deposit in

forfeited.

a) To rescind the contract (for which rescission notice in writing to the

contractor under the hand of the Executive Engineer shall be conclusive

evidence) and in that case the security deposit of the contractor shall

stand forfeited and be absolutely at the disposal of Pradhikaran.

b) To carry out the work or any part of the work departmentally

debiting the contractor with the cost of the work, expenditure incurred

on tools and plant, and charges on additional supervisory staff including

the cost of work charged establishment for getting the un-executed part

of the work completed and crediting him with the value of the work

done departmentally in all respects in the same manner and at the same

rates as if it had been carried out by the contractor under the terms of his

contract. The certificate of the Executive Engineer as to the cost and

other allied expenses so incurred and as to the value of the work so done

departmentally shall be final and conclusive against the contractor.

c) To order that the work of the contractor be measured up and to take

such part thereof as shall be unexecuted out of his hands and to give it to

Page 12: MAHARASHTRA JEEVAN PRADHIKARANmjp.maharashtra.etenders.in/tpoimages/mjp/tender/Tender...Maharashtra Jeevan Pradhikaran, such specifications with designs and drawings shall form a part

Contractor No. of Correction Executive Engineer

another contractor to complete, in which case all expenses incurred on

advertisement for fixing a new contracting agency, additional

supervisory staff including the cost of work charged establishment and

cost of the work executed by the new contract agency will be debited to

contractor and the value of the work done or executed through the new

same manner and at the same rates as if it had been carried out by the

contractor under the terms of his contract. The certificate of the

Executive Engineer as to all the cost of the work and other expenses

incurred as aforesaid for or in getting the unexecuted work done by the

new contractor and as to the value of the work so done shall be final and

conclusive against the contractor.

In case the contract shall be rescinded under clause (a) above, the

contractor shall not be entitled to recover or be paid, any sum for any

work therefore actually performed by him under this contract unless and

until the Executive Engineer shall have certified in writing about the

performance of the such work and the amount payable to him in respect

thereof and he shall only be entitled to be paid the amount so certified.

In the event of either the courses referred to in clause (b) or (c) being

adopted and the cost of the work executed departmentally or through a

new contractor and other allied expenses exceeding the value of such

work credited the contractors, the amount of excess shall be deducted

from any money due to the contractor by Pradhikaran under the contract

or otherwise howsoever or from his security deposit or the sale proceeds

thereof provided however that the contractor shall have no claim against

Pradhikaran even if the certified value of the work done departmentally

or through a new contractor exceeds the certified cost of such work and

allied expenses, provided always that whichever of the three courses

mentioned in clauses (a), (b) and (c) is adopted by the Executive

Engineer, the contractor shall have no claim to compensation for any

loss sustained by him by reason of not having purchased or procured

any materials, or entered into any engagements, or made any advance on

account of or with a view to the execution of the work or the

performance of the contract. The extra cost involved in the completion

of the balance work carried out through the other contractor under

Clause - 3(C) shall be recoverable from the contractor over and above

the compensation levied under Clause 2 and the Security Deposit shall

be apportioned against the total recoveries for this purpose also.

Clause 4 : If the progress of any particular portion of the work is unsatisfactory the

Executive Engineer shall not-with-standing that the general progress of

the work is satisfactory in accordance with clause 2, be entitled to take

action under clause 3 (b) after giving the contractor 10 days notice in

writing. The contractor will have no claim for compensation, for any

loss sustained by him owning to such action.

Action when

the progress

of any

particular

portion of

the work is

un-

satisfactory.

Page 13: MAHARASHTRA JEEVAN PRADHIKARANmjp.maharashtra.etenders.in/tpoimages/mjp/tender/Tender...Maharashtra Jeevan Pradhikaran, such specifications with designs and drawings shall form a part

Contractor No. of Correction Executive Engineer

Clause 5 : In any case in with any of the powers conferred upon the Executive

Engineer by clauses 3 and 4 hereof shall have become exercisable and

the same shall not have been exercised, the non exercise thereof shall

not constitute a waiving of any of the condition hereof and such power

shall not-withstanding be exercisable in any future case of default by the

contractor for which under any clause or clauses hereof he is declared

liable to pay compensation amounting to the whole of security deposit

and the liability of contractor for past and future compensation shall

remain unaffected. In the event of the Executive Engineer taking action

under sub-clause (a) or (c) of clause 3 he may, if he so desires take

possession of all or any tools and plant, materials and stores in or upon

the work of the site thereof or belonging to the contractor, or procured

by him and intended to be used for the execution of the work or any

part thereof, paying or allowing for the same in account at the contract

rates, or in the case of contract rates not being applicable at current

market rates, to be certified by the Executive Engineer whose certificate

thereof shall be final. In the alternative the Executive Engineer may, by

notice in writing to the contractor, his clerk of the works, foreman or

other authorized agent require him to remove such tools, plant, materials

or stores from the premises within a time to be specified in such notice,

and in the event of the contractor failing to comply with any such

requisition the Executive Engineer may remove them at the contractor’s

expense or sell them by auction or private sale at risk and account of the

contractor in all respects and the certificate of the Executive Engineer as

to the expense of any such removal and the amount of the proceeds and

expense of any such sale shall be final and conclusive against the

contractor.

Contractor

remains

liable to pay

compensatio

n if action

not taken

under

Clause 3 &

4.

Power to

take

possession

of or require

removal of

or sell

contractor’s

plant.

Clause 6 : If the contractor shall desire an extension of the time for completion of

the work on the ground of his having been unavoidably hindered in his

execution or on any other ground, he shall apply in writing to the

Executive Engineer before the expiration of the period stipulated in the

tender or before the expiration of 30 days from the date to which he was

hindered as aforesaid or on which the case for asking for extension

occurred, whichever is earlier and the Executive Engineer or in the

opinion of Superintending Engineer or Chief Engineer, as the case may

be, if in his opinion there were reasonable grounds for granting an

extension, grant such extension as he thinks necessary or proper. The

decision of the Executive Engineer in this matter shall be final.

Extension of

time

Clause 7 :

On completion of the work the contractor shall be furnished with a

certificate by the Executive Engineer (herein after called the Engineer-

in-charge) of such completion but no such certificate shall be given nor

shall the work be considered to be complete until the contractor shall

Final

certificate

Page 14: MAHARASHTRA JEEVAN PRADHIKARANmjp.maharashtra.etenders.in/tpoimages/mjp/tender/Tender...Maharashtra Jeevan Pradhikaran, such specifications with designs and drawings shall form a part

Contractor No. of Correction Executive Engineer

have removed from the premises on which the work shall have been

executed, all scaffolding surplus materials and rubbish and shall have

cleaned of the dirt from all woodwork, doors, windows, walls, floor or

other parts of any building, in or upon which the work has beem

executed, or of which he may have had possession for the purpose of

executing the work nor untill the work shall have been measured by the

Engineer-in-charge or where the measurements have been taken by his

subordinates untill they have received the approval of the Engineer-in-

charge, the said measurements being binding and conclusive against the

contractor. If the contractor shall fail to comply with the requirements

of this clause as to the removal of scaffolding, surplus material and

rubbish, and cleaning off dirt on or before the date fixed for the

completion of the work, the Engineer-in-charge may at the expense of

the contractor, remove such scaffolding, surplus materials and rubbish,

and dispose of the same as he thinks fit and clean off such dirt as

aforesaid; and the contractor shall forth with pay the amount of all

expenses so incurred but shall have no claim in respect of any such

scaffolding or surplus materials as aforesaid except for any sum actually

realized by the sale thereof.

Clause 8 : No payment shall be made for any work estimated to cost less than

rupees one thousand, till after the whole of the work shall have been

completed and a certificate of completion given. But in the case of the

works estimated to cost more than rupees one thousand, the contractor

shall on submitting a monthly bill therefore be entitled to receive

payment proportionate to the part of the work then approved and passed

by the Engineer-in-charge, whose certificate of such approval and

passing of the sum payable shall be final and conclusive against the

contractor. All such intermediate payments shall be regarded payments

by way of advance against the final payments only and not as payments

for works actually done and completed and shall not preclude the

Engineer-in-charge from requiring bad, unsound, imperfect or unskilled

work to be removed or taken away and reconstructed, or rejected, nor

shall any such performance of the contract or any part thereof, in any

respect or the accruing of any claim, nor shall it conclude determine, or

affect in any way the powers of the Engineer-in-charge as to final

settlement and adjustment of the accounts or otherwise, or in any other

way vary or affect the contract. The final bill shall be submitted by the

contractor within one month of the date fixed for the completion of the

work otherwise the Engineer-in-charge’s certificate of the

measurements and of the total amount payable for the work shall be

final and binding on all parties.

Payment on

intermediate

certificate to

be regarded

as advances.

Clause 9 :

The rates for several items of work estimated to cost more than

Rs.1,000/- agreed to within, shall be valid only when the item concerned

Payment at

Page 15: MAHARASHTRA JEEVAN PRADHIKARANmjp.maharashtra.etenders.in/tpoimages/mjp/tender/Tender...Maharashtra Jeevan Pradhikaran, such specifications with designs and drawings shall form a part

Contractor No. of Correction Executive Engineer

is accepted as having been completed fully in accordance with the

sanctioned specifications. In case where the items of work are not

accepted as so completed the Engineer-in-charge may make payment on

account of such items at such reduced rates as he may consider

reasonable in the preparation of final or on account bills.

reduced

rates on

account of

item of work

not accepted

as

completed,

to be at the

discretion of

the

Engineer-in-

charge.

Clause 10 : A bill shall be submitted by the contractor each month on or before the

date fixed by the Engineer-in-charge for all work executed in the

previous month and the Engineer-in-charge shall take or cause to be

taken the requisite measurement for the purpose of having the same

verified and the claim, so far as it is admissible shall be adjusted, if

possible, within ten days from the presentation of the bill. If the

contractor does not submit the bill within the time fixed as aforesaid, the

Engineer-in-charge may depute a subordinate to measure up the said

work in the presence of the contractor or his duly authorized agent

whose counter signature to the measurement list shall be sufficient

warrant, and the Engineer-in-charge may prepare a bill from such list

which shall be binding on the contractor in all respects.

Bill to be

submitted

monthly.

Clause 11 :- The contractor shall submit all bills on the printed forms to be had on

application at the office of the Engineer-in-charge. The charges to be

made in the bills shall always be entered at the rates specified in the

tender or in the case of any extra work ordered in pursuance of these

conditions and not mentioned or provided for in the tender, at the rates

hereinafter provided for such work.

Bill to be on

printed

form.

Clause 12 : If the specification or estimate of the work provides for the use of any

special description of materials to be supplied from the stores of

the Maharashtra Jeevan Pradhikaran or if it is required that the

contractor shall use certain stores to be provided by the Engineer-in-

charge (such material and stores, and the prices to be charged

thereof as hereinafter mentioned being so far as practicable for

the convenience of the contractor but not so as in any way to control

the meaning or effect of this contract specified in the schedule or

memorandum hereto annexed) the contractor shall be supplied with such

materials and stores as may be required from time to time to be used by

him for the purposes of the contractor only, and the value of the full

Stores

supplied by

Pradhikaran

Page 16: MAHARASHTRA JEEVAN PRADHIKARANmjp.maharashtra.etenders.in/tpoimages/mjp/tender/Tender...Maharashtra Jeevan Pradhikaran, such specifications with designs and drawings shall form a part

Contractor No. of Correction Executive Engineer

quantity of materials and stores so supplied shall be set off or reduced

from any sums then due, or thereafter to become due to the contractor

under the contract or otherwise, or from the security deposit or the

proceeds of sale thereof if the security deposit is held in Government

securities, the same or a sufficient portion thereof shall in that case be

sold for the purpose. All materials supplied to the contractor shall

remain the absolute property of Pradhikaran and shall on account be

removed from the site of work and shall at all times be open to

inspection by the Engineer-in-charge. Any such material unused and

perfectly in good condition at the time of completion or determination

of the contractor shall be returned to the Maharashtra Jeevan

Pradhikaran’s store if the Engineer-in-charge so requires by a notice in

writing given under his hand, but the contractor shall not be entitled to

return any such materials except with consent of the Engineer-in-Charge

and he shall have no claim for compensation on account of any such

material supplied to him as aforesaid but remaining unused by him or

for any wastage in or damage to any such material.

Clause 12 (A) : All stores of control materials such as cement steel etc. supplied to the

contractor by Pradhikaran should be kept by the contractor under lock

and key and will be accessible for inspection by the Executive Engineer

or his agent at all times.

Clause 13 : The contractor shall execute the whole and every part of the work in the

most substantial and workman like manner and both as regards

materials and every other respect in strict accordance with specification.

The contractor shall also confirm exactly, fully and faithfully to the

designs, drawings and instructions in writing relating to the work signed

by the Engineer-in-charge and lodged in his office and to which the

contractor shall be entitled to have access for the purpose of inspection

at such office, or on the site of the work during office hours. The

contractor will be receive three sets of contract drawings and working

drawings as well as one certified copy of the accepted tender along with

the work order free of cost. Further copies of the contract drawing and

working drawings if required by him, shall be supplied at the rate of Rs.

100 per set of contract drawing and Rs. 50 per working drawing except

where otherwise specified.

Work to be

executed in

accordance

with

specification

, drawings,

orders etc.

Clause 14 (1) : The Engineer-in-charge shall have power to make any alterations in, or

additions to the original specifications, drawings, designs and

instructions that may appear to him to be necessary or advisable during

the progress of the work and the contractor shall be bound to carry

out the work in accordance with any instructions in this connection

which may be given to him in writing signed by the Engineer-in-charge

Alterations

in

specification

s and

designs not

to invalidate

Page 17: MAHARASHTRA JEEVAN PRADHIKARANmjp.maharashtra.etenders.in/tpoimages/mjp/tender/Tender...Maharashtra Jeevan Pradhikaran, such specifications with designs and drawings shall form a part

Contractor No. of Correction Executive Engineer

and such alteration shall not invalidate the contract and any additional

work which the contractor may be directed to do in the manner above

specified as part of the work shall be carried out by the contractor on the

same conditions in all respects on which he agreed to do the main work,

and at the same rates as are specified in the tender for the main work.

And if the additional and altered work includes any class of work for

which no rate is specified in this contract, then such class of work shall

be carried out at the rates entered in Schedule of Rates of the Division

or at the rates mutually agreed upon between the Engineer-in-charge and

the contractor whichever are lower. If the additional or altered

work, for which no rate is entered in the Schedule of Rates of the

Division, is ordered to be carried out before the rates are agreed upon,

then the contractor shall, within seven days of the date of receipt by him

of the order to carry out the work, inform the Engineer-in-charge of the

rate which it is his intention to charge for such class of work, and if the

Engineer-in-charge for does not agree to this rate he shall by notice in

writing be at liberty to cancel his order to carry out such class of work

and arrange to carry it out in such manner as he may consider advisable,

provided always that if the contractor shall commence work or incur any

expenditure in regard thereto before the rates shall have been

determined as lastly herein-before mentioned then in such case he shall

only be entitled to be paid in respect of the work carried out or

expenditure incurred by him prior to the date of the determination of the

rate as aforesaid according to such rates or rates as shall be fixed by the

Engineer-in-charge. In the event of a dispute the decision of the

Superintending Engineer, M J P Water Management Circle, Panvel will

be final.

contracts.

Rate for

works not

entered in

estimate or

schedule of

rates of the

district.

Where, however, the work is to be executed according to the designs,

drawings and specifications recommended by the contractor and

accepted by the competent authority the alterations above referred to

shall be within the scope of such designs, drawings and specifications

appended to the tender. The time limit for the completion of the work

be extended in the proportion that the increase in its cost occasioned by

alterations or addition bears to the cost of the original contract

work, and the certificate of the Engineer-in-charge as to such

proportion shall be conclusive.

Extensions

of time in

consequence

of additions

or

alterations.

Clause 15 :

1) If at any time after the execution of the contract documents, the

Engineer shall for any reason whatsoever (other than default on the part

of the Contractor and for which Pradhikaran is entitled to rescind the

contract) desire that the whole or any part of the work specified in the

tender should be suspended for any period or that the whole or part of

the work should not be carried out at all, he shall give to the contractor a

notice in writing of such desire and upon the receipt of such notice the

Contractor shall forth with suspend or stop the work wholly or in part as

No claim to

any payment

or

compensatio

n for

alteration in

or restriction

of work.

Page 18: MAHARASHTRA JEEVAN PRADHIKARANmjp.maharashtra.etenders.in/tpoimages/mjp/tender/Tender...Maharashtra Jeevan Pradhikaran, such specifications with designs and drawings shall form a part

Contractor No. of Correction Executive Engineer

required, after having due regard to the appropriate stage at which the

work should be stopped or suspended so as not to cause any damage or

injury to the work already done or in danger the safety thereof it

provided that the decision of the Engineer as to the state at which the

work or any part of it could be or could have been safely stopped or

suspended shall be final and conclusive against the Contractor. The

contractor shall have no claim to any payment or compensation

whatsoever by reason of or in pursuance of any notice as aforesaid, on

account of any suspension, stoppage or curtailment except to the extent

specified hereinafter.

2) Where the total suspension of work ordered as aforesaid continued

for a continuous period exceeding 90 days, the contractor shall be

liberty to withdraw from the contractual obligations under the contract

so far as in pertains to the unexecuted part of the work by giving a 10

days prior notice in writing to the Engineer, within 30 days of the expiry

or the said period of 90 days, of such intention and requiring the

Engineer to record the final measurements of the work already done and

to pay the final bill. Upon given such notice the contractor shall be

deemed to have been discharged from his obligation to complete the

remaining unexecuted the work under this contract. On receipt of such

notice the Engineer shall proceed to complete the measurement and

make such payment as may be finally due to the Contractor within a

period of 90 days from the receipt of such notice in respect of the work

already done by the Contractor such payment shall not in any manner

prejudice the right of the Contractor to any further compensation under

the remaining provision of this clause.

3) Where the Engineer requires the contractor to suspend the work for a

period in excess of 30 days at any time or 60 days in the aggregate, the

contractor shall be entitled to apply to the Engineer within 30 days of

the resumption of work after such suspension for payment of

compensation to the extent of pecuniary loss suffered by him in respect

of working machinery rendered idle on the site or on account of his

having had to pay the salary or wages of labour engaged by him during

the said period of suspension. Provided always that the contractor shall

not be entitled to any claim in respect of any such working machinery,

salary or wages for the first 30 days whether consecutive or in the

aggregate of such suspension or in respect of any suspension

whatsoever occasioned by unsatisfactory work or any other default on

his part. The decision of the Engineer in this regard shall be final and

conclusive against the contractor.

4) In the event of No claim to

compen-

sation

Page 19: MAHARASHTRA JEEVAN PRADHIKARANmjp.maharashtra.etenders.in/tpoimages/mjp/tender/Tender...Maharashtra Jeevan Pradhikaran, such specifications with designs and drawings shall form a part

Contractor No. of Correction Executive Engineer

i) Any total stopage of work on notice from the Engineer under Sub-

clause (1) in that behalf.

on account

of loss due

to delay in

ii) Withdrawal by the Contractor from the contractual obligation to

complete the remaining unexecuted work under Sub clause (2) on

account of continued suspension of work for a period exceeding 90

days.

supply of

materials by

Pradhikaran

iii) Curtailment in the quantity of an item or items originally tendered

on account of any alteration, omission or substitutions in the

specifications, drawing designs, or instructions under clause 14 (1)

where such curtailment exceeds 25 % in quantity and the value of the

quantity curtailed beyond 25 percent at the rates for the item specified in

the tender is more than Rs. 5000/- It shall be open to the contractor

within 90 days from the service of (i) the notice of stoppage of work or

(ii) the notice of with drawl from the contractual obligations under the

contract on account of the continued suspension of work or (iii) notice

under clause 15 (1) resulting in such curtailment to produce to the

Engineer satisfactory documentary evidence that he had purchased or

agreed to purchase material for use in the contracted work, before

receipt by him of the notice of stoppage, suspension or curtailment and

require the Pradhikaran to take over on payment such material at the

rates determined by the Engineer, provided however such rates shall in

no case exceeds the rates at which the same were acquired by the

contractor. The Pradhikaran shall thereafter take over the material so

offered, provided the quantities offered are not in excess of the

requirements of the unexecuted work as specified in the accepted tender

and are of quality and specification approved by the Engineer.

Clause 15 A :

The contractor shall not be entitled to claim any compensation from

Pradhikaran for the loss suffered by him on account of delay by the

Pradhikaran in the supply of materials entered in Schedule A where

such delay is caused by -

No claim to

compensatio

n on account

of loss due

to delay in

supply of

materials by

Pradhikaran.

i) Difficulties relating to the supply of

railway wagons

ii) Force majeure.

iii) Act of God.

iv) Act of enemies of the state or any other reasonable cause beyond

the control of Pradhikaran.

Page 20: MAHARASHTRA JEEVAN PRADHIKARANmjp.maharashtra.etenders.in/tpoimages/mjp/tender/Tender...Maharashtra Jeevan Pradhikaran, such specifications with designs and drawings shall form a part

Contractor No. of Correction Executive Engineer

In the case such delay in the supply of materials, Pradhikaran shall grant

such extension of time for the completion of the works as shall appear to

the Executive Engineer to be reasonable in accordance with the

circumstances of the case. The decision of the Executive Engineer as to

the extension of time shall be accepted as final by the contractor.

Clause 16 :

Under no circumstances whatever shall the contractor be entitled to any

compensation from Pradhikaran on any account unless the contractor

shall have submitted claim in writing to the Engineer-in-charge within

one month of the cause of such claim occurring.

Time limit

for

unforeseen

claims.

Clause 17 : If at any time before the security deposit is refunded to the contractor, it

shall appear to the Engineer-in-charge or his subordinate in-charge of

the work, that any work has been executed with unsound, imperfect or

unskilled workmanship or with materials of inferior quality or that

any materials or articles provided by him for the execution of the

work are unsound, or of a quality inferior to that contracted for, or are

otherwise not in accordance with the contract it shall be lawful for the

Engineer-in-charge to intimate this fact in writing to the contractor and

then not with standing the fact that the work, materials or articles

complained of may have been inadvertently passed, certified and paid

for, the contractor shall be bound forthwith to rectify, or remove and

reconstruct the work so specified in whole or in part, as the case may

require, or if so required shall remove the materials or articles so

specified and provide other proper and suitable materials or articles at

his own charge and cost and in the event of his failing to do so within a

period to be specified by the Engineer-in-charge in the written

intimation aforesaid, the contractor shall be liable to pay compensation

at the rate of one percent on the amount of the estimate for every day

not exceeding ten days, during which the failure so continues, and in the

event of any such failure as aforesaid the Engineer-in-charge may

rectify or remove and re-execute the work or remove and replace the

materials or articles complained of as the case may be at the risk and

expense in all respects of the contractor. Should the Engineer-in-charge

consider that any such inferior work or materials as prescribed above

may be accepted or made use of it shall be within his discretion to

accept the same at such reduced rates as he may fix therefore.

Action and

compensatio

n payable in

case of bad

work.

Clause 18 : All works under or in course of execution or executed in pursuance of

the contract shall at all times be open to the inspection and supervision

of the Engineer-in-charge and his subordinates, and the contractor shall

at all times during the usual working hours, and at all other times at

which reasonable notice of the intention of the Engineer-in-charge or his

subordinate to visit the works shall have been given to the contractor,

Works to be

open to

inspection.

Contractor

Page 21: MAHARASHTRA JEEVAN PRADHIKARANmjp.maharashtra.etenders.in/tpoimages/mjp/tender/Tender...Maharashtra Jeevan Pradhikaran, such specifications with designs and drawings shall form a part

Contractor No. of Correction Executive Engineer

either himself be present to receive orders and instructions, or have a

responsible agent duly accredited in writing present for that purpose.

Orders given to the contractor’s duly authorized agent shall be

considered to have the same force and effect as if they had been given to

the contractor himself.

or

responsible

agent to be

present

Clause 19 :

The contractor shall give not less than five days notice in writing to the

Engineer-in-charge or his subordinate in-charge of the work before

covering up or otherwise placing beyond the reach of measurement any

work in order that the same may be measured and correct dimensions

therefore taken before the same is covered up or placed beyond the

reach of measurement any work without the consent in writing of the

Engineer-in-charge or his subordinate in charge of the work, and if any

work shall be covered up or place beyond the reach of measurement

without such notice having been given or consent obtained, the same

shall be uncovered at the contractor’s expense and in default thereof no

payment or allowance shall be made for such work or for the materials

with which the same was executed.

Notice to be

given before

work is

covered.

Clause 20 :

If during the period specified below as “Defect liability period”

reckoned from the date of completion as certified by the Engineer-in-

charge pursuant to clause 7 of the contract, in the opinion of Executive

Engineer, the said work is defective in any manner, whatsoever, the

contractor shall forthwith, on receipt of notice in that behalf from the

Executive Engineer, duly commence execution and completely carryout

at his costs rectifying and setting right the defect specified therein

including dismantling & reconstructing of unsafe portion strictly in

accordance with and in the manner prescribed & under the supervision

of the Executive Engineer in the event of the contractor failing or

neglecting to commence execution of the said rectification work within

the period prescribed therefore in the said notice and/or to complete the

same as aforesaid as required by the said notice, the Executive Engineer

get the same executed and carried out departmentally or by any other

agency at the risk on account and at the cost of contractor.

Contractor

liable for

damage

done and for

imperfection

s

The contractor shall forthwith on demand pay to the Pradhikaran the

amount of such costs, charges and expenses sustained or incurred by the

Pradhikaran of which the certificate of Executive Engineer, shall be

final and binding on the contractor. Such cost charges and the expenses

shall be deemed to be arrears of land revenue and in the event of the

contractor failing or neglecting to the same on demand as aforesaid

without prejudice to any other rights and remedies of the Pradhikaran

the same may be recovered from the contractor as arrears of land

revenue. The Pradhikaran shall also be entitled to deduct the same from

any account which may then be payable or which may thereafter

Page 22: MAHARASHTRA JEEVAN PRADHIKARANmjp.maharashtra.etenders.in/tpoimages/mjp/tender/Tender...Maharashtra Jeevan Pradhikaran, such specifications with designs and drawings shall form a part

Contractor No. of Correction Executive Engineer

become payable by the Pradhikaran to the contractor either in respect of

said work or any other work whatsoever or from the amount of security

deposit retained by the Pradhikaran.

Defect liability period for works is as under :

1) 5 Years

Clause 21 :

The contractor shall supply at his own cost all materials (except such

special materials, if any as may be supplied from the Pradhikaran stores)

plant, tools, appliances, implements, ladders, tools, tackle, scaffolding

and any temporary works which may be required for the proper

execution of the work, whether in the original, altered or substituted

form, and whether included in the specifications; or other documents

forming part of the contract or referred to in these conditions or not and

which may be necessary for the purpose of satisfying or complying with

the requirements of the Engineer-in-charge as to any matter on which

under these conditions he is entitled to be satisfied or which he is

entitled to require together with carriage here for, to and from the work.

The contractor shall also supply without charge the requisite number of

persons with the means and materials necessary for the purpose of

setting out works, and counting, weighing and assisting in the

measurement or examination at any time and from time to time of the

work or materials. Failing this the same may be provided by the

Engineer-in-charge at the expense of the contractor and the expenses

may be deducted from any money due to the contractor under the

contract and or from his security deposit or the proceeds of sale thereof

or of a sufficient portion thereof. The contractor shall provide all

necessary fencing and lights required to protect the public from accident

and shall also be bound to bear the expenses of defense of every suit,

action or other legal proceedings at law, that may be brought by any

person for injury sustained owing to neglect of the above precautions,

and to pay damages and costs which may be awarded in any such suit,

action, or proceedings to any such person, or which may with the

consent of the contractor be paid for compromising any claim by any

such person.

Contractors

to supply

plant,

ladders

scaffoldings,

etc.

And is liable

for damages

arising from

non

provision of

lights,

fencing etc.

Clause 21 A :

The contractor shall provide suitable scaffolds and working platforms,

gangways and stairways and shall comply with the following

regulations in connection therewith :-

a) Suitable scaffolds be provided for workmen for all work that cannot

be safely done from a ladder or by other means.

b) A scaffold shall not be constructed, taken down, or substantially

altered except

Page 23: MAHARASHTRA JEEVAN PRADHIKARANmjp.maharashtra.etenders.in/tpoimages/mjp/tender/Tender...Maharashtra Jeevan Pradhikaran, such specifications with designs and drawings shall form a part

Contractor No. of Correction Executive Engineer

i) under the supervision of a competent and responsible person; and

ii) as far as possible by competent workers possessing adequate

experience in this kind of work.

c) All scaffolds and appliances connected therewith and all ladders

shall :-

i) be of sound material

ii) be of adequate strength having regard to the loads and strains to

which they will be subjected; and

iii) be maintained in proper condition.

d) Scaffolds shall be so constructed that no part thereof can be

displaced in consequence of normal use.

e) Scaffolds shall not be overloaded and so far as practicable the load

shall be evenly distributed.

f) Before installing lifting gear on scaffolds special precautions shall be

taken to ensure the stability of the scaffolds.

g) Scaffolds be periodically inspected by a competent person.

h) Before allowing a scaffold to be used by his workman the contractor

shall, whether the scaffold has been erected by his workmen or not, take

steps to ensure that it complies fully with the regulations herein

specified.

i) Working platforms, gangways and stairways shall -

i) be so constructed that no part thereof can sag unduly or unequally;

ii) be so constructed and maintained, having regard to the prevailing

conditions as to reduce as far as practicable risks of persons

tripping or slipping; and

iii) be kept free from any unnecessary obstruction.

j) In the case of working platforms, gangways, working places and

stairways at a height exceeding

i) every working platform and every gangway shall have be closely

Pradhikaran unless other adequate measures are taken to ensure

safety;

ii) every working platform and gangway shall have adequate width;

and

iii) every working platform, platform, gangway, working place and

stairway shall be suitably fenced.

Page 24: MAHARASHTRA JEEVAN PRADHIKARANmjp.maharashtra.etenders.in/tpoimages/mjp/tender/Tender...Maharashtra Jeevan Pradhikaran, such specifications with designs and drawings shall form a part

Contractor No. of Correction Executive Engineer

k) Every opening in the floor of a building or in a working platform

shall except for the time and to the extent required to allow the excess of

persons or the transport or shifting of material, be provided with suitable

means to prevent the fall of persons or material.

l) When persons are employed on a roof where there is a danger of

falling from a height exceeding (To be prescribed) suitable precautions

shall be taken to prevent the fall of persons or material.

m) Suitable precautions shall be taken to prevent persons being struck

by articles which might fall from scaffolds or other places.

n) Suitable means of access shall be provided to all working platforms

and other working places.

o) The contractor(s) will have to make payments to the labourers as per

Minimum Wages Act.

Clause 21 B :

The contractor shall comply with the following regulations as regards

the Hoisting Appliances to be used by him.

a) Hoisting machines and tackle, including their attachments,

anchorages and supports shall –

i) be of good mechanical construction, sound material and adequate

strength and free from patent defect; and

ii) be kept in good repair and in good working order.

b) Every rope used in hoisting or lowering material or as a means of

suspension shall be of suitable quality and adequate strength and free

from patent defect.

c) Hoisting machines and tackle shall be examined and adequately

tested after erection on the site and before use and be re-examined in

portion at intervals to be prescribed by the Pradhikaran.

d) Every chain, ring, hook, shackle, swivel and pulley block used in

hoisting or lowering material or as a means of suspension shall be

ascertained by adequate means.

e) Every crane driver or hoisting appliance operator shall be properly

qualified.

f) No person who is below the age of 18 years shall be in control of any

hoisting machine, including any scaffold which give signals to the

operator.

Page 25: MAHARASHTRA JEEVAN PRADHIKARANmjp.maharashtra.etenders.in/tpoimages/mjp/tender/Tender...Maharashtra Jeevan Pradhikaran, such specifications with designs and drawings shall form a part

Contractor No. of Correction Executive Engineer

g) In case of every hoisting machine and every chain, ring, hook,

shackle, swivel and pulley blocks used in hoisting or lowering as a

means of suspension, the safe working load shall be ascertained by

adequate means.

h) Every hoisting machine and all gear referred to in the preceding

regulation shall be plainly marked with the safe working load.

i) In the case of a hoisting machine having a variable safe working load,

each safe working load and the conditions under which it is applicable

shall be clearly indicated.

j) No part of any hoisting machine or of any gear referred to in

regulation “g” above shall be loaded beyond the safe working load

except for the purpose of testing.

k) Motors, gearing, transmissions, electric wiring and other dangerous

parts of hoisting appliances shall be provided with efficient safeguards.

l) Hoisting appliances shall be provided with such means as will reduce

to a minimum risk of the accident of the load.

m) Adequate precautions shall be taken to reduce to a minimum the risk

of any of a suspended load becoming accidentally displaced.

Clause 22 : The contractor shall not set fire to any standing jungle, trees, brushwood

or grass without a written permit from the Executive Engineer. When

such permit is given, and also in all cases when destroying cut or dug up

trees, brushwood, grass etc. by fire, the contractor shall take necessary

measures to prevent such fire spreading to or otherwise damaging

surrounding property. The contractor shall make his own arrangements

for drinking water for the labour employed by him.

Measure for

prevention

of fire

Clause 23 :

Compensation for all damages done intentionally or unintentionally by

contractor’s labours whether in or beyond the limits of Pradhikaran’s

property including any damage caused by spreading of fire mentioned in

clause 22 shall be estimated by the Engineer-in-charge or such other

officer as he may appoint and the estimate of the Engineer-in-charge

subject to the decision of the Superintending Engineer on appeal shall

be final and the contractor shall be bound to pay the amount of the

assessed compensation on demand failing which the same will be

recovered from the contractor as damages in the manner prescribed in

clause 1 or deduced by the Engineer-in-charge from any sums that may

be due to or become due from Pradhikaran to the contractor under this

contract or otherwise thereof.

Liability of

contractors

for any

damage

done in or

outside

work area.

Page 26: MAHARASHTRA JEEVAN PRADHIKARANmjp.maharashtra.etenders.in/tpoimages/mjp/tender/Tender...Maharashtra Jeevan Pradhikaran, such specifications with designs and drawings shall form a part

Contractor No. of Correction Executive Engineer

The contractor shall bear the expenses of defending any action or

other legal proceeding that may be brought by any person for injury

sustained by him owing to neglect of precautions to prevent the spread

of fire and he shall also pay any damages and cost that may be awarded

by the Court in consequence.

Clause 24 : The employment of female laborers on works in the neighborhood of

soldier’s barracks should be avoided as far as possible.

Employment

of female

labour.

Clause 25 : No work shall be done on a sunday without the sanction in writing of

the Engineer-in-charge.

Work on

Sunday.

Clause 26 : The contract shall not be assigned or sublet without the written approval

of the Engineer-in-charge and if the contractor shall assign or sublet his

contract, or attempt so to do or become insolvent or commence any

proceedings to get himself adjudicated and in solvent or make any

composition with his creditors or attempt so to do or if bribe gratuity,

gift, loan perquisite, reward or advantage, pecuniary or otherwise, shall

either directly or indirectly be given, promised, or offered by the

contractor or any of his servants or agents to any public officer or

person in the employ of Pradhikaran in any way relating to his office or

employment, or if any such officer or person shall become in any way

directly or indirectly interested in the contract, the Engineer-in-charge

there upon by notice in writing rescind the contract and the security

deposit of the contractor shall thereupon stand forfeited and be

absolutely at the disposal of Pradhikaran and same consequences shall

ensure as if the contractor had been rescinded under clause 3 hereof and

in addition the contractor shall not be entitled to recover or to be paid

for any work therefore actually performed under the contract.

Work not to

be sublet.

Contract

may be

rescinded

and security

deposit

forfeited for

subletting it

without

approval or

for bribing a

public

officer or if

contractor

becomes

insolvent.

Clause 27 :

All sums payable by a contractor by way of compensation under any of

these conditions shall be considered as a reasonable compensation to be

applied to the use of Pradhikaran without reference to the actual loss or

damage sustained and whether any damage has or has not been

sustained.

Sum

payable by

way of

compensatio

n to be

considered

as

reasonable

compen-

sation

without

reference to

actual loss.

Page 27: MAHARASHTRA JEEVAN PRADHIKARANmjp.maharashtra.etenders.in/tpoimages/mjp/tender/Tender...Maharashtra Jeevan Pradhikaran, such specifications with designs and drawings shall form a part

Contractor No. of Correction Executive Engineer

Clause 28:

In the case of a tender by a partnership firm any change in the

constitution of the firm shall be forth with notified by the contractor to

the Engineer-in-charge for his information.

Changes in

the

constitution

of firm to be

notified.

Clause 29 :-

All work to be executed under the contract shall be executed under the

direction and subject to the approval in all respects of the

Superintending Engineer of the Pradhikaran, for the time being, who

shall be entitled to direct at what point or points and in what manner

they are to be commenced, and from time to time carried on.

Direction

and control

of

Superintendi

ng Engineer.

Clause 30:

(1)Except where otherwise specified in the contract and subject to the

powers delegated to him by Pradhikaran under the code rules then in

force, the decision of the Superintending Engineer of the Circle for the

time being shall be final, conclusive and binding on all parties to the

contract upon all questions relating to the meaning of the specifications,

designs, drawings and instruction herein before mentioned and as to the

quality of workmanship or material, used on the work, or as to any other

question, claim, right, matter, or things whatsoever, in any way arising

out of, or relating to the contract designs, drawings, specifications,

estimates, instructions, orders or these conditions or otherwise

concerning the works, or the execution or failure to execute the same

whether arising, during the progress of the work or after the completion

or abandonment thereof.

(2) The contractor may within 30 days of receipt by him of any order

passed by the Superintending Engineer of the Circle as aforesaid appeal

against it to the Chief Engineer concern with the contract work or

project provided that –

a) The accepted value of the contract exceeds Rs 10 lakh.

b) Amount of claim is not less than Rs 1.00 lakh.

(3) If the contractor is not satisfied with the order passed by the Chief

Engineer as aforesaid, the contract may, within 30 days of receipt by

him of any such order, appeal against it to the Member Secretary

(Technical), Maharashtra Jeevan Pradhikaran who if convinced that

prima facie, the contractor’s claim rejected by the Superintending

Engineer / Chief Engineer is not frivolous and that there is some

substance in the claim of the contractor as would merit a detailed

examination in the claim of the contractor as would merit a detailed

examination and decision by Pradhikaran shall put up to Pradhikaran for

suitable decision. The decision of the MJP shall be final and binding on

the contractor and the Engineer-in-Charge.

Page 28: MAHARASHTRA JEEVAN PRADHIKARANmjp.maharashtra.etenders.in/tpoimages/mjp/tender/Tender...Maharashtra Jeevan Pradhikaran, such specifications with designs and drawings shall form a part

Contractor No. of Correction Executive Engineer

Clause 31 : Deleted

Clause 32 :

When the estimate on which a tender is made includes lump sums in

respect of parts of the work the contractor shall be entitled to payment in

respect of items of work involved or the part of the work in question at

the same rates as are payable under this contract for such items, or if the

part of the work in question is not in the opinion of the Engineer-in-

charge capable of measurement, The Engineer-in-Charge may as his

discretion pay the lump sum amount entered in the estimate, and the

certificate in writing of the Engineer-in-charge shall be final and

conclusive against the contractor with regard to any sums payable to

him under the provisions of this clause.

Lump sums

in estimates.

Clause 33 :

In the case of any class of work for which there is no such specification

as is mentioned in rule 1 of form B-1 such work shall be carried out in

accordance with the Divisional Specification, then in case the work shall

be carried out in all respects in accordance with the instructions and

requirements of the Engineer-in-charge.

Action

where no

specification

.

Clause 34 :

The expression ‘works’ or ‘work’ where used in these conditions shall,

unless there be something in the subject or context repugnant to such

construction be construed to mean the work or the works contracted to

be executed under or in virtue of the contract, whether temporary or

permanent and whether original, altered, substituted or additional.

Definition

of work.

Clause 35 :

The percentage referred to in the tender shall be deducted from/added to

the gross amount of the bill before deducting the value of any stock

issued.

Contractors

percentage

whether

applied to

net or gross

amount of

bill.

Clause 36 :

All quarry fees, royalties, octroi dues and ground rent for stacking

materials, if any, should be paid by the contractor, who will not be

entitled to refund of such charges from MJP. (please see special clause

for royalty).

Refund of

quarry fees

and

royalties.

Clause 37 :

The contractor shall be responsible for and shall pay compensation to

his workmen payable under the Workman’s Compensation Act, 1923

(VIII of 1923) hereinafter called the said Act) for injuries caused to the

workmen. If such compensation is payable and or paid by

Compen-

sation under

Workman’s

Compen-

Page 29: MAHARASHTRA JEEVAN PRADHIKARANmjp.maharashtra.etenders.in/tpoimages/mjp/tender/Tender...Maharashtra Jeevan Pradhikaran, such specifications with designs and drawings shall form a part

Contractor No. of Correction Executive Engineer

Pradhikaran as principal under sub section (1) of section 12 of the said

act on behalf of the contractor, this shall be recoverable by Pradhikaran

from the contractor under sub-section (2) of the said section. Such

compensation shall be recovered in the manner laid down in clause 1

above.

sation Act.

Clause 37 A :

The contractor shall be responsible for and shall pay the expense of

providing medical aid to any workmen who may suffer a bodily injury

as a result of an accident. If such expenses are incurred by

Pradhikaran the same shall be recoverable from the contractor forthwith

and deducted without predjudice to any other remedy of Pradhikaran

from any amount due or that may become due to the contractor.

Clause 37B :

The contractor shall provide all necessary personal safety equipment

and first-aid apparatus available for the use of the persons employed on

the site and shall maintain the same in condition suitable for immediate

use at any time and shall comply with the following regulations in

connection therewith:-

a) The worker shall be required to use the equipment so provided by the

contractor and the contractor shall take adequate steps to ensure proper

use of the equipment by those concerned.

b) When work is carried on in proximity to any place where there is a

risk of drowning, all necessary equipment shall be provided and kept

ready for use and all necessary steps shall be taken for the prompt

rescue of any person in danger.

c) Adequate provision shall be made for prompt first-aid treatment of

all injuries likely to be sustained during the course of the work.

Clause 37C :

The contractor shall duly comply with the provisions of “The

Apprentices Act, 1961 (LII of 1961), the rules made there under the

orders that may be issued from time to time under, the said Act and the

said Rules and on his failure or neglect to do so he shall be subject to all

the liabilities and penalties provided by the said Act and said Rules”.

Clause 38 :

(1) Deleted

Claims for

quantities of

works

entered in

the tender or

estimates.

Page 30: MAHARASHTRA JEEVAN PRADHIKARANmjp.maharashtra.etenders.in/tpoimages/mjp/tender/Tender...Maharashtra Jeevan Pradhikaran, such specifications with designs and drawings shall form a part

Contractor No. of Correction Executive Engineer

(2) Quantities in respect of the several items shown in the tender are

approximate and no revision in the tendered rates shall be permitted in

respect of any of the items so long as, subject to any special provision

contained in the specifications prescribing a different percentage of

permissible variation, the quantity of the items does not exceed the

tender quantity by more than 25 percent and so long as the value of the

excess quantity beyond this limit, at the rate of the items specified in the

tender, is not more than Rs. 5,000/- ( which ever is more )

(3) The contractor shall, if ordered in writing by the Engineer, to do so

also carry out any quantities in excess of the limit mentioned in Sub

clause (1) hereof on the same conditions as and in accordance with the

specification in the tender and at the rates (i) derived from the rates

entered in the current schedule of rates and in the absence of such rates

(ii) at the rate prevailing in the market, the said rates being increased or

decreased as the case may by the percentage which the total tendered

amount bears to the estimated cost of the work as put to tender based

upon the schedule of rates applicable to the year in which the tenders

were invited (for the purpose of operation of this clause this cost shall

be taken to be Rs. 1,16,15,612/- (Rupees One Crore Sixteen Lac

Fifteen Thousand Six Hundred Twelve Only) as per DSR 2011 -

2012

4) This clause is not applicable to Extra Item.

(5) Claims arising out of reduction in the tendered quantity of any item

beyond 25 percent will be governed by the provisions of clause 15 only

when the amount of such reduction beyond 25 percent at the rate of item

specified in the tender is more than Rs. 5,000/-. This reduction

mentioned in clause no. 14 & 15 of work and site condition.

(6) There shall be no change in the rate if the excess is less than or equal

to 25%. Also there shall be no change in the rate if the quantity of work

done is more than 25% of the tendered quantity, but the value of the

excess work at the tender rate does not exceed Rs. 5,000/-

(7) The quantities to be paid at the tender rates shall include

a) tendered quantity plus

b) 25 % excess of tendered quantity or the excess quantity of the

value of Rs. 5,000/- at tendered rate which ever is more.

CLARIFICATION TO THE CLAUSE OF EXCESS QUANTITY.

1) The Executive Engineer shall see that the claim towards excess

quantities under this clause 38 is submitted to higher authority

immediately on its cropping up. Executive Engineer while making such

payments shall see that the total expenditure on the scheme shall not

Page 31: MAHARASHTRA JEEVAN PRADHIKARANmjp.maharashtra.etenders.in/tpoimages/mjp/tender/Tender...Maharashtra Jeevan Pradhikaran, such specifications with designs and drawings shall form a part

Contractor No. of Correction Executive Engineer

exceed sanctioned cost of scheme.

2) Quantity is equal to that of quantity as per “Schedule B” i.e.

estimated quantity put to tender plus 25% or Rs 5000 /- ( Whichever is

more ) shall be paid at accepted tender rate as usual after submission of

excess quantity proposal to the competent authority for approval.

3(a) Excess quantities upto 25% of tender quantity or quantities within

Rs.5000/- (Rupees Five Thousand only) cost whichever is more are to

be paid at tendered rates. After submitting the proposal to the competent

authority for approval, then only Executive Engineer can make

payments.

3(b) The Executive Engineer is hereby authorized to make 50%

payment of the excess quantity beyond 25% over tender quantity or Rs.

5,000.00 (Rupees Five Thousand Only) cost, whichever is more at

proposed rates after submission of excess quantity proposal to the

competent authority for approval.

4) The powers for approval of excess beyond estimated quantity worth

Rs. 10.00 lakhs are vested with Superintending Engineer. The Chief

Engineer is empowered to approve proposal of excess quantity worth

Rs. 30.00 lakhs only subject to condition that due to approval of excess

quantity proposal there should not be any increase in the sanctioned cost

of the Scheme. Excess Quantity proposal involving approval of excess

quantity beyond 30.00 lakhs is in the power of Member Secretary

subject to revised administrative approval to the scheme.

Clause 39 :

The contractor shall employ any femine, convict or other labour of a

particular kind of class if ordered in writing to do so by the Engineer-in-

charge.

Employment

of female or

other labour.

Clause 40 :

No compensation shall be allowed for any delay caused in the starting

of the work on account of any acquitition of land and in the case of the

clearance works, for any delay in according sanction to estimates.

Claim for

compensatio

n for delay

in starting

the work.

Clause 41 :

No compensation shall be allowed for any delay in execution of the

work on account of water standing in borrow pits or compartments. The

rates are inclusive for hard or cracked soil excavation in mud, sub-soil

water or water standing in borrow pits and no claim for any extra rate

shall be entertained, unless otherwise expressly specified.

Claim for

compensatio

n for delay

in the

execution of

work.

Clause 42 :

The contractor shall not enter upon or commence any portion of work

except with the written authority and instruction of the Engineer-in-

Entering

upon or

Page 32: MAHARASHTRA JEEVAN PRADHIKARANmjp.maharashtra.etenders.in/tpoimages/mjp/tender/Tender...Maharashtra Jeevan Pradhikaran, such specifications with designs and drawings shall form a part

Contractor No. of Correction Executive Engineer

charge or of his subordinate in charge of the work failing such authority

the contractor shall have no claim to ask for measurements of or

payment for work.

commencing

any portion

of work.

Clause 43:

i) No contractor shall employ any person who is under the age of 12

years.

Minimum

age of

persons

employed,

the employ-

ment of

donkeys and

or other

animals and

the payment

of fair

wages.

ii) No contract shall employ donkeys or other animals with breeching

of string or thin rope. The breeching must be at least three inches wide

and should be of tape (Nevar).

iii) No animal suffering from sores; lameness or emaciation or which is

immature shall be employed on the work.

iv) The Engineer-in-charge or his agent is authorized to remove from

the work any person or animal found working which does not satisfy

these conditions and no responsibility shall be accepted by Pradhikaran

for any delay caused in the completion of the work by such removal.

v) The contractor shall pay fair and reasonable wages to the workman

employed by him in the contract undertaken by him. In the event of any

dispute arising between the contractor and his workman on the grounds

that the wages paid are not fair and reasonable, the dispute shall be

referred without delay to the Executive Engineer who shall decide the

same. The decision of the Executive Engineer, shall be conclusive and

binding on the contractor, but such decision shall not in any way affect

the condition in the contract regarding the payment to be made by

Pradhikaran at the sanctioned tender rates.

vi) The contractor shall provide drinking water facilities to the workers

similar amenities shall be provided to the workers engaged on large

work in urban areas.

vii) The contractor to take precautions against accidents which take

place on account of labour using loose garments while working near

machinery.

Page 33: MAHARASHTRA JEEVAN PRADHIKARANmjp.maharashtra.etenders.in/tpoimages/mjp/tender/Tender...Maharashtra Jeevan Pradhikaran, such specifications with designs and drawings shall form a part

Contractor No. of Correction Executive Engineer

Clause 44 :

Payment to contractors shall be made by cheques drawn on any Bank

within the Divisional limits, convenient to them, provided the amount

exceeds Rs. 1000. Amount not exceeding Rs. 1000 will be paid in cash.

Method of

payment.

Clause 45 :

Any contractor who does not accept these conditions shall not be

allowed to tender for works. Entering into contract by the Contractor

with MIP by the contractor shall be considered as incontrovertible proof

of acceptance of all conditions of the contract by the contractor.

Acceptance

of

conditions

compulsory

before

tendering

for work.

Clause 46 :

If Government declares a state of scarcity or famine to exist in any

village situated within 16 Kilometers of work, the contractor shall

employ upon such parts of the work as suitable for unskilled labour any

person certified to him by the Executive Engineer, or by any person to

whom the Executive Engineer may have delegated his duty in writing to

be in need of relief and shall be bound to pay to such person wages not

below minimum which may arise in connection with the

implementation of this clause shall be decided by the Executive

Engineer whose decision shall be final and binding on the Contractor.

Employment

of scarcity

labour.

Clause 47 :

The price quoted by the contractors shall not in any case exceed the

control price, if any, fixed by Govt. or reasonable price which is

permissible to him to charge as private purchaser for the same class and

description, the controlled price or the price permissible under Hoarding

and Profiteering Prevention Ordinance 1948 as commended from time

to time, if the price quoted exceeds the controlled price or the price

permissible under Hoarding and Profiteering Prevention Ordinance the

contractor will specifically mention this fact in the tender along with

reasons for quoting such higher price. The purchaser at his discretion

will in such case exercise the right of revising the price at any stage so

as to conform with the controlled price as permissible under the

Hoarding and Profiteering Prevention Ordinance. This discretion will

be exercised without prejudice to any other action that may be taken

against the Contractor.

Price not to

Exceed

fixed by

Govt.

Clause 48 :

The rates to be quoted by the contractor must be inclusive of sales tax /

VAT. No extra payment on this account will be made to the contractor.

Rate

inclusive

of Sales

Page 34: MAHARASHTRA JEEVAN PRADHIKARANmjp.maharashtra.etenders.in/tpoimages/mjp/tender/Tender...Maharashtra Jeevan Pradhikaran, such specifications with designs and drawings shall form a part

Contractor No. of Correction Executive Engineer

Tax/ VAT

Clause 49 :

In case of materials that remain surplus with the contractor from those

issued for the work contracted from the date of ascertainment of the

materials being surplus will be taken as the date of sale for the purpose

of sales tax and the sales tax will be recovered on such sale.

Sales Tax on

surplus

material.

Clause 50 :

The contractor shall employ at least 80 percent of the total number of

unskilled labour to be employed by him on the said work from out of

the persons ordinarily residing in the district in which site of the said

work is located. Provided; however, that if the required number of

unskilled labour from that district is not available, the contractor shall in

the first instance employ such number of persons as is available and

thereafter may with the previous permission in writing of the Executive

Engineer, in charge of the said work, obtain the rest of his requirement

of unskilled labour from outside the district.

Employment

of local

lobour.

Clause 51 :

The contractor shall pay the laboures skilled and unskilled according to

the wages prescribed by the minimum wages Act applicable to the area

in which the work of contractors labours engaged contractor is located.

Wages to be

paid to the

skilled &

unskilled by

the

Contractor.

52 Clause 52 :

All amounts whatsoever which the contractor is liable to pay to the

Pradhikaran in connection with the execution of the work including the

amount payable in respect of (i) materials and or stores supplied/issued

here under by Pradhikaran to the contractor (ii) Hire charges in respect

of heavy plant, machinery and equipment given on hire by Pradhikaran

to the contractor, for execution by him of the work and/or on which

advance have been paid by the Pradhikaran to the contractor shall be

deemed to be arrears of the land revenue and the Pradhikaran may

without prejudice to any other rights and remedies of the Pradhikaran

recover the same from the Contractor as arrears of land revenue.

53 Clause 53 :-

The successful tenders will be required to produce to the satisfaction of

the specified concerned authority a valid and consequentlicense issued

in favour under the provision of the contract labour ( Regulation and

Abolition ) Act 1970 before starting the work. On failure to do so, the

acceptance of tender should be liable to be withdrawn and also Earnest

Money / Security Deposit forefeited..

The contractor shall duly comply with all the provisions of the Contract

labour (Regulation and Abolition) Act, 1970 (37 of 1970) and The

Page 35: MAHARASHTRA JEEVAN PRADHIKARANmjp.maharashtra.etenders.in/tpoimages/mjp/tender/Tender...Maharashtra Jeevan Pradhikaran, such specifications with designs and drawings shall form a part

Contractor No. of Correction Executive Engineer

Maharashtra Contract Labour (Regulation and Abolition) Rules 1971 as

amended from time to time and all other relevant statutory provisions

concerning payment of wages particularly to workmen employed by the

contractor and working on the site of the work. In particular the

Contractor shall pay wages to each worker employed by him on the site

of the work at the rates prescribed under the Maharashtra contract

labour (Regulation and Abolition) Rules, 1971. If the contractor fails or

neglects to pay wages at the said rates or makes short payment and

Pradhikaran makes such payment of wages in full or the part thereof

less paid by the contractor as the case may be, the amount so paid by the

Pradhikaran to such workers shall be deemed to be arrears of land

revenue and the Pradhikaran shall be entitled to recover the same as

such from the Contractor or deduct the same from the amount payable

by the Pradhikaran to the contractor here under or from any other

amount/s payable to him by the Pradhikaran.

Clause 54 :-

Where the workers are required to work near machine and are liable to

accident they should not be allowed to wear loose clothes like Dhoti,

Jhabba etc

Clause 55 :

Provision of all applicable Indian Laws shall be treated as applicable for

this contract.

Clause 56 :

In view of the difficult position regarding the availability of the foreign

exchange, no foreign exchange will be released by the department for

the purchase of the plant and machinery required for the execution of

the work concerned.

Clause 57 :

The tendered rates shall be inclusive of all taxes, tax livable in respect

of works contract under the provisions of the Maharashtra Sales Tax on

transfer of property in goods involved in the execution of works

contract Act, 1985 (Maharashtra Act No .XIX of 1985). However the

works contract tax shall be deducted from the Contractor's Running

Account bills at the rates applicable as per rules in force and the same

shall be remitted in the Govt. treasury / Bank and no reimbursement in

this respect shall be made by the department.

Clause 58 :- (A) Anti-Malaria A other health services

(1) The anti-malaria health measures shall be taken as directed by

the Joint Director (Malaria and Filaria), Health Services, Pune.

(2) Contractor shall see that mosquitogenic conditions are not

created so as to keep vector population to minimum level.

Page 36: MAHARASHTRA JEEVAN PRADHIKARANmjp.maharashtra.etenders.in/tpoimages/mjp/tender/Tender...Maharashtra Jeevan Pradhikaran, such specifications with designs and drawings shall form a part

Contractor No. of Correction Executive Engineer

(3) Contractor shall carry out anti malarial measures in the area as

per guidelines prescribed under National Malaria Eradication

Programme and as directed by the Joint Director (M and F),

Health Services, Pune.

(4) In case of default in carrying out prescribed anti-malaria

measures resulting in increase in malaria incidence, contractor

shall be liable to pay to Government the amount spent by

Government on anti malaria measures to control the situation in

addition to fine.

(5) Relations with Public Authorities:

The contractor shall make sufficient arrangements for draining

away the village water as well as water coming from the bathing

and washing places and shall dispose off this water in such a

way as not to cause, any nuisance. He shall also keep the

premises clean by employing sufficient number of sweepers.

The contractor shall comply with all rules, regulations, bye-laws

and directions given from time to time by any local or public

authority in connection with this work and shall pay fees or

charge which are livable on him without any extra cost to

Government.

Clause 58 (B) :

Successful contractor will have to enter into an agreement in the form

specified by the Pradhikaran on a stamp paper of required amount as

per the rules in force. Stamp charges shall be borne by the Contractor

1) Receipts for payments made on account of any work, when executed

by a firm should also be signed by all the partners except where the

contractors are described in their tender as firm, in which case the

receipt shall be signed in the name of the firm by one of the partners, or

by some other person having authority to give effectual receipts of the

firm.

2) All works shall be measured net by standard measure and according

to the rules and customs of the MJP and in absence of such rules and

custom in MJP then as per rules and customs of P. W. Department of

Govt. of Maharashtra without reference to any local custom.

3) The measurements of work will be taken according to the

usual methods in use in the Maharashtra Jeevan Pradhikaran and no

proposals to adopt alternatives methods will be accepted. The Executive

Engineer's decision as to what is the usual method in use in the

Pradhikaran will be final.

Page 37: MAHARASHTRA JEEVAN PRADHIKARANmjp.maharashtra.etenders.in/tpoimages/mjp/tender/Tender...Maharashtra Jeevan Pradhikaran, such specifications with designs and drawings shall form a part

Contractor No. of Correction Executive Engineer

4) The contractor will have to construct shed, for storing

controlled and valuable materials issued to him under Schedule 'A' of

the agreement, at work site having double locking arrangement. The

materials will be taken for use in the presence of the Department person.

No materials will be allowed to be removed from the site of works.

5) The tendered rate shall be inclusive of all taxes, duties levies, cess

(including Sales Tax) as amended from time to time. No extra payment

on this account shall be made to the contractor.

Clause 59 : Price Variation Clause.

If during the operative period of the Contract as defined in condition (i)

below, there shall be any variation, in the Consumer Price Index (New

Series) for Industrial Workers for Mumbai Centre as per the Labour

Gazette published by the Commissioner of Labour, Government of

Maharashtra and/or in the whole-sale Price Index for all commodities

prepared by the Office of Economic Adviser, Ministry of Industry,

Government of India, or in the price of petrol/ oil and libricants and

major construction materials like bitumen, cement, steel, various types

of metal pipes etc., then subject to the other conditions mentioned

below, price adjustment on account of…..

1. Labour Component

2. Material Component

3. Petrol, Oil and Lubricants Component

4. Bitumen Component

5. HYSD & Mild Steel Component

6. Cement Component

7. C.I. & D.I. pipes component.

Calculated as per the formula hereinafter appearing, shall be made.

Apart from these, no other adjustments shall be made to the contract

price for any reasons whatsoever. Component percentage as given

below are as of the total cost of work put to tender. Total of Labour,

Material and POL components shall be 100 and other components shall

be as per actuals.

1. Labour Component – K1 (55%)

2. Material Component – K2 (40%)

3. POL Component – K3 (05%)

4. Bitumen Component Actual

5. HYSD & Mild Steel Component Actual

6. Cement Component Actual

7. C.I. & D.I. Pipe Component Actual

NOTE : If Cement, Steel, Bitument, C.I. & D.I. Pipes are

Price

variation

clause.

Page 38: MAHARASHTRA JEEVAN PRADHIKARANmjp.maharashtra.etenders.in/tpoimages/mjp/tender/Tender...Maharashtra Jeevan Pradhikaran, such specifications with designs and drawings shall form a part

Contractor No. of Correction Executive Engineer

supplied on Schedule”A”, then respective component shall not be

considered. Also if particular component is not relevant same shall be

deleted.

Star rates for material:

1. M.S. Plates : Rs.45,000/- per M.T.

2. Cement : Rs. 5,600/- per M.T.

3. Reinforcement : Rs.40,000/- per M.T.

1. Formula for Labour Component :

K1 L1 – Lo

V1 = 0.85 P -------------- x -----------------

100 Lo

Where,

V1 = Amount of price variation in Rupees to be Allowed for Labour component

P = Cost of work done during the quarter under consideration minus

The cost of Cement, HYSD and Mild Steel, bitumen, C.I. & D.I. Pipes

Calculated at the basic star rate as applicable for the tender, consumed during the

quarter under consideration.

K1= Percentage of labour component as indicated above.

Lo= Basic consumer price index for Mumbai central shall be average consumer

price index for the quarter preceding the month in which the last date prescribed

for receipt of tender falls.

L1= Average consumer price index for Mumbai centre for the quarter under

consideration.

2. Formula for Materials Component :

V2= 0.85 P K2 x M1 – Mo

100 Mo

Where,

V2= Amount of price variation in Rupees to be Allowed for Materials

component.

P= Same as worked out for labour component.

K2= Percentage of material component as indicated above.

Page 39: MAHARASHTRA JEEVAN PRADHIKARANmjp.maharashtra.etenders.in/tpoimages/mjp/tender/Tender...Maharashtra Jeevan Pradhikaran, such specifications with designs and drawings shall form a part

Contractor No. of Correction Executive Engineer

Mo= Basic wholesale price index shall be averave wholesale price index for the

quarter preceding the month in which to the last date prescribed for receipt

of tender, falls.

M1= Average wholesale price index during the quarter under consideration.

3. Formula for Petrol, Oil and Lubricant Component

K3 P1 – Po

V3= 0.85 P -------- x ---------------

100 Po

Where,

V3= Amount of price variation in Rupees to be Allowed for POL component.

P= Same as worked out for labour component.

K3= Percentage of petrol, oil and lubricant component

Po= Average price of HSD at Mumbai during the quarter preceding the month

in which the last date prescribed for receipt of tender, falls.

P1= Average price of HSD at Mumbai during the quarter under consideration.

4. Formula for Bitumen Component :

V4= QB (B1 – Bo)

V4= Amount of price variation in Rupees to be allowed for Bitumen

component.

QB= Quantity of Bitumen (Grade..) in metric tonnes used in the permanent

works and approved enabling works during the quarter under

consideration.

B1= Current, average ex-refinery price per metric tonne of Bitumen (Grade..)

under consideration including taxes (octroi, excise, sales tax) during the

quarter under consideration.

B0= Basic rate of Bitumen in rupees per metric tonne as considered for

working out value of P or average ex-refinery price in rupees per metric

ton including taxes (Octroi, excise, sales tax) for Bitumen for the grade of

bitumen under consideration prevailing quarter preceding the month in

which the last date prescribed for receipt of tender, falls, whichever is

higher.

Page 40: MAHARASHTRA JEEVAN PRADHIKARANmjp.maharashtra.etenders.in/tpoimages/mjp/tender/Tender...Maharashtra Jeevan Pradhikaran, such specifications with designs and drawings shall form a part

Contractor No. of Correction Executive Engineer

5. Formula for HYSD and Mild Steel component :

So (Sl1 – Slo )

V5 = ------------------------- x T

Slo

Where,

V5 = Amount of price variation in Rupees to be allowed for HYSD/ Mild Steel

component.

S0 = Basic rate of HYSD/ Mild steel in rupees per metric tonne as considered

for working out value of P

Sl1 = Average steel Index as per RBI Bulletin during the quarter under

consideration.

Sl0 = Average of steel Index as per RBI Bulletin for the quarter preceding the

month in which the last date prescribed for receipt of tender, falls.

T= Tonnage of steel used in the permanent works for quarter under

consideration.

6. Formula for Cement Component :

Co (Cl1 – Cl0)

V6 = ---------------------- x T

Cl0

Where,

V6 = Amount of price escalation in Rupees to be allowed for cement

component.

C0= Basic rate of cement in rupees per metric tonne as considered for working

out value of P

Cl1= Average cement Index as per RBI Bulletin during the quarter under

consideration.

Cl0= Average of cement Index as per RBI Bulletin for the quarter preceding the

month in which the last date prescribed for receipt of tender, falls.

T= Tonnage of cement used in the permanent works for quarter under

consideration.

Page 41: MAHARASHTRA JEEVAN PRADHIKARANmjp.maharashtra.etenders.in/tpoimages/mjp/tender/Tender...Maharashtra Jeevan Pradhikaran, such specifications with designs and drawings shall form a part

Contractor No. of Correction Executive Engineer

7. Formula for C.I. / D.I. pipe component

V7 = Qd(D1 – Do)

Where:

V7 = Amount of price escalation in rupees to be allowed for C.I. / D.I.

pipe components.

Do = Pig Iron basic price in rupee per tonne considered for working out

value of P.

D1 = Average Pig Iron price in rupees per tonne during the quarter under

consideration (published by IISCO).

Qd = Tonnage of C.I. / D.I. pipes used in the works during the quarter

under consideration.

i) This price variation clause shall be applicable to all contracts in B1/B2 &

C form but shall but shall not apply to price works. The price variation

shall be determined during each quarter as per formula given above in this

clause.

ii) The Price variation under this Clause shall not be payable for the extra

items required to be executed during the completion of the work and also

on the excess quantities of items, payable under the provisions of Clause

38/37 of the contract from B-1/ B-2 respectively. Since the rates payable

for extra items or the extra quantities under Clause 38/37 are to be fixed as

per current DSR or as mutually agreed to yearly revision till completion of

such work. In other words, when the completion/ execution of extra items

as well as extra quantities under Clause 38/37 of the contract from B-1/B-

2 extends beyond the operative date of the DSR then rates payable for the

same beyond the date shall be revised with reference to the current DSR

prevalent at that time on your to year basis or revised in accordance with

mutual agreement thereon as provided for in the Contract, whichever is

less.

iii) This clause is operative both ways, i.e. if the price variation as calculated

above is on the plus side, payment on account of the price variation shall

be allowed to the contractor and if it is on the negative side, the

Government shall be entitled to recover the same from the Contractor and

the amount shall be deductible from any amounts due and payable under

the contract.

iv) To the extent that full compensation for any rise or fall in costs to the

Contractor is not entirely covered by the provision of this or other clause

Page 42: MAHARASHTRA JEEVAN PRADHIKARANmjp.maharashtra.etenders.in/tpoimages/mjp/tender/Tender...Maharashtra Jeevan Pradhikaran, such specifications with designs and drawings shall form a part

Contractor No. of Correction Executive Engineer

in the contract, the unit rate and price included in the contracts shall be

deemed to include amounts to cover the contingency of such other actual

rise or in fall in cost.

v) Definition of quarter for calculation of escalation as per formula quarter

means the preceding immediate three months from the last date of receipt

of tender. The calendar month cannot be considered.

Note : The escalation payment will not be released to the contractor without prior

approval from the C.E. Engineer, MJP Water Management, Thane

Clause 60:

The contractor shall provide and maintain guards, guard rails, temporary bridge and

walkways, watermen headlights and danger signals illuminated from sunset to sunrise

and other necessary appliances and safeguards to protect the work ,life property, the

public excavation, equipment and materials barricades shall be substantial construction

and shall be painted such as to increase then visibility at night. For any accident arising

out of the neglect of above instructions, the contractor shall be bound to bear the

expenses of defence of every suit, action or other legal proceedings, at law that may be

brought by any person for injury sustained owing to neglect of the above precaution and

to pay all damages and costs which may be awarded in such suit, action or proceedings to

any such person on which may be with consent of the contractor paid in compromising

any claim by any such person.

Clause 61: (Insurance)

Contractors shall take out necessary Insurance Policy / Policies so as to provide

adequate insurance cover for execution of the awarded contract work from the Director

of Insurance, Maharashtra State, Mumbai - 51 only. Its postal address for

correspondence is "264, Ist Floor, MHADA, Opp. Kalanagar, Bandra (East), Mumbai -

400 051. Tel. No. 6438403 / Fax : 6438461 / 6438690). Insurance however, if the

contractor desire to effect insurance with the local office of any insurance company, the

same should be under the co-insurance-cum-servicing arrangements approved by the

Director of Insurance If the policy taken out by the contractor is not on co-insurance

basis (G.I.F. 60% and Insurance company 40%) the same will not be accepted and the

amount of premium calculated by the Director of Insurance will be recovered directly

from the amount payable to the contractors for the executed contract work which may

be noted

a) Loss of or damage to the Civil and Mechanical equipment's

supplied / installed including the materials such as pipes, valves

specials etc. brought on.

b) Loss of or damage to contractor’s equipment's including his

vehicles.

Page 43: MAHARASHTRA JEEVAN PRADHIKARANmjp.maharashtra.etenders.in/tpoimages/mjp/tender/Tender...Maharashtra Jeevan Pradhikaran, such specifications with designs and drawings shall form a part

Contractor No. of Correction Executive Engineer

c) Loss of or damage to property (except the works, Plant Material and

Equipment) in connection with the contractor. And ;

Personal injury or death due to vehicles of the contractor and / or due to any

accident that may arise at or around the site to the Contractor personal or to

the MJP staff or to any other person not connected with MJP/contractor.

1. Policies and certificates for insurance shall be delivered by the

Contractor to the Engineer for the Engineer's approval before the date of

actual starting of work. All such insurance shall provide for compensation

to be payable in the types of proportions of currencies required to rectify

the loss or damage incurred.

2. If the contractor does not produce any of the policies and certificates

required, the engineer may effect the insurance for which the contractor

should have produced the policies and certificates and recover the premiums it

has paid from payments otherwise due to the contractor or, if no payment is

due, the payment of the premiums shall be of debt due.

3. Alterations to the terms of insurance shall not be made without the

approval of the engineer.

4. The minimum insurance cover for loss and damages to physical, injury

and death shall be 10% of the contract cost per occurrence with number

of occurrences as 4 (four). After each occurrence the contractor shall

pay additional premium necessary so as to keep the insurance policy

valid always till the defect liability period is over.

5. No payment will be released to the contractor until the insurance

coverage with the Govt. insurance fund, Maharashtra State is

provided and unless the proof of insurance coverage is produced by the

contractor to the Engineer- in- charge.

Clause 62: (CSMC)

In case MJP decides to appoint a construction, supervision and management consultant for

supervising/ monitoring works under this contract, the civil / mechanical / electrical

contractor shall be liable to execute the work under the supervision of C.S.M.C. All

decisions regarding the work in such cases shall be taken by the C.S.M.C. on behalf of

MJ.P. and will be binding on the contractor.

In such cases the contractor will have to sign the agreement between the M.J.P. of

C.S.M.C. in token of acceptance of the C.S.M.C. as the sole supervisor of the works under

the agreement.

Page 44: MAHARASHTRA JEEVAN PRADHIKARANmjp.maharashtra.etenders.in/tpoimages/mjp/tender/Tender...Maharashtra Jeevan Pradhikaran, such specifications with designs and drawings shall form a part

Contractor No. of Correction Executive Engineer

Clause 63:

Royalty of Excavation:

During execution of work excavation is required to be carried out for various sub work

for which royalties required is to be paid by the contractor as per Clause 36.

During execution of work and till completion if the point of royalty is raised by Collector

office it will be soul responsibility of contractor to pay royalty charges / compensation if

any to concern. Until the certificate from the competent authority from Collector office,

regarding royalty charges is not submitted by the contractor final bill and security deposit

for such work will not be payable to the contractor.

Contractor Executive Engineer

M.J.P. Water Management Div., Virar

Page 45: MAHARASHTRA JEEVAN PRADHIKARANmjp.maharashtra.etenders.in/tpoimages/mjp/tender/Tender...Maharashtra Jeevan Pradhikaran, such specifications with designs and drawings shall form a part

Contractor No. of Correction Executive Engineer

MAHARASHTRA JEEVAN PRADHIKARAN MAHARASHTRA JEEVAN PRADHIKARAN WATER MANAGEMENT CIRCLE, NEW PANVEL

MAHARASHTRA JEEVAN PRADHIKARAN WATER MANAGEMENT DIVISION, VIRAR

Name of Work : Vasai-Virar Sub-Regional Water Supply Scheme

(Surya) stage-II Part-I.

Designing, Providing and constructing RCC ESR of

capacity 1.25 ML @ Tulinj, Nallasopara (E).

MATERIAL SCHEDULE “A”

Schedule showing the material to be supplied by M.J.P. for work contracted to be

executed and preliminary and ancilliary and rates at which they will be charged for:

Sr.

No.

Description Quantity Rate at which

the material will

be charged to the

contractor

Unit Place of

Delivery

1 2 3 4 5 6

--NIL--

Contractor Executive Engineer

M.J.P. Water Management Div., Virar

Page 46: MAHARASHTRA JEEVAN PRADHIKARANmjp.maharashtra.etenders.in/tpoimages/mjp/tender/Tender...Maharashtra Jeevan Pradhikaran, such specifications with designs and drawings shall form a part

Contractor No. of Correction Executive Engineer

MAHARASHTRA JEEVAN PRADHIKARAN MAHARASHTRA JEEVAN PRADHIKARAN WATER MANAGEMENT CIRCLE, NEW PANVEL

MAHARASHTRA JEEVAN PRADHIKARAN WATER MANAGEMENT DIVISION, VIRAR

Name of Work : Vasai-Virar Sub-Regional Water Supply Scheme

(Surya) stage-II Part-I.

Designing, Providing and constructing RCC ESR of

capacity 1.25 ML @ Tulinj, Nallasopara (E).

OBLIGATORY TECHNICAL CONDITIONS

1. The design of R.C.C. ESR / MBR / GSR shall be carried out by a

designer having minimum qualification of graduation in Civil

Engineering / Structural Engineering. He shall sign the design and affix

his name and stamp. The designer shall ascertain the bearing capacity on

site. He shall check the bottom slab reinforcement before casting. He

should check vertical wall reinforcement twice during execution and also

check the top slab reinforcement before casting. The necessary

certificate from designer for checking the above items shall be submitted

to the Executive Engineer prior to casting of structural member.

2. The design shall be carried out in conformity with following IS Codes

(latest revisions).

a) IS 456/2000

b) IS 3370 – Part I & IV (latest versions).

c) IS 875 – 1987

d) IS 11682 – 1985

e) IS 1893 – 1984 with inclusion of seismic zones as per latest circular.

f) IS 1786 – 1985 (or latest version) for cold worked steel high grade

deformed bars. (Tor steel of 415 grade and mild steel grade I shall only be

used).

g) IS 13920 / 1993 for ductile detailing, applicable for ESRs under seismic

zone III, IV and V (Recent editions of IS shall be referred).

h) B.S.I. publication S.P. 34 (S & T) 1987.

3. The free board shall be included in the depth of water for design purposes.

4. Minimum free board shall be 300 mm, measured below the soffit of the deepest

roof / beam.

5. Maximum water depth shall not exceed 5.0 m.

Page 47: MAHARASHTRA JEEVAN PRADHIKARANmjp.maharashtra.etenders.in/tpoimages/mjp/tender/Tender...Maharashtra Jeevan Pradhikaran, such specifications with designs and drawings shall form a part

Contractor No. of Correction Executive Engineer

6. Clear cover to reinforcement shall be provided as below:-

a) Footing / Raft 50 mm at bottom and sides and

40 mm at top

b) Columns 40 mm

c) Braces, beams, slab (bottom and roof)

vertical wall, gallery

25 mm

7. Minimum thickness of container members shall be as below:

a) Bottom slab and vertical wall 200 mm

b) Roof slab 120 mm

8. The design and casting of container members which includes bottom and

roof beams, bottom and roof slab, vertical wall gallery and internal

columns shall be done in M-25 grade of concrete.

9. PCC shall be in M-20 grade of concrete.

10. The staging shall be designed for ductile detailing as per IS 13920 /

1993.

11. The width of braces shall be maximum of the following in case of Earth

Quake Zone III and above.

a) 250 mm

b) 75% of column side (column diameter in case of circular column).

12. Width to depth ratio in case of braces shall preferably be more than 0.30.

13. Increase in permissible stresses in braces, for Ear th Quake / wind Force

design will not be allowed.

14. The maximum center to center vertical distance between braces shall be

6.0 m vertical. The joints of braces and columns, the links to the column

bars shall be tied properly and this shall be thoroughly checked before

concreting.

15. All members of container should be designed as uncracked section as per

I.S. 3370. Column should be designed by “Working stress method”: and

as per I.S. 456-2000. It can be checked by limit state method I.S. 11682-

1985 should be followed for design of staging. Minimum dia of column

should be 400 mm for staging and 200 mm for column inside container.

16. Brace at G.L. shall be provided without exception.

Page 48: MAHARASHTRA JEEVAN PRADHIKARANmjp.maharashtra.etenders.in/tpoimages/mjp/tender/Tender...Maharashtra Jeevan Pradhikaran, such specifications with designs and drawings shall form a part

Contractor No. of Correction Executive Engineer

17. Wherever annular raft is provided, the inside and outside width of raft

shall be provided in such a way that the center of gravity of upward

reaction shall coincide with center of column raft beams.

18. Uplift pressure (if any) on the foundation of structure should be

considered as per available water table at site in rainy season.

19. 20 mm thick cement plaster with C.M. 1:2 prop. With water proof

compound shall be provided to the container from inside (including roof

beams and roof slabs etc.)

20. The shape of container may be square or circular. Similarly the column

shape may also be square or circular.

21. The size of column (width or diameter) for staging shall not be less than

400 mm. columns, if required to be provided inside container, for

supporting roof ring beam / slab may be provided as per design

requirements, following minimum cover requirements. However the size

shall not be less than 200 x 200 mm (or 200 mm diameter).

22. Minimum diameter of main bars in the footing shall be 10 mm and clear

distance between reinforcing bars shall not be more than 180 mm.

23. Water density shall be taken as 1000 kg. / cum and live load on gallery

shall be considered as 300 kg. / sq.m. Minimum load of water proof

treatment on roof slabs shall be taken as 100 kg. / sq.m.

24. The diameter, weight per meter, tensile strength and minimum

elongation properties of steel, brought by the contractor shall be got

tested from the approved laboratory before using it. It shall be used only

when the test report indicates that the steel is in accordance with the IS

specifications and design presumptions.

25. Pipe Assembly:

a) The inlet, outlet, overflow and bypass piping shall be of D.I.D.F.

pipes as mentioned separately for each E.S.R. All flanges such as

duck foot bend bell mouth, tees, tail pieces for C.I.D.F. shall be

provided and fixed for inlet, outlet, overflow, bypass and washout

arrangement.

b) Spout type overflow arrangement shall not be allowed. Overflow

arrangement shall be from top to bottom as a vertical pipe

assembly with proper drainage arrangement.

c) The vertical pipe assembly and horizontal pipe line from duck

foot bend of vertical pipe upto a distance of 5 m beyond external

Page 49: MAHARASHTRA JEEVAN PRADHIKARANmjp.maharashtra.etenders.in/tpoimages/mjp/tender/Tender...Maharashtra Jeevan Pradhikaran, such specifications with designs and drawings shall form a part

Contractor No. of Correction Executive Engineer

face of outermost column. Bypass arrangement shall be in

D.I.D.F. pipes.

d) Duckfoot bends for inlet, outlet and overflow arrangements

individual columns with footings resting at foundation level of

ESR /GSR columns / raft shall be provided.

e) The manhole frame and covers, provided in the roof slab, shall be

of cast iron only. Mild steel covers shall not be allowed.

f) Lightening conductor, electronic / digital, water level indicator,

domed central ventilator and M.S. ladders / RCC staircase shall be

provided as per Department’s specifications.

g) Inlet, outlet bye-pass and scour valves with chambers shall be

provided. Chamber for overflow shall be provided.

26. MATERIAL: For Foundation, ACC Suraksha or its equivalent cement

should only be used.

(a) Cement: Only 43-grade cement shall be used conforming to IS-

8112 (latest version) specification, super plasticizer in the

proportion of 0.5% (0.25 kg/ cement bag of 50 kg.) should be

used.

(b) Steel : Reinforcement of Fe-415 C.T.D. bars conforming to I.S.

1786-1985 shall be used. Except for the reinforcement bars for

stirrups the minimum dia reinforcing bars shall be 10 mm. For

bottom slab and vertical wall and columns, it should not be less

than 12 mm.

(c) Centering: Centering should be designed by the contractor. The same

should be approved by the competent authority before construction. Only

steel / plywood centering shall be used.

(d) Following concrete grade should be used for various components of

E.S.R. / M.B.R.

a) Water Container - M-30

b) Staging - M-30

c) Foundation - M-30

d) P.C.C. - M-20

27. The R.C.C. design submitted by the contractor shall be got checked from

the nearest Govt. Engineering College / IIT / VJTI / VRCE / WCE for

which the scrutiny charges shall be borne by the contractor. The delay in

checking designs from third party as above shall be treated as delay on

the part of contractor for operation of tender clauses.

Page 50: MAHARASHTRA JEEVAN PRADHIKARANmjp.maharashtra.etenders.in/tpoimages/mjp/tender/Tender...Maharashtra Jeevan Pradhikaran, such specifications with designs and drawings shall form a part

Contractor No. of Correction Executive Engineer

28. Barricading shall be provided for each site till completion of the work.

29. Valves should be of make approved by M.J.P. Valves from castings out of cupola

furnace will not be accepted castings from induction furnace will only be

accepted.

30. The agency should carry out working survey from available permanent bench

mark and block contouring of the plot shall be done. The contour survey and

preparation of drawings is included in the contractors offer and no separate

payment shall be made for this.

31. The contractor should make his own arrangement for transportation of material

and labour considering the site condition including head load arrangement or

mechanical arrangement or approach road etc. no claims shall be entertained on

this account.

32. Suitable side drain arrangement to drain rain water should be made by the

contractor at no extra cost during the entire execution of the work.

33. The contractor shall take the trial bores at each site of ESR / MBR for

ascertaining the strata for designing foundation. In case of pile foundation, the

trial bores up to rock level need to be taken. The results of the trial bores must be

submitted to the competent authority of MJP for deciding the depth of proposed

piles prior to submission of R.C.C. designs of E.S.R. Only end bearing piles

resting on rocky strata are to be provided for foundation of E.S.R. The contractor

should determine depth of foundation for each site before submitting R.C.C.

design.

34. The offer should include clearing the site on completion of the work and the site

should be cleared off all the debris, balance un-used material such as aggregate,

sand, steel etc. as per the directions of Engineer-in-charge.

Contractor Executive Engineer

M.J.P. Water Management Div., Virar

Page 51: MAHARASHTRA JEEVAN PRADHIKARANmjp.maharashtra.etenders.in/tpoimages/mjp/tender/Tender...Maharashtra Jeevan Pradhikaran, such specifications with designs and drawings shall form a part

Contractor No. of Correction Executive Engineer

MAHARASHTRA JEEVAN PRADHIKARAN MAHARASHTRA JEEVAN PRADHIKARAN WATER MANAGEMENT CIRCLE, NEW PANVEL

MAHARASHTRA JEEVAN PRADHIKARAN WATER MANAGEMENT DIVISION, VIRAR

Name of Work : Vasai-Virar Sub-Regional Water Supply Scheme

(Surya) stage-II Part-I.

Designing, Providing and constructing RCC ESR of

capacity 1.25 ML @ Tulinj, Nallasopara (E).

GENERAL SPECIFICATION

SPECIFICATION FOR ELEVATED SERVICE RESERVOIRS / GROUND

SERVICE RESERVOIRS, DESIGN CRITERIA AND ASSUMPTIONS

DESIGN STANDARDS:

The structural design of the water tank shall conform to the following standard

specifications and code of practice IS:456 - code of practice of plain and reinforced

concrete. (latest edition).

IS : 3370 – code of practice for concrete (Part I to IV) structures for storage of liquids

(latest edition) IS-1893 criteria for Earth Quake resistance.

IS-875 (Revised – 1987) Part I – Dead Load

Part II – Imposed load

Part III – Wind Load

IS-11682-1985 Criteria for design of RCC staging for overhead

water tanks.

IS-13620-1993 Fusion bonded epoxy coated reinforcement bars

– specifications.

IS-13920-1993 Ductile detailing of RCC structures subject to

seismic forces.

DESIGN OF STRUCTURES:

The Indian standard (latest edition) on the date of tender shall be applicable to the design

of structure. On items not specifically covered by Indian Standard code of practice,

reference shall be made to relevant standard specifications. If some of the standards have

provisions on any items relating to design, the decision of the competent authority,

Maharashtra Jeevan Pradhikaran in such matters shall be final and binding.

WIND LOADING:

Provision shall be made in the design for basic Wind loading as per IS-875 – Part – III on

the exposed area of water tank and staging.

SEISMIC LOADING:

Provision for seismic loading for seismic zone IV should be made in designing G.S.R. /

E.S.R.s as per Indian Std. I.S. 1893 – Latest revision.

Page 52: MAHARASHTRA JEEVAN PRADHIKARANmjp.maharashtra.etenders.in/tpoimages/mjp/tender/Tender...Maharashtra Jeevan Pradhikaran, such specifications with designs and drawings shall form a part

Contractor No. of Correction Executive Engineer

PERMISSIBLE SAFE BEARING CAPACITY:

The strata is likely to vary from site to site. The tenderer is however advised to verify

actual strata before tendering and designing the structures. He should satisfy himself

about the bearing capacity of foundation at various sites and shall quote the offer and

design accordingly with due justification for assumption, for structural safety of structure

as a whole.

The bearing capacity of foundation under normal loading conditions is as given in the

table attached with obligatory conditions.

FREE BOARD:

Minimum free board required from soffit of deepest beam should not be less than 30 cm.

The tank foundation and other members shall be designed for water depth including free

board level.

PROCEDURE FOR CHECKING DETAILED CALCULATION AND WORKING

DRAWINGS:

Immediately on award of contract and no later than two weeks from the date of work

order, the tenderer shall supply six copies of contract drawings marked advance copy for

incorporating in the agreement. He shall therefore prepare at his own cost further detailed

working drawings with supplying design calculations and shall submit them within one

month from the date of work order for approval of the Superintending Engineer,

Maharashtra Jeevan Pradhikaran, Circle Thane. The design shall be got checked from

VJTI / IIT, Mumbai or any other Institute approved by M.J.P. as directed by

Superintending Engineer Expenditure for checking of R.C.C. designs by the above third

party shall be borne by the contractor. The R.C.C. design and drawing should be

submitted to third party through Superintending Engineer. One copy of accepted tender

should be submitted to third party for knowing tender conditions.

The comments of the Engineer/ Institute shall be complied with and modified corrected

design and drawings shall be resubmitted for approval within a fortnight of the issue of

corrected design and drawings. Only after all the comments have been fully complied

with all the corrections, the approval will be granted by the Institute and finally by the

Superintending Engineer, Maharashtra Jeevan Pradhikaran Circle Thane. One technical

person along with reference books shall be appointed to the office for facilitating

complete checking of design.

Reference books, literature referred to for design shall have to be produced on demand

for facilitating studying of design. Nine sets of working drawings and four sets of

approved design calculations shall then be supplied and these will be officially

authentically by the department.

The copies shall be distributed as under:-

Four copies of the approved drawings will be supplied to the field staff.

Page 53: MAHARASHTRA JEEVAN PRADHIKARANmjp.maharashtra.etenders.in/tpoimages/mjp/tender/Tender...Maharashtra Jeevan Pradhikaran, such specifications with designs and drawings shall form a part

Contractor No. of Correction Executive Engineer

One set of copies will be returned to the contractor for his record.

Two sets of drawings and two sets of design calculations will be retained by the

Superintending Engineer.

UNITS FOR DESIGN:

Design is SI units only should be given.

The design shall have no conditions. Any conditions or assumptions on which lump sum

offer is based shall be submitted by the financial repercussion and in case any conditions

or assumptions are not acceptable, the same shall be withdrawn before final

consideration.

The design shall ensure soundness, strength of structure and shall strictly confirm the

criteria stipulated herein.

The design shall be accompanied by preliminary but fairly detailed indicative drawings.

All the details such as depth of water, height of tank, dia. of tanks general arrangements

of staging and bracing shall be given in the drawing.

The tender offer shall be accompanied by an indication of quantities of steel (structural

and other separately) and cement required for his design.

For any deviation from the obligatory provisions and conditions the offer will be treated

as conditional and will be liable to be rejected summarily.

Eventhough the design submitted by contractor are generally approved by the competent

authority of the department the contractor will not be relieved of his contractual

obligation till completion of defect liability period. In case, if any damage/ failure either

during testing or after commissioning whether due to faulty design or defective

construction occurs, all repairs or reconstructions of the structure shall be carried out by

the contractor entirely at his risk and cost. No claim for such repairs/ reconstructions as a

result of damage failure will be entertained.

CONSTRUCTION PROGRAMME

The contractor shall furnish detailed programme of work within 15 days from issue of

acceptance letter. This programme shall include targets of various items, details and

adequacy of machinery deployment of labour structure of procurement of important

materials. The information should indicate proper planning by contractors to complete the

work in prescribed contract period. This should be in the form of PEPT-CPM diagram

showing all the activities involved such as construction programme of work should be

strictly adhered to. Further if the contractor will not adhere to execute the work as per

scheduled programme and if contractor unnecessarily delays the work, liquidated

damages will be recovered from the contractor at the rate decided by the Engineer-in-

charge and it will be maximum 10% of contract value.

Page 54: MAHARASHTRA JEEVAN PRADHIKARANmjp.maharashtra.etenders.in/tpoimages/mjp/tender/Tender...Maharashtra Jeevan Pradhikaran, such specifications with designs and drawings shall form a part

Contractor No. of Correction Executive Engineer

R.C.C. CAST IN SITU BORES PILING WORK

1. GENERAL:

Cast in situ R.C.C. piles shall be of the design and layout shown on the plan as

prepared by the patentee and approved by the Engineer. After the casing is

suitable to the required depth on the suitable hard strata or to rock, the

reinforcement cage shall be lowered into the in casing Cement concrete of the

specified quality is then poured into the casing and compacted and then casing

gradually withdrawn.

2. EQUIPMENTS:

The equipments will consists of heavy steel casing section with the screwed ends

for connections and various types of percussion or rotary boring tools for boring

and lifting the board materials and water if any from the casing or add

mechanically with the suitable machinery arrangement for driving the casing or

boring proceeds within it shall also be provided. The casing shall be of suitable

thickness, a sufficient strength and rigidity to permit driving with heavy hammers

and to prevent distortion due to soil pressures until filed with concrete.

DRIVING

The boring tool shall be centered at the exact pile location. Boring and driving shall then

proceed alternatiely till the appropriate strata is reached when the casing is being drien

care shall be taken to check that it is truly vertical. Sequence of boring and driving or vice

versa will depend upon the strata passed through. The item will cover boring and driving

the casing through all strata softer then rock. The contractor will not be entitle to any

compensation or extra rate if the depth to which pile are required to be driven are increase

or decrease.

Contractor will be responsible for any compensation that may have to be paid due to

injury to persons or damage to work and properly caused by this pile driving operation.

When the boring is done to satisfactory strata according to plan and approved by the

Engineer and casing filling driven to the required depth all loose material existing at the

bottom of the hole after completing the boring operation shall be removed before pouring

concrete.

Water may be used in the boring operation only to the extent absolutely necessary for

facilitating boring. All necessary steps shall be taken to prevent surface water from

entering the hole and all water which may have in filtrated into the holes shall be

removed before pouring concrete. If necessary the inside of the pile shall be inspected by

lowering light and it should be seen that any material like earth clay etc. sticking to the

casing is removed.

4. TOLERANCE:

Utmost care shall be taken to see that the pile shell is driven and plumbed as far as

possible unless remedial measure are necessary due to design equipment a shift of

8 cm. in position and cant of 2% of that height will be permitted. If the cant is

Page 55: MAHARASHTRA JEEVAN PRADHIKARANmjp.maharashtra.etenders.in/tpoimages/mjp/tender/Tender...Maharashtra Jeevan Pradhikaran, such specifications with designs and drawings shall form a part

Contractor No. of Correction Executive Engineer

more than 2% and shift more than 8 cm. appropriate remedial measure by way of

redesigning the pipe cap and/or driving additional pile as may be approved by the

Engineer shall be provided by the contractor without any extra cost.

5. REINFORCEMENT:

Steel reinforcement shall conform to specification No. B-10 from book of

standard specifications of Government of Maharashtra longitutional bars of the

required size shall be fabricated into cage with spirals or stirrups accurately to the

patentee approved by the Engineer. Placing of longitudinal bars may be lap. The

stirrups or spirals shall be tied to the longitudinal bar with 1.63 mm wire. The

longitudinal bar shall extend 60 mm over the top of the piles or as shown on the

piles for being connected to the steel of the pile cap or foundation footing. The

exposed length of reinforcements shal not be measured or paid after driving the

casing to the required depth. The cage of reinforcement bars shall be lowered into

the shell and held in such way that the cage remains truly in the direction of the

axis of the shell and with the designed cover of concrete all round during pouring

concrete. The reinforcement of the cage shall be got approved in writing by the

Engineer before placing it in the casing.

6. CONCRETE:

Cement concrete shall comply with specification No. B-6 from Book of standard

specifications” of Govt. of Maharashtra for ordinary Portland cement concrete

grade M-25, the maximum size of coarse aggregate shall be 20 mm. The

contractor will be responsible to see that all the materials to be used are of

specified quality and not damaged in storage. The inside of the casing shall be

cleaned if necessary before concrete is poured. As the concrete is to be pour in to

the casing sufficient water to allow flowof concrete shall be provided. Incase the

surrounding area is dry, extra water absorbed from the concrete by the ground to

be made upto the amount of extra water will be decided by the Engineer.

Surrounding area shall also be well watered for atleast 6 hour before concrete and

kept well watered for 3 days. In water logged ground care shall be taken to inspect

that the soundness of concrete is not affected by sub soil water, when the concrete

is being poured compaction shall be made by approved means. The bottom of the

shell be maintained not less than 30 cm below the top of the concrete during

withdrawal of casing and pouring operation unless otherwise permitted by the

Engineer. Concrete shall be placed in one continuous operation from the bottom

of the pile cap and shaft be carried out in such a manner as to avoid segregation. If

water is met with it shall be removed. If it is impossible to remove it concrete

shall be laid by tremis. All the piles shall be cast to level previously fixed and any

extra length of pile shall be cut carefully by chiseling in such away that no

damage result to the piles itself. The top of the pile shall be dressed to plain

surface. Both these operation when necessary will be carried out by the contractor

at his own cost.

7. DEFECTIVE PILES:

If the cant and shift are more than permissible, if concrete is of poor quality the

load test is unsatisfactory or that any defect which in the opinion of the Engineer

Page 56: MAHARASHTRA JEEVAN PRADHIKARANmjp.maharashtra.etenders.in/tpoimages/mjp/tender/Tender...Maharashtra Jeevan Pradhikaran, such specifications with designs and drawings shall form a part

Contractor No. of Correction Executive Engineer

will affect strength or life of the pile, will be rejected or the following other

corrective method approved by the Engineer shall be adopted for the pile in

question at the contractor’s cost.

A. One or more additional piles sallbe cast adjacent to the defective pile and

so arrangedas to take the design load.

B. The pile cap or footing shall be redesigned and extended and properly

embedded in the pile to take to the designed load.

8. TEST OF CONCRETE:

One test of three 15 cm (about 6”) cubes shall be made for concrete poured on the

first day and there after one for every fifteen piles cast or one for each week’s

operation whichever is more. The age of test shall be 28 days but 7 days test may

be used if the relation between the strength at 28 days and 7 days is established by

sufficient number of test. These cubes shall be got tested from an approved

laboratory. All the expenses for materials moulds labours transport test etc. shall

be borne by the contractor. If any test cube result shows the strength of concrete

below the minimum specified, the piles represented by the sample shall be liable

to be rejected.

9. LOAD TEST:

Load test shall be carried out on the piles indicated by the Engineer. They shall

generally be about 1 percent of the total number of piles subject to minimum of 1

pile for each ESR. The load test shall be carried out according to specification No.

B-17.

If the tests are not satisfactory the piles may be rejected or it is possible to adopt

corrective measures by driving additional piles and redesigning the pile cap in the

opinion of engineer such measures shall be provided by the contractor without

any extra cost to the department.

10. ITEM TO INCLUDE:

A. All labour, materials, use of equipment such as casing, boring and driving

equipment, providing concrete, compaction, reinforcement and withdrawal

of casing including dewatering.

B. Compensation for any injury persons and damage to property due to

operations of piles driving.

C. Test to concrete

D. Correction of defects if any during load tests.

Page 57: MAHARASHTRA JEEVAN PRADHIKARANmjp.maharashtra.etenders.in/tpoimages/mjp/tender/Tender...Maharashtra Jeevan Pradhikaran, such specifications with designs and drawings shall form a part

Contractor No. of Correction Executive Engineer

CEMENT CONCRETE:

The Contractor shall make field arrangement for testing of all materials for cement

concrete i.e. slump test, bulkage test, compression test, etc. The concrete cube moulds 3

Nos. of 15 x 15 x 15 cm size shall be kept at site during concreting operation, one set of

six 15 cm (about 6”) cubes shall be prepared from the concrete to be used in work for

compression test on the first three days operation and thereafter, for every 60 cubic meter

of concrete or three days work whichever is less. If source of aggregate, grading is

changed one set of 6 test cubes shal be taken for each changed batch 3 cubes shall be

tested for test at 7 days age and 3 at 28 days in at Govt. laboratory or at any approved

laboratory. All the testing of materials will be borne by the Contractor. The entire

responsible of the testing of materials will be borne by the Contractor.

Mixing of concrete shallbe done with concrete mixer only.

For providing Electric wiring duct tubes of the required diameter and length shall be

provided through walls, beams, and floors, slabs as and when directed without any extra

cost.

a) The contractor will make his own arrangement for raising all materials, tools etc.

required for the work.

b) No extra charges for the carriage of water will be allowed.

c) The rates for all items are also inclusive of all charges such as carting, lifting etc.

no extra payment for any lead and lifts will be paid for any item.

d) The contractor should not be sub-leted without written permission of the

Engineer-in-charge.

e) The conditions in the tender notice will be binding on the Contractor and the

Tender Notice will form a part of agreement.

REQUIREMENT OF STRENGTH OF CONCRETE:

i) Controlled Concrete:

Full payment shall be made when 80% of the test cube results are equal to and

above the minimum specified strength and the remaining 20% of the results above

80% of the specified strength.

ii) Ordinary Concrete:

Full payment shall be made when 75% of the cube results are equal and above the

specified strength and the remaining 25% of the results are above 75% of

specified strength.

Cases failing outside the limit shall be examined by the Engineer-in-charge on

merits in each case.

FUSION BONDED EPOXY COATED REINFORCING BARS –

SPECIFICATIONS:

1. COATING MATERIALS:

The coating material shall meet the requirements specified as per I.S.

Page 58: MAHARASHTRA JEEVAN PRADHIKARANmjp.maharashtra.etenders.in/tpoimages/mjp/tender/Tender...Maharashtra Jeevan Pradhikaran, such specifications with designs and drawings shall form a part

Contractor No. of Correction Executive Engineer

The patching or repairing material or both shall be compatible with the coating,

insert in concrete and feasible for repairs all the coating plant or in the field. This

material shall be approved by the purchaser prior to use. The patching or repair

shall be performed in accordance with the recommendation of the material

manufacturer.

2. REINFORCING STEEL:

Steel reinforcing bars to be coated shall conform to IS 1786:1985.

3. SURFACE PREPARATION:

The surface of the steel reinforcing bars to be coated shall be cleaned by abrasive

blast cleaning to near white metal. The surface profile shall be free from mill

scale, rust and foreign matter when viewed under well-lit conditions.

The coating shall be applied to the cleaned surface as soon as possible after

cleaning. Any formation of rust blooms on the cleaned bars are to be removed by

blast cleaning before application of the coating. However, in no case shall the

coating be delayed more than eight hours after cleaning unless otherwise

permitted by the purchaser.

4. APPLICATION OF COATING:

The coating shall be applied as an electro statically charged dry powder sprayed

on to the grounded steel bar using an electrostatic spray gun. The powder may be

applied to either a hot or cold bar. The coated bar shall be given a thermal

treatment specified by the manufacturer of the epoxy resin which will provide a

fully cured finish coating. Temperature shall be controlled as recommended by

the manufacturer of the coating to ensure a workman like job without blistering or

other defects.

5. REQUIREMENTS OF COATED BARS:

Coating Thickness:

For acceptance purposes atleast 90 percent of all coating thickness measurements

shall be 0-1 mm to 0-3 mm after curing. The coating thickness limits do not apply

to patched areas. A minimum of 15 measurements shall be taken approximately

evenly spaced along each side of the test bar. At least 90 percent of these

measurement shall be within the specified limits.

NOTE : By mutual agreement between the purchaser and the manufacturer, thicker

coating may be accepted where the bars are not to be bent on worked after the coating has

been applied.

CONTINUITY OF COATING:

The coating shall be visually inspected after curing for continuity of the coating and shall

be free from holes, voids, contamination, cracks and damaged areas discernible to the

unaided eye. In addition, there shall be not more than an average of two holidays per 300

mm when tested in accordance with 8.2.

Page 59: MAHARASHTRA JEEVAN PRADHIKARANmjp.maharashtra.etenders.in/tpoimages/mjp/tender/Tender...Maharashtra Jeevan Pradhikaran, such specifications with designs and drawings shall form a part

Contractor No. of Correction Executive Engineer

Note: Holiday means a pinhole not discernible to the unaided eye.

ADHESION:

The adhesion of coating shall be evaluated on a representative number of bars selected in

accordance with 9.4 from each production lot. No visible cracks or disbanding in the

coating on the outside radius shall be allowed when tested in accordance with 8.3.

6. TEST METHODS:

The thickness of the coating shall be measured on the body of reinforcing bar

between deformations and ribs or both, on a straight length. Non-destructive

coating thickness measurements using magnetic gauges shall be used.

Pencil type pull-off gauges which require the operator to observe the reading at

the instant the magnet is pulled from the surface and do not hold shims tightly

against the steel plate during calibration are not recommended for use.

Gauge calibration with shims shall be performed on a smooth, clean, low-carbon

steel plate (at least 75 x 75 x 13 mm) rather than on a clean reinforcing bar.

A correction factor defining the effect of the bar preparation process shall be

obtained as the difference between (a) the average of the 10 gauge reading on a

cleaned but uncoated reinforcing bar of the size and lot being coated and (b) the

average of 5 gauge readings on a smooth mild steel plate. This correction factor

shall then be subtracted from all subsequent gauge readings on coated bars.

Fixed probe gauges shall be checked to ensure that the force generated by the

spring loaded probe housing is sufficient to ensure intimate contact between the

probe housing is sufficient to ensure intimate contact between the probe tip and

the coating on the curved bar surface if intimate contact does not result it will be

necessary to remove the probe housing and utilize hand-pressure to obtain valid

indicated thicknesses.

HOLIDAYS

A 67.5 volts holiday detector shall be used in accordance with the detector manufacturers

instructions. The detector may be an in line DC detector or a hand held DC detector.

ADHESION OF COATING:

The adhesion of the coating shall be evaluated by bending production coated bars 120

degrees (after rebound) around a mandrel of size as prescribed in Table 1. The bend test

shall be made at a uniform rate and shall take upto 90 seconds to complete. The two

longitudinal deformations shall be placed in a plane perpendicular to the mandrel radius

and the test specimen shall be at thermal equilibrium between 25o and 35

oC

NOTE: The fracture partial failure of steel reinforcing bar in the bend test for adhesion of

coating shall not be considered as an adhesion failure of the coating.

Table 1 Mandrel Diameter for Bend Test Requirements:

Page 60: MAHARASHTRA JEEVAN PRADHIKARANmjp.maharashtra.etenders.in/tpoimages/mjp/tender/Tender...Maharashtra Jeevan Pradhikaran, such specifications with designs and drawings shall form a part

Contractor No. of Correction Executive Engineer

(Clause 8.3)

Bar Diameter (mm) Mandrel Diameter (mm)

(1) (2)

6 60

8 80

10 100

12 100

16 125

18 150

20 150

22 200

25 200

28 2325

32 280

36 280

40 400

45 450

50 500

7. FREQUENCY TEST:

Coating thickness shall be tested at a frequency of not less than one full length bar

every twenty bars for each size.

Continuity of coating shall be determined by testing one full length bar in every

twenty bars for each size.

Coating thickness over the whole of the coated bar section shall be determined by

sectioning and examining one bar in every twenty tones for each size.

For testing adhesion of coating, samples shall be selected from each size

according to the frequency given below:

Nominal size of Bar (mm) No. of Samples

Upto 16 1 for every 1 tonnes

Above 16 and upto 25 1 for every 2 tonnes

Above 25 1 for every 4 tonnes

8. RETEST:

If the specimen for coating thickness orfor adhesion of coating fails to meet the

specified requirements twice the number of samples originally selected shallbe

tested for each failure test. If the results of these retests meet the specified

requirements the coated bar represented by the samples shall be accepted.

9. HANDLING AND IDENTIFICATION:

All systems for handling coated bars shall have padded contact areas all bundling

bands shall be padded or suitable banding shall be used to prevent damage to the

coating. All bundles of coated bars shall be lifted with a strong back, spreader bar,

multiple supports, or a platform bridge to prevent bar-to-bar abrasion from sags in

the bundles of coated bars. The bars or bundles shall not be dropped or dragged.

The identification of all reinforcing bars shall be maintained throughout the

fabrication and coating processes to the point of shipment.

Page 61: MAHARASHTRA JEEVAN PRADHIKARANmjp.maharashtra.etenders.in/tpoimages/mjp/tender/Tender...Maharashtra Jeevan Pradhikaran, such specifications with designs and drawings shall form a part

Contractor No. of Correction Executive Engineer

10. INSPECTION:

All tests and inspection shall be made at the place of manufacture prior to

shipment, unless otherwise specified.

PERMISSIBLE COATING DAMAGE AND REPAIR AFTER COATING

APPLICATION:

Coating damage due to fabrication and handling need not be repaired in case where the

damages area is 40 mm2 or smaller.

All damaged areas larger than 40 mm2 shall be repaired with patching material.

Maximum amount of damage shall not exceed 2 percent of the surface area of each bar

(total of damage in 13.1 and 13.2)

Patching shall be done in accordance with the patching material manufacturer’s

recommendations.

12. REJECTION:

Coated bars represented by the samples that do not meet the requirements of this

specification shall be rejected. By mutual agreement between the purchaser and

the manufacturer, such bar may be stripped of coating, recleaned, re-coated, and

resubmitted for acceptance test in accordance with the requirements of the

specification.

MANUFACTURER’S CERTIFICATE:

13. If requested by the purchaser, the manufacturer shall furnish,at the time of

shipment, a written certificate that the coated reinforcing bars meet the

requirements of this specification.

14. IDENTIFICATION AND MARKING

The manufacturer or supplier shall mark the bars in such a way that all finished

bars can be traced to the cast from which they are made or the original

identification mark of the bars.

Each bundles containing the bars may also be suitably marked with the Standard

Mark in which case the concerned test certificate shall also bear the Standard

Mark.

For each bundle of bars a tag shall be attached indicating the Cast No. /Lot No.

grade and size of the bars.

Contractor Executive Engineer

M.J.P. Water Management Div., Virar

Page 62: MAHARASHTRA JEEVAN PRADHIKARANmjp.maharashtra.etenders.in/tpoimages/mjp/tender/Tender...Maharashtra Jeevan Pradhikaran, such specifications with designs and drawings shall form a part

Contractor No. of Correction Executive Engineer

MAHARASHTRA JEEVAN PRADHIKARAN MAHARASHTRA JEEVAN PRADHIKARAN WATER MANAGEMENT CIRCLE, NEW PANVEL

MAHARASHTRA JEEVAN PRADHIKARAN WATER MANAGEMENT DIVISION, VIRAR

Name of Work : Vasai-Virar Sub-Regional Water Supply Scheme

(Surya) stage-II Part-I.

Designing, Providing and constructing RCC ESR of

capacity 1.25 ML @ Tulinj, Nallasopara (E).

ADDITIONAL CONDITIONS OF CONTRACT

1. Receipts for payments made on account of any work, when executed by a

firm should also be signed by all the partners except where the contractors

are described in their tender as firm, in which case the receipt shall be signed

in the name of the firm by one of the partners, or by some other person

having authority to give effectual receipts of the firm.

2. All work shall be measured net by standard measure and according to the

rules and customs of the MJP and in absence of such rules and customs of

P.W. Department of Govt. of Maharashtra without reference to any local

custom.

3. The measurements of work will be taken according to the usual methods in

use in the Maharashtra Jeevan Pradhikaran and no proposals to adopt

alternative methods will be accepted. The Executive Engineer’s decision as

to what is the usual method in use in the Pradhikaran will be final.

4. The accepted tender rates shall be treated for the completed item of work, to

cover the item wording specified in the Schedule B and also to cover the

specifications mentioned in the contract and the rate shall also be inclusive of

all incidentals charges including leads and lifts involved for materials and

labour required water for construction purposes, including curing, hydraulic

testing etc.. No payment on any such account shall be admissible to the

contractor under this contract.

5. The submission of tender of the contractor shall be treated as in-

controvertible proof of the contractor having visited all the sites of the work

under this contract and that of obtaining necessary information about all local

conditions, sites, quarries, means of accesses, nature of sub-soils conditions,

source and availability of required materials and labour and arrangement

required for their transport and storage, difficulties if any required to be

overcame during execution and trial run period, weather conditions etc. No

extra payment over accepted tender rates shall be admissible on these

accounts or on account of any similar other grounds.

6. The contractor shall not sell or otherwise dispose off or remove except for

the purpose of this contract, the rubble stone metal, sand or other material

which may be obtained from any excavation made for the purpose of the

Page 63: MAHARASHTRA JEEVAN PRADHIKARANmjp.maharashtra.etenders.in/tpoimages/mjp/tender/Tender...Maharashtra Jeevan Pradhikaran, such specifications with designs and drawings shall form a part

Contractor No. of Correction Executive Engineer

contract. All such material shall be MJP’s property and shall be dispose off

in the manner and at place as may be directed by the Engineer-in-charge.

Contractor with the permission of the Engineer-in-charge in writing and

when directed by him, use any of the material free of cost.

7. The contractor shall make his own arrangements for obtaining rubble,

khandki, metal, sand murum etc. from Government or private quarry.

Application of the contractor for the reasonable area of Government land

required for this purpose can be recommended to Revenue authorities

without any guarantee of making the land for quarry available.

8. The contractor shall provide all labours, skilled as well as unskilled, pegs,

line strings , side rails (wooden as well as steel etc.),as and when required as

per approved design and make available such other material for lining out,

setting out, checking of work, taking measurements, testing of hydraulic and

other structures without any payments by the MJP to him. He will also

provide proper approach and access to all his works and stores without any

extra cost over his tendered rates for the items to be inspected.

Contractor Executive Engineer

M.J.P. Water Management Div., Virar

Page 64: MAHARASHTRA JEEVAN PRADHIKARANmjp.maharashtra.etenders.in/tpoimages/mjp/tender/Tender...Maharashtra Jeevan Pradhikaran, such specifications with designs and drawings shall form a part

Contractor No. of Correction Executive Engineer

MAHARASHTRA JEEVAN PRADHIKARAN MAHARASHTRA JEEVAN PRADHIKARAN WATER MANAGEMENT CIRCLE, NEW PANVEL

MAHARASHTRA JEEVAN PRADHIKARAN WATER MANAGEMENT DIVISION, VIRAR

Name of Work : Vasai-Virar Sub-Regional Water Supply Scheme

(Surya) stage-II Part-I.

Designing, Providing and constructing RCC ESR of

capacity 1.25 ML @ Tulinj, Nallasopara (E).

WORK AND SITE CONDITIONS

1. LAND REQUIRED FOR CONSTRUCTION:

The contractor has to make his own arrangement for obtaining the land required

for use as construction yard, and office area both for the contractor and the M.J.P.

This land can be obtained either on rental basis or by purchase directly from the

owner shall remain his property. This land will be leveled up by the contractor at

his cost as per actual requirements. Contractor shall make necessary arrangements

at his own cost for the required foundations for structure including pile

foundation.

2. POWER:

The contractor swill have to make his own arrangement for obtaining necessary

power supply from MSEB, MJP will however extend possible co-operation to the

contractor by way of writing letters, issues f certificates (if possible) etc. for

facilitating the contractor to get electrical power supply from MSEB. No financial

or other liability will rest on the MJP. In case electric supply is not made available

by MSEB. Then the contractor will have to arrange for diesel generating sets

without any extra cost. The contractor will have to make all arrangements for

distributing electricity beyond this point both for work site and office areas

including the department office.

All writing and methods of construction for overload distribution lines and other

lines should be in accordance with the Indian electricity Act, 1910. The

Contractor should manage his work considering these probable electrical failures

and no extra claim will be admissible on this account.

Contractor will not be entitled to any claim arising out of power supply failures.

All rules as per latest electricity acts shall be applicable strictly.

The layout and methods of laying the lines and wiring shall have prior approval of

the Engineer.

The Contractor shall be and remain answerable and liable for any loss or damage

or injury to any person or any property of M.J.P. or others caused by or arising

from the failure of observance of Indian electricity Act, 1910 and Indian

Electricity Rules 1956. The contractor shall not claim any extra payment to

interruption in supply.

Page 65: MAHARASHTRA JEEVAN PRADHIKARANmjp.maharashtra.etenders.in/tpoimages/mjp/tender/Tender...Maharashtra Jeevan Pradhikaran, such specifications with designs and drawings shall form a part

Contractor No. of Correction Executive Engineer

3. WATER SUPPLY:

The Contractor will have to make his own arrangement, for water required during

construction of entire structure as well as for rendering water tightness test of E.S.R.

4. TELEPHONE:

The Contractor will have to make his own arrangement. The MJP will have

however, assist in this case, only to the extent of giving necessary certificate and

recommendary letter to Telephone Department, subject to the condition that no

financial or other liability will rest with the MJP. The contractor shall bear the full

charges as levied by the Department as also the monthly rental etc. no claims of

any sort on this account will be entertained.

PAYMENT CONDITIONS FOR E.S.R.’s

The tentative schedule for break of stagewise payment of each E.S.R. is given below:

Sr.No. Stage Completed Payment

1. Submission and approval of design excavation and P.C.C.

for foundation leveling course

10%

2. Footing and columns or pile foundations upto G.L. 10%

3. Half staging height above G.L. 10%

4. Full staging height 10%

5. Centering for bottom slab and beam and gallery etc.

20% Laying of complete steel for bottom slab, beam and gallery

etc.

Concreting of bottom slab and beam and gallery

6. Vertical wall-full height 10%

7. Roof slab 5%

8. Inlet, outlet, washout, byepass and overflow pipes, specials,

valves and accessories, providing fixing etc. complete.

10%

9. Inside plaster and ladder fixing and epoxy painting from

inside.

5%

10. Railing, water level indicator, lightening conductor and

ventilator.

5%

11. Finishing, cement painting, BB Masonry chambers and site

clearance etc. complete.

5%

Total 100%

NOTE: The above schedule of payment is tentative contractors should submit his

schedule to Superintending Engineer for approval. After approval to such schedule the

payment at various stages of works will be made.

Contractor Executive Engineer

M.J.P. Water Management Div., Virar

Page 66: MAHARASHTRA JEEVAN PRADHIKARANmjp.maharashtra.etenders.in/tpoimages/mjp/tender/Tender...Maharashtra Jeevan Pradhikaran, such specifications with designs and drawings shall form a part

Contractor No. of Correction Executive Engineer

MAHARASHTRA JEEVAN PRADHIKARAN MAHARASHTRA JEEVAN PRADHIKARAN WATER MANAGEMENT CIRCLE, NEW PANVEL

MAHARASHTRA JEEVAN PRADHIKARAN WATER MANAGEMENT DIVISION, VIRAR

Name of Work : Vasai-Virar Sub-Regional Water Supply Scheme

(Surya) stage-II Part-I.

Designing, Providing and constructing RCC ESR of

capacity 1.25 ML @ Tulinj, Nallasopara (E).

DETAILED SPECIFICATIONS FOR E.S.R. / G.S.R.

CLEARING VEGETATION ETC.:

The Contractor shall clear site of work of all grass, shrubs, trees, stems, rubbish etc.

at his own cost before start of the work and after every monsoon till the defect

liability period. The cleared grass, trees etc. shall be disposed off by the contractor

as directed by the Engineer-in-charge.

All useful timber shall be loaded, transported, unloaded and stacked at a place as

directed by Engineer-in-charge without any extra cost.

Rules and Regulations of the forest department wherever applicable shall be strictly

followed by the Contractor.

The Contractor shall clear the site of all rubbish building materials, debris,

excavated materials etc. and restore the site neat, clean and tidy condition to the full

satisfaction of the Engineer.

CONTRACTOR’S RESPONSIBILITY:

The contractor shall carefully examine the site and make all inspections necessary in

order to determine the full extent of the work required to make the completed work

conform to the drawings and specifications. The contractor shall satisfy himself as

to the nature and location of the work conditions, the conformation and condition of

the existing ground surface. The contractor shall satisfy himself as to the character,

quality and quantity of surface and sub-surface materials or obstacles or utilities to

be encountered. Any inaccuracies or discrepancies between the actual field

conditions and the drawings or between the drawings and specifications must be

brought to the Engineer’s attention in order to clarify the exact nature of the work to

be performed.

SAFETY:

The contractor shall familiarize himself with and shall at all times conform to all

regulations on construction safety and trench construction safety in force in the state

of Maharashtra in India.

QUALITY ASSURANCE

A) BY CONTRACTOR:

The contractor shall exercise due care to assure procurement storage and

placement of materials from site or off site sources which will comply with

Page 67: MAHARASHTRA JEEVAN PRADHIKARANmjp.maharashtra.etenders.in/tpoimages/mjp/tender/Tender...Maharashtra Jeevan Pradhikaran, such specifications with designs and drawings shall form a part

Contractor No. of Correction Executive Engineer

the requirements, specifications and standards and cost such tests and

inspections as may desire performed by qualified personnel or independent

specialist testing services for the determination of soil properties and for the

proper control of the works.

B) BY ENGINEER:

The Engineer, through the project representative will be the on-site judge of

the acceptability of the works done, based on such observations and tests he

may require to perform.

C) BY ORDER:

The Owner may provide specialist inspection and testing by independent

testing services, engaged and paid for by the owner.

INSPECTION:

A) Observation and compaction tests may be made by the Engineer during the

filling and compacting operations so as to monitor and check the control

being exercised by the contractor in constructing the full in accordance with

these specifications. If the compacted fill is found unsuitable, the Engineer

may order to complete removal of the fill and the reconstruction hereof in

accordance with the specifications.

B) These tests by the Engineer in no way absolves the contractor of his

obligations in having proper and sufficiently frequent tests carried out and in

exercising control over the performance of his work.

EXCAVATION:

1. SITE PREPARATION

Site preparation shall include, within the boundaries of the work as shown on

the place the grubbing, stripping and removal of all vegetation, organic

material, and other unsuitable excess material areas which will be under fills

shall be cleared and grubbed to a depth of 12 cm or sufficiently deep to

remove large roots, loose rocks, and other unsuitable materials as determined

by the Engineer. These materials shall become the property of the M.J.P. and

shall be removed from the premises. The materials pronounced useful by the

Engineer will be conveyed and properly stacked as directed within specified

lead.

(A) All rock foundation and abutment surfaces shall be cleared of all loose

materials by hand or other effective means and shall be free of standing

water when fill is placed. Fill immediately adjacent to such rock foundations

or not accessible with large compaction equipment shall be compacted to the

specified density by means of hand tamping or manually directed power

tampers or plate vibrators.

Page 68: MAHARASHTRA JEEVAN PRADHIKARANmjp.maharashtra.etenders.in/tpoimages/mjp/tender/Tender...Maharashtra Jeevan Pradhikaran, such specifications with designs and drawings shall form a part

Contractor No. of Correction Executive Engineer

(B) Where ordered by the Engineer top soil shall be stripped to such depths and

over such areas as a separate operation prior to any further excavation which

may be required. Topsoil shall be stored to re-use.

2. SITE GRADING:

After all unsuitable material has been removed from the site, the existing

surface shall be excavated or filled to the elevations and slopes and

dimensions indicated on the drawings or as directed by the Engineer and the

Contractor shall perform all operations related thereto. It will be

responsibility of contractor to install substantial reference marks bench

marks etc. and maintain them in position as long as required. Road and

drainage work required within the property limits at each site shall be

required as part of the site grading.

3. EXCAVATION:

The contractor shall excavate all materials of whatever nature encountered to

lines levels, curves and grades shown on the drawing. After completion of

this excavation and before and further work is done the Engineer will

examine the sub-grade.

A) The contractor shall notify the Engineer before starting excavation to enable

him to take cross sectional L-sectional levels for purposes of measurement

before ground is disturbed. The contractor may be required to carry out

excavation 3 m deeper than shown on the drg. And extra lift rate shall be

payable to the contractor basic rate of excavation being same.

B) The entire area within the limits of earthwork as indicated shall be

constructed to the lines, grades, elevations, slopes and cross sections

indicated on the drawings with added allowance for thickness of free

draining fills or other specials materials such as clay where required. Slopes

and drainage feature shall present a neat, uniform appearance upon

completion of the work and shall be approved by the Engineer. Excavated

materials meeting the requirements of fill materials may be conserved for

subsequent use or placed as earth fill immediately after excavation provided

the Engineer gives his approval large rocks unacceptable as earth fill material

may be stockpiled for use as rip rap where required. The suitability of all

excavated materials for specific purposes shall be determined by the

Engineer the contractor shall not waste or otherwise dispose of suitable

excavated materials. All excavations shall be performed under the limitations

and requirements set out in this specification pertaining to control of water

content.

FOSSIL ETC.:

All fossils, relics, coins, minerals and any other items of archeological importance

found in excavation or dismantling shall be handed over to the Engineer’s

Page 69: MAHARASHTRA JEEVAN PRADHIKARANmjp.maharashtra.etenders.in/tpoimages/mjp/tender/Tender...Maharashtra Jeevan Pradhikaran, such specifications with designs and drawings shall form a part

Contractor No. of Correction Executive Engineer

representative. should any structure be uncovered the Engineer’s instructions shall

be obtained before its demolition or removal.

SHORING:

All excavations shall suitably and effectively be supported at the sides and ends to

prevent any fall or run from any portion of the ground outside the excavation and to

prevent settlement of damage to structures adjacent to the excavation. Any extra

excavation necessary to provide space for such support or other working space shall

be at the Contractor’s expense. If, for any reason, any portion of the bottoms, sides

or ends of any excavations shall give way, the contractor shall at his own expense

take all necessary remedial measures including the excavation and removal of all the

ground thereby disturbed both within and outside the nominal limits of excavat ion

and such extra excavation shall not be paid for the contractor shall submit a detailed

plan for review showing the design of shoring, bracing, sloping or other provisions

to be made for worker protection from the hazard of caving ground during the

excavation of such trench or trenches or during the pipe installation or any

construction therein.

If ordered by the Engineer, the contractor shall have to provide additional supports

or sheeting or modify the arrangements as directed.

This however shall not exempt the contractor from the liability of damages to

persons and property due to failure of shoring etc.

Unless specifically provided for in the tender the shoring and strutting shall be

deemed to be part of excavation item only and nothing extra shall be paid to

contractor.

SLOPING FACES:

Where the contractor elects and is permitted by the Engineer to perform excavation

with sloping faces, other than sloping excavations where required by the Engineer

or as specified in the tender and without shoring the excavated faces shall be to

stable slopes and heights and the resulting extra excavation shall be held to be in

excess of the payment lines and shall not be paid for. The decision of required slope

(or steps) to be allowed for such open excavation will be that of the Engineer-in-

charge and in any dispute arising on this account, decision of the Chief Engineer

will be final and binding on the contractors.

TRIMMING EXCAVATIONS:

When excavation to specified levels for the foundation of any structure or to

specified limits for the face of any structure required to about undisturbed ground or

for laying pipelines the Contractor shall not excavate the last 150 mm until

immediately before commencing the construction work except where the Engineer

shall permit otherwise. Should the contractor have excavated to within 150 mm

above these specified levels or to within 150 mm of these specified limits before he

is ready or able to commence the constructional work he shall, where required by

the Engineer, excavated further so as to remove not less than 150 mm of material

Page 70: MAHARASHTRA JEEVAN PRADHIKARANmjp.maharashtra.etenders.in/tpoimages/mjp/tender/Tender...Maharashtra Jeevan Pradhikaran, such specifications with designs and drawings shall form a part

Contractor No. of Correction Executive Engineer

immediately before commencing the constructional work and such further

excavation and consequent backfill shall not be paid for.

Before commencement of any constructional work all shattered and loose material

shall be removed from the excavations by hand, so as to ensure that the work rest on

a solid and perfectly clean foundation or abuts against solid ground.

ENGINEER’S INSPECTION:

When the specified levels or limits of excavation are reached the Engineer will

inspect the ground exposed and if he considers that any part of the ground is by its

nature unsuitable he may direct the Contractor to excavate further. Such further

excavation shall be refilled to the specified levels or limits with concrete, masonry

selected excavated material or selected imported materials as directed by the

Engineer, and payment shall be allowed to the Contractor. In case excavation is

done deeper through mistake by the Contractor than shown on plans or ordered by

the Engineer, the extra depth shall be made up with concrete or masonry of

proportion as directed by the Engineers. The cost of excess excavation and the

filling by masonry / concrete shall not be paid for.

If the material forming the bottom of any excavation, while acceptable to the

Engineer at the time of his inspection subsequently become unacceptable to him due

to exposure to weather conditions or due to flooding or have become puddle, soft or

loose during the progress of the works, the Contractor shall remove such damaged,

softened or loosened material and excavate further by hand. Such further excavation

and consequent backfill shall not be paid for. After each excavation is completed the

contractor shall notify the engineer to that effect and no footing or pipe will be

allowed to be laid until the Engineer has approved the depth and dimensions of

excavation and nature of foundation material and levels / measurements are

recorded.

DISPOSAL OF SURPLUS MATERIAL:

If the quantity of excavated material to be disposed of in permanent dumps exceed

the quantity which can be disposed of in the permanent disposal areas in the site, it

shall be disposed of off site so a location as directed by the Engineer. Surplus

material or unsuitable material ordered to be disposed of shall be transported off the

site and deposited at such a disposal site. Material so deposited shall be shaped up

or spread and leveled as directed by the Engineer. Unless specific lead is mentioned

in the wording of item, the rate shall be taken to be applicable for all leads. Any

necessary work to provide access to disposal site or other preliminary work in

connections therewith shall be carriedout at the contractors cost. The materials

suitable and useful for other works shall be stacked as directed by the Engineer. If

rubble is available from the Excavation, the same shall be property of the M.J.P. and

shall be stacked as directed.

Page 71: MAHARASHTRA JEEVAN PRADHIKARANmjp.maharashtra.etenders.in/tpoimages/mjp/tender/Tender...Maharashtra Jeevan Pradhikaran, such specifications with designs and drawings shall form a part

Contractor No. of Correction Executive Engineer

FILL:

1. FILL MATERIAL:

When the quantities of suitable materials obtained from excavations are

insufficient to construct the specified fills, additional materials shall if

directed by the Engineer, be obtained by the contractor from approved

borrow areas. Borrow pits shall be excavated and finally dressed in a manner

to eliminate steep or unstable side slopes or other hazardous or unsightly

conditions. The extent and depth of borrow pits within the limits of the

designated borrow areas shall be approved by the Engineer.

A) Excess excavated or fill material may be deposited on the site in accordance

with compaction requirements and subject to the approval of the Engineer.

All excess excavation fill material not approved for disposal on the site or to

the disposal dump shall become the property of the Contractor and shall be

removed from the site.

B) Rocks or other solid materials which are larger then 18 cm. in greatest

dimensions shall not be used as fill without the Engineer’s approval. Smaller

rocks shall be well distributed throughout the fill area and sufficient earth or

other fine material shall be placed around the large material as it is deposited

so as to fill the interstices and produce a dense, compact fill.

2. DEPOSITION OF FILL:

Materials for fills may be obtained from the required excavations. Fill

material shall be deposited in layers of not more than 18 cm. in loose

thickness for heavy equipment and not more than 10 cm. loose thickness for

hand compacted fill, including manually directed power tamping and

compared to the required densities by suitable compaction equipment.

Additional fill may be required and shall be obtained from approved

borrower areas. The contractor is responsible for the arrangement and

payment for all embankment material and the material selected shall meet the

approval of the Engineer.

3. DETERIORATION OF MATERIAL:

If the material being placed as backfilling, while acceptable at the time of

selection, become unacceptable to the Engineer due to exposure to weather

conditions or due to flooding or have become puddle, soft or segregated

during the progress of the works, the contractor shall at his own expenses

remove such damaged, softened or segregated material and replace it with

fresh approved materials.

The contractor shall when placing the backfilling make due allowance for

any settlement that may occur before the end of the period of maintenance.

Where necessary the contractor shall at the end of the period of maintenance

remove any excess material or make up any deficiency of backfilling to the

specific levels.

Page 72: MAHARASHTRA JEEVAN PRADHIKARANmjp.maharashtra.etenders.in/tpoimages/mjp/tender/Tender...Maharashtra Jeevan Pradhikaran, such specifications with designs and drawings shall form a part

Contractor No. of Correction Executive Engineer

4. CONTROL OF COMPACTION:

The moisture content shall be controlled as specified herein and the surface

materials of the foundation shall be compacted the surface scarified and

bonded with the first layer of earth fill subsequent layers of earth fill shall be

bonded in a similar manner. No pending or jetting shall be permitted.

A) Fill material shall be moistened or dried to within two (2) percent of

optimum moisture content (Proctor) and compacted to meet or exceed the

following listed values when in accordance with these specifications.

1. Fills and backfills under and adjacent to structures shall be compacted

to not less than 95 per cent of maximum dry density.

2. All other fills shown on the plans shall be compacted not less than 90

per cent of maximum dry density.

B) All working areas shall be protected from damage shall be maintained at all

times, and water shall be prevented from standing on top of constructed fills

and back fills. Heavy equipment shall not be operated within 60 cm of any

structure and vibrating rollers not allowed within 150 cm. of any structure.

Surplus excavated material is the property of MJP so contractor is not empowered to

sell this excavated material to any other agency.

The material shall be conveyed by means of suitable device / manner.

The material conveyed to the place of disposal shall either be stacked or spread as

directed by Engineer-in-charge or his representative.

The route opening and maintenance payment of any royalties, compensation to land

owners and for damages of any etc. during the process of conveyance etc. shall be

entire responsibilities of the contractor.

The item includes all labour, material and equipment required for loading,

unloading, stacking or spreading the material.

CEMENT CONCRETE:

The contractor shall make field arrangement for testing of all materials for cement

concrete i.e. slump test bulk age test, compression test etc. The concrete cube moulds 3

Nos. of 15 x 15 x 15 cm. size shall be kept at site during concreting operation, one set of

six 15 cm. (about 6”) cubes shall be prepared from the concrete to be used in work for

compression test on the first three days operation and thereafter, for every 60 cubic meter

of concrete or three days work whichever is less. If source of aggregate, grading is

changed, one set of 6 test cubes shall be taken for each changed batch 3 cubes shall be

tested for test at 7 days age and 3 at 28 days in at Govt. laboratory or at any approved

laboratory. All the testing charges will be borne by the contractor. The entire

responsibility of the testing of materials will be borne by the contractor.

Page 73: MAHARASHTRA JEEVAN PRADHIKARANmjp.maharashtra.etenders.in/tpoimages/mjp/tender/Tender...Maharashtra Jeevan Pradhikaran, such specifications with designs and drawings shall form a part

Contractor No. of Correction Executive Engineer

Mixing of concrete shall be done with concrete mixer only.

For providing electric wiring duct tubes of the required diameter and length shall be

provided through walls, beams and floors, slabs as and when directed without any extra

cost.

a. The contractor will make his own arrangement for raising all material tools etc.

b. No extra charges for the carriage of water will be allowed.

c. The rates for all items are also inclusive of all charges such as carting, lifting etc.

no extra payment for any lead and lifts will be paid for any item.

d. The contract should not be sub-leted without written permission of the Engineer-

in-Charge.

e. The conditions in the tender notice will be binding on the contractor and the

Tender Notice will form a part of agreement.

REQUIREMENT OF STRENGTH OF CONCRETE:

1) CONTROLLED CONCRETE:

Full payment shall be made when 80% of the test cube results are equal to and

above the minimum specified strength and the remaining 20% of the results above

80% of the specified strength.

2) ORDINARY CONCRETE:

Full payment shall be made when 75% of the test cube results are equal to and

above the minimum specified strength and the remaining 25% of the results above

75% of the specified strength.

Cases failing outside the limit shall be examined by the Engineer-in-Charge on

merits in each case.

CRITERIA FOR TESTING OF CONCRETE CUBES AND ACCEPTANCE

STANDARDS FOR STRENGTH OF CONCRETE:

Frequency of sampling of concrete cubes (I.S. 456/ 2000 clause 15.2)

a) No. of samples to be taken during concreting, based on the quantum of concrete

cast shall be as follows:

Quantity of Concrete in cubic meter No. of Samples

1 to 5 1

6 to 15 2

16 to 30 3

31 to 50 4

51 and above 4 + 1 additional sample for each

additional 50 cum. or part thereof.

Page 74: MAHARASHTRA JEEVAN PRADHIKARANmjp.maharashtra.etenders.in/tpoimages/mjp/tender/Tender...Maharashtra Jeevan Pradhikaran, such specifications with designs and drawings shall form a part

Contractor No. of Correction Executive Engineer

b) At least one sample shall be taken from each shifts of concreting and three test

specimens (cubes of size 15 x 15 x 15 cm. ) shall be cast from each such sample

for testing of the compressive strength. Additional three cubes will also have to

be taken for 7 days test.

c) The test strength of the sample shall be the average of the strength of the three

specimen.

ACCEPTANCE CRITERIA (IS:456/2000 CLAUSE 16):

The concrete test shall be supposed to be acceptable if the compressive strength (i.e.

average strength of the three specimen) of the samples fulfill the following requirements.

a) Every sample has a test not less than the characteristic value.

b) The strength of one or more samples, though less than the characteristic value is

in each case not less than the greater of following:

i) The characteristic strength minus 1.35 times the standard deviation and.

ii) 0.8 times the characteristic strength.

c) And the average strength of all the samples is not less than the chrematistic

strength plus 1.65 x the standard deviation

Number of samples

d) However, it should be noted that individual variation should not be more than +

15 percent of average.

STANDARD DEVIATION VALUES:

Grade of Concrete Assumed Standard Deviation in Kg/cm2

M-15 35.0 Kg/cm2

M-20 46.00 Kg/cm2

M-25 53.00 Kg/cm2

CURING OF CONCRETE CUBES (I.S. 516/1959, CLAUSE 3.3):

The test specimen (cubes) shall be stored on the site at a place free from vibration under

damp matting sacks or other similar materials for 24 hours + ½ hours, from the time of

adding the water to the other ingredients. The temperature of the place of storage shall be

within the range of 22o to 32

o C. After the period of 24 hours, these shall be marked for

future identification, removed from the moulds and unless required for testing within 24

hours, stored in clean water at temperature of 24o to 30

o C until those are transported to

the testing laboratory. Samples shall be sent to the testing laboratory well packed in

damp sand, damp sacks or other suitable material so as to arrive there in a damp

condition, not less than 24 hours before the time of test. On arrival at the testing

laboratory the specimen shall be stored in time of test.

On arrival at the testing laboratory the specimen shall be stored in water at a temperature

of 270 + 2

0 C, until the time of test records of the daily minimum and maximum

temperatures shall be kept both during the period specimen remain on the site and in the

laboratory.

Page 75: MAHARASHTRA JEEVAN PRADHIKARANmjp.maharashtra.etenders.in/tpoimages/mjp/tender/Tender...Maharashtra Jeevan Pradhikaran, such specifications with designs and drawings shall form a part

Contractor No. of Correction Executive Engineer

TEST PROCEDURE (IS 516/1959 CLAUSE 5.5):

Specimen stored in water shall be tested immediately on removal from water and while

those are still in the wet condition. Surface water and grit shall be wiped off the

specimens and any projecting fins removed. Specimen, when received dry, shall be kept

in water for 24 hours before taken for testing. The dimensions of the specimen to the

nearest 0.2 mm and also weight shall be noted before testing.

Here, it should be specifically noted that age of concrete cube will be the age as on the

date of testing i.e. time difference between addition of water to dry ingredients / and

actual testing.

SPECIFICATION FOR FORM WORK:

GENERAL DESCRIPTION:

Requirement specified herein are for providing form work along with supporting

scaffolding therefore for cast in situ concrete as indicated specified and required.

QUALITY ASSURANCE:

A. REQUIREMENT:

All form work shall be constructed of plywood, sheet metal or other approved

material, it shall be firmly supported, adequately strutted, braced and tied to

withstand the placing and vibrating of concrete and the effects of weather.

Design of structures shown on the Engineer’s drawings does not include any

allowance or consideration for imposed construction loads one copy of the

contractor’s shoring and form work drawing shall be submitted to owner’s record

purposes only and not for review or approval. Forms shoring and false work shall

be adequate for imposed live and dead loads including equipment and men height,

of concrete drop, concrete and foundation pressure and stresses, wind pressure,

lateral stability and other safety factors during construction. The contractor shall

be responsible for the calculations and designs for the form work. The contractor

shall be held solely responsible for any failure and for safely of work and

workmen. He shall pay necessary compensation, if needed for damages to work,

property and injuries to persons. The scaffolding, hoisting arrangements and

ladders shall have easy approach to work spot and afford easy inspection.

B. STANDARD AND TOLERANCE:

All form work shall be fabricated in compliance with the best modern practice so

that the finished surface is even, unblemished, free of fins and true to line, level

and shape as shown by the drawing. The form work shall comply with the

requirements of IS:456.

i) Faces of form work in contact with concrete shall be free from adhering

foreign matter, projecting nails and he like, splits or other defects and all

form work shall be clean and free from standing water, dirt, shavings,

chippings or other foreign matter. Joints shall be water tight to prevent the

escape of mortar or the formation of fins or other blemishes on the face of

the concrete.

Page 76: MAHARASHTRA JEEVAN PRADHIKARANmjp.maharashtra.etenders.in/tpoimages/mjp/tender/Tender...Maharashtra Jeevan Pradhikaran, such specifications with designs and drawings shall form a part

Contractor No. of Correction Executive Engineer

ii) Openings for inspection of the inside of the form work and for the removal

of water used for washing down shall be provided and so formed as to be

easily closed before placing concrete. Bore placing concrete all bolts

pipes or any other fixtures which are to be built in shall be fixed in their

correct positions and cores and other devices for forming holes shall be

hold fast by fixing the form work or otherwise. Holes shall not be cut in

any concrete without the approval of the Engineer.

SHOP DRAWINGS:

Concrete construction joints and expansion joints shall be of the type and at location

indicated and shop drawings for approval shall be submitted showing proposed location

and type of construction for any joints not shown on the drawings and sequences of

forming and concrete placing operation Shop Drawings shall be submitted at least 15

working days in advance of form fabrication.

2.0 MATERIAL:

2.1 FORM WORK COATING:

The coating on all form work shall be of non staining mould oil that will not level

residual matter on surface of concrete or a adversely affect bonding to concrete of

any subsequent paint plaster, mortar or other applied materials. Coatings

containing mineral oils, paraffin’s, waxes or other non drying ingredients are not

permitted. For concrete surfaces contacting potable stored water the coatings and

form release agents shall be completely non-toxic. Care shall be taken to prevent

the coating from coming into contact with reinforcement or with concrete at

construction joints.

2.2 TIMBER:

Timber shuttering shall be fabricated from partially seasoned timber which shall

not warp under the effects of the temperature and humidity. Boards shall be

strong enough to support the stresses imposed on the shuttering without flexing.

The planks shall be sawn straight and all edges and planes shall be straight and

fees from warp.

2.3 JOINTS:

All joints shall be bonded to prevent loss of grout during concrete.

2.4 PLYWOOD:

Plywood shall conform to IS:4990 and shall be braced as necessary wooden forms

shall be lined with plywood.

2.5 METAL FORMS:

Metal forms shall be true to detail in good condition, clean, free from dents,

bends, rust and mineral oils. They shall be of adequate gauge with appropriate

angle frame.

Page 77: MAHARASHTRA JEEVAN PRADHIKARANmjp.maharashtra.etenders.in/tpoimages/mjp/tender/Tender...Maharashtra Jeevan Pradhikaran, such specifications with designs and drawings shall form a part

Contractor No. of Correction Executive Engineer

2.6 MOULDS:

For grooves, drips, rebates, profiles, champers and similar items smooth finished

limber coated with specified form coating shall be used.

3.0 EXECUTION:

3.1 SHORING ON TRENCHES AND FALSE WORK FOR CONCRETE:

The loads shall be properly distributed over base area on which shoring is erected,

either concrete slabs or ground. If on ground, it shall be protected against under

mining or settlement, particular against wetting of soils and near excavations.

The forms shall be constructed to produce finished structure all in lines, grades

and camber as required jacks, wedges, or similar means shall be used and firmly

anchored to take any settlement in form work which may occur before placing of

concrete camber for beams and slabs shall be as indicated.

3.2 FORM CONSTRUCTION:

Forms shall be built to exact shapes, sizes, lines and dimensions as required to

obtain accurate alignment, location and gardened level and plumb work in

finished structures. Provision shall be made for openings, offsets, keyways re-

accesses mouldings, reglects, cambers, blocking joint screeds, bulk heads,

anchorages and other required features. Forms shall be made for easy removal

without hammering or prying against concrete. Metal spreaders may be used to

provide accurate spreading of forms. Construction of forms shall be such that

there will be no sagging, leakage or displacement occurring during and after

pouring of concrete. Forms shall be coated with specified coating materials only

prior to placement of reinforcing steel and coating material shall not come into

contract with reinforcing bars.

A. SLOPES:

Form work shall be provided for the top surfaces of sloping work where the slope

exceed fifteen degrees from the horizontal (except where such top surface is

specified as shaped finish) and shall be anchored to enable the concrete to be

properly compacted and to prevent floatation. Care being taken to prevent air

being trapped.

B. CHAMFERS:

All exterior horizontal angles on the finished concrete of 90 degree or less along

with tops of walls shall be given 20 mm x 20 mm chamfers, columns are required

to have chamfers on vertical angles, which run out 125 mm from the bottom and

top of the column, other exterior angle shall be left sharp, unless otherwise

ordered by the Engineer.

C. TIES:

No ties or bolts or other device shall be built into the concrete for the purpose of

supporting form work without the prior approval of the Engineer. The whole or

part of any such supports shall be capable of removal so that no part remaining

embedded in the concrete shall be nearer than 50 mm from the surface in the case

Page 78: MAHARASHTRA JEEVAN PRADHIKARANmjp.maharashtra.etenders.in/tpoimages/mjp/tender/Tender...Maharashtra Jeevan Pradhikaran, such specifications with designs and drawings shall form a part

Contractor No. of Correction Executive Engineer

of reinforced concrete and 150 mm in the case of un reinforced concrete. Holes

left after removal of such support shall be neatly filled with 1:3 dry pack mortar

which shall contain just sufficient water to make it plastic. It shall be well

rammed into the whole and finished flush.

D. FORM WINDOWS:

Windows shall be provided in the form work wherever directed or necessary for

access for concrete placement and vibration. Windows shall be of size adequate

for tremies and vibrators, spaced at maximum 1.8 meters horizontally and shall be

tightly closed and sealed before placing higher concrete.

E. CLEANOUTS AND CLEANING:

Temporary openings shall be provided in wall, column and slab form work for

cleaning and inspection. Prior to pouring, all forms and surfaces shall be cleaned

and coated to receive concrete.

F. RE-USE:

Form material shall be cleaned and reconditioned before re-use.

3.3 EMBEDDED PIPING, CONDUITS AND ANCHORS:

All trades which require openings for the passage of pipes, electrical conduits and

other inserts shall be consulted and the necessary pipe sleeves, anchors or other

required inserts shall be properly and accurately installed. Openings required by

other trades shall be reinforced as indicated and required conduits or pipes shall

be located so as not to reduce the strength of the construction and in no case shall

pipes other than conduits be placed in a slab 4.5” (11.4 cm) or less in thickness.

Conduit buried in a concrete slab shall not have an outside diameter greater than

1/3 of the slab and in placed below bottom reinforcing steel or over top

reinforcing steel. Conduits may embedded in wall provided they are not larger in

outside diameter than 1/3 the thickness of the wall, are not spaced closer than

three diameters on center, and do not impair the strength of the structure Electrical

conduits shall be placed with due regard to allowable bend continuity in its length

from outlet to outlet and shall be equipped with a pull-cord. The outlets shall be

temporarily plugged to totally avoid ingress of concrete or grout.

4.0 FIELD QUALITY CONTROL:

A. CONTROL DURING CONCRETE PLACEMENT:

Required slab and beam camber shall checked and correctly maintained as

concrete placement and to promptly seat any mortar leaks.

B. DEFECTS IN FORMED SURFACES:

Workmanship in form work and concreting shall be such that concrete

shall normally require no making good, surfaces being perfectly

compacted and smooth. If any blemishes are revealed after removal of

form work, the Engineer’s decisions concerning remedial measures shall

Page 79: MAHARASHTRA JEEVAN PRADHIKARANmjp.maharashtra.etenders.in/tpoimages/mjp/tender/Tender...Maharashtra Jeevan Pradhikaran, such specifications with designs and drawings shall form a part

Contractor No. of Correction Executive Engineer

be obtained immediately. These measures may include, but shall not be

limited to the following.

(i) Fins, pinhole bubbles, surface discoloration and minor defects may

be rubbed down with sacking immediately the form work is

removed.

(ii) Abrupt and gradual irregularities may be rubbed down with

carborundum and water after the concrete has been fully cured.

These and any other defects shall be remedied by methods

approved by the Engineer which may include using a suitable

epoxy dove tailed shape at least 75 mm. deep and refilling with

concrete over steel mesh reinforcement sprung into the dove tail.

C. REMOVAL OF FORMS AND SHORING:

From work shall be so designed as to permit easy removal without

resorting to hammering or levering against the surface of the concrete.

The periods of time elapsing between the placing of the concrete and the

striking of the form work shall be as approved by the Engineer after

consideration of the loads likely to be imposed on the concrete and shall

be in any case be not less than the periods shown below, depending on the

ambient temperature.

Location of Form Time for striking

using ordinary

Portland cement

(Days)

i) Beam sides, walls and columns 3

ii) Slab Soffits upto 4.5 M span 7

iii) Slab soffits beyond 4.5 M span and

beam soffits upto 6 m span.

14

iv) Beam soffits and arch ribs more than 6

M span.

21

Sequence of striking form work shall be approved by the Engineer in

important structures.

Not with standing for foregoing in the contractor shall be held responsible

for any damage arising from removal of formwork before the structure is

capable of carrying its own weight and any incidental loading. The

contractor shall be wholly responsible for repairing or reconstruction as

directed by the Engineer the section of the works so affected.

D. SHORING AND FALSE WORK REMOVAL

In retaining wall construction shoring and false work shall not be removed

until 21 days after concrete placement or until concrete has attained at

Page 80: MAHARASHTRA JEEVAN PRADHIKARANmjp.maharashtra.etenders.in/tpoimages/mjp/tender/Tender...Maharashtra Jeevan Pradhikaran, such specifications with designs and drawings shall form a part

Contractor No. of Correction Executive Engineer

least 90 percent of the 28 day design compressive strength as

demonstrated by control test cylinders whichever is earlier.

E. RESTRICTION

Construction equipment or permanent loads shall not be imposed on

columns, supported slabs, or supported beams until concrete has attained

the 28 days design compressive strength as demonstrated by control test

cylinders.

F. CONCRETE CURING DURING REMOVALS

Concrete shall be thoroughly wetted as soon as forms are first loosened

and shall be kept wet during the removal operations and until curing media

or sacking is applied. Potable water supply with hose or buckets shall be

ready at each removal location before removal operations are commenced.

5.0 MODE OF MEASUREMENT & PAYMENT:

This item shall generally form part of item of concrete plain or R.C.C. in which

case, no separate payment shall be made.

If, however it occurs in the tender as a specific item, the payment hall be based on

sq.m.

PLAN REINFORCED CEMENT CONCRETE:

1. CONCRETE PROPORTION

a) Proportion of concrete for types of work

i) M-20 P.C.C. for leveling course, for foundation

ii) M-30 R.C.C. for entire structure of E.S.R.

b) General specifications of this work shall be as per standard specification

of Public Works Department, latest edition, section B-6, BR-27, BR-29,

BR-38.

c) Whenever concrete is to be laid in trenches, the trench shall be cleaned

and watered before placing. The sub soil water which is met shall be

removed and the trench shall be kept dry during and after 2 hours of

placing concrete.

Mixing of concrete shall be done with concrete mixers

a) The contractor will make his own arrangement for receiving material, tool

etc. required for the work.

b) No extra charges for the carriage of water will be allowed.

c) The rates for all items are inclusive of all charges such as carting, lifting

etc. No extra payment for any lead and lifts will be paid for any item.

Page 81: MAHARASHTRA JEEVAN PRADHIKARANmjp.maharashtra.etenders.in/tpoimages/mjp/tender/Tender...Maharashtra Jeevan Pradhikaran, such specifications with designs and drawings shall form a part

Contractor No. of Correction Executive Engineer

3. MIX DESIGN:

The following instructions shall be followed as regards preliminary design of mix

and methods of batching of plain cement and reinforced cement concrete. These

instructions should be treated as supplementary to the relevant provisions in the

specifications for the respective items contained in the book of standard

specification and will be carried the provisions contained therein wherever they

are contrary to the following instructions.

The preliminary mix design and batching for various grades of concrete shall be

governed by the following guidelines.

1. M-20 to M-30 Preliminary mix design must be carried out for these mixes.

However, weigh batching shall be insisted for cement only for concrete

M-20 and above.

2. Above M-30 Preliminary mix design must be prepare for such mixes

weigh batching should be insisted for cement fine aggregate and course

aggregate.

For the grades of concrete M-20 and above the preliminary mix design shall be

carried out from the approved laboratory. The rate quoted by the contractor in the

agreement for these items shall be final and binding on him irrespective of content

of cement required as per preliminary mix design and there shall be no adjustment

in the agreement rate for these item on this account.

The charges for preliminary design of concrete mix shall be entirely borne by the

contractor.

For grades of concrete M-20 and above where cement is to be used by

weightment, the cost of extra cement required to make up the under weight bags

shall be borne by the contractor.

STEEL REINFORCEMENT FOR RCC WORK:

1. DETAILS:

The item provides for supply tor steel bars, cutting, bending, binding with

binding wire and placing in position, welding for reinforcement in the RCC.

Tor steel bars shall confirm to specification A-10 of standard specification of

Public Works Departments latest edition and conforming to IS:1786-1985

requirements for H.Y.S.D. reinforcement and should be of Fe 415 grade only.

The binding wire shall confirm to specification A-15 of standard specification

book of Public Work Department latest edition.

During contractor’s supply, if any, the steel bars shall be supplied directly to the

site of work. Binding reinforcement shall confirm accurately to the dimensions

Page 82: MAHARASHTRA JEEVAN PRADHIKARANmjp.maharashtra.etenders.in/tpoimages/mjp/tender/Tender...Maharashtra Jeevan Pradhikaran, such specifications with designs and drawings shall form a part

Contractor No. of Correction Executive Engineer

and shapes in the details drawings (approved) or as directed by the Engineer-in-

Charge.

Bars shall be bend cold only in no way bending by heat will be allowed. Bars

with kinks, bends, or cracks shall not be used.

Details of length, size laps and bending diagram shall be got approved from the

Engineer-in-Charge.

As far as possible full lengths of bars shall be placed as per drawing details.

When full lengths are not available bars be splices only after written permission

of Engineer-in-Charge. Splices shall be staggered and in tension zone shall be

avoided strictly. Bars shall be lapped as specified in IS:456-2000 with due

regards to the grade of concrete. Welding may be used for large diameter of bar

only after permission of Engineer-in-Charge.

Welding, if permitted shall conform to specification B-10.7 of standard

specification on public works department.

All reinforcement shall be accurately placed in position with spacing and cover

shown in detailed drawing and firmly held during the placing and setting of

concrete, Bars shall be tied at all inter sections. Binding wire of 1.2 mm or 1.6

mm diameter (about 16 or 18 gauge) shall be used. Spacing of the bars shall be

maintained by means of stays, blocks ties, spacers, intervals so that bars will not

be displaced during placing. Vibrating or complacent concrete. Placing bars for

reinforcement on a layer of fresh concrete as the work progress will not permitted.

The use of pieces of broken stones or bricks or wooden blocks for layers of bars

shall be separated by precast cement blocks, spacer bars or other devices.

Full details of numbers, sizes, weights, laps, welds, spacing of bars placed in

position in different parts of the work shall be recorded by the contractor and

certified and signed by the Engineer-in-Charge or his representative to show that

all reinforcement has been placed correctly as per sanctioned drawing or as

directed by the Engineer-in-Charge in writing, before placing concrete. No

concrete shall be placed in position until the Engineer or his representative has

inspected and certified the correctness of reinforcement, recording the steel

measurements and has given permission in writing to place concrete. After

approval of reinforcement as above, it will be the contractor’s responsibility to see

that the spacing of reinforcement and arrangements are to tampered within any

way before or during concreting.

The contractor shall produce the test certificate of steel. In addition, actual test

shall be carried out according to IS:432-1966 in an approved laboratory and the

cost of test shall be borne by the contractor, including all transport etc.

Page 83: MAHARASHTRA JEEVAN PRADHIKARANmjp.maharashtra.etenders.in/tpoimages/mjp/tender/Tender...Maharashtra Jeevan Pradhikaran, such specifications with designs and drawings shall form a part

Contractor No. of Correction Executive Engineer

This item includes

a) Cost of labour, material use of tools, plant and tackle and other incidental items to

complete the work satisfactorily.

b) Supplying, conveying, cleaning, cutting, bending, binding with 1.22 mm. or 1.66

mm diameter (16 to 18 gauge) binding wire on spot welding and placing

reinforcement in position and maintaining it clean and in position till the concrete

is laid.

c) In no case any foreign material e.g. oil, grease, etc. which prevent bonding

between steel and concrete shall remain on steel bars during placing of concrete.

The lengths of the bars shall be measured correct to two places of decimals of

meters. The weights for payments shall be calculated according to standard weights

mentioned in the ISI handbook correct upto 0.10 kg.

However, no extra claim for overweight of steel will be considered for payment

whether it is the contractors responsibility to bring the steel as per standard weight.

PROVIDING AND APPLYING EPOXY PAINT TO INTERNAL SURFACE

OF CONTAINER OF E.S.R.:

1. DETAILED SPECIFICATIONS:

Providing and applying Goodlass Nerolac paint or equivalent with two coats.

The materials shall consists of two packs consisting of Base and catalyst. The

base consist of fine zinc dust ground in epoxy resin solution supplied in paste

form catalyst. The non volatile portion of material should consist of 90-92

zinc dust and curing agent shade shall be glory. The paint shall provide a

complete rust inhibitive barrier coating of high mechanical and abrasion

resistance. The film shall be compatible for fusion and spot welding. Pot life

shall be 4 to 6 hours.

COVERING:

Coverage shall be 8.10 sq.m / litre per coat going a film thickness of one millimeter.

MIXING RATIO:

The proportion of mixing of base and hardner should be as specified by the

manufacturer by weight and volume. The mixed primer shall confirm to the

specifications.

Viscosity of ready mixed paint 15-22 in Fort cup No.4 @ 300C.

APPLICATION:

To be applied by spray over a properly blast cleaned surface:

DRYING TIME:

1) Dust free 10 to 15 minutes.

(2) Chemical curing – 24 to 48 hours.

Page 84: MAHARASHTRA JEEVAN PRADHIKARANmjp.maharashtra.etenders.in/tpoimages/mjp/tender/Tender...Maharashtra Jeevan Pradhikaran, such specifications with designs and drawings shall form a part

Contractor No. of Correction Executive Engineer

PROCEDURE:

Blasted steel surface shall be cleaned of dust and grit and shall be primed

immediately following cleaning. The surface shall be dry at the time primer is

applied. Paint shall not be applied during rain or fog unless protected from weather

by suitable housing and subject to permission of Engineer. The primer shall be

applied by hand spraying and shall be in accordance with the instruction of

application supplied by the manufacturer. The priming coat shall be uniform and

free from floods, spot, runs, drips, or bare spots. Any bare spot shall be recoated

with an additional application of primer. All runs, sags, floods or drips shall be

removed or all such defects shall be remade by reblasting and repriming at the

discretion of the Engineer and at the cost of contractor.

APPLICATION OF ZINC RICH PRIMER:

The primer shall be prepared in the manner and proportion as specified by the

manufacturer as mentioned. However the mixed primer shall conform to the

specifications of epoxy. The mix of zinc rich epoxy primer shall be prepared 15

minutes before applying on the works site.

One coat of zinc rich epoxy primer shall be applied by spray right upto the edge of

the member giving a thickness of approx. 1 mm.

No thinner shall be added to the ready mixed paints without the prior written

approval of the Engineer. Though the priming coat become dust free, dry in 10-15

minutes the finishing coat shall only be applied after following the film to cure at

least for 48 hours.

CEMENT PLASTER:

1. GENERAL:

This specification lays down the requirements of cement plaster to be applied

to concrete, stone or brick masonry surface. In cement mortor of specific

proportion and thickness.

2. PREPARATION:

For masonry all joints in the frame work that is to be plastered shall be raked

out to a depth not less than the width of the joints or as directed by the

Engineer-in-charge. The raking shall be done taking care not to allow any

chipping of masonry. In new work the raking out shall be done while the

mortar in the joints in still green. Smooth surface of concrete or plaster etc.

must be suitably roughened to provide necessary bond for the plaster. All

dirt, soot, oil paint or any other materials that might interfere with

satisfactory bond shall be removed and surface wetted before plastering is

started.

3. MATERIALS:

Cement mortar shall be prepared from cement and sand as specified for RCC

work and mixed in the proportion specified sand shall be screened and

Page 85: MAHARASHTRA JEEVAN PRADHIKARANmjp.maharashtra.etenders.in/tpoimages/mjp/tender/Tender...Maharashtra Jeevan Pradhikaran, such specifications with designs and drawings shall form a part

Contractor No. of Correction Executive Engineer

washed if called up on to do so. Water proofing compound of directed make

in directed quantities shall be added where it is water proof plaster,

scaffolding shall be prepared from sound materials and shall be provided

wherever situation demands for facility of proper working.

4. GAUGING:

Patch of plaster 15 cm x 15 cm shall be put on about 3 m apart as gauges to

ensure even plastering in one plane.

5. POINTING:

In all plastering work, the mortar shall be firmly applied with some what

more than the required thickness and well pressed into the joints and on the

surface and rubbed and leveled with a flat wooden rule to give required

thickness. Long straight edges shall be freely used to ensure a perfectly plane

and even surface. All corners shall be finished to their true angles or rounded

as directed and shall present a neat appearance. The mortar shall adhere to

the masonary or concrete surface intimately when set and there should be no

hollow sound when struck. Cement plaster shall be done from top

downwards.

6. FINISHING:

In any continuous face of a wall, finishing treatment of any type shall be

carried out continuously and day to day breaks made to coincide with

architectural breaks in order to avoid unsightly junctions. All mouldings shall

be worked true to template and drawn neat, clean and level. All exposed

angles, junctions and openings shall be carefully finished.

7. WATERING:

All pointing work shall be kept damp continuously for a period of 14 days.

To prevent excessive evaporation of the sunny and wind ward side of the

building in hot, dry weather matting or gunny bags may be hung over on the

out side of the plaster in the beginning and kept moist. If the contractor fails

to water the work to the satisfaction of the Engineer-in-charge, the requisite

labour, materials and equipment to water the work properly shall be engaged

departmentally at the cost of the contractor.

The item includes:

a) Erecting, dismantling and removing the scaffolding as and when

necessary.

b) Preparing the surface to receive the plaster.

c) Providing cement plaster of specified proportion, specified average

thickness with specified number of costs.

Page 86: MAHARASHTRA JEEVAN PRADHIKARANmjp.maharashtra.etenders.in/tpoimages/mjp/tender/Tender...Maharashtra Jeevan Pradhikaran, such specifications with designs and drawings shall form a part

Contractor No. of Correction Executive Engineer

d) All labour, materials, use of tools and equipments to complete the

plastering work as per specifications.

e) Curing for 14 days.

f) Any moulding work if, shown on the drawings or as specified unless

separately provided in the tender. If the average thickness of plaster

provided by the contractor is more than what is specified on any account

no extra payment shall be made.

WATER PROOF CEMENT PLASTER

1. GENERAL:

The item shall conform to specification No. KPP-2 for ordinary cement

plaster and in addition to the following.

2. WATER PROOFING:

While preparing the cement mortar of specified proportion, the approved

water proofing compound at the rate of 1 kg. per one bag of cement or as per

manufacturer’s instructions shall be added in mortar while mixing. The

contractor shall bring the water proofing compound to site of work in

original packing and shall be got approved from the Engineer-in-charge. The

water proofing compound shall be mixed in dry cement and sufficient care

shall be taken while mixing to see that the water proofing material gets wet

and integrally mixed with the cement and does not run out separately when

water is added.

CEMENT BASED PAINTING:

1. GENERAL:

This specification lays down the requirements of applying cement based

paint in specified coats to concrete or masonry surface.

2. MATERIALS:

Cement paint with a base of white Portland cement of approved manufacture

colour and shade shall be used. Approved quality cement based paint shall be

brought to site in original air tight containers with seals intact.

Scaffolding wherever necessary shall be provided to the entire satisfaction of

the Engineer-in-charge.

3. PREPARATION:

The surface to be painted shall be cleaned of all loose dust and dirt, pa int and

all cracks, holes, an surface defects shall be repaired with cement plaster

cured and allowed to set hard before the painting is commenced, the surface

is wetted well and water is allowed to run off. Any grease oil paint shall be

removed by approved methods.

Page 87: MAHARASHTRA JEEVAN PRADHIKARANmjp.maharashtra.etenders.in/tpoimages/mjp/tender/Tender...Maharashtra Jeevan Pradhikaran, such specifications with designs and drawings shall form a part

Contractor No. of Correction Executive Engineer

4. APPLICATION OF PAINT:

Mixing of paint and procedure of painting shall be as specified by the

manufacturer when no specifications are given following specifications shall

generally apply. The dry cement shall be thoroughly mixed with clean fresh

water to produce paint of required consistency (normally water of ordinary

paint). The paint shall be kept stirred and used within one hour of mixing

hardened or damaged paint shall not be used. The paint shall be applied by

brushes in the manner specified by the manufacturer.

The number of coats shall be specified in the wording of the item. When

more than one coat is to be given the subsequent coats shall be applied after

the preceding coat is thoroughly hardened, inspected and approved.

5. CURING:

Each application of paint should be wetted at the end of the day with a fine

water spray, depending on climatic conditions. Wetting shall be done only

after an interval of atleast 6-8 hours after the application in dry weather. The

painted surface shall be kept dump for at least two days and protected from

direct sun.

The item includes:

a) All materials and labour for painting.

b) All equipment and scaffolding.

c) Curing as per specifications.

d) Non uniform colour or shade shall rectified without any extra cost.

The item shall measured on sq.m. basis of area painted.

G.I. PIPE RAILING:

1. The specifications lay down the requirement of Materials, Labour for fixing

G.I. Pipes for Railing.

2. MATERIALS:

a) Posts:

The posts shall be R.C.C. M-250 of height & size specified in the item. The

same shall be fixed to the bottom slab firmly at specified distance.

Alternatively, the vertical post shall be angle iron of specified size and height

or G.I. pipe posts of specified size and height and fixed to the bottom slab

securely at a specified distance.

b) Railing:

For railing the G.I. pipes of specified dia and in specified No. of rows are to

be provided. The G.I. pipes shall pass through the vertical posts. For circular

railing the pipes shall be carefully bent along the curvature and the same

shall have no kins.

Page 88: MAHARASHTRA JEEVAN PRADHIKARANmjp.maharashtra.etenders.in/tpoimages/mjp/tender/Tender...Maharashtra Jeevan Pradhikaran, such specifications with designs and drawings shall form a part

Contractor No. of Correction Executive Engineer

c) Painting:

The railing shall be painted by means of appropriate type of paints such as

synthetic enamel paint three coats for M.S. & G.I. materials and cement

based paint in two coats for R.C.C. posts.

3) FIXING:

All the materials fabricated as per specified size etc. shall be transported to

site of work by the contractor at his own risk and cost. The vertical posts

shall be fixed to the bottom slab etc. firmly by means of hold fasts of

adequate size or as directed by the Engineer-in-charge. The horizontal pipes

shall be in parallel rows at specified distance. Painting shall be carried out

only after final erection is completed. The work shall be carried out to the

entire satisfaction of the Engineer-in-charge.

The item includes:

All materials and labour for fabricating, transport, erection on site of work,

fixing and painting to the satisfaction of the Engineer-in-charge.

ACCESS TO VARIOUS LEVELS OF RESERVOIR:

1) SPIRAL STAIRCASE (ABOVE 2.00 LAKH LIT. CAPACITY)

A RCC precast step spiral staircase one meter wide from ground level to

bottom slab level, gallery to roof slab level of RCC ESR with intermediate

platforms and sufficient number of stiffeners at intermediate levels and with

proper landing and railings as provided for the spiral staircase.

A M.S. Grill gate of 2.0 M height with locking arrangement of approved

design shall be provided and fixed by the contractor as directed.

2) M.S. STAIRCASE (FOR ESR CAPACITY LESS THAN 2 LAKH LIT.

BUT STAGING MORE THAN 8M)

M.S. Staircase with one meter width from ground level to bottom slab,

gallery to roof slab, with intermediate platforms. 2 Nos. of ladder also should

be provided to access to inside of tank. The ladder should be fabricated from

heavy angles, steps and railing as directed by E.I.C.

3) M.S. LADDERS:

M.S. ladder should be provided for staging less than 8 m and capacity upto 2

lakh lit as directed by E.I.C.

4) ALUMINIUM LADDER:

Two numbers of heavy type aluminium ladder of required length and des ign

as approved by the Department shall be provided by the Contractor for each

E.S.R. This shall be for the access to inside of tank. The Contractor shall

furnish to the MJP catalogues of various manufacturer of the ladders.

The make and type approved shall only be supplied.

Page 89: MAHARASHTRA JEEVAN PRADHIKARANmjp.maharashtra.etenders.in/tpoimages/mjp/tender/Tender...Maharashtra Jeevan Pradhikaran, such specifications with designs and drawings shall form a part

Contractor No. of Correction Executive Engineer

ANCILLIARIES:

PROVIDING AND FIXING G.I. HAND RAILING:

Railing for Roof of service Reservoir and bottom gallery shall be of medium class

GI pipes of 25 mm dia. in three rows and shall be fixed in position in RCC post 150

mm x 150 mm at bottom and 100 mm x 100 mm at one meter high and spaced at 1.5

meter center to center. The railing shall be painted with one coat of primer two coats

of approved shade of enamel oil paint R.C.C. posts shall be painted with approved

shade of snowcem. Work shall be carried out as per standard specifications Sr. 5(b)

Page No. 145. If dome is provided at roof then contractor has to provide 1.20 m

wide horizontal slab for walkway along periphery railing shall be provided.

PROVIDING AND FIXING WALL MOUNTED ELECTRONIC &

MECHANICAL WATER LEVEL INDICATOR:

The Contractor shall provide and install the Electronic Water Level indicator of the

type manufactured by Modi Electronics and Engineering Co. or equivalent

Additional Mechanical type water level indicator shall also be fixed for every ESR.

The make and type shall be got approved before actual procurement. The literature /

catalogue/ if any are required in this behalf shall be provided by the Contractor to

the Engineer to facilitate the selection. The electronic and mechanical water level

indicator shall be installed on one of the external columns at eye level with

necessary protective iron box with locking arrangement and glass window for easy

reading. The electronic water level indicator shall be complete with wiring from

service Reservoir to instrument, with probes placed in such a way as to indicate

correct level of water in the Reservoir without any difficulty. One No. 230 Volt.

Amp. Electric point shall be provided.

VENTILATORS:

Adequate shaft type ventilators shall be provided. It shall be minimum 1.00 meter in

dia and 1.5 M height shall be closed by mosquito proof double mesh net fixed in

wooden frame screwed to RCC columns of suitable size additional cowl type C.I.

ventilators shall also be provided as per requirements and as directed by Engineer-

in-charge.

LIGHTENING ARRESTOR:

The lightening arrestor components shall be provided as per IS-2309-1969 code of

practice for protection of buildings and allied structure against lightening and as per

Electricity rules duly designed for the requirement of the job to give complete

protection against lightening.

The lightening arrester shall provide influence of 45 degrees and shall protect the

entire structure. The lowest most portion of type for 2.00 meter above ground level

shall be enclosed in 50 mm dia. G.I. class “B” pipe. The entire installation shall be

checked for earth resistance and certificate shall be produced.

Page 90: MAHARASHTRA JEEVAN PRADHIKARANmjp.maharashtra.etenders.in/tpoimages/mjp/tender/Tender...Maharashtra Jeevan Pradhikaran, such specifications with designs and drawings shall form a part

Contractor No. of Correction Executive Engineer

PROVIDING AND FIXING M.S. MANHOLE FRAME & COVER:

Four number of C.I. manhole frame and covers heavy type of size 90 cm x 60 cm

weighting not less than 50 kg. each set with locking arrangements be provided for

access into the tank. The cover and frame is to be painted with two coats of anti

corrosive paint. The locking arrangement shall be hinge type flat with eye.

HYDRAULIC TESTING FINISHING AND HANDING OVER THE ESR:

HYDRAULIC TESTING: WATER TIGHTNESS TEST:

After construction of reservoir is completed, it shall be tested for water tightness.

Water for this purpose will have to be supplied by the contractor. The contractor

will make his own arrangement for taking connection, necessary pumping, at his

own costs. The tank will be tested as per clause 10 to IS 3370 (Part I) latest code.

The container filled with water to its F.S.L. shall be bone dry from outside and the

total drop in the surface level over a period of seven days shall not exceed 40 mm.

unreasonable delay in giving the test will invite penal action under appropriate

clause of the contract. Hydraulic / water tightness test of structure should be carried

out as per I.S. 3370 (Part-I) – 1965 clause 10 only.

FINISHING:

The contractor shall finish all the construction joints by cement mortar 1:2

proportion from outside including plastering at places as directed so also honey

combing in any. The finish shall be entirely to the satisfaction of the Engineer.

CEMENT PAINTING:

FROM OUTSIDE AND EPOXY PAINTING FROM INSIDE:

As per Bd-0-8 (Page 391) the work will be carried out by cement based paint. Three

coats shall be applied. The colour shed shall be got approved from the competent

authority. The paint shall be cured sufficiently by making sprinkling arrangement.

Two coats of epoxy paint shall be applied to the container from inside bottom, side

walls and from inside to roof and on all inside area of container.

PAINTING LETTERS OF E.S.R.:

Marathi and English letters of suitable size will be painted with best quality paint to

the satisfaction of Engineer-in-charge indicating name and capacity of Reservoir

and name of W.S.S. etc.

SITE CLEARANCE:

Site shall be made clean and clear by disposing surplus excavated stuff as directed,

removing all excess construction materials as directed, if belonging to MJP and

removing out of premises, if belonging to the Contractor. The labour camp, if

installed at the MJP premises shall be removed before handing over. The premises

shall be generally leveled to the satisfaction of the Engineer.

HANDING OVER:

The site with structure and ancillaries along with pucca shed of store shall be

handed over to the MJP after completion of the work.

Page 91: MAHARASHTRA JEEVAN PRADHIKARANmjp.maharashtra.etenders.in/tpoimages/mjp/tender/Tender...Maharashtra Jeevan Pradhikaran, such specifications with designs and drawings shall form a part

Contractor No. of Correction Executive Engineer

ITEM NO. 2

Providing, fabrication and transportation of M.S. pipes of various dia. from contractors

materials as per IS:3589-2001 and IS:5504 (Latest version).

SCOPE:

The scope or special specifications shall cover the following works under the contract.

Fabricating M.S. pipes of various dia (O.D.) with required thick M.S. plates and testing

the pipes by any approved agency of MJP. The agency for third party inspection will be

fixed by the Superintending Engineer. The work includes transporting of fabricated pipes

from contractor’s factory to laying site.

PROVIDING M.S. PIPES:

1. Pipes to be supplied under this contract shall conform to IS:3589-2001 for welded

Steel pipes for water, subject to specific requirements given below:

2. In case supplier propose to supply pipes to the Standards superior to the above

standards no weightage will be given while evaluating the bid and for payment.

Specific Requirements.

i) Method of Manufacturer

Electric resistance welded (ERW).

Electric Fusion (arc) welded (EFW).

ii) Applicable standards (with latest edition)

IS:3589-2001 and IS:5504 (Latest version), specification for Electrically welded

M.S. pipes for water.

iii) Inspection

Inspection of M.S. pipes is divided in two parts.

Inspection during manufacturing:

a) Testing and identification of plate/ strips material for manufacturing.

b) Qualification of welding process to be used for manufacturing of pipes.

c) Qualification of welders.

d) Dimensional check before start of welding to avoid projection at a later

stage.

iv) Inspection of Ready built Pipes:

This consists of :

1. Visual inspection.

2. Dimensional check.

3. Hydraulic pressure test.

4. Mechanical tests.

a) Tensile Test.

b) Flattening test (for ERW pipes only)

c) Guided bend test for pressure.

Page 92: MAHARASHTRA JEEVAN PRADHIKARANmjp.maharashtra.etenders.in/tpoimages/mjp/tender/Tender...Maharashtra Jeevan Pradhikaran, such specifications with designs and drawings shall form a part

Contractor No. of Correction Executive Engineer

v) Testing and Acceptances Critical Visual inspection

All pipes shall be free from defects such as cracks, surface flaws, laminations, etc.

The ends shall be cleanly cut and reasonably square with axis of the pipe.

vi) Dimensions and Tolerances:

The dimensions such as O.D. and thickness shall conform to the requirement of

order as per applicable specifications. The tolerance are as under:

Outside diameter and length

Pipes Body – The tolerance on pipe body shall be as under:

Nominal Size Tolerance

Various Diameter 0.750

Pipe Ends

Ovality for distance of 100 mm from the end of the pipe shall be

as below:

Upto and including 250 mm - 1.6 mm

- 0.4 mm

Over 250 mm - 2.4 mm

- 0.8

Thickness:

Though it is specified in IS:3589-2001 no negative tolerate for thickness of plates of M.S.

is permitted as far as this contract is concerned.

The thickness will be verified by Ultrasonic thickness gauge. The thickness of shell for

various dia. Pipe should be as per requirement.

vi) Straightness:

Finished pipe shall not deviate from straightness by more than 0.2 percent of the

total length or 6 mm which is lower.

vii) Hydraulic Pressure Test:

Each pipe shall be hydraulically tested at manufacturer’s work shop for hydraulic

test pressure as calculated form the formula.

2 ST

P = D

Where :

P - Test pressure in Mpa

S - Stress in Mpa which is taken as 600 of the specified minimum tensile

strength.

T - Specified thickness in mm.

D - Specified outside diameter in mm.

Page 93: MAHARASHTRA JEEVAN PRADHIKARANmjp.maharashtra.etenders.in/tpoimages/mjp/tender/Tender...Maharashtra Jeevan Pradhikaran, such specifications with designs and drawings shall form a part

Contractor No. of Correction Executive Engineer

ix) Mechanical Test Sampling:

The procedure for sampling of pipes for various tests and criteria for conformity

shall be as given in IS;4711-1974.

x) Tensile Test:

Tensile test shall be carried out as per IS:1894-1972. The parent metal of pipe is

subjected for measurement of ultimate tensile and elongation properties. Another

sample is taken for testing of strength of the weld, ultimate tensile strength of

which should normally be more than or equal to ultimate tensile strength of which

should normally be more than or equal to ultimate tensile strength of parent metal.

However, the minimum mechanical properties as per IS:3589-2001 should be as

under.

Steel Grade (Fe) Tensile Strength (Min.

Mpa)

Percentage Elongation

(Min.)

410 410 18

xi) Fattening Test : (For ERW Pipes)

A ring not less than 40 mm length taken from one end of each selected pipes shall

be fattened between two parallel plates. The test shall taken by keeping the weld

at 90 degree to the direction of the force. No opening shall occur by fracture in the

weld until the distance between plates is less than 66% of original O.D. of pipe

and no cracks or breaks on the metal elsewhere that in the weld shall occur until

the distance between the plate is less than 33% or original O.D. of pipe.

The approved pipes are stamped on one end for identification by inspecting

authority and documented accordingly is dispatch document.

Steel’s Tensile Requirements –

Standard IS:3589-2001

Fe 410 MPa grade – B steel

Ultimate Tensile Strength 410 MPa

Yield Stress 2600 kg ./ sqm.

Design requirements internal factory test

pressure for

1000 mm dia – 2.54 MPa

Design pressure taken should be maximum of the following:

a) 1.5 times maximum working pressure.

b) Sum of maximum working pressure plus surge pressure.

Page 94: MAHARASHTRA JEEVAN PRADHIKARANmjp.maharashtra.etenders.in/tpoimages/mjp/tender/Tender...Maharashtra Jeevan Pradhikaran, such specifications with designs and drawings shall form a part

Contractor No. of Correction Executive Engineer

However, the design pressure should not exceed 5 MPa as per IS:3589-2001

specifications.

Allowable Stresses to be used:

Particulars IS:3589-2001

Specified minimum Yield stress for combined

bending and direct compression for design test

pressure without considering surge (i.e. for 1.5

times working pressure only)

2600 kg / sq.m.

1300 kg / sq.m.

For combined bending and direct tension for

design test pressure without considering surge

(i.e. for 1.5 times working pressure only).

1560 kg/ sq.cm.

For design pressure considering working and

surge pressure.

1950 kg /sq.cm.

In the event of conflict between the clauses mentioned herein and relevant IS codes,

provisions of the above specification shall prevail over.

xii) Condition of supply:

The pipes shall be supplied with one shop coat of red oxide as per IS:2074

internally and externally.

DRAWINGS:

Fabrication – Working drawings shall have to be prepared by the contractor taking into

consideration the sizes and lengths of the M.S. Plates, flats etc. The third party and MJP

should approve the drawing for fabrication of pipes as per specification in IS:3589-2001.

The pipes should be manufactured by contractor as per approved drawing. All

dimensions should be specified as per detailed specifications.

FACTORY:

The factory or arrangement of a factory equipped with all necessary electrical and

mechanical equipment for carrying out various operations involved in the work under the

tender, such as rolling, automatic welding, cutting testing etc.

The tenderer shall fabricate pipes and specials at factory and transport them to the laying

site.

The factory shall be equipped with at least the following minimum number of various

equipment and plant.

A) Plate bending machine for rolling of pipe drum

1) for pipes upto 1300 mm dia.

For plates 5 to 12 mm thick.

1 Nos.

Page 95: MAHARASHTRA JEEVAN PRADHIKARANmjp.maharashtra.etenders.in/tpoimages/mjp/tender/Tender...Maharashtra Jeevan Pradhikaran, such specifications with designs and drawings shall form a part

Contractor No. of Correction Executive Engineer

B) Automatic welding machine

i) For welding joint of steel Plates of the required

thickness.

For inside welding

For outside welding

1 Nos.

1 No.

C) Hydraulic testing machines testing machine capable of

testing of length to be fabricated.

1 No.

D) Adequate gantry or crane of required capacity

1 No.

E) Channel bending machine suitable for rolling ring girders

for pipes of the required diameters.

1 No.

F) Lathe for machine flange rings plates etc.

1 No.

G) Lathe for machine expansion joints of required diameter.

1 No.

H) Mobile crane for loading, unloading of pipes Adequate for the

job.

I) Compressing equipment for plates of the required

thickness to required curvatures.

The intending contractor shall have to satisfy the authorities about his capacity to

fabricate or get fabricated the pipes and specials as covered in the tender scope, within

the time specified. The factory shall have to provide minimum equipment as listed above

and additional equipment. If required to maintain schedule progress n the work, if the

Engineer so directs. Adequate Fabrication facilities for specials and for testing shall be

provided.

PIPE SUPPLY OF MATERIALS:

The MJP will not supply M.S. materials such as plates, flats etc. required for the

fabrication of pipes. All requirement of such materials will have to be arranged by the

contractor from open market. The plates required for fabrication of M.S. pipes under this

tender shall conform to IS:2062 Grade ‘B’ and also meet the requirement as per IS:3589

Fe-410 grade for it’s tensile strength.

The conveyance of fabricated material from workshop to site of work shall be deemed to

have been covered in the relevant items of fabrication of pipes, specials etc. the

contractor should note that the steel plates and other structural steel required for

fabrication of specials is to be procured by him from open market at his cost. The

contractor has to procure such plates in several stages as the circumstances demand, or as

directed by Engineer-in-charge.

Page 96: MAHARASHTRA JEEVAN PRADHIKARANmjp.maharashtra.etenders.in/tpoimages/mjp/tender/Tender...Maharashtra Jeevan Pradhikaran, such specifications with designs and drawings shall form a part

Contractor No. of Correction Executive Engineer

The Pradhikaran shall not however supply any steel or structural steel to the contractor

for his use for preparing jigs, testing arrangements, platforms etc. in the factory or in the

field. The contractor shall have to make his own arrangements for procuring them at his

own cost immediately on receipt of work order and the Pradhikaran shall not entertain

any request for extension of completion period or compensation on increase in cost etc.

SPECIFICATIONS FOR FABRICATIONS OF PIPE:

CUTTING OF PLATES TO SIZE:

The pipe drums shall normally be fabricated with any one longitudinal joint. However, if

the plates of exact size are not available, the contractor shall fabricate pipe drums with

two longitudinal points at the approval of the Engineer.

The plates shall cut on all the four sides to the exact dimensions and shape required by a

suitable plate cutting machine such as oxyacetylene cutting shall not be more than 8 mm

in width and length. After rolling / bending all the edges of the plates shall be cleaned by

brushing, grinding. The standard length of fabricated pipes shall be in meters.

The plates shall be given a bevel at the edges depending upon the welding machine to be

used by the contractor. Ends of the pipes fabricated shall necessarily have ‘V’ edges, with

an included angle of 75o + 2.5o in case of manual welding as in the field, manual

welding is to be done. Fore pipes of diameter less than 1200 mm. In the factory where

automatic machine having sufficient penetration is used the edges in the pipe may be

square cut, the type of joints to be adopted in the factory shall depend on the type of

welding machine to be used and the method of welding to be adopted. Experimental

welding shall be demonstrated by the contractor to the Engineer-in-charge in the factory

and testing of samples there from shall be done by the Engineer-in-charge at contractor’s

cost before finally deciding the voltage and current characteristics for proper welding to

be adopted. After the plates are cut, the edges shall be made smooth to remove all

inequalities by means of polishing grinder. Care shall be taken to see that cut edges of the

plate are perfectly straight. Jigs to be used for this purpose shall be checked before the

plates are rolled into pipes drums. Corrections if any shall be made re-cutting, if

necessary, if any plate or flat is found to be warped. The defect shall be removed by

putting the plate into roller press at the contractor’s cost. If the contractor finds that some

of the plates are laminated or are badly corroded, these shall be stacked separately and

shall not be used for fabrication of pipes etc. The contractor shall not be entitled for any

extra claim on account of handling and cutting plates, which are subsequently rejected by

the Engineer.

Marginal cutting as well as left over pieces of plates and other steel sections shall be

collected by the contractor and stacked separately in the yard.

ROLLING OF PLATES:

The plates cut to exact size shall be put into rolling machine to form the pipe drum of the

required diameter. The contractor shall adjust the rolling machine so as to give an

uniform curvature to the pipe drum throughout its circumference. The curvature shall be

checked by the contractor’s foreman during the process of rolling and rolling shall be

repeated till such state that exact curvature in obtained. Contractor shall roll the pipe

Page 97: MAHARASHTRA JEEVAN PRADHIKARANmjp.maharashtra.etenders.in/tpoimages/mjp/tender/Tender...Maharashtra Jeevan Pradhikaran, such specifications with designs and drawings shall form a part

Contractor No. of Correction Executive Engineer

drum even after longitudinal welding is done. If proper curvature is not obtained any

testing on weld shall be carried out only after welding or rerolling of pipe. If required.

Heating of plates shall not be allowed to have the desired curvature.

TACKING OF DRUMS:

Rolled drums shall then be taken to the assembly platform for tacking for longitudinal

welding. Where machine welding is to be done there shall be no need to have a gap

between the faces depending upon penetration obtained. If hand welding is permitted by

the Engineer, gap shall be between 2 to 4 mm. Clamp spiders, tightening rings or any

other approved gadgets shall be used during assembling and taking.

The contractor shall put serial numbers, plate thickness and letter MJP inside the drums

before these are tacked.

The tacked drums shall then be taken to the assembly platform for taking them to make

pipes of 6 meter lengths.

Maximum length shall not exceed 12 meters and the contractor shall comply with such

orders without claiming any additional cost for the same.

During tacking, care shall be taken to see that the longitudinal joints of abutting pipes

drums are staggered as 90o as shown on the drawings.

The assembly shall be truly cylindrical and without kinks, the faces being exactly at right

angles to the axis of the pipe. The contractor shall provide at his cost suitable gadget to

check the corrections and shall be as per Para 8 of IS:3589.

WELDING OF PIPES:

Assembly as described above shall then be transferred to an automatic welding machine

of approved make for full welding. All the circumferential joints as well as longitudinal

joints shall be done on automatic welding machine only. The Engineer may at his

discretion allow hand welding only for the sealing run or for some minor welding. The

Engineer-in-charge, during the progress of work, shall issue working drawings or

instructions specifying the details of welding joints for the different fabrication work.

Electrodes of approved make conform to IS:814 and size only shall be used for welding

depending upon the thickness of the plates and the type of joint. The current and the arc

voltage required for the machine shall be decided after the experimental welding is done.

All expenses for these experiments shall be borne by the contractor. The current and the

arc voltage once decided shall not be altered. Without the permission of the Engineer-in-

charge for the particular thickness of plate. The welding shall conform to IS:822 and 823.

In case of thin plates gas welding may be resorted to Gas Welding also shall be subject to

the same specifications and tests as those for the electric welding.

The welders employed by the contractor shall be sufficiently experienced and qualified as

per relevant IS in welding works to execute the works of standards as specified in IS:817

and type of welding work carried particularly for this type of work. Their work shall be

Page 98: MAHARASHTRA JEEVAN PRADHIKARANmjp.maharashtra.etenders.in/tpoimages/mjp/tender/Tender...Maharashtra Jeevan Pradhikaran, such specifications with designs and drawings shall form a part

Contractor No. of Correction Executive Engineer

tested by the Engineer-in-charge before they are entrusted with the job and also from time

to time during the progress of the work. The contractor shall keep the record of welding

as may be prescribed by the Engineer-in-charge to enable him to know the performance

of each welder. Only the person permitted by Engineer-in-charge shall carry out welding

work. Hand welding shall preferably be carried out by a pair of welders. A joint entrusted

to a particularly individual or a part shall as far as possible be completed only by them in

all respects indicating sealing run.

WELDING JOINTS

ELECTRODES:

Welding electrodes to the used for welding in this contract shall conform to the Indian

Standard Specifications IS:814 (Specification for covered electrodes for metal arc

welding of mild steel). The contractor shall use standard electrodes, depending on the

thickness of the plate to be welded and the type of joint. The contractor shall also use

standard current and arc voltage, required for the machine as per the manufacturer’s

directions. The contract will use only the approved welding consumables by MJP.

TYPES OF WELDING JOINTS:

The circumferential joints of the pipes shall be butt welded. With required number of

runs internally and externally. All fillet welds shall have a throat thickness not less than

0.7 times the thickness of the pipe to be welded.

WELDING PROCEDURE:

All part of pipes, specials, etc. shall have all loose scale, slag, rust, paint and any other

foreign material removed with wire brush and left clean and dry. All scale and slag shall

be removed from each run of weld when that run is completed. Welding shall conform to

relevant provisions of IS:3589 and IS:816:1969 (Latest revision).

TESTING OF WELDED JOINTS:

Welded joints shall be tested in accordance with procedure laid down in Indian Standard

Specifications IS:3600 (Code of Practice for Testing Fusion Welded Joints and Weld

Metal in Steel).

At least one test specimen shall be taken out for testing per ten joints done Test pieces

shall be taken out from the places pointed out by the Engineer. They shall be machined

and tested as early as possible. /The shape of the test pieces removed for testing shall be

such that it shall give the specimen of the required dimensions with the weld in the

middle of the specimen and at same time leave the hole in the pipe with rounded corner.

This hole shall be patched plated with a plate of suitable size cut from a separate pipe of

same diameter. It must ensure good butt weld.

TESILE TEST:

The test specimen taken perpendicularly across the weld shall be shaped in accordance

with Indian Standard Specifications IS:223. The tens on test specimen shall be machined.

The protruding welded portion from inside as well as outside shall be removed by

machining before the specimen is tested. If the specimen shows defective machining or

Page 99: MAHARASHTRA JEEVAN PRADHIKARANmjp.maharashtra.etenders.in/tpoimages/mjp/tender/Tender...Maharashtra Jeevan Pradhikaran, such specifications with designs and drawings shall form a part

Contractor No. of Correction Executive Engineer

develops flaws not associated with welding. It shall be discarded and another specimen

substituted. The welded joint shall show a strength not less than the minimum tensile

strength for the plate in accordance with IS:2062.

BEND TEST:

Bend test specimen shall also be prepared in the same fashion as they tensile test

specimen. The specimen shall stand being bend cold through 180 around a pin that has a

diameter equal to 4.5 times the plates thickness without developing cracks. For this test,

face representing inside of the pipe shall be placed next to the pin.

TRE-PANNED PLUGS:

Tre-panned plugs shall be taken out from any welded portion as pointed out by the

Engineer. These plugs shall not show any defects in welding such as inclusion of slag,

below holes, cavities etc. The plug shall be 12 mm in diameter and shall be taken out by

means of suitable electrically operated hack-saw. Such holes in the pipe shall either be

filled back by inserting a steel stud and welding around or threading the hold and

providing suitable G.I. plug. This test shall be done only if considered necessary by the

Engineer.

PROCEDURE ON FAILURE TEST SPECIMEN:

If the test specimen fails in either tensile or bend test or in both, two additional test

specimen shall be taken out from the same section and shall be tested for tensile and bend

tests. If any one of them fails, extensive gousing and re-welding shall be done for the

welded joints in that section to the full satisfaction of the Engineer. However, if both the

samples give satisfactory result, the joint from which the original sample was taken and

had failed shall be repaired to the satisfaction of the Engineer, by gousing and welding

etc. at contractor’s cost.

Welder, who had done the welding of the joint that has failed shall be solely held

responsible. Since all other factors like electrodes, current arc voltage etc. are already

controlled, negligence on the part of the welder only is responsible for such failure. For

first such failure the welder shall be warned and if the welded joint done by him fails for

the second time, he shall be removed from the job.

WORKMANSHIP:

All pipes shall be fabricated out of steel plates of Fe.410 grade shall be free from

excessive pitting. Crack surface flaws, laminations or any other defect. All such defective

plates shall be stored separately and should not be sued. All the pipes shall be properly

stored in different stacks size wise. The pipes shall be truly cylindrical and straight in

axis, acceptable tolerance being as per IS:3589. The ends of the pipes shall be accurately

out with level for field welding depending on sizes as specified earlier. The tolerance in

outside diameter for beveled and for butt welding shall be as per Table 2 para 12 IS:3589.

In case of pipes to which flange adopters are to be fixed, the external diameter of the pipe

shall not be more than + 1 mm. Than the theoretical one.

Page 100: MAHARASHTRA JEEVAN PRADHIKARANmjp.maharashtra.etenders.in/tpoimages/mjp/tender/Tender...Maharashtra Jeevan Pradhikaran, such specifications with designs and drawings shall form a part

Contractor No. of Correction Executive Engineer

The contractor shall have to roll the pipes several times to achieve this accuracy. The

longitudinal welding at the ends of the pipes shall be ground smooth and flush with the

plates for atleast a length of 200 mm from the ends. No additional payment shall be made

for re-rolling or grinding the welds as described below.

Any minor repair in welding that is required to be done shall be done only after obtaining

the permission from the Engineer-in-charge. Whenever he finds that the work has not

been done by the contractor as specified above and to his satisfaction and the pipes

fabricated have injurious defects, these shall be liable for rejection. No payment shall be

made to the contractor for such fabrication and welding and the cost of such wastage

shall be recovered from the contractors bills on this account. Decision in this regard of

the Engineer-in-charge shall be final and binding on the contractor.

TEST ON WELDS:

The test on welds shall conform to para 14 of IS:3589. The testing for tensile bend and

flattering test for circumferential joints shall confirm to para 14 of IS:3589.

HYDRAULIC TESTING OF FABRICATED PIPES AT FACTORY:

The pipe length fabricated shall be as specified earlier above. The contractor shall

provide all the required machines and apparatus for testing all the pipes at the factory.

The arrangements made by the contractor for hydraulic testing of pipes shall be subject to

the approval by the Engineer. The contractor shall paint inside the serial number of pipe,

the diameter and the plate thickness and letters MAHARASHTRA JEEVAN

PRADHIKARAN as well as the date of the test etc. as directed by the Engineer. The

pipes shall be inspected through before testing for any apparent defect in welding and the

contractor shall repair such defects by gousing and rewelding. Such pipes will be laid

only on approval of the Engineer-in-charge. Necessary provisions for storage tank for

water for testing, water pumping arrangements, if necessary and making available the

required water shall be made by the contractor.

Hydraulic testing of pipe manufactured will be done by inspection through third party at

the fabrication site and to the satisfaction of the Engineer-in-charge or his authorized

representative. Third party will be approved by MJP and charges for pipe testing will be

borne by the contractor.

Accurate pressure gauge of approved make shall be mounted on one end of the pipe to

indicate the pressure inside the pipe being tested. Each pipe shall be tested to the test

pressure as under and as per IS:3589-2001.

For M.S. Pipes - 12 kg/cm2

The Engineer at his discretion may accept untested pipes if the total length of fabricated

pipes of that particular diameter is less than 50 meters.

The pressure shall be applied gradually by approved means and shall be maintained at

least for 10 minutes or till inspection by third party approved by MJP and Engineer-in-

charge during which time the pipes be hammered throughout its length with sharp blows

Page 101: MAHARASHTRA JEEVAN PRADHIKARANmjp.maharashtra.etenders.in/tpoimages/mjp/tender/Tender...Maharashtra Jeevan Pradhikaran, such specifications with designs and drawings shall form a part

Contractor No. of Correction Executive Engineer

with 1 kg. hand hammer. The pipe shall stand the test without showing any sign of

weakness, leakage, oozing or seating. If any leakage is observed, on approval of

Engineer-in-charge, it shall be repaired by gousing and rewelding or as directed by him.

No separate additional payment shall be made for dewatering, gousing, repairing and

retesting and the handling required to be done for such pipes.

MEASUREMENT AND PAYMENT FOR PROVIDING AND FABRICATING OF

PIPES:

Providing and fabrication of pipes shall be measured in Running meter of pipes

fabricated and shall include the cost of supplying all the labour, material, machinery for

loading, unloading if any, handling plate, cutting and shaping the same to the required

size and shape, forming “V” edge, rolling the plates to form pipes drums, assembling the

drums to form pipes, tacking and full welding of all circumferential and one longitudinal

joints on the automatic welding machine and stacking them sizewise in the yard. The rate

includes loading, unloading and transportation of pipe from workshop to work site. No

secured advance shall be granted against M.S. plates required for fabrication of pipes.

Only 80% payment shall be released after supply of pipes of works site and remaining

10% payment shall be released after lowering, laying pipes and balance 10% after giving

satisfactory hydraulic testing of pipes laid.

NOTE:

The alignment of pipe line is above steel turss pipe over bridge across railway tracks near

Vasai Road Railway Station, hence there is limited space for stacking pipes.

ITEM NO. 3

PROVIDING SUPPLYING ISI STANDARD M.S. SPECIALS ETC.:

GENERAL:

The main specials and appurtenances to be fabricated under this contract are as per list,

mentioned below. The typical drawings for these to be provided luring execution, by the

contractor.

The contractor shall give working drawings for the specials and appurtenances for

fabrication thereof depending on the site condition and the Engineer-in-charge shall

check and accord approval.

(a) Plain ended specials or plain ended branch flanged special.

(b) “Y” branches and Tees

Tapers

Straps

And other miscellaneous specials and appurtenances. Such as domes, dished manhole

covers and other specials as required.

MATERIALS FOR SPECIALS:

The material of the fabricated specials should be same as that of the pipe material

specified and confirming to IS:2062, it includes bends required, M.S. tapers, tees, etc.

complete as well as.

Page 102: MAHARASHTRA JEEVAN PRADHIKARANmjp.maharashtra.etenders.in/tpoimages/mjp/tender/Tender...Maharashtra Jeevan Pradhikaran, such specifications with designs and drawings shall form a part

Contractor No. of Correction Executive Engineer

WORKMANSHIP:

ONE PIECE CANT AND COMPOSITE BENDS:

Composite bends shall consist of two or more pieces joints together to give the required

deflection. Detailed drawings of the composite bends required on the work shall be

prepared by the contractor from time to time before cutting the plates. The contractor

shall first compute the development of the shape and shall make templates wherever

necessary if the templates cannot be prepared the shape be drawn on the plate and cut

taken.

“Y” BRANCHES AND TEES:

“Y” Branches and Tees also shall be fabricated in one or more pieces, depending on the

size required and the sizes of plates available. Incase of Tees and “Y” branches, if the

diameter of the branch is more than 1/3 diameter of the main, then they only shall be paid

under respective items of works for fabrication of pipe, pipes saddles, cutting, welding

etc.

DISHED MANHOLE COVER:

For fabrication of dished manhole covers, the contractor shall use special dress in the

hydraulic press to obtain the required shape. The plate shall be cold pressed and no

heating shall be permitted.

PLUG PLATES:

Plug plates shall be fabricated as shown on the drawings. The size of plug may vary from

25 mm to 40 mm diameter as directed by the Engineer. The hole for plug in the plug plate

shall be cut, drilled and threaded exact size and the contractor shall provide a suitable G.I.

plug for every plug plate.

LADDERS:

Ladders shall be fabricated from M.S. plates flats and bars as per the drawing and shall

have the curvature suitable for the diameter of the pipe which they are to be fixed, as

indicated in the drawings.

LOOSE FLANGE RINGS:

Loose flange rings shall be cut of the plates of suitable thickness as directed by the

Engineer. In order to avoid the wastage of steel plates, shall be cut in maximum 4

segments, to form a complete ring when welded together. Bolt holes of required size at

the exact c/c distance in required pitch circle shall be drilled through the flange rings.

They shall be mounted and lack welded on pipes / specials etc. as shown on the drawing

whenever required.

STIFFNER RINGS:

Stiffner rings shall be cut out of the M.S. channel of suitable size as required by the

Engineer-in-charge. In order to avoid wastage, these shall be cut in segments to form

rings when welded together. These shall be provided of site in segments and shall be

welded on the pipes as per instructions of the Engineer-in-charge.

Page 103: MAHARASHTRA JEEVAN PRADHIKARANmjp.maharashtra.etenders.in/tpoimages/mjp/tender/Tender...Maharashtra Jeevan Pradhikaran, such specifications with designs and drawings shall form a part

Contractor No. of Correction Executive Engineer

PRESSURE AND NON-PRESSURE TYPE BLANK FLANGES:

These shall be cut out from the plates of suitable thickness as required by the Engineer.

Pressure type blank flanges shall be strengthened by welding over them angles as

directed by the Engineer. Suitable handles shall be welded to the blank flanges.

SADDLE PIECES:

Saddles pieces of various diameters shall be fabricated to fit properly on the pipes.

TAPERS AND WEARING PLATES:

The tapers shall be fabricated in one or more pieces as may be necessary according to

their lengths and sizes of plates available. These shall have stiffening rings fixed on them

as per details supplied by the Engineer-in-charge during fabrications.

SPECIAL CARE TO BE TAKEN DURING FABRICATION OF COMPOSITE

BENDS, TEES AND ‘Y’ BRANCHES:

The testing of these specials is not envisaged at the fabrication stage. These shall be

subjected to test when the complete pipe line is tested hydraulically. In view of this, the

contractor in his own interest shall fabricate any welded specials with all due care so that

there is no failure of any welded joint during testing of the completed pipe line, which

will invite dewatering the main, repairing and retesting. If directed by Engineer-in-

charge, the contract will have to manufacture M.S. bends from the available M.S. pipes

by cutting and welding the pipes pieces as required including giving a covering coat of

gray graphite paint. In such cases payment will be proposed for cutting and welding

operations under relevant item of work and no payment will be make under this item.

MEASUREMENT AND PAYMENT:

Fabrication of the various specials appurtenance shall be measured and paid under the

relevant item in the Bill of Quantities on weight basis. These items shall include the cost

of supply of all labour, material and machinery for fabricating these specials and

appurtenances as per specifications and shall include all cost of conveying material from

factory to site and handling materials within the fabrication yard stacking them properly

in the yard and all other ancillary works involved. Deduction for bolt holes shall not be

made while computing weight for payment. 10% amount for this item shall be withheld

till satisfactory hydraulic test is given for M.S. specials and minor fixtures procured and

fabricated.

ITEM NO. 4:

SPECIFICATION FOR MANUFACTURE SUPPLY AND DELIVERY OF

SLUICE VALVE:

GENERAL :

The Sluice Valves proposed to be procured through this tender are to be used for drinking

water supply schemes under execution.

WORK UNDER THIS CONTRACT:

The works entitled manufacture, supply and delivery of Sluice Valves for transmission

mains shall comprise the manufacture, supply and delivery of the goods as mentioned in

the Bill of Quantities.

Page 104: MAHARASHTRA JEEVAN PRADHIKARANmjp.maharashtra.etenders.in/tpoimages/mjp/tender/Tender...Maharashtra Jeevan Pradhikaran, such specifications with designs and drawings shall form a part

Contractor No. of Correction Executive Engineer

a) Sluice Valve PN 1.0 of IS:2906:1984 of 350 mm dia size.

NOTE:

The above goods to be used for conveyance of portable water at temperatures varying

from 10 degree centigrade to 40 degree centigrade.

The tender price shall include all labour and machinery and all materials necessary for the

proper manufacture of the goods for tests at the contractors works for the insurance and

for delivery to works for the proper maintenance and for discharging every obligations

and requirement of the contract, in accordance with the intent of the contract documents,

as stated in the General conditions of contract.

STANDARDS:

Where reference is made to a particular standard. It shall be the latest revision of the

Indian standard institution. Unless otherwise specified, the sluice valves shall be in

accordance with the provisions of IS:780:1980 and IS:2906:1984 for sizes of the sluice

valves covered under relevant standards.

MARKING OF SLUICE VALVES:

Each sluice valve shall be marked as IS:2906:1984

PACKING AND HANDLING:

The contractor shall dispatch from the manufacturer’s works goods adequately protected

to prevent damage and deterioration during transportation and storage etc. The packing is

to be quite obust to withstand rough handling during the transit by road/ rail/ sea and

storage.

Each package / create will contain sluice valve of one size only in relevant class. The

packing procedure followed shall be in accordance with para 12 of IS:780:190 and para

12.1 of IS:2906:1984.

The contractor shall use proper handling equipment or follow suitable handling method

as approved by the Engineer to unload the materials at the delivery site to prevent

damage to the good and equipments.

INDEPENDENT AND LOCAL TEST:

The contractor will have to arrange independent test from Engineer-in-charge for all the

valves supplied under this contract and cost of such testing is deemed to be included in

the offer quoted by the contractor.

The contractor will have to produce necessary test certificate issued by the manufacturer

regarding performance of satisfactory test.

INFORMATION GIVEN TO CONTRACTORS:

The following information as required vide Appendix – A of IS:780 and Appendix – D of

IS:2906 is furnished giving specific requirements of the supply.

Page 105: MAHARASHTRA JEEVAN PRADHIKARANmjp.maharashtra.etenders.in/tpoimages/mjp/tender/Tender...Maharashtra Jeevan Pradhikaran, such specifications with designs and drawings shall form a part

Contractor No. of Correction Executive Engineer

a) All sluice valves shall be with stainless steel spindles. The spindles shall be with

square threads. The stainless steel will conform to IS:7703:1973. Welded or

screwed collars on spindles shall not be permitted.

b) All sluice valves shall be of non-rising spindle types.

c) All sluice valves shall be tested for closed and condition only.

d) All sluice valves shall be provided with caps.

e) All sluice valves shall be installed in a vertical position on a horizontal pipe lines.

f) All valves shall be manually operated.

g) No tail piece or adapter be supplied with the valves.

h) No by-pass arrangements be provided.

Approved makes of M.J.P. will be acceptable only.

The Vendor should be as per approved list of MJP.

DISTANCE PIECES:

Distance piece shall provided when the gap between the pipe faces to be jointed is more

than 30 cms. Measured in the evening. Distance pieces shall be cut from the pipe pieces

on site or can be cut in factory.

TAPERS AND BENDS ETC.:

These shall be fabricated in the factory and shall be welded on site as per

requirements. Laying of tapers shall be paid for laying as specials for the diameter

in the large size. Bends shall be measured along the mean length.

FIXING DIFFERENT VALVES:

A) THE VALVE SHALL BE BROUGHT BY CONTRACTOR:

The item includes fixing of valves at site of work including cost of

transportation, loading and unloading etc. all materials and labours required

for fixing including testing. The size of nuts, bolts, and packing shall be as

per I.S. specifications and suitable for the type of valves and as per the

directions of Engineer-in-charge. The location of the valves shall be decided

by the Engineer-in-charge.

B) APPURTENANCES:

i) Appurtenance such as sluice valves, shall be supplied by the

contractor. The contractor shall transport them to the site and fix them

at the place as shown on the drawings or as directed by the Engineer-

in-charge.

Page 106: MAHARASHTRA JEEVAN PRADHIKARANmjp.maharashtra.etenders.in/tpoimages/mjp/tender/Tender...Maharashtra Jeevan Pradhikaran, such specifications with designs and drawings shall form a part

Contractor No. of Correction Executive Engineer

ii) Before any of the valves are fixed at the pre-determined position,

these shall be cleaned, greased and it shall be checked that these are in

proper working condition. The valves shall be fixed in true plumb and

level. Sluice valves, shall be properly supported on wooden sleepers

till the Anchor block casted sets.

DISPOSING OFF SURPLUS EXCAVATED MATERIAL:

The surplus excavated stuff shall be disposed off by mechanical means beyond 50

meter upto necessary lead as directed by Engineer-in-charge. The item includes cost

of loading, unloading, transportation, all labour etc. complete and stacking and

disposing off surplus stuff as directed.

The work of disposing off surplus excavated stuff shall be carried out as per the

specification No. B-17 page No. 25 at Standard Specification Red Book of P.W.D.

Supply of M.S. Plates, conforming to I.S. 2062-1999 and should be of Fe410 Grade-

B only.

The item shall include supply of M.S. plates for fabrication of M.S. pipes and

required M.S. plain and flanged specials etc.

ALIGNING AND FIXING STEEL WORK ETC.:

Work shall be carried out as per standard specifications No. Bd-C-3 Page 275, Bd-C-6

Page No. 277, Bd-C-2 Page 275, Bd-C-8 Page 278 and as directed by Engineer in charge

ITEM NO. 5:

Providing and applying one coat of Gamma coating or equivalent such as Dr. Bake,

Asian Paints epoxy primer 50 to 60 microns thick etc.

This work should carried out as per manufactures specification.

ITEM NO. 6:

PROVIDING FUSION BONDED EPOXY COATING TO REINFORCEMENT

BARS ETC.:

1. COATING MATERIALS:

The coating material shall meet the requirements specified as per I.S.

The patching or repairing material or both shall be compatible with the coating,

inert in concrete and feasible for repairs at the coating plant or in the field. This

material shall be approved by the purchaser prior to use. The patching or repair

shall be performed in accordance with the

2. REINFORCING STEEL

Steel reinforcing bars to be coated shall conform to IS:1786:1985.

Page 107: MAHARASHTRA JEEVAN PRADHIKARANmjp.maharashtra.etenders.in/tpoimages/mjp/tender/Tender...Maharashtra Jeevan Pradhikaran, such specifications with designs and drawings shall form a part

Contractor No. of Correction Executive Engineer

3. SURFACE PREPARATION:

The surface of the steel reinforcing bars to be coated shall be cleaned by abrasive

blast cleaning to near white metal. The surface profile shall be free from mill

scale, rust and foreign matter when viewed under well-lit conditions.

The coating shall be applied to the cleaned surface as soon as possible after

cleaning. Any formation of rust blooms on the cleaned bars are to be removed by

blast cleaning before application of the coating. However, in no case shall the

coating be delayed more than eight hours after cleaning unless otherwise

permitted by the purchaser.

4. APPLICATION OF COATING:

The coating shall be applied as an electro statically charged dry powder sprayed

onto the grounded steel bar using an electrostatic spray gun. The powder may be

applied to either a hot or cold bar. The coated bar shall be given a thermal

treatment specified by the manufacturer of the epoxy resin which will provide a

fully cured finish coating. Temperature shall be controlled as recommended by

the manufacturer of the coating to ensure a workman like job without blistering or

other defects.

5. REQUIREMENTS OF COATED BARS:

Coated Thickness

For acceptance purposes at least 90 per cent of all coating thickness

measurements shall be 0-1 mm to 0.3 mm after curing. The coating thickness

limits do not apply to patched areas. A minimum of 15 measurements shall be

taken approximately evenly spaced along each side of the test bar. At least 90 per

cent of these measurement shall be within the specified limits.

NOTE: By mutual agreement between the purchaser and the manufacturer,

thicker coating may be accepted where the bars are not to be bent on worked after

the coating has been applied.

CONTINUITY OF COATING:

The coating shall be visually inspected after curing for continuity of the coating and shall

be free from holes, voids, contamination, cracks and damaged areas discernible to the

unaided eye. In addition there shall be not more than an average of two holidays per 300

mm when tested in accordance with 8.2

Note : Holiday means a pinhole not discernible to the unaided eye.

ADHESION:

The adhesion of coating shall be evaluated on a representative number of bars selected in

accordance with 9.4 from each production lot. No visible cracks or disbanding in the

coating on the outside radius shall be allowed when tested in accordance with 8.3

Page 108: MAHARASHTRA JEEVAN PRADHIKARANmjp.maharashtra.etenders.in/tpoimages/mjp/tender/Tender...Maharashtra Jeevan Pradhikaran, such specifications with designs and drawings shall form a part

Contractor No. of Correction Executive Engineer

6. TEST METHODS:

The thickness of the coating shall be measured on the body of reinforcing bar

between deformations and ribs or both, on a straight length. Non-destructive

coating thickness measurements using magnetic gauges shall be used.

‘Pencil’ type pull-off gauges which require the operator to observe the reading at

the instant the magnet is pulled from the surface and do not hold shims tightly

against the steel plate during calibration are not recommended for use.

Gauge calibration with shims shall be performed on a smooth, clean, low-carbon

steel plate (at least 75 x 75 x 13 mm) rather than on a clean reinforcing bar.

A correction factor defining the effect of the bar preparation process shall be

obtained as the difference between (a) the average of the 10 gauge readings on a

cleaned but uncoated reinforcing bar of the size and lot being coated and (b) the

average of 5 gauge readings on a smooth mild steel plate. This correction factor

shall then be subtracted from all subsequent gauge readings on coated bars.

Fixed probe gauges shall be checked to ensure that the force generated by the

spring loaded probe housing in sufficient to ensure intimate contact between the

probe tip and the coating on the curved bar surface. If intimate contact does not

result, it will be necessary to remove the probe housing and utilize hand pressure

to obtain valid indicated thicknesses.

HOLIDAYS:

A 67.5 volts holiday detector shall be used in accordance with the detector

manufacturer’s instructions. The detector may be an in line DC detector or a hand held

DC detector.

ADHESION OF COATING:

The adhesion of the coating shall be evaluated by bending production coated bars 120

degrees (after rebound) around a mandrel of size as prescribed in Table 1. The bend test

shall be made at a uniform rate and shall take upto 90 seconds to complete. The two

longitudinal deformations shall be placed in a plane perpendicular to the mandrel radius

and the test specimen shall be at thermal equilibrium between 250 and 35

0C.

NOTE : The fracture partial failure of steel reinforcing bar in the bend test for adhesion

of coating shall not considered as an adhesion failure of the coating.

TABLE 1 MANDREL DIAMETER FOR BEND TEST REQUIREMENTS:

(Clause 8.3)

Bar Diameter (mm) Mandrel Diameter (mm)

8 80

10 100

12 100

16 125

18 150

Page 109: MAHARASHTRA JEEVAN PRADHIKARANmjp.maharashtra.etenders.in/tpoimages/mjp/tender/Tender...Maharashtra Jeevan Pradhikaran, such specifications with designs and drawings shall form a part

Contractor No. of Correction Executive Engineer

20 150

22 2--

25 Q2--

29 225

32 29-

36 280

40 400

45 450

50 500

7. FREQUENCY OF TEST:

Coating thickness shall be tested at a frequency of not less than one full length bar

every twenty bars for each size.

Continuity of coating shall be determined by testing one full length be in every

twenty bars for each size.

Coating thickness over the whole of the coated bar section shall be determined by

sectioning and examining one bar in every twenty tonnes for each size.

For testing adhesion of coating, samples shall be selected from each size

according to the frequency given below:

Nominal size of Bar (mm) No. of Samples

Upto 16 1 for every 1 tonnes

Above 16 and upto 25 1 for every 2 tonnes

Above 25 1 for every 4 tonnes

8. RETEST:

If the specimen for coating thickness or for adhesion of coating fails: meet the

specified requirements, twice the number of samples

9. HANDLING AND IDENTIFICATION

All systems for handling coated bars shall have padded contact areas. All bunding

bands shall be padded or suitable banding shall be used to prevent damage to the coating.

All bundles of coated bars shall be lifted with a strong back, spreader bar, multiple

supports, or a platform bridge to prevent bar-to-bar abrasion from stags in the bundles of

coated bars. The bars or bundles shall not be dropped or dragged.

The identification of all reinforcing bars shall be maintained throughout the

fabrication and coating processes to the point of shipment.

10. INSPECTION:

All tests and inspection shall be made at the place of manufacture prior to

shipment, unless otherwise specified.

Page 110: MAHARASHTRA JEEVAN PRADHIKARANmjp.maharashtra.etenders.in/tpoimages/mjp/tender/Tender...Maharashtra Jeevan Pradhikaran, such specifications with designs and drawings shall form a part

Contractor No. of Correction Executive Engineer

PERMISSIBLE COATING DAMAGE AND REPAIR AFTER COATING

APPLICATION:

Coating damage due to fabrication and handling need not be repaired in case where the

damages area is 40 mm2 or smaller.

All damaged areas larger than 40 mm2 shall be repaired with patching material.

Maximum amount of damage shall not exceed 2 percent of the surface area of each bar

(total of damage in 13.1 and 13.2)

Patching shall be done in accordance with the patching material manufacturer’s

recommendations.

12. REJECTION:

Coated bars represented by the samples that do not meet the requirements of this

specification shall be rejected by mututal agreement between the purchaser and the

manufacturer, such bar may be stripped of coating, recleaned, re-coated, and resubmitted

for acceptance test in accordance with the requirements of the specification.

MANUFACTURER’S CERTIFICATE:

13. If requested by the purchaser, the manufacturer shall furnish, at the time of

shipment, a written certificate that the coated reinforcing bars meet the requirements of

this specification.

14. IDENTIFICATION AND MARKING:

The manufacturer or supplier shall mark the bars in such a way that all finished bars can

be traced to the cast from which they are made or the original identification mark of the

bars.

Each bundle containing the bars may also be suitably marked with the Standard Mark in

which case the concerned test certificate shall also bear the Standard Mark.

For each bundle of bars a tag shall be attached indicating the Cast No. / Lot No. grade

and size of the bars.

Contractor Executive Engineer

M.J.P. Water Management Div., Virar

Page 111: MAHARASHTRA JEEVAN PRADHIKARANmjp.maharashtra.etenders.in/tpoimages/mjp/tender/Tender...Maharashtra Jeevan Pradhikaran, such specifications with designs and drawings shall form a part

Contractor No. of Correction Executive Engineer

MAHARASHTRA JEEVAN PRADHIKARAN MAHARASHTRA JEEVAN PRADHIKARAN WATER MANAGEMENT CIRCLE, NEW PANVEL

MAHARASHTRA JEEVAN PRADHIKARAN WATER MANAGEMENT DIVISION, VIRAR

Name of Work : Vasai-Virar Sub-Regional Water Supply Scheme

(Surya) stage-II Part-I.

Designing, Providing and constructing RCC ESR of

capacity 1.25 ML @ Tulinj, Nallasopara (E).

DECLARATION BY THE CONTRACTOR

I hereby declare that, I have made myself / ourselves throughly conversant with the local

conditions regarding the materials, such as stones, murum, sand, availability of water etc.

and labour on which I have based my rates for this work. The specifications and

requirements of lead for this work have been carefully studied and understood by me before

submitting this tender. I undertake to use only the materials to be approved by the

Executive Engineer-in-charge of this work or his Authorised representative, before starting

the work and also to abide by his decision.

I hereby undertake to pay the labours engaged in the work as per minimum wages Act –

1984 and its amendments from time to time applicable to the zone concerned.

Contractor’s Signature

Page 112: MAHARASHTRA JEEVAN PRADHIKARANmjp.maharashtra.etenders.in/tpoimages/mjp/tender/Tender...Maharashtra Jeevan Pradhikaran, such specifications with designs and drawings shall form a part

Contractor No. of Correction Executive Engineer

MAHARASHTRA JEEVAN PRADHIKARAN MAHARASHTRA JEEVAN PRADHIKARAN WATER MANAGEMENT CIRCLE, NEW PANVEL

MAHARASHTRA JEEVAN PRADHIKARAN WATER MANAGEMENT DIVISION, VIRAR

Name of Work : Vasai-Virar Sub-Regional Water Supply Scheme

(Surya) stage-II Part-I.

Designing, Providing and constructing RCC ESR of

capacity 1.25 ML @ Tulinj, Nallasopara (E).

UNDERTAKING FOR GUARANTEE

I/WE GUARANTEE THAT

1. I/we will replace, repair and adjust free of all charges to the employer, any part of the

work which fails to comply with the specifications and amendment to such specification as

referred to in specifications attached to tender for wear and tear expected until the completion and

for a period of 24 months from the date of acceptance certificate issue under Clause-20 of

General Conditions of Contract of Form B-1 from the date of completion of work.

2. All the works will be of a type which has been proved in service, to be suitable for the

duty required by the specifications and will be manufactured by the specifications and will be

manufactured and tested in accordance with the appropriate standard specifications approved by

the Engineer-in-charge.

3. I/we accept and abide by the clause relating to quality and guarantee of work.

Contractor Executive Engineer

M.J.P. Water Management Div., Virar