15
Ken Wyllie, CERN LHCC, 12th March 2013 1 LHCb Upgrade Electronics Status On behalf of the LHCb collaboration

LHCb Upgrade Electronics Status On behalf of the LHCb collaboration

  • Upload
    sugar

  • View
    45

  • Download
    0

Embed Size (px)

DESCRIPTION

LHCb Upgrade Electronics Status On behalf of the LHCb collaboration. Outline. Architecture review(s) Overview of sub-detectors Overview of common electronics Conclusions. Upgrade Architecture. Current. Readout Supervisor. L0 Hardware Trigger. HLT. 1MHz event rate. Upgrade. - PowerPoint PPT Presentation

Citation preview

Page 1: LHCb Upgrade Electronics  Status On behalf of the  LHCb  collaboration

1Ken Wyllie, CERN LHCC, 12th March 2013

LHCb Upgrade Electronics

Status

On behalf of the LHCb collaboration

Page 2: LHCb Upgrade Electronics  Status On behalf of the  LHCb  collaboration

LHCC, 12th March 20132Ken Wyllie, CERN

Outline

Architecture review(s)

Overview of sub-detectors

Overview of common electronics

Conclusions

Page 3: LHCb Upgrade Electronics  Status On behalf of the  LHCb  collaboration

LHCC, 12th March 20133Ken Wyllie, CERN

Ken Wyllie, CERN 3

HLT

Current

HLT++

Upgrade

1MHzeventrate

40MHzeventrate

Readout Supervisor

L0 Hardware Trigger

Readout Supervisor

Low-level Trigger

50 Tb/s

Upgrade Architecture

Page 4: LHCb Upgrade Electronics  Status On behalf of the  LHCb  collaboration

LHCC, 12th March 20134Ken Wyllie, CERN

Architecture Review

TELL40

SOL40

Page 5: LHCb Upgrade Electronics  Status On behalf of the  LHCb  collaboration

LHCC, 12th March 20135Ken Wyllie, CERN

Review summary 1

Agenda (5/12/12) + Review Report:

https://indico.cern.ch/conferenceDisplay.py?confId=212204

Many thanks to our external reviewers:

• Alex Kluge (NA62, ALICE)• Philippe Farthouat (ATLAS)• Jorgen Christiansen (PH-ESE)

Presentations on: 1. Front-end & Back-end2. Timing & Fast Controls3. Expt. Control System4. DAQ-interface5. Infrastructure

Page 6: LHCb Upgrade Electronics  Status On behalf of the  LHCb  collaboration

LHCC, 12th March 20136Ken Wyllie, CERN

Positive feedback from reviewers: ‘NO SHOWSTOPPERS’-------------------------------------------------------------------------------Specific points on:

• Obsolescence

• Buffering on TELL40

• TELL40 firmware organisation

• Using Cu-links Tell40 <-> DAQ

• Tight schedule of ASICs-------------------------------------------------------------------------------Updated specifications note: LHCb-PUB-2011-011

Review summary 2

‘old’ systems under review

buffering being implemented

firmware coordination startedworkshop

in April

links under study with CERN & contractors

manpower + stronger collaboration

Page 7: LHCb Upgrade Electronics  Status On behalf of the  LHCb  collaboration

LHCC, 12th March 20137Ken Wyllie, CERN

Review of architecture implementation proposed by each sub-detector

• check feasibility

• check all architecture features included

• ideas from external reviewers

• prepare solid ideas for TDR

Specific mandate to 2 external reviewersDocumentation prepared in advance by sub-detectors

Sub-detector Architecture Reviews in 2013

Outer Tracker 6th March Upstream Tracker October

Calorimeter 12th June VeLo To be confirmed

RICH September SciFi/Inner Tracker To be confirmed

Muon October

Page 8: LHCb Upgrade Electronics  Status On behalf of the  LHCb  collaboration

LHCC, 12th March 20138

Sub-detectors: VeLo + Si trackers

VeLo:

Timepix3 submission imminent

Precursor to Velopix: design to start immediately

TOTTime of Arrival

Q(t)

clock

timeDiscr. out

thr

SALT chip (UT, IT, VeLo-strips)

Front-end + ADC (6-bits):

prototypes submitted

shaper5pF – 45pF

0ns 25 50 75

Page 9: LHCb Upgrade Electronics  Status On behalf of the  LHCb  collaboration

LHCC, 12th March 20139

Sub-detectors: Trackers

Outer Tracker:TDC in FPGA on prototype module

Also test of:DC-DC convertorsoptical link

SciFi:PACIFIC chip: design started.Specific issues with signal shape

ADC

Page 10: LHCb Upgrade Electronics  Status On behalf of the  LHCb  collaboration

LHCC, 12th March 201310Ken Wyllie, CERN

Sub-detectors: Particle-IDRICHPrototyping with existing or new chip (Maroc/Claro) connected to MaPMT

CalorimeterNew chip ICECAL:Tested with prototype digital module

MuonNew proposal to re-build ‘off-detector’ modules (obsolescence)

Page 11: LHCb Upgrade Electronics  Status On behalf of the  LHCb  collaboration

LHCC, 12th March 201311Ken Wyllie, CERN

Common Electronics Status 1

Common Electronics

Page 12: LHCb Upgrade Electronics  Status On behalf of the  LHCb  collaboration

LHCC, 12th March 201312Ken Wyllie, CERN

We rely HEAVILY on ‘White Paper’ projects (CERN-PH):

• GBT chipset 15,000 pieces• Versatile Link 9,000 pieces• DC-DC power convertors few 1000 pieces

Common Electronics Status 2

GBTX chip layout

Versatile link dual-transmitter

DC-DC convertor

Page 13: LHCb Upgrade Electronics  Status On behalf of the  LHCb  collaboration

LHCC, 12th March 201313Ken Wyllie, CERN

TELL40: Significant progress

AMC40 available soon for usersbuffering to be implemented

ATCA40: 1st prototype under test

ATCA infrastructurehardware investigationsoftware for control/monitoring

Firmware organisation Workshop at CERN 9/10 AprilALL sub-detectors will be present

formattingbuffering etc etc

Common Electronics Status 3

Page 14: LHCb Upgrade Electronics  Status On behalf of the  LHCb  collaboration

LHCC, 12th March 201314Ken Wyllie, CERN

Proposal to transmit detector data directly to surface (TELL40s)

Technically feasible?Tested 400m single fibre with VL

+ Tell40-AMC: OKHigh quality fibre: expensive…….Try lower grade + 12-way ribbon

Financially feasible?Discuss with companies:• Procurement• Installation• Testing

Optical fibres

Page 15: LHCb Upgrade Electronics  Status On behalf of the  LHCb  collaboration

LHCC, 12th March 201315Ken Wyllie, CERN

ConclusionElectronics architecture blessed by reviewersClear guidelines for sub-detector implementation

Already huge progress by sub-projects

2013 is a crucial year:

Manpower must increase

Detector requirements must be clear to allow good electronics design

- critical items are ASIC designs