Latest Advancements in Instrumentation, Monitoring and QA/QC Techniques for Deep Excavation Support Systems: Al Hilal Project, Abu Dhabi – A Case History Presentors : : Khaldoun Fahoum Khaldoun Fahoum (Langan (Langan International International ) ) Hussein Hatata Hussein Hatata (Al-Ghurair (Al-Ghurair Construction – Construction – Foundations) Foundations)

Latest Advancements in Instrumentation, Monitoring and QA/QC Techniques for Deep Excavation Support Systems: Al Hilal Project, Abu Dhabi – A Case History

Embed Size (px)

Citation preview

Page 1: Latest Advancements in Instrumentation, Monitoring and QA/QC Techniques for Deep Excavation Support Systems: Al Hilal Project, Abu Dhabi – A Case History

Latest Advancements in Instrumentation, Monitoring and

QA/QC Techniques for Deep Excavation Support Systems: Al Hilal Project, Abu Dhabi –

A Case HistoryPresentors : :

Khaldoun Fahoum Khaldoun Fahoum (Langan International(Langan International))

Hussein Hatata Hussein Hatata (Al-Ghurair Construction – (Al-Ghurair Construction – Foundations)Foundations)

Page 2: Latest Advancements in Instrumentation, Monitoring and QA/QC Techniques for Deep Excavation Support Systems: Al Hilal Project, Abu Dhabi – A Case History

Table Of ContentsTable Of Contents

Project DescriptionProject Description

Applied Instrumentation TechniquesApplied Instrumentation TechniquesMonitoring Process and Analysis DataMonitoring Process and Analysis Data

QA/QC Techniques Implemented in the QA/QC Techniques Implemented in the ProjectProject

Efficiency of the QA/QC Techniques, Efficiency of the QA/QC Techniques, Instrumentation and MonitoringInstrumentation and Monitoring

Importance of Instrumentation, Monitoring Importance of Instrumentation, Monitoring and QA/QC Techniques for Al Hilal Bank and QA/QC Techniques for Al Hilal Bank Project. Project.

Page 3: Latest Advancements in Instrumentation, Monitoring and QA/QC Techniques for Deep Excavation Support Systems: Al Hilal Project, Abu Dhabi – A Case History

Project Project DescriptionDescription

Page 4: Latest Advancements in Instrumentation, Monitoring and QA/QC Techniques for Deep Excavation Support Systems: Al Hilal Project, Abu Dhabi – A Case History

ClientClient : : Al Hilal BankAl Hilal BankStructural EngineerStructural Engineer : : DESIMONEDESIMONEEngr. & Architect of RecordEngr. & Architect of Record : : SEREXSEREX Geotechnical ConsultantGeotechnical Consultant : : Langan InternationalLangan InternationalContractorContractor : : Al-Ghurair Construction – Al-Ghurair Construction – Foundations Foundations

Plot area:Plot area: 4,650 m²4,650 m²Scope of Works:Scope of Works:Shoring:Shoring:- - 800 mm thick diaphragm wall – 300 m Length – 19 to 24 m Pit 800 mm thick diaphragm wall – 300 m Length – 19 to 24 m Pit depth depth - 34 Tubular Steel Struts in 2 rows and 10 Concrete Struts in - 34 Tubular Steel Struts in 2 rows and 10 Concrete Struts in 2 or 3 rows at corners. 2 or 3 rows at corners.Piling:Piling:- - 1000mm Dia. Bored cast in situ Tension Piles – 197 Nos. – 1000mm Dia. Bored cast in situ Tension Piles – 197 Nos. – 8.0m to 11.0m Long. 8.0m to 11.0m Long.

Project Key DataProject Key Data

Page 5: Latest Advancements in Instrumentation, Monitoring and QA/QC Techniques for Deep Excavation Support Systems: Al Hilal Project, Abu Dhabi – A Case History

DW Layout

Existing Bridges

Site LocationSite Location

Page 6: Latest Advancements in Instrumentation, Monitoring and QA/QC Techniques for Deep Excavation Support Systems: Al Hilal Project, Abu Dhabi – A Case History

Al Hilal Bank Tower Site Location

Site Condition and ConstraintsSite Condition and Constraints

Page 7: Latest Advancements in Instrumentation, Monitoring and QA/QC Techniques for Deep Excavation Support Systems: Al Hilal Project, Abu Dhabi – A Case History

Boreholes LocationBoreholes Location

Page 8: Latest Advancements in Instrumentation, Monitoring and QA/QC Techniques for Deep Excavation Support Systems: Al Hilal Project, Abu Dhabi – A Case History

BH-2

BOREHOLES

BH-7 BH-4

The ground water table was at 2.0m below existing ground, making The ground water table was at 2.0m below existing ground, making a water head of average 20.0 meter. a water head of average 20.0 meter.

Soil stratification from top to bottom starting from existing ground Soil stratification from top to bottom starting from existing ground was as follows:was as follows:

- 1.5m thick of made ground - 1.5m thick of made ground

- 5.5m thick of medium dense SAND - 5.5m thick of medium dense SAND

- 14.0m thick of very weak, moderately weathered - 14.0m thick of very weak, moderately weathered SANDSTONE/CALCARENITE SANDSTONE/CALCARENITE

- very weak, moderately weathered MUDSTONE inter-bedded with - very weak, moderately weathered MUDSTONE inter-bedded with GYPSUM layers down to 50.0m from ground. GYPSUM layers down to 50.0m from ground.

Site Ground ConditionSite Ground Condition

Page 9: Latest Advancements in Instrumentation, Monitoring and QA/QC Techniques for Deep Excavation Support Systems: Al Hilal Project, Abu Dhabi – A Case History

Importance of Importance of Instrumentation, Instrumentation,

Monitoring and QA/QC Monitoring and QA/QC Techniques for Al Hilal Techniques for Al Hilal

Bank ProjectBank Project

Page 10: Latest Advancements in Instrumentation, Monitoring and QA/QC Techniques for Deep Excavation Support Systems: Al Hilal Project, Abu Dhabi – A Case History

Bridges Foundations in the Vicinity of the Shoring SystemBridges Foundations in the Vicinity of the Shoring System

800mm THK D. Wall

X X

Page 11: Latest Advancements in Instrumentation, Monitoring and QA/QC Techniques for Deep Excavation Support Systems: Al Hilal Project, Abu Dhabi – A Case History

Cross Section of Shoring near Existing Bridge FoundationCross Section of Shoring near Existing Bridge Foundation

Page 12: Latest Advancements in Instrumentation, Monitoring and QA/QC Techniques for Deep Excavation Support Systems: Al Hilal Project, Abu Dhabi – A Case History

Continuous dewatering is needed to ensure dry excavation and Continuous dewatering is needed to ensure dry excavation and continuous monitoring of dewatering system is essential during continuous monitoring of dewatering system is essential during excavation and construction of the basements to maintain the safety excavation and construction of the basements to maintain the safety of neighboring structures and pit base.of neighboring structures and pit base.

Specific Engineering Risks and Limitations Associated Specific Engineering Risks and Limitations Associated with Al Hilal Tower Sitewith Al Hilal Tower Site

DW was flush with existing bridge deck on 3 sides. Safety has to be DW was flush with existing bridge deck on 3 sides. Safety has to be ensured and excessive movement of the existing structures has to be ensured and excessive movement of the existing structures has to be prevented.prevented.

Space allowed for shoring system including its movement and Space allowed for shoring system including its movement and waterproofing is 1.0 meter from bridge deck edges.waterproofing is 1.0 meter from bridge deck edges.

Page 13: Latest Advancements in Instrumentation, Monitoring and QA/QC Techniques for Deep Excavation Support Systems: Al Hilal Project, Abu Dhabi – A Case History

QA/QC Techniques QA/QC Techniques Implemented in the Implemented in the

ProjectProject

Page 14: Latest Advancements in Instrumentation, Monitoring and QA/QC Techniques for Deep Excavation Support Systems: Al Hilal Project, Abu Dhabi – A Case History

Measures Taken for Protection of Neighboring Structures

During the construction of the guide wall, trial pits were carried out in the proximity of potential locations of bridges foundations. Wherever a foundation location showed to be critical, the soil in the vicinity of the foundation was carefully excavated to expose it.

The top of diaphragm wall was adjusted on localized reaches along the bridge sides to suit the existing bridges foundations levels.

Alignment of guide wall was highly controlled by survey techniques to minimize deviation from theoretical position of the wall and maintain a minimum safe clearance from the bridge deck and foundation during excavation.

The side of the bridge deck was covered by rubberized sheet of approximately 20 to 50mm thick as a protection.

Page 15: Latest Advancements in Instrumentation, Monitoring and QA/QC Techniques for Deep Excavation Support Systems: Al Hilal Project, Abu Dhabi – A Case History

Measures Taken for Protection of Neighboring Structures

Page 16: Latest Advancements in Instrumentation, Monitoring and QA/QC Techniques for Deep Excavation Support Systems: Al Hilal Project, Abu Dhabi – A Case History

Supporting & Formation of Excavated Trench Sides

During trench excavation, fluctuation of supporting fluid level was carefully controlled. Its level was not allowed to fall below the level required for trench stability.

Bentonite slurry quality was controlled through a comprehensive testing routine to ensure consistent characteristics.

Page 17: Latest Advancements in Instrumentation, Monitoring and QA/QC Techniques for Deep Excavation Support Systems: Al Hilal Project, Abu Dhabi – A Case History

Supporting & Formation of Excavated Trench Sides

Adjacent panel joints were formed by means of special stop ends fitted with PVC water stops for a better water tightness of the wall, more control on cages vertical alignment and formation of an effective shear key.

Page 18: Latest Advancements in Instrumentation, Monitoring and QA/QC Techniques for Deep Excavation Support Systems: Al Hilal Project, Abu Dhabi – A Case History

Surveying, Monitoring & Testing Routine During Construction & Excavation Works

Survey monitoring of position of diaphragm wall and depth checking was routinely performed during trench excavation.

During site excavation, monitoring of diaphragm wall and existing bridges surrounding the site was carried out on a regular basis.

Coordination between Contractor & Engineer to ensure the full compliance with the project QA/QC plans and the implementation of strict reputable international standards in that field.

Observation wells were installed and used for both preliminary pumping test and monitoring ground water head during excavation works and onwards.

The trench cutting machine was equipped with a depth and inclination monitoring system offering an effective tool to control the plumbness of excavation and the depth of the trench.

Page 19: Latest Advancements in Instrumentation, Monitoring and QA/QC Techniques for Deep Excavation Support Systems: Al Hilal Project, Abu Dhabi – A Case History

Applied Applied InstrumentationInstrumentation

TechniquesTechniques

Page 20: Latest Advancements in Instrumentation, Monitoring and QA/QC Techniques for Deep Excavation Support Systems: Al Hilal Project, Abu Dhabi – A Case History

Shoring Wall Movement InstrumentationShoring Wall Movement Instrumentation

Inclinometer

10 Inclinometers were installed 10 Inclinometers were installed along the shoring periphery at an along the shoring periphery at an average spacing of 30.0 meters down average spacing of 30.0 meters down to the toe of diaphragm wall to to the toe of diaphragm wall to measure the horizontal deflection of measure the horizontal deflection of the wall.the wall.

Inclinometer

Page 21: Latest Advancements in Instrumentation, Monitoring and QA/QC Techniques for Deep Excavation Support Systems: Al Hilal Project, Abu Dhabi – A Case History

Shoring Wall Movement InstrumentationShoring Wall Movement Instrumentation

Monitoring Point on DW.

80 survey points were marked along 80 survey points were marked along the internal face of the diaphragm wall at the internal face of the diaphragm wall at top level and bottom of pit excavation at top level and bottom of pit excavation at intervals not exceeding 10.0 meters to intervals not exceeding 10.0 meters to monitor the movement of the wall. Ground monitor the movement of the wall. Ground surface survey points were further fixed.surface survey points were further fixed.

Page 22: Latest Advancements in Instrumentation, Monitoring and QA/QC Techniques for Deep Excavation Support Systems: Al Hilal Project, Abu Dhabi – A Case History

Ground Water Level Measurement SystemGround Water Level Measurement System

Observation Well

3 observation wells were installed 3 observation wells were installed before starting of excavation works to before starting of excavation works to monitor the ground water level.monitor the ground water level.

Page 23: Latest Advancements in Instrumentation, Monitoring and QA/QC Techniques for Deep Excavation Support Systems: Al Hilal Project, Abu Dhabi – A Case History

Monitoring Process Monitoring Process and and

Analysis of DataAnalysis of Data

Page 24: Latest Advancements in Instrumentation, Monitoring and QA/QC Techniques for Deep Excavation Support Systems: Al Hilal Project, Abu Dhabi – A Case History

Pit Excavation StagesPit Excavation Stages

Diaphragm wall Construction.Diaphragm wall Construction.

Running the dewatering system.Running the dewatering system.

Progress of excavation works with installation of struts as Progress of excavation works with installation of struts as lateral restraint system.lateral restraint system.

Maintaining the finally excavated pit in dry condition.Maintaining the finally excavated pit in dry condition.

Page 25: Latest Advancements in Instrumentation, Monitoring and QA/QC Techniques for Deep Excavation Support Systems: Al Hilal Project, Abu Dhabi – A Case History

Pit Excavation StagesPit Excavation Stages

Page 26: Latest Advancements in Instrumentation, Monitoring and QA/QC Techniques for Deep Excavation Support Systems: Al Hilal Project, Abu Dhabi – A Case History

Pit Excavation StagesPit Excavation Stages

Page 27: Latest Advancements in Instrumentation, Monitoring and QA/QC Techniques for Deep Excavation Support Systems: Al Hilal Project, Abu Dhabi – A Case History

Pit Excavation StagesPit Excavation Stages

Page 28: Latest Advancements in Instrumentation, Monitoring and QA/QC Techniques for Deep Excavation Support Systems: Al Hilal Project, Abu Dhabi – A Case History

Pit Excavation StagesPit Excavation Stages

Page 29: Latest Advancements in Instrumentation, Monitoring and QA/QC Techniques for Deep Excavation Support Systems: Al Hilal Project, Abu Dhabi – A Case History

Pit Excavation StagesPit Excavation Stages

Page 30: Latest Advancements in Instrumentation, Monitoring and QA/QC Techniques for Deep Excavation Support Systems: Al Hilal Project, Abu Dhabi – A Case History

Pit Excavation StagesPit Excavation Stages

Page 31: Latest Advancements in Instrumentation, Monitoring and QA/QC Techniques for Deep Excavation Support Systems: Al Hilal Project, Abu Dhabi – A Case History

Shoring Wall Monitoring Shoring Wall Monitoring

Monitoring of constructed shoring wall and surrounding Monitoring of constructed shoring wall and surrounding structures was carried out regularly to ensure the stability of structures was carried out regularly to ensure the stability of the whole area.the whole area.

Inclinometers readings were taken once a week.Inclinometers readings were taken once a week.

Survey Points were monitored twice weekly.Survey Points were monitored twice weekly.

Readings were promptly recorded, rigorously analyzed Readings were promptly recorded, rigorously analyzed and compared to values anticipated in the design and and compared to values anticipated in the design and specification warning threshold.specification warning threshold.

Page 32: Latest Advancements in Instrumentation, Monitoring and QA/QC Techniques for Deep Excavation Support Systems: Al Hilal Project, Abu Dhabi – A Case History

Wall Movement Monitoring by InclinometersWall Movement Monitoring by Inclinometers + Indicates deflection + Indicates deflection towards the Excavation side. towards the Excavation side.

- Indicates deflection towards - Indicates deflection towards the Earth side. the Earth side.

Page 33: Latest Advancements in Instrumentation, Monitoring and QA/QC Techniques for Deep Excavation Support Systems: Al Hilal Project, Abu Dhabi – A Case History

Wall Movement Monitoring by Land SurveyWall Movement Monitoring by Land Survey

Page 34: Latest Advancements in Instrumentation, Monitoring and QA/QC Techniques for Deep Excavation Support Systems: Al Hilal Project, Abu Dhabi – A Case History

Wall Movement Monitoring by Land SurveyWall Movement Monitoring by Land Survey

Page 35: Latest Advancements in Instrumentation, Monitoring and QA/QC Techniques for Deep Excavation Support Systems: Al Hilal Project, Abu Dhabi – A Case History

Ground Water Level Monitoring Ground Water Level Monitoring

Ground water level was regularly observed through the Ground water level was regularly observed through the observation wells to enable tracing anomalies related to observation wells to enable tracing anomalies related to ground water flow, hence allowing raising early warnings ground water flow, hence allowing raising early warnings about the complexities associated with severe fluctuations on about the complexities associated with severe fluctuations on the overall stability of the system.the overall stability of the system.

Page 36: Latest Advancements in Instrumentation, Monitoring and QA/QC Techniques for Deep Excavation Support Systems: Al Hilal Project, Abu Dhabi – A Case History

Efficiency of the Efficiency of the QA/QC Techniques, QA/QC Techniques, Instrumentation and Instrumentation and

MonitoringMonitoring

Page 37: Latest Advancements in Instrumentation, Monitoring and QA/QC Techniques for Deep Excavation Support Systems: Al Hilal Project, Abu Dhabi – A Case History

Efficiency of the Instrumentation, Monitoring & Efficiency of the Instrumentation, Monitoring & QA/QC TechniquesQA/QC Techniques

The specified deviation of the internal face of the diaphragm wall was less than 100mm along the whole depth, the strict application of QA/QC techniques resulted in successfully achieving this tolerance along the whole perimeter of the wall.

Proper implementation of QA/QC techniques throughout all phases of the project from design to final construction, helped controlling the wall deflection to a maximum of 18mm.

As part of the project quality requirements, a pumping test was conducted to produce an enhanced final design of the dewatering system. Consequently, a dry and safe excavation could always be maintained.

Page 38: Latest Advancements in Instrumentation, Monitoring and QA/QC Techniques for Deep Excavation Support Systems: Al Hilal Project, Abu Dhabi – A Case History

Efficiency of the Instrumentation, Monitoring & Efficiency of the Instrumentation, Monitoring & QA/QC TechniquesQA/QC Techniques

The inclusion of the instrumentation and monitoring techniques into the project allowed a better understanding of the system behavior and contributed to an reliable construction risk management through continuous monitoring along the intended life span of the system.

Thanks to the effective implementation of QA/QC procedures and the efficient use of instrumentation and monitoring techniques, site neighboring structures were unaffected and their functionality was maintained, despite being sensitive to ongoing construction activities.

Page 39: Latest Advancements in Instrumentation, Monitoring and QA/QC Techniques for Deep Excavation Support Systems: Al Hilal Project, Abu Dhabi – A Case History

Found it with Quality Build it with ConfidenceFound it with Quality Build it with Confidence

PERSPECTIVE VIEW OF THE SUPERSTRUCTURE TO BE CONSTRUCTED ON TOP OF THE SHORING SYSTEM