Upload
karin-baker
View
213
Download
1
Embed Size (px)
Citation preview
Latest Advancements in Instrumentation, Monitoring and
QA/QC Techniques for Deep Excavation Support Systems: Al Hilal Project, Abu Dhabi –
A Case HistoryPresentors : :
Khaldoun Fahoum Khaldoun Fahoum (Langan International(Langan International))
Hussein Hatata Hussein Hatata (Al-Ghurair Construction – (Al-Ghurair Construction – Foundations)Foundations)
Table Of ContentsTable Of Contents
Project DescriptionProject Description
Applied Instrumentation TechniquesApplied Instrumentation TechniquesMonitoring Process and Analysis DataMonitoring Process and Analysis Data
QA/QC Techniques Implemented in the QA/QC Techniques Implemented in the ProjectProject
Efficiency of the QA/QC Techniques, Efficiency of the QA/QC Techniques, Instrumentation and MonitoringInstrumentation and Monitoring
Importance of Instrumentation, Monitoring Importance of Instrumentation, Monitoring and QA/QC Techniques for Al Hilal Bank and QA/QC Techniques for Al Hilal Bank Project. Project.
Project Project DescriptionDescription
ClientClient : : Al Hilal BankAl Hilal BankStructural EngineerStructural Engineer : : DESIMONEDESIMONEEngr. & Architect of RecordEngr. & Architect of Record : : SEREXSEREX Geotechnical ConsultantGeotechnical Consultant : : Langan InternationalLangan InternationalContractorContractor : : Al-Ghurair Construction – Al-Ghurair Construction – Foundations Foundations
Plot area:Plot area: 4,650 m²4,650 m²Scope of Works:Scope of Works:Shoring:Shoring:- - 800 mm thick diaphragm wall – 300 m Length – 19 to 24 m Pit 800 mm thick diaphragm wall – 300 m Length – 19 to 24 m Pit depth depth - 34 Tubular Steel Struts in 2 rows and 10 Concrete Struts in - 34 Tubular Steel Struts in 2 rows and 10 Concrete Struts in 2 or 3 rows at corners. 2 or 3 rows at corners.Piling:Piling:- - 1000mm Dia. Bored cast in situ Tension Piles – 197 Nos. – 1000mm Dia. Bored cast in situ Tension Piles – 197 Nos. – 8.0m to 11.0m Long. 8.0m to 11.0m Long.
Project Key DataProject Key Data
DW Layout
Existing Bridges
Site LocationSite Location
Al Hilal Bank Tower Site Location
Site Condition and ConstraintsSite Condition and Constraints
Boreholes LocationBoreholes Location
BH-2
BOREHOLES
BH-7 BH-4
The ground water table was at 2.0m below existing ground, making The ground water table was at 2.0m below existing ground, making a water head of average 20.0 meter. a water head of average 20.0 meter.
Soil stratification from top to bottom starting from existing ground Soil stratification from top to bottom starting from existing ground was as follows:was as follows:
- 1.5m thick of made ground - 1.5m thick of made ground
- 5.5m thick of medium dense SAND - 5.5m thick of medium dense SAND
- 14.0m thick of very weak, moderately weathered - 14.0m thick of very weak, moderately weathered SANDSTONE/CALCARENITE SANDSTONE/CALCARENITE
- very weak, moderately weathered MUDSTONE inter-bedded with - very weak, moderately weathered MUDSTONE inter-bedded with GYPSUM layers down to 50.0m from ground. GYPSUM layers down to 50.0m from ground.
Site Ground ConditionSite Ground Condition
Importance of Importance of Instrumentation, Instrumentation,
Monitoring and QA/QC Monitoring and QA/QC Techniques for Al Hilal Techniques for Al Hilal
Bank ProjectBank Project
Bridges Foundations in the Vicinity of the Shoring SystemBridges Foundations in the Vicinity of the Shoring System
800mm THK D. Wall
X X
Cross Section of Shoring near Existing Bridge FoundationCross Section of Shoring near Existing Bridge Foundation
Continuous dewatering is needed to ensure dry excavation and Continuous dewatering is needed to ensure dry excavation and continuous monitoring of dewatering system is essential during continuous monitoring of dewatering system is essential during excavation and construction of the basements to maintain the safety excavation and construction of the basements to maintain the safety of neighboring structures and pit base.of neighboring structures and pit base.
Specific Engineering Risks and Limitations Associated Specific Engineering Risks and Limitations Associated with Al Hilal Tower Sitewith Al Hilal Tower Site
DW was flush with existing bridge deck on 3 sides. Safety has to be DW was flush with existing bridge deck on 3 sides. Safety has to be ensured and excessive movement of the existing structures has to be ensured and excessive movement of the existing structures has to be prevented.prevented.
Space allowed for shoring system including its movement and Space allowed for shoring system including its movement and waterproofing is 1.0 meter from bridge deck edges.waterproofing is 1.0 meter from bridge deck edges.
QA/QC Techniques QA/QC Techniques Implemented in the Implemented in the
ProjectProject
Measures Taken for Protection of Neighboring Structures
During the construction of the guide wall, trial pits were carried out in the proximity of potential locations of bridges foundations. Wherever a foundation location showed to be critical, the soil in the vicinity of the foundation was carefully excavated to expose it.
The top of diaphragm wall was adjusted on localized reaches along the bridge sides to suit the existing bridges foundations levels.
Alignment of guide wall was highly controlled by survey techniques to minimize deviation from theoretical position of the wall and maintain a minimum safe clearance from the bridge deck and foundation during excavation.
The side of the bridge deck was covered by rubberized sheet of approximately 20 to 50mm thick as a protection.
Measures Taken for Protection of Neighboring Structures
Supporting & Formation of Excavated Trench Sides
During trench excavation, fluctuation of supporting fluid level was carefully controlled. Its level was not allowed to fall below the level required for trench stability.
Bentonite slurry quality was controlled through a comprehensive testing routine to ensure consistent characteristics.
Supporting & Formation of Excavated Trench Sides
Adjacent panel joints were formed by means of special stop ends fitted with PVC water stops for a better water tightness of the wall, more control on cages vertical alignment and formation of an effective shear key.
Surveying, Monitoring & Testing Routine During Construction & Excavation Works
Survey monitoring of position of diaphragm wall and depth checking was routinely performed during trench excavation.
During site excavation, monitoring of diaphragm wall and existing bridges surrounding the site was carried out on a regular basis.
Coordination between Contractor & Engineer to ensure the full compliance with the project QA/QC plans and the implementation of strict reputable international standards in that field.
Observation wells were installed and used for both preliminary pumping test and monitoring ground water head during excavation works and onwards.
The trench cutting machine was equipped with a depth and inclination monitoring system offering an effective tool to control the plumbness of excavation and the depth of the trench.
Applied Applied InstrumentationInstrumentation
TechniquesTechniques
Shoring Wall Movement InstrumentationShoring Wall Movement Instrumentation
Inclinometer
10 Inclinometers were installed 10 Inclinometers were installed along the shoring periphery at an along the shoring periphery at an average spacing of 30.0 meters down average spacing of 30.0 meters down to the toe of diaphragm wall to to the toe of diaphragm wall to measure the horizontal deflection of measure the horizontal deflection of the wall.the wall.
Inclinometer
Shoring Wall Movement InstrumentationShoring Wall Movement Instrumentation
Monitoring Point on DW.
80 survey points were marked along 80 survey points were marked along the internal face of the diaphragm wall at the internal face of the diaphragm wall at top level and bottom of pit excavation at top level and bottom of pit excavation at intervals not exceeding 10.0 meters to intervals not exceeding 10.0 meters to monitor the movement of the wall. Ground monitor the movement of the wall. Ground surface survey points were further fixed.surface survey points were further fixed.
Ground Water Level Measurement SystemGround Water Level Measurement System
Observation Well
3 observation wells were installed 3 observation wells were installed before starting of excavation works to before starting of excavation works to monitor the ground water level.monitor the ground water level.
Monitoring Process Monitoring Process and and
Analysis of DataAnalysis of Data
Pit Excavation StagesPit Excavation Stages
Diaphragm wall Construction.Diaphragm wall Construction.
Running the dewatering system.Running the dewatering system.
Progress of excavation works with installation of struts as Progress of excavation works with installation of struts as lateral restraint system.lateral restraint system.
Maintaining the finally excavated pit in dry condition.Maintaining the finally excavated pit in dry condition.
Pit Excavation StagesPit Excavation Stages
Pit Excavation StagesPit Excavation Stages
Pit Excavation StagesPit Excavation Stages
Pit Excavation StagesPit Excavation Stages
Pit Excavation StagesPit Excavation Stages
Pit Excavation StagesPit Excavation Stages
Shoring Wall Monitoring Shoring Wall Monitoring
Monitoring of constructed shoring wall and surrounding Monitoring of constructed shoring wall and surrounding structures was carried out regularly to ensure the stability of structures was carried out regularly to ensure the stability of the whole area.the whole area.
Inclinometers readings were taken once a week.Inclinometers readings were taken once a week.
Survey Points were monitored twice weekly.Survey Points were monitored twice weekly.
Readings were promptly recorded, rigorously analyzed Readings were promptly recorded, rigorously analyzed and compared to values anticipated in the design and and compared to values anticipated in the design and specification warning threshold.specification warning threshold.
Wall Movement Monitoring by InclinometersWall Movement Monitoring by Inclinometers + Indicates deflection + Indicates deflection towards the Excavation side. towards the Excavation side.
- Indicates deflection towards - Indicates deflection towards the Earth side. the Earth side.
Wall Movement Monitoring by Land SurveyWall Movement Monitoring by Land Survey
Wall Movement Monitoring by Land SurveyWall Movement Monitoring by Land Survey
Ground Water Level Monitoring Ground Water Level Monitoring
Ground water level was regularly observed through the Ground water level was regularly observed through the observation wells to enable tracing anomalies related to observation wells to enable tracing anomalies related to ground water flow, hence allowing raising early warnings ground water flow, hence allowing raising early warnings about the complexities associated with severe fluctuations on about the complexities associated with severe fluctuations on the overall stability of the system.the overall stability of the system.
Efficiency of the Efficiency of the QA/QC Techniques, QA/QC Techniques, Instrumentation and Instrumentation and
MonitoringMonitoring
Efficiency of the Instrumentation, Monitoring & Efficiency of the Instrumentation, Monitoring & QA/QC TechniquesQA/QC Techniques
The specified deviation of the internal face of the diaphragm wall was less than 100mm along the whole depth, the strict application of QA/QC techniques resulted in successfully achieving this tolerance along the whole perimeter of the wall.
Proper implementation of QA/QC techniques throughout all phases of the project from design to final construction, helped controlling the wall deflection to a maximum of 18mm.
As part of the project quality requirements, a pumping test was conducted to produce an enhanced final design of the dewatering system. Consequently, a dry and safe excavation could always be maintained.
Efficiency of the Instrumentation, Monitoring & Efficiency of the Instrumentation, Monitoring & QA/QC TechniquesQA/QC Techniques
The inclusion of the instrumentation and monitoring techniques into the project allowed a better understanding of the system behavior and contributed to an reliable construction risk management through continuous monitoring along the intended life span of the system.
Thanks to the effective implementation of QA/QC procedures and the efficient use of instrumentation and monitoring techniques, site neighboring structures were unaffected and their functionality was maintained, despite being sensitive to ongoing construction activities.
Found it with Quality Build it with ConfidenceFound it with Quality Build it with Confidence
PERSPECTIVE VIEW OF THE SUPERSTRUCTURE TO BE CONSTRUCTED ON TOP OF THE SHORING SYSTEM