KUL Commercial Project - Bandra (E) - Qtn Dt. 30.05.13

  • Upload
    jnanam

  • View
    215

  • Download
    0

Embed Size (px)

Citation preview

  • 7/27/2019 KUL Commercial Project - Bandra (E) - Qtn Dt. 30.05.13

    1/8

    Corporate Office: 5/6, Ground Floor, Embassy Apartments, 291, Bellasis Road, Opp. ST Depot, Mumbai

    Central, Mumbai 400 008. Tel: +91 22 23012971. Email: [email protected]

    Rose Group Company

    Date: 30-05-2013

    TO,

    M/s. Kumar Builders,

    Mumbai

    Kind Attn: Ms. Shefali Sancheti.

    Sub:- Quotation for Shell Structure works of OFFICE BUILDING NO. 4

    NEAR BLDG. NO. 6 & 7 (2 Basement + Stilt + 14 Upper floors)

    Sub Structure & Super Structure Work

    (RCC, Block work, Intl. Plaster in Kitchen, toilet & Common area and Extnl. Plaster)ON S. NO. 341 PART AT KHER NAGAR, BANDRA (EAST), MUMBAI

    Respected Sir,

    We thank you for inviting us to quote for work under subject matter above. We are pleased to submit herewith

    the quotation complete in all respect with. The rates have been quoted for in respect to the scope of works

    mentioned hereafter.

    The Construction of the 2 Basement + Stilt + 14 Floor + Terrace floors commercial building shall be carried out

    complete in all respect for the scope of work described hereunder-

    Rate excluding Piling

    Approximate Built-up Area : 57670.64 Sq. Ft. BUA(to be ascertained with final VFC Drawing)

    Rate per Sqft Built-up Area : Rs. 623/-(Using H 20 Beams Doka Style as used by L&T)

    NoteThe Built up Area are subjected to change as per final drawings (Cement, Concrete and Steel will be provided by the developer free of cost at site.)

    Basic rate of Steel Rs. 40,000 / M.T.

    Basic rate of Cement Rs. 300 / Bag of 50 kgs

    Basic rate of Sand Rs. 5,800 / Brass

    Basic rate of Aggregate Rs. 2,400 / BrassBasic rate of Block Rs. 4,200 / Cu. M.

    The total final amount shall be evaluated on basis of actual total built-up area constructed on site on the basis of

    the mode measurement describe hereunder and duly certified by the Architect. The rates shall be calculated onbasis of the mode of measurement defined hereunder to arrive at the total contract value.

  • 7/27/2019 KUL Commercial Project - Bandra (E) - Qtn Dt. 30.05.13

    2/8

  • 7/27/2019 KUL Commercial Project - Bandra (E) - Qtn Dt. 30.05.13

    3/8

    Corporate Office: 5/6, Ground Floor, Embassy Apartments, 291, Bellasis Road, Opp. ST Depot, Mumbai

    Central, Mumbai 400 008. Tel: +91 22 23012971. Email: [email protected]

    Rose Group Company

    11. Podium & stilt 50%

    12. Service ducts ( if enclosed and with slab ) 50%

    Measurements:

    The site In-charge will jointly measure all the works in progress with the contractors authorized agent. Suchmeasurement will be recorded in the measurement sheets by the contractor and will be signed by representative

    of Site In-charge. For the purpose of taking joint measurement, the contractors representative shall be bound to

    be present whenever required by the Engineer In-Charge.

    Payment Schedule to the contractor: The contractor will be paid as per the payment schedule.

    Payment Schedule:

    Consider following assumptions for :

    a. Concrete - 1.6 Cft / Sft BUA

    b. Steel - 6 Kg / Sft BUA

    Running account payments:

    All Running Account payments shall be regarded as payments by way of advance against the final payment only

    and not as payments for work actually done and completed.

    Sr. No. Details of Work Percentage

    1 Completion of Plinth 10%

    2 Completion of typical slabs (divide over the slabs) 50%

    3 Completion of Block work 12%

    4 Completion of Internal Plaster 8%

    5 Completion of External Plaster 12%

    6 UG tank, OHT, LMR, Security cabin, compound wall, paving, elevation 5%

    7 Housekeeping 2%

    8 Handover 1%

  • 7/27/2019 KUL Commercial Project - Bandra (E) - Qtn Dt. 30.05.13

    4/8

    Corporate Office: 5/6, Ground Floor, Embassy Apartments, 291, Bellasis Road, Opp. ST Depot, Mumbai

    Central, Mumbai 400 008. Tel: +91 22 23012971. Email: [email protected]

    Rose Group Company

    SCOPE OF WORK

    (RCC Brickwork & Plaster)

    a) The specified work shall consist of Sub Structure & Super Structure Work (RCC, Block work, Int.Plaster in Kitchen, toilet & Common area and Ext. Plaster) Contract on Sq. ft. basis with Part Material

    (Only cement and steel shall be supplied free of Cost by Developer at Site) in accordance with the

    plan given by the Developer to the Contractor with specification, rates etc. given in Bill of quantities

    appearing hereunder and as described more particularly herein.

    b) The Developer shallprovide drawings approved by Architects/ Structural consultants to the contractorto execute the work at Site.

    1. CONCRETE

    Proving of Footings/Pile caps, Beams, Columns, Slabs, Chajjas, Lifts Machines Room, Lift Well, Lintels,

    Copings, UG & OH Water Storage Tanks, R.C.C. Staircase & other Walls in Site machine mixed concretecomplete with the grade of concrete as per detailed specifications of R.C.C. Consultant including all formworks,

    reinforcement and inserts required to carry on the said works. Formwork for slabs shall be 12mm ply form.

    2. MASONRY

    All masonry woks shall be Block masonry as per Architectural drawings and specifications.External masonry shall be of block 150mm thick constructed in C:M 1:5.

    Internal partition wall and elevation masonry shall be constructed in half brick walls in C:M 1:5.

    R.C.C. runners with required reinforcement shall be provided at mid-depth of the half brick walls.

    All masonry works will be carried out in proper line, level & plumb.

    3. PLASTER

    All internal walls shall be applied with single coat 8-12mm thick in C.M. 1:4.

    No plaster shall be rendered to the ceilings.

    External plaster shall be finished with 5-10mm thick plaster in C.M. 1:4 with a thickness of 6-10mm over the

    backing coat.

    4. EXCAVATIONExcavation charges not included and shall be charged separately as per actual.

  • 7/27/2019 KUL Commercial Project - Bandra (E) - Qtn Dt. 30.05.13

    5/8

    Corporate Office: 5/6, Ground Floor, Embassy Apartments, 291, Bellasis Road, Opp. ST Depot, Mumbai

    Central, Mumbai 400 008. Tel: +91 22 23012971. Email: [email protected]

    Rose Group Company

    Terms and Conditions

    1) The basic rate shall include all transportation, loading VAT or any other taxes applicable.2) Services tax and Vat applicable shall be paid by the owner.3) WATER AND ELECTRICITY

    a) Construction Water: To the extent possible, water for construction purpose shall be arranged at

    one source only by the Developer and charged as per prevailing rates with meter being installed by theContractor. The Contractor shall make the arrangement for storage of the construction water and

    distribution, including the piping, pumping and its distribution up to the place of works.

    b) Electricity : To the extent possible, electricity for construction purpose, labour hutment and general

    illumination in and around the work place shall be arranged and borne by the Developer at one source

    only. The electricity for labor hutments shall be arranged at one source only by the Developer and

    charged as per prevailing rates with a meter.

    General common area lighting to be in scope of main contractor.

    Water and Electricity as available for the work will be supplied at one point but charges for the same

    will be payable by the contractor at actual. The amount shall be recoverable from the contractors bill

    at the current market price of the same.

    c) Water supply shall be provided free of cost at point for the labour hutments and drinking purpose.

    4) Bills shall be made as per the mode of the payment attached herewith. Payments against R.A. Billsshall be paid within 7-10 days from the date of submission of the R.A. Bill.

    5) Advance (5% of Contract Amount) against mobilization shall be paid to the Contractor and may berecovered from 2

    ndR.A. Bill onwards @ 5% of the bill amount.

    6) Retention @ 2% of the value of the works executed shall be deducted from R.A. Bills and 50% shall berelease on the general completion of works.

    Balance 50% shall release after the completion of defect liability period of 6 months or one monsoonwhichever is early.

    7) Cement and steel shall be supplied free of Cost by Developer at site.RMC shall be supplied by the Developer with Rs.150/- pumping charges.

    8) The period of completion of the works shall be 12 months (plus 3 months Grace Period), Subject toavailability of VFC Drawing & Front.

    9) Delay in execution of works due to a delay from our end either in terms of elements etc. shall beadmitted by us for a period of 30 days in all. A delay beyond shall be claimed as idle charges at the rate

    of Rs. 50,000/week against idle labour, equipment, machinery etc. Also in case of unexpected delay the

    rates shall be liable for a escalation.

  • 7/27/2019 KUL Commercial Project - Bandra (E) - Qtn Dt. 30.05.13

    6/8

    Corporate Office: 5/6, Ground Floor, Embassy Apartments, 291, Bellasis Road, Opp. ST Depot, Mumbai

    Central, Mumbai 400 008. Tel: +91 22 23012971. Email: [email protected]

    Rose Group Company

    10) The Site In Charge or his Senior officer appointed by the Developer shall lookafter Co-ordination ofwork and shall be authorized to inspect the work of Contractor, in way and manner as may be desired

    by the Developer.

    11) In case of work for which no such specification is supplied by the Developer, such work shall becarried out in accordance to with the instructions of the Developers Site in charge and General

    ManagerTechnical.

    12) Insurance by the Contractor:a) The contractor shall take the appropriate insurance policies to cover all risks involved in course of

    execution of work related to labour, personnel, Machinery or otherwise.

    b) The contractor shall be liable for any liability, loss, claim arising in respect of any damage to

    property or in respect of personal injury or death of any person appointed by the contractor or anysub contractor engaged by the Contractor or for any loss caused on account of any act of Contractor

    to any other Person or Property.

    b) Contractor shall cover insurance, which he may be required under any law from time to time orotherwise to secure himself against risk of accident etc. The Developer may ask the Contractor to

    take any other specific policy provided always that Developer shall not be liable for any peril

    which can be insured or otherwise.

    The contractor shall comply with conditions and observe all acts, rules and Regulations including

    the following:-a) Employees state Insurance Act, 1948: As applicable to himself, his employees or any other

    persons engaged or employed in course of work or in work related to Contract. The Contractor

    shall maintain all cards and records as required under the act in respect of employees and paymentsand the contractor shall secure the agreement of the sub-contract to maintain such records. Any

    expenses incurred for the contributions making contributions or maintaining records shall be in the

    contractors account.

    b)Workman Compensation and employees Liability Insurance: - The Contractor alone shall

    be liable for compensation payable under workman compensation Act or any other law in force.

    The Contractor shall take insurance policy for all the contractors employees engaged in the

    performance of this contract to cover all risks. If any of the work is given on Sub-Contract, the

    contractor shall require the sub-contractor to provide for compensation of workmen and also to

    provide Developers liability insurance for the latters employees if such employees are not covered

    under the contractors insurance.

    c) Minimum wages Act:- Wages shall be paid as per the prevailing Government Rules and recordsmust be maintained as required.

    13) Labour Laws:-a) The contractor shall comply with all rules and regulations, obligations and restrictions imposed

    under the labour laws or any other law in force. The contractor will also ensure compliance with

    all the regulations for all his subcontractor as regards to applicable Central, State, Municipal and

    local laws. The Contractor further agrees to indemnify the Developer from any liability or penalty

    which may be imposed by the Central, State, Municipal or local authorities and also from all

    claims, suits or proceedings in respect thereof.

    b) Notwithstanding anything contained herein, the relationship between Developer and Contractor ison principal to principal basis and Developer shall not be liable for acts of Contractor in any way

    whatsoever and Contractor is not agent of the Developer.

  • 7/27/2019 KUL Commercial Project - Bandra (E) - Qtn Dt. 30.05.13

    7/8

    Corporate Office: 5/6, Ground Floor, Embassy Apartments, 291, Bellasis Road, Opp. ST Depot, Mumbai

    Central, Mumbai 400 008. Tel: +91 22 23012971. Email: [email protected]

    Rose Group Company

    c) The Contractor further agrees and undertake as under:-

    (i) No labour below the age of eighteen years shall be employed at the site. Also no family of labours

    will be allowed at site.

    (ii) Contractor shall arrange required medical facility for his workers.

    (iii) Wearing safety gadget/particularly glows, harness safety helmet & safety shoes are compulsoryfor all the workers, Supervisors and engineers etc. but if they do not do so, the Site-in charge will levy

    fine/penalty as deemed fit by him regularly.

    iv) The contractor shall comply with the provision of the Apprentices act, 1961 and the rules andorders issued there under from time to time. The contractor shall also be Liable for any pecuniary

    liability arising on account of any violation by him of the Act and indemnify Developer in respectthereof. The Developer may frame its own rule to levy penalties.

    14) Safety:The Contractor at his own cost shall take all safety measures to prevent accidents, mishaps etc. on site

    and otherwise in course of work. Safety helmets, safety belts and all safety equipments as may be

    required and safety instructions shall be given by the contractor to his work force and staff wherever

    required.

    No person either labour or staff or visitor must be present at site without helmet. Safety nets of

    Minimum of 1000 wide inside the compound or as per requirement on site to be provided by the

    contractor at the periphery of the building, at the Contractors Own cost.

    The Contractor will provide necessary safety training to all the persons employed on the premises and

    protect their health and personal safety at your own cost. Any injured person has to be provided

    proper medical aid without any loss of time.

    Rates are all inclusive and among other things include the following:-All the cost of material such as river sand, metal, Blocks, plasticizer, retarders (construction

    chemicals), Safety net and binding wire as required for quality construction with speed in mind.

    All shuttering material such as 12 mm ply (no plates), Beam bottom, steel props, runners, spans and the

    required tools and tackles required for the same (1 New Set of slab shuttering & 2 sets of bottoms)

    shall be brought by contractor at site with additional half set of slab shuttering without additional cost.

    All machinery etc. for lifting, shifting, placing, or transferring the materials for the purpose of

    construction wherever if required should be one by the Contractor. All necessary equipment for

    quality checks of material such as stilt contained, sieve analysis, cube moulds, flakiness,dust, porosity,

    as required will be brought by the contractor. Compulsory helmet, safety belt and safety shoes for the

    people (workers as well as managers).Daily cleaning the site and maintaining good housekeeping.

    Following all the laws w.r.t. to maintain records for labours such as their payment, PF, etc. workmen

    compensation insurance, working hours as per BMC rules, and following all law and order as per

    prevailing, and coming in future.

    Hope you find offer reasonable and competitive in accordance to your requirements.

    We look forward to be associated with you for the said works.

    We assure of our best services in terms of quality and timely completion of the project.

  • 7/27/2019 KUL Commercial Project - Bandra (E) - Qtn Dt. 30.05.13

    8/8

    Corporate Office: 5/6, Ground Floor, Embassy Apartments, 291, Bellasis Road, Opp. ST Depot, Mumbai

    Central, Mumbai 400 008. Tel: +91 22 23012971. Email: [email protected]

    Rose Group Company

    ForPHEENIX CONSTRUCTIONS

    Partner