ISC and Offshore Substation Design ISC Consulting Engineers A/S has many years of experience in the design of offshore substations, dating back to the design of the world’s first offshore substa- tion, installed at the Nysted Offshore Wind Farm in 2003. ISC’s experience in the design of offshore structures is founded on the knowledge obtained from over 38 years in the off- shore oil and gas industry. Since then ISC has successfully under- taken the complete detailed design of further 15 offshore substations. ISC’s portfolio clearly demonstrates a com- prehensive expertise within the field of offshore substation design, including a broad spectrum of topside layouts as well as jacket and monopile substructures. ISC has also demonstrated the ability to work alongside local authorities across Europe to produce superior solutions which conform to the local requirements. PRINCESS AMALIA (120 MW) No. of transformers : 1 Topside weight : 650 tonnes Installation year : 2007 Water depth : 19-24 meters Substructure : Monopile Detailed Design : Topside Owner : Eneco WALNEY 1 (183.6 MW) No. of transformers : 2 Topside weight : 1030 tonnes Jacket weight : 994 tonnes Installation year : 2010 Water depth : 21 meters Substructure : Jacket Detailed Design : Topside and jacket Owner : Dong Energy GODE WIND 01 (332 MW) No. of transformers : 2 Topside weight : 1950 tonnes Jacket weight : 1800 tonnes Installation year : 2015 Water depth : 30 meters Substructure : Jacket Detailed Design : Topside and jacket Owner : Dong Energy WEST OF DUDDON SANDS (389 MW) No. of transformers : 2 Topside weight : 1580 tonnes Jacket weight : 1230 tonnes Installation year : 2013 Water depth : 19 meters Substructure : Jacket Detailed Design : Topside and jacket Owner : Dong Energy and Scottish Power NYSTED I (166 MW) No. of transformers : 1 Topside weight : 670 tonnes Installation year : 2003 Water depth : 6-10 meters Substructure : Concrete gravity Detailed Design : Topside Owner : Dong Energy GUNFLEET SANDS (172 MW) No. of transformers : 2 Topside weight : 1315 tonnes Transition piece : 155 tonnes Installation year : 2008 Water depth : 6-15 meters Substructure : Monopile Detailed Design : Topside Owner : Dong Energy GODE WIND 02 (252 MW) No. of transformers : 2 Topside weight : 1950 tonnes Jacket weight : 1790 tonnes Installation year : 2015 Water depth : 33 meters Substructure : Jacket Detailed Design : Topside and jacket Owner : Dong Energy BORKUM RIFFGRUND 1 (320 MW) No. of transformers : 2 Topside weight : 1880 tonnes Jacket weight : 1720 tonnes Installation year : 2013 Water depth : 24 meters Substructure : Jacket Detailed Design : Topside and jacket Owner : Dong Energy NORDSEE ONE (324 MW) No. of transformers : 2 Topside weight : 1790 tonnes Jacket weight : 1310 tonnes Installation year : 2015 Water depth : 28 meters Substructure : Jacket Detailed Design : Topside and jacket Owner : RWE Innogy HORNS REV 2 (209 MW) No. of transformers : 1 Topside weight : 1238 tonnes Jacket weight : 798 tonnes Installation year : 2008 Water depth : 13 meters Substructure : Jacket Detailed Design : Topside and jacket Owner : Energinet.dk NORTHWIND (216 MW) No. of transformers : 1 Topside weight : 1140 tonnes Installation year : 2013 Water depth : 20 meters Substructure : Monopile Detailed Design : Topside Owner : Northwind Offshore Energy WALNEY 2 (183.6 MW) No. of transformers : 2 Topside weight : 1030 tonnes Jacket weight : 995 tonnes Installation year : 2011 Water depth : 24 meters Substructure : Jacket Detailed Design : Topside and jacket Owner : Dong Energy LILLGRUND (110.4 MW) No. of transformers : 1 Topside weight : 670 tonnes Installation year : 2007 Water depth : 4-10 meters Substructure : Concrete gravity Detailed Design : Topside Owner : Vattenfall BALTIC 1 (48.3 MW) Transition piece weight : 1100 tonnes Installation year : 2010 Water depth : 19 meters Substructure : Monopile Detailed Design : Monopile Owner : EnBW Borkum Riffgrund 1, installation German Bight, August 2013. Location : German Bight Location : German Bight Location : German Bight Location : Belgian North Sea Location : UK Irish Sea Location : UK North Sea Location : UK Irish Sea Location : German Baltic Sea Location : UK Irish Sea Location : German North Sea Location : Danish North Sea Location : Sweden Öresund Location : Netherlands North Sea Location : Danish Baltic Sea NORDSEE OST (295 MW) Installation year : 2014 NORDSEE ONE (324 MW) Installation year : 2015 GODE WIND 01 (332 MW) GODE WIND 02 (252 MW) Installation year : 2015 NORTHWIND (216 MW) Installation year : 2013 WEST OF DUDDON SANDS (389 MW) Installation year : 2013 BORKUM RIFFGRUND 1 (320 MW) Installation year : 2013 WALNEY 2 (183.6 MW) Installation year : 2011 WALNEY 1 (183.6 MW) Installation year : 2010 BALTIC 1 (48.3 MW) Installation year : 2010 GUNFLEET SANDS (172 MW) Installation year : 2008 HORNS REV 2 (209 MW) Installation year : 2008 PRINCESS AMALIA (120 MW) Installation year : 2007 NYSTED 1 (166 MW) Installation year : 2003 LILLGRUND (110.4 MW) Installation year : 2007 NORDSEE OST (295 MW) No. of transformers : 2 Topside weight : 1600 tonnes Installation year : 2014 Water depth : 23 meters Substructure : Jacket Detailed Design : Topside Owner : RWE Innogy Location : German Bight Detailed Designs

ISC and Offshore Substation Design€¦ · ISC and Offshore Substation Design ISC Consulting Engineers A/S has many years of experience in the design of offshore substations, dating

Embed Size (px)

Citation preview

ISC and Offshore Substation Design

ISC Consulting Engineers A/S has many years of experience in the design of offshore substations, dating back to the design of the world’s first offshore substa-tion, installed at the Nysted Offshore Wind Farm in 2003.ISC’s experience in the design of offshore structures is founded on the knowledge obtained from over 38 years in the off-shore oil and gas industry.

Since then ISC has successfully under-taken the complete detailed design of further 15 offshore substations. ISC’s portfolio clearly demonstrates a com-prehensive expertise within the field of offshore substation design, including a broad spectrum of topside layouts as well as jacket and monopile substructures.ISC has also demonstrated the ability to work alongside local authorities across Europe to produce superior solutions which conform to the local requirements.

PRINCESS AMALIA (120 MW)

No. of transformers : 1Topside weight : 650 tonnesInstallation year : 2007Water depth : 19-24 metersSubstructure : MonopileDetailed Design : TopsideOwner : Eneco

WALNEY 1 (183.6 MW)

No. of transformers : 2Topside weight : 1030 tonnesJacket weight : 994 tonnesInstallation year : 2010Water depth : 21 metersSubstructure : JacketDetailed Design : Topside and jacket Owner : Dong Energy

GODE WIND 01 (332 MW)

No. of transformers : 2Topside weight : 1950 tonnesJacket weight : 1800 tonnesInstallation year : 2015Water depth : 30 metersSubstructure : JacketDetailed Design : Topside and jacketOwner : Dong Energy

WEST OF DUDDON SANDS (389 MW)

No. of transformers : 2Topside weight : 1580 tonnesJacket weight : 1230 tonnesInstallation year : 2013Water depth : 19 metersSubstructure : JacketDetailed Design : Topside and jacket Owner : Dong Energy and Scottish Power

NYSTED I (166 MW)

No. of transformers : 1Topside weight : 670 tonnesInstallation year : 2003Water depth : 6-10 metersSubstructure : Concrete gravityDetailed Design : TopsideOwner : Dong Energy

GUNFLEET SANDS (172 MW)

No. of transformers : 2Topside weight : 1315 tonnesTransition piece : 155 tonnesInstallation year : 2008Water depth : 6-15 metersSubstructure : MonopileDetailed Design : Topside Owner : Dong Energy

GODE WIND 02 (252 MW)

No. of transformers : 2Topside weight : 1950 tonnesJacket weight : 1790 tonnesInstallation year : 2015Water depth : 33 metersSubstructure : JacketDetailed Design : Topside and jacketOwner : Dong Energy

BORKUM RIFFGRUND 1 (320 MW)

No. of transformers : 2Topside weight : 1880 tonnesJacket weight : 1720 tonnesInstallation year : 2013Water depth : 24 metersSubstructure : JacketDetailed Design : Topside and jacket Owner : Dong Energy

NORDSEE ONE (324 MW)

No. of transformers : 2Topside weight : 1790 tonnesJacket weight : 1310 tonnesInstallation year : 2015Water depth : 28 metersSubstructure : JacketDetailed Design : Topside and jacketOwner : RWE Innogy

HORNS REV 2 (209 MW)

No. of transformers : 1Topside weight : 1238 tonnesJacket weight : 798 tonnesInstallation year : 2008Water depth : 13 metersSubstructure : JacketDetailed Design : Topside and jacketOwner : Energinet.dk

NORTHWIND (216 MW)

No. of transformers : 1Topside weight : 1140 tonnesInstallation year : 2013Water depth : 20 metersSubstructure : MonopileDetailed Design : TopsideOwner : Northwind Offshore Energy

WALNEY 2 (183.6 MW)

No. of transformers : 2Topside weight : 1030 tonnesJacket weight : 995 tonnesInstallation year : 2011Water depth : 24 metersSubstructure : JacketDetailed Design : Topside and jacket Owner : Dong Energy

LILLGRUND (110.4 MW)

No. of transformers : 1Topside weight : 670 tonnesInstallation year : 2007Water depth : 4-10 metersSubstructure : Concrete gravityDetailed Design : TopsideOwner : Vattenfall

BALTIC 1 (48.3 MW)

Transition piece weight : 1100 tonnesInstallation year : 2010Water depth : 19 metersSubstructure : Monopile Detailed Design : Monopile Owner : EnBW

Borkum Riffgrund 1, installation German Bight, August 2013.

Location : German Bight

Location : German Bight

Location : German Bight

Location : Belgian North Sea

Location : UK Irish Sea Location : UK North Sea

Location : UK Irish Sea

Location : German Baltic Sea

Location : UK Irish Sea

Location : German North Sea Location : Danish North Sea

Location : Sweden Öresund

Location : Netherlands North Sea

Location : Danish Baltic Sea

NORDSEE OST (295 MW)Installation year : 2014

NORDSEE ONE (324 MW)Installation year : 2015

GODE WIND 01 (332 MW)GODE WIND 02 (252 MW)

Installation year : 2015

NORTHWIND (216 MW)Installation year : 2013

WEST OF DUDDON SANDS (389 MW)Installation year : 2013

BORKUM RIFFGRUND 1 (320 MW)Installation year : 2013

WALNEY 2 (183.6 MW)Installation year : 2011WALNEY 1 (183.6 MW)Installation year : 2010

BALTIC 1 (48.3 MW)Installation year : 2010

GUNFLEET SANDS (172 MW)Installation year : 2008

HORNS REV 2 (209 MW)Installation year : 2008

PRINCESS AMALIA (120 MW)Installation year : 2007

NYSTED 1 (166 MW)Installation year : 2003LILLGRUND (110.4 MW)

Installation year : 2007

NORDSEE OST (295 MW)

No. of transformers : 2Topside weight : 1600 tonnesInstallation year : 2014Water depth : 23 metersSubstructure : JacketDetailed Design : TopsideOwner : RWE Innogy

Location : German Bight

Detailed Designs