1. Check The Part Number of the LAN Interface on Packing.

It should be (H0098C) for Pasolink V4

2. Pasolink V4 1+1 IDU “Switch Unit” Needs to be removed for LAN Interface installation, No need to de-install whole IDU From Rack.

Page 2: Installation Procedure of Pasolink V4 LAN Interface

3. Pasolink V4 1+0

Please “Switch OFF” IDU, Remove all connections PCM E1 cable, Power cable, Grounding cable, Alarm Cables, NMS Cables etc & Remove the IDU from Rack.

4. In case of Pasolink V4 1+1, “Switch OFF” IDU & Remove “Switch Unit”. Remove all Screws to Remove Top Cover of Switch Unit.

Page 3: Installation Procedure of Pasolink V4 LAN Interface

5. In case of Pasolink V4 1+0 , Remove all Screws to open TOP Cover.

6. Remove TOP Cover of V4 1+0 IDU or TOP cover of “Switch Unit” of V4 1+1

Page 4: Installation Procedure of Pasolink V4 LAN Interface

7. Identify the LAN Interface Connector in IDU.

8. Remove the “Front Plate” for 2-Port LAN Interface.

9. Remove the “two screws” from inside the IDU to open Front Plate.

Page 5: Installation Procedure of Pasolink V4 LAN Interface

10.Install “Support Stud” which comes with LAN INTF Module.

11.Remove the “Screw” to install the Support Stud for LAN Interface.

12.Install “Support Stud” from where the Screw is removed.

Page 6: Installation Procedure of Pasolink V4 LAN Interface

13.Install the “LAN Interface Module.”

14.Fix the “Screw” on LAN INTF Mod. which is removed before for Support Stud.

15.Fix the “Two Screws” from where the Front Plate has been removed.

Page 7: Installation Procedure of Pasolink V4 LAN Interface

16.Install the Top Cover of IDU In case of V4 1+0 & Switch Unit in case of V4 1+1

17.Install V4 1+0 IDU in Rack or Install V4 1+1 Switch Unit in IDU Chassis.a) Pasolink V4 1+0 with “LAN INTF Module”

b) Pasolink V4 1+1 Switch Unit with “LAN INTF Module”

18.Connect Grounding Cable, IF cable, Power Cable, PCM E1 Cable, LAN Cable, NMS Cable, AUX alarm cable if it is there before switch ON the IDU.

-----------------------------------------------------END-----------------------------------------------

Page 8: Installation Procedure of Pasolink V4 LAN Interface

LAN Interface Settings with PNMTj

1) After Installation of LAN Interface in IDU, Login to Pasolink V4 by PNMTj

Page 9: Installation Procedure of Pasolink V4 LAN Interface

2) Click ON “Configuration” & Go to “Equipment Setup”

3) Check Whether LAN Interface card is Mounted Properly or NOT in “Optional Panel Status”.

Page 10: Installation Procedure of Pasolink V4 LAN Interface

Status Should be “Mounted” & Green Color. Click On the “Port Setting”

4) Do the Following Settings as Required

Page 11: Installation Procedure of Pasolink V4 LAN Interface

Note : Be careful while Allotting the Bandwidth as Particular E1 will be disable & Traffic can be down. Please Follow the bellow table while Allotting the Bandwidth & shift the traffic to appropriate channel at both the sites in the hop.

Page 12: Installation Procedure of Pasolink V4 LAN Interface

5) After Configuring the “LAN Ports Alarms” can be checked & when the Bandwidth is Allotted some of the E1s get “disabled”.

Page 13: Installation Procedure of Pasolink V4 LAN Interface

6) When Traffic is Connected In LAN Port, It will become “Normal”

Additional Information :

1) IF Port1 & Port2 are being used, while configuring Port 2 Bandwidth should be equal to or less than Port1.

2) Ethernet Port - Bandwidth should be same at Both the End in Hop.