Installation of the BP Atlantis Flowlines and Risers By HMC IPLOCA 2008 Presented by: Simon Webb BP and Bas Zoon HMC Date: 7 October 2008

Installation of the BP Atlantis Flowlines and Risers By HMC BP... · HMC SOW highlights of the Atlantis Installation Projects Semi Submersible Production Quarters (PQ) installed by

  • Upload
    others

  • View
    4

  • Download
    3

Embed Size (px)

Citation preview

Page 1: Installation of the BP Atlantis Flowlines and Risers By HMC BP... · HMC SOW highlights of the Atlantis Installation Projects Semi Submersible Production Quarters (PQ) installed by

Installation of the BP Atlantis Flowlines and Risers By HMC

IPLOCA 2008

Presented by: Simon Webb BP and Bas Zoon HMCDate: 7 October 2008

Page 2: Installation of the BP Atlantis Flowlines and Risers By HMC BP... · HMC SOW highlights of the Atlantis Installation Projects Semi Submersible Production Quarters (PQ) installed by

2

HMC SOW highlights of the Atlantis Installation Projects

Semi Submersible Production Quarters (PQ) installed by HMC24 inch export oil line and a 16 inch export gas line, installed by HMCHMC flow line scope; transport and installation of work 5 PIP lines and one water injection line from drill centre to PQ offshore Gulf of Mexico

- Water Depth +2 km (7000 ft)- Length ~2 km Flowline and ~3 km Riser- 16 inch x 10.75 inch PIP

Page 3: Installation of the BP Atlantis Flowlines and Risers By HMC BP... · HMC SOW highlights of the Atlantis Installation Projects Semi Submersible Production Quarters (PQ) installed by

3

The Atlantis Field

Page 4: Installation of the BP Atlantis Flowlines and Risers By HMC BP... · HMC SOW highlights of the Atlantis Installation Projects Semi Submersible Production Quarters (PQ) installed by

4

The Atlantis Field

Page 5: Installation of the BP Atlantis Flowlines and Risers By HMC BP... · HMC SOW highlights of the Atlantis Installation Projects Semi Submersible Production Quarters (PQ) installed by

5

Pipeline Design

Procurement

Fabrication

SCR pull-in equipment on the Atlantis Floater

System Integration Testing

Load out onto HMC provided Barges

Onshore Scope of Work

Page 6: Installation of the BP Atlantis Flowlines and Risers By HMC BP... · HMC SOW highlights of the Atlantis Installation Projects Semi Submersible Production Quarters (PQ) installed by

6

The Atlantis Field

Page 7: Installation of the BP Atlantis Flowlines and Risers By HMC BP... · HMC SOW highlights of the Atlantis Installation Projects Semi Submersible Production Quarters (PQ) installed by

7

Onshore Fabrication – Bayou, New Iberia

Page 8: Installation of the BP Atlantis Flowlines and Risers By HMC BP... · HMC SOW highlights of the Atlantis Installation Projects Semi Submersible Production Quarters (PQ) installed by

8

Onshore Fabrication – Spool Piece Load out

Page 9: Installation of the BP Atlantis Flowlines and Risers By HMC BP... · HMC SOW highlights of the Atlantis Installation Projects Semi Submersible Production Quarters (PQ) installed by

9

System Integration Testing

Page 10: Installation of the BP Atlantis Flowlines and Risers By HMC BP... · HMC SOW highlights of the Atlantis Installation Projects Semi Submersible Production Quarters (PQ) installed by

10

SCR Pull-in Chain Jack on Atlantis PQ

Page 11: Installation of the BP Atlantis Flowlines and Risers By HMC BP... · HMC SOW highlights of the Atlantis Installation Projects Semi Submersible Production Quarters (PQ) installed by

11

The Spread: Transportation Barge

Page 12: Installation of the BP Atlantis Flowlines and Risers By HMC BP... · HMC SOW highlights of the Atlantis Installation Projects Semi Submersible Production Quarters (PQ) installed by

12

Keys to Success

• The Team!• Detailed Onshore Preparation • DCV Balder; The Proper

Equipment for the Work an Inherently flexible vessel

• Excellent Crew and interfaces with Client and SIMOPS

• Flexibility to manage schedule and procedures (using MOC processes)

• Contingency and Emergency response planning

• Safety Management

Page 13: Installation of the BP Atlantis Flowlines and Risers By HMC BP... · HMC SOW highlights of the Atlantis Installation Projects Semi Submersible Production Quarters (PQ) installed by

13

Balder Deck During The Atlantis Project

Page 14: Installation of the BP Atlantis Flowlines and Risers By HMC BP... · HMC SOW highlights of the Atlantis Installation Projects Semi Submersible Production Quarters (PQ) installed by

14

SIMOPS in Action

Page 15: Installation of the BP Atlantis Flowlines and Risers By HMC BP... · HMC SOW highlights of the Atlantis Installation Projects Semi Submersible Production Quarters (PQ) installed by

15

Team Continuity and Achievement

Page 16: Installation of the BP Atlantis Flowlines and Risers By HMC BP... · HMC SOW highlights of the Atlantis Installation Projects Semi Submersible Production Quarters (PQ) installed by

16

PLET PULL IN ANIMATION

Page 17: Installation of the BP Atlantis Flowlines and Risers By HMC BP... · HMC SOW highlights of the Atlantis Installation Projects Semi Submersible Production Quarters (PQ) installed by

17

SLIDING PIP On Balder Deck and in Tower

Page 18: Installation of the BP Atlantis Flowlines and Risers By HMC BP... · HMC SOW highlights of the Atlantis Installation Projects Semi Submersible Production Quarters (PQ) installed by

18

INNER PIPE PULL OUT

Page 19: Installation of the BP Atlantis Flowlines and Risers By HMC BP... · HMC SOW highlights of the Atlantis Installation Projects Semi Submersible Production Quarters (PQ) installed by

19

Tower welding

Page 20: Installation of the BP Atlantis Flowlines and Risers By HMC BP... · HMC SOW highlights of the Atlantis Installation Projects Semi Submersible Production Quarters (PQ) installed by

20

RISER TRANSFER - ANIMATION

Riser Transfer of 750 mT dry LoadTransfer with three systems, Crane A&R and Chain JackSpool piece installed on Balder No divers required

Page 21: Installation of the BP Atlantis Flowlines and Risers By HMC BP... · HMC SOW highlights of the Atlantis Installation Projects Semi Submersible Production Quarters (PQ) installed by

21

Lessons Learned

Integrated team (BP and HMC) to work issues

Team continuity and team approach is essential to success –recognise the need for team career development over long projects

Three years of onshore engineering/planning ensured smooth offshore execution

Understand the technical complexity – resource accordingly

Plan for SIMOPS