Upload
haphuc
View
227
Download
6
Embed Size (px)
Citation preview
Semi-Annual Environmental Monitoring Report Project number: 42265-023 January 2015 Period: July to December 2014
IND: Assam Urban Infrastructure Investment Program – (Tranche 1) This report has been submitted to ADB by the Guwahati Development Department and Urban Development Department of the Government of Assam and is made publicly available in accordance with ADB’s public communications policy (2011). It does not necessarily reflect the views of ADB. The environmental monitoring report is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board of Directors, Management, or staff, and may be preliminary in nature. In preparing any country program or strategy, financing any project, or by making any designation of or reference to a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.
:::: Government of Assam ::::
Assam Urban Infrastructure Investment Program (AUIIP) Guwahati Development Department
3rd Floor, Tripti Tower, Ganeshguri, Guwahati-05 Tel No.: +91 361 2349839, Fax No.: +91 3612349849
E -mail: [email protected], Website: http://www.auiip.nic.in
No.ADB/AUIIP/ GHTY/87/2014/529 Date: .04 .2015
From,
The Project Director,
Assam Urban Infrastructure Investment Program (AUIIP)
To,
Sri Vijay Padmanabhan,
Senior Urban Development Specialist
SAUW, ADB
Sub: Submission of Semi Annual Environment Monitoring Report (period July-Dec'2014)
of Assam Urban Infrastructure Investment Program.
Dear Vijay,
As per the subject cited above, we are submitting herewith the Semi Annual
Environment Monitoring Report (period July-Dec '2014) of Assam Urban Infrastructure Investment
Program The report is enclosed herewith.
This is for favour of your information and necessary action.
Encl: As stated above. Yours Faithfully,
Projec rector
Assam Urban I rastructure
Investment rogram
(AUIIP)
Project Director
Assam Urban Infrastructure Investment Programme
Ganeshguri, Guwahati-5
Government of Assam
Guwahati Development Department
&
Urban Development Department
Fifth (5th) REPORT
SEMI ANNUAL ENVIRONMENT MONITORING REPORT
(Period July to December 2014)
January 2015
ASSAM URBAN INFRASTRUCTURE INVESTMENT PROGRAM (AUIIP)
(ADB Loan No: 2806-IND)
AUIIP: ADB Loan – 2806 Semi Annual Environment Monitoring Report for AUIIP (July to December- 2014)
2 of 51
TABLE OF CONTENTS
I. INTRODUCTION ........................................................................................................... 5
II. IMPLEMENTATION PROGRESS .................................................................................. 8
III. ENVIRONMENTAL PROCEDURE REVIEW ............................................................... 17
IV. IMPLEMENTATION STATUS OF ENVIRONMENT MEASURES ................................ 22
V. ENVIRONMENTAL MONITORING AND EVALUATION ............................................. 23
VI. MAJOR PROJECT ISSUES AND PROBLEMS ENVIRONMENTAL CONTEXT ......... 25
VII. CONSULTATIONS AND RECOMMENDATIONS ENVIRONMENTAL CONTEXT ...... 25
VIII. GRIEVANCE REDRESSAL ....................................................................................... 25
IX. ISSUES AND ACTION PLAN ..................................................................................... 26
ANNEXURE 1: ENVIRONMENTAL LEGISLATION AND POLLUTION CONTROL ACTS 28
ANNEXURE 2: ENVIRONMENT FOREST AND OTHER COMPLIANCE........................... 32
ANNEXURE 3: CONSENT TO ESTABLISH – WATER TREATMENT PLANT .................. 32
ANNEXURE 4: NOC FROM AIRPORT AUTHORITY OF INDIA FOR LANDFILL SITE AT
GHORAMARA, ASSAM ..................................................................................................... 36
ANNEXURE 5: COMPLIANCE OF APPLICATION OF EMP .............................................. 37
ANNEXURE 6: ENVIRONMENT PERFORMANCE FACT SHEET ..................................... 49
ANNEXURE 7: PUBLIC CONSULTATION ON ENVIRONMENTAL ISSUES .................... 50
ANNEXURE 8: SAMPLE GRIEVANCE REGISTRATION FORM ....................................... 51
AUIIP: ADB Loan – 2806 Semi Annual Environment Monitoring Report for AUIIP (July to December- 2014)
3 of 51
ABBREVATIONS
ADB - Asian Development Bank
AUIIP - Assam Urban Infrastructure Investment Program
APCB - Assam Pollution Control Board
AUWSSB - Assam Urban Water Supply and Sanitary Board
BSR - Basic Schedule of Rates
BRTS - Bus Rapid Transit System
CDTA - Capacity Development Technical Assistance
CRZ - Coastal Regulation zone
CTE - Consent to Establish
CTO - Consent to Operate
DFO - Divisional Forest Officer
DMB - Dibrugarh Municipal Board
DSC - Design and Supervision Consultant
DTP - Dibrugarh Town Protection
EARF - Environmental Assessment and Review Framework
EC - Environmental Clearance
EIA - Environmental Impact Assessment
EM - Environment Monitoring
EMP - Environmental Management Plan
FHH - Female Headed Households
GAP - Gender Action Plan
GDD - Guwahati Development Department
GMC - Guwahati Municipal Corporation
GoA - Government of Assam
GMDA - Guwahati Metropolitan Development Authority
GRM - Grievance Redress Mechanism
IEC - Information, Education and Communication
IEE - Initial Environmental Examination
ILRP - Income and Livelihood Restoration Program
IOCL - Indian Oil Corporation Ltd.
AUIIP: ADB Loan – 2806 Semi Annual Environment Monitoring Report for AUIIP (July to December- 2014)
4 of 51
LOA - Letter of Acceptance
LOI - Letter of Intent
MFF - Multi Tranche Financing Facility
NABET - National Accreditation Board for Education and Training
NOC - No Objection Certificate
NTP - Notice to Proceed
PD - Project Director, AUIIP
PHED - Public Health Engineering Department
PIU - Project Implementation Unit
PMC - Project Management Consultants
PMU - Project Management Unit
PPMS - Project Performance Monitoring System
PSO - Project Support Office, Guwahati
PUC - Pollution Under Control
RP - Resettlement Plan
SM - Social Monitoring
SPPTS
- Support project program and Technical Assistance
SPS - Safeguards Policy Statement, 2009
STP - Sewage Treatment Plant
SWM - Solid Waste Management
TL - Team Leader
TOR - Terms of Reference
DTL - Dy. Team Leader
UDD - Urban Development Department
WO - Work Order
WTP - Water Treatment Plant
AUIIP: ADB Loan – 2806 Semi Annual Environment Monitoring Report for AUIIP (July to December- 2014)
5 of 51
I. INTRODUCTION
A. Background
1. Guwahati is the largest city and gateway of North-Eastern states of India. The city is
lagging behind in respect of providing basic services like water supply, sewerage, proper
drainage and scientific solid waste management system. It has almost no sewerage
system and more than two third of the area has not been covered by any piped water
supply system. Further, Dibrugarh, the third largest populous city of Assam is suffering
with the inadequacy of drainage and improper management of solid waste system.
2. Looking forward to improve the quality of life, Govt. of Assam have prioritized some
projects and taken initiatives for Infrastructure development in the field of water supply,
sewerage, drainage and solid waste management. Basing on the priority, the Govt. has
identified projects and decided to implement water supply and sewerage scheme for
Guwahati and rehabilitation of Dibrugarh Town Protection (DTP) drain as well as
improving Solid Waste Management (SWM) system for Dibrugarh. Due to requirement of
huge investment, the Govt. of Assam have availed external funding assistance in order to
address the situation and improve the basic service levels. The work for supply of surface
water based water supply project to South Guwahati West Zone funded under JNNURM
Program is in progress and in completion stage. A surface water based water supply
project work for South Guwahati Central Zone with JICA assistance also has been
started. The water supply of South Guwahati East zone as well as drainage and solid
waste management of Dibrugarh are under implementation with funding assistance of
ADB under Assam Urban Infrastructure Investment Program (AUIIP), which has been
constituted to implement the ADB funded project on behalf of Guwahati Development
Department and Urban Development Department of Government of Assam.
3. The estimated cost of the investment program is $ 285.80 million and is proposed to be
implemented in a period of six years from 01-03-2012 to 31-12-2017 in 2 Projects i.e. in
Project-I & Project-II. Assam Urban Infrastructure Investment Program envisages
implementation of physical investments in various components ,namely (1)Water Supply
in South East Guwahati (2) Sewerage System in South East Guwahati (3) Pilot Project of
Bus Rapid Transport in Guwahati (4) Drainage for Dibrugarh and (5) SWM for Dibrugarh.
Other components include Capacity Building, Institutional development, Governance,
Urban Reforms and Investment Program Support.
4. The Project - I is being implemented at an estimated cost of $115.50 million out of which
ADB share is $ 81.0 million and GOA share is $ 34.50 million. A tripartite agreement
between Govt. of India, Govt. of Assam & ADB was signed on 9 March 2012 for $ 81
million loan agreement for Project-I (ADB loan No.2806 –IND). The work of Project-I is
targeted to be implemented during the period from 01.03.2012 to 31.12.2016. The Loan
Agreement between the State Govt. and ADB for Project-II investment plan will be signed
in a later stage.
5. To support implementation of the Program, AUIIP have engaged Design & Supervision
Consultant (DSC) as well as Project Management consultant (PMC).The work of Project
Management Consultancy (PMC) services under AUIIP has been entrusted to M/s Tetra
Tech India Ltd. in association with M/s Poyry Environment GmbH and M/s Vision EIS
AUIIP: ADB Loan – 2806 Semi Annual Environment Monitoring Report for AUIIP (July to December- 2014)
6 of 51
Consulting Pvt. Ltd. Design and Supervision work of the project has been entrusted to
M/s Shah Technical Consultant (P) Ltd. in association with SMEC India (P) Ltd.
B. Project & Report Purpose
6. AUIIP has been set up by Government of Assam to oversee the implementation and
monitoring of various sub projects in the project cities of Guwahati and Dibrugarh.
7. Sub projects under Project-I has been classified by ADB as environmental assessment
Category B (some negative impacts but less significant than category A) and the impacts
of subprojects were assessed through Initial Environmental Examination (IEE), prepared
according to ADB Safeguard Policy (SPS 2009).
8. This report is the “Environment Monitoring Report” for the period July to December 2014
to describe the implementation of the mitigation measures and monitoring recommended
in the IEE.
C. Project Profile Project- I
9. Till 31st December, 2014, contract agreement has been signed for three sub projects, two
sub projects at Guwahati and one at Dibrugarh under Project-I. Also “Notice to Proceed” (NTP)/Work Order has been issued to selected bidder for all the three sub projects.
10. List of sub projects under Project-I is given hereunder:
Table 1: Sub Project status under Project I of AUIIP
Town Code Sub project Status
Tranche I
Water Supply System (WS)
Guwahati AUIIP/PR-
1/GUW/WS-01
Construction of Transmission
water supply pipelines and allied
works at Guwahati
Procurement process completed.
Letter of Acceptance issued on
30.04.2013, agreement done on
29.05.2013 and notice to
proceed issued on 04.06.2014
Guwahati AUIIP/PR-
1/GUW/WS-02
Construction of storage
reservoirs of various capacities
at 6 locations at Guwahati,
approach road and allied works
Procurement process completed.
Letter of Acceptance issued on
06.06.2012, agreement done on
01.02.2013 and notice to
proceed issued on 30.05.2013
Guwahati AUIIP/PR-
1/GUW/WS-03
Tentative package - Design,
Build and operation (DBO) of
Intake works, Raw water rising
man, WTP, clear water pumping
station, laying of distribution pipe
line and associated works at
Guwahati
Design completed. BID
documents prepared and
submitted to GOA and ADB for
approval. Selection of new intake
site is done.
Works shifted to Tranche II and
clubbed with water distribution
network and will be invited as
one DBO contract.
Invitation of BID is expected
shortly.
AUIIP: ADB Loan – 2806 Semi Annual Environment Monitoring Report for AUIIP (July to December- 2014)
7 of 51
Town Code Sub project Status
Tranche I
Strom Water Drainage (DR)
Dibrugarh AUIIP/PR-
1/DIB/DR-01
Construction of RCC DTP Drain,
Widening of Culverts and allied
works in Dibrugarh from
chainage 0 to 9500 m
Selection of construction agency
done. Letter of Acceptance issued
on 13.12.2013. Agreement signed
on 20.02.2014 and notice to
proceed issued on 25.03.2014
Solid Waste Management (SWM)
Dibrugarh AUIIP/PR-
1/DIB/SWM-01
Design, Build and Operation
(DBO) of 100 MT processing
plant and 60 MT sanitary land fill
site and allied works at
Dibrugarh
Under DPR preparation &
approval stage. Will be finalized
after obtaining Environmental
clearance
Dibrugarh AUIIP/PR-
1/DIB/SWM-02
Procurement of equipment for
primary, secondary collection
and transportation vehicles for
Municipal Solid Waste
Management at Dibrugarh
Under designing stage
11. Table 2 show the status of the sub project, starting date, schedule date of completion and
physical progress
Table 2: Status of Sub-project Awarded/Implementation under Project-I (Upto 31st December 2014)
Location Component, name of the sub project (Code No.)
Starting date of Implementation
Projected months of completion (as per Work order)
Schedule date of completion (Extended date of completion)
Physical progress (%) as on 31.12.2014
Guwahati City
Water Supply- Construction of storage reservoirs of various capacities at 6 locations at Guwahati, approach road and allied works (AUIIP/PR-1/GUW/WS-02)
30.05.2013 1100 days 36 months 5 days
04.06.2016 9%
Guwahati City
Construction of Transmission water supply pipelines and allied works at Guwahati (AUIIP/PR-1/GUW/WS-01)
04.06.2014 900 Days or 2 yrs 5 months 20 days
24.11.2016 Nil
Dibrugarh City
Construction of RCC DTP
Drain, Widening of
Culverts and allied works
in Dibrugarh from chainage
0 to 9500 m (AUIIP/PR-
1/DIB/DR-01)
25.03.2014 1095 Days or 36 months
25.03.2017 Nil
AUIIP: ADB Loan – 2806 Semi Annual Environment Monitoring Report for AUIIP (July to December- 2014)
8 of 51
II. IMPLEMENTATION PROGRESS
A. Major works and progress
12. Till date physical work has been started for one sub project under Project-I. Table 3
shows the work progress status format. Work scope for the package for which Work
Order (NTP) has been issued is also given hereunder.
13. Monitoring and reporting on Environmental safeguard has already been started.
AUIIP: ADB Loan – 2806 Semi Annual Environment Monitoring Report for AUIIP (July to December- 2014)
9 of 51
Table 3: Major Works under Sub project and Progress – Project- I
Location Component, Name of Sub Projects (Code No.)
List of major works under the sub project
Type of works continued at present
Expected changes from approved scope
Fulfillment of objectives- Type of remedial measures needed
Key assumptions and risks that affect attainment of the objectives
Guwahati city
Water Supply - Construction of storage reservoirs of various capacities at 6 locations at Guwahati, approach road and allied works (AUIIP/PR-1/GUW/WS-02)
o Construction, testing and commissioning of six numbers of Ground Level Service Reservoirs (GLSR) of different capacities at Gopal Nagar, North Jyotinagar, Kenduguri, Jonaki Nagar, NabaJyotinagar and Basistha (Capacity 2.8 to 17 million litter)
o Providing and erecting all auxiliary items pipe assembly work for inlet, outlet, over flow, bypass and wash out pipes with butterfly and sluice valves and R.C.C chambers, drainage pipes with manhole chambers, water level indicator, lightening arrestor, ventilation arrangement, stairs to roof slab, stairs for going inside, etc.
o Construction of earth retaining walls at specified locations at each reservoir site.
o Construction of approach
Geo technical
investigation completed
Construction of
approach road to
Gopalnagar reservoir
site continued
Rubble masonary work
along approach road at
Gopalnagar continued
Excavation for reservoir
at Gopalnagar started
Retaining wall
construction at
Gopalnagar started
Nil Strict application of
mitigation measures
Delayed in
execution
process
AUIIP: ADB Loan – 2806 Semi Annual Environment Monitoring Report for AUIIP (July to December- 2014)
10 of 51
Location Component, Name of Sub Projects (Code No.)
List of major works under the sub project
Type of works continued at present
Expected changes from approved scope
Fulfillment of objectives- Type of remedial measures needed
Key assumptions and risks that affect attainment of the objectives
road to each reservoir location.
Guwahati city
Construction of Transmission water supply pipelines and allied works at Guwahati (AUIIP/PR-1/GUW/WS-01)
Supplying, laying, jointing, testing and commissioning of about 20.45 Km length of mild steel pipe line of nominal internal diameter ranging from 1300mm to 700mm.
Supplying, laying, jointing, testing and commissioning of about 5.3 km length of gravity pipe line of Ductile Iron (Class K-9) of 500mm nominal internal diameter.
Earth work excavation, laying of bedding wherever specified, backfilling the trenches, and restoring and making good all surfaces which are damaged during excavation,
Fixing and connecting all pipe line fixtures such as valves, bends, tees, blank flanges, tail pieces, flow meter etc.,
Construction of all appurtenant structures including construction of
No physical work
AUIIP: ADB Loan – 2806 Semi Annual Environment Monitoring Report for AUIIP (July to December- 2014)
11 of 51
Location Component, Name of Sub Projects (Code No.)
List of major works under the sub project
Type of works continued at present
Expected changes from approved scope
Fulfillment of objectives- Type of remedial measures needed
Key assumptions and risks that affect attainment of the objectives
road crossings, drainage crossings, pedestals, supports, anchor/ thrust blocks, valve chambers, etc.
Dibrugarh city
Construction of RCC DTP Drain, Widening of Culverts and allied works in Dibrugarh from chainage 0 to 9500 m (AUIIP/PR-1/DIB/DR-01)
Widening and construction of 9.500 km (chainage 0 - 9500 m) reinforced cement concrete (RCC) drain with linings;
Construction of 17 nos. box culverts; and
Construction of sullage pumping station.
No physical work
AUIIP: ADB Loan – 2806
Semi Annual Environment Monitoring Report for AUIIP (July to December- 2014)
12 of 51
B. Compliance of Safeguard Loan Covenants
14. The status of compliance of ADB’s major Loan Covenants related to Safeguard issues
is shown below:
Serial no. as per loan agreement
Program Specific Covenants Status / Issues
Environment
14 The Borrower shall cause the State to ensure
that the preparation, design, construction,
implementation, operation and
decommissioning of each Subproject comply
with (a) all applicable laws and regulations of
the Borrower relating to environment, health,
and safety; (b) the Environmental Safeguards;
(c) the EARF; and (d) all measures and
requirements set forth in the relevant IEE and
EMP, and any corrective or preventative
actions set forth in the Environment Monitoring
Report.
Under compliance
Documents are prepared by complying all
relevant State and National Laws, Safeguard
Policy Statement (SPS 2009) of ADB,
Environment Assessment Review Framework
(EARF) for PR-I. Same will be followed for
subsequent Program.
Initial Environmental Examination (IEE),
Environment Management Plan (EMP) report
prepared and approved by ADB (for PR-I). In
case of any change of scope and locations IEE
will be revised. Documentation for next tranches
commenced & review under progress as per
project design.
All measures and requirements as prescribed in
IEE and EMP will be considered during
implementation.
Corrective or preventive action plans which will
be reflected in Environment Monitoring Report
and project implementation authority will be
taken care.
Human and Financial Resources to Implement
Safeguards Requirements
18. The Borrower shall cause the State to make
available necessary budgetary and human
resources to fully implement the EMPs
Under compliance
Budgetary provisions have been included in
EMPs
Resettlement and Environmental Officer of
Implementation Agency are not in place but
expected to be placed before starting of the
physical activities.
Human resources (project consultant, i.e
Environment Safeguard Specialist of DSC and
PMC) for implementation of EMPs are in place
AUIIP: ADB Loan – 2806
Semi Annual Environment Monitoring Report for AUIIP (July to December- 2014)
13 of 51
Serial no. as per loan agreement
Program Specific Covenants Status / Issues
for regular compliance.
Safeguards – Related Provisions in Bidding Documents
and Works Contracts
19. The Borrower shall cause the State to ensure
that all bidding documents and contracts for
Works contain provisions that require
contractors to:
(a) comply with the measures and
requirements relevant to the contractor set
forth in the IEEs, the EMPs, the RPs and any
IPP (to the extent they concern impacts on
affected people during construction), and any
corrective or preventative actions set out in a
Safeguards Monitoring Report;
(b) make available a budget for all such
environmental and social measures;
(c) provide the PMU with a written notice of
any unanticipated environmental, resettlement
or indigenous peoples risks or impacts that
arise during construction, implementation or
operation of the Project that were not
considered in the IEEs, the EMPs, the RPs or
any IPP;
(d) adequately record the condition of roads,
agricultural land and other infrastructure prior
to starting to transport materials and
construction; and
(e) fully reinstate pathways, other local
infrastructure, and agricultural land to at least
their pre-project condition upon the completion
of construction.
Under compliance
(a) Approved IEEs, EMPs and RPs are attached
in Bidding documents. This will be followed for
all the sub projects.
In case of any change of scope, revised IEEs,
EMPs will be prepared and corrective measures
will be disclosed to contractor and same will be
reflected in the “Environment Monitoring Report”
(b) All IEEs indicate budgetary provisions for
implementation of EMPs
(c) With the development of sub project and
implementation, in case of additional
impacts/risks due to change in scope/area, that
will be reflected in the revised IEEs, EMPs and
Environment Monitoring Report and accordingly
project Executing Agency will inform the
Construction Agency for taking relevant
corrective measures.
(d) Haul roads will be marked properly (by
avoiding residences and agricultural land)
before commencement of transportation of
materials.
(e) Pathways, land which are likely to be
affected for a short period during
implementation of the sub project will be
restored by concerned construction agency
before acceptance of the work. Restoration
status will be reflected in post construction
monitoring report
Safeguards Monitoring and Reporting
20. The Borrower shall cause the State to do the
following:
(a) submit semi-annual Safeguards
Monitoring Reports to ADB and disclose
Under compliance
(a) 4th semi-annual Safeguards Monitoring
AUIIP: ADB Loan – 2806
Semi Annual Environment Monitoring Report for AUIIP (July to December- 2014)
14 of 51
Serial no. as per loan agreement
Program Specific Covenants Status / Issues
relevant information from such reports to
affected persons promptly upon submission;
(b) if any unanticipated environmental and/or
social risks and impacts arise during
construction, implementation or operation of
the Project that were not considered in the
IEEs, the EMPs, the RPs or any IPP, promptly
inform ADB of the occurrence of such risks or
impacts, with detailed description of the event
and proposed corrective action plan; and
(c) report any breach of compliance with the
measures and requirements set forth in the
EMPs, the RPs or any IPP promptly after
becoming aware of the breach.
Report was prepared for the period January to
June 2014. This is 5th
semi-annual
environment monitoring report for the
period July to December 2014. Next semi-
annual report is due on 30th
June 2015
(b) With the development of project and
implementation, in case of additional
impacts/risks due to change in scope/area, will
be reflected in revised IEEs, EMPs and
accordingly Executing Agency (EA) will inform
the ADB along with corrective action plan which
will be reflected in the Monitoring Report.
(c) In case of any breach of compliance with the
measures and requirements set forth in the
EMP; EA will promptly inform ADB and suitable
corrective action plan will be planned.
Prohibited List of Investments
21. The Borrower shall ensure or cause the State
to ensure that no proceeds of the Loan are
used to finance any activity included in the list
of prohibited investment activities provided in
Appendix 5 of the SPS.
Complied
Under Project - I, there is no violation of
prohibited investment activities as per ADB SPS
(2009) Appendix 5.
Same will be followed in subsequent project.
Labor Standards
23. The Borrower shall cause the State to ensure
that Works contracts follow all applicable labor
laws of the Borrower and the State and that
these further include provisions to the effect
that contractors (i) carry out HIV/AIDS
awareness programs for labor and disseminate
information at worksites on risks of sexually
transmitted diseases and HIV/AIDS as part of
health and safety measures for those
employed during construction; (ii) follow and
implement all statutory provisions on labor
(including not employing or using children as
labor, equal pay for equal work), health, safety,
welfare, sanitation, and working conditions;
and (iii) maximize employment of women and
local poor and disadvantaged persons for
construction purposes, provided that the
Complied in document and to be complied
during implementation
Provision are included (as per EMP & BID
document) to carry out HIV/AIDS awareness
programs for construction contractor,
application of all relevant labour laws for health
and safety including child labour law and
engagement of local labours (preferably from
economically backward group) covering women
labours.
In case of any breach of provision, necessary
corrective measures as per contract clauses
shall be taken.
All activities including awareness program will
be reflected in “Monitoring Report”.
AUIIP: ADB Loan – 2806
Semi Annual Environment Monitoring Report for AUIIP (July to December- 2014)
15 of 51
Serial no. as per loan agreement
Program Specific Covenants Status / Issues
requirements for efficiency are adequately met.
Such contracts shall also include clauses for
termination in case of any breach of the stated
provisions by the contractors.
C. Environmental and Social Organization and Management along with
Implementation Arrangements
15. Guwahati Development Department (GDD) and Urban Development Department
(UDD) of the Government of Assam (GoA) will be the Executing Agency (EA) on behalf
of Govt. of Assam. PIU of AUIIP will be the implementing agency for Dibrugarh. A
state-level PMU, headed by a Project Director (PD) is in-charge of overall execution
and technical supervision, monitoring, and financial control of all activities under the
Project.
16. Two Project Implementation Units (PIUs) dedicated exclusively to the Project will be
set up in Guwahati and Dibrugarh. Each PIU will be headed by a senior technical
officer and assisted by qualified and experienced officers seconded from the ULB,
finance, and other line departments. The PIUs will be responsible for the day-to-day
activities of project implementation in the field and will be under the direct
administrative control of the PMU.
17. The PMU will have a Safeguard Officer (SO) to ensure mitigation of any environmental
and social impacts due to the subproject. The PMU’s Safeguards Officer (PMU SO) will
have the following responsibilities: (i) address environmental and social safeguards
issues; (ii) implement the EARF/RF/IPF; (iii) monitor implementation of safeguards
plans; (iv) guide the PIUs as and when necessary on safeguard issues; and (v)
endorse/submit periodic safeguard monitoring reports received from PMC to the PMU
PD, who will then submit these to ADB. The PMU will seek GoA clearance for
submission and disclosure of the environmental and social monitoring report to ADB. It
will also coordinate with national and state agencies to resolve inter-departmental
issues, if any.
18. The PMU is assisted by PMC Safeguards Specialists (Environment & Social). The
PMC Safeguards Specialists will (i) review and finalize all reports in consultation with
the PMU SO; (ii) provide project management support, (iii) assure the technical quality
of safeguards issues related to design and construction, (iv) prepare EIA/IEE/RP/IPP
reports; and (iv) provide advice on policy reforms on safeguard matter. In addition, the
PMC Safeguards Specialists will assist the PMU on the procurement needs and other
project implementation aspects and assist in ensuring capacity building on
environmental management of the PMU, contractors, and line departments through
capacity development support and training.
AUIIP: ADB Loan – 2806
Semi Annual Environment Monitoring Report for AUIIP (July to December- 2014)
16 of 51
19. The PIUs will each have an Environment Officer (EO) and Resettlement Officer (RO)
who will be responsible for implementation of the EMP in each EIA/IEE and the RP/IPP
respectively. Both officers will undertake surveys and record their observations
throughout the construction period to ensure that safeguards and mitigation measures
are provided as intended. Both will be responsible for (i) implementing and monitoring
safeguards compliance activities, public relations activities, gender mainstreaming
activities and community participation activities; (ii) obtaining statutory clearances and
obtaining NOCs from government agencies/other entities and entering into agreements
with them for use of their land; and (iii) coordinating for obtaining ROW clearances with
related State and National agencies.
20. In addition Resettlement Officer, RO of PIUs. (i) coordinate with district administration
and NGO for land acquisition and R&R aspects and address any problems and/or
delays; (ii) monitor physical and financial progress on land acquisition and R&R
activities; and (iii) organise monthly meetings with the NGO to review the progress on
R&R.
21. Environment Safeguard Specialist as part of the DSC team to (i) update the existing
IEEs in the detailed design stage; (ii) assist in the monitoring of EMP during
construction stage; and (iii) prepare EIAs/IEEs for new subprojects, where required to
comply with national law and/or ADB procedure. Figure 1 shows the implementation
arrangement for environment and resettlement safeguards. ADB will approve all final
IEEs prior to award of any contract.
Figure 1: Safeguards Implementation Arrangement
AUIIP: ADB Loan – 2806
Semi Annual Environment Monitoring Report for AUIIP (July to December- 2014)
17 of 51
III. ENVIRONMENTAL PROCEDURE REVIEW
A. Environmental Legal Requirement
22. Rules, Policies and Regulations currently in force in India related with environmental
issues applicable to infrastructure related projects is attached at Annexure 1.
However, of most of the subproject under AUIIP are likely to cause relatively minor
negative impacts only, therefore it is expected that most of the sub projects would not
invite any serious nature of Environmental related legal issue. Subprojects and
activities which will need to be complied with appropriate laws are:
o Components that require the acquisition of forest land;
o Water Treatment Plant (WTP); and
o Composting and landfill facilities
23. The specific requirements to ensure compliance by these components and subprojects
are shown in Table 4.
Table 4: Action Required Ensuring Subprojects Comply with National
Environmental Laws
Component Applicable Legislation Compliance Action Required
1. All components that require acquisition of forest land
Forest (Conservation) Act 1980; Wildlife (protection) Act 1972
Approval from State Principal Chief Conservator of Forest and Ministry of Environment and Forests (MoEF), Government of India
Identification of non- forest land and formulate an afforestation program.
2. Water Treatment Plant (WTP) – Surface water and Sewage Treatment Plant (STP)
Water (Prevention and Control of Pollution)Act 1974
Consent to Establish (CTE) and Consent to Operate (CTO) from Assam Pollution Control Board (APCB), Government of Assam.
Based on project review and site inspection, Assam Pollution Control Board (APCB) provides CTE before construction, and stipulates the disposal standards to be met during operation. After completion of construction, CTO is issued confirming compliance with the CTE conditions, if any
Renewal of CTO during operation of surface Water Treatment Plant (WTP) and Sewage Treatment Plant (STP)
Based on the performance of the WTP/STP and its compliance with the disposal standards CTO to be renewed every year.
3. All composting and landfill facilities
Municipal Solid Wastes (Management and handing) Rules 2000
Authorization of proposed site by APCB
Authorization to be issued based on land use in and around the site and
AUIIP: ADB Loan – 2806
Semi Annual Environment Monitoring Report for AUIIP (July to December- 2014)
18 of 51
Component Applicable Legislation Compliance Action Required
groundwater condition. 4. Waste management facilities including composting, landfills and transfer stations
Environment (Protection) Act 1986: Environmental Impact Assessment Notification 2006, amended in 2009 Category B
Requires environmental clearance from State Environment Impact Assessment Authority, SEIAA
Based on preliminary information and site visits, project will be categorized as B1 or B2. B1 projects require EIA study for approval.
B. Compliance with Environmental Regulations
24. Five subprojects have been considered under Project- I. As per state and national
rules clearance and consent are required for few projects.
25. Clearance status for subprojects under Project -I is given in Table 5 below.
26. Environmental compliance status for the running project is enclosed in Annexure 2.
Table 5: Present Status of Environment, Forest & other clearances (Project-I)
(Upto 31st December 2014)
City Work (Sub project Code No.)
Applicable Legislation/ Type of clearance
Subject / Issue
Clearance given by and date
Remarks/ Action needed
Guwahati (PR-I)
Design, Build and operation (DBO) of Intake works, Raw water rising man, WTP, clear water pumping station and associated works at Guwahati (AUIIP/PR-1/GUW/WS-03) Works shifted to Tranche II and clubbed with water distribution network and will be invited as one DBO contract.
Water (Prevention and Control of Pollution) Act. 1974/ Consent to Establish (CTE) for WTP from Assam Pollution Control Board (APCB) Consent to operate will be required before operation
Application Form for “Consent to Establish” CTE for WTP/ Application submitted to Assam Pollution Control Board on 30.06.2012 and thereafter request for advance renewal on 24.06.2014
Consent to Establish (CTE) for WTP (South Guwahati East Zone) is obtained from Pollution Control Board, Assam on 19.10.2012. Further extension of CTE obtained, which valid upto 18.10.2017 (CTE & extension order attached in Annexure 3)
Complied CTE conditions will be complied during construction Before commissioning Consent to Operate shall be required.
Construction of storage reservoirs of various capacities at 6 locations at Guwahati, approach road and allied works (AUIIP/PR-1/GUW/WS-02)
Forest (Conservation) Act 1980- Forest clearance for construction of GLSRs
Requirement of tree cutting at Gopal Nagar reservoir site
Permission for cutting of trees at Gopal Nagar reservoir site obtained from DFO, Kamrup East Division on13.08.2013.
An amount of Rs. 2,19,273 is deposited by
Permission obtained. Tree feeling at Gopalnagar done
Complied
AUIIP: ADB Loan – 2806
Semi Annual Environment Monitoring Report for AUIIP (July to December- 2014)
19 of 51
City Work (Sub project Code No.)
Applicable Legislation/ Type of clearance
Subject / Issue
Clearance given by and date
Remarks/ Action needed
AUIIP to the Forest Department as valuation and operation cost of felling of trees.
Enumeration report for felling of 73 trees was issued by DFO on 24.12.2013. Feeling of trees by forest dept.
Requirement of Forest Clearance for Jonakinagar GLSR site located within Hengrabari RF
Initially application send from GMDA to Divisional Forest Officer (DFO), Kamrup east Division on 23.03.2012. As per direction of DFO PD, PMU has sent compliance report to DFO, Kamrup East Division basing on the query of Nodal Officer (FC Act) for moving to higher authority for permission
Revised proposal for transfer of forest land measuring 0.358 Ha submitted to the DFO, Kamrup East Division vide letter no. KRS 854/2007/736 dated 08.04.2013.
Joint land verification survey with GPS was completed along with ACF, Ranger, Beat Officer and Surveyor, Forest.
Joint tree enumeration on the site completed with forest officials.
Compensatory afforestation land surveyed
Preparation of 4 types of digitized maps in shape file and cost estimate for ten years of compensatory
Under Compliance Process initiated for diversion of forest land - Follow up necessary to obtained final clearance by 31
st
March 2015
AUIIP: ADB Loan – 2806
Semi Annual Environment Monitoring Report for AUIIP (July to December- 2014)
20 of 51
City Work (Sub project Code No.)
Applicable Legislation/ Type of clearance
Subject / Issue
Clearance given by and date
Remarks/ Action needed
afforestation from forest department is under process for submission of the completed proposal to PCCF for land transfer.
Undertaking on non-judicial stamp paper by State Govt. for agreeing to pay the NPV/ safety zone regeneration etc. –completed
Obtaining of FRA (Forest Right Act., 2006) clearance certificate
Requirement of Forest Clearance for construction of reservoir at Basistha located at Garhbhanga RF
PD, PMU has submitted application to Principal Chief Conservator of Forest on 09.09.2013 for necessary permission
Revised proposal for transfer of forest land measuring 0.26 Ha submitted to Forest department
Joint land verification survey with GPS was completed along with ACF, Ranger, Beat Officer and Surveyor, Forest.
Joint tree enumeration on the site completed with forest officials
Compensatory afforestation land surveyed
Preparation of 4 types of digitized maps in shape file and cost estimate for ten years of compensatory a forestation from forest department is under process for submission of the completed proposal to PCCF for land transfer.
Under Compliance Process initiated for diversion of forest land - Follow up necessary to obtained final clearance by 31
st
March 2015
AUIIP: ADB Loan – 2806
Semi Annual Environment Monitoring Report for AUIIP (July to December- 2014)
21 of 51
City Work (Sub project Code No.)
Applicable Legislation/ Type of clearance
Subject / Issue
Clearance given by and date
Remarks/ Action needed
Undertaking on non-judicial stamp paper by State Govt. for agreeing to pay the NPV/ safety zone regeneration etc. –completed
Obtaining of FRA (Forest Right Act., 2006) clearance certificate
Dibrugarh (PR-I)
Construction of RCC DTP Drain, Widening of Culverts and allied works in Dibrugarh from chainage 0 to 9500 m (AUIIP/PR-1/DIB/DR-01)
Forest (Conservation) Act 1980- Forest clearance for construction of drains
Application send to forest dept. for getting NOC on tree felling along the drain
Joint verification by forest dept., DMB and revenue dept. completed
Detail cost estimation for removal of 147 trees (Rs. 1,51,990/-) send by DFO, Dibrugarh division to project EA
Follow up. NOC & tree felling before starting of construction
Dibrugarh (PR-I)
Design, Build and Operation (DBO) of 100 MT processing plant and 60 MT sanitary land fill site and allied works at Dibrugarh (AUIIP/PR-1/DIB/SWM-01)
Environmental Impact Assessment (EIA) Notification 2006, amended in 2009 / Environmental Clearance for construction of landfill and composting facility
Engagement of NABET approved organization for Environment Clearance (EC) was done
Proposed project was presented (ref. to submitted Form I) on 03.08.2013 in the 2
nd
meeting of newly formed State Level Expert Appraisal Committee (SEAC) in Assam for getting Terms of Reference (TOR) for EIA study
Visit to project site was done by SEAC members on 20
th and 21
st
September 2013. Terms of Reference for
EIA was received The NABET approved
organization engaged for the work failed to commence the EIA study. A separate agency has been engaged for Environmental clearance.
Submission of final EIA report at earliest and Final environment clearance from SEAC
AUIIP: ADB Loan – 2806
Semi Annual Environment Monitoring Report for AUIIP (July to December- 2014)
22 of 51
City Work (Sub project Code No.)
Applicable Legislation/ Type of clearance
Subject / Issue
Clearance given by and date
Remarks/ Action needed
Primary data generation in and around landfill site completed and also secondary data collection completed. Draft EIA report prepared and public hearing conducted at Dibrugarh project site
No Objection Certificate (NOC) from Dibrugarh Airport
Online application has been submitted to Airport Authority of India (AAI) for getting NOC from Airport Authority of India (AAI)
No Objection Certificate (height clearance only) for construction of Sanitary Landfill project at Ghoramara, Dibrugarh was obtained from AAI on 28.06.2013 (NOC attached in Annexure 4)
Complied
.
IV. IMPLEMENTATION STATUS OF ENVIRONMENT MEASURES
27. Field activities have been started (for one sub project) under the Project-I. Application
of EMP commenced as per IEE report. Site specific EMP was prepared by concerned
contractor of water storage reservoirs. The compliance monitoring format for
application of mitigation measures against impacts on air, water, soil environment,
social and safety aspects is enclosed in Annexure 5. Summary compliance status of
EMP application and actions/ corrective measures presented in Table 6 below.
Table 6: Summary Compliance status of Environment Management and
Monitoring Plan (31.12.2014)
Location Name of Sub Project EMP being Implemented
(Yes / No)
Overall Status of EMP Implementation
(Excellent/Satisfactory/ Partially
Satisfactory/Below Satisfaction/Poor/Very
Poor)
Actions Proposed or continued/Additional Corrective Measures Required
Guwahati City
Water Supply- Construction of storage reservoirs of various capacities at 6 locations at Guwahati, approach road and allied works (AUIIP/PR-1/GUW/WS-02)
Yes Partially Satisfactory Stabilisation /disposal of earth generated from cutting and excavation
PUC certificate for all equipment & vehicles engaged in the project.
Use of PPE to be
AUIIP: ADB Loan – 2806
Semi Annual Environment Monitoring Report for AUIIP (July to December- 2014)
23 of 51
Location Name of Sub Project EMP being Implemented
(Yes / No)
Overall Status of EMP Implementation
(Excellent/Satisfactory/ Partially
Satisfactory/Below Satisfaction/Poor/Very
Poor)
Actions Proposed or continued/Additional Corrective Measures Required
continued Improvement in water
sprinkling at working site
Complete use of barricade near approach road which under construction
Water Supply- Construction of Transmission water supply pipelines and allied works at Guwahati (AUIIP/PR-1/GUW/WS-01)
No - No physical progress
Dibrugarh City
Drainage - Construction of RCC DTP Drain, Widening of Culverts and allied works in Dibrugarh from chainage 0 to 9500 m (AUIIP/PR-1/DIB/DR-01)
No - No physical progress
V. ENVIRONMENTAL MONITORING AND EVALUATION
28. For effective monitoring, selected environmental parameters have been identified as
indicators which will be qualitatively and quantitatively measured and compared over a
period of time in order to assess/ensure the compliance of EMP. The environmental
performance indicators are physical, biological and social characteristics identified as
most important in affecting the environment at critical locations all along the subproject
locations. The parameters identified as performance indicators are:
o Air, noise and water quality
o Compliance to EMP
o Compliance to local/state/national environmental regulations
29. During implementation process, performance monitoring fact sheet is being prepared
against each possible environmental impact and attached with the monitoring report.
Annexure 6 shows the Performance Fact Sheet for implementation of EMP.
30. During year 2013 base line air and noise quality monitoring has been carried out at 6
water reservoir sites. During report period physical work is started only at Gopalnagar
reservoir site, accordingly construction phase air and noise quality monitoring has
been carried out at that site only. Ambient air quality data is presented in Table 7. At
all the locations concentration of ambient air quality parameters are well below the
CPCB standard. Increasing trend of concentration levels for all the parameters is
AUIIP: ADB Loan – 2806
Semi Annual Environment Monitoring Report for AUIIP (July to December- 2014)
24 of 51
observed. Complete mitigation measures like suppression of dust, control of vehicle
emission are required at working sites.
Table 7: Base line Ambient Air Quality Monitoring Data at reservoir sites
Locations Stage Date of Monitoring
Parameters
SO2
µg/m3
NO2 µg/m
3
PM2.5
µg/m3
PM10 µg/m
3
CO µg/m
3
Lead (Pb) µg/m
3
Package- Water Supply: Construction of storage reservoirs of various capacities at 6 locations at Guwahati, approach road and allied works (AUIIP/PR-1/GUW/WS-02) Near proposed reservoir site at Gopal Nagar
Base line 23.06.2013 8.0 13.0 21.0 37.0 0.2 BDL During construction
17.02.2014 7.0 14.0 20.0 34.0 BDL BDL
During construction
28.05.2014 20.0 27.0 24.0 38.0 BDL BDL
During Construction
05.08.2014 23.0 26.0 27.0 45.0 BDL BDL
Near proposed reservoir site at Jonaki Nagar
Base line 23.06.2013 8.0 12.0 17.0 23.0 0.1 BDL
Near proposed reservoir site at North Jyoti nagar
Base line 23.06.2013 8.0 14.0 19.0 34.0 0.1 BDL
Near proposed reservoir site at Nabajyoti Nagar
Base line 19.10.2013 10.0 17.0 20.0 34.0 0.1 BDL
Near proposed reservoir site at Kenduguri.
Base line 21.10.2013 7.0 17.0 21.0 34.0 BDL BDL
Near proposed reservoir site at Basistha.
Base line 21.10.2013 9.0 15.0 23.0 36.0 0.1 BDL
Standard as per CPCB
80.0 80.0 60.0 100.0 2000 1.0
(CPCB: Central Pollution Control Board, BDL: Below Detection Limit)
31. Noise level monitoring data is presented in Table 8. At all the locations base line noise
level is below the prescribed standard. It is noted that there is increase in construction
noise at Gopalnagar reservoir site. Noise level is marginally higher than the standard.
Complete mitigation measures as per EMP needs to be applied.
Table 8: Base Line Noise Level Monitoring Data at Reservoir Sites
Locations Stage (Date) Sound Level in Leq dB(A)
Water Supply- Construction of storage reservoirs of various capacities at 6 locations at Guwahati, approach road and allied works (AUIIP/PR-1/GUW/WS-02)
Near proposed reservoir site at Gopal Nagar
Base line Day- 42 Night - 39
Standard as per CPCB Industrial area: Day Time- 75 Night Time- 70 Residential area: Day time- 55 Night Time- 45
During construction (18.02.2014)
Day- 38 Night - 33
During construction (28.05.2014)
Day- 62 Night – 48
AUIIP: ADB Loan – 2806
Semi Annual Environment Monitoring Report for AUIIP (July to December- 2014)
25 of 51
Locations Stage (Date) Sound Level in Leq dB(A)
During construction (05.08.2014)
Day- 64 Night - 45
Near proposed reservoir site at Jonaki Nagar
Base line Day – 45 Night - 38
Near proposed reservoir site at North Jyoti nagar
Base line Day – 39 Night - 38
Near proposed reservoir site at Nabajyoti Nagar
Base line Day – 46 Night - 40
Near proposed reservoir site at Kenduguri.
Base line Day – 48 Night - 37
Near proposed reservoir site at Basistha.
Base line Day – 43 Night - 39
(Note: Date of sampling Base line: 23.06.2013, 23.10.2013, During construction: 18.02.2014,
28.05.2014 & 05.08.2014 CPCB: Central Pollution Control Board)
32. “During construction” monitoring carried out as per Environment Management and
Monitoring Plan.
VI. MAJOR PROJECT ISSUES AND PROBLEMS ENVIRONMENTAL CONTEXT
33. Field activity of the one sub-project under Project- I just started. Till date, no major
issues and problems have been encountered with, at the sub project locations.
VII. CONSULTATIONS AND RECOMMENDATIONS ENVIRONMENTAL
CONTEXT
34. For protection of local environment during construction phase, application of mitigation
measures will be done as per specified EMP. Pubic consultation during construction/
implementation phase will be planned as per the requirement. Annexure 7 shows the
blank consultation format for recording.
VIII.GRIEVANCE REDRESSAL
35. A project Grievance Redressal Mechanism (GRM) have to be established to receive,
evaluate and facilitate the resolution of affected people’s concerns, complaints and grievances about the social and environmental performance at the level of the Project.
The GRM will aim to provide a time-bound and transparent mechanism to voice and
resolve social and environmental concerns linked to the project. The grievance
redressal mechanism and procedure is depicted in Figure 2 below. Annexure 8 shows
the sample Grievance Registration Form and Action taken report
AUIIP: ADB Loan – 2806
Semi Annual Environment Monitoring Report for AUIIP (July to December- 2014)
26 of 51
Figure 2: Grievance Redressal Mechanism
36. Till date no GR committee is set up in AUIIP. As per project Executing Agency process
has been initiated for setting up GR committee and which will be completed shortly.
IX. ISSUES AND ACTION PLAN
37. Urbanization has increased at a rapid pace in India over the recent years, much faster
than the increase in urban infrastructure facilities to support them. Also, pressure of
population has been more on larger towns/cities putting enormous pressure on the
resources of municipalities so much so that most are unable to keep up with the
provision of even basic services and infrastructure resulting in irregular availability of
water, sanitation and public amenities. In extreme cases, this has aggravated risks to
public health and safety. Assam is no exception and 2 cities selected under this
program is in dire need of upgradation of such urban infrastructure facilities which
includes, augmentation of water supply, sewerage network, drainage facilities and of
course solid waste management.
38. Experience from ADB-funded urban projects show complex social, economic, legal,
institutional, and management issues in urban development – largely derived from
realities of urban life in developing countries like India. Urban projects typically consist
of a variety of infrastructure such as roads, water, sewerage, gas pipelines, and slum
improvement/upgrading activities. It is important to mention in this context that the final
detailed engineering design in each sub project of AUIIP was prepared keeping in
mind to avoid or minimize social and environmental impact as far as possible.
However, since all the developments foreseen are city/town centric, it is difficult to
avoid any impact whatsoever in densely populated towns or cities.
AUIIP: ADB Loan – 2806
Semi Annual Environment Monitoring Report for AUIIP (July to December- 2014)
27 of 51
39. One sub project was just started at Guwahati. Action plan for satisfactory
environmental compliance along with time frame is given below.
Table 9: Action plan consider for satisfactory Environmental Compliance
Action To be taken by Time frame
Instruction to contractors and monitoring for
o Proper and quick disposal of excavated surplus earth material
o Complete use of PPE o Water sprinkling at dry period o Collection of PUC certificate o Collection of consent to operate for
stone crusher plant
Contractors, DSC To be complied as per project
advancement
o During construction monitoring in respect to air and noise quality at all project sites
Contractors To be continued as per EMP
Public consultation during construction DSC, Contractor To be done as per location and
nature of the work
AUIIP: ADB Loan – 2806
Semi Annual Environment Monitoring Report for AUIIP (July to December- 2014)
28 of 51
ANNEXURE 1: ENVIRONMENTAL LEGISLATION AND POLLUTION CONTROL ACTS
The Government of India has formulated various policy guidelines; acts and regulations aimed at the sustenance of environment in general, which are briefly summarized and applicable acts with the projects, are described in the following sub-sections.
Sl. No. Sources Legislation
1 Water Pollution The Water (Prevention and Control of Pollution) Act, 1974, as
amended in 1988
2 Air Pollution The Air (Prevention and Control of Pollution) Act, 1981, as
amended by Amendment Act, 1987
3 Noise Pollution The Noise Pollution (Regulation and Control) Rules, 2000
4 Environment The Environment (Protection) Act, 1986
5 Public Liability The Public Liability Insurance Act, 1991
The Public Liability Insurance Rules, 1991
6 Hazardous Waste Hazardous Waste (Management and Handling) Rules, 1989
Batteries (Management and Handling) Rules, 2001 Manufacture, Storage and Import of Hazardous Chemical
Rules, 1989 Emergency Planning Preparedness and Response for
Chemical Disasters Rules, 1995 Manufacturing, Use, Import, Export and Storage of
Hazardous Microorganisms, Genetically Modified Engineered Organisms or Cell Rules, 1993
Hazardous Microorganisms and Genetically Modified Organisms (Manufacture, Use Import Expert and Storage) Rules, 1999
Bio- Medical Waste (Management and Handling) Rules, 2000
7 Municipal Solid Waste Municipal Solid Waste (Management and Handling) Rules, 2000
Recycled Plastics Manufacturing and Usage Rules, 1999
8 EIA Notification The Ministry of Environment and Forests has revised the EIA
notification, 1994, and issues the revised EIA notification on
14th September 2006
9 Use and Management of
Explosive
The Explosives Act, 1884 and The Explosives Rules, 1983
THE ENVIRONMENT PROTECTION ACT, 1986 AND THE EIA NOTIFICATION, 1994
The Environmental (Protection) Act, 1986 is the umbrella legislation providing for the protection of environment in the country. This Act provided for the Environment (Protection) Rules, which have been formulated under the act “The Environmental Impact Assessment Notification, 1994 and the Amendments / Revised EIA notification on 14th September 2006”.and Year 2009.
AUIIP: ADB Loan – 2806
Semi Annual Environment Monitoring Report for AUIIP (July to December- 2014)
29 of 51
THE FOREST (CONSERVATION) ACT, 1980
The Forest (Conservation) Act, 1980 pertains to the cases of diversion of forest area and felling of roadside plantation. Depending on the size of the tract to be cleared, clearances are applied for at the following levels in the governments:
If the area of forests to be cleared or diverted exceeds 20 ha (or, 10ha in hilly area), the prior permission of the Central Government is required;
If the area of forest to be cleared or diverted is between 5 to 20 ha, the Regional Office of Chief Conservator of Forests is empowered to approve;
If the area of forest to be cleared or diverted is below or equal to 5 ha, the State Government can give permission;
and If the area to be clear-felled has a forest density of more than 40%, permission to undertake any work is needed from the Central Government, irrespective of the area to be cleared.
THE WILDLIFE (PROTECTION) ACT, 1972
The Wildlife Protection Act has allowed the government to establish a number of National Parks and Sanctuaries over the past 25 years, to protect and conserve the flora and fauna of the state.
THE WATER (PREVENTION AND CONTROL OF POLLUTION) ACT, 1974, AS AMENDED IN 1988 AND THE AIR (PREVENTION AND CONTROL OF POLLUTION) ACT, 1981, AS AMENDED BY AMENDMENT ACT, 1987
The water (Prevention and Control of Pollution) Act, 1974 resulted in the establishment of the Central and State level Pollution Control Boards whose responsibilities include managing water quality and effluent standards, as well as monitoring water quality, prosecuting offenders and issuing licenses for construction and operation of certain facilities. The SPCB is also empowered to set air quality standards and monitor and prosecute offenders under the air (Prevention and Control of Pollution) Act, 1981.
AUIIP: ADB Loan – 2806
Semi Annual Environment Monitoring Report for AUIIP (July to December- 2014)
30 of 51
Project EIA Clearance
CRZ Clearance
Wet Land
Forest Clearance
Wild Life Act applicability
Tree Cutting Permission
Permission from State/ National Archaeological dept.
Consent for establishment of crusher from quarry material supplier
MSW Rules
CTE/CTO
Authorization
Ground Water Permission
PUC Date of Environmental Monitoring
Permission for Chlorinization (storage of Chlorine cylinder) at WTP
Water Supply- Construction of storage reservoirs of various capacities at 6 locations at Guwahati, approach road and allied works (AUIIP/PR-1/GUW/WS-02)
NR NA No Yes To be obtained
No Yes. Under process. Done at 1 site (Gopalnagar). Rest will be done after getting NOC from forest dept.
NR Yes. Not obtained
NA NR NR NR Obtained Rest under process
Done on 23.06.2013, 23.10.2013 and 17-18.02.2014, 28.05.2014, 05.08.2014
NR
Water Supply - Construction of Transmission water supply pipelines and allied
NR NA No Yes To be obtained
No To be obtained. Process initiated for getting NOC
NR Yes. Not obtained
NA NR NR NR Yes. To be obtained
To be done
NR
AUIIP: ADB Loan – 2806
Semi Annual Environment Monitoring Report for AUIIP (July to December- 2014)
31 of 51
works at Guwahati (AUIIP/PR-1/GUW/WS-01) Drainage - Construction of RCC DTP Drain, Widening of Culverts and allied works in Dibrugarh from chainage 0 to 9500 m (AUIIP/PR-1/DIB/DR-01)
NR NA No No No Tree cutting permission process initiated through joint verification. Estimated cost received from DFO Dibrugarh
NR To be obtained
NA NR NR NR Yes. To be obtained
To be done
NR
AUIIP: ADB Loan – 2806
Semi Annual Environment Monitoring Report for AUIIP (July to December- 2014)
32 of 51
ANNEXURE 2: ENVIRONMENT FOREST AND OTHER COMPLIANCE (DECEMBER 31ST, 2014)
ANNEXURE 3: CONSENT TO ESTABLISH – WATER TREATMENT PLANT
AUIIP: ADB Loan – 2806
Semi Annual Environment Monitoring Report for AUIIP (July to December- 2014)
33 of 51
AUIIP: ADB Loan – 2806
Semi Annual Environment Monitoring Report for AUIIP (July to December- 2014)
34 of 51
AUIIP: ADB Loan – 2806
Semi Annual Environment Monitoring Report for AUIIP (July to December- 2014)
35 of 51
AUIIP: ADB Loan – 2806
Semi Annual Environment Monitoring Report for AUIIP (July to December- 2014)
36 of 51
ANNEXURE 4: NOC FROM AIRPORT AUTHORITY OF INDIA FOR LANDFILL SITE AT GHORAMARA, DIBRUGARH, ASSAM
AUIIP: ADB Loan – 2806
Semi Annual Environment Monitoring Report for AUIIP (July to December- 2014)
37 of 51
ANNEXURE – 5: COMPLIANCE OF APPLICATION OF EMP
Water Supply- Construction of Overhead water storage reservoir
Project: Water Supply - Construction of storage reservoirs of various capacities at 6 locations at Guwahati, approach road and allied works
Package No: AUIIP/PR-1/GUW/WS-02
Progress: 9 %
Physical progress :
Construction of approach road to Gopalnagar reservoir site continued
Rubble masonary work along approach road at Gopalnagar continued
Excavation for reservoir at Gopalnagar- started
Retaining wall construction at Gopalnagar started
Sr. No.
Field Mitigation Activities and Method
Parameters monitored Location
Responsible for Mitigation
Monitoring Method
Responsible for Monitoring
Date of Monitoring
Compliance Status/ Explanation
Pre Construction Design phase
1 Site clearance
Site preparation work completed including necessary clearance for Gopalnagar Relevant NOC
from line dept Tree felling
permission
Tree felling requirement – site environment plan
NOC – paper documents from line agency
Reservoir construction site, approach road
DSC/PIU Observation and document checking
DSC’s Environment Safeguard Spl.
02.07.2014 04.07.2014 11.07.2014 16.07.2014 02.08.2014 22.08.2014 09.09.2014 10.09.2014 04.10.2014 06.10.2014 13.10.2014 18.10.2014 27.10.2014 03.11.2014 24.11.2014 27.11.2014
Done as per present requirement. Continuous process. Rest under progress
AUIIP: ADB Loan – 2806
Semi Annual Environment Monitoring Report for AUIIP (July to December- 2014)
38 of 51
Sr. No.
Field Mitigation Activities and Method
Parameters monitored Location
Responsible for Mitigation
Monitoring Method
Responsible for Monitoring
Date of Monitoring
Compliance Status/ Explanation
19.12.2014 22.12.2014
2 Utility Shifting of affected utilities like electric and telephone poles, water lines
List of affected utilities if any and operators
Bid document to include requirement for a contingency plan for service interruptions
OHSR construction site, approach road
DSC/PIU Observation and document checking
DSC’s Environment Safeguard Spl.
Do Not required now
3 Traffic Management
Planning for Traffic Management
Ensure traffic management plan is part of contract documents and being implemented
Approach Road and road junction
DSC/PIU Observation and document checking
DSC’s Environment Safeguard Spl.
Do Not required as per the present situation.
4 Water supply Health risk due to closure of water supply
Schedule of closure
Delivery of GMC of potable water to affected people
OHSR construction site, nearby locations
DSC/PIU Checking of records Visual observation
DSC’s Environment Safeguard Spl.
Do Not required as per present nature of work
5 Construction work camps (if needed), hot mix plants, stockpile areas, storage areas, and disposal areas.
Planning for setting up worker camps, hot mix plant, stockpile area, storage and disposal areas Prioritize areas
within or nearest possible vacant space in the subproject location
Non use of
List of selected location for construction work camps, hot mix plants, stockpile areas, storage areas, and disposal areas.
OHSR construction site and nearby location
DSC/PIU Observation and document checking
DSC’s Environment Safeguard Spl.
Do Local labours employed. Slow progress of work. Construction of labour camp undergoing
AUIIP: ADB Loan – 2806
Semi Annual Environment Monitoring Report for AUIIP (July to December- 2014)
39 of 51
Sr. No.
Field Mitigation Activities and Method
Parameters monitored Location
Responsible for Mitigation
Monitoring Method
Responsible for Monitoring
Date of Monitoring
Compliance Status/ Explanation
residential area Arrangement of
toilet and drinking water facility
No disposal of waste in water
Construction
6 Source of Materials
Use of Govt. approved quarry sites for procurement of materials
Verify suitability of all material sources and obtain approval of Investment PMU/PIU
List of approved quarry sites and sources of materials
Bid document to include requirement for verification of suitability of sources and permit for additional quarry sites if necessary.
Construction Contractor documentation
Quarries and material source areas
Contractor Checking of records
visual inspection of sites
DSC’s Environment Safeguard Spl & PIU
Do Approval obtained procurement yet to start
7 Camp sites Establishment of temporary camps with drinking water, sanitary and solid waste management arrangement
Complaints from sensitive Receptors
Water and sanitation facilities for employees
Housekeeping –
OHSR construction site or nearby location
Contractor Visual inspection
DSC’s Environment Safeguard Spl & PIU
Do Under progress
AUIIP: ADB Loan – 2806
Semi Annual Environment Monitoring Report for AUIIP (July to December- 2014)
40 of 51
Sr. No.
Field Mitigation Activities and Method
Parameters monitored Location
Responsible for Mitigation
Monitoring Method
Responsible for Monitoring
Date of Monitoring
Compliance Status/ Explanation
Train employees in the storage and handling of materials
Remove all wreckage, rubbish, or temporary structures
regular disposal of solid waste
8 Landscape and Aesthetics
Removal of overburden and excavated material from working site and use / preservation of the same – as per mitigation measures
Fencing of storage areas
Disposal of construction debris if any as per mitigation measures
Prepare and implement Waste Management List
Avoid stockpiling of excess
Waste Management List
Complaints from sensitive receptors
PMU/PIU/DSC to report in writing that the necessary environmental restoration work has been done
OHSR construction site & approach road location
Contractor Checking of records
Visual inspection of sites
DSC’s Environment Safeguard Spl & PIU
Do Utilisation of excess earth done partly. Complete utilization/ removal necessary Material storage not yet started Waste management plan will be applied as per EMP
AUIIP: ADB Loan – 2806
Semi Annual Environment Monitoring Report for AUIIP (July to December- 2014)
41 of 51
Sr. No.
Field Mitigation Activities and Method
Parameters monitored Location
Responsible for Mitigation
Monitoring Method
Responsible for Monitoring
Date of Monitoring
Compliance Status/ Explanation
excavated soils Coordinate with
GMC for beneficial uses of excess excavated soils
9 Air quality Selection of materials storage area
Water sprinkling at construction site for arresting dust (if any during dry period)
Use tarpaulins to cover sand and other loose material- Reducing dust hazard
All vehicles and equipments mobilized to construction site and producing emission, have Pollution Control Board certification
Carry out air quality monitoring
Location of stockpiles
Complaints from sensitive receptors
Monitoring data Heavy
equipment and machinery with air pollution control
Water sprinkling arrangement
Cover materials
OHSR construction site, approach road site, and stockpile areas
Contractor Checking of records
Visual inspection of sites
DSC’s Environment Safeguard Spl & PIU
Do Location of stockpiles selected Water sprinkling done. Frequency need to be increase Air quality monitoring done as per EMP. Pollution under Control Certificate of vehicles collected partially. Rest under progress
AUIIP: ADB Loan – 2806
Semi Annual Environment Monitoring Report for AUIIP (July to December- 2014)
42 of 51
Sr. No.
Field Mitigation Activities and Method
Parameters monitored Location
Responsible for Mitigation
Monitoring Method
Responsible for Monitoring
Date of Monitoring
Compliance Status/ Explanation
10 Noise level Noise producing work needs to be conducted at day time
Regular maintenance of noise producing equipment
Require horns not be used unless it is necessary to warn other road users
Maintain maximum sound levels not exceeding 80 decibels (dbA) when measured at a distance of 10 m or more from the vehicle/s
At sensitive locations enclosures provided around generator set or other noise producing machinery.
Complaints from sensitive receptors
Use of silencers in noise-producing equipment and sound barriers
Monitoring data
City road OHSR construction site, approach road site
Contractor Checking of records
Visual inspection of sites
DSC’s Environment Safeguard Spl & PIU
Do No such noise producing machinery mobilized at site Acoustic enclosure provided for DG set. Permission obtained from pollution control board During construction noise monitoring has been done
AUIIP: ADB Loan – 2806
Semi Annual Environment Monitoring Report for AUIIP (July to December- 2014)
43 of 51
Sr. No.
Field Mitigation Activities and Method
Parameters monitored Location
Responsible for Mitigation
Monitoring Method
Responsible for Monitoring
Date of Monitoring
Compliance Status/ Explanation
11 Traffic Implement a traffic management schedule
Ensure traffic management plan is part of contract documents and being implemented
City road and OHSR construction site
Contractor Checking of records
Visual
inspection of sites
DSC’s Environment Safeguard Spl & PIU
Do Not required as per present scope of work
12 Ecological Resources – Terrestrial
Minimize removal of vegetation (if any) and disallow cutting of trees
Felling of trees done with mitigation measures i.e. planting of three trees for each tree fell.
Tree felling requirement and afforestation after final design
OHSR construction site, approach road site
PIU, Contractor
Site observation
Checking of records
DSC’s Environment Safeguard Spl & PIU
Do Complied as per present stage. More tree felling will be done at other construction sites after receiving NOC from forest dept.
13 Accessibility Plan transportation routes so that heavy vehicles do not use narrow local roads
Schedule transport and hauling activities during non- peak hours
Keep the site free from all unnecessary
Traffic Management Strategy
Complaints from sensitive receptors
Number of signages placed at subproject location.
OHSR construction site, approach road site
Contractor Visual inspection
DSC’s Environment Safeguard Spl & PIU
Do Transportation of materials not started fully No diversion of traffic is required. Signagaes will be placed as per requirement and rest mitigation measures will be considered in due course & with development of project activity
AUIIP: ADB Loan – 2806
Semi Annual Environment Monitoring Report for AUIIP (July to December- 2014)
44 of 51
Sr. No.
Field Mitigation Activities and Method
Parameters monitored Location
Responsible for Mitigation
Monitoring Method
Responsible for Monitoring
Date of Monitoring
Compliance Status/ Explanation
obstructions; Drive vehicles
in a considerate manner;
Coordinate with Guwahati Traffic Office for temporary road diversions and with for provision of traffic aids
Notify affected sensitive receptors by providing sign boards informing nature and duration of construction works and contact numbers for concerns/ complaints
14 Water
Quality Arrangement of drainage of waste water and arresting solid waste/silt from waste water generated at construction site
Areas for stockpiles, storage of fuels and lubricants and waste materials
Number of silt
OHSR construction site, approach road site
Contractor Site observation DSC’s Environment Safeguard Spl & PIU
Do Not required now. No water body nearby the project location
AUIIP: ADB Loan – 2806
Semi Annual Environment Monitoring Report for AUIIP (July to December- 2014)
45 of 51
Sr. No.
Field Mitigation Activities and Method
Parameters monitored Location
Responsible for Mitigation
Monitoring Method
Responsible for Monitoring
Date of Monitoring
Compliance Status/ Explanation
traps installed along drainages (in slope) leading to water bodies
15 Occupational
Health & safety
Develop and implement site-specific Health and Safety (H&S) Plan
Use Personal Protective Equipment like helmet, gumboot, gloves, nose mask and ear plugs
H&S Training for all site personnel
Documentation of work-related accidents;
Designate a safeguard focal person and undertake safeguards orientation by PMU/PIU
Provide specific guidance for
Site-specific Health and Safety (H&S) Plan
Equipped first-aid stations;
Medical insurance coverage for workers
Number of accidents
Supplies of potable drinking water;
Record of H&S orientation trainings
Personal protective equipments
Sign boards for hazardous areas such as energized electrical devices and lines, service rooms
OHSR construction site, approach road site
Contractor Checking of records
Visual inspection of sites
DSC’s Environment Safeguard Spl & PIU
Do Site-specific Health and Safety (H&S) Plan under implementation H & S training arranged for the labourer on regular basis Drinking water and first aid box available at site Insurance arranged for the labourer All accidents are recorded by contractor Overall compliance is satisfactory
AUIIP: ADB Loan – 2806
Semi Annual Environment Monitoring Report for AUIIP (July to December- 2014)
46 of 51
Sr. No.
Field Mitigation Activities and Method
Parameters monitored Location
Responsible for Mitigation
Monitoring Method
Responsible for Monitoring
Date of Monitoring
Compliance Status/ Explanation
suitable PPE for every on-site work assignment
Ensure availability of First aid box at all working sites and labour camp
Provide medical insurance coverage for workers;
Provide supplies of potable drinking water at working sites;
Provide H&S orientation training to all new workers
Mark and provide sign boards for hazardous areas such as energized electrical devices and lines, appropriate
AUIIP: ADB Loan – 2806
Semi Annual Environment Monitoring Report for AUIIP (July to December- 2014)
47 of 51
Sr. No.
Field Mitigation Activities and Method
Parameters monitored Location
Responsible for Mitigation
Monitoring Method
Responsible for Monitoring
Date of Monitoring
Compliance Status/ Explanation
Disallow worker exposure to noise level greater than 85 dBA for a duration of more than 8 hours per day without hearing protection.
16 Community Health & safety
Plan truck routes (for carrying construction materials including pipes) to avoid narrow or congested roads and tourist sites
Consideration of public safety - as per prescribed mitigation measures
Provide protective fencing around open trenches
Provide road signs and flag persons to warn
Traffic Management Strategy
Complaints from sensitive receptors
City road and OHSR construction site and approach road site
Contractor Visual inspection
DSC’s Environment Safeguard Spl & PIU
Do Caution tape placed partially along the access road – under construction No permanent barricade arranged by the contractor but instruction is given to the contractor for arrangement of the same
AUIIP: ADB Loan – 2806
Semi Annual Environment Monitoring Report for AUIIP (July to December- 2014)
48 of 51
Sr. No.
Field Mitigation Activities and Method
Parameters monitored Location
Responsible for Mitigation
Monitoring Method
Responsible for Monitoring
Date of Monitoring
Compliance Status/ Explanation
17 Socio cultural resources
Strictly follow the protocol for chance finds in any excavation work
Stop work immediately to allow further investigation if any finds are suspected; and
Chance find protocol
OHSR construction site and approach road site
Contractor Checking of records
DSC’s Environment Safeguard Spl & PIU
Do Not required till date
18 Employment generation
The use of labor intensive construction measures will be used where appropriate
Employ local (unskilled) labor if possible
Training of labor to benefit individuals beyond completion of the subproject
Employment record
OHSR construction site and approach road site
Contractor Checking of records
DSC’s Environment Safeguard Spl & PIU
Do At present local laboures are engaged
NA: Not Applicable, NR- Not Required
AUIIP: ADB Loan – 2806
Semi Annual Environment Monitoring Report for AUIIP (July to December- 2014)
49 of 51
ANNEXURE 6: ENVIRONMENT PERFORMANCE FACT SHEET
S.
No.
Su
b p
roje
ct C
od
e
Nam
e o
f S
ub
Pro
ject
Nam
e o
f C
on
tra
cto
r
EM
P P
art
of
con
tract
Docum
en
t (Y
es /
No
)
EM
P b
ein
g Im
ple
me
nte
d
(Ye
s /
No
)
Ove
rall
Sta
tus o
f E
MP
Im
ple
me
nta
tion
(E
xcelle
nt,
Sa
tisfa
cto
ry,
Pa
rtia
lly
Sa
tisfa
cto
ry,
Be
low
Sa
tisfa
cto
ry)
Environmental Consents / Clearances Required
Nomination of
Environmental
& Social Safegua
rd Officer
by Contract
or (Nominated / Yet
to be Nominat
ed)
Dust Control
(Excellent,
Satisfactory,
Partially Satisfact
ory, Below
Satisfaction)
Labour Camp
Management
(Excellent,
Satisfactory,
Partially Satisfactory, Below Satisfacti
on )
Workers Safety
Measures
(Excellent,
Satisfactory,
Partially Satisfact
ory, Below
Satisfaction )
Traffic
Safety
Measures
(Excellent
,
Satisfacto
ry,
Partially
Satisfacto
ry, Below
Satisfactio
n )
Tre
e
Cutt
ing
Cru
sh
er
Ba
tchin
g
Pla
nt
Hot
Mix
Pla
nt
Die
sel
Ge
ne
rato
r
Se
t
Po
llutio
n U
nd
er
Con
trol
(PU
C)
Ce
rtific
ate
s f
or
Con
tra
cto
r's V
eh
icle
s
ASSAM (AUIIP, Loan No. 2806)
1
. AU
IIP/P
R-1
/GU
W/W
S/0
2
Construction of
storage reservoirs of various capacities
at 6 locations
at Guwahati, approach road and
allied works
M/s IVRCL Pvt. Ltd.
Yes
Yes Partially Satisfact
ory
Done for one
location at Gopalnaga
r.
For rest
awaited for
NOC
No- Not yet
collected
As per plan
crusher plant
will be established at project
site after due
permission from pollutio
n control board
NR
as
per
prese
nt
work
NR
as
per
pre
se
nt
wo
rk
Consent
obtained
from Assam Polluti
on Contro
l Board
Obtained
partly. Rest under progre
ss
Nominat
ed
Partially
Satisfact
ory
Under
constructi
on
Partially
Satisfact
ory
NR as per
present
work
AUIIP: ADB Loan – 2806 Semi Annual Safeguard Monitoring Report for AUIIP (July to December 2014)
50 of 51
ANNEXURE 7: PUBLIC CONSULTATION ON ENVIRONMENTAL ISSUES DURING CONSTRUCTION/ IMPLEMENTATION
PLACE OF CONSULTATION DATE OF CONSULTATION PROJECT NAME PACKAGE NO. NAME OF THE FIELD SUPERVISORS NAME OF THE PERSONS ADDRESS
S.No. POINTS DISCUSSED REMARKS
01.
02.
03.
04.
05
06.
07
08
09
10
Consultation Summary
Participants
AUIIP: ADB Loan – 2806 Semi Annual Safeguard Monitoring Report for AUIIP (July to December 2014)
51 of 51
ANNEXURE 8: SAMPLE GRIEVANCE REGISTRATION FORM (To be available in Hindi, Assamese and English or local language, if any)
The Assam Urban Infrastructure Investment Program (AUIIP) welcomes complaints, suggestions,
queries and comments regarding project implementation. We encourage persons with grievance to
provide their name and contact information to enable us to get in touch with you for clarification and
feedback.
Should you choose to include your personal details but want that information to remain confidential,
please inform us by writing/typing *(CONFIDENTIAL)* above your name. Thank you.
Date Place of registration
Contact Information/Personal Details
Name Gender Male Female
Age
Home Address
Village / Town
District
Phone no.
Complaint/Suggestion/Comment/Question Please provide the details (who, what, where and how) of your grievance below: If included as attachment/note/letter, please tick here:
How do you want us to reach you for feedback or update on your comment/grievance?
FOR OFFICIAL USE ONLY
Registered by: (Name of official registering grievance)
If – then mode:
Note/Letter
Verbal/Telephonic
Reviewed by: (Names/Positions of Official(s) reviewing grievance)
Action Taken:
Whether Action Taken Disclosed:
Yes
No
Means of Disclosure:
GRIVENCES RECORD AND ACTION TAKEN
Sr. No. Date Name and Contact No. of Complainer
Type of Complain
Place Status of Redress
Remarks