72

in - a100.gov.bc.caa100.gov.bc.ca/appsdata/acat/documents/r13362/Vernon_creek_fish… · Creek and effluent from storm drains. These chronic problems will require a unified effort

  • Upload
    others

  • View
    0

  • Download
    0

Embed Size (px)

Citation preview

Page 1: in - a100.gov.bc.caa100.gov.bc.ca/appsdata/acat/documents/r13362/Vernon_creek_fish… · Creek and effluent from storm drains. These chronic problems will require a unified effort
Page 2: in - a100.gov.bc.caa100.gov.bc.ca/appsdata/acat/documents/r13362/Vernon_creek_fish… · Creek and effluent from storm drains. These chronic problems will require a unified effort

TABLE OF CONTENTS

Execut ive Summary .................................................. 1 I n t r o d u c t i o n ....................................................... 4 D e s c r i p t i o n o f Vernon Creek ........................................ 5 Method ............................................................. 7 Reach Boundaries ................................................... 8 ....................................... Factors A f f e c t i n g Enhancement 10 .................................................. 6.1 Land Use 10 ........................................ 6.2 Water Flow and Use 11 ............................................ 6.3 Waste Problems 14 .............................................. 6.4 Enumerations 16 ........................................ Fishery Enhancement Opt ions 18

7.1 Format ion o f A Vernon Creek Committee ..................... 18 7.2 Clean-up and Creek Maintenance ............................ 20 7.3 Reach 1 D e s c r i p t i o n ....................................... 21 ....................................... 7.4 Reach 2 D e s c r i p t i o n 28 ....................................... 7.5 Reach 3 D e s c r i p t i o n 32 ....................................... 7.6 Reach 4 D e s c r i p t i o n 35 ....................................... 7.7 Reach 5 D e s c r i p t i o n 40

F ishery Enhancement Methods and Costs .............................. 47 ..................... 8.1 Reach 1 Enhancement Methods and Costs 47 8.2 Reach 2 Enhancement Methods and Costs ..................... 53 8.3 Reach 3 Enhancement Methods and Costs ..................... 54 ..................... 8.4 Reach 4 Enhancement Methods and Costs 55 ..................... 8.5 Reach 5 Enhancement Methods and Costs 57 ........................... Time Schedule f o r Enhancement Procedures 61 .......................................... 9.1 C u l v e r t (Reach 1 ) 62 .......................... 9.2 Concrete Weir Removal (Reach 2) 62 .................................. 9.3 Weir Placement (Reach 4 ) 63 ...................................... 9.4 C lay C l i f f (Reach 5 ) 63 ................................ 9.5 Gravel Placement (Reach 5 ) 64 ........................... 9.6 Creek Clean-up (Reaches 1 t o 5 ) 64 .................................................. References C i t e d 65 ................................................. References Unc i ted 67 ................................................... Acknowledgements 70

Page 3: in - a100.gov.bc.caa100.gov.bc.ca/appsdata/acat/documents/r13362/Vernon_creek_fish… · Creek and effluent from storm drains. These chronic problems will require a unified effort

'Vernon Creek has lost much of its capability as a spawning stream for

game fish due to water extraction, flood control, channelization, sedimentation,

and pollution. Sisiutl Resources was retained by the Habitat Conservation

Foundation to plan the restoration and enhancement of fish habitat in this

system.

Two major factors affecting the fishery are minimum flows in Vernon

Creek and effluent from storm drains. These chronic problems will require a

unified effort from a number of agencies and we have recommended the reformation

of a Vernon Creek Committee. The Committee should involve the various Branches

of the Ministry of Environment, and representatives from the City of Vernon

and Regional District of North Okanagan. It should be formed as soon as

possible and will require a number of years to tackle these issues.

Many alterations are required to improve the stream channel for fish

passage and spawning. The channel shape and location need modification in

some areas, banks require stabilization in other areas, and spawning

substrate is lacking in some locations. In order to describe these

enhancement priorities more precisely we divided the Creek into the

following reaches:

REACH 1 Okanagan Lake - Okanagan Landing Road REACH 2 Okanagan Landing Road - 43rd Street REACH 3 43rd Street - Polson Park REACH 4 Bottom of Polson Park - Top of Pol son Park REACH 5 Pol son Park - Kalamalka Lake

Page 4: in - a100.gov.bc.caa100.gov.bc.ca/appsdata/acat/documents/r13362/Vernon_creek_fish… · Creek and effluent from storm drains. These chronic problems will require a unified effort

Reach 1 has such a low gradient that siltation will continue to be a

problem regardless of enhancement procedures. Major improvements would

involve bank sloping and riprapping but costs would outweigh benefits unless

benefits other than fisheries (i .e. nutrient control) are considered. The

Vernon Creek Committee should establish policy in this regard. Fisheries

work in Reach 1 should include removal of debris jams and improved passage

through the culvert at Okanagan Landing Road.

Reach 2 has an ideal slope for kokanee spawning and is amply endowed

with good spawning gravel. Residents report sizeable numbers of fish, but

Ministry of Environment staff have avoided enumerating this reach in the past

due to private property and extremely tight bank cover. Detailed enumerations

in the future are highly recommended. The only enhancement required in this

reach is the removal of a concrete weir which presently hinders fish passage.

Reach 3 requires the removal of 2 debris jams.

each 4 requires extensive work to overcome high velocities and eroding .

banks. Channel widening and extensive riprapping are needed,,and rock weirs

need to be installed to form pools and dissipate energy. This section is all

within Polson Park and extensive negotiations with the City of Vernon will be

necessary.

Reach 5 contains a large clay and sand cliff which sloughs into the

creek causing siltation in downstream areas. The creek will need to be

diverted into a new channel to bypass this area. In addition, Reach 5 has

excellent potential as a spawning area but has insufficient gravel because

there are no upstream areas from which to recruit gravel. Sinch shifting

Page 5: in - a100.gov.bc.caa100.gov.bc.ca/appsdata/acat/documents/r13362/Vernon_creek_fish… · Creek and effluent from storm drains. These chronic problems will require a unified effort

could result in downstream flooding, a test patch of new gravel should be

deposited and then observed prior to major gravel addition.

All the enhancement options for each reach have been discussed in detail.

Biological rationale, engineering methods, and costs have been provided.

Page 6: in - a100.gov.bc.caa100.gov.bc.ca/appsdata/acat/documents/r13362/Vernon_creek_fish… · Creek and effluent from storm drains. These chronic problems will require a unified effort

INTRODUCTION

The kokanee and trout fisheries of Okanagan Lake are two of the most

important f isheries in the Okanagan Region. Despite the i r importance,

these f isheries have been reduced, largely due t o a continuing decrease

in the number of tributary streams which are suitable for spawning (Houston,

1984). Ninety percent of stream areas i n the Okanagan have been destroyed

w i t h the resul t t h a t Okanagan Lake i s down to 15% of i t s kokanee carrying

capacity (Canada - British Columbia Okanagan Basin Agreement, 1974).

Vernon Creek, which flows from Kalamalka Lake through the City of

Vernon t o the north arm of Okanagan Lake, i s a prime example of a severely

diminished spawning area. A once productive stream, i t s capabili t ies have

been drastical ly reduced due t o water extraction, flood control devices,

channelization, urbanization, pollution and erosion. Water i s clean and

clear as i t enters Vernon Creek a t the Kalamalka Lake outlet , b u t i s

extremely turbid and fu l l of sediment by the time i t reaches Okanagan Lake.

This report constitutes the in i t i a l planning phase of a Habitat

Conservation Foundation project to rejuvenate Vernon Creek. I t investigates

the reasons for habitat losses, suggests enhancement options, and provides

cost and benefits of b r i n g i n g Vernon Creek back t o i t s once pr0ductiv.e

s tate .

Page 7: in - a100.gov.bc.caa100.gov.bc.ca/appsdata/acat/documents/r13362/Vernon_creek_fish… · Creek and effluent from storm drains. These chronic problems will require a unified effort

DESCRIPTION OF VERNON CREEK

Vernon Creek flows from Kalamalka Lake through the C i t y o f Vernon and

dra ins i n t o Okanagan Lake ( f i g . 1 ). It i s 10.5 km long and drops a t o t a l

of 50 metres i n e levat ion. This r e s u l t s i n an average g rad ien t o f 0.47%

and ranges between 0.1% and 1.1 % (Morley, 1976). Stream wid th va r ies from

3 metres i n t he steeper sect ions t o 10 metres i n f l a t t e r areas near

Okanagan Lake. BX Creek, which f lows o u t o f Swan Lake, i s t h e o n l y major

t r i b u t a r y t o Vernon Creek.

Vernon Creek has been channelized through Polson Park and through

r e s i d e n t i a l areas downstream t o Okanagan Landing Road. This has increased

stream ve loc i t y , and both res idents and t h e C i t y o f Vernon have r ip rapped

t h e banks t o reduce erosion. Farther down t h e creek, e ros ion has become a

ser ious problem, leav ing the banks denuded and 'cons tan t ly sloughing, and

t h e water s i l t laden and t u r b i d year round. Adding t o t h e s i l t a t i o n

problems i s t he existence o f storm sewers, drainage d i tches , and misuse o f

t h e creek by res idents and land owners. The volume o f f l o w i s c o n t r o l l e d

a t the o u t l e t o f Kalamalka Lake by t h e C i t y of Vernon.

Page 8: in - a100.gov.bc.caa100.gov.bc.ca/appsdata/acat/documents/r13362/Vernon_creek_fish… · Creek and effluent from storm drains. These chronic problems will require a unified effort

1 I

LOWER VERNON CREEK STUDY AREA

(SEE FIGURE 1

!

OKANAGAN LAKE

CANADA

WASHINGTON U.S.A.

FIGURE I , LOCATION OF STUDY AREA

Page 9: in - a100.gov.bc.caa100.gov.bc.ca/appsdata/acat/documents/r13362/Vernon_creek_fish… · Creek and effluent from storm drains. These chronic problems will require a unified effort

METHOD

Vernon Creek was visited by a biological survey team which walked the

entire creek from Kalamalka Lake to Okanagan Lake, recorded and photographed

specific problem sites, and made a general assessment of the creek.

Because the survey was undertaken in the months of July and August the

water level was higher than would be encountered in September and October

when kokanee spawning occurs- To compensate for this, Sisiutl Resources

arranged to have the creek lowered to its minimum allowed flow of 3 cfs for

one day (August 8, 1986). Water velocities were taken on this day and all

possible fish barriers were reinspected.

During the week of August 11th to August 15th our engineer visited

Vernon Creek with a biologist to finalize the procedures to be used and to

determine the cost for each enhancement option.

Page 10: in - a100.gov.bc.caa100.gov.bc.ca/appsdata/acat/documents/r13362/Vernon_creek_fish… · Creek and effluent from storm drains. These chronic problems will require a unified effort

REACH BOUNDARIES

Vernon Creek can l o g i c a l l y be d iv ided i n t o 5 sect ions o r reaches based

upon physical cha rac te r i s t i cs and enhancement p o t e n t i a l ( f i g . 2 ).

REACH 1 extends from the i n l e t o f Okanagan Lake upstream t o t h e c u l v e r t a t

t h e Okanagan Landing Road crossing adjacent t o Vernon Hel icopters.

REACH 2 extends from Okanagan Landing Road t o t h e 43rd St reet crossing of

t h e creek ( j u s t above the sewage p lan t ) .

REACH 3 extends from t h e 43rd Street crossing t o t h e bottom o f Polson

Park.

REACH 4 i s t h a t po r t i on o f the Creek which f lows from the t o p end of

Polson Park t o the bottom o f Polson Park.

REACH 5 extends from t h e t o p o f Polson Park up t o t h e Kalamalka Lake

o u t l e t .

Page 11: in - a100.gov.bc.caa100.gov.bc.ca/appsdata/acat/documents/r13362/Vernon_creek_fish… · Creek and effluent from storm drains. These chronic problems will require a unified effort
Page 12: in - a100.gov.bc.caa100.gov.bc.ca/appsdata/acat/documents/r13362/Vernon_creek_fish… · Creek and effluent from storm drains. These chronic problems will require a unified effort

6.0 FACTORS AFFECTING ENHANCEMENT

6.1 LAND USE

Because Vernon Creek runs through an urban centre, almost all of the

land adjacent to it has been subdivided and is now privately owned or

leased.

The results of private ownership and its effect on the creek is quite

evident. In many portions of the creek, the channel has been relocated

or straightened, which has resulted in a faster flow. Higher velocities

have caused erosion in several sections of the creek resulting in an

increased sediment load and infilling downstream. To prevent further

erosion of their property, many land owners have riprapped banks with

broken concrete, tires, and other materials. Some pol lution has occurred

as a result of owners disposing of garbage into the creek.

Page 13: in - a100.gov.bc.caa100.gov.bc.ca/appsdata/acat/documents/r13362/Vernon_creek_fish… · Creek and effluent from storm drains. These chronic problems will require a unified effort

WATER FLOW AND USE

The flow of Vernon Creek is controlled by a regulating device at the

Kalamalka Lake out let. The City of Vernon measures the flow daily and

adjusts it if necessary. When this device was installed, the Habitat

Protection Section of the Ministry of Environment set a sustained minimum

flow of 3 cfs to protect the fishery (Jones, 1986).

On August 8, 1986, the City of Vernon lowered the creek flow to this

minimum level so that our biophysical survey team could estimate its effect

on fish migration. After observing the creek at minimum flow, it was

strongly felt that a higher flow would make fish passage considerably easier

in several areas. In our opinion, a minimum flow of 4 - 5 cfs would be more suitable. However, formal procedures for determining exact flow requirements

are available (Neuman and Newcombe, 1977; Britton, 1974; Newco~iibe, 1980) and

a study should be undertaken to determine the optimum flow to support the

Vernon Creek fishery . Perhaps further studies to determine water

availability should also be undertaken as recommended by Letvak (1985).

There are currently 16 water licences on Lower Vernon Creek (Table I)

which draw a total of 942.6 acre feet of water during the irrigation season.

Because this is such a large volume of water, there may be a substantial

difference in flow between Kalamalka Lake and Okanagan Lake, even though

BX Creek adds to the flow partway down the creek. For this reason the

predetermined minimum flow should be sustained in the lower end of the creek.

Page 14: in - a100.gov.bc.caa100.gov.bc.ca/appsdata/acat/documents/r13362/Vernon_creek_fish… · Creek and effluent from storm drains. These chronic problems will require a unified effort

Table I

WATER LICENCES ON LOWER VERNON CREEK

O f f i c i a l Licence Date L e t t e r Reach Lot Number Obtained User Flow Designation Number Number

City of Vernon

Thomas, Les l i e R. and T i l l y

Symington, George w . McLean, Gordon W.

Vernon Free Methodist Church

Brandt , Clayton and Marjorie M. Humphr i es

Normey,. Marion I .

Ci ty of Vernon

~ r o n s o n , W.U.C.

72.26 AF I r r .

4.75 AF I r r .

4.5 AF I r r .

4.5 AF I r r .

4.75 AF I r r .

0.75 AF I r r .

0.29 AF I r r .

24.37 AF I r r .

192.00 AF I r r .

Plan 1707 Lot 6

Plan 9738 Lot 1

Plan 9738 Lot 2

Plan 9738 Lot 3

Plan 85356

Plan 11091 Lot 1

- Plan 23913 Lot 4

Plan 23913 Lot 1

Plan 509 Lot 4

Page 15: in - a100.gov.bc.caa100.gov.bc.ca/appsdata/acat/documents/r13362/Vernon_creek_fish… · Creek and effluent from storm drains. These chronic problems will require a unified effort

Table I (continued)

Licence Date Number Obtained User

Official Letter Reach

Flow Designation Number Lot Number

0131168 1938 06 14 Bennett, Russell J.

0241 997 1889 08 16 South Vernon Irrigation District

. 0346229 1872 03 04 Big Chief Mobile Home Park

020 130 1953 08.31 Tronson, W.U.C.

02581 36 1964 07 30 Rediversion from BX Creek

0285262 1969 03 07 Young, Cecil H.

0 1 98574 1953 02 16 South Vernon Irrigation District

25.00 AF Irr. Cc

5,000 GD Dom. Q 310.00 AF Irr.

48.00 AF Irr. P

7.50 AF Irr. Q

4.00 AF Irr. R

240.00 AF Irr. A A

2 Plan 14428 Lot 2

2 Plan 30297 Lot 2

2 Plan 1911 Lot 1

2 Plan 25828 Lot 1

2 Plan 0500

3 Plan R1482

Page 16: in - a100.gov.bc.caa100.gov.bc.ca/appsdata/acat/documents/r13362/Vernon_creek_fish… · Creek and effluent from storm drains. These chronic problems will require a unified effort

WASTE PROBLEMS

The flow of wastes into Vernon Creek appears t o be one of the major

reasons for i t s decline in productiveness, since i t has, a t times, resulted

in complete f i sh k i l l s (Nickel, 1986; Jones, 1986; and Vest, 1986). In the

past, the sewage plant has released effluent s t raight into the creek.

Combined w i t h the many storm drains which empty into Vernon Creek ( f ig . 2 ) ,

i t may have had a drast ic effect on f i sh populations.

The City of Vernon has, in recent years, solved much of th i s sewage

problem by switching t o spray i rr igat ion on land. Now sewage no longer flows

through Vernon Creek. Unfortunately, t h i s form of disposal has n o t been

capable of handling a l l of Vernon City 's sewage. The Waste Management Branch

was forced t o allow sewage t o be released into the creek in the spring of

1984 and 1985 and will be forced to do so again in the spring of 1987. I t i s

unlikely tha t t h i s will occur again a f t e r 1987, and there i s assurance that

no harmful waste will be deposited by the 1987 release (Nickel, 1986). The

water quality of Vernon Creek in the lower reaches i s expected to improve

further over the next 8 - 10 years because septic f ie lds situated in the low

flood plain will be changed over to a sewage outfal l into Okanagan Lake.

A t present, the storm sewers which empty into Vernon Creek are the

greatest waste concerns. As of 1980, there were in excess of 75 storm

discharges into the Vernon Creek system (Peterson and Wright, 1980). These

are separate from the City sanitary sewer system which i s designed t o carry

domestic sewage and commercial waste t o the sewage treatment plant. Peterson

and Wright (1980) s t a t e that they found "o i l , gasoline, solvents, soap and

Page 17: in - a100.gov.bc.caa100.gov.bc.ca/appsdata/acat/documents/r13362/Vernon_creek_fish… · Creek and effluent from storm drains. These chronic problems will require a unified effort

chlorinated water were frequently discharged into ei ther the storm system or

direct ly into the creek." During the biophysical survey, staff members noted

traces of gasoline or o i l entering the creek from a storm drain adjacent t o

a weir 100 metres below the sewage plant ( f ig . 9 , s i t e A ).

A large f i sh k i 11 occurred i n Vernon Creek and BX Creek on July 2, 1980

when water from a f i r e a t a local furniture store entered BX Creek. "The

water turned black and had a burnt odour" and entered the creek a t high

temperatures. Combined with the 22 service stations and 2 car washes i n

Vernon tha t Peterson and Wright stated were connected t o the storm drain

system, i t i s evident that the storm drains are potentially very hazardous

t o f i sh i n Vernon Creek.

Peterson and Wright recommended tha t i n the future the f i r e department

"pump any contaminated water t o the sanitary sewer when possible," and tha t

a1 1 service stations and other commercial businesses discharge t o the sanitary

sewer system. I t i s our opinion tha t t h i s recommendation i s sound, and should

- be followed despite the time and cost required for such a project. Because

BX Creek enters into Vernon Creek, i t too should be included in th i s project.

Due t o the scope of t h i s project, we are unable to provide a cost estimate.

Page 18: in - a100.gov.bc.caa100.gov.bc.ca/appsdata/acat/documents/r13362/Vernon_creek_fish… · Creek and effluent from storm drains. These chronic problems will require a unified effort

ENUMERATIONS

In the past, Vernon Creek has not been 'completely enumerated by the

Fish and Wild1 ife Branch. Escapements in Vernon Creek have dropped drastically

from 1971 to 1984 (Table 11), which seems to indicate a decrease in the

productivity of the stream. Unfortunately, it is impossible to know if this

is accurate or not because only Reaches 1 and 5 (fig. 2) have been enumerated

(Matthews, 1986).

In the future, Vernon Creek should be enumerated completely to ensure

an accurate estimation of escapements in this tributary. Helicopter

enumeration would not be feasible because only 50% - 70% of the creek could. be enumerated due to overhanging vegetation (Biggs, 1986). It wi 11 therefore

be necessary to enumerate the creek on foot.

With an adequate enumeration, it will then be possible to decide if a

kokanee egg plant is desirable. Should an egg plant be necessary, it should

take place in Reaches 2 and 5.

Page 19: in - a100.gov.bc.caa100.gov.bc.ca/appsdata/acat/documents/r13362/Vernon_creek_fish… · Creek and effluent from storm drains. These chronic problems will require a unified effort

TABLE I1 Best Estimates of annual escapements of Kokanee in selected Okanagan Lake tributary streams (from Houston, 1984)

I

A Stream u

I

Equesis

Mission

Peachland

Powers

Trepanier

Whiteman

Okanagan R. 36,800 * * * 81,000 , * 8,800 * 31,050 5,500

Trout * * * * * * * a * 50 3 50 20

Coldstream 61,410 * * 4 50 * * * * * * 9,271 17,000

Vernon 1,460 * * 7 0 * A * * * * 14 130

Page 20: in - a100.gov.bc.caa100.gov.bc.ca/appsdata/acat/documents/r13362/Vernon_creek_fish… · Creek and effluent from storm drains. These chronic problems will require a unified effort

7 .O FISHERY ENHANCEMENT OPTIONS

7.1 FORMATION OF A VERNON CREEK COMMITTEE

In response to major resource management conflicts that were developing

along the Lower Vernon Creek system, a committee of Provincial Government

agencies involved was struck in 1976. The Departments of Recreation and

Conservation, Municipal Affairs, and Environment were all represented and

met several times "in an attempt to identify these conflicts and develop

solutions" (Anthony, 1976).

In the course of these meetings the change in the quantity and quality

of the creek's flow due'to damming, watershed clearing, sanitary and storm

sewer discharge, channel relocation, and flood plain infilling was discussed.

Erosion and infilling throughout the creek, weed growth at the mouth of

Vernon Creek.due to sediment build-up, fish spawning, and the installation

of bridges, culverts, and dykes were identified as the major resource use

problems.

Although the Vernon Creek Committee was able to identify the major

resource use problems, there was insufficient data at the time to provide

solutions. The majority of their recommendations were derived or obtained

from the 1974 Okanagan Basin Study and the 1974 Kalamalka - Wood Lake Basin Management Study. These were the recommendations made by the Vernon Creek

Committee :

1. Implement Recommendation 1 1 of the Okanagan Basin Study which involves monitoring the watershed; and further that top priority be given to monitoring the quantity and quality of the flow in Lower Vernon Creek.

2 . Request the Government of British Columbia to endorse and implement Recommendation 19 and Recommendation 10 of the Okanagan Basin Study which provides for multi-purpose

Page 21: in - a100.gov.bc.caa100.gov.bc.ca/appsdata/acat/documents/r13362/Vernon_creek_fish… · Creek and effluent from storm drains. These chronic problems will require a unified effort

management of tributaries such as Vernon Creek; and further to prepare a multi-purpose management plan (Recommendation 22) for Lower Vernon Creek watershed as quickly as possible.

3. Request the Okanagan Basin Water Board to implement a development moratorium on a strip 300 feet wide along Vernon Creek from Kalamalka Lake to Okanagan Lake; to prohi bit infi lling, building construction, gravel removal and tree removal within this corridor; and further to maintain the moratorium until the multi-purpose management plan is prepared.

4. Request the Comptroller of Water Rights to not approve any channel relocations on Lower Vernon Creek until the multi- purpose management plan is prepared.

5. Request the British Columbia Government and the Okanasan Basin Water Board to endorse and implement ~ecommendation 270 (sewage outfall removal ) . -

Of the recommendations, only number 5 was acted upon completely. It

is our opinion that all 5 recommendations should have been followed, and

if possible, should be taken into consideration at present. It is also

our opinion that a similar committee should be formed in order to unite the

Provincial Government agencies involved with Vernon Creek. With the

additional information now available an agreement and solution to the

resource use problems on Vernon Creek is much more likely to be found.

Page 22: in - a100.gov.bc.caa100.gov.bc.ca/appsdata/acat/documents/r13362/Vernon_creek_fish… · Creek and effluent from storm drains. These chronic problems will require a unified effort

CLEAN-UP A N D C R E E K MAINTENANCE

One of the most important and immediate needs of Vernon Creek is a

complete clean-up of the banks and streambed. There i s a great deal of wood

debris and garbage throughout the creek (especially Reaches 2 and 3) which

has already caused 3 blockages.

Such blockages make fish passage extremely diff icult . For this reason

the entire channel should be cleaned up, with a l l debris, garbage, and

blockages removed. Once this has been done, an annual clean-up and

maintenance schedule should be established. The best m o n t h for creek

clean-up would be August when the water level is low and there are no

kokanee or eggs present.

On August 18, 1986, a representative of Sisiutl Resources met with

Gary De Leenheer of the Vernon Rod and Gun Club. Mr. De Leenheer expressed

a great deal of interest in taking on the creek clean-up as a C l u b project

provided there would be funding assistance from the Habitat Conservation

Foundation. I t i s our recommendation t h a t the creek clean-up be undertaken

by the Vernon Rod and Gun Club in conjunction with supervision from the

Ministry of Environment.

Page 23: in - a100.gov.bc.caa100.gov.bc.ca/appsdata/acat/documents/r13362/Vernon_creek_fish… · Creek and effluent from storm drains. These chronic problems will require a unified effort

REACH 1 DESCRIPTION

The f i r s t reach extends a t o t a l o f 1.5 k i lomet res from Okanagan Lake t o

t h e i n t e r s e c t i o n o f Vernon Creek and Okanagan Landing Road ( f i g . 3 ) A t

present, t h e p o t e n t i a l o f t h i s reach f o r f i s h spawning i s very low due t o

extreme s i l t a t i o n .

The water throughout t h i s reach, espec ia l l y i n t h e lower h a l f , i s very

t u r b i d due t o s i l t a t i o n ( f i g . 4 ). According t o an in terv iewed res ident , t h e

water has become inc reas ing l y d i r t y over t h e l a s t 12 years and now stays

d i r t y a l l year round. Much o f t h i s t u r b i d i t y appears t o be due t o carp and

o the r coarse f i s h d igg ing up t h e streambed and c a t t l e us ing t h e creek f o r

water ing purposes ( f i g . 6 ) . The water i n t h i s reach moves s lowly and was

measured a t 0.27 m/s on August 8, 1986 by means o f t h e " f l o a t i n g ch ip"

method. Because,the water v e l o c i t y i s so slow, t h i s s t r e t c h o f t he creek

ac ts as a catch basin f o r t h e e n t i r e system and s i l t and o the r f i n e s are

deposited cons tant ly . Such ac t i on has l e f t t he streambed heav i l y laden w i t h

s i l t and unuseable f o r spawning f i s h .

The banks are sloughing and denuded except f o r areas where land owners

have 1 ined t h e bank w i t h w i l l o w t rees . Unfor tunate ly , eros ion has

progressed so f a r t h a t p l a n t i n g o f t r e e s o r o the r vegetat ion would no t be a

s o l u t i o n f o r t h e r e s t o f t h i s reach ( t h e banks are extremely steep and up

t o 3 metres i n he igh t ) .

I n order t o enhance t h i s area f o r kokanee and t r o u t spawning it would

be necessary t o c u t back and slope t h e banks, and r i p r a p 70% o f t he reach.

The streambed i t s e l f i s s i l t laden t o such a depth t h a t s c a r i f i c a t i o n would

Page 24: in - a100.gov.bc.caa100.gov.bc.ca/appsdata/acat/documents/r13362/Vernon_creek_fish… · Creek and effluent from storm drains. These chronic problems will require a unified effort

SCALE 1 : 10,000 I --r 1

0 K) 100 200 300 400 100 600 700 800 METRES

REACH I FIGURE 3

Page 25: in - a100.gov.bc.caa100.gov.bc.ca/appsdata/acat/documents/r13362/Vernon_creek_fish… · Creek and effluent from storm drains. These chronic problems will require a unified effort

not reduce the fines to an acceptable level for spawning. It would therefore

be necessary to line the creek bed with new gravel, and possibly filter

cloth. To keep the cattle out of the creek, 1000 metres of fencing would

be necessary, and a watering channel would have to be constructed. Due to

the cost involved, such a project would not be worthwhile from a fisheries

point of view. However, if a committee of all the agencies interested in

Vernon Creek was struck, such a project might be feasible through group

funding. Such enhancement procedures should only be considered after work

is completed on the upper reaches of Vernon Creek to ensure that siltation

does not occur due to upstream erosion.

Several partial and complete blockages in Reach 1 could hinder fish

migration and should be removed. Approximately 0.8 kilometres upstream from

Okanagan Lake (fig, 3 ,site A), a tree obstruction spans the entire creek

and could hinder 'fish passage if it collects debris. It should be removed

or kept clean of debris. Seventy metres below the Okanagan Landing Road

culvert, there is a complete blockage of the creek due to a pile-up of trees,

wood, and assorted garbage which has reportedly been deposited by a resident

just upstream of the culvert (fig. 3 ,site B and fig. 7 ). This blockage

could be removed with 2 man days and a truck.

The culvert at the Okanagan Landing Road crossing (fig. 3 ,site C and

fig. 8 ) is thought to be nearly impassable to upstreaming kokanee

(Wightman and Taylor, 1978). Upon inspection, our biological survey crew

felt that this would be true under low flow conditions. The culvert is

flatbottomed and multiplated, and was installed at a grade of 3.5% - 4.0%. On August 8, 1986, the water depth was approximately 15 cm, and the stream

Page 26: in - a100.gov.bc.caa100.gov.bc.ca/appsdata/acat/documents/r13362/Vernon_creek_fish… · Creek and effluent from storm drains. These chronic problems will require a unified effort

velocity was 1.8 m/s. I n order t o ensure fish passage a series of offset

ba

ffles should be installed t o reduce water velocity and/or the culvert

should be backflooded through the use of rock gabions or concrete to ensure

adequate water depth. Such backflooding would also produce a pool which fish

could rest i n before ascending the culvert.

Page 27: in - a100.gov.bc.caa100.gov.bc.ca/appsdata/acat/documents/r13362/Vernon_creek_fish… · Creek and effluent from storm drains. These chronic problems will require a unified effort

REACH 1

Fig. 4 Outlet of Vernon Creek to Okanagan Lake *note turbidity of water

Fig. 5 Fence Obstruction Above Mobile Home Park

Page 28: in - a100.gov.bc.caa100.gov.bc.ca/appsdata/acat/documents/r13362/Vernon_creek_fish… · Creek and effluent from storm drains. These chronic problems will require a unified effort

REACH 1

11

L..

Fig. 6 Vernon Creek Showing Cow Pasture and Watering Hole

Fig. 7 Debris Jam Approximately 70 Metres Below the Okanagan Landing Road Crossing

Page 29: in - a100.gov.bc.caa100.gov.bc.ca/appsdata/acat/documents/r13362/Vernon_creek_fish… · Creek and effluent from storm drains. These chronic problems will require a unified effort

REACH 1

Page 30: in - a100.gov.bc.caa100.gov.bc.ca/appsdata/acat/documents/r13362/Vernon_creek_fish… · Creek and effluent from storm drains. These chronic problems will require a unified effort

REACH 2 DESCRIPTION

The second reach extends from the Okanagan Landing Road to the 43rd

Street crossing of Vernon Creek just above the sewage plant (fig. 9 ) . Improved. substrate and velocity make this area much more viable as a spawning

ground for kokanee than Reach 1.

Throughout this stretch the creek is characterized by faster moving

water (0.48 m/s) which is almost all riffle and run. The banks at the very

downstream end are approximately 1.5 metres high, composed of silt and clay,

and currently sloughing (fig. 10 ). The banks throughout the rest of this

reach are low (less than 1 metre) and stable with little or no erosion

taking place. In many cases, property owners have riprapped the banks with

broken concrete.

Approximately 115 of the streambed in this area is composed of gravel

adequate for spawning purposes. On this assumption, this reach could support

8,600 spawning pairs. This estimate is based upon the fol lowing .standards :

spawning area per pair of 0.279 m2 ; length of reach is 3000 metres; average

width of creek is 4 metres. Although residents report this area is heavily

used by spawning fish it has been poorly enumerated in the past because of

its extreme inaccessibility (Matthews, 1986). In future enumerations, this

area should be of highest priority.

Collecti.ons of debris throughout the reach presently pose no difficulty

for fish passage but should be cleaned out to prevent formation of further

blockages.

Page 31: in - a100.gov.bc.caa100.gov.bc.ca/appsdata/acat/documents/r13362/Vernon_creek_fish… · Creek and effluent from storm drains. These chronic problems will require a unified effort

. .

SCALE 1 a 10,000

-0-

OF VERNON

I

i 1

(CONCRETE WlERl

I

CllY LOT DD.8106

SEWAGE PLANT

REACH 2 I

j

r w- -

Page 32: in - a100.gov.bc.caa100.gov.bc.ca/appsdata/acat/documents/r13362/Vernon_creek_fish… · Creek and effluent from storm drains. These chronic problems will require a unified effort

Approximately 100 metres below the sewage treatment plant an old concrete

weir appears to be completely impassable to migrating fish at low water levels

(fig. 11 ). The original owner of this weir is unknown, but it has been used

in the recent past by the Ministry of Environment, in conjunction with Water

Survey of Canada, to measure effluent levels released by the sewage plant

(Dobson, 1986). The weir wi 11 be used this year from November 1 st to

April 30th, but will not likely be used again. The stop log which is in

place at present should be removed forAkmanths_afAptemherand Qst&w05 - - - - - - - -

this year, and the entire structure should be removed in the following year.

Page 33: in - a100.gov.bc.caa100.gov.bc.ca/appsdata/acat/documents/r13362/Vernon_creek_fish… · Creek and effluent from storm drains. These chronic problems will require a unified effort

REACH 2

Fig. 10 Collapsing Bank 100 Metres Above Okana an Landing Road Crossing (very typical bank structure for Reach 1 anflower Reach 2)

Fig. 1 1 Concrete Weir Below Sewage Plant

Page 34: in - a100.gov.bc.caa100.gov.bc.ca/appsdata/acat/documents/r13362/Vernon_creek_fish… · Creek and effluent from storm drains. These chronic problems will require a unified effort

REACH 3 DESCRIPTION

Reach 3 covers the area between 43rd Street and the downstream end of

Pol son Park (fig . 12) . Throughout this reach, the creek runs through

residential and industrial areas. Much of the stream has been channelized

and runs straight and fairly swiftly (0.73 mls). The banks are stable in

Reach 3 due to vegetative growth and bank revetment by residents. The creek

bed is composed of larger gravel and cobbles with stretches of good spawning

gravel in slower running areas. Some silt is present in certain areas,

particularly in backwaters and inside corners, but does not pose a problem.

One hundred and fifty metres upstream of 43rd Street (behind the John

Howard Society) there is a complete blockage of trees and wood debris (fig. 12,

site A and fig. 13). There is a great deal of garbage, wood, and other

debris on the right bank, and another complete blockage exists just behind

the Vernon Transit System building (fig. 12, site B). All three accumulations

should be cleaned up. I

BX Creek, which flows out of Swan Lake, joins Vernon Creek 500 metres

below the intersection of erno on Creek and 32nd Street (fig. 1 4 ) . Like

Vernon Creek, its flow is also regulated. Because the creek is small, runs

through a fairly urbanized area, and has been heavily polluted in the past,

it offers no potential for enhancement.

Page 35: in - a100.gov.bc.caa100.gov.bc.ca/appsdata/acat/documents/r13362/Vernon_creek_fish… · Creek and effluent from storm drains. These chronic problems will require a unified effort

SCALE 1 10,000

REACH 3

FIGURE 12

Page 36: in - a100.gov.bc.caa100.gov.bc.ca/appsdata/acat/documents/r13362/Vernon_creek_fish… · Creek and effluent from storm drains. These chronic problems will require a unified effort

Fig. 13 Obstruction Behind John Howard Society

Fig. 14 Confluence of Vernon Creek (left) and BX Creek

Page 37: in - a100.gov.bc.caa100.gov.bc.ca/appsdata/acat/documents/r13362/Vernon_creek_fish… · Creek and effluent from storm drains. These chronic problems will require a unified effort

REACH 4 DESCRIPTION

Reach 4 covers the portion of the creek within the confines of Polson

Park (fig. 15). Due to channelization, this stretch of the creek is straight,

narrow, and fairly fast (0.78 mls). At the time of inspection the water

throughout this stretch was clean and free of silt and other fines. The

banks in this area were riprapped with broken concrete to prevent sloughing

and erosion, but have now fallen into a state of disrepair (fig. 17).

In its present state, Reach 4 is not beneficial to the Vernon Creek

fishery. The water velocity is great enough that spawning gravel will not

hold, and because there are no pools for resting, even fish passage is

difficult. The greatest advantage to the fishery would be a reduction in

velocity which can be obtained by several methods. The City of Vernon is

planning on riprapping all of Polson Park (Vest, 1986). Before this

renovation takes place, a recommendation should be made that the creek should

not be less than 4 - 5 metres in width at any point through Polson Park. Once the City has completed the work, backf looding devices made of rock or

concrete should be installed every 20 - 30 metres. Such devices will result

in pools of deeper, slower water which migrating fish can rest in.

Producing a meandering creek through Polson Park to increase the length

of the stream, and thereby slow the velocity would not be possible. The

creek runs beside a steep bank on the left side through much of the Park.

On the right side there are decorative pools in the Park (f fg. 18) and then

a road. Because of its close proximity to these obstructions very little

curvature could be produced. Also, the Park has underground irrigation and

Page 38: in - a100.gov.bc.caa100.gov.bc.ca/appsdata/acat/documents/r13362/Vernon_creek_fish… · Creek and effluent from storm drains. These chronic problems will require a unified effort

SCALE 1 10,000

HIGH SCHOOL /

REACH 4

FIGURE 15

Page 39: in - a100.gov.bc.caa100.gov.bc.ca/appsdata/acat/documents/r13362/Vernon_creek_fish… · Creek and effluent from storm drains. These chronic problems will require a unified effort

to change the creek's path would involve major plumbing changes. A t the

upstream end of the Park there is a concrete barrier which may present

problems for fish passage (fig. 19). It wi'll no longer be a problem if

additional pooling devices are installed to increase the water depth below

the barrier.

Page 40: in - a100.gov.bc.caa100.gov.bc.ca/appsdata/acat/documents/r13362/Vernon_creek_fish… · Creek and effluent from storm drains. These chronic problems will require a unified effort

REACH 4

Fig.16 Culvert and Storm Pipes at the Lower End of Polson Park

Fig. 17 Collapsing Riprap in PoIson Park

Page 41: in - a100.gov.bc.caa100.gov.bc.ca/appsdata/acat/documents/r13362/Vernon_creek_fish… · Creek and effluent from storm drains. These chronic problems will require a unified effort

REACH 4

Fig. 18 Decorative Pools in Park

Fig. 19 Concrete and Rock Barriers

Page 42: in - a100.gov.bc.caa100.gov.bc.ca/appsdata/acat/documents/r13362/Vernon_creek_fish… · Creek and effluent from storm drains. These chronic problems will require a unified effort

REACH 5 DESCRIPTION

Reach 5 extends from the upper boundary .of Polson Park to the

Kalamalka Lake outlet (fig. 20). Of all the reaches, Reach 5 has the most

potential for enhancement as a spawning ground for kokanee.

Reach 5 is characterized by fairly fast moving water (0.64 m/s) made

up almost completely of riffle and run. The banks are stable, covered by - . : . , t -

vegetation, and have no need for riprap or other strengthening. There is

very little erosion taking place in this reach, leaving the water clean and

clear. The exception to this is a large clay cliff (fig. 20, site A and

fig. 21) which sloughs at various times and deposits fines into the creek. . . .

The creek bed is composed of large cobble and small rocks with little or no

silt. Because this is the upper end of the creek and Kalamalka Lake is a

large, buffering lake, the creek has had little opportunity' to replenish

lost gravel. Addition of gravel in certain areas would greatly enhance this

reach for spawning.

The eroding cliff mentioned earlier is approximately 500 - 700 metres upstream from Polson Park. The creek flows immediately begide this cliff

for 20 - 50 metres and when the bank sloughs it deposits large amounts of silt and other fines into the creek. This must be repaired by diversion of

the creek. A retaining wall is not a solution because of the height and

steepness of the cliff.

There are three culverts at the Browne Road crossing (fig. 20, site B).

They do not appear to pose any problems because they have been installed

at different levels. This means that there is always at least one culvert

Page 43: in - a100.gov.bc.caa100.gov.bc.ca/appsdata/acat/documents/r13362/Vernon_creek_fish… · Creek and effluent from storm drains. These chronic problems will require a unified effort
Page 44: in - a100.gov.bc.caa100.gov.bc.ca/appsdata/acat/documents/r13362/Vernon_creek_fish… · Creek and effluent from storm drains. These chronic problems will require a unified effort

which is easily accessible to fish.

There are several part i a1 blockages of. debris throughout this reach.

None of them pose a problem yet, but two should be removed. These include a

pile of willow debris and a private bridge near the Kal Nursery at the end

of Browne Road (fig. 20 ,site c and fig. 22), and a collapsed fence in the

water at the upper end of Dutch's Campground (fig. 20 ,site E and fig. 24 ).

Below the campsite, the bridge forming a driveway for Alpine Distributors

has three culvert$ and a concrete weir which the City uses to measure water

flow (fig. 23). The .weir acts as a backf looding device, and has a notch in

it for fish passage. It does not appear to present any problems. The area

immediately below the weir has excellent potential as a spawning bed and is

easily accessible.

The portion' of the creek which extends from Alpine Distributors to the

Railway bridge also has considerable potential as a spawning area. There

are already a few pools suit,able for trout rearing in this stretch and patches

of good spawning gravel (fig.25 and fig. 26). There are occasional boulders

scattered throughout this reach which slow the water and provide excellent

habitat for rainbow fry to rear and for migrating adult kokanee and rainbow

to rest. The addition of several more boulders in certain places is.

recommended. Because this is the upper end of the creek, there would be no

danger of debris piling up on the boulders.

Page 45: in - a100.gov.bc.caa100.gov.bc.ca/appsdata/acat/documents/r13362/Vernon_creek_fish… · Creek and effluent from storm drains. These chronic problems will require a unified effort

REACH 5

.

Fig. 21 Sloughing Embankment Above Polson Park *note storm drains

Debris Caught on Private Bridge (End of Browne Road)

Page 46: in - a100.gov.bc.caa100.gov.bc.ca/appsdata/acat/documents/r13362/Vernon_creek_fish… · Creek and effluent from storm drains. These chronic problems will require a unified effort

REACH 5

Fig. 23 Weir Used by City to Calculate Flow

Fig. 24 Collapsed Fence in Campground

Page 47: in - a100.gov.bc.caa100.gov.bc.ca/appsdata/acat/documents/r13362/Vernon_creek_fish… · Creek and effluent from storm drains. These chronic problems will require a unified effort

REACH 5

Fig. 25 Spawning Gravel on Upper End of Reach

Page 48: in - a100.gov.bc.caa100.gov.bc.ca/appsdata/acat/documents/r13362/Vernon_creek_fish… · Creek and effluent from storm drains. These chronic problems will require a unified effort

REACH 5

- .

Fig. 27 Railway Bridge at Upper End of Reach - - - - - - - - - -

Fig. 28 Flow Regulating Dam at Kalamalka Lake Outlet

- 46

Page 49: in - a100.gov.bc.caa100.gov.bc.ca/appsdata/acat/documents/r13362/Vernon_creek_fish… · Creek and effluent from storm drains. These chronic problems will require a unified effort

8.0 FISHERY ENHANCEMENT METHODS AND COSTS

8.1 REACH 1 ENHANCEMENT METHODS AND COSTS

BANK STABILIZATION AND EROSION CONTROL

Since the cost of this project outweighs the benefits, we do not

recommend that it be undertaken by the Habitat Conservation Foundation.

If a Vernon Creek Committee is formed, this project should be reviewed, and

the feasibility of making it a group project should be discussed. In the

event that this occurs, the following method and approximate costs would

be appropriate.

A Caterpillar 225 backhoe or equivalent would be necessary to cut back

the banks and form a 2:1 slope. If the land owners will not allow the over-

burden material to be deposited and spread over their land by bulldozer,

said material will have to be trucked away. Once a 2: 1 slope is obtained,

the banks should be riprapped with 12" minus rock to a thickness of .30

metres. It would not be worthwhile to lay new gravel on the stream bed

because low water velocities make this area unsuitable for spawning.

In 1976, an extensive study of the erosion problems in Vernon Creek

and the cost of repair was undertaken by the British Columbia Water

Investigations Branch. The cost estimate given for this reach was $164,000.

Our engineering consultant felt this estimate was still fairly valid.

Page 50: in - a100.gov.bc.caa100.gov.bc.ca/appsdata/acat/documents/r13362/Vernon_creek_fish… · Creek and effluent from storm drains. These chronic problems will require a unified effort

SITE SPECIFIC RECOMMENDATIONS

Site A (Obstruction)

Because this obstruction has only caused a partial blockage it does not

need to be removed. Removal of the collected debris around it when the annual

creek cleanup occurs will be sufficient.

Site B (Debris Obstruction)

Removal of this obstruction will involve 2 man days of work. Permission

for access should be obtained from Vernon Helicopters. A power saw, truck,

and winch will be needed. A screen device should be placed downstream of

the obstruction in order to catch material which floats free during the

removal process. The material from the obstruction should be hauled away.

Cost Estimate : $ 400 .OO

Site C (Culvert)

The Okanagan Landing Road culvert appears to be a major hindrance to

fish passage. To ensure fish passage, the velocity in a culvert less than

24.4 metres in length should not exceed 1.2 mls, and the depth of water

should not be less than 0.23 metres (Dane, 1978). At present, this culvert

does not meet either of these criteria. In order to meet both these

requirements, the installation of baffles and backflooding devices will be

necessary.

Through experimentation, it has been found that an offset baffle design

is the most successful (Dane, 1978). This "consists of 'paired' baffles

attached to the sides and bottom of the culvert and extending out into the

flow of water".

Page 51: in - a100.gov.bc.caa100.gov.bc.ca/appsdata/acat/documents/r13362/Vernon_creek_fish… · Creek and effluent from storm drains. These chronic problems will require a unified effort

"One of the baffles extends out from one side of the culvert and is positioned perpendicular (90') to the flow of water. The opposing baffle extends out from the other culvert wall at an oblique (30') angle to the flow of water and also terminates before the center of the culvert at a position slightly upstream from its pair member. The baffles are usually between 0.31 - 0.61 metres in height and produce a flow pattern compatible with fish migration while minimizing interference with debris or bedload movement through the structure. "

By using Dane's design (fig. 29) for offset baffles, it can be seen

that the culvert, which is approximately 20 metres in length and 4 metres

in width, would require 3 pairs of offset baffles. Concrete baffles should

be used because they conform to the bottom of the culvert ensuring that no

water passes between the baffle and culvert. In addition, they are longer

lasting than wooden ones. The baffles should be attached to the culvert by

welding reinforcing steel or bolts to the culvert. The concrete baffles can

then be formed and poured directly in the culvert. We recommend a baffle

height of 30 cm.

Backflooding of the culvert will be necessary to ensure sufficient

water depth for fish passage. This should be done by forming a weir with

rock gabions or large boulders (0.60 metres - 1.0 metres in diameter). The

crest elevation of this weir should be sufficient to provide a minimum

water depth of 0.23 metres above the lowest point of the baffle structure

(Dane, 1978). Because this will result in a fairly high structure, a second

and lower weir should be installed 6 metres below the first as shown in

figure 30 (Government of Canada, and Province of British Columbia, 1980).

A low flow channel or notch 60 cm wide and 30 cm deep should be

incorporated into both weirs for fish passage. It will not be necessary

to riprap the banks because it has been done previously. However, we would

Page 52: in - a100.gov.bc.caa100.gov.bc.ca/appsdata/acat/documents/r13362/Vernon_creek_fish… · Creek and effluent from storm drains. These chronic problems will require a unified effort
Page 53: in - a100.gov.bc.caa100.gov.bc.ca/appsdata/acat/documents/r13362/Vernon_creek_fish… · Creek and effluent from storm drains. These chronic problems will require a unified effort

Lost Rock Invert Control f Level wlth Streom Bed

PROFILE ON # OF CULVERT ROCK CONSrRUCNON- (ONE STEP)

7- Culvert Rmove Top Gabion a t & to

15- 30 cm, / form ~ o t c h e s for Fish ~ossoge

30 cm f m a x ~ Ck Fil led Gobions ( t y d . . . - -

Noturol Stable Streom t rod , \

-,- - 1 -

PROFILE ON 4 OF CUf VERr GABION CONSTRUCTION - (TWO STEP)

FIGURE 30. CULVERT BACKFLOODING

- 51 -

Page 54: in - a100.gov.bc.caa100.gov.bc.ca/appsdata/acat/documents/r13362/Vernon_creek_fish… · Creek and effluent from storm drains. These chronic problems will require a unified effort

advise adding a small amount of riprap to the streambed immediately

downstream of the culvert and two weirs to prevent scouring.

Rather than remove the small concrete weir presently in place, we

would recommend instal 1 ing the first backflooding device immediately

upstream of it. The concrete weir will then prevent scouring and under-

mining of the device.

Cost Estimate:

Concrete Baffle Instal lation =

Caterpillar 225 Backhoe - 10 hours @ $100.00 =

Supply and Delivery of Riprap or Boulders - 9 cu. metres @ $20.00 =

Total Estimated Cost:

Page 55: in - a100.gov.bc.caa100.gov.bc.ca/appsdata/acat/documents/r13362/Vernon_creek_fish… · Creek and effluent from storm drains. These chronic problems will require a unified effort

REACH 2 ENHANCEMENT METHODS AND COSTS

Site A (Concrete Weir)

Because the weir is sti 11 being used by the Water Management Section

of the Ministry of Environment, removal of the structure will have to be

negotiated and approved. It is unlikely that the weir will be used after

the spring of 1987 (Dobson, 1986), so it should be removed in the fall of

1987.

The weir is presently in a weakened state due to scouring and undermining

and could be easily removed by a backhoe equipped with a hoe ram. Access to

the weir can be obtained from the right (north) bank. It will be necessary

for the backhoe operator to make some very minor changes to the bank to gain

access to the weir.

Once the weir has been broken up, the backhoe can load a 12 yard dump

truck and the pieces can then be hauled away.

Cost Estimate :

Caterpi 1 lar 225 Backhoe equipped with hoe ram - 4 hours @ $100.00 =

12 yard Dump Truck - 1 hour @ $50.00 =

Total Estimated Cost :

Page 56: in - a100.gov.bc.caa100.gov.bc.ca/appsdata/acat/documents/r13362/Vernon_creek_fish… · Creek and effluent from storm drains. These chronic problems will require a unified effort

REACH 3 ENHANCEMENT METHODS AND COSTS

Site ÿÿ and B (Blockages)

Both of these blockages should be removed using the same methods and

materials prescribed for Reach 1, site B. Access to the A blockage can be

obtained from either the right or left bank. Permission should be obtained

from the John Howard Society. Access to B blockage is available from the

left bank. Once again, permission should be obtained from the land owner.

Both blockages will require 2 man days of work each.

Cost Estimate :

2 Blockages @ $400.00 =

Total Estimated Cost:

Page 57: in - a100.gov.bc.caa100.gov.bc.ca/appsdata/acat/documents/r13362/Vernon_creek_fish… · Creek and effluent from storm drains. These chronic problems will require a unified effort

REACH 4 ENHANCEMENT METHODS AND COSTS

Poo 1 ing Dev ices

In order to produce holding pools and reduce the water velocity in the

park a series of backflooding devices made of concrete or rock should be used.

We recommend rock because it is aesthetically more pleasing and can be easily

removed or modified if necessary. The boulders used should be between 0.60 m

and 1.0 m to ensure that they do not move during spring freshet.

A small excavator should be used to place and partially bury the

boulders. The boulders should be no more than 0.45 m above the natural

stream bed. A low flow channel or notch 0.60 m wide and 0.30 m in depth

must be provided in each device. To ensure that these rock weirs are effec-

tive, any other gaps between the boulders should be plugged by placing

smaller rock in the upstream side of the gap.

Weir separation should be approximately 20 - 30 metres. However, a

closer study should be made to match spacing between each weir with changes

in the stream gradient. It is imperative that each successive'weir backflood

the previous one, or the weirs will become a hindrance rather than a benefit

to fish migration. Backf looding wi 11 also prevent scouring at the downstream

edge of each weir.

Permission for this project must be obtained from the Parks Board and

the Engineeriqg Department of the City of Vernon. The project should be

undertaken during or immediately after the City renovates the riprap on the

banks and during the time window specified by the Habitat Protection Section.

The City is tentatively planning on doing this in August of 1987 (Vest, 1986).

Page 58: in - a100.gov.bc.caa100.gov.bc.ca/appsdata/acat/documents/r13362/Vernon_creek_fish… · Creek and effluent from storm drains. These chronic problems will require a unified effort

Cost Estimate:

Caterpillar 225 Backhoe or Excavator -

30 hours @ $100.00 =

Boulders Supplied and Delivered - 60 cu. metres @ $30.00 =

Total Estimated Cost:

Page 59: in - a100.gov.bc.caa100.gov.bc.ca/appsdata/acat/documents/r13362/Vernon_creek_fish… · Creek and effluent from storm drains. These chronic problems will require a unified effort

REACH 5 ENHANCEMENT METHODS AND COSTS

Site 'A (Clay Cliff)

At present, Vernon Creek flows immediately adjacent to the base of this

cliff for approximately 20 - 30 metres. To stop sedimentation, the stream

will have to be diverted away from the cliff. This will involve approximately

65 metres of channelization. The new channel should be 1.3 metres deep and

5 metres wide. The banks should be cut back to form a 2:1 slope and then

riprapped with 12 inch minus rock. The new channel should be started 6 metres

upstream of the confluence of the cliff and creek and carried straight for

65 metres where it will rejoin the creek (fig. 31).

In order to complete the job, a Caterpillar 225 backhoe or equivalent

and a D6 bulldozer will be needed. The land is owned by the City of Vernon

(Vest, 1986), and permission in writing will have to be obtained from them.

Permission should also be obtained to spread the overburden material on the

land. If permission to do so cannot be obtained, the material will have to

be trucked away.

To gain access to this area, the Canadian National Railway must permit

access across their tracks.

Cost Estimate:

Caterpi 1 lar 225 Backhoe -

25 hours @ $100.00 =

D6 Bulldozer - 10 hours @ $100.00 =

Page 60: in - a100.gov.bc.caa100.gov.bc.ca/appsdata/acat/documents/r13362/Vernon_creek_fish… · Creek and effluent from storm drains. These chronic problems will require a unified effort

RAN

LOT 24

SCALE 1 :500 '-

0 5 10 20 30

\ \

b

STEEP PROPERTY CLAY

CUFF PROPOSED CHANNEL IA '- DEEP

PLAN 550

PROPOSED CREEK RELOCATION

FIGURE 31

Page 61: in - a100.gov.bc.caa100.gov.bc.ca/appsdata/acat/documents/r13362/Vernon_creek_fish… · Creek and effluent from storm drains. These chronic problems will require a unified effort

12 inch Riprap - 130' linear metres @ $15.00 =

Total Estimated Cost :

Sites C and E (Obstructions)

Both of these obstructions are only partial blockages of the stream

caused by debris piling up against the bridge and fence. Removal of the

debris during the creek cleanup project will be sufficient. 'The owners of

the fence at Site B (Dutch's Campground and. a private resident) should be

contacted to rebuild the portion which has fallen into the creek.

Gravel Replacement

Because Reach 3 is the upper portion of the creek it has had little

opportunity for gravel recruitment. Although there are several patches of

excellent spawning gravel, many areas have lost gravel over time and are now

composed of cobbles and small rocks. Restoration of gravel in these areas

would benefit the fishery. Unfortunately, it is difficult to tell if the

gravel was lost over a great deal of time, or whether it has occurred in a

short amount of time due to high velocity freshet flows.

For this reason we recommend placing a test patch of new gravel in this

reach to determine if the gravel will remain during high flows. We recommend

a patch 0.15 metres deep and 12 metres long, from bank to bank (5 metres).

This equals 9 metres3 which is equivalent to one 12 yard truckload. Bank

run gravel (uncrushed) should be used rather than crushed gravel because it

does not compact as tightly, leaving a larger number of intersitial spaces.

The interstitial spaces provide a greater water flow resulting in higher egg

survival.

Page 62: in - a100.gov.bc.caa100.gov.bc.ca/appsdata/acat/documents/r13362/Vernon_creek_fish… · Creek and effluent from storm drains. These chronic problems will require a unified effort

Sieve analysis before and after the gravel is placed, and then annually

for two years will determine whether the gravel is staying in place. If a

sufficient amount has remained, further gravel should be added, and boulders

could be added to enhance stream habitat.

We recommend placing the gravel in the area upstream of the railway

bridge (fig. 20). A bobcat will be needed to spread the gravel.

Cost Estimate :

Supply and Delivery of Gravel - 9 cu. metres @ $35.00 =

Bobcat - 4 hours @ $50.00 =

Total Estimated Cost:

Page 63: in - a100.gov.bc.caa100.gov.bc.ca/appsdata/acat/documents/r13362/Vernon_creek_fish… · Creek and effluent from storm drains. These chronic problems will require a unified effort

9.0 TIME SCHEDULE

A time schedule for the work to be done has been provided on the following

pages. Enumerations, the debris blockages, and the Vernon Creek Committee were

not i nc 1 uded .

Enumerations of Vernon Creek should be undertaken annually in September

and October throughout the course of the project. Such enumerations will

indicate if egg plants are necessary and whether increased spawning ground

should be provided.

Funding for the debris blockages has already been applied for, and it is

hoped that their removal will be completed this fall.

The Vernon Creek Committee should be organized as soon as possible. Topics

of discussion should include erosion control in Reach 1, storm drains and

minimum flow.

Page 64: in - a100.gov.bc.caa100.gov.bc.ca/appsdata/acat/documents/r13362/Vernon_creek_fish… · Creek and effluent from storm drains. These chronic problems will require a unified effort

CULVERT ( R E A C H 1 )

October, 1986 - Obtain permission from North Okanagan Regional District

November, 1986 - Apply for Habitat Conservation Foundat ion funds

December, 1986 t o April, 1987 - Write contract

- Obtain approval from Water Management and Habitat Protection

June, 1987 - Advertise contract

July, 1987 - Select Contractor

August, 1987 - Complete project

September t o October, 1987 - Assess project

CONCRETE WEIR REMOVAL (REACH 2 )

September, 1986 - Removal of stoplog

November, 1986 - Replacement of stoplog

December t o April, 1987 - Negotiate removal of entire structure

- Obta in written consent from Water and Waste Management

November, 1987 - Apply for funds from Hab i t a t ~onservat ion Foundation

December, 1987 - Write up contract - Obtain approval from Water Management and Habitat Protection

June, 1988 - Advertise contract

July, 1988 - Select contractor

August, 1988 - Complete project

September t o October, 1988 - Assess project

Page 65: in - a100.gov.bc.caa100.gov.bc.ca/appsdata/acat/documents/r13362/Vernon_creek_fish… · Creek and effluent from storm drains. These chronic problems will require a unified effort

WEIR PLACEMENT ( R E A C H 4 )

October, 1986 - Obtain permission of City of Vernon - Review and modify recommended engineering with City of

Vernon

November, 1986 - Apply for Habitat Conservation Foundat ion funding

December t o April, 1987 - Obtain approval of Water Management and Habitat Protection

- Prepare contract

June, 1987 - Advertise contract

July, 1987 - Select contractor

August, 1987 - Complete project

September t o October, 1987 - Assess project

CLAY CLIFF ( R E A C H 5)

December t o April, 1987 - Obta in permission from Canadian National Railway and City

of Vernon

November, 1987 - Apply for funds from Habitat Conservation Foundation

December t o April, 1988 - Write contract

- Obtain approval from Water Management and ~ a b i t a t Protection

June, 1988 - Advertise Contract

July, 1988 - Select contractor

August, 1988 - Complete project

September t o October, 1988 - Assess project

Page 66: in - a100.gov.bc.caa100.gov.bc.ca/appsdata/acat/documents/r13362/Vernon_creek_fish… · Creek and effluent from storm drains. These chronic problems will require a unified effort

9.5 GRAVEL PLACEMENT [REACH 5 )

vember, 1987 - Obtain Water Management permiss ion - In fo rm C i t y o f Vernon and North Okanagan Regional D i s t r i c t - Apply f o r funds f rom H a b i t a t Conservat ion Foundat ion

December t o Ap r i 1, 1988 - Prepare con t rac t

June, 1988 - Adver t i se con t rac t

Ju ly , 1988 - Se lec t con t rac to r

August, 1988 - Complete g rave l placement - Complete s ieve analyses

September, 1989 - Repeat s ieve analyses

September, 1990 - Complete s ieve analyses

October, 1980 - Determine whether f u r t h e r g r a v e l placement i s necessary

CREEK CLEAN-UP (REACHES 1 t o 5 )

November, 1986 - Rod and Gun Club .should apply f o r P u b l i c Conservat ion Assistance Fund monies ($1,000.00)

June, 1987 - Organize clean-up

August, 1987 - Complete clean-up

These procedures should be repeated annual ly .

Page 67: in - a100.gov.bc.caa100.gov.bc.ca/appsdata/acat/documents/r13362/Vernon_creek_fish… · Creek and effluent from storm drains. These chronic problems will require a unified effort

10.0 REFERENCES CITED

Anonymous. 1985. Trout Creek Hatchery - A Proposal for Increasing Tourism in the Southern Okanagan. Ministry of Environment. Unpublished.

Anthony, E.D. 1976. Final Report of Lower Vernon Creek Committee. Unpubl i shed. 10 PP*

Biggs, D. 1986. Personal Communication. Owner/Operator Vernon He1 icopters. Vernon.

Britton, E.W. 1974. Determination of Minimum and Optimum Discharge for Salmonid Production. British Columbia Fish and Wildlife Branch. 32 pp.

Canada British Columbia Okanagan Basin Agreement. 1974. Fisheries and Wildlife Potentials of the Okanagan Basin. Technical Supplement. 249 pp.

Dane, B.G. 1978. Recommendations for the Design and Installation of Culverts in British Columbia to Avoid Conflict with Anadromous Fish. Fisheries and Marine Service Technical Report No. 811. 57 pp.

Dobson, D. 1986. Personal Communication. Engineer, Water Management Branch. Ministry of Environment. Penticton, B.C.

Government of Canada, and Province of British Columbia. 1980. Stream Enhancement Guide. 82 pp.

Houston, C.J.G. 1984. Kokanee Escapements in Okanagan Lake, 1971 - 1984. Unpublished.

Jones, D. 1986. Personal Communication. Head, Habitat Protection Section Region 8. Fish and Wildlife Branch. Ministry of Environment. Penticton, B.C.

Letvak, D.B. 1983. Summary Report on Tributary Water Management Studies. Okanagan Basin Implementation Agreement, Program V. 39 pp.

Matthews, S. 1986. Personal Communication. Fisheries Technician, Fish and Wildlife Branch Region 8. Ministry of Environment. Penticton, B.C.

Morley, J. H. 1976. Vernon Creek Erosion Study. Water Investigations Branch. 15 PP*

Neuman, H.R., and Newcombe, C.P. 1977. Minimum Acceptable Stream Flows in British Columbia. Fisheries Management Report No. 70. 49 pp.

Newcombe, C.P. 1980. A Procedure to Estimate Changes in Fish Production Caused by Changes in a Stream's Discharge. Fish and Wildlife Branch. Ministry of Environment. Victoria, B.C. 19 pp.

Page 68: in - a100.gov.bc.caa100.gov.bc.ca/appsdata/acat/documents/r13362/Vernon_creek_fish… · Creek and effluent from storm drains. These chronic problems will require a unified effort

Nickel, R. 1986. Personal Communication. Head, Okanagan Water Control Project. Ministry of Environment. Penticton, B.C.

Peterson, R., and Wright, P. 1980. Discharges to Storm Drains in Vernon Area. Unpublished. 44 pp.

Vest, R.A. 1986. Personal Communication. Engineer, City of Vernon. Vernon, B.C.

Wightman, J.C., and Taylor, G. 1978. Overview and Rating of Production Capabilities and Enhancement Opportunities for Rainbow Trout and Kokanee in Tributaries to Upper Okanagan Basin Lakes. Technical Report. Fish Habitat Improvement Section. British Columbia Fish and Wildlife Branch. 183 pp.

Page 69: in - a100.gov.bc.caa100.gov.bc.ca/appsdata/acat/documents/r13362/Vernon_creek_fish… · Creek and effluent from storm drains. These chronic problems will require a unified effort

1 1 .O- REFERENCES UNCITED

Acara, A.H. 1977. Meadow Creek Spawning Channel. F i s h e r i e s and Marine S e r v i c e Technical Report No. 744.

Alexander, D.G. August 1979. Nutrient Loadings from Urban Storni Sewer Runoff t o Okanagan and Skaha Lakes. P rogress Report of t h e Okanagan Basin Implementat ion Agreement.

Alexander, D. G. J u l y 1982. Summary of Nitrogen and Phosphorus Loadings t o t h e Okanagan Main Valley Lakes from C u l t u r a l and Natura l Sources : Working Report . Okanagan Bas i n Imp1 ementa t i on Agreement.

Canadian Bio-Resources Engineer ing Ltd. March 1982. N u t r i e n t Loadings from Non P o i n t Sources . P rogress Report. Okanagan Basin Implementation Agreement .

Chamberlin, T.W. ( e d i t o r ) 1980. Aquatic Survey Terminology: APD Technical Paper 2.

Cor r igan , D . , and E . R . Haughton. Apr i l 1973. Task Report on P r e s e n t Loadings of Phosphorus and Nitrogen t o t h e Okanagan Lake System. Task #105. P o l l u t i o n Cont ro l Branch. Dept. of Lands, F o r e s t s and Waters.

Cor r igan , D. and E.R. Haughton. February 1973. Task 151. The Value of S p o r t F i sh ing i n t h e Okanagan Basin. In land Waters D i r e c t o r a t e . Pacif ic Region. Water Planning ,and Management Branch.

F i e l d , P.M. 1985. Trou t Creek Spawning Channel F e a s i b i l i t y Study.

Fish H a b i t a t Survey. 1969. Okanagan Lake Tr ibu to ry Streams.

Gray, C.B.J. n.d. N u t r i e n t Composition of t h e Major T r i b u t a r i e s , a n d I n t e r c o n n e c t i n g Rivers of t h e Okanagan Basin. Nat ional Water Research I n s t i t u t e . In land Waters D i r e c t o r a t e .

G r i f f i t h , R.P. 1982. An Evaluat ion of 1981 Boulder Placements Aimed a t Enhancing Rearing H a b i t a t of J u v e n i l e Salmonids i n Small Streams.

Hal 1 , G. D. September 1972. Water Demand Study Task #54a. Water Resources Serv ice . Dept. of Lands, F o r e s t s and Waters.

Haughton, E .R . , J . Feddes, and L. Bodnaruk. Apri l 1973. Task Report on F u t u r e Loadings of Phosphorus and Nitrogen t o t h e Okanagan Lake System. Task 103. P o l l u t i o n Control Branch. Dept. of Lands, F o r e s t s and Water Resources.

Haughton, E .R . March 1980. Municipal Waste Loading i n t h e Okanagan. Waste Management Branch. M i n i s t r y of Environment. Report No. 79-13.

Hendren, M . K . 9 and W.K. Oldham. December 1973. Storm Sewer Discharge Study - Addendum t o Task 133; Prepared by Facu l ty of Applied Sc ience , U.B.C. f o r P o l l u t i o n Control Branch. Dept. of Lands, F o r e s t s and Water Resources.

Page 70: in - a100.gov.bc.caa100.gov.bc.ca/appsdata/acat/documents/r13362/Vernon_creek_fish… · Creek and effluent from storm drains. These chronic problems will require a unified effort

Houston, C. n.d. Final Report - Main Valley Lakes. Fish and Wildlife Branch. Ministry of 'Environment.

ousto on, C. n.d. Minimum Flow Estimates in Tributary Streams, 1981. Fish and Wildlife Branch. Ministry of Environment.

Houston, C. n.d. Okanagan Main Valley Lakes, Creel Census. Fish and Wildlife Branch. Ministry of Environment.

Houston, C. 1984. Kokanee Escapements in Okanagan Lake.

Kennedy, G.F., and W.K. Oldham. December 1972. Task Report on the Estimate of Nutrient Contribution to Receiving Waters from Agricultural Sources via Groundwater Transport and Estimate of Total Nutrients Ul t imately Reaching Receiving Waters in Groundwater. Task 139 (Part). Faculty of Applied Science. U. B. C. Vancouver.

Koshinsky, G.D. September 1971. Abstract on Fish Habitat Survey: Okanagan Tributary Streams - 1969. From a Report of Same Title by D.M. Galbraith and G.W. Taylor. Partial F~lfillment of Task #66. B.C. Fish and Wild- 1 ife Branch. Dept . of Recreation and Conservation.

Leach, T.A.J. 'August 1971. Major Water Use Development in the Vernon Creek Watershed. File 0281792. Water Investigations Branch. Dept . of Lands, Forests and Water Resources.

Leach, T.A.J. October 1972. Continuing Water Quantity and Quality Monitoring Recommendat ions for the Okanagan Basin. Files 0281792-c-1 and c-4. Draft for discussion at Board - Committee Meeting in Penticton. October 30,1972.

Lindsay, R.A. 1982. Physical and Biological Criteria Used in the Design of the Hi 11 Creek Spawning Channel.

Mih, Walter C. 1976. Restoration of Stream Gravel.

Narver, D.W. 1973. Are Hatcheries and Spawning Channels Alternatives to Stream Protection?

Narver, D.W. March 1974. Technical Supplement I I I - Water Quantity Alternatives and Supporting Water Quantity Data.

Narver, D.W. March 1974. Technical Supplement IV - Water Quality and Waste Loadings in the Okanagan Basin.

Narver, D.W. March 1974. Technical Supplement VI - Review and Evaluation of Wastewater Treatment in the Okanagan Basin.

Narver, D.W. March 1974. Technical Supplement VII - Value and Demand for Consumptive Use of Water in the Okanagan Valley.

Narver, D.W. March 1974. Technical Supplement IX - Fisheries and Wildlife in the Okanagan Basin.

Page 71: in - a100.gov.bc.caa100.gov.bc.ca/appsdata/acat/documents/r13362/Vernon_creek_fish… · Creek and effluent from storm drains. These chronic problems will require a unified effort

Oldham, W.K., and G.F. Kennedy. December 1972. Task Report on In f luence o f Sept ic Tank E f f 1 uent on Receiving Water Nu t r i en t Gain from Groundwater. Task 139 ( p a r t t h e r e o f ) Facu l ty o f Appl ied Science. U.B.C. f o r P o l l u t i o n Control Branch. Dept. o f Lands, Forests and Water Resources.

Oldham, W.K. January 1973. Task Report on t h e Spray I r r i g a t i o n o f Sewage Treatment P lan t E f f luent a t Vernon B.C. Task 147 ( p a r t t h e r e o f ) Facu l ty o f Applied Science. U.B.C. P o l l u t i o n Cont ro l Branch. Dept. o f Lands, Forests and Water Resources.

Oldham, W.K. December 1971. P re l iminary Estimates o f Present Water Demands i n t h e Okanagan Basin. Task #15a. Dept. o f F i she r ies and Forestry. Water Planning and Operations. Vancouver.

Oldham, W.K. December 1971. Pre l im inary Estimates o f Future Water Demands on t h e Okanagan Basin. Task #15b. Dept. o f F isher ies and Forestry. Water Planning and Operations. Vancouver.

Parchomchuk, W., and K. Cooper. August 1977. A Summary o f Proposed Waste Treatment and C o l l e c t i on Fac i 1 it i e s Okanagan Basin. Okanagan Basin Water Board and Environment Canada.

Parchomchuk, W., and K. Cooper. August 1972. Pre l im inary Task Report on Flows i n T r i b u t a r i e s t o Okanagan Lake (Supply and Demand a t Present and Future Development). Task #35. Water I n v e s t i g a t i o n Branch. Dept. o f Lands, Forests and Waters. F i l e 0281792-c-1.

Parchomchuk, W., and K. Cooper. September 1972. Addendum #1 t o Pre l im inary Task Report on Flows i n T r i b u t a r i e s t o Okanagan Lake (Supply and Demand a t Present and Future Development). Task #35. Water I n v e s t i g a t i o n Branch. Dept. o f Lands, Forests and Water Resources.

Parchomchuk, W., and K. Cooper. October 1972. Task Report on 1980 Pro jec t ions f o r Flows i n Selected T r i b u t a r i e s t o Okanagan Lake. Task #35. Water I nves t i ga t i on Branch. Dept. o f Lands, Forests and Waters. F i l e 0281792-c-1.

Parchomchuk, W., and K. Cooper. June 1972. N u t r i e n t Loadings and Lake Manage- ment A l te rna t ives . F i she r ies Research Board o f Canada. West Vancouver.

Talbot, R.J. 1965. Proposed Channel Reconstruct ion o f Vernon Creek. Water Resources Inves t i ga t i on .

Page 72: in - a100.gov.bc.caa100.gov.bc.ca/appsdata/acat/documents/r13362/Vernon_creek_fish… · Creek and effluent from storm drains. These chronic problems will require a unified effort

ACKNOWLEDGEMENTS

Sis iut l Resources would like t o thank Mr. David Smith for supervision 1

I and assistance t h r o u g h o u t the project. We are also indebted to Mr. Robert

- I Moody for g u i d i n g the project through the necessary pol ic ies and procedures.

We would also l ike t o acknowledge the kind cooperation and advice of

3 Neil Banera, Dick Biggs, Gary De Leenheer, Don Dobson, David Jones, Steven

1 Matthews, Richard Nickel, Peter Tassie, and especial l y Richard Vest.