Upload
others
View
7
Download
0
Embed Size (px)
Citation preview
IEM Daily Field Report
Prepared By: Joseph Spinelli IEM Representative
Page 1 of 4
Signed In Signed Out Southwest Brooklyn Marine Transfer Station
1824 Shore Parkway Brooklyn, New York 11214
Date: July 12, 2016 Inspector: Joseph Spinelli Location /
Description:
Project #: URLI1401 Site Time: 0700 to 1530 Assigned by: SPD
Day Weather General Site Conditions
Monday Thursday Clear Cloudy Warm Clear
Tuesday Friday Overcast Windy Hot Muddy
Wednesday Rain Cold Temperature Range: 72 ºF to 79 ºF
General Contractor: Prismatic Development Corporation (PDC) Construction Manager: URS / LiRo
G/C Name: Richard Tonnensen CM Name: Michael Balarezo / Michael Pokorny
S/C&S/C Supervisor: NA CM Phone #: 917-983-5608 / 917-983-5616
Equipment and Machinery in Use(1):
Crane(s)
Elevating Work Platforms
Forklift with extendable arm (Lull)
Water Tank Truck (1) List of equipment and machinery is based on field observations and is not inclusive of every equipment and machinery that may have been present at the site.
Personnel on Site(1):
Personnel Organization Personnel Organization
Personnel PDC Michael Pokorny URS / LiRo
Robert Amrhein Certified Safety Michael Balarezo URS / LiRo
Nelson Mendez EnTech Nabil Saadi URS / LiRo
Personnel AEL, Presco, Stonebridge, Solar Inc., Blue
Diamond, Olympic, K&M Roberto Vazquez URS / LiRo
Joe Incorvaia Total Safety Consultant Victor Bogatyrev URS / LiRo
Andrew Port Louis Berger Tom Karas URS / LiRo
Erdal Gurten Greeley and Hansen (1) List of personnel on site is based on field observations and is not inclusive of every personnel that may have been present at the site.
Observations:
Time Stamp Details
Time On Site: 7:00 am
7:00 am Four air monitoring stations were set up at perimeter locations by EnTech, forming a quadrangle around the anticipated work area, as specified by the CM. According to EnTech, air monitoring is occurring at the four air monitoring stations beginning at 6:30 am. The air monitoring station locations are depicted on the Sketch.
7:00 am to 2:00 pm Presco installing rebar for the walls of the Con Edison building in the eastern section of the site, and in the western section of the second floor of the main building.
7:00 am to 2:30 pm Solar installing electrical wiring and conduit on the second floor of the main building, and working in the electrical control box room.
7:00 am to 2:00 pm Presco bending rebar on the ramp in the northern section of the site. Presco utilizes a Lull forklift to transport rebar around the site.
Day / Date: Tuesday / July 12, 2016 Client: URS / LiRo H2M Project No.: URLI1401
Prepared By: Joseph Spinelli IEM Representative
Page 2 of 4
Time Stamp Details
7:00 am to 2:30 pm GC utilizing elevating work platforms to paint the structural steel connections on the ceiling in the northern portion of the second floor of the main building.
7:00 am to 3:15 pm GC installing steel box forms for a wall on the second floor of the main building in the central portion of the site.
7:00 am to 3:00 pm
Stonebridge utilizing two cranes to erect structural steel in the western section of the concrete foundation slab. Stonebridge utilizing a crane in the northern section of the site to install precast walls on the eastern exterior of the main building. Stonebridge utilizing elevating work platforms to bolt structural steel in the central and eastern sections of the main building. Stonebridge welding structural steel throughout the main building and in the southern section of the site. Stonebridge fastening metal sheets onto the roof of the main building in the southern section of the main building. Stonebridge constructing monitoring hoods in the southern section of the site.
7:00 am to 3:00 pm Blue Diamond installing duct work in the central portion of the first floor of the main building.
7:00 am to 3:00 pm Olympic installing piping on the first floor of the main building.
7:00 am to 3:20 pm GC installing wooden forms for the walls of the Con Edison building in the eastern section of the site. GC installing wooden forms in the western and southeastern sections of the second floor of the main building.
7:00 am to 1:30 pm K&M Fire Protection installing sprinkler mains in the eastern section of the first floor of the main building.
8:45 am to 11:00 am A flatbed truck delivering scaffolding materials enters the site through the gate and the Stabilized Construction Entrance on 25th Avenue. A Lull forklift is utilized to unload the scaffolding materials and place them in the western section of the site.
9:00 am to 12:00 pm A flatbed truck delivering lumber and insulating material enters the site through the gate and the Stabilized Construction Entrance on 25th Avenue. A Lull forklift is utilized to unload the materials and place them in the northwestern section of the site.
9:30 am to 10:00 am & 12:00 pm to 12:30 pm
Site work stops for a work break.
12:45 pm to 1:30 pm A flatbed truck delivering precast walls enters the site through the gate and the Stabilized Construction Entrance on 25th Avenue. A crane in the northern section of the site is utilized to unload the materials and place them in the northeastern section of the site.
2:45 pm to 3:20 pm Two concrete trucks enter the site through the gate and the Stabilized Construction Entrance on 25th Avenue. The first truck pours two walls at the Con Edison building and the second truck pours one wall on the ramp in the eastern section of the site.
3:30 pm Site work stops for the day. The concrete truck utilizes the concrete washout station in the northwestern section of the site and exits the site through the gate and the Stabilized Construction Entrance on 25th Avenue. EnTech removes air monitoring stations.
Time Off-Site: 3:30 pm
General Observations:
According to EnTech, particulate matter and total organic vapors were not detected at concentrations greater than the action levels.
The GC was observed implementing dust suppression at the site by wetting down the ground surface with water from the water tank at 7:45 am and 1:10 pm.
Issues discussed this date with Construction Manager: None.
Persons Contacted: N/A
Status: N/A
Notes: N/A
IEM Daily Field Report
SKETCH
Prepared By: Joseph Spinelli IEM Representative
Page 3 of 4
Approximate Location of Air Monitoring Stations B3.
Approximate Location of Air Monitoring Stations B1.
Approximate Location of Air Monitoring Stations B4.
Approximate Location of Air Monitoring Stations B2.
Approximate location of rebar and wooden/steel box form installation
Approximate location of concrete pouring
Approximate location of concrete washout station
IEM Daily Field Report
PHOTOGRAPH LOG
Prepared By: Joseph Spinelli IEM Representative
Page 4 of 4