14
Atelier 13 Ichthys Development A Major LNG Project Antoine Moreau Ichthys CPF Manager Yves Pouradier TOTAL E&P, Projects and Construction 1

Ichthys Development A Major LNG Project - EVOLEN · 2019. 4. 15. · LPG : 1.6 MTPA Cond : 15,000 b/d Refrigeration: 4 x Frame 7 + helpers; WHR CCPP : 450 MW Storage • LNG 2 x 165,000

  • Upload
    others

  • View
    5

  • Download
    1

Embed Size (px)

Citation preview

Page 1: Ichthys Development A Major LNG Project - EVOLEN · 2019. 4. 15. · LPG : 1.6 MTPA Cond : 15,000 b/d Refrigeration: 4 x Frame 7 + helpers; WHR CCPP : 450 MW Storage • LNG 2 x 165,000

Atelier 13

Ichthys Development

A Major LNG Project

Antoine Moreau – Ichthys CPF Manager

Yves Pouradier – TOTAL E&P, Projects and Construction

1

Page 2: Ichthys Development A Major LNG Project - EVOLEN · 2019. 4. 15. · LPG : 1.6 MTPA Cond : 15,000 b/d Refrigeration: 4 x Frame 7 + helpers; WHR CCPP : 450 MW Storage • LNG 2 x 165,000

General • INPEX 76% Operator - TOTAL 24%

• Browse Basin, 200 km offshore Western Australia; Water depth 235 to 275 m;

• Condensate gas

• Production of Condensate (offshore) + LNG, LPG and Condensate (Darwin)

2

Page 3: Ichthys Development A Major LNG Project - EVOLEN · 2019. 4. 15. · LPG : 1.6 MTPA Cond : 15,000 b/d Refrigeration: 4 x Frame 7 + helpers; WHR CCPP : 450 MW Storage • LNG 2 x 165,000

3

Overall Field Layout

3

Field approx. 40 x 20 km Phased development of the two reservoirs • Brewster • Plover

Page 4: Ichthys Development A Major LNG Project - EVOLEN · 2019. 4. 15. · LPG : 1.6 MTPA Cond : 15,000 b/d Refrigeration: 4 x Frame 7 + helpers; WHR CCPP : 450 MW Storage • LNG 2 x 165,000

4

All project facilities have 40 year design life Cyclonic conditions CPF and FPSO permanently moored for 40 years

Offshore Facilities

Page 5: Ichthys Development A Major LNG Project - EVOLEN · 2019. 4. 15. · LPG : 1.6 MTPA Cond : 15,000 b/d Refrigeration: 4 x Frame 7 + helpers; WHR CCPP : 450 MW Storage • LNG 2 x 165,000

5

SURF Overview

A major subsea development • 13 Drill Centres, 50 X-mas Trees • Hydrate inhibition by MEG loop • Dual 18’’ CRA flowlines + CS MEG lines • 18 Flexibles Risers + 6 Umbilicals • Large Riser Support Structure + other subsea structures • Power interconnection umbilical CPF-FPSO

Page 6: Ichthys Development A Major LNG Project - EVOLEN · 2019. 4. 15. · LPG : 1.6 MTPA Cond : 15,000 b/d Refrigeration: 4 x Frame 7 + helpers; WHR CCPP : 450 MW Storage • LNG 2 x 165,000

6

Page 7: Ichthys Development A Major LNG Project - EVOLEN · 2019. 4. 15. · LPG : 1.6 MTPA Cond : 15,000 b/d Refrigeration: 4 x Frame 7 + helpers; WHR CCPP : 450 MW Storage • LNG 2 x 165,000

7

CPF: A World Record Semi-Sub

Gas-Liquid Separation / Boosters / Dehydration / Gas Export

Page 8: Ichthys Development A Major LNG Project - EVOLEN · 2019. 4. 15. · LPG : 1.6 MTPA Cond : 15,000 b/d Refrigeration: 4 x Frame 7 + helpers; WHR CCPP : 450 MW Storage • LNG 2 x 165,000

8

4 leg semi-sub Operates 200-year storm; survives 10,000-year storm Process • 1.8 BSCFD feed gas • 3 x 33% Trains : inlet separation, liquids transfer to FPSO, booster comp (future), TEG dehydration • Export Compression (4) • Flare stack 150 m Utilities • Power generation with FPSO interconnection Topsides • 115 x 145 m LQ 200 POB Hull • 110.3 x 110.3 m • Spread moored, 4 x 7 chains • Displacement ~155,000 m3

• Integrated deck, erection by lifting

CPF

Page 9: Ichthys Development A Major LNG Project - EVOLEN · 2019. 4. 15. · LPG : 1.6 MTPA Cond : 15,000 b/d Refrigeration: 4 x Frame 7 + helpers; WHR CCPP : 450 MW Storage • LNG 2 x 165,000

9

Condensate Stabilization, Storage and Offloading MEG Regeneration / Water Treatment and Disposal

FPSO

Page 10: Ichthys Development A Major LNG Project - EVOLEN · 2019. 4. 15. · LPG : 1.6 MTPA Cond : 15,000 b/d Refrigeration: 4 x Frame 7 + helpers; WHR CCPP : 450 MW Storage • LNG 2 x 165,000

10

Ship shaped new build FPSO Operates 200-year storm, survives 10,000-year storm 336 x 59 m Weathervaning turret mooring

Process • 2 trains (Cond-Water separation, Flash Gas Compression) • 80,000 bopd • Cond / Water Mercury removal • MEG Regeneration / Storage • Water Treatment / Disposal

Storage 1.1 Mb; tandem offloading

Utilities • Heating Medium (MEG regen) • Power generation with CPF interconnection

LQ 200 POB

FPSO

Page 11: Ichthys Development A Major LNG Project - EVOLEN · 2019. 4. 15. · LPG : 1.6 MTPA Cond : 15,000 b/d Refrigeration: 4 x Frame 7 + helpers; WHR CCPP : 450 MW Storage • LNG 2 x 165,000

Gas Export Pipeline

11

• 885 km • Water depth 0-250 m • 42’’; 202 bar

• Capacity 1,8 MSCFD; dense phase or multiphase operation

• Internal coating

• 3 x 42’’ diverless connectors • Steel ~700,000 t

• Rocks ~700,000 t

Page 12: Ichthys Development A Major LNG Project - EVOLEN · 2019. 4. 15. · LPG : 1.6 MTPA Cond : 15,000 b/d Refrigeration: 4 x Frame 7 + helpers; WHR CCPP : 450 MW Storage • LNG 2 x 165,000

12

LNG Plant

Page 13: Ichthys Development A Major LNG Project - EVOLEN · 2019. 4. 15. · LPG : 1.6 MTPA Cond : 15,000 b/d Refrigeration: 4 x Frame 7 + helpers; WHR CCPP : 450 MW Storage • LNG 2 x 165,000

LNG Plant

13

APCI Process C3/MR LNG : 2 x 4.2 MTPA LPG : 1.6 MTPA Cond : 15,000 b/d

Refrigeration: 4 x Frame 7 + helpers; WHR

CCPP : 450 MW Storage • LNG 2 x 165,000 m3

• C3/C4 85,000 + 65,000 m3

• Cond 2 x 60,000 m3

LNG Loading Jetty LPG + Cond. Jetty

Modular construction (except tanks, tall vessels, large rotating equipment) Massive dredging works

Page 14: Ichthys Development A Major LNG Project - EVOLEN · 2019. 4. 15. · LPG : 1.6 MTPA Cond : 15,000 b/d Refrigeration: 4 x Frame 7 + helpers; WHR CCPP : 450 MW Storage • LNG 2 x 165,000

A Very Challenging Project

• Development of major magnitude in all perspectives

• Largest ever built CPF

• Cyclonic environment

• Several components beyond current state of the art, will be qualified

• 40 year design life

• Highest HSE expectations

Build a project for 40 years of

safe and reliable operation