Upload
others
View
6
Download
0
Embed Size (px)
Citation preview
WIND TURBINE SHUTTLE
HUISMAN PRODUCT BROCHURE
01DESCRIPTION 03
1.1 Vessel General 03
1.2 Purpose of the Vessel 04
1.3 High Workability 04
1.4 Installation Scenarios 05
1.5 High Transit Speed and Excellent Seakeeping 06
1.6 Running on LNG Fuel 06
1.7 DP3 System 07
1.8 Vessel Motion Compensation System 07
1.9 Motion Compensation in the Hoisting System 08
1.10 Ballast System 09
1.11 Structural Design 09
1.12 Maintenance, Repair & Decommisioning 10
1.3 Additional Applications of the Vessel 10
1.4 Shallow Draft Catamaran Version 10
02TECHNICAL SPECIFICATIONS 11
2.1 Vessel 11
2.2 Top Side Equipment 11
TABLE OF CONTENTS
WIND TURBINE SHUTTLE
Artist’s impression of WTS
1. DESCRIPTION
1.1 Vessel general
To improve the efficiency of offshore wind turbine installation,
Huisman developed the Wind Turbine Shuttle: a dynamically
positioned, fast sailing (14 knots) SWATH - Small Water plane
Area Twin Hull - type construction vessel which can carry
and install two fully assembled wind turbines. By combining
low vessel motions, compensating systems and an accurate
dynamic positioning system, the wind turbine is kept virtually
stationary in relation to the fixed foundation during installation.
WIND TURBINE SHUTTLE ADVANTAGES
At least 80% workability in annual North Sea conditions
Excellent vessel motion characteristics
Active roll and pitch vessel motion compensation
systems
Active heave, pitch and surge compensation hoisting
systems
High transit speed and DP3
Can transport up to two wind turbines in one piece
Commissioning and testing onshore, turbine earlier
online
Also capable of installing jackets, mono piles, piling, and
other offshore structures
3
4
1.2 Purpose of the vessel
The vessel is especially dedicated to installing wind turbines
offshore. Fully assembled wind turbines delivered to the
installation site minimizing the time of construction works
offshore.
The vessel can also carry two large jackets or two large mono
piles or combinations thereof. In case of jacket installation the
wind turbines shuttle can carry the piles needed to secure the
jacket to the seafloor.
The vessel is able to transport simultaneously two complete
wind turbines with a maximum mass of 1000mt each. This
enables the vessel to install all current models of wind
turbines and future models up to an approximate size of 8MW.
As the wind turbines can be fully erected, commissioned and
tested onshore, the offshore commissioning time is minimized.
The wind turbines will be earlier on-line and deliver power
faster to the grid. The vessel can also carry and install two
complete foundations (jacket type and mono piles) with the
maximum weight of 2000mt each.
The main capabilities of the new vessel are:
Installing complete wind turbines
Installing complete foundations (jacket type)
Installing complete foundations (mono piles)
Pile driving
All year operation in The North Sea
High yearly performance with very limited down time.
1.3 High workability
Traditionally, crane vessels and jack-up platforms are utilized
for offshore construction works. Normally parts of the wind
turbines are loaded into the vessel and then transported to the
wind farm site. The wind turbines are assembled from these
parts offshore utilizing a large crane. However the workability
of crane vessels without jack-up system is very low. Even a
moderate sea state makes the lifting operation impossible.
Operating the vessels or platforms equipped with the jack-up
system is time consuming. The lowering and retrieving of the
legs of the jack-up system takes time. These operations are
also sensitive to environmental conditions. Normally the transit
speed of these vessels is quite low.
WIND TURBINE SHUTTLE
The WTS is a SWATH-type vessel which provides excellent
vessel motions and therefore a large workability. Since the
unit is not jacked out of the water, the workability is not limited
by this operation. Also no additional time is consumed by
this operation. The unit has two large underwater pontoons,
rather small columns and a deck box above the water. As
soon as the unit sails out of the harbour, the draft is adjusted
so that the pontoons are submerged beneath the water line,
providing low vessel motions during the transit and during the
installation.
WTS with two wind turbines
WTS with two mono piles
WTS with two jackets
WTS with piles
5
The vessel is able to install wind turbines with a maximum
significant wave height of 3.5m. This gives the unit a
workability of at least 80% of the year in North Sea conditions
in the open areas and up to 95% closer to the shore. By
choosing the heading, the vessel will mainly endure (limited)
heave, pitch and surge motions. Additionally the vessel is
equipped with an active pitch and roll damping system to
further reduce vessel motions.
1.4 Installation scenarios
Minimization of offshore work is achieved by transporting
the wind turbines as entirely tested units. All the testing and
commissioning is done onshore. This requires a low number
of dedicated shore bases (e.g. Denmark, East of England,
and Scotland). The vessel has an optimised hull form and
significant installed power to reach a high transit speed. In 12
hours the vessel can travel approx. 150 miles.
WTS picking up wind turbine from a
shore base
North Sea with wind parks and 150 miles radius from 3 shore bases (East of England,
Esbjerg (DK), Scotland)
Load two wind turbines
Sail to wind farm
Install two wind turbines
Sail back to harbour
Contingency
Total for two wind turbines
Load two foundations
Sail to wind farm
Install two foundations
Sail back to harbour
Contingency
Total for two foundations
Total for two wind turbines & foundations
Number of wind turbines & foundations per year based on;
workability of 80% for installation of wind turbines and a
workability of 90% for installation of foundations, excl. piling
2
4
4
4
6
20
2
4
2
4
4
16
36
409
2
8
4
8
6
28
2
8
2
8
4
24
52
284
2
12
4
12
6
36
2
12
2
12
4
32
68
217
[hrs]
[hrs]
[hrs]
[hrs]
[hrs] +
[hrs]
[hrs]
[hrs]
[hrs]
[hrs]
[hrs] +
[hrs]
[hrs]
[-]
Distance shore base to wind farm 50 100 150 [miles]
1.5 High transit speed and excellent seakeeping
Since the WTS can take only two wind turbines or two
foundations the requirement for covering the distance
between the shore base and the installation site in a
short time is of major importance. At the same time good
seakeeping performance is required for installation. A SWATH
type vessel is chosen due to combination of excellent
seakeeping characteristics and the high transit speed.
Extensive research and model testing resulted in a highly
optimized hull shape.
1.6 Running on LNG fuel
The vessel will be equipped with diesel generator sets
capable of running on both MDO and LNG. If LNG bunker
facilities are provided all operations of the Wind Turbine
Shuttle can be performed using LNG fuel making the whole
installation campaign even more environmentally friendly.
6
WIND TURBINE SHUTTLE
Resistance model tests in towing tank
Seakeeping model tests in waves
CFD calculations
1.7 DP3 system
The high redundancy of the DP3 system is provided by
arranging all four diesel generators in 4 separated engine
rooms.
The vessel is equipped with two large variable pitch propellers
to obtain a transit speed of 14 knots. Together with the large
variable pitch propellers, eight tunnel thrusters are used
for dynamic positioning during installation operations. The
dynamic positioning system keeps the vessel in place during
installation of the wind turbines, even in the most severe
weather conditions. By using dynamic positioning (instead
of mooring or jacking out of the water) the installation is very
fast.
1.8 Vessel motion compensation system
Although the SWATH type vessel provides excellent
seakeeping performance even more effort was put into
further improvement of motions in waves. Active roll and pitch
compensation systems were developed. The system utilizes
a moving mass. For roll compensation a mass driven in the
transverse direction is applied. For pitch two masses are
used, which move in the longitudinal direction. The vessel
motions are reduced by 30-40% when the system is in active
mode. These systems will be mostly used during the wind
turbine installation sequence when the vessel motions have to
be minimized as much as possible.
7
Separated engine rooms
Set-up for testing active pitch compensation system
1.9 Motion compensation in the hoisting system
Huisman has used its 25 years of experience in the
application of active heave compensation systems on cranes
and other lifting devices for the design of the Wind Turbine
Shuttle. The wind turbine is held in place by a hoist frame.
This frame consists of two tables connected by a steel
structure. Each table is equipped with an active controlled,
horizontal movable, XY-clamp. The wind turbine hoist frame
connected to the hoist tackle at the bottom table.
A passive heave compensation system in the combination
with active wire connection between the wind turbine and the
foundation is applied for soft controlled lowering and landing
of the wind turbine on the foundation.
Once the wind turbine is lowered a quick connector is
engaged firmly connecting the wind turbine with the
foundation. From this point the Wind Turbine Shuttle can
sail to the next installation site. The bolt connections can be
safely made while the wind turbine is still secured by the quick
connector. The quick connector will be picked up later.
8
WIND TURBINE SHUTTLE
Upper clamp
Lower clamp
1.10 Ballast system
A conventional water ballast system is utilized for changing
the draft from shallow harbour draft to the submerged transit /
installation draft.
During installation, the load of the wind turbine is transferred
from the WTS to the foundation. A constant draft has to
be maintained. Here a dedicated water ballast system is
applied allowing fast water ballast exchange minimizing the
wind turbine installation time. The longitudinal position of
the dedicated water ballast tanks is close to the longitudinal
centre of gravity of the wind turbines. This allows pumping
the amount of water equal to the weight of the wind turbine
without necessity to compensate for trim change since the
trim remains constant.
1.11 Structural design
The installation of the wind turbines and jacket foundations
requires large recesses in the deck box structure. The
requirement for high speed and rudder arrangement make
the struts long and very narrow, thereby attracting significant
wave forces. The structural design of the vessel is carefully
performed covering both the global strength and the fatigue
requirements.
The design wave approach is applied for the global structural
analysis of the vessel. The strength against the yield stress
and buckling is checked. Fatigue is considered from the very
beginning of this project. ANSYS is applied for the structural
finite element analysis (FEA). The wave conditions of The
North Sea set very high requirements for the design with
respect to the fatigue. The major structural connections of the
WTS are carefully checked for fatigue and the geometry of
these connections is optimized
9
Pump room
1.12 Maintenance, repair, & decommissioning
Due to its capacity to transport two wind turbines at the
same time, the vessel is perfectly suited for exchanging wind
turbines. The vessel can install one or two new or refurbished
wind turbines and pick up two old wind turbines. All repair,
maintenance and decommissioning work is performed
onshore. Because the wind turbine shuttle can transport
complete turbines, it is an excellent tool for power upgrades
and overhaul of existing wind turbines.
1.13 Additional Applications of the Vessel
The vessel also provides an excellent platform for offshore
construction works. The Wind Turbine Shuttle can be
deployed for installation and removal of the top sides and
foundations of existing oil platforms. The fact that the vessel
is equipped with the highest level DP3 system means that the
vessel can be also utilized in the oil industry.
1.14 Shallow Draft Catamaran Version
A shallow draft catamaran version of the Wind Turbine Shuttle
can be used in the areas with shallow water depths (see
figure). The installations will be carried out in mild weather
conditions.
10
WIND TURBINE SHUTTLE
Structure of WTS
Decommissioning of top sides
Catamaran Type WTS with shallow draft
11
GENERAL
MAIN DIMENSIONS
MARINE SYSTEMS
PAY LOAD*
CAPACITIES
MISCELLANEOUS
GENERALClassification
Length over all
Breadth
Airgap during installation / sailing
Depth to main deck (also freeboard deck)
Design draught
Harbour draught
Scantling draught
Displacement at design draught
Payload (wind turbine)
Payload (wind turbines foundations)
Main engines
Total installed engine power
No. of independent engine rooms
Main propulsion (CPP)
Tunnel thrusters
Dynamic positioning class
Service speed
Payload (two wind turbines)
Payload (two wind turbine foundations or monopiles)**
Payload (40 piles, max length of piles approx. 50m)**
* one of these options at the time
** minimum draft with payload of 4000 mt is approx. 11.5m
MDO
LNG
Fresh water
Water ballast capacity
Complement in 1 and 2 person cabins
Main hoist fwd
Main hoist aft
2 x PMOC
134.4 [m]
72.0 [m]
7.4 [m]
28.8 [m]
16.0 [m]
9.5 [m]
18.0 [m]
Approx. 38000 [mt]
2000 [mt]
4000 [mt]
4 x 5.7 [MW]
22.8 [MW]
4 [-]
2 x 8.0 [MW]
8 x 1.6 [MW]
DP3 [-]
14 [knots]
2000 [mt]
4000 [mt]
4000 [mt]
600 [m3]
600 [m3]
400 [m3]
17506 [m3]
100 [-]
1600 [mt]
1600 [mt]
2 x 300 [mt]
2.1 Vessel
2. TECHNICAL SPECIFICATIONS
DNV 1A1 Wind Turbine
Installation unit, DYNPOS-AUTRO
INSTALLATION TOWER / CRANAGE2.2 Top side Equipment
Note: Specifications might be subject to changes as the design progresses
HUISMAN EQUIPMENT BV
Admiraal Trompstraat 2
3115 HH Schiedam
P.O. Box 150
3100 AD Schiedam
The Netherlands
Harbour no. 561
Phone: +31 (0)88 070 22 22
Fax: +31 (0)88 070 22 20
E-mail: [email protected]
www.huismanequipment.com
062015