MIDAS ONE
www.milahaoffshore.com
GENERAL DESCRIPTION
This document has been prepared to provide a functional overview of the Modular
Offshore Drilling and Workover Package.
As the Workover package is modular it can be configured/customised to suit specific
applications. This can include the addition of handling equipment for larger pipe or
conductor sizes as well as picking the drill pipe up from any of 3 sides.
The Modular Drilling and Workover package can be built with the mud system on
either side to allow access of the rig to all well locations on the platform.
In its current configuration it is set up to sit on Rig Skid beams up to 16 metres apart
and to operate on side track drilling or well abandonment operations with the
Modular Rig System. Sitting on the rig skidding beams allows the Modular Rig and
Mud system to skid quickly and efficiently from well to well.
INTRODUCTION
FUNCTIONAL OVERVIEW
The system consists of the following packages:
o Rig System Support Beams and Skidding System
o Rig Substructure including BOP transport system, Well Control Stack and Bell nipple
o Drill floor c/w Iron Roughneck, Rig Assist Jack, Mud Bucket and Tiger Tail.
o Pipe handling Cat Walk Machine
o Mast system including hoist mechanism.
o Top Drive system including wash pipe, Drill motor, I-BOP’s and Hydraulic Elevators.
o Stair Towers including Pipe handling winches and Standpipe manifold.
TECHNICAL OVERVIEW
The system consists of easily transportable equipment skids to ensure quick and
efficient assembly/disassembly of the Modular Rig System on any location.
Subject to Crew and Crane availability the Modular Rig System can be built and
operational within 3 to 5 days.
MIDAS ONE
www.milahaoffshore.com
Technical Specifications: Rack and Pinion Hoist 300,000 lb (150 tn) SWL
56.81 ft (17.32 m) Clear Working Height (stroke length) 114 ft (34.76 m) Overall Height
Top Drive 23,600 ft lb @ 115 RPM output
5000 psi Circulating Pressure Casing Jack 600,000 lb (300 tn) SWL
300,000 lb Snub Capacity Skid Beams 17 Meters long
4.6 Metres outer width to Flange Skidding System Skidding System suitable to skid the Modular
unit and the Mud System to access wells in X and Y directions.
Sub Structure Substructure designed to handle and operate with 13 5/8” 10K stack with Annular.
Hydraulic Power Units 3 x 600 HP Diesel Driven HPU’s. 3000 litre Fuel Tank.
Pipe Handling Machine 2 3/8-in. to 20-in. Pipe Range Hydraulic Rotating Elevator 2 3/8-in. to 9 5/8-in. Pipe Range Power Slips 2 3/8-in. to 14-in. Pipe Range Pipe Tailing Arm
2 3/8-in. to 10 3/4-in. Pipe Range Pipe Make up 60,000 ft lb (81 kNm) Max make up torque
80,000 ft lb (108 kNm) Max break out torque 2 3/8-in. to 8 1/2-in. Pipe Range
Catheads 31,500 lb (14 tn) Line Pull Manual Tongs 100,000 ft lb Max torque rating
4-in. to 21-in. Pipe Range BOP Closing Unit 350 USG 7 Function Closing Unit c/w 2 remote
stations Choke Manifold 3 1/16-in. 10 k Manifold (1 remote, 2 manual
chokes) Standpipe Manifold 4 1/16-in. 5 k Manifold Data Acquisition System Ability to monitor all relevant well parameters
in real time. Remote monitoring (Exported in WITS format)
Fire and Gas System Ability to monitor fire and gas at relevant locations around the unit.
Displays for Control Cabin and platform CCR CCTV System 6 x pan and tilt Dome camera
1 x CCTV monitor (mounted in Control Cabin) Overall Weight 230 tonnes, skid rail weight (excluding
hookload)
96 tonnes, auxiliary equipment on pipe deck
www.milahaoffshore.com
MIDAS ONE
3 General Arrangement 2 Koomy Skid Unit
1 Choke Manifold Skid
5 Drill Floor 4 Control, Human Machine Interface
www.milahaoffshore.com
MIDAS ONE
9 Top Drive 6 Iron Roughneck, Drill Floor
8 HPU System
7 Catwalk Machine
www.milahaoffshore.com
MIDAS ONE
MILAHA Offshore Service Company PTE LTD (Singapore) One Pemimpin, 1 Pemimpin Drive #06-12, Singapore 576151 [email protected], [email protected] +65 69080994 / +65 91192275 / +65 91192486
Top Drive
Drill Floor
DCR
Sub Structure
Shaker House
Rack & Pinion Hoist Mast
Winch Package
PoorBoy Degasser
Mud Plant