Upload
thilina
View
221
Download
0
Embed Size (px)
Citation preview
8/3/2019 Group Presentation 03
1/29
Design of Optimum Earthing System
to Substation Using a Software
Presented by GroupC
D V G Chamara
L Neelawala
D H S Piyumika
S L Prabashwara
G W V Priyantha
E A K Sandakalum
T M Weerakkody
8/3/2019 Group Presentation 03
2/29
Associated Journals
N M Tabatabaei and S R Moetezaeei,Design of Grounding Systems in
Substations by ETAP Intelligent Software,
International Journal on Technical andPhysical Problems of Engineering, Vol 2,No. 4, P 45-49, March 2010
E U Ubeku and F Odiase, SubstationEarthing Grid Safety Analysis, International
journal of Electrical and Power Engineering,Vol 3, No. 5, P262-267, 2009
8/3/2019 Group Presentation 03
3/29
Abstract
Journal 1:In a properly designed ground system,under faulty conditions voltage
gradient should not exceed the limitsthat can be tolerated by the humanbody.
maximum tolerable potential
deference should be carefullydesigned. Genetic algorithm wasdeveloped to find the optimum
grounding system to ensure safety ofeo le even at severe fault.
8/3/2019 Group Presentation 03
4/29
Abstract (contd..)
Journal 2:
The study presents a user interactiveprogram to design a substation
earthing grid system. Standard IEEE80 and 2000 are used to write theprogram for simulation of touch, step
and mesh potentials to avoid trial anderror process to ensure accuracy andsafety.
8/3/2019 Group Presentation 03
5/29
8/3/2019 Group Presentation 03
6/29
Objective of Earthing Design
To provide a direct path for electric currentsto flow to the ground
under normal and fault conditions
without exceeding any operating and
equipment limits, or adversely affectingthe continuity of service
To ensure that persons in the vicinity ofgrounded facilities are not exposed to the
danger of electrical shockmaintaining step and touch voltages attolerable values
8/3/2019 Group Presentation 03
7/29
Key Factors of EarthingDesign Ground Potential Rise (GPR)
1. Ground Potential Rise (GPR) is a phenomenon that occurswhen large amounts of electric current enter to the earth.
2. typically caused when substations or high-voltage towersfault, or when lightning strikes occur (fault current).
3. The voltages produced by a Ground Potential Rise or EarthPotential Rise event can be hazardous to both personneland equipment.
8/3/2019 Group Presentation 03
8/29
Key Factors of EarthingDesign Touch and Step Potential
8/3/2019 Group Presentation 03
9/29
Touch PotentialThe potential difference between the ground
potential rise (GPR) and the surface potential at
the point where a person is standing while atthe same time having a hand in contact with agrounded structure
Key Factors of EarthingDesign
Step voltage
The difference in surface potential
experienced by a person bridging a distanceof 1m with the feet without contacting any
grounded object
8/3/2019 Group Presentation 03
10/29
Algorithm for program
8/3/2019 Group Presentation 03
11/29
Algorithm for program
8/3/2019 Group Presentation 03
12/29
Design Procedure
Step 1:Determine the soil resistivity profile and the soil model needed(that is, uniform or two-layer model).
Step 2:Determine the conductor size. The fault current should be themaximum expected future fault current, and the time, tc, shouldreflect the maximum possible clearing time
Amm2 conductor cross section in mm2
I rms current in kA
Tm maximum allowable temperature in C
Ta ambient temperature in C
Tr reference temperature for material constants inC
o thermal coefficient of resistivity at 0 C in 1/C
r thermal coefficient of resistivity at referencetemperature Trin 1/C
r resistivity of the ground conductor at referencetemperature
Ko 1/oor (1/r)Trin C
tc duration of current flow in s
TCAP thermal capacity per unit volume
8/3/2019 Group Presentation 03
13/29
Step 3:Determine The tolerable touch and step voltages. The choice oftime, ts, is based on the judgment of the design engineer
Estep= (RB+6Cs) IB
Etouch= (RB+1.5Cs) IB
Design Procedure
Tolerable body current limit
IB= rms value of the current through the body in mA
ts= duration of the current exposure in s (from 0.03 3
s)
k= empirical constant related to electric shock energy
For a 50kg person, k50=116
For a 70kg person, k70=157
IB =ts
k
Effect of a thin layer of surface material
Corrective factor Cs used to compute effective foot resistance in thepresence of a finite thickness of surface material
8/3/2019 Group Presentation 03
14/29
Design Procedure
Step 4:The preliminary design should include a conductor loopsurrounding the entire grounded area, plus adequate crossconductors to provide convenient access for equipmentgrounds, etc.The initial estimates of conductor spacing and ground rodlocations should be based on the current IG and the area beinggrounded.
70 m
70 m
8/3/2019 Group Presentation 03
15/29
Design ProcedureStep 5:
Estimate the preliminary resistance of the grounding system.For the final design, more accurate estimates of the resistance maybe desired. Computer analysis based on modeling the componentsof the grounding system in detail can compute the resistance with ahigh degree of accuracy, assuming the soil model is chosencorrectly.
Step 6:Determine the grid current.
To prevent over design of the grounding system, only that portion ofthe total fault current, that flows through the grid to remote earthshould be used in designing the grid. The current should, however,reflect the worst fault type and location, the decrement factor, andany future system expansion.
Step 7:If the GPR of the preliminary design is below the tolerable touchvoltage, no further analysis is necessary. Only additional conductorrequired to provide access to equipment grounds is necessary.
GPR= If,max.Rg
This Should be less than Etouch voltage
8/3/2019 Group Presentation 03
16/29
8/3/2019 Group Presentation 03
17/29
Design Procedure
Step 9:If the computed mesh voltage is below the tolerable touchvoltage, the design may be complete .If the computed mesh voltage is greater than the tolerabletouch voltage, the preliminary design should be revised
Step 10:
If both the computed touch and step voltages are belowthe tolerable voltages, the design needs only therefinements required to provide access to equipmentgrounds. If not, the preliminary design must be revised.
Step 11:If either the step or touch tolerable limits are exceeded,revision of the grid design is required.These revisions may include smaller conductor spacings,additional ground rods, etc.
8/3/2019 Group Presentation 03
18/29
Design Procedure
Step 12:After satisfying the step and touch voltage requirements, additional
grid and ground rods may be required.The additional grid conductors may be required if the grid design
does not include conductors near equipment to be grounded.Additional ground rods may be required at the base of surge
arresters, transformer neutrals, etc.The final design should also be reviewed to eliminate hazards due totransferred potential and hazards associated with special areas ofconcern.
DISADVANTAGE OF MANUAL
8/3/2019 Group Presentation 03
19/29
DISADVANTAGE OF MANUAL
CALCULATION
1 ITERRATIVE PROCEDURE
2 TIME CONSUMING
3. LACK OF MUTUAL EFFECTCONSIDERATION
4. FREQUENCY RESPONSE IS NOT INCONSIDARATION
5. NONLINEERITY AND CLIMATE CHANGESARE NOT IN CONSIDERATION
8/3/2019 Group Presentation 03
20/29
Sample StimulationResults
Case-01 :
8/3/2019 Group Presentation 03
21/29
Sample StimulationResults
Case-02:
8/3/2019 Group Presentation 03
22/29
Sample StimulationResults
Case-03:
8/3/2019 Group Presentation 03
23/29
Sample StimulationResults
Case 04: Designing of Earth SystemNetwork with the same interval
Case 05 : Design of Earth System Network
with optimum conductors land base networkoptimization single variable
Case 06 : Designing of Earth SystemNetwork with comprehensive multivariateoptimization (based on optimizing thenumber of conductors and earth rodnetworks
8/3/2019 Group Presentation 03
24/29
Sample StimulationResults
8/3/2019 Group Presentation 03
25/29
Sample StimulationResults
8/3/2019 Group Presentation 03
26/29
Advantages over ManualProcess Associated complex equations can be solved
more accurately. Mutual effects of adjacent grounding objects
can be taken into the account.
Facility to simulate under various soil layermodels with seasonal effects. Simulate under fast transient and power
frequencies. 3D Geometry of the grounding system can be
modeled Ability to design cost optimum safe grounding
system.
8/3/2019 Group Presentation 03
27/29
Future Milestones
Substation Grounding is a complexprocess due to number of involvedphenomena. One of major problem iswhen lightning occur, non-linear andionization phenomena appear in thesoil. Therefore, we should investigateand develop a model to evaluate
performance of soil under impulsetransient. Thereafter this model can beincorporate to existing software.
8/3/2019 Group Presentation 03
28/29
Conclusion
Substation earthing grid design is a , Trial andError Procedure and Large No of parametersinvolved in the calculation. Therefore,Accurate computation of earthing behavior
under steady and transient conditions can onlybe achieved through advance computer basesoftware only.It has Ability to implement cost optimize design
where necessary. And also Advance featureslike stimulation for different cases can beeasily analyzed and modeled. So we highlyrecommended a advanced computer softwaresuch as MATLAB, ETAP, for the Grounding
Substation Design.
8/3/2019 Group Presentation 03
29/29
Thank You