15
Franz Peters, Georg Gassner WPM/HLS Status and Schedule [email protected]. edu June 17 th , 2008 1 WPM & HLS Status and Schedule Franz Peters, Georg Gassner SLAC / MET Reminder Hardware Status Schedule

Franz Peters, Georg Gassner WPM/HLS Status and [email protected] June 17 th, 2008 1 WPM & HLS Status and Schedule Franz Peters, Georg Gassner

Embed Size (px)

Citation preview

Page 1: Franz Peters, Georg Gassner WPM/HLS Status and Schedulefpet@slac.stanford.edu June 17 th, 2008 1 WPM & HLS Status and Schedule Franz Peters, Georg Gassner

Franz Peters, Georg GassnerWPM/HLS Status and Schedule [email protected]

June 17th, 20081

WPM & HLS Status and ScheduleFranz Peters, Georg Gassner SLAC / MET

WPM & HLS Status and ScheduleFranz Peters, Georg Gassner SLAC / MET

Reminder Hardware Status Schedule

Reminder Hardware Status Schedule

Page 2: Franz Peters, Georg Gassner WPM/HLS Status and Schedulefpet@slac.stanford.edu June 17 th, 2008 1 WPM & HLS Status and Schedule Franz Peters, Georg Gassner

Franz Peters, Georg GassnerWPM/HLS Status and Schedule [email protected]

June 17th, 20082

Reminder

Undulator Length = 132 Meter plus…

33 U-Segments need to be stable in a line within a few microns

X & Y- Motion of single U - Segments could be larger, eventually…

Vertical U-Position = f (Support temperature) = ~ 15 Micron/ºC

Unpredictable motions may occur by several reasons, as …

Undulator Length = 132 Meter plus…

33 U-Segments need to be stable in a line within a few microns

X & Y- Motion of single U - Segments could be larger, eventually…

Vertical U-Position = f (Support temperature) = ~ 15 Micron/ºC

Unpredictable motions may occur by several reasons, as …

Page 3: Franz Peters, Georg Gassner WPM/HLS Status and Schedulefpet@slac.stanford.edu June 17 th, 2008 1 WPM & HLS Status and Schedule Franz Peters, Georg Gassner

Franz Peters, Georg GassnerWPM/HLS Status and Schedule [email protected]

June 17th, 20083

WPM = Wire Position Monitor

HLS = Hydro Leveling System

Conductive wire is stretched (140 m) inside a conductive tube (8 mm)

RF Signal (CW) is transmitted along this air isolated “coaxial cable”

RF loops inside the tube. Loop currents determines the wire position

Conductive wire is stretched (140 m) inside a conductive tube (8 mm)

RF Signal (CW) is transmitted along this air isolated “coaxial cable”

RF loops inside the tube. Loop currents determines the wire position

Pipe ½ filled with water. Water surface used as common reference

Capacitive sensors measure the distances to this common reference

Ultrasonic sensor detects distance of surface to under water plains

Pipe ½ filled with water. Water surface used as common reference

Capacitive sensors measure the distances to this common reference

Ultrasonic sensor detects distance of surface to under water plains

Reminder

Page 4: Franz Peters, Georg Gassner WPM/HLS Status and Schedulefpet@slac.stanford.edu June 17 th, 2008 1 WPM & HLS Status and Schedule Franz Peters, Georg Gassner

Franz Peters, Georg GassnerWPM/HLS Status and Schedule [email protected]

June 17th, 20084

WPM measures:X & Y- Positions relative to two stretched wires

HLS measures:Y - Positions relative to the water surface

Common Task: X & Y Positon monitoring of U-Segments Resolution: < Micrometer Data rate: Every few minutes Operation: Continously, no drifts

116 mm111 mm

265 mmGoal: One micrometer stabilityThermally driven:15 micrometer / K

260

mm

245

mm

1400

mm

WPM & HLS will operate as one Alignment Diagnostic System, ADS

Reminder

Page 5: Franz Peters, Georg Gassner WPM/HLS Status and Schedulefpet@slac.stanford.edu June 17 th, 2008 1 WPM & HLS Status and Schedule Franz Peters, Georg Gassner

Franz Peters, Georg GassnerWPM/HLS Status and Schedule [email protected]

June 17th, 20085

Reminder

ADS Position sensors at the girders

360

562

375

130

26

0

90

265

550

60

470

80

93

60

Girder Girder

HLS pots

WPM supports

2" Pipe

115

Quadrupole

Beam

H2O Level

50

M10

M6M6

170

245 245

245

Upper wire

Lower wire

Wire position monitor

Left Right

Page 6: Franz Peters, Georg Gassner WPM/HLS Status and Schedulefpet@slac.stanford.edu June 17 th, 2008 1 WPM & HLS Status and Schedule Franz Peters, Georg Gassner

Franz Peters, Georg GassnerWPM/HLS Status and Schedule [email protected]

June 17th, 20086

ADS SensorsLeft to right:Wire Position Monitor- Four loops with SMA con.

Field distribution- 4 Loops around the wire

WPM gap view- Gap = 8 x 8 mm

Left to right:HLS Capacitive sensor- Shown, down side up

HLS Pot & Sensor- Pot with pipe adapter- Bracket to the girder- Sensor on top, ready to go

Page 7: Franz Peters, Georg Gassner WPM/HLS Status and Schedulefpet@slac.stanford.edu June 17 th, 2008 1 WPM & HLS Status and Schedule Franz Peters, Georg Gassner

Franz Peters, Georg GassnerWPM/HLS Status and Schedule [email protected]

June 17th, 20087

HLS Hardware

Water pipes and pots

Bellows

Ultrasonic sensor

Capacitive sensor

Water pipe inside girder

Page 8: Franz Peters, Georg Gassner WPM/HLS Status and Schedulefpet@slac.stanford.edu June 17 th, 2008 1 WPM & HLS Status and Schedule Franz Peters, Georg Gassner

Franz Peters, Georg GassnerWPM/HLS Status and Schedule [email protected]

June 17th, 20088

HLS Hardware

Integration of LTU beam line monitors Water refill station

Undulator

HLS Sensors

HLS Pipe

Beam dump

LTU beam line

WPM End station

Top view

HLS Sensors

HLS Pipe

Beam dump

LTU beam line

WPM End station

Undulator

Page 9: Franz Peters, Georg Gassner WPM/HLS Status and Schedulefpet@slac.stanford.edu June 17 th, 2008 1 WPM & HLS Status and Schedule Franz Peters, Georg Gassner

Franz Peters, Georg GassnerWPM/HLS Status and Schedule [email protected]

June 17th, 20089

WPM Hardware

Monitors at a short break sectionWire tube support system

Page 10: Franz Peters, Georg Gassner WPM/HLS Status and Schedulefpet@slac.stanford.edu June 17 th, 2008 1 WPM & HLS Status and Schedule Franz Peters, Georg Gassner

Franz Peters, Georg GassnerWPM/HLS Status and Schedule [email protected]

June 17th, 200810

WPM Hardware

Monitor cablingElectronics sub-station Wire position monitorMonitor signal cabling

U-1U-33

WPM Section 140 m

Undulator Segments Electronic Substation Initial Trajectory Section

E-2

Undulator Section 132 m

End Station

Beam direction

E-1

1 65

BPM s

123456

Signal cabling

Page 11: Franz Peters, Georg Gassner WPM/HLS Status and Schedulefpet@slac.stanford.edu June 17 th, 2008 1 WPM & HLS Status and Schedule Franz Peters, Georg Gassner

Franz Peters, Georg GassnerWPM/HLS Status and Schedule [email protected]

June 17th, 200811

WPM Hardware

Wire End Station< Wire terminals< Aluminum supports Anocast stands (Granite + Epoxy)

Wire vibration needs to be minimized! First harmonic frequency ~ 0.5 Hz Coupling to the ground is crucial…

Dis

tanc

e to

flo

or 1

400

mm

Beam pipe

265

265

140 m wires

SideView

FrontView

TOPView

Page 12: Franz Peters, Georg Gassner WPM/HLS Status and Schedulefpet@slac.stanford.edu June 17 th, 2008 1 WPM & HLS Status and Schedule Franz Peters, Georg Gassner

Franz Peters, Georg GassnerWPM/HLS Status and Schedule [email protected]

June 17th, 200812

HLS Status

HardwareLevel sensors 100% completed

Tube system 90% completed

Network & cables 80% completed

Sensor calibration 70% completed

HardwareLevel sensors 100% completed

Tube system 90% completed

Network & cables 80% completed

Sensor calibration 70% completed

SoftwareInterface with sensors completed and tested

Interface with LCLS controls defined and tested

Data exchange between data dump and analysis computer tested

Data analysis theory defined, but not coded

SoftwareInterface with sensors completed and tested

Interface with LCLS controls defined and tested

Data exchange between data dump and analysis computer tested

Data analysis theory defined, but not coded

Page 13: Franz Peters, Georg Gassner WPM/HLS Status and Schedulefpet@slac.stanford.edu June 17 th, 2008 1 WPM & HLS Status and Schedule Franz Peters, Georg Gassner

Franz Peters, Georg GassnerWPM/HLS Status and Schedule [email protected]

June 17th, 200813

WPM Status

Wire tube support system 100% completed

Local computers & ADC Interfaces 100% completed

Monitor signal cable assemblies 100% completed

Wire end stations & terminals 90 % completed

Wire position monitors 90% completed

Wire tubes & tube connections 90% completed

Local electronics stations 80% completed

Signal processing & Data acquisition 70% completed

Software, Application & Analysis 50 % completed

Wire tube support system 100% completed

Local computers & ADC Interfaces 100% completed

Monitor signal cable assemblies 100% completed

Wire end stations & terminals 90 % completed

Wire position monitors 90% completed

Wire tubes & tube connections 90% completed

Local electronics stations 80% completed

Signal processing & Data acquisition 70% completed

Software, Application & Analysis 50 % completed

Page 14: Franz Peters, Georg Gassner WPM/HLS Status and Schedulefpet@slac.stanford.edu June 17 th, 2008 1 WPM & HLS Status and Schedule Franz Peters, Georg Gassner

Franz Peters, Georg GassnerWPM/HLS Status and Schedule [email protected]

June 17th, 200814

ADS Schedule

Water tube system comes assembled with girders, installation June to 25/10/08

Installation of sensors and cable connections July to 25/10/08

HLS will be commissioned partly in sections of some girder July to November

Commissioning of entire HLS needs time after last girder is placed.

Water tube system comes assembled with girders, installation June to 25/10/08

Installation of sensors and cable connections July to 25/10/08

HLS will be commissioned partly in sections of some girder July to November

Commissioning of entire HLS needs time after last girder is placed.

HLS

Girders has to be in place, before wire tube installation can start June to 25/10/08

Installation of substations and cabling can be done any time July to 25/10/08

Due to stretched wires are needed, commissioning starts November 08

Pre-checks of the system will minimize, but not wipe out time for commissioning.

Girders has to be in place, before wire tube installation can start June to 25/10/08

Installation of substations and cabling can be done any time July to 25/10/08

Due to stretched wires are needed, commissioning starts November 08

Pre-checks of the system will minimize, but not wipe out time for commissioning.

WPM

In general

Schedule needs to be synchronized with installation of the Undulator SegmentsSchedule needs to be synchronized with installation of the Undulator Segments

Page 15: Franz Peters, Georg Gassner WPM/HLS Status and Schedulefpet@slac.stanford.edu June 17 th, 2008 1 WPM & HLS Status and Schedule Franz Peters, Georg Gassner

Franz Peters, Georg GassnerWPM/HLS Status and Schedule [email protected]

June 17th, 200815

End of Presentation