FOOTHILL MUNICIPAL WATER DISTRICT Recycled Water Project Board Workshop May 20, 2013

FOOTHILL MUNICIPAL WATER DISTRICT

Embed Size (px)

DESCRIPTION

FOOTHILL MUNICIPAL WATER DISTRICT. Recycled Water Project Board Workshop. May 20, 2013. Outline. Past /Present Drivers Project Background and Description Benefits Present Benefits and Partnerships Project Alternatives Hydrogeologic Modeling with Percolation Test - PowerPoint PPT Presentation

Citation preview

Page 1: FOOTHILL MUNICIPAL WATER DISTRICT

FOOTHILL MUNICIPAL WATER DISTRICT

Recycled Water Project

Board Workshop

May 20, 2013

Page 2: FOOTHILL MUNICIPAL WATER DISTRICT

2

Outline• Past /Present

– Drivers– Project Background and Description– Benefits

• Present– Benefits and Partnerships– Project Alternatives – Hydrogeologic Modeling with Percolation Test– CEQA Plus and Title 22– Raymond Basin Management Board

• Future – Budget and Funding– Schedule– Next Steps– Design Bid Build or Design Build Operate – Schedule

5/20/2013

Page 3: FOOTHILL MUNICIPAL WATER DISTRICT

3

Driver – Senate Bill SBX7-7 Water suppliers to increase water use efficiency

Urban Water Conservation Reducing per capita 10% by December 31, 2015 Reducing per capita 20% by December 31, 2020

Effective 2016 urban retail water supplies not meeting water conservation requirements are not eligible for State water grants and loans

The recycled water program assists in meeting this requirement

5/20/2013

Page 4: FOOTHILL MUNICIPAL WATER DISTRICT

4

Driver – Delta Conveyance Delta Steward Council – May 16, 2013

Adopted FINAL Delta Plan Certifies Programmatic EIR Adopted Regulations to Implement Policies of Delta Plan

Additional pressure for assurances to reduce reliance on Delta Conveyance Senate President pro Tem Darrell Steinberg Sunne McPeak from CA Emerging Technology Fund Environmental Groups

2nd Driest Year in Nor. Cal and Colorado River Potential Shortages in 2 to 3 years

5/20/2013

Page 5: FOOTHILL MUNICIPAL WATER DISTRICT

5

Background – 2007-2009

Weighting 1 0.9 0.9 1 1 0.9 0.8

Emergency Reliability

Rate Mitigation

Reliability of Infrastructure

Supply Shortage (Drought)

Environmental Impacts

Energy Use Greenhouse

Gases

Other Challenges

Priority

Second MWD Interconnection

3 1 3 1 4 2 3 15.8

Recycled Water 4 5 4 6 3 3 5 27.8

Groundwater 6 3 5 5 5 4 2 28.4

Partnering/Transfers (Desalination)

1 4 1 5 3 3 3 18.6

San Gabriel Pipeline 4 2 3 1 3 2 1 15.1

Conservation 2 4 2 3 6 6 5 25.8

Interties 4 5 4 1 5 4 4 24.9

Debris Basins 3 4 2 3 3 5 2 20.5

• Master Plan put on hold second interconnection• Water Resources Plan prioritized developing reliability

5/20/2013

Page 6: FOOTHILL MUNICIPAL WATER DISTRICT

6

Background – 2011 and 2012

• Feasibility study approved by SWRCB• Reviewed 17 Alternatives• Narrowed down to Alternative A-6, MBR

plant near Oak Grove Drive at 0.25 MGD recharge at John Muir High School

• Two Firms hired to develop then review regulations and costs

• Costs dropped based on less purple pipe

5/20/2013

Page 7: FOOTHILL MUNICIPAL WATER DISTRICT

7

Background - 2012• Cal Poly Pomona began working on

project in August 2012 – Field of Green• IRWMP process began in September

2012• November 2012 Board authorizes

proceeding with hydrogeologic evaluation, CEQA Plus, and Program Management services and payment of fee for grant application

5/20/2013

Page 8: FOOTHILL MUNICIPAL WATER DISTRICT

8

Background - 2013• January 2013 - Board adopted resolution

regarding WaterSMART Grant• March 2013 - Board authorized consulting

services for conceptual report for Title 22• March 2013 - Draft groundwater recharge

regulations changed • April 2013 - Labor Compliance resolution

adopted by Board• April 2013 - Board approved amendment to

hydrogeologic modeling agreement for two other modeling runs

5/20/2013

Page 9: FOOTHILL MUNICIPAL WATER DISTRICT

9

Recycled Water Use in Area• Los Angeles County Sanitation District

– La Cañada Flintridge Country Club• City of Glendale/LADWP

– Landscape Irrigation

• City of Burbank– Landscape Irrigation– Fire Fighting

• Descanso Gardens and City of Pasadena– Verdugo Hills Golf Course MBR

• Claremont Colleges MBR

5/20/2013

Page 10: FOOTHILL MUNICIPAL WATER DISTRICT

10

Description Watershed approach to developing recycled water

Construction of a 0.25 MGD MBR plant

Recharge to groundwater basin and receive credits

Stormwater and urban runoff capture, treatment, and recharge

Reduce carbon footprint and lower greenhouse emissions

Conservation and education outreach component

5/20/2013

Page 11: FOOTHILL MUNICIPAL WATER DISTRICT

115/20/2013

Project Alternatives

Page 12: FOOTHILL MUNICIPAL WATER DISTRICT

04/19/2023

12

Recycled Water Flow

Page 13: FOOTHILL MUNICIPAL WATER DISTRICT

13

Benefits of Recycled Water Project Enhance local supply and reduce dependency on

imported water

Reduction in greenhouse gases and energy usage

Demonstrate watershed approach to developing

local supplies and benefitting the community• Water Education

• Watershed Integrity and Health

• Public Outreach

Support of stakeholders – city, school, church,

Sanitation Districts, County Public Works5/20/2013

Page 14: FOOTHILL MUNICIPAL WATER DISTRICT

14

Quantified Benefits

Recharge Recycled Water: 280 AFY

Other Recharge: 38 AFY average

• Estimated Stormwater Capture: 15 AFY

• Estimated Urban Runoff Capture: 23 AFY

Barren Land: Half Acre Improvement

Energy Savings: 600 Megawatts

• Enough for 85 Southern California homes annually

5/20/2013

Page 15: FOOTHILL MUNICIPAL WATER DISTRICT

15

Project Details - Partnerships

La Cañada Unified School District and City of La Cañada Flintridge: Athletic fields Stormwater and urban runoff capture

Cal Poly Pomona: Civil Engineering Department, Department of Landscape Architecture and Department of Urban and Regional Planning Preparation of a 3D model of infiltration galleries Development of drought tolerant landscaping for both MBR and

LCHS sites Development of a conservation and educational component to the

Project Undergraduate Development

5/20/2013

Page 16: FOOTHILL MUNICIPAL WATER DISTRICT

16

Project Support Congresswoman Judy Chu Congressman Adam Schiff Assemblymember Mike Gatto Los Angeles County Supervisor Michael D. Antonovich Metropolitan Water District of Southern California Los Angeles County Sanitation District Los Angeles County Department of Public Works Council for Watershed Health Arroyo Seco Foundation La Cañada United Methodist Church La Cañada Unified School District City of La Cañada Flintridge Cal Poly Pomona

5/20/2013

Page 17: FOOTHILL MUNICIPAL WATER DISTRICT

17

Hydrogeologic Model• 3 areas modeled:

– Athletic fields– Flint Creek Wash– Behind Devil’s Gate Dam

• Results:– All 3 alternatives achieve CDPH minimum of

four months retention time from active wells.– All alternatives do not exceed the RWC of 20%

over a 120-month period.

5/20/2013

Page 18: FOOTHILL MUNICIPAL WATER DISTRICT

18

Hydrogeologic Model - Percolation Tests

5/20/2013

4 feet per day average percolation

Page 19: FOOTHILL MUNICIPAL WATER DISTRICT

19

CEQA Plus

• Initial Study to be distributed June via FMWD website, via email notice to Board packet distribution list which includes newspapers and blogs, public agencies, other entities

• Workshop will be scheduled for 30 days from release of document

• Recommended action at August Board meeting

5/20/2013

Page 20: FOOTHILL MUNICIPAL WATER DISTRICT

20

Title 22 – Conceptual Report

• Conceptual Report drafted on May 9, 2013• Provides:

– Summary key requirements or topics, – References to Title 22 and FMWD method of

compliance• All items are achievable - no fatal flaws

with the project

5/20/2013

Page 21: FOOTHILL MUNICIPAL WATER DISTRICT

21

Raymond Basin Management Board

• Originally stormwater and urban runoff to be captured was to be credited to account

• RBMB has stated no longer able to provide 100% credit

• RBMB willing to provide some capital contribution

5/20/2013

Page 22: FOOTHILL MUNICIPAL WATER DISTRICT

04/19/2023

22

Estimated Project Budget

Total: $2,935,300

Page 23: FOOTHILL MUNICIPAL WATER DISTRICT

23

Per Acre-Foot Cost

• Assume 280 Acre-feet of sales• Receive IRWMP and USBR grants• Principal = $1,185,300• 30 year term• 3.0% interest rate

Cost per Acre-foot = $810

5/20/2013

Page 24: FOOTHILL MUNICIPAL WATER DISTRICT

24

Per Acre-Foot Cost – Above Scenario

Year 1 Year 30

Recycled Water $810 $1,616

Groundwater Pumping $100 $236

Total $910 $1,852

5/20/2013

Year 1 Year 30

MWD Rate $917 $2,160

Main Plant Pumping $50 $118

Total $967 $2,278

Assume 3% inflation factor

Over time, difference increases from $57 per acre-foot to $426 per Acre-foot

Page 25: FOOTHILL MUNICIPAL WATER DISTRICT

255/20/2013

Year 1

Year 3

Year 5

Year 7

Year 9

Year 11

Year 13

Year 15

Year 17

Year 19

Year 21

Year 23

Year 25

Year 27

Year 29

$-

$500

$1,000

$1,500

$2,000

$2,500 Comparison of Recycled Water and Imported Water Costs

Recycled Water Cost Avoided Imported Water Cost

Do

llars

First year sav-ings is about

$57/AF

Year 30 sav-ings is about

$425/AF

• 280 AF sales• $1.5 million IRWMP Grant• $300,000 USBR Grant

Page 26: FOOTHILL MUNICIPAL WATER DISTRICT

26

IRWMP Grant

• Initial presentation September 2012 • For $1.45M• Ranked #1 in Subregion and #3 in Region• Application submitted to State in March

2013• 50% of capital costs of approximately $3

million• Results October 2013

5/20/2013

Page 27: FOOTHILL MUNICIPAL WATER DISTRICT

27

USBR WEEG Grant

• Submitted grant January 2013• For $300,000• Only infiltration galleries portion• Recycled water plant construction not

allowed under this type of grant• Results June 2013

5/20/2013

Page 28: FOOTHILL MUNICIPAL WATER DISTRICT

28

Other Potential Funding USBR

Title XVI Program CalFed Funding

MWD LRP - Up to $250/AF of production MWD Foundational Action Funding Program - $500k

SWRCB Low Interest Loans iBank Low Interest Loans Internal FMWD Funding

• Water Sales• District Revenues/Reserves

5/20/2013

Page 29: FOOTHILL MUNICIPAL WATER DISTRICT

29

Current Status• Feasibility Study Completed – accepted by SWRCB• Percolation Testing – complete• Basin Hydrogeologic Modeling – complete• CEQA – in process• Title 22 Conceptual Report – in progress• WEEG application submittal – complete• IRWMP application submittal – complete• Fields of Green project – complete• Appraisal for easement – complete• Status meetings with various entities – in progress• Contract negotiations – in progress

5/20/2013

Page 30: FOOTHILL MUNICIPAL WATER DISTRICT

30

Next Steps• Release Initial Study - Late June• Public Hearing - Mid July• CEQA Finalization - August Brd. Mtg• Finalize agreements for

– Raymond Basin Management Board– Los Angles County Sanitation District– La Cañada United Methodist Church– La Cañada Unified School District

• Sampling of LACSD Sewer for Preliminary Design

5/20/2013

Page 31: FOOTHILL MUNICIPAL WATER DISTRICT

31

Preliminary Design• 30% Design• Scope of Services

– Treatment (Primary, Secondary, Tertiary)– Chemical Feed System– Instrumentation and Controls– Hydraulics– Site Layout– Design Standards– Architectural Programming– Discharge Design– Cost Estimate– Project Delivery Recommendation (DBBO or DBO)

5/20/2013

Page 32: FOOTHILL MUNICIPAL WATER DISTRICT

32

Implementation ScheduleProject Element Start Date End Date

Development/Finalize External Funding

July 2012 September 2013

Environmental Documentation (CEQA)

December 2012 June 2013

Partnership Agreements November 2012 November 2013

Title 22 Report March 2013 September 2013

Preliminary Design July 2013 February 2014

Final Design Solicitation and Completion

April 2014 October 2014

Permitting February 2014 February 2015

Construction Bidding October 2014 April 2015

Construction and Start Up

May 2015 June 2016

Operation October 2016 -

5/20/2013