27
1 EXECUTIVE SUMMARY REPORT OF CEIA STUDY FOR MOHANPURA IRRIGATION PROJECT 1. GENERAL The Water Resources Department, state government of Madhya Pradesh envisages to develop Mohanpura dam, near village Banskhedi in district Rajgarh. The dam is proposed constructed across river Newaj. The catchment area intercepted at the dam site is 3726 sq. km. The proposed Mohanpura dam proposes to provide water for irrigation, domestic and industrial uses. The project location map is enclosed as Figure-1. 2. PROJECT DESCRIPTION The key features of the project are a 1361 m long earthen dam on left flank and 875 m long on right flank. The GCA of the Mohanpura project is 92860 ha in Rajgarh and Khilichipur tehsils of Rajgarh district. It is proposed to irrigate about 35500 ha Kharif and 62250 ha of Rabi season. The index map of the project showing the dam and canal distribution system is enclosed as Figure-2. The land required for various project components is of about 7,348 ha. The details are given in Table-1. Table-1: Details of land to be acquired for the project S. No. Project Name Revenue Land (ha) Private Land (ha) Total (ha) 1. Dam & Reservoir 1888 5163 7051 2. Canal Network 46 106 152 3 Colony & Approach Road and other project components 13 - 13 4 Resettlement and Rehabilitation 132 - 132 Total 2079 5269 7348 3. STUDY AREA The study area covered as a part of the EIA study is as below (Refer Figure-3). Submergence area Area to be acquired for various project appurtenances Area within 10 km of various project appurtenances including i.e. canal network, etc. Gross Command Area Catchment Area intercepted at the dam site 4. ENVIRONMENTAL BASELINE STATUS The baseline status for the above referred categories has been described in the following sections.

Final Ex. Summary - Mohanpura Project · Xanthium strumarium, Argemone mexicana, Cynodon dactylon, Saccharum munja, etc. Floristics During floristic survey in the Pre-Monsoon, Monsoon

  • Upload
    others

  • View
    2

  • Download
    0

Embed Size (px)

Citation preview

Page 1: Final Ex. Summary - Mohanpura Project · Xanthium strumarium, Argemone mexicana, Cynodon dactylon, Saccharum munja, etc. Floristics During floristic survey in the Pre-Monsoon, Monsoon

1

EXECUTIVE SUMMARY REPORT OF CEIA STUDY FOR MOHANPURA

IRRIGATION PROJECT

1. GENERAL

The Water Resources Department, state government of Madhya Pradesh envisages

to develop Mohanpura dam, near village Banskhedi in district Rajgarh. The dam is

proposed constructed across river Newaj. The catchment area intercepted at the dam

site is 3726 sq. km. The proposed Mohanpura dam proposes to provide water for

irrigation, domestic and industrial uses. The project location map is enclosed as

Figure-1.

2. PROJECT DESCRIPTION

The key features of the project are a 1361 m long earthen dam on left flank and 875

m long on right flank. The GCA of the Mohanpura project is 92860 ha in Rajgarh and

Khilichipur tehsils of Rajgarh district. It is proposed to irrigate about 35500 ha Kharif

and 62250 ha of Rabi season. The index map of the project showing the dam and

canal distribution system is enclosed as Figure-2.

The land required for various project components is of about 7,348 ha. The details

are given in Table-1.

Table-1: Details of land to be acquired for the project

S. No. Project Name Revenue

Land (ha)

Private

Land (ha)

Total (ha)

1. Dam & Reservoir 1888 5163 7051

2. Canal Network 46 106 152

3 Colony & Approach Road and other project components

13 - 13

4 Resettlement and Rehabilitation 132 - 132

Total 2079 5269 7348

3. STUDY AREA

The study area covered as a part of the EIA study is as below (Refer Figure-3).

• Submergence area

• Area to be acquired for various project appurtenances

• Area within 10 km of various project appurtenances including i.e. canal network, etc.

• Gross Command Area

• Catchment Area intercepted at the dam site

4. ENVIRONMENTAL BASELINE STATUS

The baseline status for the above referred categories has been described in the

following sections.

Page 2: Final Ex. Summary - Mohanpura Project · Xanthium strumarium, Argemone mexicana, Cynodon dactylon, Saccharum munja, etc. Floristics During floristic survey in the Pre-Monsoon, Monsoon

2

4.1 PHYSCIO-CHEMICAL ASPECTS

4.1.1 Meteorology

The project area of the proposed Mohanpura Irrigation project experiences semi-arid

climate characterized by hot summer, pleasant cold winter and general dryness

throughout the years, except during monsoon season. The year may be divided into

four seasons. The summer season lasts from March to about middle of June, followed

by the south-west monsoon season from mid-June to the end of September. October

and November constitute the post monsoon or transition period. The winter season is

observed from December to February.

4.1.2 Geology and Sesimicity

The Mohanpura dam site on river Newaj sub-basin is in Malwa Plateau of western

Madhya Pradesh which is characterised by a typical trappean topography comprising

extensive plains. The region is occupied by rocks of two chronologically different

geological domains. The upper most sequence comprises thick cover of basaltic lava

flows and associated inter trappeans of the Deccan trap complex covering the

sedimentary sequence of Vindhyan super group.

Seismically, the area has not experienced any major geological event in the recent

past. Being located in a flat/peneplained country, the risks of other natural hazards

are minimal.

4.1.3 Soils

The pH in soils of the command area lies within neutral range, i.e. 6.5 to 8.5. The

Electrical Conductivity indicates that salt concent is low in the soils. The

concentration of Available Potassium, Available Nitrogen and Available Phosphorus

ranged from 90 to 174 kg/ha, 210 to 322 kg/ha, 9 to 22 kg/ha. The concentration of

various nutrients indicate low to moderate productivity. The bulk density ranged

form 1.15 to 1.33 g/cc. The porosity ranged from 45 to 61% and a distinct

correlation was observed with soil texture and bulk density. The increase in bulk

density was reflected in the lower porosity in various samples.

4.1.4 Surface Water Quality

The pH level indicates that water is in neutral range. The total hardness in various

water samples ranged from 120 to 122 mg/l, 76.8 to 78.0 mg/l and 108.5 to 110

mg/l in pre-monsoon, monsoon and winter seasons respectively. The total hardness

level in surface water sample is well below the permissible limit of 200 mg/l,

specified for meeting drinking water requirement. The TDS level ranged from 278 to

282 mg/l, 145 to 152 mg/l and 219 to 226 mg/l in pre-monsoon, monsoon and

Page 3: Final Ex. Summary - Mohanpura Project · Xanthium strumarium, Argemone mexicana, Cynodon dactylon, Saccharum munja, etc. Floristics During floristic survey in the Pre-Monsoon, Monsoon

3

winter seasons respectively. The TDS levels were well below the permissible limit of

500 mg/l. The EC levels were well below the permissible limit of 2250 µS/cm

specified for irrigation water requirements as pr IS:2296. This indicates the

suitability of water for meeting irrigation and drinking water requirements. The BOD

and COD values are well within the permissible limits, which indicates the absence of

organic pollution loading.

4.1.5 Ground Water Quality

pH level in various groundwater samples in various seasons was observed to be with

neutral range 6.5 to 8.5. This indicates neutral nature of the water, and are within

the permissible limit specified for meeting drinking and irrigation water requirements

The total hardness in various ground water samples ranged from 50 to 279 mg/l, 50

to 235 mg/l and 50 to 265 mg/l in pre-monsoon, monsoon and winter seasons

respectively. The total hardness level in various groundwater samples were higher

than the permissible limit of 200 mg/l, specified for meeting drinking water

requirement. The alkalinity was found to be higher than the total hardness in all the

water sampling stations monitored as a part of the study, which indicates that the

entire hardness is contributed by carbonate hardness. The TDS level ranged from

196 to 876 mg/l, 105 to 410 mg/l and 152 to 810 mg/l in pre-monsoon, monsoon

and winter seasons respectively. The TDS levels were well above the permissible and

cause of rejection limits of 500 mg/l and 1500 mg/l respectively. This trend is also

reflected in the concentration of various ations and anions as well.

The BOD an COD values are well within the permissible limits, which indicates the

absence of pollution loading in the study area.

4.1.6 Ambient Air Quality

As a part of the field studies, various ambient air quality was monitored at various

locations. Based on the findings of the ambient air quality monitoring, it can be

concluded that the ambient air quality is quite good in the area. Values of

parameters, e.g. SO2 and NOx were well within the permissible limits specified for

residential, rural and other areas. However, at one location RPM value was found to

be higher than the permissible limit of 100 µg/m3 for residential, rural and other

areas.

4.1.7 Noise Environment

The day time equivalent noise level at various sampling stations were observed to be

well within the permissible limits specified for residential area.

Page 4: Final Ex. Summary - Mohanpura Project · Xanthium strumarium, Argemone mexicana, Cynodon dactylon, Saccharum munja, etc. Floristics During floristic survey in the Pre-Monsoon, Monsoon

4

4.1.8 Land use pattern

The land use pattern of the command area is given in Table-2.

Table-2 : Landuse pattern of the command area of Mohanpura Irrigation

project

Type of land Area

(ha)

Percentage of command

area

Vegetation 6962 7.50

Scrubs and grasslands 15226 16.40

Barren 28413 30.60

Agriculture 39388 42.42

River/ Water bodies 2067 2.23

Exposed Rock 612 0.66

Built-up area 190 0.20

Total 92860 100.0

Note : Figure in parenthesis indicate percentage.

The major landuse category in the command area of Mohanpura irrigation projectis

agriculture land, as it accounts for about 42.42% of the total area. The area under

vegetation is only 7.5% of the command area. Barren land and Built-up

land/exposed area account for about 30.6% and 0.20%, respectively of the total

command area. The area under water bodies is only 2.23% of the command area of

Mohanpura Irrigation Project.

4.2 ECOLOGICAL ASPECTS

4.2.1 Vegetation

The type of vegetation met within a given area depends on climate, soil and the

nature past treatment. Broadly speaking based on altitude, the study area falls under

tropical forests. As per Champion and Seth (1968) Classification, the following forest

types were encountered in the project area:

I. Group 5. Dry tropical forests

E1. Tropical dry deciduous forest

DS1. Anogeissus pendula scrub (5/E1/DS1):

II. Group 6. Tropical thorn forests

6B. Northern tropical forests

C2. Ravine thorn forests (6B/C2)

DRY TROPICAL FORESTS (5/E1/DS1): There is a considerable intermixture of

smaller trees which in this type form part of the main canopy layer. There is usually

thin shrubby undergrowth including some evergreen xerophytic species. Bamboo

species planted or natural are leafless during summer season. The commonly

observed tree species are Acacia catechu, Anogeissus pendula, Acacia pennata,

Page 5: Final Ex. Summary - Mohanpura Project · Xanthium strumarium, Argemone mexicana, Cynodon dactylon, Saccharum munja, etc. Floristics During floristic survey in the Pre-Monsoon, Monsoon

5

Feronia limonia, Madhuca indica, Butea monosperma, Azadiractha indica, Mangifera

indica, Aegale marmelos, etc. The shrub communities include species like Cassia

tora, Calotropis procera, Solanum xanthocarpum, Carica carranda, Vitex negundo,

etc. The herbaceous species of these types of forests recorded includes Achynathus

aspera, Xanthium strumarium, Cynodon dactylon, Saccharum munja, etc.

TROPICAL THORN FORESTS FORESTS (6B/C2): An open low forest in which

thorny usually hardwooded species predominate, Acacia catechu-Acacia nilotica-

Phoenix humalis species association, being particularly characteristics of this type of

forests. There is usually a thin grass growth during monsoon season, but more or

less, soil is barren. The main tree species reported in the area include Acacia

catechu, Acacia nilotica, Holarrhena pubescens, Butea monosperma, Diospyros

melanoxylon, Ficus bengalensis, Azadirachta indica, etc. The dominant shrub species

are Calotropis procera, Vitex negundo, Zizyphus nummularia, Cassia tora,

Achyranthus aspera, Solanum xanthocarpum, etc. The herbaceous flora include

Xanthium strumarium, Argemone mexicana, Cynodon dactylon, Saccharum munja,

etc.

Floristics

During floristic survey in the Pre-Monsoon, Monsoon Season and Winter season,

maximum number of plant species recorded during the monsoon season. In Pre-

Monsoon Season, a total of 103 plant species were recorded from the Mohanpura

Major Irrigation Project. Of these, 49 species are trees, 27 are shrubs, 19 herbs, 1

bamboo and 7 climbers. No epiphytic, parasitic and gymnosperm species recorded

from the study area in this season.

In Monsoon Season, a total of 177 plant species were recorded, which is the

maximum number of plant diversity in the project area. Of these, 49 species are

trees, 27 are shrubs, 87 herbs, 1 bamboo and 12 climbers.

During the floristic survey in Winter season, a total of 128 plant species were

recorded from the Mohanpura Major Irrigation Project. Of these, 49 species are

trees, 27 are shrubs, 39 herbs, 2 bamboo and 10 climbers. No epiphytic, and

gymnosperm species recorded from the study area.

4.2.2 Fauna

The project command is virtually devoid of any forests, with high degree of human

interferences. No major wildlife is observed in the area. The commonly observed

faunal species in the area are Common Jungle Cat, Jackal, rat, Wild Boar, etc.

Page 6: Final Ex. Summary - Mohanpura Project · Xanthium strumarium, Argemone mexicana, Cynodon dactylon, Saccharum munja, etc. Floristics During floristic survey in the Pre-Monsoon, Monsoon

6

4.2.3 Fisheries

Some important fishes genera which have been identified are Catla sp, Labeo spp,

Cirrihinus sp, Clarius sp, Mystus sp, Rita sp, Heteropneuptus sp., Notopterus spp,

Channa spp, Mastacembelus sp, Rasbora sp, Wallago sp. present in the region.

4.3 SOCIO-ECONOMIC ASPECTS

4.3.1 Demographic profile

The total population of the command area as about 1.71 lakhs. The male and female

population is 82,400 and 83,150. The number of females per 1000 males is 1009.

The percentage of SC and ST Population is 15.76% and 3.82% respectively. The

overall literacy rate in the command area tehsils is 38.57%. It is observed that total

main workers in the command area are 81777 accounting for about 47.6% of the

total population. The remaining (52.4%) are the dependent population. The major

occupation in the command area is agriculture.

4.3.2 Agriculture

The major crops grown in the command area are oil seeds, which account for about

54.43% of the total cropped area. Cereals and Pulses are grown over 19.18% and

1.63% of the total cropped area. The cropping pattern is a clear indicator of the lack

of water availability for irrigation in the command area.

5. PREDICTION OF IMPACTS

The impacts on various aspects of environment are briefly described in the following

sections.

5.1 IMPACTS ON LAND ENVIRONMENT

a) Construction Phase

Environmental degradation due to immigration of labour population

The peak labour and technical staff congregation would be of the order of 2000 and

500 respectively. The total increase in population shall be of the order of 6,200.

Separate accommodation and related facilities for workers, service providers and

technical staff are to be provided as a part of the project. The congregation of labour

force is likely to create problems of sewage disposal, solid waste management and

felling of trees for meeting fuel requirements, etc.

Operation of construction equipment

During construction phase, various types of equipment will be brought to the site.

These include batching plant, earth movers, etc. The siting of these construction

equipment would require significant amount of space. In addition, land will be

required for storage of various construction material as well. However, land for this

Page 7: Final Ex. Summary - Mohanpura Project · Xanthium strumarium, Argemone mexicana, Cynodon dactylon, Saccharum munja, etc. Floristics During floristic survey in the Pre-Monsoon, Monsoon

7

purpose will be temporarily acquired, i.e. for the duration of project construction

phase.

Efforts must be made for proper siting of these facilities. Various criteria for selection

of these sites would be:

• Proximity to the site of use • Sensitivity of forests in the nearby areas

• Proximity from habitations

• Proximity to drinking water source

Soil erosion

The runoff from various construction sites, will have a natural tendency to flow

towards along with the natural drainage. Thus, the disposal of drainage effluent with

such high turbidity levels is bound to affect the water quality, especially in the lean

season. The drains/nallahs close to various construction sites along the canal

alignment are seasonal in nature. Normally in such rivers biological productivity is

not high. Hence, the increase in turbidity levels are not expected to be significant in

nature.

b) Operation Phase

Acquisition of land

The tentative total land required for various project components is of about 7,348

ha. About 2079 ha of government land and 5269 ha of private land is to be acquired.

No forest land is to be acquired for the project. Based on the ownership status of the

land of the land to be acquired, appropriate compensatory measures have been

formulated.

Change in land use pattern

The GCA and ICA of the project are 82625 ha and 75,000 ha respectively. At

present, the cropped area in CCA is 79,950 ha, which will increase to 97,750 ha in

project operation phase. Thus, about 17,800 ha which at present is barren, would be

cropped during project operation phase. This would increase the agriculture

production in the command area and is a significant positive impact. The details of

cropped area during pre-project and project operation phase are given in Table-3.

Table-3: Cropped area during pre-project phase

Name of the crop Area under cultivation (ha)

Pre-project Post-project

Kharif

Soyabean 21300 35500

Sub-total(A) 21300 35500

Rabi

Hybrid Wheat 21750 36250

Page 8: Final Ex. Summary - Mohanpura Project · Xanthium strumarium, Argemone mexicana, Cynodon dactylon, Saccharum munja, etc. Floristics During floristic survey in the Pre-Monsoon, Monsoon

8

Name of the crop Area under cultivation (ha)

Pre-project Post-project

Ordinary Wheat 7800 13000

Gram 7800 13000

Sub-total( B) 58650 62250

Total (A+B) 79950 97750

5.2 IMPACTS ON WATER RESOURCES AND QUALITY

a) Construction Phase

Impacts due to sewage generation from labour camps

The construction phase also leads to mushrooming of various allied activities to meet

the demands of the immigrant labour population in the project area. The increase in

the population is expected to be of the order of 6,200. The labour population is likely

to be congregated at three to four labour colonies.

The total domestic water requirements of the labour population (including families) is

expected to be of the order of 0.837 mld @ 135 lpcd. It is assumed that about 80%

of the water supplied will be generated as sewage. Thus, the total quantum of

sewage generated is expected to be of the order of 0.67 mld. The total BOD load

contributed by various labour camps/colonies will be about 225 kg/day. The above

pollution loading is likely to be spread over 3 to 4 labour camps. The disposal of

sewage without treatment could lead to adverse impacts on land environment or

water environment in which the effluent from the labour camps/colonies are

disposed.

Impacts due to runoff from construction sites

Substantial quantities of water would be used in the construction activities. With

regards to water quality, waste water from construction activities would mostly

contain suspended impurities. Adequate care should be taken so that excess

suspended solids in the wastewater are removed before discharge into water body.

b) Operation Phase

Impacts on downstream users

The total water requirement for irrigation of command of Mohanpura Irrigation

project is 350.37 Mm3 The surface water and groundwater availability in the project

area are 794 Mm3 and 79.4 Mm3. The total water availability works out to 873.40

Mm3. The total surface water requirements upstream of Mohanpura dam is of the

area of 293.038 Mm3. The details are given as below:

• Irrigation requirement of constructed medium. Minor and : 253.038 Mm3

Page 9: Final Ex. Summary - Mohanpura Project · Xanthium strumarium, Argemone mexicana, Cynodon dactylon, Saccharum munja, etc. Floristics During floristic survey in the Pre-Monsoon, Monsoon

9

Proposed projects

Domestic use : 10 Mm3 • Industrial use : 20 Mm3

• Environmental and Ecological requirements : 10 Mm3

The total upstream of use of groundwater is 60 Mm3. The net water available at dam

site is (873.40 – 293.038 – 60) 520.362 Mm3. About 68.308 Mm3 of water will be

available by regeneration from various sources including irrigation, domestic and

industrial use.

The storage capacity of Mohanpura Reservoir is 539.42 Mm3. The downstream water

requirements are 13.2 Mm3, which includes water requirement for environmental and

ecological balance (52 Mm3) drinking water including reservoir & supply losses (20

Mm3) and industrial use (60 Mm3). Considering irrigation water requirements as

350.37 Mm3, the water available for miscellaneous use and for providing irrigation in

drought year for Kharif crop (539.42 – 52.20 – 60 – 350.37) shall be 57.05 Mm3.

Impacts on waterlogging and soil salinity

The total water requirement during Kharif and Rabi seasons is 332.097 Mm3 over an

irrigated command of 75,0000 ha. This works out to an average water depth of 443

mm. The area irrigated under ponded and pressure irrigation is 67,500 and 7,500 ha

respectively. The irrigated water not being utilized in ponded irrigation is

(0.46*67,500 ha*0.443m) 137.55 Mm3. The irrigated water not being utilized in

pressure irrigation is (0.20*7,500 ha*0.443m) 6.65 Mm3. The total irrigation water

being infiltrated into ground waster is 144.2 Mm3. For an irrigated command of

65,0000 ha, the average depth of water being wasted works out to an average water

depth of 192 mm. The quantum of water not being utilized is quite small and is not

expected to cause any significant problem of waterlogging.

Changes in water quality due to increased use of fertilizers

With the introduction of irrigation, use of fertilizers is likely to increase, to maintain

the increased levels of production. The drainage system (natural or man-made) is

likely to contain much higher level of nutrients. The climatic conditions in the project

area too is suitable for the proliferation of eutrophication in the project area. Thus, in

the project operation phase, there will be increased probability of eutrophication in

the water bodies receiving agricultural runoff. As a part of Environmental

Management Plan, appropriate control measures have been recommended.

Page 10: Final Ex. Summary - Mohanpura Project · Xanthium strumarium, Argemone mexicana, Cynodon dactylon, Saccharum munja, etc. Floristics During floristic survey in the Pre-Monsoon, Monsoon

10

Impacts due to effluent from project colony

It is proposed to provide biological treatment facilities including secondary treatment

units for sewage so generated from the project colony. This will ensure that there

are no adverse impacts due to disposal of effluents from the labour colony.

5.3 IMPACTS ON TERRESTRIAL ECOLOGY

a) Construction Phase

Flora

Workers and other population groups residing in the area may use fuel wood (if no

alternate fuel is provided) for whom firewood/coal depot could be provided. In

absence of alternative source of fuel, the labour population would resort to cutting of

trees and vegetation in areas close to various construction sites. Hence, to minimize

such impacts, it shall be mandatory for the contractor to provide fuel to labour

population.

Fauna

During construction phase, a large number of machinery and construction labour will

have to be mobilized. This activity may create some disturbance to the wildlife

population. The forest area shall not be covered for irrigation. The area which is to

be irrigated, and comprises mainly of agriculture land interspersed with settlement.

As a result of absence of forest or vegetal cover in the command area and increased

level of human interferences in the area, wildlife is generally absent in the area.

b) Operation Phase

Impacts on vegetal cover

No forest area is to be acquired for the project. However, as a part of field studies,

ecological survey was conducted at three locations in the submergence area, which is

spread over an area of 7051 ha. The details of total species at various sampling sites

in submergence area are given in Table-4.

Table-4: Details of floral species at various sampling sites in submergence area

Site Dominant species Tree

density

(no/ha) Trees Shrubs Herbs

Submergence

site-I

Jatropha

curcas, Butea monosperma,

Acacia

catechu

Lantana

camara, Sida

rhombifolia,

Achyranthes aspera,

Vitex

Saccharum

munja, Cassia tora,

Xanthium

strumarium

124

Page 11: Final Ex. Summary - Mohanpura Project · Xanthium strumarium, Argemone mexicana, Cynodon dactylon, Saccharum munja, etc. Floristics During floristic survey in the Pre-Monsoon, Monsoon

11

Site Dominant species Tree

density

(no/ha) Trees Shrubs Herbs

nugundo

Submergence

site-II

Butea

monosperma, Acacia

catechu,

Madhuca indica

Lantana

camara, Cassia

occidentalis,

Sida rhombifolia,

Achyranthes

aspera, and Vitex

nugundo

Saccharum

munja, Cassia tora,

Xanthium

strumarium Argemone

mexicana

104

Submergence site-III

Butea monosperma,

Acacia

catechu

Lantana camara,

Cassia

occidentalis, Calotropis

procera, Achyranthes

aspera, and

Vitex nugundo

Saccharum munja,

Cassia tora,

Xanthium strumarium,

Andrographis paniculata

84

It can be seen from Table-4 that Butea monosperma, Acacia catechu, Jatropha

curcas and Madhuca indica were the dominant tree species. Amongst shrubs,

Lantana camara, Cassia occidentalis, Sida rhombifolia, Achyranthes aspera, and

Vitex nugundo were the dominant species. The dominant herbaceous species in the

submergence area were Saccharum munja, Cassia tora, Xanthium strumarium

Argemone Mexicana. The tree density ranged from 84 to 124 per ha, which is quite

low. No Rare, Endangered or Threatened species are reported in the project area.

The tree density at various sampling sites in the submergence area ranged from 104

to 124 tree/ha. Normally in a dense forest, tree density is of the order of 1000-1200

trees/ha. Thus, land to be acquired in reservoir submergence tree density is low.

The introduction of irrigation in the area will increase the agriculture production of

the area, leading to the increased availability of fodder as a result of increased

agricultural by products and residues. The increased level of fodder availability would

Page 12: Final Ex. Summary - Mohanpura Project · Xanthium strumarium, Argemone mexicana, Cynodon dactylon, Saccharum munja, etc. Floristics During floristic survey in the Pre-Monsoon, Monsoon

12

reduce the presence on existing pasture and vegetal cover, which is a significant

positive impact.

Impacts on wildlife

The area to be brought under irrigation within the command area shall be devoid of

forests. The project area is interspersed with settlements and agricultural land. In

such settings large scale faunal population is not observed. Thus, no significant

impact on wildlife is anticipated due to the project.

The increase in vegetal cover would improve the organic content of the soils. As a

result microbial activity would improve, leading to increase in the type and number

of micro-organisms observed in the soils of the command area. This in the long run

is expected to improve the soil fertility.

Impacts due to excavation of construction material from river bed

During the construction phase a large quantity of construction material like stones,

pebbles, gravel and sand would be needed. Significant amount of material is

available in the river bed. It is proposed to extract construction material from borrow

areas in the river bed. The extraction of construction material may affect the river

water quality due to increase in the turbidity levels.

5.4 IMPACTS ON AQUATIC ECOLOGY

Impacts on fisheries potential

The proposed project would increase the water availability in the command area. As

a result, there will be increase in potential for tank and pond fisheries. Currently,

within the command area, tank and pond fisheries is in vogue. With the increased

availability of water the tank and fisheries potential would improve. The average fish

yield is of the order of 1 to 2 tonnes/ha/yr in fishing ponds. Thus, with introduction

of extensive culture, the fish production is expected to increase, which is a significant

positive impact.

5.5 IMPACTS ON NOISE ENVIRONMENT

a) Construction Phase

Noise due to construction equipment

In a water resource project, the impacts on ambient noise levels are expected due to

operation of construction equipment. It is a known fact that there is a reduction in

noise level as the sound wave passes through a barrier. Thus, no increase in noise

levels is anticipated as a result of various activities, during the project construction

phase. There could be marginal impacts on the population residing in proximity to

the canal alignment during construction phase as a result of various activities.

Page 13: Final Ex. Summary - Mohanpura Project · Xanthium strumarium, Argemone mexicana, Cynodon dactylon, Saccharum munja, etc. Floristics During floristic survey in the Pre-Monsoon, Monsoon

13

However, based on past experience in similar projects, the impact however, is not

expected to be significant.

5.6 IMPACTS ON AIR QUALITY

a) Construction Phase

Pollution due to fuel combustion in various equipment

The operation of various construction equipment requires combustion of fuel.

Normally, diesel is used in such equipment. The major pollutant which gets emitted

as a result of diesel combustion is SO2. The SPM emissions are minimal due to low

ash content in diesel. The short-term increase in SO2, even assuming that all the

equipment are operating at a common point, is quite low, i.e. of the order of less

than 1µg/m3. Hence, no major impact is anticipated on this account.

Fugitive Emissions from various sources

During construction phase, there will be increased vehicular movement. Lot of

construction material like sand, fine aggregate is stored at various sites, during the

project construction phase. Normally, due to blowing of winds, especially when the

environment is dry, some of the stored material can get entrained in the

atmosphere. However, such impacts are visible only in and around the storage sites.

The impacts on this account are generally, insignificant in nature.

5.7 INCREASED INCIDENCE OF WATER-RELATED DISEASES

a) Construction Phase

During construction phase or for permanent settlement, if adequate precautions are

not taken, the vector-borne disease epidemiology may show sudden or long lasting

change. Many of the immigrant population could be reservoir of infection for various

communicable diseases. Once they settle in labour camps/colonies, there could be

increased incidence of various diseases. This aspect needs to be looked into with

caution, and efforts must be made to ensure that a thorough check up of the labour

population congregating in the area is conducted. Those affected by any ailments

need to be properly quarantined depending on the ailment with which they are

suffering.

b) Operation Phase

Increased incidence of water-related diseases

The association between irrigation development and the incidence of water related

diseases such as malaria, etc is well established. The available data clearly indicates

that the major water related diseases prevalent in the project area are malaria and

gastroenteritis. The preferred environmental setting for vectors is fresh water open

Page 14: Final Ex. Summary - Mohanpura Project · Xanthium strumarium, Argemone mexicana, Cynodon dactylon, Saccharum munja, etc. Floristics During floristic survey in the Pre-Monsoon, Monsoon

14

to sunshine or moderate shade. The habitats for larvae growth are permanent or

semi-permanent standing fresh water such as small ponds, pools, standing

agricultural water, permanent or semi-permanent fresh water such as open stretches

or canals. Thus, the project may create favorable conditions for breeding of new

pathogens or vectors such as mosquitoes, etc. The experience of various project

confirms the above mentioned hypothesis. In the project area, a sudden spurt in the

incidence of malaria is expected, if adequate control measures are not taken up.

Improvement in availability of water for various uses, increased agricultural

production, availability of diversified food, strengthening of educational and health

facilities significantly improves public health in the project area. On the other hand,

water resources development also has negative impacts, since, it could increase the

habitat of certain vectors like mosquitoes. Thus, poorly planned and managed water

resources projects could increase the prevalence of vector-borne diseases like

malaria and filariasis.

5.8 IMPACTS DUE TO COMMAND AREA DEVELOPMENT

Increased income Level

The total profit from agriculture production would increase from Rs. 1264.65 miliion

per year at pre-project level to Rs. 4678.46 million per year in project operation

phase. Thus there will be an increase in total profit from agriculture production by

about Rs. 3413.81 miliion per year. The increase in income level is a significant

positive impact. The net profit shall increase from pre-project land of Rs. 21,500 per

ha to Rs. 47,953 per ha. Thus, the project will play a significant role in poverty

alleviation in the project area.

The increased income levels will have a quantitative effect on the quality of demand

for various facilities, which will facilitate improvement in the infrastructure sector.

The increased income levels would lead to demands for better communication,

health, education and other services. The increased income levels would also provide

an impetus for development of these facilities.

Improvement in livestock

During project operation phase, food grain production will increase from 7.36 lakh

tonnes per year to 24.52 lakh tonnes per year. The increase in agriculture

byproducts would be of the order of 17.16 tonnes per year. Assuming even 50% of

agriculture by product is usable as fodder, hence, about 8.58 lakh tonnes of

additional fodder would be available. This would satisfy the fodder requirements of

Page 15: Final Ex. Summary - Mohanpura Project · Xanthium strumarium, Argemone mexicana, Cynodon dactylon, Saccharum munja, etc. Floristics During floristic survey in the Pre-Monsoon, Monsoon

15

about 94,000 cattles per year. This will reduce the pressure on the existing forests or

vegetation of the area, which is a significant positive impact.

Employment generation

The introduction of irrigation requires a greater amount of labour in fields. This would

improve the employment scenario not only for the local farmers, but would also

increase the demand for agricultural labour. On average, labour demand in irrigated

and unirrigated field is 200 mandays/year/ha and 100 mandays/ha/year. The

employment potential in with out -project phase for a cropped area of 58,650 ha has

about 5.87 million which will increase to 19.55 million mandays in project operation

phase. Thus, with the increase in the irrigation intensity, manpower requirement in

the agriculture sector would increase by 13.68 million man days per year, which is a

significant positive impact.

6. ENVIRONMENTAL MANAGEMENT PLAN

6.1 ENVIRONMENTAL MEASURES DURING CONSTRUCTION PHASE

Facilities in Labour Camps

It is proposed that it should be made mandatory for the contractor involved in the

construction activities to provide adequate facilities for water supply and sanitation.

It is recommended that the contractor provides living units of 30-40 m2 to each of

the labour family involved in the construction activities. The unit should have proper

ventilation.

Water supply

Appropriate water supply sources need to be identified. Proper infrastructure for

storage and if required treatment e.g. disinfection orother units, should also be

provided.

Sewage treatment

The labour population is proposed to be situated in existing colonies. One community

toilet needs to be provided for 20 persons. The sewage from the community toilets

shall be treated in a sewage treatment plant comprising of aerated lagoons and

secondary settling tank.

Provision of community kitchen and Free Fuel

A community kitchen could be provided where workers have their meals. The fuel

used in such community kitchens could be LPG or diesel. The project contractor in

association shall make necessary arrangements for supply of fuel to labour

population for which provision shall be kept in the cost estimate.

Page 16: Final Ex. Summary - Mohanpura Project · Xanthium strumarium, Argemone mexicana, Cynodon dactylon, Saccharum munja, etc. Floristics During floristic survey in the Pre-Monsoon, Monsoon

16

Solid waste management

The labour colonies will generate substantial amount of municipal wastes. Adequate

facilities for collection, conveyance and disposal of solid waste needs to be

developed. For solid waste collection, masonry storage vats, each of 2 m3 capacity

should be constructed at appropriate locations in various labour camps. These vats

should be emptied at regular intervals and the collected waste can then be

transported to landfill sites. Two covered trucks to collect the solid waste from

common collection point and transfer it to the disposal site should be put to service.

A suitable landfill site should be identified and designed to contain municipal waste

from various project township, labour colonies, etc.

Restoration of construction sites

Normally construction sites are left unreclaimed, with construction waste being left

without being properly disposed. In the proposed project, it is proposed to collect the

construction waste from various construction sites, and disposed off at sites

identified in consultation with the district administration. The various construction

sites would be properly levelled. The levelling or reclamation of various construction

sites, should be made mandatory for the contractor, hence, no additional cost has

been earmarked as a part of the cost to be earmarked for implementation of EMP.

6.2 MAINTENANCE OF WATER QUALITY

In the project operation phase, a colony is likely to be set up. It is proposed to

provide sewage treatment plant in the project colony, cost of which shall be included

in the contract for constructing the project colony.

6.3 HEALTH DELIVERY SYSTEM

The various measures for control of Public Health are listed as below:

- The site selected for habitation of workers should not be in the path of

natural drainage.

- Adequate drainage system to dispose storm water drainage from the

labour colonies should be provided.

- Adequate vaccination and immunization facilities should be provided

for workers at various construction sites.

- The labour camps and resettlement sites should be at least 2 to 3 km

away from quarry areas.

It is proposed to develop one dispensary if the proposed project area. The staffing

details are given in Table-5.

Page 17: Final Ex. Summary - Mohanpura Project · Xanthium strumarium, Argemone mexicana, Cynodon dactylon, Saccharum munja, etc. Floristics During floristic survey in the Pre-Monsoon, Monsoon

17

Table-5 : Details of staff in the dispensary

Para medical staff Numbers

Doctors 1

Auxiliary Nurse 3

Attendant 3

Driver 3

Total 10

The dispensary building shall have the following facilities:

• waiting hall where 20-30 people can sit.

• rooms for doctors • one room for staff

• two rooms for stores

• one general ward to accommodate 10 beds • one minor operation theater/dressing room

• one garage with space for vehicle

A first aid post shall be provided at the major construction sites. These posts will

have the following facilities:

- First aid box with essential medicines including ORS packets

- First aid appliances-splints and dressing materials

- Stretcher, wheel chair, etc.

6.4 SUSTENANCE & ENHANCEMENT OF FISHERIES POTENTIAL

The commissioning of the proposed Mohanpura Irrigation Project will increase the

water availability in the project command area. It is proposed to stock the reservoir

with fingerlings. Adequate infrastructure in terms of nurseries, rearing ponds, etc.

shall be commissioned.

6.5 CONTROL OF WEEDS ON AGRICULTURE LANDS

Measures against weeds comprise mechanical (cultivation and mowing), cultural or

cropping, biological and chemical means. These include:

- hand weeding

- adopting farming practices that change the conditions in such a way as to

enable plants to complete with weeds

- use of weedicides.

6.6 PESTS CONTROL

Integrated pest management strategy should be followed to reduce the use of

pesticides. In this method, a limited number of insecticidal sprays are undertaken

and simultaneously bio-control agents like pheromones, etc. are used. The

pheromones are organic compounds developed specifically for each type of pest

which are commercially synthesized in the laboratories and sold in the market.

Page 18: Final Ex. Summary - Mohanpura Project · Xanthium strumarium, Argemone mexicana, Cynodon dactylon, Saccharum munja, etc. Floristics During floristic survey in the Pre-Monsoon, Monsoon

18

Integrated pest management strategy shall be followed to reduce the use of

pesticides. In this method, a limited number of insecticidal sprays are undertaken

and simultaneously bio-control agents like pheromones, etc. are used. The

pheromones are organic compounds developed specifically for each type of pest

which are commercially synthesized in the laboratories and sold in the market.

6.7 TRAINING AND EXTENSION COURSES FOR FARMERS

The change from rainfed to irrigated cropping requires extension, training and

demonstration programmes for farmers. Considering these aspects it is proposed

that the project authorities needs to provide adequate training to farmers. The

training shall include the following aspects of environmental protection:

• Prevention of spread of water related diseases;

• Safe use of agro-chemicals, and

• Environmental conservation programmes.

6.8 CONTROL OF AIR POLLUTION

The following measures are recommended:

• The contractor will be responsible for maintaining properly functioning

construction equipment to minimize exhaust.

• Construction equipment and vehicles will be turned off when not used for

extended periods of time.

• Unnecessary idling of construction vehicles to be prohibited.

• Effective traffic management to be undertaken to avoid significant delays in

and around the project area.

• Road damage caused by sub-project activities will be promptly attended to

with proper road repair and maintenance work.

• Identification of construction limits (minimal area required for construction

activities).

• When practical, excavated spoils will be removed as the contractor proceeds

along the length of the activity.

• When necessary, stockpiling of excavated material will be covered.

• Excessive soil on paved areas will be sprayed (wet) and/or swept and

unpaved areas will be sprayed and/or mulched.

• Contractors will be required to cover stockpiled soils and trucks hauling soil,

sand, and other loose materials (or require trucks to maintain at least two

feet of freeboard).

Page 19: Final Ex. Summary - Mohanpura Project · Xanthium strumarium, Argemone mexicana, Cynodon dactylon, Saccharum munja, etc. Floristics During floristic survey in the Pre-Monsoon, Monsoon

19

• Contractor shall ensure that there is effective traffic management at site. The

number of trucks/vehicles to move at various construction sites to be fixed.

• Dust sweeping - The construction area and vicinity (access roads, and

working areas) shall be swept with water sweepers on a daily basis or as

necessary to ensure there is no visible dust.

6.9 NOISE CONTROL MEASURES

The contractors will be required to maintain properly functioning equipment and

comply with occupational safety and health standards. The construction equipment

will be required to use available noise suppression devices and properly maintained

mufflers.

The effect of high noise levels on the labour population involved in construction

activities is to be considered as likely to be particularly harmful. To prevent these

effects, it has been recommended by international specialist organisations that the

exposure period of affected persons be limited as specified in Table-6. Alternatively,

they should be provided with effective personal protective measures such as ear

muffs or ear plugs to be worn during periods of exposure.

Table-6 : Maximum Exposure Periods specified by OSHA

-----------------------------------------------------------------------------------------------

Maximum equivalent continuous Unprotected exposure noise level dB(A) period per day for 8

hrs/day and 5

days/week ----------------------------------------------------------------------------------------------

90 8 95 4

100 2

105 1 110 1/2

115 1/4

120 No exposure permitted at or above this level

-----------------------------------------------------------------------------------------------

The other measures to control noise could be as follows:

• Equipment and machineries should be maintained regularly to keep the noise

generation

• Silencers and mufflers of the individual machineries to be regularly checked;

• Yearly audiometric survey on workers exposed to high noise levels should be

undertaken.

Page 20: Final Ex. Summary - Mohanpura Project · Xanthium strumarium, Argemone mexicana, Cynodon dactylon, Saccharum munja, etc. Floristics During floristic survey in the Pre-Monsoon, Monsoon

20

7. CATCHMENT AREA TREATMENT PLAN

Silt Yield Index (SYI) method has been used to prioritize sub-watershed in a

catchment area for treatment. The area under very high and high erosion categories

is to be treated at the project proponent cost. In the catchment of the proposed

Mohanpura Irrigation Project, there is no area under very high erosion category.

Hence, CAT plan has been suggested for high erosion category, as a part of the

present EIA study, the expenses of which have to be borne by project proponents.

The area under high erosion category is 277135 ha. The details are given in Table-7.

An amount of Rs. 1539.39 million has been earmarked for Catchment Area

Treatment.

Table-7 : Area under different erosion categories

Category Area (ha) Percentage

Medium 95465 25.62

High 277135 74.38

Total 372600 100.00

Following Engineering and Biological measures have been suggested for the

catchment area treatment.

1. Engineering measures

- Nallah Bunding - Contour Bunding

- Angle iron barbed wire fencing

2. Biological measures

- Development of nurseries - Plantation/afforestation

- Pasture development

- Social forestry

8. RESETTLEMENT AND REHABILITATION PLAN

The provisions of the MPPKKVVA - 1985 and NRRP – 2007 have been taken into

consideration, and the best option has been recommended for preparation of

Resettlement and Rehabilitation Plan for the PAFs.

8.1 MEASURES FOR RESETTLEMENT

• Any affected family whose house has been acquired or lost, may be allotted

free of cost house site to the extent of actual loss of area of the acquired

house but not more than 250 sqm of land in rural areas. In addition, about

25% of the plot size would be required for providing civic amenities and about

25% of the plot size for providing infrastructure facilities.

Page 21: Final Ex. Summary - Mohanpura Project · Xanthium strumarium, Argemone mexicana, Cynodon dactylon, Saccharum munja, etc. Floristics During floristic survey in the Pre-Monsoon, Monsoon

21

• Sensitized conscious effort needs to be put-in to ensure entire population of

the village or area is shifted and resettled as far as possible en-masse so that

communities, kinship ties, socio-cultural relations and social harmony is not

disturbed.

• All PAFs losing homestead would be provided with House Building assistance

of Rs. 150,000.

• In case of a project involving land acquisition on behalf of a requiring body,

the stamp duty and other fees payable for registration of the land or house

allotted to the affected families shall be borne by the requiring body.

• The land or house allotted to the affected families under this policy shall be

free from all encumbrances

• The land or house allotted to the affected families under this policy may be in

the joint names of wife and husband of the affected family.

• Each affected family that is displaced and has cattle, shall get financial

assistance of such amount as the appropriate Government may decide but

not less than Rs. 15,000 for construction of cattle shed.

• Each affected family that is displaced shall get a one-time financial assistance

of such amount as the appropriate Government may decide but not less than

Rs. 10,000, for shifting of the family, building materials, belongings and

cattle.

• Each affected person who is a rural artisan, small trader or self-employed

person and who has been displaced shall get a one-time financial assistance

of such amount as the appropriate Government may decide but not less than

Rs. 25,000 for construction of working shed or shop.

• In case of a project involving land acquisition on behalf of a requiring body,

each affected family which is involuntarily displaced shall get a monthly

subsistence allowance equivalent to 25 days minimum agricultural wages per

month for a period of 1 year from the date of displacement.

• Amenities and Infrastructural facilities to be provided at Resettlement Areas.

Such facilities and amenities shall, inter alia, include Internal Village Road

Network, drainage Network within the Resettlement site, sanitation Network

within the Resettlement site, safe drinking water, footpath, public transport,

drinking water trough for cattle, Place of Worship, Cremation grounds, Fair

Price shops and other shops, Post Office, Panchayat Ghar, Community Hall,

Health Care Facility, Garden and children's playground, Educational

Page 22: Final Ex. Summary - Mohanpura Project · Xanthium strumarium, Argemone mexicana, Cynodon dactylon, Saccharum munja, etc. Floristics During floristic survey in the Pre-Monsoon, Monsoon

22

institutions (schools) in resettlement sites, Space for weekly market,

8.2 MEASURES FOR REHABILITATION

The following measures are suggested to be extended as rehabilitation measures to

the PAFs losing land:

• Based on past experiences, it is observed that a land for land may not be

available in the command area. Thus it is suggested that Rehabilitation grant

may be extended in-lieu of land to PAFs losing land.

• In case of a project involving land acquisition on behalf of a requiring body,

the affected families who have not been provided agricultural land shall be

entitled to a rehabilitation grant equivalent to 750 days minimum agricultural

wages or such other higher amount as may be prescribed by the appropriate

Government.

• Fishing rights in the reservoirs shall be given to the affected families, if such

rights were enjoyed by them in the affected area;

• Stamp duty and other fees payable for Registration of the land allotted to the

affected families shall be borne by the requiring body.

• Land allotted to the affected families under this policy shall be free from all

encumbrances.

• Land allotted to the affected families under this policy may be in the joint

names of wife and husband of the affected family.

• In case each khatedar in the affected family is allotment of wasteland or

degraded land in lieu of the acquired land, s/he shall be entitled for a one-

time "financial assistance of not less than Rs. 15,000/ha for land

development.

• A provision of Rs. 10,000 per PAFs being kept for a one-time financial

assistance to each khatedar in the affected family for agricultural production

• Preference to given to atleast one person per affected family in providing

employment in the project, subject to the availability of vacancies and

suitability of the affected person for the employment.

• A provision of Rs. 500/month for 6 months for one person per PAF shall be

given for training.

• Scholarship @ Rs. 500 per month to atleast 1 child per PAF for a period of 1

year.

Page 23: Final Ex. Summary - Mohanpura Project · Xanthium strumarium, Argemone mexicana, Cynodon dactylon, Saccharum munja, etc. Floristics During floristic survey in the Pre-Monsoon, Monsoon

23

• A provision of Rs. 500/month for 6 months for one person per PAF shall be

given to extend other skill development opportunities to eligible persons.

• Requiring body shall give preference to willing landless labourers and

unemployed affected persons while engaging labour in the project during the

construction phase.

• One person from each affected family shall be offered necessary training

facilities for development of entrepreneurship, technical and professional skills

for self-employment.

8.3 BUDGET

The total budget for implementation of the Rehabilitation and Resettlement Plan is

Rs. 6952.75 million. The details are given in Table-8.

Table-8: Budget for implementation of the Rehabilitation and Resettlement

Plan

S. No. Components of R&R Cost (Rs. million)

A Payment of compensation of acquired properties

1 Private lands (cultivated irrigated, cultivated un-

irrigated and un-cultivated).

3877.82

2 Housing plots & homesteads structures 1226.34

3 Trees 3.04

4 Shops 6.84

5 Wells 9.12

6 Diversion of roads and construction of bridges 20.40

7 Shifting of electric poles 7.14

Sub-Total [A] 5150.70

B Resettlement Plan

1. Land required for providing Housing plots @ 250 sqm

to 1120 house losers = 166.5 ha (including land for civic amenities and infrastructure facilities)

2. House building assistance 666.00

3. Financial assistance for construction of cattle-shed 66.60

4. Financial assistance for shifting of the family, building

materials, belongings and cattle

44.40

5. Financial assistance for construction of working shed or shop.

111.00

6. Subsistence allowance 199.80

7. Civic amenities and Infrastructure facilities at

Resettlement colony

324.5

Sub-Total [B] 1412.3

C Rehabilitation Plan

1. Land required under “land for land” option = 2500 ha irrigated land in the command area

2. Land development cost in case wasteland or degraded

land is allotted

37.50

3. Financial assistance for agricultural production 25.0

4. Training to take on suitable jobs 7.50

Page 24: Final Ex. Summary - Mohanpura Project · Xanthium strumarium, Argemone mexicana, Cynodon dactylon, Saccharum munja, etc. Floristics During floristic survey in the Pre-Monsoon, Monsoon

24

S. No. Components of R&R Cost

(Rs. million)

5. Scholarships 15.0

6. Other Skill Development 7.50

7. Training facilities for development of entrepreneurship,

technical and professional skills for self-employment

15.0

8. Rehabilitation Grant - in case “land for land” or “jobs in

project” are not given

281.25

Sub-Total [C] 388.75

D Project Monitoring & Evaluation [D] 1.00

Total [A+B+C+D] 6952.75

9. LOCAL AREA DEVELOPMENT PLAN

The area development activities proposed as a part of the plan given in following

paragraphs:

Upgradation of educational facilities

It is proposed to upgrade the primary schools in various villages in the periphery of

the affected villages. The following activities are proposed under ladp activities:

• Up-gradation of school fixtures, equipment

• Improvement of drinking water and sanitation facilities

• School bus service • Scholarship to students

Improvement of Public Health Facilities • Furniture, Beds and other items

• Up-gradation of Pathological laboratory

• Up-gradation of operation theater (labor room)

An amount of Rs. 140.3 million is being made for implementation of the LADP

Activities. The details are shown in Table-9.

Table 9: Budget for implementation of Local Area Development Plan

S. No. Items Budget (Rs. million)

1 Construction/ Up-gradation schools in Study Area (refer

Table–16.1)

75.5

2 Scholarships to students in the Study Area (refer Table–16.2) 40.8

3 Improvement of Public Health Facility (refer Table-16.3) 24.0

Total 140.3

10. DISASTER MANAGEMENT PLAN

The following measures have been suggested as a part of the Disaster Management

Plan:

• Dam Safety and Maintenance Manual • Emergency Action Plan (EAP)

• Administration and Procedural Aspects

Page 25: Final Ex. Summary - Mohanpura Project · Xanthium strumarium, Argemone mexicana, Cynodon dactylon, Saccharum munja, etc. Floristics During floristic survey in the Pre-Monsoon, Monsoon

25

• Preventive Action

• Communication System • Notifications

• Evacuations Plans and Evacuation Team

• Public Awareness for Disaster Mitigation • Management after receding of Flood Water

11. ENVIRONMENTAL MONITORING PROGRAMME

An Environmental Monitoring Programme should be undertaken during construction

and operation phase of the project. The details of environmental monitoring

programme are given in Tables -10 and 11 respectively.

Table-10: Environmental Monitoring Programme during Construction Phase

S.

No.

Particulars Parameters Frequency Location

1. Treated waste water from STPs

pH, BOD, COD, TSS and Oil &

Grease

Once every month

Before and after treatment from

the STPs at

various labour camps

2. Ambient Air quality SPM, RPM, SO2,

NOx and CO

Once every

season

At major

construction sites

3. Noise Equivalent noise

level (Leq)

Every month At major

construction sites.

4. Soil Erosion Soil erosion

rates, stability of bank

embankment,

etc.

Every month Various sites in

the catchment area.

5. Water-related

diseases

Identification of

water related

diseases, adequacy of

local control and curative

measure,

etc.

Once every

season

Labour camps

and nearby

settlements

Table-11: Environmental Monitoring Programme during Project Operation

Phase

S. No. Particulars Parameters Frequency Location

1. Water pH, Turbidity,

Total Dissolved Solids, Calcium,

Magnesium,

Chlorides, Sulphate,

Nitrates, Iron,

DO, BOD, COD

Pre monsoon

Season and Post monsoon

season

Reservoirs.

Page 26: Final Ex. Summary - Mohanpura Project · Xanthium strumarium, Argemone mexicana, Cynodon dactylon, Saccharum munja, etc. Floristics During floristic survey in the Pre-Monsoon, Monsoon

26

S. No. Particulars Parameters Frequency Location

etc.

2. Treated Waste Water from

STP

pH, BOD, COD, TSS, and Oil &

Grease.

Once every month

Before and after treatment from

STP

3. Erosion & Siltation

Soil erosion rates, stability of bank

embankment, etc.

Twice a year (pre & post

monsoon Season)

--

4. Ecology Status of

afforestation programmes

Once in 5

years

--

5. Fisheries Phytoplanktons,

zooplanktons, benthic life, fish

composition

Twice a

year

Reserviors.

6. Incidence of water-related

diseases

Cause and control measures for

various

diseases.

Once in a year

Settlements around

Reservoirs and

in command areas

7 Meteorological

Parameters

Temperature,

rainfall, humidity, cloud

cover, wind speed

and direction, Solar Insolation,

Evaporation Rate

Continuous At a location

close to dam site

12. COST ESTIMATES

12.1 COST FOR IMPLEMENTING ENVIRONMENTAL MANAGEMENT PLAN

The total amount to be spent for implementation of Environmental Management Plan

(EMP) is Rs. 9064.39 million. The details are given in Table-12.

Table-12: Cost for Implementing Environmental Management Plan

S. No. Item Cost (Rs. million)

1. Bio-diversity conservation Plan 44.73

2. Fisheries Management Plan 80.90

3. Environmental Management in labour camp 143.50

4. Public health delivery system 69.69

5. Restoration and Landscaping of construction sites 29.10

6. Greenbelt development 2.40

7. Air Pollution Control 10.79

8. Water Pollution Control 1.50

9. Energy Conservation measures 5.00

10. Public Awareness Programmes 5.00

11. Resettlement and Rehabilitation Plan 6952.75

12. Local Area Development Plan 140.3

Page 27: Final Ex. Summary - Mohanpura Project · Xanthium strumarium, Argemone mexicana, Cynodon dactylon, Saccharum munja, etc. Floristics During floristic survey in the Pre-Monsoon, Monsoon

27

S. No. Item Cost (Rs. million)

13. Catchment Area Treatment Plan 1539.39

14. Disaster Management Plan 21.00

15. Environmental Monitoring during construction phase (Refer

Table-13)

17.49

16. Purchase of noise meter 0.15

17. Purchase of meteorological instruments 0.70

Total 9064.39

12.2 COST FOR IMPLEMENTING ENVIRONMENTAL MONITORING PROGRAMME

The cost required for implementation of the Environmental Monitoring Programme is

of the order of Rs.17.49 million @ Rs.2.68 million/ year. A 10% annual price increase

may be considered for every year. The construction period for estimation of cost for

implementation of Environmental Monitoring programme during construction phase

has been taken as 6 years. The details are given in Table-13. The cost required for

implementation of the Environmental Monitoring Programme in operation phase is of

the order of Rs.2.6 million/year. The details are given in Table-14.

Table-13: Cost for Implementing Environmental Monitoring Programme during construction phase

S. No Item Cost

(Rs. million/year)

Total cost for construction

period of 6 years with 10% escalation per year (Rs. million)

1 Water quality 0.144 1.11

2 Ambient Air quality 0.48 3.70

3 Soil Erosion 0.144 1.11

4 Ecology 1.00 7.71

5. Incidence of water related

diseases

0.50

3.86

Total 2.68 17.49

Table-14: Cost for Implementing Environmental Monitoring Programme during operation phase

S. No Item Cost

(Rs. million/year)

1 Water quality 0.10

2 Ecology 1.00

3 Fisheries 1.00

4 Incidence of water related diseases 0.50

Total 2.60