Upload
truonghanh
View
214
Download
1
Embed Size (px)
Citation preview
Drainage and wastewater treatment system project forThai Hoa town, Nghe An province”
Environmental Impact Assessment (EIA) - 1 –
PCO Consultant, 2010
CONTENTS
CONTENTS ......................................................................................................................... 1
LIST OF TABLES ............................................................................................................... 6
1. EXECUTIVE SUMMARY.......................................................................................... 7
2.LEGAL AND TECHNICAL BACKGROUND ......................................................... 10
2.1. Legal background of Viet Nam goverment ........................................................... 10
2.2. Environmental policies of the World Bank (WB) ................................................. 12
2.3. Technical data sources ......................................................................................... 13
3. ASSESSMENT METHODOLOGY .......................................................................... 15
4. ORGANIZATION ..................................................................................................... 17
4.1. Consultant for preparing Environment Impact Assessment Report ....................... 17
CHAPTER I: PROJECT DESCRIPTION ....................................................................... 19
1.1. PROJECT NAME: ................................................................................................. 19
1.2. PROJECT OWNER: .............................................................................................. 19
1.3. GEOGRAPHICAL LOCATION OF THE PROJECT ......................................... 19
1.3. TOTAL INVESTMENT ......................................................................................... 19
1.5. SCOPE OF WORK ................................................................................................ 20
1.6.2. Construction of stormwater sewer system .......................................................... 22
1.6.3. Wastewater sewer system ................................................................................. 25
1.6.4. Management and operation of drainage and wastewater treatment system ......... 31
1.6. IMPLEMENTATION SCHEDULE ...................................................................... 33
CHAPTER II: NATURAL, SOCIO-ECONOMIC AND ENVIRONMENTAL
CONDITIONS ................................................................................................................... 35
2.1 NATURAL CONDITIONS ..................................................................................... 35
2.1.2. Topography and area ......................................................................................... 35
2.1.2. Climate ............................................................................................................. 36
2.1.3. Geological conditions ........................................................................................ 38
2.1.4. Hydrological conditions .................................................................................... 38
2.1.5. Mineral resource ............................................................................................... 39
2.1.6. Forest Resource ................................................................................................. 39
2.2. SOCIO-ECONOMIC CONDITIONS.................................................................... 39
2.2.1. Economic development situation ....................................................................... 39
2.2.2. Social development ........................................................................................... 40
2.3. CURRENT SITUATION OF DRAINAGE ........................................................... 43
2.3.1. Current situation of drainage system .................................................................. 43
2.3.2. Current situation of drainage channels and sewers ............................................ 43
2.3.3. Current situation of flooding and inundations .................................................... 44
2.4. CURRENT SITUATION OF ENVIRONMENTAL SANITATION ................... 45
2.4.1. Current situation of household sanitation ........................................................... 45
2.4.2. Current situation of solid waste collection and treatment ................................... 46
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Drainage and wastewater treatment system project for Thai Hoa town, Nghe An province”
Environmental Impact Assessment (EIA) PCO Consultant, 2010
2
2.5. OTHER TECHNICAL INFRASTRUCTURE CONDITIONS ............................ 47
2.5.1. Traffic condition ............................................................................................... 47
2.5.2. Power supply..................................................................................................... 48
2.5.3. Water supply ..................................................................................................... 49
2.6. THE STATUS OF ENVIRONMENT QUALITY ................................................. 49
2.6.1. The status of air environment quality ................................................................. 49
2.6.2. The status of surface water environment quality ............................................... 53
2.6.3 The status of underground water environment quality ........................................ 57
2.6.4 The status of wastewater environment quality .................................................... 61
2.6.5. The status of sludge quality ............................................................................... 66
CHAPTER III:
ENVIRONMENT IMPACT ASSESSMENT .................................................................... 70
3.1. OVERVIEW OF THE IMPACTS OF PROJECT ................................................ 70
3.1.1. Positive impact of the project ............................................................................ 70
3.1.2. Negative impacts of the project ......................................................................... 72
3.1.3. The Project’s affected scale: .............................................................................. 73
3.2. ASSESSMENT OF PROPOSAL TECHNICAL OPTIONS ................................. 74
3.2.1. Design of stormwater and wastewater sewer system .......................................... 74
3.2.2. Location and Design of wastewater pumping station ......................................... 75
3.2.3. Location of Wastewater Treatment Plants selection ........................................... 75
3.2.4. Wastwater treatment technology selection ......................................................... 78
3.2.5. Assessment of wastewater receiving ability of Hieu river: ................................. 79
3.2.6. Assessment of wastewater mixing ability meeting domestic water standard.. ..... 82
3.2.7. Assessment of sludge treatment techonology and discharge location: ................ 85
3.2.8. Compensation and Site Clearance: .................................................................... 86
3.3. ENVIRONMENT IMPACT ASSESSMENT IN CLEARANCE PHASE ............ 86
3.3.1. Impacts on atmosphere ...................................................................................... 87
3.3.2. Water pollution sources ..................................................................................... 89
3.3.3. Impacts on soil environment .............................................................................. 89
3.3.4. Solid waste impacts ........................................................................................... 90
3.3.5. Impacts on lanscape .......................................................................................... 90
3.3.6. Impacts on the socio-economic life.................................................................... 91
3.4. ENVIRONMENT IMPACT ASSESSMENT IN CONSTRUCTION PHASE ..... 91
3.4.1. Impacts on the atmosphere ................................................................................ 93
3.4.2. Impacts on water ............................................................................................... 97
3.4.3. Impacts on soil .................................................................................................. 99
3.4.4. Impacts of solid waste ....................................................................................... 99
3.4.5. Impacts on landscape ..................................................................................... 101
3.3.6. Impacts on the socio-economic life.................................................................. 101
3.5. ENVIRONMENTAL IMPACT ASSESSMENT DURING OPERATION PHASE
...................................................................................................................................... 103
3.5.1. Bad smell and toxic gas ................................................................................... 104
Drainage and wastewater treatment system project for Thai Hoa town, Nghe An province”
Environmental Impact Assessment (EIA) PCO Consultant, 2010
3
3.5.2. Waste water and overflowing rainwater ........................................................... 105
3.5.3. Sludge and domestic solid waste ................................................................... 105
3.3.4. Impacts on landscape ...................................................................................... 106
3.3.5. Environment safety and risks ........................................................................... 106
CHAPTER IV:
MITIGATION MEASURES FOR ADVERSE IMPACTS, PREVENTATION AND
RESPONSE TO ENVIRONMENTAL PROBLEMS ..................................................... 108
4.1. MITIGATION MEASURES IN THE PRE-CONSTRUCTION PHASE .......... 108
4.1.1. Research methodology and specific assesment on the project area’s location and
land situation ............................................................................................................ 108
4.1.2. Site plans ........................................................................................................ 108
4.2. MITIGATION MEASURES DURING CONSTRUCTION PHASE ................. 109
4.2.1. Air pollution limitation .................................................................................... 109
4.2.2. Mitigation of impact on water environment ..................................................... 110
4.2.3. Mitigation of impact on soil environment ........................................................ 111
4.2.4. Mitigation of impact on transportation and flood in the construction ............... 112
4.2.5. Mitigation measures for environmental problems ............................................ 112
4.3. MITIGATION MEASURES DURING OPERATION PHASE ........................ 113
4.3.1. Minimizing impacts on air environment .......................................................... 113
4.3.2. Minimizing impact on water environment ....................................................... 114
4.3.3. Minimizing impact on soil environment .......................................................... 114
4.3.4. Reducing impact on ecosystem and socio-economy ......................................... 115
4.4. MEASURES FOR PREVENTING ENVIRONMENT RISKS ........................... 115
4.5. FLOOD CONTROLS ........................................................................................... 117
4.6. SANCTION METHODS ...................................................................................... 118
CHAPTER V:
THE ENVIRONMENTAL MANAGEMENT PLAN ..................................................... 119
5.1. ENVIRONMENT MANAGEMENT PROGRAM .............................................. 119
5.1.1. Organization for implementation of EMP ........................................................ 119
5.1.3. Estabilishment of EMP .................................................................................... 122
5.2. ENVIRONMENT MONITORING PROGRAM (EMP) .................................... 134
5.2.1. Environment monitoring plan .......................................................................... 135
5.2.2. The proposed environmental monitoring program for the project. .................... 138
5.3. CAPACITY BUILDING ...................................................................................... 141
CHAPTER VI:
PUBLIC CONSULTATION............................................................................................ 143
6.1. OBJECTIVES OF PUBLIC CONSULTATION ................................................. 143
6.4. METHOD AND ORGANIZATION OF PUBLIC CONSULTATION ............. 143
6.3. PUBLIC CONSULTATION RESULTS .............................................................. 144
6.3.1. Consultation results of the affected people....................................................... 144
6.3.2. Results of local authorities consultation. .......................................................... 148
6.6. DISCLOSURE ...................................................................................................... 148
Drainage and wastewater treatment system project for Thai Hoa town, Nghe An province”
Environmental Impact Assessment (EIA) PCO Consultant, 2010
4
CONCLUSION AND RECOMMENDATION ............................................................... 150
I. CONCLUSION ........................................................................................................ 150
II. RECOMMENTATIONS ........................................................................................ 151
IX. COMMITMENTS OF THE PROJECT OWNER............................................... 152
APPENDIX ...................................................................................................................... 154
Drainage and wastewater treatment system project for Thai Hoa town, Nghe An province”
Environmental Impact Assessment (EIA) PCO Consultant, 2010
5
ABBRIVIATIONS
MONRE The Ministry of Natural Resources and Environment
MOH The Ministry of Health
CPO The Central Project Office
DONRE The Department of Natural Resources and Environment
DPC District People’s Committee
EIA Environmental Impact Assessment
EA Environment Assessment
EMP Environment Management Plan
EPC Environment Protection Commitment
FS Feasibility Study
RAP Resettlement Action Plan
SEI Social-Economic Investigation
GOV Government of Vietnam
IDA International Development Association
MARD The Ministry of Agriculture and Rural Development
ND The Decree
ODA Official Development Assistance
PIP Project Implementation Plan
PMM Project Management Manual
PFS Pre-Feasibility Study
PPMU Provincial Project Management Unit
PPC Provincial People’s Committee
PM Pipeline network
WPS Wastewater pumping station
QCVN Vietnam Regulation
TCVN Vietnam Standard
TOR Term of Reference
WB The World Bank
WTP Wastewater Treatment Plant
Drainage and wastewater treatment system project for Thai Hoa town, Nghe An province”
Environmental Impact Assessment (EIA) PCO Consultant, 2010
6
LIST OF TABLES
Page
Table i. List of projects that involve making EIA reports or EPCs......... Error! Bookmark not
defined.
Table1.1. Proposed work on rain water drainage ............................................................. 24
Table 1.4. Project Implementation Schedule ....................................................................... 33
Table: Population of Thai Hoa town up to the end of 2009 ................................................ 40
Table 2.6. The forecast population growth of Thai Hoa town phase 2020 - 2030 .............. 41
Table 2.9. Analyzing results of surrounding air component content .................................. 49
Table 2.10. Analyzing results of surrounding air component content ................................. 50
Table 2.10. Analyzing results of surrounding air component content .... Error! Bookmark not
defined.
Table 2.10. Analyzing results of surrounding air component content .... Error! Bookmark not
defined.
Table 2.11. Analyzing result of surface water quality in studied area ................................. 54
Table 2.12. Analyzing result of surface water quality in studied area .... Error! Bookmark not
defined.
Table 2.13. Analyzing result of underground water in studied area ...... Error! Bookmark not
defined.
Table 2.13. Analyzing result of underground water in studied area ................................... 58
Table 2.14. Analyzing results of wastewater environment quality .......... Error! Bookmark not
defined.
Table 2.15. Analyzing result sludge samples in studied area .............................................. 67
Table 2.15. Analyzing result sludge samples in studied area .... Error! Bookmark not defined.
Table 5.1: Roles and fuctions of environment management of participations .................. 119
Table 5.2: EMP of project: “Drainage and wastewater treatment for Thai Hoa town, Nghe
An province” ..................................................................................................................... 123
Table 5.3: Environment observation and supervision prpgrams ....................................... 138
LIST OF DIAGRAM, CHART Page
Chart 2.1: The structure of the economic sectors of Thai Hoa Town in 2009 .............................. 40
Chart 2.2. Average income of households (1000 VND/household/month)) .................................. 42
Chart 2.3. Analyzing result of COD (mg/l) criterion in wastewater compared to standard ............. 64
Chart 2.4. Analyzing result of BOD5 (mg/l) criterion in wastewater compared to standard ........... 64
Chart 2.5. Analyzing result of SS (mg/l) criterion in wastewater compared to standard ................ 65
Drainage and wastewater treatment system project for Thai Hoa town, Nghe An province”
Environmental Impact Assessment (EIA) PCO Consultant, 2010
7
Chart 2.6. Analyzing result of Coliform criterion in wastewater compared to standard ................. 65
Drainage and wastewater treatment system project for Thai Hoa town, Nghe An province”
Environmental Impact Assessment (EIA) PCO Consultant, 2010
8
1. EXECUTIVE SUMMARY
Introduction:
Thai Hoa town lies in the northwestern area of Nghe An province on coordinates from
19°13’ – 19°33’ of north latitude and 105 ° 18 '- 105 ° 35' of east longitude; about 90km
distant from Vinh city to the North-West . Along with the whole country and the non-stop
movement of the general development of the world, Thai Hoa town has also achieved certain
progress steps in economy, culture …
Currently, the drainage system in Thai Hoa town is still inadequate; especially there is
no wastewater collection and treatment system. The existing drainage system is completely
natural, fails to meet certain specifications or planning orientations. The absence of a
complete drainage system caused local inundations, rain water natural overflow on the
surface, causing environmental pollution as wastewater is not collected, current sewers are not
periodically dredged, maintained, renovated. The households in the town discharge
wastewater naturally into drainage areas around the house.... causing unpleasant odor, much
affecting the environment and landscape of the town.
Vietnam Urban Wastewater and Water Supply Project (VUWSWP) is funded by ODA
of the World Bank to improve water supply, collection and wastewater treatment system, and
drainage services in the urban areas of several provinces in the country including Thai Hoa
town - Nghe An province. The " Drainage and wastewater treatment system project for Thai
Hoa Town, Nghe An province" is one of the sub-project of drainage and wastewater treatment
together with the provinces of Thanh Hoa, Quang Nam, Ninh Binh, Lam Dong, Quang Tri
and Binh Phuoc (hereinafter referred to as Thai Hoa town sub-project).
The drainage and wastewater treatment sub-project for Thai Hoa town, Nghe An
Province is essential to meet the needs and desires of residents and leaders of all levels of the
town, of the province with an aim to improve environmental sanitation conditions, gradually
completing the technical infrastructure, meeting the needs of a civilized, modern society, and
ensuring sustainable development of the town. The objectives of sub-project inculde: .
- To improve urban environmental conditions and quality of life for residents in
Thai Hoa Town, Nghe An province through the construction of, drainage, and
wastewater treatment works
- To enhance the durability of the urban infrastructure and urban services in Thai
Hoa town
- To reduce environment pollution for urban areas; to reduce epidemics caused by
waste stagnant and untreated wastewater
- To promote economic, social, infrastructure development of Thai Hoa town.
The EIA report for Thai Hoa town sub-project to carry out the Article 18 of the
Environmental Protection Law of the Vietnam Government, the Project Owner requests the
consultant to prepare the Environment Impact Assessment (EIA) report to submit to the State
management agencies on environmental protection for appraisal and approval (Nghe An
province’s Department of Natural Resources and Environment held the appraisal and Nghe
An Provincial People's Committee) will approve in accordance with Article 11, the Decree
Drainage and wastewater treatment system project for Thai Hoa town, Nghe An province”
Environmental Impact Assessment (EIA) PCO Consultant, 2010
9
No. 80/2006/ND-CP dated 09/08/2006 of the Government and The Decree No.21/2008/ND-
CP dated 28/02/2008, amending and supplementing some articles of the Decree No.
80/2006/ND-CP dated 09/08/2006 of Government detailing and guiding the implementation
of some articles of Environmental Protection Law) and according to the safeguard policies of
the World Bank
The EIA report includes the following works:
Project desciption:
Drainage subproject in Thai Hoa town is implemented within four urban wards (Hoa Hieu,
Quang Phong, Quang Tien, Long Son) and two communes (Nghia Tien & Nghia My.),
includes the following works:
- Construction of separate wastewater and stormwater sewer system.
- Construction of 6 WWPSs
- Construction of 2 WWTPs: + the treatment plant in the West bank of Hieu
river, capacity 2,000 m3/day; + the treatment plant in the East bank of Hieu
river, capacity 4,000 m3/day.
- Construction of manholes and house connection network.
Environmental background status:
On the basis of collecting secondary data, survey and evaluation of natural, socio-
economic conditions, sampling and analysis of the quality of environmental
background status (air, surface water, wastewater, groundwater, sludge) in the project
area to assess the current situation in the region, determine the scope of environmental
impact by the project.
Environmental impact:
The positive impacts: improving sanitary conditions of households with about 6,000
households benefited directly when connecting to the wastewater collection and treatment
system of the project; completing the infrastructure of the town; reducing environmental
pollution, diseases caused by the stagnant and untreated wastewater.
The negative impacts: being considered thoroughly in 3 phases of the project (preparation,
construction and operation phase). Notably, the impacts on socio-economic life of land
acquisition: 12.7 ha of agricultural land at Long Son ward with 68 affected households and
9.1 ha of agricultural land in Nghia Tien with 69 affected households; During the construction
phase, the physical impacts include spoil soil and rock, dust and emissions from the
transportation, construction, risk and labour accident. During the operation phase, impacts are
mainly bad odour and sludge (1.8 tons/day with a maximum capacity of 6000 m3/day of the
two treatment plants), environmental incidents.
Mitigation measures
On the basis of assessment of adverse environmental impacts and risks, environmental
incidents besides the process of considering the elements & the existing natural, socio-
Drainage and wastewater treatment system project for Thai Hoa town, Nghe An province”
Environmental Impact Assessment (EIA) PCO Consultant, 2010
10
economic and environmental conditions to offer measures to minimize adverse impacts,
prevent and respond to environmental problems. The mitigation measures are given
specifically for each impact source mentioned above in each phase of the project.
Environmental Management Plan (EMP):
The EMP of “Drainage and wastewater treatment system project for Thai Hoa town, Nghe
An province” was contructed on the basis of the combination from the information about the
activities os the project in preparation, construction and operation time; impacts to
environment; measures to reduce the negative impacts; the costs; schedule; implementers and
supervisors.
Public Consultation and Information Disclosure:
Public Consultation: The Consultant, the Project Owner had 2 steps (in March and June ,
2010) to organize the consultation meeting with representatives of some households,
institutional organizations and local authorities, etc with approximately 30 people in one
meeting. By applying the method of participatory assessment (MPA), opinions were
collected for the project: step 1 – the first environmental consultation about current status of
environment in the project area, priorities for environmental improvement, concerned issues
of local authority and households may affected due to the construction of project works; Step
2 – The second environmental consultation abouth draft EIA report of the project to receive
opinions and agreement for the project implementation.
Information Disclosure: the final EIA report (in Vietnamese) was announced to the locals
uring the project preparation. Also the environmental reports must also be sent to the Vietnam
Development Information Center (VDIC) for storage and information. The notification of the
environmental Impact assessment report must be conducted before implementing the project.
Commitments of the project owner:
Based on the environmental impacts arising from the implementation of the project and the
terms of the Environmental Protection Law, decrees, circulars, decisions and ordinances on
environmental protection of Viet Nam goverment, the investor – Thai Hoa Town People's
Committee to implement environmental management programs, environmental monitoring
program as outlined in Chapter 5, implementation of commitments to the community as
outlined in Chapter 6 of this EIA report.
Conclusion and Recommendations:
Reaffirm some of the contents mentioned in the report and propose necessary
recommendations to ensure that the project to be implemened brings about practical and
sustainable efficiency.
Drainage and wastewater treatment system project for Thai Hoa town, Nghe An province”
Environmental Impact Assessment (EIA) PCO Consultant, 2010
11
2.LEGAL AND TECHNICAL BACKGROUND
2.1. Legal background of Viet Nam goverment
The Environment Impact Assessment Report of "The drainage and wastewater
treatment system project for Thai Hoa town, Nghe An Province" is prepared on the basis of
the following available legal documents:
Legal documents:
Viet Nam Environment Protection Law No.52/2005/QH11 of Viet Nam National
Assembly dated 29/11/2005 which came into effect from 1st of July, 2006.
The Decree 80 /2006/ND- CP dated 09/06/2006 of the Government on detailing and
guiding the execution of some articles of the Environmental Protection Law.
The Decree No.21/2008/ND-CP dated 28/02/2008, amending and supplementing
some articles of the Decree No. 80/2006/ND-CP dated 09/08/2006 of Government
detailing and guiding the implementation of some articles of Environmental Protection
Law.
The Decree No. 88/2007/ND-CP dated 28/05/2007 of the Government on drainage in
the urban and industrial areas.
The Decree No. 59/2007/NĐ-CP dated 09/04/2007 of the Government on solid waste
management.
Circular No.05/2008/TT-BTNMT dated 08/12/2008 of Ministry of Natural Resources
and Environment on guiding the assessment of strategic environment, environment
impacts and environment projection commitment.
Decision No.22/2006/QD-BTNMT dated 18/12/2006 of the Minister of Natural
Resources and and Environment on compulsory application of Vietnam Environment
Standards
Decision No. 16/2008/QD-BTNMT dated 31/12/2008 of Ministry of Natural
Resources and Environment on issuance of national technical environment standards.
Decision No.3733/2002/QD -BYT dated 10/10/2002 of the Minister of Health
promulgating the 21 occupational sanitation standards, 05 rules and 07 parameters on
occupational sanitation
Decision No.147/2005/QD- TTg dated 15/06/2005 of Nghe An Province’s People's
Committee on approval of socio-economic development projects in the West of Nghe
An province, in which, Thai Hoa urban is put on the first priority of rapid development
to become the economic and cultural center of the northwest of Nghe An province up
to 2010.
Decision No. 3907/2008/QD-UBND dated 12/9/2008 of Nghe An Province’s People's
Committee on approval of the detailed planning of Thai Hoa town center
Document No. 288/UBND-TH dated 18/01/2010 of Nghe An Province’s People's
Committee on proposal of water supply and wastewater projects;
Based on the volume of investment items and current status of the project area to
determine the scope of assessement under Decree No. 80/2006/ND- CP dated 09/06/2006 and
Decree No.21/2008/ND-CP dated 28/02/2008 on amending and supplementing some articles
Drainage and wastewater treatment system project for Thai Hoa town, Nghe An province”
Environmental Impact Assessment (EIA) PCO Consultant, 2010
12
of Decree No. 80/2006/ND-CP dated 09/08/2006 of the Government on detailed regulations
and guidelines of some articles of Environmental Protection Law: The Project must prepare
environmental impact assessment to submit to the provincial authorities for approval
(approved by Nghe An province).
Applicable standards and regulations:
a. Standards related to water quality
- QCVN 08-2008: National Technical Regulation on surface water quality;
- QCVN 09-2008: National technical regulation on ground water quality;
- QCVN 14-2008: Quy National technical regulation on domestic wastewater
quality;
- QCVN 24: 2009: National technical regulation on the quality of industrial
wastewater.
b. Standards related to air quality
- QCVN 05:2009/BTNMT – National Technical Regulation on ambient air
quality
- QCVN 06:2009/BTNMT – National Technical Regulations on some hazardous
substances in ambient air..
c. Standards related to noise and vibration
- TCVN 5949:1998 - Noise in public areas and residential areas, the maximum
allowable noise level.
- TCVN 6962:2001 - Vibration and shock. Vibration caused by construction
activities and industrial production. Maximum levels permitted for industrial and
residential areas.
- Decision No. 3733/2002/QD-BYT of the Ministry of Health issued on
10/10/2002 regarding the application of 21 occupational sanitation standards.
d. Standards related to soil quality
- Vietnam Regulation QCVN 15-2008: National technical regulation on plant
protection chemical residues in soil;
- QCVN 03:2008/BTNTM: National Technical Regulation on permissible limits
of heavy metals in soil.
e. Standards related to construction
- Viet Nam standard TCVN 7222: 2002; General requirements on the
environment for centralized domestic wastewater treatment plants;
- QCXDVN 01: 2008/BXD: Viet Nam construction regulation on construction
planning
- QCVN 07:2010/BXD: National Technical regulation of the urban technical
infrastructure facilities;
Drainage and wastewater treatment system project for Thai Hoa town, Nghe An province”
Environmental Impact Assessment (EIA) PCO Consultant, 2010
13
2.2. Environmental policies of the World Bank (WB)
Besides environmental review procedures and approval of the Government of
Vietnam, "The drainage and wastewater treatment system project for Thai Hoa town, Nghe
An Province" must be prepared and implemented in accordance with environmental and
social safety policies of the WB. Through studying the project area and proposed activities,
the policy on social and environmental safety of the World Bank follow as:
- Guidelines on Environmental Assessment OP 4.01 and BP 17.5
- Natural Ecosystem (OP/BP 4.04)
- Pesticide Management (OP 4.09)
- Culture heritage (draft OP 4.11 - OPN 11.03)
- Involuntary resettlement (OP/BP 4.12)
- Ethnic minority (OD 4.20)
- Forestry (OP/BP 4.36)
The environmental safeguard policy OP 4:01: This policy offers only the basic
requirements for environmental assessment process including public
consultation requirements for projects funded by the WB. OP 4:01 establishes
requirements for the classification of projects based on the environmental impact
levels of the project. Drainage and wastewater treatment project for Thai Hoa
Town belongs to the Class B project, so the project must prepare environmental
assessment report submitted to WB (the environmental assessment report must
be approved by the competent authority of the Government of Vietnam)Đọc ngữ
âm.
The environmental safeguard policy OP 4:01: This policy offers only the basic
requirements for environmental assessment process including public
consultation requirements for projects funded by the WB. OP 4:01 establishes
requirements for the classification of projects based on the environmental impact
levels of the project. Drainage and wastewater treatment project for Thai Hoa
Town belongs to the Class B project, so the project must prepare environmental
assessment report submitted to WB (the environmental assessment report must
be approved by the competent authority of the Government of Vietnam).
According to the policy on natural ecosystem (OP/BP 4:04): this policy gives
the approach of the WB for projects located in important areas of conservation
or likely affecting the natural environment. Thus, in the project area without any
natural ecosystems like virgin forest, mangrove forest, natural conservation area,
historical relic areas, sensitive ecological area, it is not required for preparing
report for this content. However, the contents of this assessment will be carefully
considered in the environmental assessment report.
According to the policy on cultural value (OP 4.11 - OPN 03.11): This policy
offers the WB's approach to the protection of cultural property. Thus, in the
project areas without the historical relics or cultural, religious-believable
conservation area, (the pagodas, temples, churches, cemeteries, ...) the separate
Drainage and wastewater treatment system project for Thai Hoa town, Nghe An province”
Environmental Impact Assessment (EIA) PCO Consultant, 2010
14
report to this content for project is not required. However, the content of this
assessment will be carefully considered in the environmental assessment report.
According to the resettlement policy (OP/BP 4.12): Resettlement plan report
(RP) has been prepared for the project. The environmental assessment report
will also mention the contents of evaluation of the scale and extent of being
affected temporarily or permanently from permanent or temporary land
acquisition or temporary requisition of land when the project is implemented,
cited from RP report.
Thus, for the drainage and wastewater treatment system project for Thai Hoa town, in
order to guarantee the environmental safeguard, it only has to prepare the environmental
impact assessment report (EIA) under the Policy on Environmental Safeguard OP 4:01 of
World Bank and Decree No.21/2008/ND-CP dated 28/02/2008, amending and supplementing
some articles of Decree No. 80/2006/ND-CP dated 09/08 / 2006 of the Government of
Vietnam.
Consultation: According to the operational procedures of the World Bank and the
Decree No. 21/2008/ND-CP, the project must carry out the consultation twice, the contents of
the counseling programs must be recorded.
The first consultation1 will be conducted for households that are likely to be affected
by the implementation of the project items. This consultation process is conducted in March,
2010 along with the socio-economic investigation, survey programs and data collection of the
background environment in the project area.
The 2nd consultation2 on the draft of EIA report was conducted in June 2010. The
minutes of the consultation meeting was attached in the annex.
Disclosure of information3: According to the operating procedures of the World Bank,
and the Decree No. 80/2006/ND-CP and Decree No. 21/2008/ND-CP, the EIA report must be
notified publicly. Environment Impact Assessment Report must be on display in Washington
DC, Vietnam Development Information Center (VDIC) in Hanoi, Thai Hoa town’s People's
Committee, Nghe An province’s Department of Natural Resources and Environment, the
Project Management Unit, people's committees of communes/wards in the study area of the
project.
2.3. Technical data sources
a. Source of documents, references
1. Le Thac Can and the group of authors (1994), Environmental Impact Assessment,
Publisher of Science and Techniques, Hanoi.
2. Trinh Xuan Lai (2002), Design calculation of wastewater treatment works,
Publisher of Science and Techniques, Hanoi.
3. Environmental Protection Law of the Socialist Republic of Vietnam, 2005.
4. The set of Vietnam Standards TCVN - 1995, 1998, 2005 on the environment, the set
1 Minutes of the first environmental consultation meeting of the project in March, 2010 is attached in the annex 2 Minutes of the second environmental consultation meeting of the project in June, 2010 is attached in the annex
3 Documents on disclosure of information is attatched in the annex.
Drainage and wastewater treatment system project for Thai Hoa town, Nghe An province”
Environmental Impact Assessment (EIA) PCO Consultant, 2010
15
of national technical regulations on the environment, MOH standards and current
supplementary standards.
5. Dang Kim Chi (2000), Environmental Chemistry, publisher of science and
Techniques,, Hanoi.
6. Hoang Trong Yem (2000), Organic Chemistry - Volume 3, publisher of science and
Techniques, Hanoi.
7. Tran Ngoc Chan (2000), air pollution and emission gas treatment - Volume 1,
publisher of science and Techniques, Hanoi.
8. Ngoc Chan (2000), air pollution and emission gas treatment - Volume 2, publisher
of science and Techniques, Hanoi.
9. Tran Ngoc Chan (2000), air pollution and emission gas treatment - Volume 3,
publisher of science and Techniques, Hanoi.
10. WHO – Assessment of sources causing soil, water, air environment pollution -
Volumes I, II Geneva, 1993.
11. Tran Van Nhan, Ngo Thi Nga (1999), Syllabus of Waterwaste treatment
Technology, publisher of science and Techniques, Hanoi.
12. Pham Ngoc Dang (2003), Air environment, publisher of science and Techniques,
Hanoi.
13. http://www.nea.gov.vn
b. Sources of documents, data of the project
- Feasibility Study Report (FS) of the Project
"The drainage and wastewater treatment system project for Thai Hoa town, Nghe An
Province";
- Report on the socio-economic investigation (SEI) of the Project
"The drainage and wastewater treatment project for Thai Hoa town, Nghe An Province";
- Report on willingness to connection (WTC) of the Project
"The drainage and wastewater treatment system project for Thai Hoa town, Nghe An
Province";
- Results of measurement, survey and analysis of environmental quality in the project area
of the Research Centre for Micro-climate, Architecture and Environment;
- Report on the Population and Population Change in 2009 – Statistics Department, Thai
Hoa town;
- Draft Plan of socio-economic development - Thai Hoa town in the period 2011 - 2015 -
Thai Hoa town’s People's Committee;
- Statistical Yearbook 2009 of Thai Hoa town;
- Statement and adjusted map of Thai Hoa urban development planning up to 2020
- Documents on the natural and socio-economic conditions of the study area and other
related documents.
- Legal documents related to the project;
Drainage and wastewater treatment system project for Thai Hoa town, Nghe An province”
Environmental Impact Assessment (EIA) PCO Consultant, 2010
16
3. ASSESSMENT METHODOLOGY
The process of preparing EIA report for "The drainage and wastewater treatment
system project for Thai Hoa town, Nghe An Province" will use the following methods:
Table. Assessment Methodology
Step Scope of work Methodology
1 – Research of
available
documents and
determine the data
requirements
- Research standards and
appropriate regulations related to
environmental quality, land use,
including the vulnerable position
and protect the historic, cultural,
land use control.
- Study the existing
documentation on the project
and environmental conditions,
the area affected by the project.
- Collecting, filtering and
aggregating the environment
data and the lack of data needed
to cater to the report.
- Planning for field surveys and
observation.
Table research. Data sources
used in this step is secondary
data provided by the following
agencies:
- PMU;
- PCO;
- Department of Natural
Resources and
Environment of Thai Hoa
town.
- Department of Natural
Resources and
Environment of Nghe An
Province, the
Environmental Protection
Agency of Nghe An
Province...
2- Site visit - Conducting field surveys,
observations and collect
information
- Implementation of monitoring
and collecting and evaluating
results;
- Comparison with the standards
and international standards to
assess the environmental status
and forecast trends and analyze
changes cause the abnormalities
of environmental quality
Use the following methods:
- field survey methods;
- Methods of identification;
- Methods of assessment;
Data: Primary data sources,
measured directly. Reliability
of data sources will be
adequately assessed in the EIA
report
3- Study the
components
- Synthesize and summarise
construction plans for each
component, together with its
specific detailed design
Table research.
This step must be done with
close cooperation with the
consultancy unit design,
construction and project
management boards (PMU);
4- Environmental
impact assessment
- Determine the potential impacts
of pre-construction, construction
and operation phase;
- Quantify the environmental
impacts.
- Determine the importance and
acceptable level of impacts.
- Evaluate issues of potential
- Methods of identification;
- Method of rapid
assessment;
- Check-list approach;
- Matrix method;
- Modeling;
Drainage and wastewater treatment system project for Thai Hoa town, Nghe An province”
Environmental Impact Assessment (EIA) PCO Consultant, 2010
17
environmental risks.
- Identify and estimate the extent
and quality of existing data, its
discrepancies and original data,
and specify the insignificant
issues
5- Propose
mitigation
measures
- Propose measures necessary for
mitigation of negative effects
and effective measures to
strengthen the positive impacts
- Forecast the remaining impacts
and estimate the extent of
damage;
- Establish a preliminary content
(impacts, mitigations) and
conduct consultations, gathering
the opinions of the People's
Committee of Ward / social
sectors.
- Table research;
- Modeling;
- Method of forecasting;
- Method of expert opinion;
- Method of map
overlapping;
6- Construct EPM - The construction of EPM should
pay attention to four aspects: (i)
measures to mitigate
environmental impacts, (ii)
monitoring plan / environmental
monitoring (iii) capacity
building plan, and (iv)
supervision of the
implementation of EMP.
- Table research, in
consultation with
stakeholders such as
Department of Natural
Resources and
Environment of Nghe An
Province, PMU and
World Bank;
7 – Public
consultation and
information
dissemination
- The environmental consultant
will assist PMU for consultation
and dissemination of information
to affected people for the
contents of such reports and
EPM
- Consultation comments from
local authorities, affected people
and groups.
+ Scope of the project and
potential environmental impacts;
+ The mitigation measures
proposed
+ Mechanisms for managing and
supervising the implementation.
- Interview;
- Questionnaire;
Drainage and wastewater treatment system project for Thai Hoa town, Nghe An province”
Environmental Impact Assessment (EIA) PCO Consultant, 2010
18
4. ORGANIZATION
4.1. Consultant for preparing Environment Impact Assessment Report
EIA report for "The drainage and wastewater treatment sub-project for Thai Hoa town,
Nghe An Province" presided by Thai Hoa town People’s Committee that the project owner
with the advices of the Consultant Association: Pacific Ocean Engineering Joint Stock
Company (PCO) and Dai Viet Construction Consulting Joint Stock Company (DAVICO) for
implementation of survey, investigation, measurement design of the project, follow ans:
Name of company: Pacific Ocean Engineering Joint Stock Company (PCO)
Represented by: Mr. Nguyen Cong Minh
Position: Director of PCO
Head office: No. 34D, Lane 249 Doi Can, Ba Dinh, Hanoi
Tel: 043.6248871 Fax: 043. 6218891
Email: [email protected]
There was close cooperation during the implementation of the report as follows:
- The Standard Lab of the Ministry of Construction LAS XD376 – the Research
Center for Micro-climate, Architecture & Environment (RCAICE).
- Department of Natural Resources and Environment, Thai Hoa town Nghe An
province.
- People's Committees, Fatherland Front Committees of the wards/ communes,
Thai Hoa town, Nghe An province.
- Experts in the field of Environment Impact Assessment.
No. Main contents of EIA
report
Participants Specialization
1 Team leader Eng. Nguyen Cong
Minh/Director
Drainage, water supply
and environment
2 Brief description of the
project and assessment of
the selected technology.
Eng. Nguyen Trung
Hieu
Drainage, water supply
and environment
Eng. Le Van Truong Drainage, water supply
and environment
3 Measuring and analyzing
current status of
background environment
MA. Trinh Van Khoa Evironmental science
Eng. Nguyen Van Hiu Evironmental science
Eng. Tran Trung Quan Evironmental science
4 Environment Impact
Assessment and proposing
mitigation measures,
prevention and response to
MA. Do Thi Kim Xuan Geography /Hydrography
Geology
BA. Nguyen Thi Thuy Evironmental science
Drainage and wastewater treatment system project for Thai Hoa town, Nghe An province”
Environmental Impact Assessment (EIA) PCO Consultant, 2010
19
the environmental
problems. BA. Phan Thi Hang Evironmental science
5 Proposing environmental
mangement and monitoring
program.
MA Pham Tuan Linh Evironmental science
Eng. Phung Cong
Thanh
Evironmental technology
6 Community consultation MA. Do Thi Kim Xuan Geography /Hydrography
Geology
BA. Nguyen Thi Thuy Evironmental science
.
Drainage and wastewater treatment system project for Thai Hoa town, Nghe An province”
Environmental Impact Assessment (EIA) PCO Consultant, 2010
20
CHAPTER I: PROJECT DESCRIPTION
1.1. PROJECT NAME:
"Drainage and wastewater treatment system project for Thai Hoa town, Nghe An Province"
1.2. PROJECT OWNER:
1- Executing agency: Nghe An Provincial People's Committee
a) Address: No. 3 Truong Thi street, Vinh City, Nghe An province.
b) Tel: 038.3 844522 Fax: 038.3 843049
2- Project Owner: Thai Hoa town’s People's Committee
a) Address: Kim Tan block, Thai Hoa town, Nghe An province.
b) Tel: 0383.812.923 Fax: 0383. 881.201
3- Representative of the Project Owner:: the PMU of the drainage and wastewater treatment
system project for Thai Hoa town
a) Address: Kim Tan block, Thai Hoa town, Nghe An province.
b) Tel: 0383.812.923 Fax: 0383. 881.201
1.3. GEOGRAPHICAL LOCATION OF THE PROJECT
Thai Hoa town is located in the Northwestern area of Nghe An province with
geographical coordinates: from 19o13’ – 19
o33’ of north latitude and 105
o18’ – 105
o35' of east
longitude 90km distant from Vinh town to the West, the boundaries of the town are limited as
follows:
- Adjacent to Nghia Dan district to the North, South and West;;
- Adjacent to Quynh Luu district and Nghia Dan district to the East
Figure H-1: Location of Thai Hoa town on Nghe An provincial map
1.3. TOTAL INVESTMENT
Total investment of the project: 469,650,927,000 VND, equivalent to 24,334,245 USD
. Of which:
WB fund (USD) Counterpart fund (USD)
Value (x1000VND) Value USD Value (x1000VND) Value USD
326,540,035,000 16,919,173 143,110,892,000 7,415,072
69,5% 30,5%
The first investment is the source of the preferential credit loans from the
International Development Association (IDA) of The World Bank (WB) (for the work of
construction, equipment and materials supply, capacity improvement and institutional
development).
Drainage and wastewater treatment system project for Thai Hoa town, Nghe An province”
Environmental Impact Assessment (EIA) PCO Consultant, 2010
21
The second is the counterpart fund of the Nghe An Provincial People's Committee (for
the preparation of investment, land acquisition, compensation and site clearance, management
board, design of construction drawings and fees of appraisal, verification).
Table. Investment capital distribution
No. Work items
Amount (1000 VND)
Total value ODA- WB Ratio Counterpart
fund Ratio
1 Stormwater drainage network 141,101,611112,881,289 80.00% 28,220,322 20.00%
2 Sewerage network -HDPE-PN6 67,910,821 54,328,656 80.00% 13,582,164 20.00%
3 Pressure pipe HDPE-PN8 10,273,098 8,218,478 80.00% 2,054,620 20.00%
4 Wastewater pumping station 2,014,940 1,813,446 90.00% 201,494 10.00%
5
WWTP - Phase I, CS:
4.000m3/day 41,380,075 33,104,060 80.00% 8,276,015 20.00%
6
WWTP - Phase I, CS:
2.000m3/day 27,581,853 22,065,483 80.00% 5,516,371 20.00%
7 House connection 13,395,800 10,716,640 80.00% 2,679,160 20.00%
8
Equipments support the operation
and management of
drainage/sewerage network
(treatment plant, pumping station
and wastewater sewer network). 24,554,240 19,643,392 80.00% 4,910,848 20.00%
9 Indirect investment cost (*) 56,413,701 0 0.00% 56,413,701 100.00%
10 Contingency (10%) 85,024,787 63,768,590 75.00% 21,256,197 25.00%
11
TOTAL -ROUNDED
(1000VNd) 469,650,927326,540,035 69.53% 143,110,892 30.47%
12 CONVERTED - USD 24,334,000 16,919,000 69.53% 7,415,000 30.47%
13 Ratio % 100.0% 69.53% 30.47%
Remark:
(*) Costs for construction supervision, training, O&M guidance using ODA fund – World
Bank.
(**): Unit: 1USD = 19.300 VND
1.5. SCOPE OF WORK
1.5.1. The service scope of project:
"The drainage and wastewater treatment system sub-project for Thai Hoa town " is invested
for construction in the area of Thai Hoa town, including 6 administrative units of the
following 4 wards: Phong Quang, Hoa Hieu, Quang Tien, Long Son and the following 2
communes: Nghia My, Nghia Tien.
Figure. H-2: Study area and serving area of the project
Following closely the detailed construction planning of Thai Hoa town approved by Nghe An
provincial people’s committee enclosed with Decision No. 3907/2008/QĐ-UBND dated
12/9/2008 about designing a drainage/sewerage system. Contents of technical – financial
proposals for the project are summarized in the table below:
Drainage and wastewater treatment system project for Thai Hoa town, Nghe An province”
Environmental Impact Assessment (EIA) PCO Consultant, 2010
22
Table 1: Technical proposals for the project
No Item Technical solutions
1 Location Thai Hoa town - Nghe An province
2 Types of drainage
system
Separate system: Construct two separate systems: Storm water sewer
system and wastewater sewer system
• Wastewater sewer system: Domestic wastewater and production
wastewater will come into one sewer system and then be treated in the
treatment plant.
• Stormwater sewer system: Rainwater is collected into one separate
sewer system and then directly discharged into rivers, canals and
ditches without treatment.
3 Investment phasing Phase 1- Up to 2020: Focus investment on constructing the storm
water sewer system, the wastewater collection and treatment system
for existing area and the town center.
Phase 2 – Up to 2030: Invest in constructing for the expanded areas of
the town, to enhance capacity of the wastewater treatment plant.
4 Stormwater drainage system.
4.1 Stormwater drainage
catchment
There area 11 rainwater drainage catchments
4.2 Proposed work on
Stormwater drainage
- Construct new sewer lines with diameter from D400 to D1400, RC
channel B800 -B1000
- Construct 36 discharge outlets
- Construct 656 surface intakes
5 Wastewater sewer system
5.1 Wastewater drainage
catchment
There are 06 catchments
5.2 Wastewater
collection sewer
system
To construct new wastewater collection sewer lines using pipe HDPE-
PN6 (for gravitational sewers) and Pipe HDPE-PN8 (for pressure
sewers) with dimension of D300-D600 along routes in Thai Hoa town:
- Construct 989 manholes
- Construct 494 connection manholes
5.3 Wastewater pumping
station system
Construct new wastewater pumping stations to convey wasterwater to
the treatment plant, reduce the piping depth. There are 6 WWPSs built
in diffirent locations in town.
5.4 Wastewater
treatment plant
Construct 2 WWTPs on the East and the West river banks of Hieu
river.
5.4.1 Wastewater
treatment plant No 1,
capacity of 6,000
m3/day
- Location: The plant is built in the field of block 4, 5, 6 of Long Son
ward (near Giong area). This location is far from the residential area
and ensures the requirements of Vietnam Construction Standard on
construction of treatment plant.
- Total area of land occupation: 12.7ha
- Diagram of wastewater treatment process:
Bar screen⇒ Receiving chamber ⇒ Anaerobic pond ⇒ facultative
pond⇒ Stabilization pond ⇒ Hieu river.
- Treated water quality meets class B standard according to QCVN
14-2008
- Receiving source: Hieu river
5.4.2 Wastewater - Location: The plant is constructed at crop field of hamlet 1 of Nghia
Drainage and wastewater treatment system project for Thai Hoa town, Nghe An province”
Environmental Impact Assessment (EIA) PCO Consultant, 2010
23
No Item Technical solutions
treatment plant No 2
capacity of 3,000
m3/day
Tien commune. This position is far from residential area and ensures
the requirements of Vietnam Construction Standard on construction of
treatment plant.
- Total area of land occupation: 9.1 ha
- Diagram of wastewater treatment process:
Bar screen ⇒ Receiving chamber ⇒ Anaerobic pond ⇒ facultative
pond ⇒ Stabilization pond ⇒ Hieu river.
- Treated water quality meets class B standard according to QCVN 14-
2008
- Receiving source: Hieu river
5.5 House connection Construct connection points from households (behind septic tanks or
sanitation works) to the outside drainage system, the works include
wastewater pipeline from households to the collection network and
transfer boxes (manholes).
Number of connection points: 6098 households
6 Assistance for
operation and
maintainance
- To procure operation and maintenance equipments of the drainage
system: Vacuum truck, road cleaning car, portable wastewater sucking
pumps
1.6.2. Construction of stormwater sewer system
Structure of stormwater sewer system
The system is built as follows:
Storm water drainage catchment.
Surface
intakes
Tertiary
sewers
Surface
intakes
Surface
intakes
Main drainage lakes and rivers
Tertiary
sewer
Tertiary
sewer
Tertiary
sewer
Surface
intakes
Secondary sewer: Main drainage sewers of the city
Tertiary sewer: Drainage sewers for sub-areas, alleys and streets
Primary sewer: main drainage lakes and rivers
Drainage and wastewater treatment system project for Thai Hoa town, Nghe An province”
Environmental Impact Assessment (EIA) PCO Consultant, 2010
24
Catchments Location/boundary
Catchment 1: This catchment is part of Quang Phong ward limited by the intersection of
ward’s people's committee on the way to Bai Tranh, high mountains is in the
east and way to Bai Tranh is in the west. The total area of this catchment is
213ha, and the population is 4,702 people. This catchment discharges water to
Khe Me lake from where discharging water to Hieu river.
Catchment 2: This catchment is a part of Quang Phong ward limited by intersection at
ward’s People’s Commitee to the north, Hieu river is in the west and way to
Bai Tranh is in the east. The total area of this catchment is 97ha, and
population is 2,322 people. This catchment area discharges water to Hieu
river.
Catchment 3: This catchments basin is part of Quang Phong ward limited by the intersection
of ward’s people's committee in the upper, high mountains are in the east and
Hieu river is in the west. The total area of this catchment is 147ha, and the
population is 3,483 people. This catchment discharges water to Khe Me lake
from where discharging water to Hieu river.
Catchment 4: This catchment is part of Quang Phong ward limited by Khe To, high
mountains are in the east and Hieu river is in the west. The total area of this
catchment is 69ha, and the population is 1,688 people. This catchment
discharges water to Hieu river and Khe To.
Catchment 5 This catchment is part of Hoa Hieu ward, next to Khe to, high mountains are
in the east, the remaining are is next to Tan Thang block, Tan Tien block. The
total area of this catchment is 170ha, and the population is 5,626 people. This
catchment discharges water to Khe To from where discharging water to Hieu
river.
Catchment 6: This catchment includes Hoa Hieu ward to the South of National Highway
NO 48; Bai Sen lake of Tan Tien block is in the North. The total area of this
catchment is 113ha, and the population is 4,505 people. This catchment
discharges water to Bau Sen lake from where discharging water to Hieu river.
Catchment 7: This catchment includes part of Hoa Hieu ward and part of Long Son ward;
high mountain is in the northwest, Nghia Hoa commune is in the west.. The
total area of this catchment is 394ha, and the population is 8,265 people. This
catchment discharges water to Lo Gach lake (planned to become detention
reservoir) from where discharging water to Hieu river.
Catchment 8: This catchment is in the north of Long Son ward, at the area of Nghia Hoa Cu
secondary school; Tan Long commune is in the north, Hieu river is in the west
and the north. The total area of this catchment is about 32ha, and the
population is 426 people. This catchment discharges water to Hieu river.
Catchment 9: This catchment includes part of Hoa Hieu ward and part of Long Son ward;
high mountain is in the northwest, Nghia Hoa commune is in the west.. The
total area of this catchment is 394ha, and the population is 8,265 people. This
catchment discharges water to Lo Gach lake (planned to become detention
reservoir) from where discharging water to Hieu river.
Catchment
10:
This catchment is part of Quang Tien ward and part of Nghia Tien ward; on
National highway No 48. The total area of this catchment is 317ha, and the
population is 3,236 people. This catchment mainly discharges water into lakes
and from where discharging water to Hieu river.
Drainage and wastewater treatment system project for Thai Hoa town, Nghe An province”
Environmental Impact Assessment (EIA) PCO Consultant, 2010
25
Figure H-3: Rainwater drainage catchment, scope of design of rainwater drainage system.
Proposed items for rain water drainage
Works for stormwater drainage item are as follows:
� Construct a number of new sewer lines on road routes where there are no stormwater
sewer system in order to enhance the drainage capacity:
- Construct new round RC sewer line D1000 along national road No. 48 for the section
from national road No. 48 to Hieu Bridge and from Nghia Dan coach station to Hieu
Bridge with a total length of 5,655m,
- Construct new round RC sewer line D800 along road routes in the town, including
road routes on national road No. 15A, near Bau Sen lake, on national road No. 48
and in Quang Phong ward with a total length of 4,455m.
- Construct new round RC sewer line D400 - L10,202m and D600 - L14,009m along
roads in the town with a total length of 22,734m.
- For lines with great slope, in order to ensure that water flow will not exceed the
speed of anti-erosion and sediment prevention, all channel s should be constructed of
reinforced concrete with dimensions and width as: B800 - L4,778m; B1000 -
L9,931m,
� Construct 656 new surface intakes with water inlets,
- Sewer lines on pavements will be round prefabricated RC centrifugal pipes, with a
load requirement of class B (H13). The piping depth at the start pont of the line:
h=0.5÷0.7m. Sewer lines are designed to self-flow with the slope complying with the
Code >=1/D,
- Round sewer lines under road will be round prefabricated RC centrifugal pipes, and
ensure load requirement of class C (H30). The depth of sewers at the start point of
the line: h=0.8m. Sewer lines are designed to self-flow with slope complying with
the Code >=1/D,
� Construct 36 discharging outlets of various types at different places in the town
� Install flood-prevention penstocks for existing discharging outlets.
Table1.1. Proposed quantity for storm water drainage item
RC pipe DN400 m 10,202
RC pipe DN600 m 14,009
RC pipe DN800 m 4,455
RC pipe DN1000 m 5,655
RC pipe DN1200 m 2,864
Catchment
11:
This catchment is part of Quang Tien ward and part of Nghia Tien ward; Hieu
river is in the east; National highway No 48 is in the north. The total area of
this catchment is 353ha, and the population is 3,827 people. This catchment
discharges water to Hieu river.
Drainage and wastewater treatment system project for Thai Hoa town, Nghe An province”
Environmental Impact Assessment (EIA) PCO Consultant, 2010
26
RC pipe DN1400 m 594
RC channel B800 m 4,778
RC channel B1000 m 9,931
Discharge outlet each 37
Surface intakes each 656
Figure H-42: Proposed items for stormwater drainage system.
1.6.3. Wastewater sewer system
Structure of wastewater sewer system
Organizational chart of wastewater drainage is shown below:
Wastewater drainage catchment:
There are 06 catchments divided as follows:
Domestic,
service &
public
wastewater
Wastewate
r
collection
manhole Domestic,
service &
public
wastewater
Wastewater
collection
manhole
Wastewater
treatment
plant
Tertiary sewers
Secondary sewers
Primary sewers
Receivers
Wastemn
Drainage and wastewater treatment system project for Thai Hoa town, Nghe An province”
Environmental Impact Assessment (EIA) PCO Consultant, 2010
27
Catchments Location/boundary
� The area in the east of Hieu river
Catchment 1: This catchment collects wastewater in part of Quang Phong. This catchment
locates on the route from Thai Hoa to Bai Tranh in the area from Khe To
bridge across Quang Phong primary school. The pumping station of this
catchment locates near Quang Phong primary school. The population of this
catchment is 2,052 people and the total area is about 65ha.
Catchment 2: This catchment is in Hoa Hieu ward, which collects wastewater from near
Hieu river to the west of the road from Thai Hoa Vegetable Projection office
and Thai Hoa high school to Khe To bridge. The pumping station of this
catchment locates at the intersection of road No.15 towards Khe To and alley
16 of Tan Thang block. The polulation of this catchment is 4,892 people and
the total area is about 36ha.
Catchment 3: Covering the central area of Thai Hoa town, Hoa Hieu ward, in cluding
national road 48 from the broast cast station to Hieu bridge and from the Post
office of Nghia Dan district to Dong Tien area, from Bau Sen lake to Thai
Hoa nursary school.. The pumping station of this area is located at the
intersection on the national road 48. The population of this area is 5079
people and area is 66 ha.
Catchment 4: This catchment covers a part of Hoa Hieu ward, a part of Long Son ward and
a part of Nghia My commune which collect wastewater along the national
road No. 48 from Nghia My commune to the area bodering Hieu river.The
pumping station of this area is located on the new road route towards Hieu
newly planned bridge. The population is 10,085 and the total area is of about
53 hectars.
� The area in the west of Hieu river
Catchment 5 Covering a part of Quang Tien ward and a part of Nghia Tien commune,
collecting wastewater along national road No. 48 towards Quy Hop from
Nghia Dan healthcare center to the lower part of high hills. The pumping
station of this area is located at the intersection of national road 48 and the
road to the culture house of Thi Nghiem hamlet. The population is 6,717
people and the total area is about 299 hectars.
Catchment 6: Covering a part of Quang Tien ward and a part of Nghia Tien commune,
collecting wastewater from the whole area along national road No. 15A from
Nghia Quang market on national road No. 15A to Hamlet 4 of Nghia Tien
commune. The pumping station of this area is located on the road near Rubber
Company. The population is of 4,966 and the total area is of about 229
hectars.
Figure H-5: Wastewater catchment.
Investment items for wastewater sewer system
(i) Wastewater collection sewer system
Determination of specific investment:
- Construction of wastewater collection sewer system using round gravitational sewer
pipe HDPE- PN6:
Drainage and wastewater treatment system project for Thai Hoa town, Nghe An province”
Environmental Impact Assessment (EIA) PCO Consultant, 2010
28
Pipe HDPE - PN6 DN300 34,135 m
Pipe HDPE - PN6 DN400 475 m
Manhole 989 manhole
Connection manhole 494 manhole
Connection pipe PVC-D160 25,958 m
- Construction of pressure Pipes HDPE-PN8-PN10
Pipe HDPE PN8 DN100 1,004 m
Pipe HDPE PN8 DN150 730 m
Pipe HDPE PN8 DN200 1,627 m
Pipe HDPE PN8 DN250 3,414 m
- Construct 6.089 connection points (connection manhole) to collecct wastewater from
transfer box to the tertiary sewer system. The transfer boxes collect wastewater from
septic tanks of households and transfers to connection manholes.
- Construct manholes on the route complying with current regulations of Viet Nam of
which the distance between manholes not exceeding 50m.
Figure. H-3: General layout of wastewater sewer system
(ii) Wastewater pumping station system
There are 6 WWPSs to be constructed as follows:
- WWPS No 01, capacity of 470 m3/day
- WWPS No 02, capacity of 1.780 m3/day
- WWPS No 03, capacity of 2.010 m3/day
- WWPS No 04, capacity of 4.530 m3/day
- WWPS No 05, capacity of 1.980 m3/day
- WWPS No 06, capacity of 2.870 m3/day
Figuer. H-7: Typical detail of WWPS
(iii)Location of wastewater treatment plant
Item Technical solutions
Wastewater treatment
plant No 1 capacity of
4,000 m3/day.
- Location: The plant is built at crop field of block 4, 5, 6 of Long Son
ward (near Giong chasm). This position is far from residential area
and ensures the requirements of Vietnam Construction Standard on
construction of the treatment plant.
- Total area of land occupation: 12.7ha
- The wastewater treatment process:
Bar screen ⇒ Receiving chamber ⇒ Anaerobic pond ⇒ Facultative
pond ⇒ Stabilization pond ⇒ Hieu river.
- Treated water quality meets class B according to QCVN 14-2008
- Receiving source: Hieu river
Drainage and wastewater treatment system project for Thai Hoa town, Nghe An province”
Environmental Impact Assessment (EIA) PCO Consultant, 2010
29
Wastewater treatment
plant No 2 capacity of
2,000 m3/day night
- Location: The plant is built at crop field of hamlet 1 of Nghia Tien
commune. This location is far from residential area and ensures the
requirements of Vietnam Construction Standard on construction of
treatment plant.
- Total area of land occupation: 9.1 ha
- the wastewater treatment process:
Bar screen ⇒ Receiving chamber ⇒ Anaerobic pond ⇒ Facultative
pond ⇒ Stabilization pond ⇒ Hieu river.
- Treated water quality meets class B according to QCVN 14-2008
- Receiving source: Hieu river
Figure H-84: General layout of WWTP 1.
Figure H-9: General layout of WWTP 2.
(iv) The receiving source of treated water.
Receivers of 2 treatment plants in the East and the West of Hieu River:
- The plant in the East: Giong area which is about 300m far from Hieu River
- The plant in the West: directly into Hieu River
The discharge outlet of the treated water is located at the downstream of Hieu River, where
the water is mainly used for agricultural irrigation and drainage.
Based on the water demand from Hieu River at the location of water discharge and the
requirements of environment protection as stipulated in Vietnam Standard QCVN
14:2008/BTNMT, the treatment process of wastewater treatment plant should ensure that the
wastewater treatment can meet standard class B before discharged into the receiver.
Table 1.2 : Required quality of input wastewater of treatment plant
No. Parameters Unit
Input
wastew
ater
quality
Standard QCVN 14:2008
(class B)
1 PH 7.2 5-9
2 Total suspended substances
(SS)
mg/l 255 100
3 BOD5 Mg/l O2 606 50
4 Total N
mg/lN 60 60
5 Total oil and grease
mg/l 4.17 20
6 Total Coliform MPN/100ml 24000 5,000
(v) Wastewater collection process:
Wastewater collection process is summarized as follows:
- Sewerage system is a gravitational one and the structure of the sewerage networks is
as follows: wastewater from households, restaurants, services, small productions,
agencies, public institutions, etc will be collected into sewerage system through
connection manholes and then conveyed to the main collection sewer system to the
wastewater pumping station and finally, to the treatment plant.
- Sewerage network depend largely on existing conditions of road routes, residential
Drainage and wastewater treatment system project for Thai Hoa town, Nghe An province”
Environmental Impact Assessment (EIA) PCO Consultant, 2010
30
distribution densit, etc. Basically, sewer lines will follow the axial road routes of the
town, placed under road or pavements.
- However, due to the terrain characteristics in some areas that residential houses are
much lower than road surface (1-3m). Therefore, collection pipelines will be installed
behind households. This allows that the piping depth will not be too deep and it is not
required to construct many wastewater pumping stations.
- The terrain elevation is absolutely made used for the drainage direction to minimize
the pipe laying depth. However, as these are gravational sewers, the pipe laying depth
will increase gradually at the end of the line. So pumping stations will be constructed
as the pipe laying depth exceeds 4.5m. Wastewater pumping stations will be
constructed to reduce the piping depth for next phases and help to increase pressure of
wastewater conveyed to the treatment plant. Location of the wastwater pumping
stations is determined through hydralic calculation and volume. Wastewater collection
pipelines must be deeper than those conveying wastewater from households to the
outside.
- Manholes arranged on the pipeline at the average distance of 40m for pipeline D300-
D400 and 50m for pipelines D500-D800.
(vi) Wastewater treatment process
In order to treat wastewater before discharging into receiving source, a series of
biological ponds will be proposed consisting of receiving chamber, bar screen, sand
sedimentation tank, anaerobic pond, facultative pond, aerobic pond, the wastewater treatment
process is as follows:
Figure. H-10: Diagrame of wastewater treatment process.
This technology is suitable with the areas far from the residential areas and having a
large land area. It ensures the treated water quality meeting class B, QCVN 14:2008/BTNMT,
water used for irrigation and agricultural production.
Anaerobic pond: where the process of wastewater settling and biochemical
degradation of dissolved contaminants occurs and the sediment continues to degrade because
of anaerobic micro-organisms. The content of contaminants which can be handled by NOS
(BOD) is of 350-850 kg/ha/day. In the anaerobic pond, the NOS content of wastewater
reduces due to methane fermentation. In order to ensure anaerobic conditions and temperature
regimes, these ponds must have a relatively great depth (2.4 - 3.6 m). The efficiency of NOS
decrease in the pond may be up to 70%. However, the NOS content of wastewater out-of-the-
pond is still quite high, up to 100-300 mg/l. Therefore, this type of pond is mainly used for
super-dense industrial wastewater treatment and used as the level I pond in multi-level pond
complex.
Facultative pond: this pond type is most commonly in wastewater treatment. The
amount of contaminants which can be treated in the pond by NOS can be up to 300 kg
/ha/day. According to applicable norms and regulations, the estimated amount of wastewater
in this pond is of 250 m3/hectare/day (37 kg /ha/day by NOS) for wastewater after treated by
biological methods or by the amount of oxygen of 6 -89 O2/m3/day & night depending on
climatic conditions. In the facultative ponds, two processes take place at the same time:
aerobic biochemical oxidization process of dissolved organic contaminants and methane
fermentation (anaerobic) of sediment at the pond bed. Oxygen is necessary for micro-
organism to oxidize aerobically organic materials because of air diffusing along water surface
and alga and moss created in the process of photosynthesis. Conversely, moss and algae uses
Drainage and wastewater treatment system project for Thai Hoa town, Nghe An province”
Environmental Impact Assessment (EIA) PCO Consultant, 2010
31
CO2, phosphates, nitrogen amon generated by microorganisms in the process of resolution of
organic substances.
The characteristics of the arbitrary pond are as follows: in terms of depth, water is
divided into three layers of aerobic, medium and anaerobic from top to bottom. Seaweed and
alga develop in self- nutrition type and depend on lighting conditions. For wastewater, the
light intensity on water surface and through the depth of 40-70 cm is reduced by 99%. Thus
the most powerful photosynthesis area limits to a certain depth only. Therefore, the selected
depth of the pond must be a little greater than the depth of photosynthetic area and equal to
0.9 - 1.5 m.
Stabilization pond (aerobic): This type of pond is divided into two groups: natural
aeration pond and artificial aeration pond.
- Natural aeration pond: oxygen is supplied due to the diffusion through aeration
surface and mainly thanks to the ability of photosynthetic of alga and seaweed. Pond which is
supplied oxygen by photosynthesis of algae and seaweed is called high load pond.
The process of photosynthesis takes place only at a small depth, high load ponds are
thus often built with depth of 15 - 30 - 50 cm so that the light can radiate to the pond bottom.
Because of disturbance in the pond, aerobic conditions are met completely. High load pond
can handle wastewater with the volume of contaminants by NOS (BOD) of 300 kg / ha/day &
night. In order to combine wastewater treatment with algae and seaweed growing for raising
livestock (pigs, chickens, ducks), it is very helpful to build this type of high load pond. The
period that water storage in high load ponds is usually for 3-7 days and nights.
- Artificial aeration pond: Aeration can be done by blowing compressed air or other
mechanical devices or leading water into the pond in rain spray type. The water retention time
in the pond is from 2-3 days to 2 weeks (but usually not more than 3 days and nights). Ponds
are constructed with a depth range from 1.5 to 5 m. The capacity of wastewater treatment is
very high, which can reach 404 kg/ ha/ day & night. It is possible for putting activated sludge
into the pond just like in the aeration tank.
(vii) Sludge treatment process:
In order to treat sludge after a long time in ponds, a sludge drying bed is proposed to
use before it is transported to the disposal site. The sludge treatment process is as follows:
Dredging sludge in the pond to transfer to the sludge drying bed occurs
discontinuously (about twice a year for one pond). Therefore, the consultant proposes that
sludge will be pumped from the pond to the sludge drying bed by using portable pumps. Once
any pond is required for dredging, operator may install sludge pumps temporarily to convey
sludge to the sludge drying bed. After completion of the work, pumps will be put into the
storage.
Portable sludge pumps are submersile ones which can be easily installed and removed.
They are fixed on the platforms in the pond. At the location of pump, sludge is collected and
pumped to the sludge drying bed.
These submersile pumps are equal to the normal pumping station. They are advanced
type with automatic control system to regulate flow, hig safety degree, easy operation and
management.
Sludge taken
from ponds
Sludge drying
bed
Disposal site
Drainage and wastewater treatment system project for Thai Hoa town, Nghe An province”
Environmental Impact Assessment (EIA) PCO Consultant, 2010
32
(viii) Land area used for constrution of Wastewater treatment plant
- Treatment plant No.1 will occupy an permanent area of 12,ha.
- Treatment plant No.2 will occupy an permanent area of 9,1ha.
(ix) Household connection of the project:
Construct house connection points (behind septic tanks or sanitation works) to the
outside drainage system including wastewater pipeline from households to the transfer boxes.
Number of connection points: 6089
®−êng - road vØa hÌ - sidewalk
cèng tho¸t n−íc
hè ga ®Êu nèi nhµ d©n
connection manhole
drainage-pipe
house
Diagram:Wastewater collection connected from households.
Figure: Structure of Household connection
1.6.4. Management and operation of drainage and wastewater treatment system
Equipments supporting to the management and operation:
After the project is put into operation, the Urban Environment Company of Thai Hoa
town (URENCO) will undertanke the management and operation of the drainage and
wastewater treatment system. To serve the management and operation of the drainage system,
Household
Household
Household
Connection manhole
Town wastewater collecti sewer
D160 - L<=20m
Drainage and wastewater treatment system project for Thai Hoa town, Nghe An province”
Environmental Impact Assessment (EIA) PCO Consultant, 2010
33
the project should support the operation and maintenance equipments of drainage system such
as sludge dredging truck, street cleaning car.
Hereinafter are the proposed equipments purchased for the management and operation
of drainage system in Thai Hoa town.
Table 1.2: Equipments
No. Type of equipments Unit Quantity
1 Vacuum truck Item 02
2 Pressure sewer cleaning truck Item 02
3 Sludge transporting truck Item 02
4 Computer system Set 02
5 Labour safety equipments Item 01
6 Portable testing equipments Item 01
Chemicals, power and water for wastewater treatment system.
As the waste water treatment process of the project is a series of biological ponds, the
operation of the waste water treatment plant uses not much chemicals, only chlorine is
used for disinfection in contact tank prior to discharge into receiver of Hieu
river. According to technical calculations in the feasibility study report of the project,
the amount of chlorine used for operating the treatment plant is 3 g/m3, with a total
treatment capacity of the phase 1 and phase 2 of the wastewater treatment plant is
6000 m3/day, so the maximum amount of chlorine used for operating at full designed
capacity of the wastewater treatment plant is 18 kg /day.
Water demand during the operation is not considerable which is used mainly for
washing, cleaning equipments of maintenance and operation of sewers and wastewater
treatment plant, water supplied for living activities of operators, watering trees,
cleaning internal roads, etc in the treatment plant, .. average amount of about 50-80
m3/month, the treatment plant will be connected to the existing water supply system in
Thai Hoa town.
Power supply: Power supplied for treatment plant is taken from high voltage source in
the area.
Power supply for 6 pumping stations:
- Pumping station No. 1: Power is taken from transformer station of Quang Phong
Primary school, about 100m far from Pumping station. P = 10 kW
- Pumping station No. 2: From transformer station near Primary school of Thai Hoa
town, about 300m far from Pumping station No. 2, 200m far from Pumping station
No. 3. P = 24 kW
- Pumping station No.3: From transformer station which is about 300m far from from
PS and near Thai Hoa commune People’s Committee.
- Pumping station No. 4: From transformer station on the national road 48, near the
entrance of the town, about 200m far from Pumping station 6. P = 20 kW
- Pumping station No. 5: From transformer station of the village, which is about 80m
far from Pumping station. P = 10 kW
Drainage and wastewater treatment system project for Thai Hoa town, Nghe An province”
Environmental Impact Assessment (EIA) PCO Consultant, 2010
34
- Pumping station No.6 From transformer station on the road 48 which is about 80m far
from the PS. P = 10 kW
Power supply for treatment plant:
� Power supplied for the treatment plant is taken from low voltage power source in the
surrounding area of the treatment plant. Power for the treatment plant 1 is taken from
the low voltage power source which is 200 m far from the plant. Power for the
treatment plant 2 is from the low voltage power source which is 80 m far from the
plant.
� The construction of a separate transformer sub-station for the treatment plant is not
necessary because the power consumption is not much (only for lighting and sludge
pumps with small capacity). Power capacity for the TP1 is 200 KW/day and for the
TP2 is 100kw/day.
Organization of workforce and project management.
As mentioned in the previous sections, in order to manage effectively the
infrastructure system of the town, and to unify in terms of functions and duties, the ,
consultant recommends that the management and operation of drainage system of the town
will be undertaken by Urban Environment Company of Thai Hoa town.
The main activities of Thai Hoa URENCO will be: Collection and treatment of waste,
management of drainage system, the main drainage rivers, streams of the town, dredging,
maintenance of the sewer network , ... Thai Hoa URENCO will play a critical role in ensuring
environmental sanitation conditions of the town..
Figure H- 8. Organizational structure of management and operation of the wastewater
treatment system.
1.6. IMPLEMENTATION SCHEDULE
Table 1.3. Project Implementation Schedule
No. Contents Completion Date
1 Preparation of construction investment project 08/2010
2 Approval of FS 10/2010
3 Official appraisal from WB 12/2010
Director
Vice director of
Admin
Vice director of
engineering
Admin
Departme
nt
Financi
al
Depart.
Depart of
Planning and
Engineering
Operatin
g Depart. WWTP Network
Mana &
oper Team.
Drainage and wastewater treatment system project for Thai Hoa town, Nghe An province”
Environmental Impact Assessment (EIA) PCO Consultant, 2010
35
4 Negotiating and signing the agreement between WB
and the Government of Vietnam
06/2011
Preparing construction drawings 09/2011
5 Construction and installation bidding 11/2011
6 Approving bidding results, negotiation, contract
awarding
12/2011
7 The agreement comes into effective 01/2012
8 Completion of Construction of components of the
project
11/2013
9 Operation, commissioning and handing over 12/2013
Drainage and wastewater treatment system project for Thai Hoa town, Nghe An province”
Environmental Impact Assessment (EIA) PCO Consultant, 2010
36
CHAPTER II: NATURAL, SOCIO-ECONOMIC AND ENVIRONMENTAL
CONDITIONS
2.1 NATURAL CONDITIONS
2.1.2. Topography and area
• Topography:
Thai Hoa is a mountainous urban with quite complex terrain which is divided by Hieu
river, including some low hills with some deep points and low valleys alternate with hillsides.
The average height is from +40 m to +70 m.
The territory topography distribution includes mainly gently slope hills and
mountains, accounting for 60% of the total area, the valley and plain hold 30%, high hills and
mountains about 10%. Because of geological tectonics, Thai Hoa has relatively flat land area,
with large area scale and relatively convenient for agricultural development.
- High mountain topography: mainly belongs to the southwest of Tien Nghia
commune with the elevation from +57 m to +74.3 m and partly belongs to Hoa
Hoa commune with the elevation from +58 m to +91.6 m with the slope of
20% to 30%.
- Gently slope plain topography: belongs to the West of Hieu river with the
elevation from +45.4m to +52.6m, with the slope less than 10% and to the
East of Hieu river with the elevation from +41.7m to +54.1m.
- Along the river side topography: has the elevation from +34.3 m to +41 m,
which is often flooded.
(Source: Natural conditions and forecasts of resources for socio-economic development -
Report on socio-economic development plans in Thai Hoa town, phase of from 2011 to 2015)
• Land and area:
The total area of natural land is 13,518.8 hectares accounting for 0.82% of natural area
of Nghe An province; in which the agricultural land area up to 2010 is 9984.5 hectares, the
non- agricultural land area is 3240.9 ha, the unused land area is 293.4 hectares
Table: Structure of land use in Thai Hoa town
Types of land Area Percentage
Agricultural land 9984.5 73.9%
Non-agricultural land 3240.9 24.0%
Unused land 293.4 2.2%
Total 13518.8 100.0%
Drainage and wastewater treatment system project for Thai Hoa town, Nghe An province”
Environmental Impact Assessment (EIA) PCO Consultant, 2010
37
Agricultural
land
74%
Non-
agricultural
land
24%
Unused land
2%
Soil: Thai Hoa area has 14 major categories of land divided into two groups: Thuy
Thanh and Dai Thanh; the two groups are quite suitable for the cultivation of industrial crops
and fruit trees with high economic values such as : coffee, rubber, tea, orange, grapefruit,
jackfruit, tangerine, melon, watermelon… (Source: Natural conditions and forecasts of
resources for socio-economic development - Report on socio-economic development plans in
Thai Hoa town, phase from 2011 to 2015)
2.1.2. Climate
Thai Hoa town giai đoạn 2011 - 2015) 2.1.3. Climate Characteristics
Thai Hoa town is a mountainous town, thus is influenced by typical climate of the the
temperature and humidity difference is quite large between seasons, especially winter and
summer; in the period from May to August each year Thai Hoa town is influenced by the
Southwest wind which makes the weather hot, dry and drought, affecting the production and
daily life of the residents in the aera. However, in rainy season (from September to April), the
humidity is high and rainfall amount is large.
(Source: Natural conditions and forecasts of resources for socio-economic development -
Report on socio-economic development plans in Thai Hoa town, phase from 2011 to 2015).
Temperature and humidity:
- Lying in the tropical and moonson climate area, Thai Hoa is a mountainous town
which is characterized by climate of the West mountainous area, impacted directly by
South-West moonson, dry and hot (from April to August) and the Noth-East moonson,
cold and wet (from November to March). The annually average temperature is rather
high, from 230 – 2500
C, total annually average temperature is 8503°C.
- Annually average temperature: 23,70 C.
- Absolutely high temperature: 420 C.
- Absolutely low temperature: 60 C. (in the Spring-Winter crop, number of days with
temperature < 150 C is 30)
- Annually average humidity: 83%
- Maximum humidity of month: 90%
Drainage and wastewater treatment system project for Thai Hoa town, Nghe An province”
Environmental Impact Assessment (EIA) PCO Consultant, 2010
38
- Minimum humidity of month: 30%
0
5
10
15
20
25
30
1 2 3 4 5 6 7 8 9 10 11 12
0
50
100
150
200
250
300
350
400
Amount of rainfall (mm)Amount of temperature (oC)
Chart: Change in temperature and rainfall during months of year 2008
Source:North-Middle Hydrometeorology Center, 2008
Rainfall:
The average annual rainfall is 1457 mm. The rainfall is unevenly distributed,
concentrated in August, September, October, causing flooding in low areas along Hieu river.
In dry season, the rainfall is negligible (only 12 mm in some month), in December, January,
February, the rainfall only reaches 229mm, which causes long-term drought. The highest
amount of rainfall during day is measured at 155mm on 31st of October, 2007.
The rainy season every year is from July to December, accounting for 50% - 55% of
the annual rainfall, a number of detailed criteria are as follows:
- The average rainfall in many years:: 1500 – 1800mm
- The average number of rainy days in many years: 130 – 150 days
- The biggest monthly rainfall: 500–600mm
Source:North-Middle Hydrometeorology Center, 2008
Wind:
The prevalent wind direction is Southwest and Northeast.
- The main Southwest wind direction is in summer (Laos wind), Northeast in winter
(northeast monsoon).
- The average wind speed is 1 – 2,5m/s.
Source:North-Middle Hydrometeorology Center, 2008
Storm:
Nghe An in general and Thai Hoa in particular is an area affected by storm. This area
often encounters storm, the average wind power is about 20 (m/s). The storm wind to Thai
Hoa area can reach 30-35m/s but weaken rapidly towards the west.
Drainage and wastewater treatment system project for Thai Hoa town, Nghe An province”
Environmental Impact Assessment (EIA) PCO Consultant, 2010
39
Overall, Thai Hoa town lies in a tropical monsoon climate. Winter is influenced by the
northeast monsoon; summer is influenced by the hot dry southwest wind. Cold air is usually
combined with other meteorological forms: Hurricane, tropical depressions, tropical
convergence solutions, ... which often cause heavy rains, strong winds, large variations in
temperature.
Source:North-Middle Hydrometeorology Center, 2008
2.1.3. Geological conditions
According to results of strata exploration survey of the Electricity Industry Investment
Consultancy & Services Center- Nghe An Department of Industry (currently Nghe An
Department of Trade and Industry), that ground in order from top to bottom is divided into
layers as follows:
- Layer 1: is clay layer, with soft, flexible state, tightly covers the construction area of
works, this is rich soil layer for paddy cultivation, with the thickness of 0,2 – 0,4m;
- Layer 2: is clay layer with gray, yellow color, medium-tight state;
Layer 2 and Layer 3 have good features of construction but must be appropriately
treated with ground before building the works.
2.1.4. Hydrological conditions
The section of Hieu river flowing through Thai Hoa area has the length of 7.4 km. The
main hydrological parameters of Hieu river in Thai Hoa town area are as follows:
+ The biggest flow in flood season: 5810m3/s.
+ The flow in dry season only reaches: 13m3/s
+ The highest water level is +47,5m (corresponding to P=5%) and is 47m
(corresponding to P=10%)
+ The lowest water level is +36,0m
+ The average water level in the annual flood season ranges from +39,0m
to42,0m (according to the factual investigations).
+ Total flow of the average (yearly) current:): 3,7 billion m3 of water
. At the center of the town, currently apart from Hieu river, there are a number of
reservoirs that regulate the air for the town center area. Yet only Bau Sen lake has the largest
area and the biggest ability of air regulation.
Bau Sen lake is located in Hoa Hieu Ward, with the area of about 5.5 hectares and a
reserve of about 100.000m3. This lake can regulate water drainage for the town apart from
creating the environmental landscape for the town.
(Source: According to Report on socio-economic development plans of Thai Hoa town
in the phase of 2011 -2015 - Natural conditions and forecast of socio-economic development
resources).
Drainage and wastewater treatment system project for Thai Hoa town, Nghe An province”
Environmental Impact Assessment (EIA) PCO Consultant, 2010
40
2.1.5. Mineral resource
According to the Report on socio-economic development plan of Thai Hoa town in
phase 2011 - 2015 - Natural conditions and forecasts of resources for socio-economic
development - the mineral resources of Thai Hoa town are of abundancy as follows:
- Porous basalt rocks have large reserves, concentratedly distributed in Nghia My and
Dong Hieu communes;
- Limestone and marble concentratedly distributed mainly in Nghia Tie commune
- Clay for production of tile: has large reserve, concentratedly distributed mainly in the
following wards / communes: Long Son, Nghia Hoa, Quang Tien, Nghia Thuan and
Nghia Tien.
- Construction sand, gravel and mineral sand gold: concentratedly distributed in in the
communes, wards where Hieu river flows through including Hoa Hieu, Quang
Phong, Quang Tien, Nghia Hoa, Long Son...
2.1.6. Forest Resource
According to the Statistics Office - People's Committee Thai Hoa town, the whole
province in 2009 to the town forest area is as follows:
- The forest area accounts for more than 3000ha with the total wood reserves of about
100.000m3 (excluding wood reserve of bamboo, neohauzeaua ...);
- Total land fund that can serve forestry development targets is of significance about
4.073,9ha, representing 30,14% of the total natural area.
2.2. SOCIO-ECONOMIC CONDITIONS
2.2.1. Economic development situation
Being a newly-established town in 2007 according to the Decree 164/2007/ND-CP of
the Government, within two years to the end of 2009, the economic growth rate of Thai Hoa
town has basically achieved the stable growth rate, people's lives are more and more
improving, national defense - security continue to be strengthened and maintained. The total
average production value per capita at constant prices in 1994 reached 8.5 million dong,, at
current prices reach 19.4 million dong;
The average gross domestic product (GDP) of the town in phase 2007- 2009 was
stable at 16-17; the economic structure moved slowly towards gradual decrease in the
proportion of the agriculture, forestry, fisheries and good increase in the proportion of the
industry, construction. The total production value in 2009 at constant prices in 1994 of the
town was 580,324 million dong, exceeding 0.9% as compared to the year plan; at the current
prices are 1,332,422 million dong, exceeding 1.2% as compared to the year plan. Specific
data of the sectors are as follows:
Drainage and wastewater treatment system project for Thai Hoa town, Nghe An province”
Environmental Impact Assessment (EIA) PCO Consultant, 2010
41
Table 2.5. GDP by sector of Thai Hoa town in 2009
No. Sector production value (million dong) Ratio
At constant
prices 1994
At constant
prices 1994
1 Agriculture, forestry and
aquaculture
80.264 204.095 15,3%
2 Industry and construction
- Of which: Industry
180.020
100.191
420.407
192.182
31,6%
3 Commerce, services 320.040 707.920 53,1%
Total 580.324 2.332.422
Chart 2.1: The structure of the economic sectors of Thai Hoa Town in 2009
(Source: Report on socio-economic survey for project, 2010) ).
2.2.2. Social development
Population:
The total population of the whole Thai Hoa town up to the end of 2009 was 102,119
people with 24,739 households, the average number of people in households according to the
socio-economic survey results in service of the project, in March/2010 is 4, 09 people per
household. The number of ethnic minorities is 5751 people the rate of natural population
growth in 2009 is 0.56%.
Table: Population of Thai Hoa town up to the end of 2009
No. Wards Population
(people)
Households
1 Hoa Hieu ward 16,271 3,978
2 Quang Phong ward 6,248 1,528
3 Long Son ward 6,905 1,688
15.3%
31.6%
53.1%
Agriculture, forestry and fisheries
Industry and construction
Services, Trade
Drainage and wastewater treatment system project for Thai Hoa town, Nghe An province”
Environmental Impact Assessment (EIA) PCO Consultant, 2010
42
No. Wards Population
(people)
Households
4 Quang Tien ward 14,337 3,505
5 Nghia My commune 8,070 1,973
6 Dong Hieu commune 11,406 2,789
7 Tay Hieu commune 11,970 2,927
8 Nghia Tien commnue 5,580 1,364
9 Nghia Hoa commune 3,774 923
10 Nghia Thuan commune 16,620 4,064
11 Other forces 939 -
Total 102,119 24,739
With the expected rate of natural population growth per on the average from 2009 - 2020 of
0.8%/year and from 2020-2030 of 0.6%/ year, the forecast population of Thai Hoa town is
shown in detail in the following table:
Table 2.6. The forecast population growth of Thai Hoa town phase 2020 - 2030
2009
(people)
2015
(people)
2020
(people)
2025
(people)
2030
(people)
102,119 108,298 113,677 118,112 122,682
(Source: Report on socio-economic survey for project, 2010)
Labor, Employment:
With aforesaid population features, it is expected that the number of people in working age
having working capability in 2010 is 32,667 people and 35,188 people in 2015, the
employment rate with vocational training in 2010 (including both short-term and long term)
accounts for 52.9% of the total labor, the rate of non-agricultural labor accounts for 35% of
the total labor. This labor source is sufficient to meet the development requirements of the
Town for the whole phase. Along with the economic transition, the labor structure working in
sectors of the national economy will also change.
On the other hand, in 2009, the town has implemented programs such as job generation,
hunger radiation and poverty reduction and obtained very good results, specifically: creating
jobs for 987 people, including 300 people of labor export. With respect of technical,
professional qualification of employees (from the primary level, technical workers upwards):
the sector group of agriculture - forestry - fishery has the lowest rate, followed by the industry
- construction sector group; the- tourism services sector group has the highest rates.
According to the results of sociological surveys, in March / 2010 of the project. The average
income VND/household/month was 5,199,720, of which this rate increases from poor to rich
households, the details are shown in the following table.
Drainage and wastewater treatment system project for Thai Hoa town, Nghe An province”
Environmental Impact Assessment (EIA) PCO Consultant, 2010
43
Table 2.6: Household average income
According to
classification of
household economy
Average income VND/household/month
Average Lowest Highest
1. Poor 1.366.830 1.000.000 3.000.000
2. Medium 4.445.380 3.500.000 16.000.000
3. Well-off 6.548.890 8.700.000 26.000.000
4. Rich 10.300.000 20.000.000 50.000.000
Average 5.199.720 1.000.000 26.000.000
Chart 2.2. Average income of households (1000 VND/household/month))
-
2,000.0
4,000.0
6,000.0
8,000.0
10,000.0
12,000.0
1. Poor
HHs
2. Middle
Hhs
3. Well-off
HHs
4. Rich
HHs
Average
1,366.8
4,445.4
6,548.9
10,300.0
5,199.7
(Source: Report on socio-economic survey for project, 2010)
Poverty issues:
According to the Report of Thai Hoa town’s People's Committee on the
implementation of socio-economic development of the town in 2009, the rate of poor
households in 2009 in the town accounts for 8.45%.
Hunger radiation and poverty reduction of the town in recent years has made great
progress, the people's spiritual and material lives are more and more improved. The value of
production per capita is quite high: 19.2 million (calculated at current prices). Programs of
social welfare, hunger radiation and poverty reduction were well implemented, therefore;
rate of poor households has been reduced significantly as compared with the average rate of
the whole Nghe An province.
Current situation of social infrastructure
• Education and training: Currently, the town has 01 Western Technical Economic
Intermediate School (Phu Quy Vocational School); 01 regular education center, 04
high schools (including 01 private high school); 09 secondary schools; 11 primary
schools, 08 nursery schools. The whole town has 32 schools (with 04 learning levels)
of which 09 schools meet national standards.
Drainage and wastewater treatment system project for Thai Hoa town, Nghe An province”
Environmental Impact Assessment (EIA) PCO Consultant, 2010
44
• Health:
All wards/communes have medical stations. In the beginning six months of 2008, the
medical examination and treatment in the General Hospital reached: 62,854 patients, reaching
52.4% of the year plan, the number of patients treated as inpatients: 7464 people, the rate of
patient bed use reached 111.7%. The health system in communes, wards have provided
medical examination and treatment for 57,814 people, inpatient treatment for 1157 people, the
system of non-public medical examination and treatment continue to serve the needs of
medical examination and treatment for people.
Work in preventive health care has been enhanced, well implemented n the area,
therefore; no epedemic happened, food hygiene and safety are set tightly. Currently, there are
four wards, communes that meet national standards of health includeing: Hieu Hoa, Nghia
Thuan, Dong Hieu and Tay Hieu; reaching the percentage of 40% of all wards, communes.
2.3. CURRENT SITUATION OF DRAINAGE
2.3.1. Current situation of drainage system
At the moment, only some roads have drainage sewers and limited in some wards in
the inner city area, concentrated along the National Road 48.
- Rainwater: is collected through surface intake system, poured into the common
drainage ditch together with wastewater or overflow on road surface and then poured
into surrounding rice fields, drainage ponds and rivers. Thus rainwater and waste
water is collected into a system of drainage ditches located on pavements of roads and
then poured into Hieu river. When there is rain, waste water is diluted by rain water
and then poured into the river, which has dramatically reduced the pollution to the
rivers significantly reducing the pollution to the surrounding environment. However,
when there is no rain, the water levels in the rivers get low, the volume of wastewater
flowing into rivers causes pollution.
- Waste water: waste water from households, flowing directly into the street sewers (for
areas having drainage sewers such as the area along National Road 48) through small
sewers (mainly including sewer pipe uPVC D100- D150). After waste water from
households flows to sewers, it is discharged into the rivers.
- Apart from households living along the roads having drainage sewers, almost residents
living in other areas (where no water drainage sewers are available) discharge
wastewater directly to the outside (fields, ditches or rivers). This has seriously affected
the environment, causing unpleasant smell, greatly influencing the local people in
surrounding area.
Figure 11 – The status of drainage system in Thai Hoa town.
2.3.2. Current situation of drainage channels and sewers
In general, the drainage system in Thai Hoa town has not been constructed completely.
The combined system with box culverts stretching along some main routes of central roads of
central wards in the town center. In the suburban communes, there is virtually no drainage
system. Most of the wastewater and rain water of households will be discharged into
surrounding rivers, lakes, ponds and fields.
Drainage and wastewater treatment system project for Thai Hoa town, Nghe An province”
Environmental Impact Assessment (EIA) PCO Consultant, 2010
45
• Hoa Hieu Ward: Most major roads of Hoa Hieu Ward have water drainage box
sewers at the two sides of the road with the width B = 0.5 ÷ 1m. Yet because
these system are not regularly dredged, repaired, some of their ditch covers
were much damaged. Many water drainage routes are open ditches, people
discharge waste directly into the ditches, which causes unpleasant odors,
polluteingthe environment and urban landscape
• Long Son Ward: the water drainage ditch routes in Long Son Ward are limited
and mainly located in roads intersected with Hoa Hieu ward. In these water
drainage ditche routes as well as in the water drainage ditch routes as of Hoa
Hieu ward, the majority of ditch covers have been damaged, degraded.
• Quang Phong Ward: the water drainage ditch routes in Quang Phong ward is
mainly located along the National Road 15A, with the width B = 0.5 m. Most
of these water drainage ditch routes have been deteriorated, many sections are
not dredged, thus there dregs, waste has filled ditch bed, reducing water
drainage ability.
• Quang Tien Ward: in Quang Tien Ward, the water drainage ditches are mainly
located along the National Road 48. Like other wards of the town, the sewer
system in Quang Tien ward is also damaged and degraded.
Table 2: Consolidation of current water drainage sewers, ditches.
No. Width B (m) Length L (m)
1 B = 1,5m 744
2 B = 1,0m 9680
3 B = 0,8m 3858
4 B = 0,5m 1162
Road surface water collection manholes (surface intakes) were built in the form of
inlets (0.5 x0, 1m) rectangle hole boring (0,1 x0, 1m). The distance between manholes on the
average from 25-35m, particularly some sections are up to 50m (along National Road 48, ..).
In many routes, road surface rain water collection manholes are in good operaion, the average
distance between the manholes is from 25-50m.
However, on some routes due to weak management, the manholes there blocked by
rubbish were damaged. On some other roads, road surface water collection manholes’
currents were blocked by building materials, refuse, greatly reducing the water drainage
ability of the roads, ...
2.3.3. Current situation of flooding and inundations
In Thai Hoa town there still exists some frequent flooding points. These points need to be
addressed thoroughly to minimize the impacts on the environmental sanitation as well as the
lives, traffic of people. The regularly flooding sites include:
• The cross-road on the National Road 48 belongs to Hoa Hieu ward: is the place where
flooding occurs regularly whenever there is heavy rain causing great influence on
daily life, environmental sanitation and transportation, which has caused urgent matter
to the people in the town.
Drainage and wastewater treatment system project for Thai Hoa town, Nghe An province”
Environmental Impact Assessment (EIA) PCO Consultant, 2010
46
• The area on the National Road 15A belonging to the territory of Quang Tien ward near
Nghia Tien commune (the section near the rubber company) is also frequently
flooded, affecting seriously daily lives of the people, esp. This is the transport road the
National Road 15A
The time of flooding usually lasts about 1-5 hours, the flooding depth is about 0.3 to 0.7 m
with the flooding area on the average is about 0.5 ha.
2.3.4. Current situation of drainage river and waste water catchment
Current situation of drainage system:
Hieu River is the largest river flowing through the project area, with the total length of
about 220 km. Hieu river has 5 branches, namely:
+ Sao river: has the basin of 160 km2, 34km long.
+ Khe Cai: 23km long .
+ Khe Ang: 23km long.
+ Khe Deu: 16km long.
+ Khe Da: 17km, with basin area of 50km2.
Bau Sen lake is located in Hoa Hieu Ward, with the area of about 5.5 hectares and a
reserve of about 100.000m3. This lake can regulate water draiage for the town apart from
creating the environmental landscape for the town.
Current situation of water drainage catchments:
Currently, the water drainage catchment of Thai Hoa town can be divided into two
main catchments as follows:
- The catchment in the East of Hieu river: is limited by Nghia Dan market, Nghia Dan
bus station to Hieu river bank. This is a huge catchment of Thai Hoa town with the
main water drainage direction from east to west. In this catchment, there still exists
some flooing points such as the cross road on the National Road 48.
- The catchment in the West of Hieu river: is limited by
the National Road 15A, Quang Trung, Lam Son hamlets (Quang Tien Ward) to Hieu
river bank. This is a catchment with quite complex terrain, but has the water drainage
direction from west to east. In this catchment, there still exists some flooding points
such as the flooding, point on the National Road 15A, near the rubber company.
2.4. CURRENT SITUATION OF ENVIRONMENTAL SANITATION
2.4.1. Current situation of household sanitation
According to information gathered from the Social-Economic Investigation, in March
2010, the number of households that have private toilets accounts for 95.4%, the number of
households that have no toilets is 4.6%. Those that have no private toilets mainly fall into
poor, medium families. They have not enough conditions to build toilets or have
psychological habits of not using toilets.
Drainage and wastewater treatment system project for Thai Hoa town, Nghe An province”
Environmental Impact Assessment (EIA) PCO Consultant, 2010
47
Table: Rate of household latrine types
Types of toilets Digging
/ bridge
latrines
One
compartmen
t latrines
Two
compartmen
t latrines
Septic tanks
(3
compartments
)
Flushing/
Penetratio
n latrines/
without
septic
tanks
Total
Classifie
d by
househol
d
economy
Poor 30.4% 30.4% 34.8% 4.3% 100.0%
Mediu
m 11.2% 13.3% 39.9% 33.5% 2.1% 100.0%
Good 1.4% 8.6% 27.1% 62.9% 100.0%
Rich 12.5% 18.8% 68.8% 100.0%
Total 9.8% 13.5% 35.4% 40.1% 1.3%
100.0
%
(Source: Report on Socio-economic survey for project, 2010)
Chart 3: Types of household latrines
0.0%
5.0%
10.0%
15.0%
20.0%
25.0%
30.0%
35.0%
40.0%
45.0%
1
9.8%
13.5%
35.4%
40.1%
1.3%
Digging/bridge latrines
One compartment latrines
Two compartment latrines
Septic tanks
Flushing/without septic tanks
(Source: Report on Socio-economic survey for project, 2010)
2.4.2. Current situation of solid waste collection and treatment
Currently, waste management and collection in Thai Hoa town do are carried out by
Thai Hoa Environmental Sanitation Company. Solid waste which is not classified at the
source is concentrated collected and taken to the dumping and burning place of the town. The
landfill of the town at the present is only temporary one that has not been properly invested,
failing to meet the requirements of a sanitary landfill, not applying any pollution treatment
measures. So the landfill of the town is now considered a pollution source which is quite
serious in the province.
The ccollection performance in the town only reaches about 40% of the volume of
waste arising in the reality. Due to weakness and lack of personnel and equipments, everyday
the volume of waste to be collected in the area is from 4 to 6 trucks, on peak days (Tet,
Drainage and wastewater treatment system project for Thai Hoa town, Nghe An province”
Environmental Impact Assessment (EIA) PCO Consultant, 2010
48
festival days) this volume is 7 trucks equivalent to about 2 - 2.5 tons per day and only
stopping at the collection and concentration in the landfill, without treatment measures.
Collection places are also limited in central areas of the town along the National Road 15 and
National Road 48 with the radius of 2 km.
Each day, each household discharges on the average 3kg of waste, 1kg of waste at the
minimum and up to 15kg at the maximum. According to the survey of households with
different living standards, waste volumes generated are also different. Often households with
difficult economic conditions have less waste than households with good, rich economic
conditions. Households doing eating, drinking service business are those having the most
waste volume.
Table 21. Types of waste treatment methods of households
Handling method of domestic
waste
Living standards Total
Poor Medium Good Rich
Burning/ burying in the
garden Proportion 88.7% 58.4% 51.3% 46.3% 59.2%
Taking to the public
landfill Proportion 0.0% 13.7% 12.7% 0.0% 11.6%
Pouring into the garden Proportion 4.8% 3.9% 1.2% 0.0% 3.1%
Throw out to the field /
vacant land area Proportion 0.0% 0.2% 0.0% 0.0% 0.1%
Sanitary group goes to
collect Proportion 6.5% 25.8% 34.9% 53.7% 27%
Total Proportion 100.0% 100.0% 100.0% 100.0% 100.0%
(Source: Report on Socio-economic survey for project, 2010)
2.5. OTHER TECHNICAL INFRASTRUCTURE CONDITIONS
2.5.1. Traffic condition
Road way:
- Thai Hoa town is located in the intersection of two life-line roads: Highway 48 route
linking the eastern districts (Quynh Luu, Dien Chau, to Highway 1A route connecting
Dong Nam Economic Zone, and Cua Lo harbour and Vinh Town) with the western
districts of Nghe An (Quy Hop, Quy Chau, Que Phong); Ho Chi Minh route,
connecting districts of Tan Ky, Do Luong, Anh Son in the south, districts of Nghia
Dan and Nhu Xuan - Thanh Hoa in the north, Thai Hoa Town has become an
important point in the economic-social development, security and defense
strengthening strategy of Nghe An province and the North Central Regional ...
- Highway 48 is the main external road through Thai Hoa town from the junction of
Yen Ly to Quy Hop. The section through the town is about 6km long, is being
renovated, upgraded, plastic pavement has width of 15m, 6m for each sidewalk.
Drainage and wastewater treatment system project for Thai Hoa town, Nghe An province”
Environmental Impact Assessment (EIA) PCO Consultant, 2010
49
- Highway 15A: present condition of the road is deteriorated, paved roads, pavement
width of 3.5 m, 5.5 m platform We already have projects to renovate and upgrade to
reach the standard of delta road level 3.
- Provincial Highway 545: the cross section current condition is narrow, 3.5 m wide
asphalt surface, land ditches on both sides.
- Ho Chi Minh road goes through the eastern, 10km away from the town.
- External Bus Station is near the town center, the area is narrow, failing to meet service
needs.
- Network traffic in expanded Thai Hoa urban center is not complete, the street does not
have the nature of urban roads, narrow cross-section, no sidewalk. Many asphalt
surfaces are deteriorated.
- Vuc Rong - Khe Son Route are being deployed with 17m wide, in which, asphalt
surface is 11m wide, the two sidewalks combined concrete slab cover ditch, 3 meter
wide each.
- Some small villages have their road surface concrete poured, 1.5 - 2m cross section.
Water way:
Hieu river flows through urban areas, the river bed is wide but the water level
difference between flood season and dry season is large, so water way exploitation on Hieu
River is not favorable.
There are some points of sand mining points on the river, only small load boats
carrying materials on the river.
Rail way:
Railway from Cau Giat to Thai Hoa town is primarily transport agricultural products,
quarrying, is not used often. Railway station has deteriorated, has seeing-off road about 200
meters long.
2.5.2. Power supply
Thai Hoa town uses national grid through Nghia Dan 110 KV station in Hoa Hieu
ward, 1 x 16MVA capacity, supply voltage of 110/35/10KV. Ensure to meet production and
activities needs of the urban.
� High tension grid:
NO List Section (mm2) Length (Km)
1 T/Hoa-N/Dan double road 110Kv line 2AC – 185 180
35Kv grid
2 Road 372 Nghia Dan – Quynh Lưu AC – 95 37
3 Road 375 Nghia Dan to An-Duc-Khanh AC – 95 5
4 Road 373 Nghia Dan-Nghia Lac AC – 95 6
� Medium tension grid:
Behind current Nghia Dan 110 KV station there are 5 10 kV roads supplying power to
Thai Hoa town and surrounding villages, the wire section of AC95, AC70, AC50. Entire Thai
Hoa town now have nine 10/0.4 kV substations with total capacity of 2070 KVA
� 0,4KV grid:
Drainage and wastewater treatment system project for Thai Hoa town, Nghe An province”
Environmental Impact Assessment (EIA) PCO Consultant, 2010
50
0.4kV grid is on the road, sections of AC70, AC50, AC35 go on the same high tension
pillars. There are 0.4 kV grid sections go on wooden pillars. Thai Hoa town is a mountain
town, residents do not focus so much low tension lines are too long, voltage loss is big.
� Lighting grid:
Town's lighting grid is incomplete, only highway 48 through the town is illuminated.
The other route has no lighting.
� Assessment of power grid:
Generally, medium voltage grid of Nghia Dan district is mainly overhead line, open
circuit ray shaped. New 35KV power grid is constructed ensuring power supply
specifications. 10 kV grid has renovated a number of main lines to serve the power
requirements for the loads, however safe supply of electricity is not high, not satisfied voltage
improve according to 22kV standard.
2.5.3. Water supply
Currently Thai Hoa town has centralized water supply system with capacity of
4000m3/day and night with Hieu river water source. Water prices are applied to collect fee in
Thai Hoa Town is VND3500/m3.
Agencies and residents in the designed area are only households along the road with
main water supply pipes collecting water directly by ∅50mm or ∅32mm the pipes.
2.6. THE STATUS OF ENVIRONMENT QUALITY
2.6.1. The status of air environment quality
Methods of measurements to determine some basic criteria for quality status of air
environment in project area such as:
� Quantity of samples: Observed in 20 locations;
� Observing frequency: Samples are taken continuously in 1 hour, twice a day and
observation is conducted in 2 continuous days.
� Sampling time: from 26 to 27/6/2010
� Observing location: In locations planned for construction of the project works such
as WWPS, pipelines, WWTP and in typical locations such as on the main road routes,
cross-road, intersection, school area, hospital, market, etc and detailed in the table
below:
Table 2.9. Analyzing results
No. Symbol Co-ordinates Sampling location Remark
1 KK1 19o19'420N;
105o26'343E
Location of WWTP 2 At the field, far from At the field, far from residentital
area
2 KK2 19o19'426N;
105o26'348E
Nghe An coffe and rubber
Company
At the entrance of the
Company, close to traffic road.
3 KK3 19o19'440N;
105o25'694E
Vegitation oil company At the entrance of the
Company, close to traffic road.
4 KK4 19o19'343N;
105o26'352E
Nghia Quang market gate At the entrance of the market,
crowded residents, households
selling food, fruits, groceries,
Drainage and wastewater treatment system project for Thai Hoa town, Nghe An province”
Environmental Impact Assessment (EIA) PCO Consultant, 2010
51
(Picture Annex: Measurements of air quality in project area)
These are typical locations of air quality, which reflect accurately the existing
conditions in the construction area of the project. The measuring machine is located at the
height of 1,2 - 1,5m and at other locations far from the defined location with the distances of
1; 7,5; 15; 30; 60m to ensure the feature of the location and to take the average value. The
average result of observing locations are specified in the table below:
Table 2.10. Analyzing results of surrounding air environment
etc.
5 KK5 19o19'438N;
105o26'356E
Nghia Thang intersection On traffic road
6 KK6 19o19'443N;
105o26'339E
Hieu river’s bridge On Bridge of Hieu river
7 KK7 19o19'458N;
105o26'258E
Treatment Plant 1 At the field, far from
residentital area
8 KK8 19o19'456N;
105o26'312E
Brick –kiln in Long Son
ward 100m away from the furnace
area, far from residential areas
9 KK9 19o19'429N;
105o26'323E
Entrance of Quang Phong
ward
On road, at the entrance of the
ward.
10 KK10 19o19'465N;
105o26'298E
Hoa Hieu 1 primary school At school gate, during school
time
11 KK11 19o19'938N;1
05o265343E
Hieu market On road at Hieu market, many
business, trading families.
12 KK12 19o19'426N;
105o25'343E
Police station in old Nghia
Dan district
At the gate of police station of
Nghia Dan district, close to the
traffic road.
13 KK13 19o19'339N;
105o26'063E
Intersection of Thai Hoa
town
Close to the edge of the road,
at intersection of Thai Hoa
town, there are many vehicles
traveling
14 KK14 19o19'339N;
105o26'060E
Bau Sen lake On road, close to Bau lake.
15 KK15 19o18'125N;
105o27'904E
Nghia My Cong industrial
zone, Nam Trung
Company
Gate of Nam Trung Company,
calm wind
16 KK16 19o18'258N;
105o27'904E
Gate of material
manufacturing factory for
hydro-power plant.
Gate of processing factory,
calm wind
17 KK17 19o18'148N;
105o27'867E
Entrance of the industrial
zone
Gate of industrial area, calm
wind
18 KK18 19o18'214N;
105o27'697E
Railway near industrial
zone.
Close to railway edge, about
100m from industrial area.
19 KK19 19o18'546N;
105o27'417E
Road of village, hospital On access road in the village,
near hospital.
20 KK20 19o18'565N;
105o27'524E
Bui Thi Anh, Dong Tam 2
area – Hoa Hieu ward.
At the gate of household.
Drainage and wastewater treatment system project forThai Hoa town, Nghe An province”
Environmental Impact Assessment (EIA) - 52 –
PCO Consultant, 2010
NO CRITERIA Unit KK1 KK2 KK3 KK4 KK5 KK6 KK7 KK8 KK9 KK10
QCVN05,
06:2009/
BTNMT
1 Temperature oC 30.8 32.0 33.9 34.3 33.1 33.3 33.4 33.1 32.5 33.6 -
2 Humidity % 75.5 72.1 66.8 56.5 60.4 58.4 60.1 60.8 65.3 56.2 -
3 Wind speed m/s 0.24 0.27 1.0 1.11 0.38 1.52 1.79 2.1 0.15 0.18 -
4 Suspended
dust µg/m3
80 184 168 168 195 168 103 158 114 108 300
5 PM10 dust µg/m3 16.8 30.5 28.3 38.5 46.1 32.9 28.5 23.1 21.5 20.4 150
6 Lead dust
(TB 24h) µg/m3
0.23 0.58 0.47 0.49 0.61 0.38 0.16 0.24 0.23 0.2 1.5
7 CO µg/m3 9000 15000 15500 12800 12500 13500 9500 23000 14000 13800 30000
8 NO2 µg/m3 67 112 98.6 88 90 148 68 82 80 76 200
9 SO2 µg/m3 112 213 183 158 193 242 124 146 132 128 350
10 H2S µg/m3 39.3 26.1 22.8 38.3 25.8 26.4 18.2 23.5 20.6 22.1 42
11 Instant noise dB 61 76.3 67.8 78.5 76.2 90.0 60.1 78.9 71.2 67.4 75
12 Leq noise dB 52 68.1 60.1 69.3 69.5 67.9 50.8 60.4 57.3 59.8 60
13 Max noise dB 72 82 78 83 81.7 97.8 74.7 89.4 77.9 76.5 -
14 Accelerating
seisemic m/s
2
0.011
0.017
0.016
0.02
0.019
0.023
0.011
0.012
0.011
0.011
-
15 Velocity
seisemic cm/s
0.12
0.16
0.15
0.19
0.17
0.12
0.09
0.1
0.09
0.101
-
Drainage and wastewater treatment system project forThai Hoa town, Nghe An province”
Environmental Impact Assessment (EIA) - 53 –
PCO Consultant, 2010
Table 2.11 Analyzing results of surrounding air environment (cont)
NO CRITERIA Unit KK11 KK12 KK13 KK14 KK15 KK16 KK17 KK18 KK19 KK20
QCVN05,
06:2009/
BTNMT
1 Temperature oC 35.7 37.7 38.1 37.8 39.6 38.5 37.2 38.5 37.8 36.2 -
2 Humidity % 47.3 45.6 41.4 42.3 37.3 43.2 45.8 43.7 45.2 53.0 -
3 Wind speed m/s 0.43 0.23 0.21 1.23 1.22 0.26 1.21 0.32 2.23 1.26 -
4 Suspended
dust µg/m3
82 180 138 133 193 158 160 156 116 123 300
5 PM10 dust
(TB 24h) µg/m3
35.2 24.1 48.3 25.1 68.7 32.5 30.2 28.7 23.4 24.2 150
6 Lead dust
(TB 24h) µg/m3
0.36 0.42 0.84 0.29 0.78 0.39 0.41 0.43 0.19 0.2 1.5
7 CO µg/m3 13000 9000 12500 9500 12000 18500 18700 13000 10000 10800 30000
8 NO2 µg/m3 103 96 145 80 113 129 116 92 89 96 200
9 SO2 µg/m3 124 98.6 183 78.1 181 188 162 159 143 148 350
10 H2S µg/m3 49.3 25.6 46.2 28.9 36.4 39.8 34.9 28.1 33.7 34.9 42
11 Instant noise dB 80.6 77.1 85.2 65.2 73.8 74.7 73.0 79.3 75.2 73.7 75
12 Leq noise dB 60 56.8 63.8 52.7 59.8 65.1 64.5 68.3 65.1 64.2 60
13 Max noise dB 88 76 94.7 74 88.9 89.6 84.2 89.3 77.3 77.9 -
14 Accelerating
seismic m/s
2
0.018
0.011
0.019
0.009
0.014
0.018
0.017
0.021
0.012
0.013
-
15 Velocity
Seismic cm/s
0.13
0.09
0.15
0.09
0.12
0.17
0.15
0.18
0.09
0.101
-
Drainage and wastewater treatment system project forThai Hoa town, Nghe An province”
Environmental Impact Assessment (EIA) - 54 –
PCO Consultant, 2010
Comparison standard of air environment measuring parameters:
- QCVN 05:2009/BTNMT – National techical standard of surrounding air quality.
Comparison standard of measuring parameters relating to noise and vibration:
- TCVN 5949:1998 – Noise in public places and residence, Tiếng ồn khu vực
công cộng và dân cư, maximum allowable noise level.
- TCVN 6962:2001 - Vibration and shock. Vibrations caused by construction and
industrial production activities. Maximum levels permitted for industrial and
residential area.
- Decision No. 3733/2002/QD-BYT of the Ministry of Health issued on
10/10/2002 regarding the application of 21 occupational health standards.
As surrounding air quality standards QCVN 05:2009/BTNMT with basic parameters
SO2, CO2, NOx, suspended dust, dust PM10 (dust concentration size ≤ 10µm), Pb dust in the
content of surrounding air. Based on the value of these parameters to assess surrounding air
quality and monitor status of content change of air parameters in the process of monitoring
and supervision.
The parameters of microclimate criteria such as temperature, humidity, wind speed,
light are favourable, noise level according to standards on the maximum number of permitted
noise level for the surrounding QCVN 05: 2009/BTNMT.
Concentration of suspended dust (TPS), PM 10, Pb, CO, NO2, SO2, H2S in 20
observation locations is lower than pemissible standard.
Noise criteria: The measuring parameters in noise and vibration levels are measured
with the position corresponding to above 20 locations to ensure the results on the overall
results on the impact of noise and vibration in the study area and residential area. These
indicators are mostly located in KK2, KK3, KK4, KK5, KK6, KK8, KK11, KK12, KK13,
KK16, KK17, KK18, , however, the allowable exess level is low ranging from 1.02 to 1.14
times.
Vibration level is selected for measurement at areas of the wastewater pumping
station located, residential areas within the project and some roads with high vehicle traffic as
the traffic junction of roads. The values are below the allowed limit.
Comment: the result on the background air parameters of survey area shows that the
current background air environmental situation is relatively good. The signs of noise pollution
have just begin at low level. The locations having noise exceeding allowable limit occur
mostly where traffic density is heavy. Therefore, when the project begins to be implemented,
there should be periodical monitoring plan in each specific phase of the project to be able to
have good coordination, completed on schedule, well operate items of project to promote
economic-social development while ensuring public health, general harmony with plans and
strategies for economic-social development in general of the Thai Hoa Town in the future.
2.6.2. The status of surface water environment quality
Methods of sampling to determine some basic criteria for quality status of surface
water environment in project area such as:
� Quantity of samples: Observed at 10 locations;
Drainage and wastewater treatment system project for Thai Hoa town, Nghe An province”
Environmental Impact Assessment (EIA) PCO Consultant, 2010
55
� Observing frequency: Sampling locations are observed in 2 days, conducting the
measurement twice a day and the results shown below are average results of
observations.
� Sampling time: from 26 to 27/6/2010
� Sampling analysis: from 28/6/2010 to 5/7/2010
� Observing/sampling location: at 10 typical locations of the project: drainage
catchments and surface water source receiving treated wastewater (Hieu river) and
reservoir in the project area. Details are shown in the table below:
(Picture Annex: Sampling of surface water environmentin project area)
Average result of the sampling locations are specified in the table below:
Table 2.11. Analyzing result of surface water environment quality
No. Symbol Sampling location Remark
1 NM1 Water of Hieu river,
wastewater treatment plant
2 (WTP 2)
No discharge points from factories,
enterprises, hospitals and sewer discharging
directly from the residential area at the
sampling point.
2 NM2 Hieu river water in the
East
No discharge points from factories,
enterprises, hospitals and sewer discharging
directly from the residential area at the
sampling point, 200m far from discharge
point.
3 NM3 Hieu river water in the
West
No discharge points from factories,
enterprises, hospitals and sewer discharging
directly from the residential area at the
sampling point, 200m far from discharge
point.
4 NM4 Water of discharging
source – WTP 1
No discharge points from factories,
enterprises, hospitals and sewer discharging
directly from the sampling point.
5 NM5 Water in lake near brick
kiln in Long Son ward.
No discharge sewer into the lake, low lake
water level
6 NM6 Water in pond of Mr.
Pham Minh Duc’s
household, in Tan Tien
block.
Pond water level low, families discharging
wastewater directly into the pond
7 NM7 Water in Bau Sen lake Few people living around the lake, the lake
water level high
8 NM8 Surface water of Nam
Trung Nghe An JSC.
Pond water level low, no outlet from the plant
to the pond
9 NM9 Surface water in pond of
Le Mau Sun’s household
Pond water level low, families discharging
water directly into pond
10 NM10 Surface water in pond of
Mr. Nguyen Viet Hong ‘s
household, hamlet 14
Pond water level low, families discharging
wastewater directly into the pond
Drainage and wastewater treatment system project forThai Hoa town, Nghe An province”
Environmental Impact Assessment (EIA) - 56 –
PCO Consultant, 2010
NO. CRITERIA UNIT NM1 NM2 NM3 NM4 NM5 NM6 NM7 NM8 NM9 NM10
QCVN
08:2008/
BTNMT(
B1)
1 Temperature oC 32.6 32.5 32.8 32.3 33.7 32.7 32.9 32.6 32.8 32.7 -
2 pH
7.2 7.23 7.11 7.16 7.18 7.24 7.18 7.22 7.21 7.16 5.5 đến 9
3 Total of suspended
substances
mg/l 80.8 81.2 80.3 79.8 84.1 88.1 87.3 80.3 77.1 81.2 50
4 Chemical oxygen
demand (COD)
mg/l02 30,2 30,1 30,5 26,7 22,3 30,1 30,4 23,6 21,7 30,5 30
5 Colifom MPN/l 3800 3780 3760 3690 3780 3800 3610 3600 3600 3530 7500
6 BOD5 mg/l 19.3 19.7 19.2 18.8 21.6 21.8 21.3 21.9 22.1 21.7 15
7 Mn mg/l 0.09 0.086 0.092 0.09 0.099 0.11 0.1 0.114 0.131 0.122 -
8 Total of Fe mg/l 1.22 1.24 1.21 1.14 1.26 1.29 1.24 1.23 1.1 1.3 1.5
9 DO mg/l 4.07 4.03 4.68 3.82 3.96 3.9 3.16 3.14 3.11 3.17 > 4
10 NH4 mg/l 0.75 0.76 0.725 0.71 0.79 0.76 0.73 0.75 0.82 0.75 0.5
11 NO3 mg/l 9.6 9.6 9.8 9.4 9.5 10.3 11.2 9.5 10.1 9.6 10
12 NO2 mg/l 0.018 0.019 0.017 0.021 0.02 0.028 0.024 0.025 0.027 0.027 0.04
13 Turbidity NTU
5.0 5.1 5.0 5.1 5.8 5.3 5.8 6.2 6.11 6.15 -
14 Conductance 419 433 426 431 429 478 452 419 491 473 -
15 Total of minirals mg/l 0.05 0.52 0.053 0.052 0.09 0.13 0.11 0.09 0.09 0.13 -
16 Total phosphorus mg/l 120 121 120 122 128 107 109 115 119 123 -
17 CL- mg/l 487 492 480 511 547 357 368 379 402 358 600
18 Pb mg/l 0.062 0.064 0.061 0.063 0.07 0.076 0.061 0.063 0.058 0.052 0.05
19 Zn mg/l 1.82 1.81 1.82 1.84 1.88 1.6 1.42 1.52 1.53 1.47 1.5
29 Pesticide residues
for vegetation
protection
mg/l 0.14 0.126 0.128 0.13 0.067 0.063 0.060 0.068 0.065 0.067 0.4
21 Oil, grease mg/l 0.10 0.11 0.11 0.08 0.09 0.07 0.09 0.09 0.08 0.08 0.1
Drainage and wastewater treatment system project forThai Hoa town, Nghe An province”
Environmental Impact Assessment (EIA) - 57 –
PCO Consultant, 2010
Applied environmental standards
� QCVN 08-2008/BTNMT: National technical standard of surface water quality;
These water samples were taken at the site and preserved in flexible sample storage
tanks before being brought to analysis at the lab. Levels of water quality parameters is
compared with limit values of the parameters and the concentration of pollutants with
standards QCVN 08:2008/BTNMT corresponding value in column B. The analytical results
show that:
Physical parameters: are measured to be pH, temperature, density, conductance.
- The temperature value of the sample changes in seasonal and sampling location,
with time of measurement at hot and sunny weather, breeze, so the temperature
range 320C.
- pH value measured at the positions are within the permitted range, suitable with
environment for the living activities of aquatic species.
- Density at sample positions within the permitted range according to standard of
column B, because of washout process and dissolving the amount of silt in
water.
- Conductance in all samples is equivalent to the average value. Conductance,
density increase in the residential areas, the treatment plants, conductance and
density are lower than other positions.
Overall, the results of the physical parameters do not greatly affect the lives of aquatic
species but promote mineralization process, promote decomposition of pollutants in water
environment so affect beneficially in reducing pollution.
Chemical Criteria of water environment: the measurements are DO, TSS, BOD5, COD,
NH4+, NO2
-, NO3
-, Fe, Cl
-, T-P, Pb2
+, Zn2
+. These criteria reflect the most basically current
status of basic chemical quality of water environment.
- O2 dissolved concentration (DO) in the water meets standard so it promotes self-
cleaning operation process of micro-organisms, especially in the area of
proposed treatment plant. Results show that at points of NM4, 5, 6, 7, 8, 9, 10,
DO concentrations are lower than 4mg/l which do not meet allowable stardard.
- BOD5 content in 10 positions meets allowable standard; content of COD in the
positions is approximat or exceed allowable standard at a low level of about 1.1
times. This indicates that the quality of surface water in the project has sign of
COD pollution. This is resulted from dialy activities of the residents when they
discharge waste into receiving body.
- NH4+N content in the samples range from 0,41 – 0,49 mgNH4
+/l, The samples
have values approximate to the allowable standard. Therefore, NH4-N parameter
has sign of pollution to surface water source.
- NO2- content is 5 - 15 times lower than than standard.
- Content of NO3-
ranges from 9,4 – 11,2 mg/l which exceeds not much the
allowable standard , about 1.2 times; These results show that there is always a
strong conversion of Nitrogen treatment micro-organisms in surface water;
Drainage and wastewater treatment system project for Thai Hoa town, Nghe An province”
Environmental Impact Assessment (EIA) PCO Consultant, 2010
58
Thus, for chemical indicators, pay attention to the dissolved oxygen concentration COD,
NH4-N, NO2-N to have management measures and adjustments in accordance with standard
of surface water quality according to standards stated in QCVN 08-2008/BTNMT, type B.
Content of heavy metals: in most samples are lower than the standard: Pb2+
concentration was much lower than standard (0.1mgPb/l), Zn concentration in measured
samples (<1µg/l) values lower than standard (2mg/l); Cl-
concentration of samples ranges
between 9-34 mgCl-/l lower than the permitted standard (250mgCl
-/l), pesticide residues in
respective water samples is negligible, valued from 0.0012 to 0.0047mg/l. Respective Fe
content is from 0.1 to 0.4 mg Fe2+
/l, lower than the allowed value in all analyzed samples.
In general, KLN parameters at the time of analysis have no sign of exceeding the
permitted standard. However, those indicators tend to rise in coming years with the socio-
economic growth as well as the necessities of life. The question is the periodical observation
and measurement to assess properly before directing and guiding the implementation of all
levels and sectors concerned.
Parameter of micro-organism: lower than THE STANDARD in all sample analyzing
locations.
Reviews: Analyzing results of chemical, physical, biological indicators above shows
most of the water environmental parameters and contaminants are within permissible limit,
except the criteria of COD, BOD5, NH4-N, NO2-N are higher than standard but not much.
This shows that surface water quality in the area is quite well, meeting the requirement of
water supply in agriculture and aquaculture.
2.6.3 The status of underground water environment quality
Through studying of hydrogeological survey report and sociological assessment, we
see that local people in the studied wards/communes, in addition to tap water, they use water
in wells, rivers, lakes and rainwater.
Methods of sampling to determine the quality of underground water environment in project
area such as:
� Quantity of samples: obseved in 10 locations;
� Observation/sampling frequency: twice a day and in 2 continuous days. The
analysis resuts shown in the table below are average results of observations.
� Sampling time: from 26 to 27/6/2010
� Sampling analysis: from 28/6/2010 to 5/7/2010
� Observation location: Taken samples of drilling wells of 20 – 30m deep of
households in the area of work items of the project.
No. Symbol Sampling location Remark
1 NN1 Well water of Le Van Quy’s house,
hamlet 1, Boi village Taken directly from the tap when
pumping wells, not through filtering,
drilling at 30 m deep
2 NN2 well water of Le Thi Ly’s house,
Huong Bac hamlet Taken directly from the tap when
pumping drilling wells, not through
Drainage and wastewater treatment system project for Thai Hoa town, Nghe An province”
Environmental Impact Assessment (EIA) PCO Consultant, 2010
59
Table 2.13. Analyzing results of underground water environment quality
filtering, drilling at 30 m deep
3 NN3 well water of Nguyen Thi Dung’s
house, Nghia Thang intersection Taken directly from the tap when
pumping drilling wells, not through
filtering, drilling at 30 m deep
4 NN4 well water of brick pack of Long Son
ward Taken directly from the tap when
pumping drilling wells, not through
filtering, drilling at 30 m deep
5 NN5 well water of Nguyen Thi Nhung’s
house Taken directly from the tap when
pumping drilling wells, not through
filtering, drilling at 30 m deep
6 NN6 well water of Nam Trung JSC, Nghe
An Taken directly from the tap when
pumping drilling wells, not through
filtering, drilling at 20 m deep
7 NN7 well water of Le Mau Son house,,
village 10 Taken directly from the tap when
pumping drilling wells, not through
filtering, drilling at 20 m deep
8 NN8 Well water of Mr. Nguyen Viet
Hong’s house, hamlet 14 Taken directly from the tap when
pumping drilling wells, not through
filtering, drilling at 20 m deep
9 NN9 Well water of Tang Thi Hoa’s house,
Dong Tam hamlet. Taken directly from the tap when
pumping drilling wells, not through
filtering, drilling at 30 m deep
10 NN10 Well water of Thai Hoa hospital. Taken directly from the tap when
pumping drilling wells, not through
filtering, drilling at 30 m deep
Drainage and wastewater treatment system project forThai Hoa town, Nghe An province”
Environmental Impact Assessment (EIA) - 60 –
PCO Consultant, 2010
N
o.
CRITERIA UNIT NN 1 NN 2 NN 3 NN 4 NN 5 NN 6 NN 7 NN 8 NN 9 NN 10
QCVN09:20
08/BTNMT
1 Temperatur
e
oC 32.6 32.8 33.3 32.4 32.7 33.1 32.7 32.5 32.9 32.9
2 pH 6.8 6.65 7.03 6.38 6.89 7.12 6.58 6.93 6.71 7.08 5.5 - 8.5
3 Hardness
(based on
CaCO3)
mg/l 324 332 338 358 413 424 459 437 468 479 500
4 Total dregs mg/l 579 568 603 543 598 549 603 518 592 587 1500
5 As mg/l 0.032 0.036 0.031 0.042 0.029 0.031 0.022 0.0215 0.0322 0.031 0.05
6 Hg mg/l 0.0005 0.0006 0.0007 0.0007 0.0008 0.0003 0.0004 0.00042 0.00057 0.00046 0.001
7 Zn mg/l 2.83 2.14 1.96 2.34 1.98 2.08 1.12 1.09 1.34 1.98 3.0
8 Cl- mg/l 170 162 160 164 168 190 178 172 178 165 250
9 Total Cu mg/l 0.34 0.21 0.31 0.35 0.39 0.37 0.31 0.28 0.33 0.41 1.0
10 Pb mg/l 0.003 0.004 0.0021 0.0019 0.0018 0.0031 0.0032 0.025 0.028 0.029 0.01
11 Fe mg/l 2.43 2.12 3.0 3.17 3.07 2.51 2.43 3.12 2.67 2.78 5
12 Colifom MPN/100
ml
5 4 4 5 5 6 5 4 4 5 3
13 Colour - 54 55 56 61 58 60 57 62 63.6 69.1 -
14 cd mg/l 0.00021 0.00022 0.00026 0.00022 0.00027 0.00022 0.00021 0.00025 0.00022 0.00026 0.005
15 Chrome VI mg/l 0.009 0.0082 0.0071 0.0069 0.008 0.009 0.012 0.0078 0.011 0.0098 0.05
16 CN- mg/l 0.0035 0.0029 0.0032 0.0027 0.0038 0.0026 0.0028 0.0027 0.0029 0.0032 0.01
17 Fluoride mg/l 0.81 0.76 0.78 0.69 0.67 0.96 0.73 0.79 0.67 0.76 1
18 Mn mg/l 0.23 0.19 0.21 0.16 0.19 0.12 0.16 0.19 0.13 0.21 0.5
19 Nitrate mg/l 18.5 12.8 16.1 14.6 15.9 20.9 21.7 19.5 16.1 18.3 15
20 Phenol mg/l 0.00011 0.00015 0.00016 0.00014 0.00017 0.00017 0.00022 0.00021 0.00019 0.00018 0.001
21 Sulphate mg/l 223 248 276 251 239 243 297 278 289 292 400
22 Mercury mg/l 0.00016 0.00019 0.0002 0.00024 0.00023 0.00031 0.00036 0.00032 0.00039 0.00037 0.001
23 Selenium mg/l 0.006 0.005 0.005 0.006 0.0037 0.004 0.0027 0.0029 0.0031 0.0028 0.01
Drainage and wastewater treatment system project forThai Hoa town, Nghe An province”
Environmental Impact Assessment (EIA) - 61 –
PCO Consultant, 2010
Applied standards in alalyzing of underground water quality
- QCVN 01:2009/BYT: National technical standard of drinking water quality;
- QCVN 09-2008/BTMT: National technical standard of underground water quality;
Groundwater samples were analyzed for indicators: pH, color, hardness, TDS,
chloride, sulfate, nitrate, cadmium, arsenic, iron, manganese, copper, lead, zinc, mercury,
phenols, selenium, for coliform the evaluation of the quality of water sources that people
currently use and the evaluation of the quality of life of people through the quality of water
they use.
Physical parameters of underground water:
- pH of samples in neutral-slightly alkaline water, ranging between 6.90 to 7.27
in the limit from 6.5 to 8.5 for water;
- Low colour level of 3 - 17 NTU, in the permitted limit from 10 - 50 NTU;
- Solidity in the samples are lower than the standard by 228-284 mgCaCO3/l,
lower than standard (300 - 500mgCaCO3/l); For this criterion, the water is
suitable for all uses .
- Total dissolved TDS solids range between 254-341 mg/l, much lower than
standard (750 - 1500mg/l). Thus, the physical parameters are currently rather
good for water for food purposes as well as other uses.
Chemical parameters and KLN criterion: measure parameters of chloride, sulfate,
nitrate, cyanide, cadmium, arsenic, iron, manganese, copper, lead, zinc, mercury, phenols,
selenium with concentrations respectively as follows:
- Concentration of chloride Cl- ranges from 0.4 to 3.4 mgCl-/l have value in the
allowable standard limit of 200 - 600mgCl-/l;
- Sulfate concentration from 2.12 to 39.3 mgSO42-/l is much lower than the
standard range of 200 - SO42-400mg/l, F- concentration of the samples 0.01-
0.36mgF-/l is approximately standard (1.0 mg/l);
- Contents of most of the criteria of KLN are many times lower, the content of
Cu ranges between 1.36 to 9.9 µgCu2+/l lower or approximate standard (1.0
mg/l);
- Concentrations of CN-, As(III & VI), Cd2+, Pb2+, Zn2+, Mn2+, Hg2+, Fe2+,
Se2+, Cr6+ are much lower than permitted standards.
- Phenol concentrations in all analyzed samples are many times less than
standard (1µg/l), the highest sample is NN2 (0.9 µg/l).
Generally, the content of the parameters of heavy metals are mostly in permitted limits
and far away from permitted standard. The quality of underground water in the studied area is
relatively good, however, also requires the management of the exploitation and use of this
precious resource.
Biological criterion: Microbial density in 10 samples all exceed the allowed value
(3MPN/100ml). Hence, it needs to have more clearly researches to be able to envisage proper
progress towards these sensitive criterion.
Drainage and wastewater treatment system project for Thai Hoa town, Nghe An province”
Environmental Impact Assessment (EIA) PCO Consultant, 2010
62
Comment: The parameters and concentrations of pollutants are basis for assessing the
quality of underground water, then have proper use, make sure to meet the standard for
drinking and living water quality. Above criteria are mostly have much lower concentrations
than the permitted standard. Except for the criterion of Coliform which is higher than THE
STANDARD. To have a comprehensive look and have an effective handling of the living
water resource.
2.6.4 The status of wastewater environment quality
Methods of sampling to determine the quality of wastewater environment in project area such
as:
� Quantity of samples: obseved in 10 locations;
� Observation/sampling frequency: twice a day and in 2 continuous days. The
analysis resuts shown in the table below are average results of observations.
� Sampling time: from 26 to 27/6/2010
� Sampling analysis: from 28/6/2010 to 5/7/2010
� Observation location: the sampling location are typical positions, these are areas with
high concentrations of population and production activities, business, industry zones,
... so it may indicate the current status of wastewater quality with typical features for
areas of Thai Hoa town.
Wastewater environment quality is shown in the table below:
No. Symbol Sampling location Remark
1 NT1 Wastewater of Rubber
Company
At the discharge point to the discharge
sewer of the area, combined concrete
stormwater sewer.
2 NT2 Wastewater in draiange
sewer of Huong Bac hamlet
Soil ditch with wastwater, stagnant water.
3 NT3 Wastewater in draiange
sewer at Nghia Quang
market
Concrete combined sewer, bussiness
househods discharge directly into sewer.
4 NT4 Wastewater in draiange
sewer to Hieu river’s bridge
Concrete combined stormwater sewer
5 NT5 Wastewater in draiange
sewer at Hoa Hieu primary
school
Concrete combined stormwater sewer
6 NT6 Wastewater in draiange
sewer at Hieu market
Concrete combined sewer, bussiness
househods discharge directly into sewer.
7 NT7 Wastewater in draiange
sewer at the intersection of
Thai Hoa town
Concrete combined stormwater sewer
8 NT8 Wastewater in draiange
sewer near Le Mau Son
household
Soil ditch with wastwater, stagnant water.
9 NT9 Wastewater in draiange
sewer of block 8
Concrete combined stormwater sewer
10 NT10 Wastewater in draiange
sewer of Dong Tam hamlet
Soil ditch with wastwater, stagnant water.
Drainage and wastewater treatment system project forThai Hoa town, Nghe An province”
Environmental Impact Assessment (EIA) - 63 –
PCO Consultant, 2010
Table 2.19. Analysis results of wastewater environment quality
NO. PARAMETERS UNIT NT1
NT2 NT3
NT4 NT5 NT6
NT7 NT8
NT9 NT10 QCVN 14 :
2008/BTNMT
Value C,
column A
QCVN 24:
2009/BTNMT
value C,
column B
1 Temperature oC 33.2 32.4 33.3 32.2 34.3 32.3 33.2 33.4 32.2 32.3 - 40
2 PH
6.73 6.14 7.1 6.24 7.23 6.13 6.76 7.1 7.02 7.18 5 - 9 5.5 - 9
3 Odor
Mùi
thối Mùi
hôi
Mùi
hôi
Mùi
hôi
Mùi
hôi
Mùi
thối Mùi
hôi
Mùi
hôi
Mùi
hôi
Mùi
hôi
- Không khó
chịu
4 Color
58 54 68 59 60 78 72 61 64 62 - 50
5 Suspended
substances
mg/l 302 248 284 258 264 324 312 259 260 223 50 100
6 Oxidization
(COD)
mg/l02 304 300 318 302 300 312 297 265 287 296 - 100
7 As mg/l 0.18 0.118 0.129 0.128 0.126 0.32 0.21 0.22 0.22 0.23 - 0.1
8 Hg mg/l 0.009 0.008 0.0086 0.007 0.007 0.008 0.006 0.0063 0.0076 0.007 - 0.01
9 Zn mg/l 2.6 2.53 2.42 2.11 2.01 2.86 2.12 2.25 2.01 2.15 - 3
10 Crom (III) mg/l 1.02 0.95 1.21 0.81 0.56 1.85 1.42 1.26 1.33 1.18 - 1
11 Crom (VI) mg/l 0.14 0.11 0.15 0.1 0.12 0.19 0.12 0.1 0.13 0.14 - 0.1
12 Cu mg/l 1.9 1.12 1.18 1.1 1.2 1.42 1.06 1.02 1.04 1.07 - 2
13 NH4 mg/l 19.4 13.2 16.4 11.8 10.2 17.0 143.6 10.8 10.3 11.4 5 10
14 Total N mg/l 55.2 42.3 55.7 50.9 51.4 50.8 46.2 44.1 48.9 47.3 30
15 Total P mg/l 7.12 5.21 6.82 4.92 4.82 7.58 7.12 7.06 7.1 7.0 6
16 Colifom MPN/l 28000 22000 26000 20000 20200 28600 20000 21000 19500 19000 3000 5000
17 BOD 5 mg/l 160 123 191 132 139 196 152 147 150 153 30 50
18 Fe mg/l 5.67 3.8 4.92 3.67 3.79 4.03 4.28 3.14 3.73 4.02 5
19 Mn mg/l 0.52 0.42 0.56 0.43 0.42 0.54 0.58 0.45 0.62 0.67 1
20 Florua mg/l 5.3 4.12 4.89 4.21 4.09 4.89 4.04 4.2 4.02 3.97 10
21 Sulfua mg/l 0.12 0.082 0.14 0.084 0.08 0.190 0.12 0.14 0.16 0.144 0.5
22 Clorua mg/l 224 201 235 206 209 269 201 208 209 212 600
23 Cadimi mg/l 0.005 0.001 0.004 0.002 0.0023 0.003 0.001 0.001 0.0035 0.0026 0.01
24 Pb mg/l 0.22 0.13 0.167 0.12 0.13 0.16 0.11 0.13 0.11 0.112 0.5
Drainage and wastewater treatment system project forThai Hoa town, Nghe An province”
Environmental Impact Assessment (EIA) - 64 –
PCO Consultant, 2010
Comparison standard:
� QCVN 14:2008/BTNMT: National technical standard of living wastewater
quality;
� QCVN 24:2009/BTNMT: National technical standard of industrial wastewater
quality.
The parameters of wastewater quality in the study area compared to standard QCVN
14:2008/BTNMT, must be less than the value of column B before the water flows into the
public catchment used for purposes of irrigation and drainage; Particularly with some
sampling locations of wastewater from factories, enterprises, the wastewater quality must
reach QCVN 24:2009/BTNMT, must be less than the value of column B before it is
discharged into the receiving sources which are water source not used for domestic water
supply. The concentration of pollutants is as follows:
a. Physical parameters of wastewater:
Including the parameters/criteria: temperature, pH, odor, color, these arameters is
analyzed quickly at the landscape with fast measurement equipments.
- Water temperature changes between 19 – 22,30C, lower than permitted standard.
- pH in the sampling areas are almost neutral, favorable for the operations of aquatic
species and to meet different purposes.
- Odor: not reach standard in all sampling locations, malodorous.
- Criterion of water color beyond the THE STANDARD at low level, from 1.1 to 1.6
times in all analyzed samples. Colour is also an important criterion, if the excess too
much will cause adiaphanous, reduce degradation of pollutants in the water under the
effect of sunlight; reduce the viability of the aquatic species then increase the risk of
meronecrosis of individuals live in the water, thereby, increasing penetration of
pollutants from those entities.
Results of physical criteria help to see the need to collect and treat wastewater in town
to help improve the aesthetics and quality of surface water environment, enhance quality of
life for people in the area.
b. Chemical parameters of wastewater:
Mentioned criteria are COD, BOD5, suspended solid (SS), total N, total P, cadimi,
arsenic, mercury, copper, lead, zinc, iron, manganese, chloride, sulfide, fluoride.
Almost chemical criteria reach permitted standard (THE STANDARD), but
concentration of COD, BOD5, Suspended solid (SS) in 10 samples are exceed THE
STANDARD: criterion of BOD5 exceeds THE STANDARD from 2,5 � 3,8 times compared
to THE STANDARD relatively to samples NT2 and NT3; criterion of COD exceeds THE
STANDARD average of 3 times. Concentration of suspended solid (SS) exceeds THE
STANDARD from 2,7 � 3,2 times compared to THE STANDARD relatively to samples
NT8 and NT3.
Concentrations of BOD5, COD are higher than standard at all locations show that there
is unlikely to have collecting solid waste treament plant or wastewater containing high
Drainage and wastewater treatment system project for Thai Hoa town, Nghe An province”
Environmental Impact Assessment (EIA) PCO Consultant, 2010
65
organic content, were not treated but flows into public receiving source, particularly shown on
the chart below:
Chart 2.3. Analyzing result of COD (mg/l) criterion in wastewater compared to standard
304 300318
302 300312
297
265287 296
0
50
100
150
200
250
300
350
NT1 NT2 NT3 NT4 NT5 NT6 NT7 NT8 NT9 NT10
COD
QCVN 24:2009
Chart 2.4. Analyzing result of BOD5 (mg/l) criterion in wastewater compared to standard
160
123
191
132 139
196
152 147 150 153
0
50
100
150
200
250
NT1 NT2 NT3 NT4 NT5 NT6 NT7 NT8 NT9 NT10
BOD 5
QCVN 14:2009
QCVN 24:2010
Drainage and wastewater treatment system project for Thai Hoa town, Nghe An province”
Environmental Impact Assessment (EIA) PCO Consultant, 2010
66
Chart 2.5. Analyzing result of SS (mg/l) criterion in wastewater compared to standard
302
248
284258 264
324312
259 260
223
0
50
100
150
200
250
300
350
NT1 NT2 NT3 NT4 NT5 NT6 NT7 NT8 NT9 NT10
Suspended solid (SS)
QCVN 14:2008
QCVN 24:2009
Criteria of heavy metals were lower than the permitted standard, only Chrome
criterion exceeds or approximate THE STANDARD at low level.
Total N and total P criteria in some samples exceed the THE STANDARD, the highest
is 1.2 times compared to THE STANDARD; NH4 criterion exceeds THE STANDARD 1.9
times higher.
Microbiological Criterion: mentioned as criterion of coliform density. According to
permitted standard in QCVN 14:2008 and QCVN 24:2009, microbial density in the samples
are higher than THE STANDARD from 6.3 to 9.5 times compared to QCVN 14:2008 and 3.8
- 5.7 times higher than QCVN 24:2009. Microbial density is important criterion for assessing
the risk of infection and spread of epidemics, to have better ways to direct epidemiology
safety issues.
Chart 2.6. Analyzing result of Coliform criterion in wastewater compared to standard
0
5000
10000
15000
20000
25000
30000
NT1 NT2 NT3 NT4 NT5 NT6 NT7 NT8 NT9 NT10
28000
22000
26000
20000 20200
28600
2000021000
19500 19000
Colifom (MPN/l) QCVN 14:2008 QCVN 24:2009
Drainage and wastewater treatment system project for Thai Hoa town, Nghe An province”
Environmental Impact Assessment (EIA) PCO Consultant, 2010
67
General comment:
For the parameters of pollution, the concentrations of these parameters are mostly in
the permitted limit or much lower than THE STANDARD. Except odor criterion, parameters
of BOD5, COD, SS, Cr, microbiological criteion have sign of pollutant. There shoud be
specific monitoring plan to each project phase and need to process wastewater before
discharge into sewers, drainage channels ... in the project area.
2.6.5. The status of sludge quality
Methods of sampling to determine the quality of sludge in project area such as:
� Quantity of samples: obseved in 10 locations;
� Sampling time: from 26 to 27/6/2010
� Sampling analysis: from 28/6/2010 to 5/7/2010
� Observation location: the sampling loaction are typical positions in drainage sewer,
these are areas with high concentrations of population and production activities,
business, industry zones, main streets, market, hopital,...
No. Symbol Sampling location Remark
1 D1 Sludge in draiange sewer of Huong
Bac hamlet
Stagnant water at location taking
sludge.
2 D2 Sludge in draiange sewer at Nghia
Quang market
Much sludge in sewer
3 D3 Sludge in draiange sewer to Hieu
river’s bridge
No.
4 D4 Sludge in drainage sewer at Hieu
maket.
Much sludge in sewer
5 D5 Sludge in drainage sewer at the
inter-section of Thai Hoa town.
Much sludge in sewer
6 D6 Sludge in draiange sewer of block 8 Stagnant water at location taking
sludge.
7 D7 Sludge in draiange sewer near Tang
Thi Hoa household, Dong Tam
hamlet
Stagnant water at location taking
sludge.
8 D8 Sludge in drainage sewer at Thai
Hoa hostel
Much sludge in sewer
9 D9 Sludge in Bau Sen lake No
10 D10 Sludge in Hieu river No
Drainage and wastewater treatment system project forThai Hoa town, Nghe An province”
Environmental Impact Assessment (EIA) - 68 –
PCO Consultant, 2010
Table 2.15. Analyzing result sludge samples in studied area
No. PARAME
TERS UNIT D1 D2 D3 D4 D5 D5 D7 D8 D9 D10
QCVN
03:2008/BTNT
M;
QCVN 15-2008
1 pH 6.78 6.52 6.79 6.54 6.97 6.46 6.58 6.54 6.15 6.98 -
2 Humidity % 34.21 37.0 36.9 34.0 33.8 47.8 47.0 46.3 44.9 45.8 -
3 SO4 g/kg 0.64 0.67 0.69 0.68 0.71 0.724 0.735 0.689 0.693 0.692 -
4 Cu g/kg 0.34 0.35 0.37 0.35 0.37 0.314 0.309 0.324 0.37 0.31 0.07
5 Pb g/kg 0.0015 0.0017 0.0018 0.0019 0.0022 0.0021 0.0022 0.0019 0.002 0.0019 0.12
6 Zn g/kg 0.014 0.016 0.015 0.016 0.013 0.0179 0.072 0.0168 0.0174 0.0165 0.2
7 Total N g/kg 0.468 0.463 0.449 0.457 0.459 0.52 0.47 0.482 0.471 0.468 -
8 Total P g/kg 0.354 0.357 0.382 0.319 0.424 0.36 0.35 0.36 0.35 0.38 -
9 Diazinon
pesticide
residues
mg/kg 0.0069 0.0064 0.0062 0.0059 0.0058 0.0054 0.0056 0.0059 0.0054 0.0057 0.05
10 Colifom MPN/kg 15900 16800 16100 15990 17900 15600 16900 17100 15900 17800 -
Drainage and wastewater treatment system project forThai Hoa town, Nghe An province”
Environmental Impact Assessment (EIA) - 69 –
PCO Consultant, 2010
Applied standards in alalyzing of underground water quality
� QCVN 03:2008/BTNTM: National technical standard of permitted limit of
underground heavy metal.
� QCVN 15-2008: National technical standard of underground pesticide residues.
For sludge samples, the value to assess of the acidity of sludge is proposed for
consideration to be pHKCl, which saw the exchange acidity in sludge and can predict the waste
discharged the river system. pHKCl value shows in all the pHKCl samples were slightly sour,
range from 6.65 to 7.06, much higher than values commonly found in alluvial soil with an
average pHKCl value of about 4.29. Thus, the content of substances to discharge into the river
with a large content of organic but not great in sludge, it shows that organic content is washed
away by water current or persistent.
Humidity of samples are different, sample D4 is the lowest (13.5%) and highest in
sample D6 (25.5%). Often in agriculture, people still use the waste water and sludge,
sediment of the rivers to supplement the content of organic matter, humus and nutrients to
plants. The higher humidity of the sludge component or organic ingredients are, the greater
the use of sludge as a common measure to add nutrients and improve the mechanical
components in agriculture.
The heavy metal criteria, as prescribed in the standard of maximum limit of some
heavy metals in soil under standard QCVN 03:2008/BTNTM for relative Cu, Fe, Zn content
with the permitted values lower than the values of 100, 200, 300 mg/kg or ppm. The analysis
results in the table on all 10 samples were reached THE STANDARD. These indicators show
that until the current time, there is no sign of contamination or accumulation of heavy metals
in the sludge environment in the river and spring in the area of research.
For analysis samples, total nitrogen concentration ranges from 82 to 352 ppm and
total Phosphorus concentration ranges from 29.96 to 56.67 ppm. Ratio of T-N/T-P of the
samples range from 2.7 to 6.2, this ratio is relatively high, suggesting that sludge in these
positions is expressed organic pollutant, especially animal protein and residues protein in the
process of farming.
Criterion of pesticides pollution is also mentioned as typical indicators of pollution of
water, soil and other chemicals used in daily life and cultivation of the people in the project
area. For 10 sludge samples for analysis, all samples have levels of pesticide residues in the
limit and much lower than THE STANDARD so it can be said that about this criterion, the
sludge in the project area has no sign of contamination of pesticides.
Figure 13 –Daagram measurement analysis baseline environment condition
* General comment:
Sludge quality in project area has typical parameters of plain soil of mechanical
components, the physical, chemical parameters and pesticide residues, heavy metals of soil is
not high, levels of some heavy metals meet the THE STANDARD in the provision of
permitted standard. Thus, almost the Physical - chemical parameters of sludge in the river bed
and sludge in the drains virtually have no sign of pollution.
Drainage and wastewater treatment system project for Thai Hoa town, Nghe An province”
Environmental Impact Assessment (EIA) PCO Consultant, 2010
70
GENERAL CONCLUSION:
� Thai Hoa Town’s drainage system status is not good. With economic growth in recent
years, the town's surface coefficient increases, flow increases, along with complicated
weather lead to overloading of existing pipes, causing flooding specially in flood
season;
� Road system of the town is expanded and develop, constructions, water supplies has
been built and upgraded, while the drainage system has not been properly cared;
� Cultural standard and awareness of local residents were not high for water, trash
discharging... arbitrarily cause flow blocked in drains, reduce the efficiency of the
existing drainage system in the region;
� Quality of surface water is now only slightly organic contaminated, but the risk of
microbiological contamination is very high. If there are not preventive measures,
preliminary treatment and collection to process under the general direction of the
town, the water quality of surface water will decrease significantly in the coming time,
when the urbanization process grow dramatically;
� Untreated wastewater directly discharged into the environment has caused
environmental pollution, especially in residential areas.
For the reasons above, that should be a investment projects suitable with the system
overall planning of drainage system and sewage treatment in Thai Hoa town until 2020, in
conformity with the general planning Adjustment of Thai Hoa Town until 2020 to meet the
development requirements of the town in particular and Nghe An Province in particular.
Therefore, “Drainage and wastewater treatment system project for Thai Hoa town -
Nghe An province" was created to specify the priority project identified in the overall plan,
step by step resolve thoroughly the flooding problem and to eliminate environmental pollution
caused by waste water, contributing to sustainable development of the economy – society
combined with environment protection of Nghe An province.
Drainage and wastewater treatment system project for Thai Hoa town, Nghe An province”
Environmental Impact Assessment (EIA) PCO Consultant, 2010
71
CHAPTER III:
ENVIRONMENT IMPACT ASSESSMENT
3.1. OVERVIEW OF THE IMPACTS OF PROJECT
3.1.1. Positive impact of the project
Drainage and Wastewater Treatment System Sub-project for Thai Hoa Town, Nghe An
province is a project aiming at environmental improvement, waste water treatment. The major
impacts of the project are positive. This is one of basic steps in the the environmental
protection through the completion of drainage, wastewaer collection and treatment system,
and gradually raises public awareness and improves sanitation conditions .
Housing sanitation improvement:
Providing a collection and wastewater treatment system for the residents in 6
communes/wards of the project. When the project is put in to operation, domestic wastewater
from connection households will be treated. The willingneess to connection survey was
carried out on 100% of households in the project area. The results show that number of
households desiring to use the collection and waste water treatment service in the first phase
of the project reach 68.9% (6089/8929 households, with about 57,410 people benefited
directly from the project).
Table 1. Connection households
No. Ward/commune Number of
households
No. of connection
households Rate (%)
1 Hoa Hieu ward 3,950 2,777 70.30%
2 Quang Phong ward 323 275 85.14%
3 Long Son ward 864 663 76.74%
4 Quang Tien ward 2,784 1,684 60.49%
5 Nghia My
commune 366 277 75.68%
6 Nghia Tien
commune 542 413 76.20%
Total 8,829 6,089 68.97%
(Source: Willingness to connection survey report of the project, 2010)
Improvement of surface water, groud water quality, flood control:
When the project is put into operation, the quality of surface and ground water in the project
area will be improved significantly because the treated water meets Class B, QCVN 14:
2008/BTNMT, ensuring quality of water source used for agricultural irrigation purposes.
Detailed quantitative results will be presented specifically in the section of assessing the
ability of reception and mixing of waste water after treatment.
Besides, when the drainage system is designed synchronously, the flooding situation at some
points as presented in the current flooding situation in the project area. Collected wastewater
will be treated which help solve the stagnant / standing water waste situation in all residential
areas, causing unsanitary and affecting people's health. Urban landscape is improved better.
Drainage and wastewater treatment system project for Thai Hoa town, Nghe An province”
Environmental Impact Assessment (EIA) PCO Consultant, 2010
72
Other economic benefits:
Average health cost paid for disease examination, staying at hospital cause by
environmental pollution due to there is no drainage system/household. When the project is not
implemented, each household has to pay approximate 720,000 VND/household/year for
health examination service for diseases relating to environmental pollution. When the project
is implemented, each household has to pay only approximate 10,000 VND/year/household for
health examination service for diseases relating to environmental pollution. This figure is very
low and we can see considerable benefits from the project, so we can say that there is no
expense paid for health examination service for diseases relating to environmental pollution
when the project is constructed.
Reducing the average expense for collecting solid waste and discharging wastewater.
When the project is not implemented, the average expense for collecting solid waste and
wastewater is approximate 10,000 VND/month/household (in which expense for collecting
solid waste is 4000VND and wastewater is 6000VND) equalling to
120,000VND/household/year. Thus total expense for collecting solid waste and
wastewater/year in the project area is 2,734,801 VND/year (with 22,790 households). Thus
there is the difference between total expense paid for drainage and environmental sanitation
service when the project is implemented and the project is not implemented. This is the
economic benefit which can be quantified.
Table 1: Impacts with and without the project
Impacts Without the project with the project
Positive
impacts
- No impact such as dust, noise,
air pollution…
- Solving the flood situation
- domestic wastwater will be
collected and treated, environment is
improved
- increasing the locals’ living
conditions in 6 wards/communes of the
project area.
Negative
impacts
- The city’s sanitation condtions
will be reduced, especially in the
density area.
- opportunity cost may be higher
and the issues of environment and
society will be higher such as:
+ Environment caused by wastwater
+ flood in rainy season
+ the surface and underground water
quality is reduced.
+ unhygienic living conditions;
+ affecting to the urban landscape;
- The whole 6 wards/communes of
the project area will be affected by the
project activities such as dust, noise,
pollution…
- In the operation period, the
receiving source can be polluted if the
treated wastewater does not meet the
standard.
Drainage and wastewater treatment system project for Thai Hoa town, Nghe An province”
Environmental Impact Assessment (EIA) PCO Consultant, 2010
73
3.1.2. Negative impacts of the project
Impact sources:
Besides the positive impacts mentioned above, the project implementation process will cause
negative impacts on the environment and people’s health in project areas. Impact sources are
determined by reviewing the performance of the Project’s work items, the socio-economic
and environmental conditions in the project area and the technological selection proposals.
Following is the summary table of environmental impacts:
Table 2: Summary of environmental impacts of the project
TT Items Environmental impacts
I Environmental impacts during site clearance period
Compensation,
land acquisition
- Change in the land use purposes
- Direct impact on local residents in the project area in using land
for production and living.
- Disordering socio-economic activities in the area.
II Environmental impacts during construction period.
1 Wastewater
pumping station
- Gathering too many workers can cause social impacts such as
dis-order of security caused by differences in lifestyle, difficult to
control the population.
- The construction causes noise, smoke, dust, operation of
construction means adversely affect the surrounding environment.
- Pollution of surface water and groundwater due to waste water
during construction.
2
Construction of
two pumping
stations
- Dust pollution: due to soil, sand and stone in the process of
excavation and leveling in which the quantity of excavation and
construction of 2 treatment plants is rather big and in large scale
so the pollution risk is high without good protecting measures.
- Air pollution, noise, vibration: the operation of construction
facilities in the area and along the transportation route of rock and
materials.
- Change in mechanical and physical properties of the ground.
- Impact on traffic along the route of transporting materials and
leveling and the areas of materials exploitation.
- Pollution of surface water: waste water from construction
activities.
- Domestic waste of workers, construction waste at site.
3
Construction of
stormwater,
wastewater and
service pipeline.
- Air pollution, dust, noise, vibration: arising from the
construction vehicles, transportation of materials;
- Obstructing the transportation of construction material.
- Occupying temporarily the site in the vicinity of the
construction area due to gathering materials.
- Occupying temporarily the site in the vicinity of the
construction area due to gathering materials.
Impact on daily activities of local residents.
- Gathering too many workers can cause social impacts such as
dis-order of security caused by differences in lifestyle, difficult to
Drainage and wastewater treatment system project for Thai Hoa town, Nghe An province”
Environmental Impact Assessment (EIA) PCO Consultant, 2010
74
TT Items Environmental impacts
control the population.
III Environmental impacts in operation period
1
Opeartion and
management of
the system
- Noise while operating the treatment plant and wastewater
pumping stations.
- Bad odor and sludge from the treatment plants.
- Risk during operation (chemical leakage, fire, explosion, output
water quality not meet standards, pollution of surface and
groundwater in the project area ...).
- Complaints / nuisance of communities, particularly the
wastewater treatment plant area and wastewater pumping
stations.
3.1.3. The Project’s affected scale:
� Firstly (Geological scale)
The environmental impacts due to the implementation of the Project occur in entire
project area, including 4 wards namely Hoa Hieu, Long Son, Quang Phong, Quang Tien and
the central residential areas of 02 communes namely Nghia Tien and Nghia My, especially at
the construction site and a part of residential area next to the Site.
The construction of rainwater drainage system and waste water collection system will
strongly affect households along the road sides, especially the town’s main roads such as
National Highway No. 48, local roads with high density of population.
During construction and installation of the Waste Water Treatment Plant, there will be
fewer impacts as the selected location is relatively far from the residential area. However, in
case the operation of the treatment plant is not good, it would affect the environmental
condition and the quality of treated water does not meet standard colume B, QCVN
14:2009/BTNMT – The national technical regulation on waste water quality when
discharging into surface water environment used for irrigation and agricultural production.
Then, the geological impact scale is not only limited in Thai Hoa town but also in neighboring
areas. Therefore, the guarantee of the effective operation of the Waste Water Treatment Plant,
technology and treated water quality are the prerequisite conditions for the implementation of
the project.
� Secondly (Time & quantity scale)
The project implementation is conducted in 02 phases (2010- 2020 & 2020- 2030)
and quantity of work items has certain impacts on the natural environment surrounding. The
main impacts when the project is completed are positive, whereas adverse impacts are
insignificant and only occur during the construction period.
The Project itself is an environmental pollution treatment work and particularly a
treatment work for wastewater sources generated from daily activities, production, business-
services, etc. This remains a shortcoming and concerned issue of most urban areas, especially
developing areas in Viet Nam. The overall impacts of the project are positive which are
suitable with the direction of the local authorities of Thai Hoa town and Nghe An province in
protecting the environment, meeting the development trend and sustainable development.
Drainage and wastewater treatment system project for Thai Hoa town, Nghe An province”
Environmental Impact Assessment (EIA) PCO Consultant, 2010
75
3.2. ASSESSMENT OF PROPOSAL TECHNICAL OPTIONS
3.2.1. Design of stormwater and wastewater sewer system
a) Selection of drainage system types:
Drainage system selected is the completely separated system, including: (1)
Rainwater drainage system: rainwater is collected into a separate sewer system, directly
discharged into river, ditch and canal without treatment; (2) Wastewater sewer system:
domestic and production waste water flows into a sewer system and treated in the treatment
plant.
Contents Separate system
Advantages
- The sanitation is best ensured. Waste water is completely
collected and treated to bring a healthy environment for the
town
- The drainage system is scientifically organized. Rain water
and waste water are separated convenient for flood control,
environment treatment and protection.
- It is suitable with new cities where the drainage system has
not been ever invested to construct.
Disadvantages - The initial construction investment capital is intensive. Two
completely separated systems must be built.
- It causes waste because in dry season, rainwater sewer
system is less.
- Management is complicated due to two existed drainage
systems.
b) Technological and engineering selection:
Stormwater drainage system is designed into 3 grades as follows:
Classification Definition
Grade 1 River, canals and ditches for natural drainage (D800 - D1000 sewers)
Grade 2 Main sewers transporting rain water to receiving sources such as cannals and
ditches and discharging into rivers (D400 – D600 sewer)
Grade 3 Sewers and ditches of the rain water receiving sub-area (D≤400 sewers)
Manhole 656 new manholes to be built to collect pavement water with intakes; test
manhole
Outlets 37 new outlets of various types to be built in positions in the town
Rain water drainage sewers are designed in accordance with standards and codes on
network construction and construction in general. Besides, the conformity of engineering
design and technology is confirmed based on reference to water drainage level of drainage
systems which have been recently implemented nationwide such as: Thai Binh, Thanh Hoa,
Vinh, Ha Tinh and so on.
Technology and engineering selection of waste water collection system for the town is
relatively proper. Waste water from households, service shops, small production shops,
agencies, public areas, etc., will be collected into the waste water collection system via a
terminal manholes then pumped into main sewer system to flow into waste water pumping
station and WWTPs. Therefore, waste water completely separated not mixing with rain water
Drainage and wastewater treatment system project for Thai Hoa town, Nghe An province”
Environmental Impact Assessment (EIA) PCO Consultant, 2010
76
will minimize risks of polluting the receiving sources and limit surrounding environment
pollution because all waste water volume is collected.
3.2.2. Location and Design of wastewater pumping station
In order to reduce depth of pipe and increase waste water pressure to WWTSs, the
pumping stations must be calculated so that water collection depth is not over 4.5m. With
water collection system conditions and characteristics, 09 pumping stations are built in the
first phase of the project. The pumping stations are constructed by cast-in-situ concrete in
rectangular or square shape with underground pumps. The pipelines in the pumping station
are made of stainless steel. The pipelines are arranged outside the station. With such waste
water pumping stations, it is possible to collect waste water from main collection sewers to
WWTPs as scheduled, meeting the waste water collection demand of local people.
With selected technology and engineering, significant impacts on environment and
local people are unavailable in the project area thanks to strengths as follows:
- Impacts of the pumping stations are minimized because it is located in a
relatively isolated area, i.e., in the center of traffic roads and discharging
points;
- When constructing, the underground pumping station is designed to ensure
aesthetics for the town. Deodorizing chemicals and special toilet equipment are
used.
- During operation, rubbish collection cycle in bar screens and periodic station
clearing cycle are available. Regarding pumping station, the station size is
sufficiently designed and arranged to calculate collection chamber and arrange
steel ladders for operation, repair and regular maintenance.
- When flood and overflow accidents happen when there is a flood, etc,
recommended measure is to increase pump capacity in the station or use
mobile pumps to directly discharge into rivers to ensure the station’s safety and
useful life.
Therefore, construction and operation of waste water collection pumping stations in
general have insignificant impacts on environment and local people in the project area.
3.2.3. Location of Wastewater Treatment Plants selection
It is very important to select location for the treatment plants to ensure the high
performance, support of local people and minimize environment impacts. Two treatment
plants are located as follows:
- The Station No. 1 is responsible for treating waste water collected from the
Eastern bank of Hieu River with capacity of Q=6,000m3/day.night. The station
is built in a crop field belonging to Blocks 4, 5, and 6, Long Son ward (next to
Giong area). This station’s land area is 12.7ha. The distance to the nearest
residential area is 500m; there is no family household living in this area;
- The Station No. 2 is responsible for treating waste water collected from the
Western bank of Hieu River with capacity of Q=3,000m3/day.night. The
station is built in hamlet 1 of Nghia Tien commune. This station’s land area is
Drainage and wastewater treatment system project for Thai Hoa town, Nghe An province”
Environmental Impact Assessment (EIA) PCO Consultant, 2010
77
9.1ha. The distance to the nearest residential area is 500m; there is no family
household living in this area.
Table 2: Assessment of WWTP location selection
Elements Characteristics Assessment
residential
area
WWTP1 (12.7 hectars), WWTP 2 (9.1 hectars), are enough
for the WWTP and its ausiliary works,
+++
Safe distance 200 meters far from the nearest residential area, (200m,
QCVN 07:2010/BXD)
+++
entrance large enough +++
land using no disput +++
land acquisition -
clearance is convinient ++
terrain good natural condition +++
low land, flooding usually happens, however, the code will be
heightened to +4.5 meters to avoid flood
++
flood concern flood ++
air distance is 200 m to avoid smell +++
ecosystem no special ecosystem is harmed +++
culture no sensitive cultural architecture +++
afformity
with plan
afformity with ThaiHoa town PC’s plan, the location of the
WWTP is approved
+++
approved by Thai Hoa town PC and Long Son CPC, Nghia
Tien CPC
+++
affecting
other
activities
no affection +++
Note: +++: Very good ++: rather good +: good 0: no impact
-: bad --: rather bad ---: very bad
According to the national technical codes QCVN 07:2010/BXD on prescribing the
minimum safety distance between waste water treatment works and residential areas are
described in following table:
Table 3.1: Minimum distance between the pumping stations, waste water treatment
works and residential areas, hospitals, schools, public works and food factories
No Types of works
Minimum safety distance (m) corresponding to capacity
(m3/day.night)
< 200
(m3/day.night)
200-5.000
(m3/day.night)
>5.00050.000
(m3/day.night)
> 50.000
(m3/day.night)
1
Waste water
pumping station 15 20 25 30
2
Waste Water
Treatment Plants:
a Mechanical 100 200 300 400
Drainage and wastewater treatment system project for Thai Hoa town, Nghe An province”
Environmental Impact Assessment (EIA) PCO Consultant, 2010
78
treatment with
sludge drying bed
b Artificial bio-
treatment with
sludge drying bed
100 150 300 400
c Bio-treatment
without sludge
drying yard, having
sludge desiccator,
closed device to
deodorize bad smell
10 15 30 40
d
Land lot to filter
waste water 100 150 300 500
e
Irrigation land lot
for watering green
trees and agriculture
purpose
50 200 400 1000
f Bio-lake 50 200
g Oxidization ditch 50 150
(Source: QCVN 07:2010/BXD – The National Technological Codes of City’s Technical
Infrastructure Works)
Therefore, selected positions for the two aforesaid stations comply with QCVN
07:2010/BXD applied for the distance to the nearest residential area. This is appropriate with
situation and requirements of the selected areas to locate the Waste Water Treatment Plants in
accordance with current regulations on environment.
� Environmental sensitive activities at the downstream behind discharge point of the
treatment plant.
Currently, at the downstream behind the discharge point of the two treatment plants
(in Giong area – Long Son ward – treatment plant 1 and in village 1 – Nghia Tien commune).
These two discharge points discharge directly into Hieu river. The consultant designs and
assesses the environmental safety for the project basing on thoroughly surveying these areas
to ensure that there is no environmental sensitive activities at the downstream behind
discharge points, specifically:
i. Taking surface water for water treatment: At the downstream of the discharge
points, there are not any surface water intake structure for water treatment.
However, at the upstream of the discharge point, there is one surface water
intake structure for water treatment with capacity of 4.000m3/day to serve the
inner area of Thai Hoa town. However, the distance between water taking
point and the discharge point is safe which is approximately 2km upstream of
the discharge point. Therefore, the discharge process will not cause adverse
impacts on explotation of the surface water source.
ii. Taking surface water for agricultural production: at the downstream of
discharge points, the action will not be done. Most area of agricultural
cultivation along two sides of Hieu river are used for planting farm produce
such as corn, sugar-cane, etc so it does not require water from Hieu river for
irrigation.
Drainage and wastewater treatment system project for Thai Hoa town, Nghe An province”
Environmental Impact Assessment (EIA) PCO Consultant, 2010
79
iii. Aquaculture: There is no aquaculture area at the downstream of the discharge
point. In stead, only activities such as construction, sifting for gold, etc which
are spontaneous activities of local people.
iv. Distance from wastewater treatment plant to the nearest residential area: (1) As
for treatment plant No.1 (in Long Son ward), the distance from the treatment
plant to the nearest residential area is safe, about 1 km (1000m). However, as
this area is under planning, so in the future, this distance is 600m; As for
treatment plant No.2 (Nghia Tien commune), the distance from treatment plant
to the nearest residential area is 500m. Residents in this area is scatteredly,
about 20 households in village 1 – Nghia Tien commune. However, these
households have large garden with the high density of green trees (about 50-
60% on average compared to the area of household). This is a favourable
condition to reduce impacts caused by bad odour when the treatment plant is
put into operation. This distance ensures meeting standard QCVN
07:2010/BXD – National technical standard for urban technical infrastructure
as mentioned above.
v. There is no public works such as hospital, schools, food processing factories
within the safe distance of the treatment plants above.
vi. Through the financial- technical comparison, the proposal has significant
strengths as follows: (i) The plant’s construction cost is lowest; (ii) Operation
management expense is lowest; (iii) Price of producing 1m3 of waste water is
lowest; (iv) Operation and management are convenient.
3.2.4. Wastwater treatment technology selection
Selected waste water treatment technology proposal is (3) biolakes when comparing
advantages and disadvantages with that of another two treatment technology solutions namely
(1) Sequencing Batch Reactor (SBR) (2) oxidization ditch technology; specifically:
Table 3 : Comparison to select option
Content Option 1 Option 2 Option 3
Method Wastewater treatment by
SBR.
Wastewater treatment by
oxidation ditch
Wastewater
treatment by
biological pond
Treatment
process
primary sedimentation
tank – SBR tank
Biological channel Using anaerobic
pond, stabilization
pond (biological
treatment ponds)
Advantages - The construction works
are simple, size of the
system are small.
- Ability of cleaning
water is high because of
the microbiology
wastewater treatment
controller (BOD5 15-25
mg/l, COD 60-80mg/l)
- Using of SBR
technology requires less
- Compliance with quality
and input wastewater flow
varying by season and time.
- High treatment efficiency,
ensure standard in strict
conditions.
- Easy management and
operation
- Not large land
occupation area.
- Low production costs
- Low initial
investment and
construction cost.
- The simple
construction.
- Easy management
and operation.
- Lowest production
cost (labor, energy)
Drainage and wastewater treatment system project for Thai Hoa town, Nghe An province”
Environmental Impact Assessment (EIA) PCO Consultant, 2010
80
energy, power, easily
cope with incidents
(labor, energy).
- Compliance with the
requirements and
characteristics of a new
urban and having new
construction of separate
drainage system completely
from the start
Disadvantages - Large land occupation
area.
- High labor cost for
management and
operation.
- Difficult process
control, requiring
monitoring system with
sophisticated, modern
targets.
- Difficult maintenance
because there are many
modern control facilities.
- Possibility of output
wastewater sweeping
sedimentation, floating
scum in discharging
stage.
- Air blowing system
easy to be choked with
sludge because of no
withdrawal of sludge.
- If the works behind
bear low load shock,
there must be an
auxiliary detention tank.
- Do not bear waste with
high content of solid
substances.
- Complex construction
works, requiring high
technology.
- The highest initial
investment costs in 03
options.
- Higher management and
operation costs than 02
other options
- More complicated
management and operation.
- Compliance with the
treatment plant of large
capacity.
- Very large land
occupation area.
- Possibility of
causing bad odor,
(especially in
summer)
Waste water treatment technology based on biological ponds operates in line with
principle of settling and decomposing sediments by the natural aeration process which is
based on survival and activities of anaerobic micro-organism. This technology is suitable with
areas far from the residential areas having large land area and extremely suitable for the
available land funds in Thai Hoa town, especially two selected proper positions including
Long Son ward and Nghia Tien commune.
3.2.5. Assessment of wastewater receiving ability of Hieu river:
Pursuant to Circular No. 02/2009/TT-BTNMT stipulating the ability to receive
wastewater of the water source – chapter II. Procedures, method of assessment for wastewater
Drainage and wastewater treatment system project for Thai Hoa town, Nghe An province”
Environmental Impact Assessment (EIA) PCO Consultant, 2010
81
receiving ability of water source, applied for Hieu river surface water source. This assessment
is considered and calculated the processes occuring in the flow such as the intergration of
substances into the flow and the conveyance and the change of those subtances.
The conservation of mass is applied (enclosed with Circular No. 02/2009/TT-BTNMT
dated 19/3/2009 of Ministry of Natural Resources and Environment) to calculate the load
carrying capacity of Hieu river with the effluent water quality of 2 treatment plants meeting
class B, QCVN 14:2008/BTNMT, and the calculation parameters are as follows:
Parameters for assessement of quality as required and surveying parameters as follows:
No. Typical
pollution
paramete
r
Unit Treated
water
quality of
the
treatment
plant
Treated water
quality meets
standard
QCVN
14:2008/BTN
MT, class B.
Quality of
Hieu river
surface water
(Taking
average value
at 4 locations:
NM1, NM2,
NM3, NM4)
Surface
water
quality as
required in
standard
QCVN
08:2008/B
TNMT,
class B1
1 BOD5 mg/l 23.64 50.00 13.00 15
2 COD mg/l 35.25 80.00 29.38 30
3 TSS mg/l 88.00 100.00 48.03 50
4 NH4+ mg/l 0.61 10.00 0.44 0.5
5 NO3- mg/l 10.40 50.00 11.00 0.04
6 NO2- mg/l 0.06 0.04 0.02 10
7 Pb mg/l 0.06 0.05 0.04 0.05
8 Zn mg/l 1.60 1.50 1.07 1.5
9 Oil and
grease mg/l 0.21 20.00 0.12 0.10
10 Coliform MPN/l 3757 5000 3758 7500
(According to surveying results of background environment, QCVN 08:2008/BTNMT and
QCVN 14:2008/BTNMT)
Indicator Content Calculation value
Ltđ
(kg/day)
Maximum pollutant bearing ability of water source to
the pollutant being considered.
In the table
Qs (m3/s) Minimum instant flow at the river section required for
assessment before receiving wastewater, (m3/s), is
determined according to guidelines at point 3.1, annex 3
of this Circular.
13 m3/s (this is
smallest instant flow
of Hieu river in dry
season, according to
data provided by the
North-Middle
Hydrometeorology
Center).
Qt (m3/s) Maximum wastewater flow determined according to
guideline at pont 3.2 of annex 3 of this Circular.
6000 m3/s
(= 2000 + 4000)
m3/s, equivalent to 2
wastewater treatment
Drainage and wastewater treatment system project for Thai Hoa town, Nghe An province”
Environmental Impact Assessment (EIA) PCO Consultant, 2010
82
plants.
Ctc (mg/l) Concentration limit value of the pollutant considered as
stipulated in the standard, code of water quality to
ensure the use purpose of the water source being
assessed, according to guideline at point 3.2, annex 3 of
this Circular.
In the table of
assessment criteria
according to
standard. QCVN
08:2008/BTNMT,
column B1
Cs
(mg/l)
Maximum concentration value of the pollutant in water
source before receiving wastewater which is determined
according to guideline at point 3.1, annex 3.
Criteria of quality of
Hieu river surface
water.
Ct (mg/l)
Maximum concentration value of pollutant in
wastewater which is determined according to guideline
at point 3.2 of annex 3.
In the table of
criteria of quality of
the effluent water
quality, QCVN
14:2008/BTNMT,
column B
86,4 The conversion factor of dimensional unit from (m3/s)*(mg/l) to (kg/day)
Fs Suppose to select safety factor is 0,4 (smallest value).
Applying fomulars to calculate maximum amount of pollutants that Hieu river water
source can receive with some typical pollutants, the results are as follows:
1. Maximum amount of pollutants that can be received by water source with some
specific pollutants calculated according to fomular: (i):
Ltđ = (Qs + Qt) * Ctc * 86,4
Parame
ter BOD5 COD TSS
Amo
ni NO2 NO3- Pb Zn
Oil,
grease
Colif
orm
(Qs + Qt) m
3/s
13.07
13.07
13.07
13.07
13.07
13.07
13.07
13.
07 13.07 13.07
Ctc(mg/l
)
15.00
30.00
50.00
0.50
0.04
10.00
0.05 1.5 0.1 7500
Ltđ (kg/day)
16938.
0
33876.
0
56460
.0
564.6
0
45.17
11292
.0
56.46
169
3.8 112.92
8469
000
2. Amount of pollutants available in the receiving source with some specific pollutants
calculated as follows:
Ln = Qs * Cs * 86,4
Results:
Parame
ter BOD5 COD TSS
Amo
ni
NO
2- NO3- Pb
Zn Oil,
grea
se
Colifor
m
Qs
m3/s 13.00 13.00 13.00 13.00
13.0
0 13.00
13.
00 13.00
13.0
0 13.00
Cs mg/l 13.00 29.38 48.03 0.44 0.02
9.80
0.0
4 1.07
0.08
3,757.5
0
Drainage and wastewater treatment system project for Thai Hoa town, Nghe An province”
Environmental Impact Assessment (EIA) PCO Consultant, 2010
83
Ln
kg/day
14,601
.60
32,994.
00
53,941.
68
490.0
0
21.0
6
11,007.
36
42.
12
1,204.
63
89.8
6
4,220,4
24
3. Amount of pollution of some pollutants from discharge source entering the receiving
source is calculated according to fomular:
Lt = Qt* Ct* 86,4
Results:
Param
eter
BOD5 COD TSS Amo
ni
NO2- NO3- Pb Zn Oil,
gre
ase
Colif
orm
Qt
m3/s 0.07 0.07 0.07 0.07 0.07 0.07 0.07
0.
07
0.0
7 0.07
Ct
mg/l
23.64
35.25
88.00
0.61
0.06
10.40
0.06
1.
60
0.2
1
3757.
50
Lt
kg/da
y
141.84
211.50
528.00
3.66
0.36
62.40
0.38
9.
60
1.2
4
2254
5
4. Ability of water source to receive amount of pollution of a specific pollutant from one
discharge point is calculated according to fomular:
Ltn = (Ltđ – Ln – Lt) * Fs
Results:
Para
meter
BOD5 COD TSS Amo
ni
NO2
-
NO3- Pb Zn Oil,
grea
se
Colifo
rm
Ltd -
Ln-Lt
2,194.
56
670.5
0
1,990.
32
70.9
4
23.7
5
222.2
4
13.97
479.57
21.8
3
4,226,
031
Ltn
877.82
268.2
0
796.1
3
28.3
8
9.50
88.90
5.59
191.83
8.73
1,690,
412
Conclusion: Therefore, the water source may receive parameters such as BOD5,
COD, TSS, Amoni, NO2-, Pb, Zn, Coliform, NO3- and oil, grease.
Assessment results of wastewater receiving ability of Hieu river water source are
applied for minimum instant flow of Hieu river. However, variation amplitude of the instant
flow in Hieu river is rather high compared to the highest flow in flooding season of 5810m3/s,
the wastewater receiving ability of Hieu river will be much bigger.
In addition, the Project Owner cooperated with consulting unit to survey thoroughly
environmental sensitive activities at the downstream of Hieu river to make a general
assessment before selecting the treatment technology using series of biological ponds:
3.2.6. Assessment of wastewater mixing ability meeting domestic water standard..
a. Hieu river.
Drainage and wastewater treatment system project for Thai Hoa town, Nghe An province”
Environmental Impact Assessment (EIA) PCO Consultant, 2010
84
Hieu is a biggest river running through the project area with total length of
approximately 220km. It is a branch of Lam river and originated from mountainous area of
Que Phong district, flowing in South-East direction passing through Quy Chau, Quy Hop,
Nghia Dan and to Thai Hoa town where it flows in South-West direction passing through Tan
Ky, Anh Son and unified with Lam river in Dinh Son and Anh Son commune.
Hieu river running through Thai Hoa town is 7.4 km long. Hydrological data of Hieu
river in Thai Hoa town are:
+ Highest flow in flood season: 5810m3/s.
+ Low in dry season: 13m3/s
+ Flow velocity in dry season: 0,4 m/s
+ Highest water level is +47,5m (with P=5%) and 47m (frequency: 10%)
+ Lowest water level: +36,0m
+ Anually average water level in flood season ranges from +39,0m to 42,0m
(according to actual survey).
+ Average water level of Hieu river: 3,9m
+ Total annually average flow 3,7 billion m3.
b. Self-cleaning ability of the river.
Wastewater after treatment is discharged into river, so it is necessary to consider the self-
cleaning ability of the river.
a) Mixing and diluting
- Fomular:
According to study results of V.A. Frolop and I.Đ.Rodzinler, the mixing factor ‘a’ is
determined by fomular:
a = 3
3
.
.
.1
1
Le
Le
eq
Q
e
α
α
−
−
+
−
Where :
Q – Flow of river water (m3/s) .
q - Maximum wastewater flow (m3/s)
Le- = 20.000 m: distance from discharge sewer to the point ensuring water quality
meeting standard of column A calculated for river lane (m)
Lt = 15.000 m distance from discharge sewer to the calculated point for straight line.
(m).
α - Coefficient counting to hydraulic factors of the mixing process and calculated by
fomular:
α = ϕ x ξ x 3
q
E
ϕ : tortous coefficient of river that can be calculated by: ϕ = t
e
L
L=
16500
20000=1,21
Drainage and wastewater treatment system project for Thai Hoa town, Nghe An province”
Environmental Impact Assessment (EIA) PCO Consultant, 2010
85
ξ Coefficient depending on location of the discharge sewer location
Discharge sewer is located along the bank: ξ = 1.
E: Diffusion coefficient in the flow. For the plain area, it is calculated by fomular:
E = 0078,0200
9,34,0
200
.=
×=tbtb HV
Vtb , Htb : Average speed and depth of the flow at the calculated river section. (m/s) ; (m).
α = ϕ x ξ x 3
q
E= 624,0
07,0
0078,0121,1 3 =××
a = 1
07,0
131
1
.1
1
3
3
3
3
20000624,0
2000006242
.
.
=
×+
−=
+
−
−
−
−
−
e
e
eq
Q
e
Le
Le
α
α
Conclusion: At the location about Le = 20.000 m far from the discharge outlet (by river lane)
the mixing coefficient
a =1.
- Diluting frequency at calculated point:
n = 71,18607,0
07,01.13).(=
+=
+
q
qQa times.
Calculation of diluting frequency:
n = nggh
ng
CC
CC
q
qQa
−
−=
+ ).(
Where :
C – Content of contamination substances in wastewater (mg/l) .
Cng - Content of contamination substances in water source (mg/l) .
Cgh – Limit content of contaminants of the mixture of wastewater and water source after
mixing. (mg/l) .
With : Le- = 20.000 m: the distance from wasewater discharge sewer to the point ensuring
water quality meeting standard column A calculated by river lane. (m):
�Q
qnxq −=α
Parameters
BOD5 COD TSS NH4+ NO3- NO2- Pb Zn Dầu mỡ
Q
qnxq −=α 0.02 0.05 0.10 0.01 0.01 0.01 0.01 0.001 0.03
a) Indicators after mixing with Hieu river water.
Content of contaminants after mixing:
Kth = α xbxKsauxl
Drainage and wastewater treatment system project for Thai Hoa town, Nghe An province”
Environmental Impact Assessment (EIA) PCO Consultant, 2010
86
α: Mixing coefficient
Kth : Criteria after mixing
Ksauxl: Criteria after treatment.
b: Allowable increase in content of sediments b=1,5-2,5; select b =2,5 according to
TCVN 7957:2008
No. Typical
pollution
paramete
rs
Unit Treated
water
quality
Surface
water
quality
of Hieu
river
Surface
water
quality
according to
QCVN
08:2008/BT
NMT, Class
B1
Surface
water
quality
according
to QCVN
08:2008/BT
NMT, A2
Mixin
g
coeffi
cient
Surfac
e
water
quality
after
mixin
g
Remark
1 BOD5 mg/l 23.64 13.00 15 6 0.02 1.37 Satisfy A
2 COD mg/l 35.25 29.38 30 15 0.05 3.99 Satisfy A
3 TSS mg/l 88.00 48.03 50 30 0.10 22.79 Satisfy A
4 NH4+ mg/l 0.61 0.44 0.5 0.2 0.01 0.01 Satisfy A
5 NO3- mg/l 10.40 9.80 10 5 0.01 0.28 Satisfy A
6 NO2- mg/l 0.06 0.02 0.04 0.02 0.01 0.001 Satisfy A
7 Pb mg/l 0.06 0.04 0.05 0.02 0.01 0.001 Satisfy A
8 Zn mg/l 1.60 1.07 1.5 1 0.001 0.005 Satisfy A
9
Oil,
grease mg/l 0.21 0.08 0.1 0.02 0.03 0.015
Satisfy A
10 Coliform MPN/l 3,757 3757 7500 5000 3758 Satisfy A
c. Conclusion.
According to available data, about 20km far from the treatment plant heading towards
the downstream, there is no intake structure to serve daily activities. Therefore, wastewater of
2 treatment plants, after being mixed with water river at the distance of 20km from the
treatment plant ensures water quality for daily activities.
Therefore, this proposal is suitable for all kinds of seasonally changed waste water,
compatible with the local conditions, ensuring qualified waste water treatment in line with
Codes type B as stipulated by Vietnam Codes – QCVN 14:2009/BTNMT, meeting
wastewater receiving ability of Hieu river water source at the downstream and suitable with
requirements of WB.
3.2.7. Assessment of sludge treatment techonology and discharge location:
In order to treat sludge generated after a long time of settling in ponds, a sludge drying
bed is recommended to treat sludge before transporting to landfill. Following is the diagram
of sludge treatment process:
Pump sludge from
treatment ponds
Sludge drying
bed
Burred in landfill
Drainage and wastewater treatment system project for Thai Hoa town, Nghe An province”
Environmental Impact Assessment (EIA) PCO Consultant, 2010
87
Being selected for the “Water drainage and waste water treatment project for Thai
Hoa town, Nghe An province”, the Bio-treatment technology is a widely used in the world to
treat waste water in general and domestic water in particular. High performance is achieved
by the technology, so, it is very suitable with requirements and funds of the Sponsor.
The proposed ludge treatment area is the landfill of Thai Hoa town with an area of
10ha, located on the hill areas of Nghia My commune. This is the landfill under the detailed
planning of Thai Hoa town. Currently, the landfill is far from residential area, about 1-2 km
from the nearest residential area.
3.2.8. Compensation and Site Clearance:
Natural environment impacts of land reclaims, compensation and site clearance are
insignificant. However, in this phase, there are some impacts on the local socio-economic
conditions such as:
- Crop land (sugar canes) of 68 households in Long Son is reclaimed to
construct the Waste Water Treatment Plant No. 1 and land of 69 households in
Nghia Tien is reclaimed to construct the Waste Water Treatment Plant No. 2.
- The project performance will change land use purpose; taking out of a part of
means of production and agricultural production of households are affected.
- It changes the local economic structure, improves living standards and
constructs infrastructure to meet the local demand of development.
For the project preparation, the project’s environment impact assessment is conducted
along with the preparation, however, the consultancy group makes an resettlement plan for the
project to compensate/ indemnify, apply production support policies, generate jobs and
suitable vocational training course, etc for affected households whose land is reclaimed as
stipulated by Vietnamese laws, current compensation price schedule of Nghe An province and
Safety Policy on resettlement, Policy framework of World Bank applied for the project to
minimize impacts on living standards of local people in the project area.
3.3. ENVIRONMENT IMPACT ASSESSMENT IN CLEARANCE PHASE
The environment impacts on the clearance phase is shown in table below:
Table 3: Impacts in clearance phase
Impact
subjects
Impacted
objectives Impacts Scopes Level
Clearance for
constructing
the WWTP
Air
Dust, noise
caused by the
clearance
WWTP area Small and
shor-term and
reduceable
Water
Suspended solid
waste
Surface water
from Tam ky
and Ban Thach
rivers
Small and
shor-term and
reduceable
Soil Workers’domest
ic solid waste
Clearanced trees
WWTP area Small and
shor-term and
reduceable
Drainage and wastewater treatment system project for Thai Hoa town, Nghe An province”
Environmental Impact Assessment (EIA) PCO Consultant, 2010
88
Ecosystem Ecosystem and
landscape is
changed by the
appearance of
the project
works
WWTP area Small and
long-term and
reduceable
Socio-economy Locals’ living Households
around WWTP
Short and not
eligible
3.3.1. Impacts on atmosphere
- Regarding site preparation for constructing rain water and waste water
drainage sewers as well as connecting with households, backfilling phase and
site preparation do not lay significant impacts on the natural and social
environment components because all sewers are along with traffic roads, field
banks in hamlets/ street teams, etc. Entire land area is public and available with
roads. Therefore, backfilling and site preparation are not required.
- Regarding construction site preparation for constructing waste water pumping
stations, there is no impact on environment and life of households because
such stations are underground on pavements in the center of traffic roads and
discharging points. Therefore, backfilling is also not required.
- However, for site preparation for constructing Waste Water Treatment Plants
in Long Son ward (12.7 ha) and Nghia Tien commune (9.1 ha), due to uneven
terrain and disqualified foundation reinforcement, a relatively large soil
volume is used. However, because the selected treatment technology is large
sized biolakes: using anaerobic, aerobic and amphoteric lakes, backfilling is
limited for entire treatment area. Dug soil volume from lakes can be used as
soil for backfilling for remaining areas in each treatment plant.
In general, activities in the project’s backfilling include cutting down, clearance,
collection of vegetation mass in the surface; backfilling, embankment, digging, rolling of the
surface will create pollution sources for the air such as dust and emission, specifically:
- Dust generated during material transportation for backfilling.
- Emission of means of transportation traveling in the Project area. Material
combustion process will discharge a relatively large volume of emission
containing the air pollutant such as: dust, CO, CO2, SO2, NOx, hydrocarbon,
etc.
a. Dust due to material transportation for backfilling:
Based on the project’s engineering design on backfilling, embankment and digging
area for the 2 Waste Water Treatment Plants based on the natural area and height, grading
height is used to calculate volume of earthworks as follows:
- Volume of grading sand is app.: 43,218 m3
- Volume of earthworks, collecting vegetables for clearance is about:
1,400 m3
Drainage and wastewater treatment system project for Thai Hoa town, Nghe An province”
Environmental Impact Assessment (EIA) PCO Consultant, 2010
89
- So, total volume of materials to be transported in this phase is approximately:
44,618 tons.
- Number of vehicles need to transport the aforesaid volume equivalent to 2,974
turns of vehicle (15 ton diesel trucks are used). This volume is concentrated
transported within 45 days. Therefore, traffic of trucks traveling in the project
area in this phase is 66 vehicles/day.
Table 15: Number of trucks grading site at the WWTPs’ location
Volume to be transported
(ton)
Total
(turns of truck)
Duration
(days)
Traffic
(truck/day)
44,618 2.974 45 66
During transportation, these trucks create a relatively large volume of dust including
dust from pavement, materials scattering and material combustion process. According to
quick assessment method of WHO, it is possible to forecast dust volume generated during
transporting the grading materials with assumptions as follows:
- Average speed 35 km/h
- Average capacity 15 tons
- Average number of wheels 6 pcs/truck
- Average road length 5 km
With above assumptions, when applying the quick assessment method of WHO-
Assessment of sources polluting land, water, air - Volume 1 - Generva 1993, the generated
dust volume of a turn of truck is 511 (kg/1000km), corresponding to average daily generated
load is 198 kg/day and 29 kg/h. The calculation results revealed that dust volume generated
during backfilling is relatively high.
Dust in the air will obstruct vision, affect health of workers and local people in the
Project’s area. Dust also affects fauna and flora. Dust covering leaf’s surface reduces
photosynthesis, affecting growth of plant.
However, this dust is not concentrated in a certain area. It is scattered as per distance
and wind direction as at calculation moment against the discharging sources, dust
concentration in the area will be reduced due to scattering in the area and application of
mitigation measures such as spraying water, covering, etc, conducted by the Employer.
Therefore, dust impacts on environment will be minimized within the allowable limit.
b. Emission gas:
Trucks transporting the grading materials into the Project’s area are operated with
petroleum and diesel. During operation, fuel is burnt, resulting in exhaust emission containing
air pollutants such as dust, CO, CO2, SO2, NOx, hydrocarbon, etc.
Emission levels of pollutants depend on various factors such as air temperature,
velocity of truck, transportation road length, kinds of fuel, pollution control measures.
According to WHO, method of forecasting pollutant load for diesel-operated trucks is as
follows:
Drainage and wastewater treatment system project for Thai Hoa town, Nghe An province”
Environmental Impact Assessment (EIA) PCO Consultant, 2010
90
Table 19: Gas emission factor due to one vehicle.
Criteria Factor
(kg/1000km)
Road length
(km)
Duration
(minutes)
Number of
vehicle
(in/out)
Emission load
(g/min.)
Dust 0,9 5 10 1 0,4500
SO2 4,15*S 5 10 1 0,0103
NOX 14,4 5 10 1 7,2000
CO 2,9 5 10 1 1,4500
HC 0,8 5 10 1 0,4000
S: Sulfur concentration in diesel, S = 0,5%
Source WHO: Evaluating soil, water and air pollution sources – Volume I, Generva, 1993.
Table 20: Dust and exhaust emission load corresponding with number of trucks.
Number
of trucks
Dust
(g/min.)
SO2
(g/min.)
NOX
(g/min.)
CO
(g/min.)
HC
(g/min.)
66 22,5000 0,5125 360,0000 72,5000 20,0000
In general, the emission generated in this phase is insignificant and non-continuous.
Moreover, because the Project’s area is large, dust and exhaust emission will be diluted and
quickly scattered in the air.
3.3.2. Water pollution sources
This phase has insignificant impacts on water environment. Mostly, physical impacts
are available such as increase in suspended solid content in water environment, some
substances due to land washout as rainwater overflows, etc. However, in general, the
remarkable impacts are unavailable. Only soil and sand are washed out resulting increase in
impurity and suspended solid, etc. It is only characterized by physical properties not water
amination impact. Other pollutants are hardly found and therefore, there is no impact on water
environment. The aforesaid impacts are insignificant, causing negligible effects.
Q = (10 persons x 45 l/person/dayx45)/100 = 202,5 (l/day)= 0,2 (m3/day).
In addition, the backfilling period is impacted by a small amount of domestic
wastewater of workers. Water amount expected to be used for activities of workers at site is
about 45l/person/day. Wastewater amount generated is equal to 80% of supplied water
amount. With the expected number of workers for the backfilling work is 10 persons within
45 days, domestic wastewater flow is calculated as follows:
3.3.3. Impacts on soil environment
Site preparation for construction has some certain impacts on soil environment,
specifically as follows:
Drainage and wastewater treatment system project for Thai Hoa town, Nghe An province”
Environmental Impact Assessment (EIA) PCO Consultant, 2010
91
- Regarding areas used for constructing pipelines, sewers, manholes and
treatment plants, vegetable matter is removed, creating smooth surface for
construction. Therefore land surface is changed.
- Pedological terrain’s mechanical, physical and chemical properties are
changed in a short time due to a volume of soil and stone will be transported to
create a reinforce foundation as designed.
Generally, impacts due to backfilling and site clearance only change land surface but
these impacts are only the soil surface layer. Therefore, there is no remarkable impacts on soil
environment quality.
3.3.4. Solid waste impacts
* Solid waste generated during clearing the surface
Solid waste impacts in this phase are mainly plant, weed and other materials (wastes,
bladders, plastics, etc) in the site clearance area. These solid wastes are easily treated by waste
collection of rubbish collectors and transportation to recycle facilities. Organic solid waste
such as plants, weed, and so on are burnt or collected into piles for farmers to use in their
agricultural production.
* Domestic solid waste of workers in temporary camps
Solid waste of workers is a remarkable impact source. Discharging volume is assessed
in accordance with quick assessment method of WHO, solid waste volume discharged every
day is 0.5 kg and corresponding to solid waste discharge load of the entire construction phase
is 225 kg (for 10 workers in 45 days of backfilling)
Solid waste volume is not great but if it is discharged randomly, it will be a risk on
polluting the domestic water sources of workers in camps, surface water sources, resulting in
a series of digestion epidemics for human being, cattle and domestic animal.
3.3.5. Impacts on lanscape
Site preparation for constructing sewers, pumping stations and manholes do not waste
time. It can be conducted quickly. Construction positions are relatively convenient without
barriers for this work. Therefore, there is insignificant impacts on fauna and flora life when
prepare the site for such items. Thanks to small occupied land area and short construction
time, it only changes at the moment of construction. Post-construction situation will be
quickly recovered.
Landscape is changed in the treatment plant area during grading to prepare the Site.
The ecosystem is changed and replaced by another one. Previously, permanent reclaimed
areas are agricultural production land such as crops (sugar canes), short term vegetables, etc.
Therefore when backfilling, it will be destroyed and replaced by soil foundation filled with
black sand.
The Site preparation cause coat loss, facilitating surface washout, affecting Hieu River
quality as well as living conditions of aquatic living creatures in the subaqueous ecosystems.
Besides, the construction site is not located in the preserve area, historical relics,
cultural tourism areas, etc. Accordingly, impacts of this phase are local and available in a
short time. Therefore impacts on landscape in the backfilling is regarded as insignificant.
Drainage and wastewater treatment system project for Thai Hoa town, Nghe An province”
Environmental Impact Assessment (EIA) PCO Consultant, 2010
92
3.3.6. Impacts on the socio-economic life
It seems that there are no adverse impacts on the socio-economic lives when site
clearance is conducted, only positive impacts are available:
- The positive impacts are obtained from reclaiming the agricultural land of
households in the site of constructing the treatment plants. There is no
buildings affected. Therefore, from this land reclaim, they will get an amount
of money for their current life in the current period.
- Significant impacts due to site clearance can be counted on including some
households can trade and render some services for the Project’s performance,
etc.
- However, this process is implied with adverse impacts due to agricultural land
reclaim. Some local residents when receiving the compensation, if it is spent
for the bad purposes, will be self- indulged due to unhealthy awareness and
actions such as indulgence, not working, etc, increasing the social evils in the
area.
- Traffic density increase in the Project area: During construction, transportation
of raw materials, plants and equipments cause increase in the local traffic
density. Moreover, the Project is situated near the center of Thai Hoa town, so
the traffic density is much more high.
3.4. ENVIRONMENT IMPACT ASSESSMENT IN CONSTRUCTION PHASE
The environment impacts in the construction phase is described in the table as follows:
Table 32: General environment impact assessment during the Project’s
performance
Operation Soil Water Air Biological
resource
Socio-
economi
cs
To construct separated drainage
and wastewater sewer systems. ++ ++ + + ++
To construct waste water pumping
stations and discharging outlets ++ + + + +
To construct 02 waste water
treatment plants: the plant No. 1 is
located in Long Son ward
whereas, the plant No. 2 is in
Nghia Tien commune.
+++ + ++ + ++
To transport raw materials and
equipment for the Project’s
performance.
+ + +++ + +
To reserve and store raw materials
for construction. + + ++ + +
Daily activities of workers at Site + ++ ++ + +
Notes:
+ : Less adverse impacts;
++ : Adverse impacts at average level;
+++: Adverse impacts at strong level.
Drainage and wastewater treatment system project for Thai Hoa town, Nghe An province”
Environmental Impact Assessment (EIA) PCO Consultant, 2010
93
Table 3.6. The main impacted areas in the construction period:
Work items The main impacted areas: Distance to the nearest area
(m)
Stormwater,
wastewater
collection
pipelines,
manholes,
discharge
outlets along
the line.
- Construction of RC round sewer D1000
along national road 48 from national
road 48 to Hieu bridge and Nghia Dan
station and from Nghia Dan station to
Hieu bridge with total length of 5,655m.
About 10 – 20 m (households
living near the pavements of
the road route).
- Construction of RC round sewer D800
along road routes in the town such as
national road 15A, the area near Bau Sen
lake, national road 48 and Quang Phong
ward with total length of 4,455m.
About 10 – 20 m (households
living near the pavements of
the road route).
- RC round sewer D400 - L10,202m;
D600 - L14,009m along road in
residential areas of wards/communes in
Thai Hoa town with total length of
22734m.
About 10 – 20 m (households
living near the pavements of
the road route).
Wastewater
pumping station
- PS1: On pavement near Quang Phong
primary school – Quang Phong ward.
About 20m
- PS 2: At the intersection of road 15 to
To stream and alley 16.
About 30m
- PS 3: On pavement, near the
intersection of national road 48, near
Thai Hoa town People’s Committee.
About 20m
-PS 4: At the intersection of new road
heading towards newly planned Hieu
bridge.
About 30m
- PS 5: At the intersection of national
road 48 and road accessing to cultural
house in Thi Nghiem village.
About 30m
- PS 6: At the national road 15A between
Quang Tien ward and Nghia Tien
commune (near Rubber Company)
About 30m
TwoWastewater
Treatment
Plants
- WWTP 1: At the rice field of blocks 4,
5, 6 in Long Son ward (near Giong area).
The area used for the plant is 12.7ha.
About 1000m far from the
existing residential area, 600m
from the planned residential
area.
- WWTP 2: The plant is constructed in
the rice field in village 1, Nghia Tien
commune. The area for the plant is 9.1
ha.
About 500m
House
connection
points
Construct 6089 connection points for
registered households.
0m (at the gate of household)
In this phase, activities are conducted such as earthworks along roads to construct and
install the rain water and waste water sewer systems, waste treatment biolakes; installing
Drainage and wastewater treatment system project for Thai Hoa town, Nghe An province”
Environmental Impact Assessment (EIA) PCO Consultant, 2010
94
treatment equipments, etc. These activities are the great impact source to the natural
environment components such as air, solid, water, etc., because waste and pollutants are born. It
is summarized as follows:
Table 21: Pollutant sources during construction
Waste sources Wastes Affected factors
To transport
construction
materials
- Dust along roads, soil and
sand scattered
- Exhaust emission of trucks:
Dust, CO, SO2, NO2
- The atmosphere
- Safety and health of worker
To dig and embank
sewers and
biological ponds
- Solid waste:
- Dust, exhaust emission
- The atmosphere
- The soil environment
- Safety and health of worker
To construct and
install
- Dust, CO, SO2, NO2
- Noise, vibration
- Building waste
- The soil environment
- The water environment
- Safety and health of worker
Other activities such
as vehicle operation,
construction
machines
- Noise, vibration, CO, SO2,
NO2, HC - The atmosphere
Domestic activities
of workers
- Domestic waste water
- Domestic waste
- The soil environment
- The water environment
3.4.1. Impacts on the atmosphere
a) Dust generation
According to Basic Design of the project, raw material volume used to construct and
volume of waste soil and stone from constructing sewer system, pumping stations, Waste
Water Treatment Plants for the Project is relatively huge, approximately 16,404 tons. Number
of trucks needed to transport the above volume is about 1094 turns of truck (15 ton load
diesel-operated trucks) during construction in nearly 2 years (600 days). Then, the average
truck traffic will be 2 trucks/day. Like the dust volume forecast method while backfilling as
stated by WHO, the average generated load will be 21.1 kg/days with 01 turn of truck/ day
and 42.2 kg/day for 02 turns of truck/day.
Table 23: Forecast of dust load generated during transportation
Sources
Number
of truck
turns
Dust arising factor
(asphalt road,
1000km)
Dust arising
volume
(kg/1000km.
Turns of
truck)
Average dust
arising
volume
(kg/day)
To transport raw 1 3,7× f 2111,588 21,1
Drainage and wastewater treatment system project for Thai Hoa town, Nghe An province”
Environmental Impact Assessment (EIA) PCO Consultant, 2010
95
materials 2 3,7× f 2111,588 42,2
Source WHO: Evaluating soil, water and air pollution sources - Volume, Generva, 1993.
Notes:
f: factor of arising the secondary dust when truck operates in roads as per formula:
f = v.M0,7
.n0,5
Where:
- v : Average velocity of truck (km/h).
- M : Average load of truck (ton).
- n : Number of average wheels.
Dust impacts:
- Dust is generated during transporting, loading and unloading the raw materials. Dust
scattering level in this phase varies remarkably. The pollution level depends on the truck
velocity, construction intensity, temperature, wind direction and speed in the area, the soil
humidity and air temperature in a day.
Generated dust will impact directly on environment and living conditions of
residential areas in construction area of the project as mentioned in table 3.6. The
transportation of excavation soil, rock for backfilling and excavation of sewer lines will
generate a largest amount of dust. However, through the surveying of existing coditions and
based on the detailed construction planning of Thai Hoa town, the main road routes planned
for transportation are national road 48, national road 15A and provincial road 545. Therefore,
the whole residents living along those routes will be affected directly by amount of dust
generated from soil, rock and transportation vehicles. The other residential areas along roads
in the town are places for gathering soil, rock, construction materials so the impact level may
be lower, and the construction duration is short, so the impacts are only on local scale and will
disapear when the construction is completed.
- Dust affects human being and animal mainly through respiratory system such as
pneumonia, asthma and tuberculosis. Dust reduces photosynthesis ability and growth of plant.
Dust generated in this process is usually large sized without widespread ability. Most of dust
will be scattered not far from the Site.
In general, in this phase the roads have been ballasted. Material components are less
dust. Therefore, its effect coverage is within the narrower space compared with that in the
backfilling phase. Canvas and watering will be applied to humidify the transportation roads to
effectively avoid dust scattering and limiting its impacts on environment.
b) Generated emission gas:
Means of transportation are mainly petroleum and diesel operated types. During
operation, the fuel burning will release a relatively high emission containing air pollutants
such as flue gas, CO, CO2, SO2, NOx, hydrocarbon, etc.
Emission levels of pollutants depend on various factors such as air temperature,
velocity of truck, transportation road length, kinds of fuel, pollution control measures.
According to WHO, method of forecasting pollutant load for diesel-operated trucks is as
follows:
Drainage and wastewater treatment system project for Thai Hoa town, Nghe An province”
Environmental Impact Assessment (EIA) PCO Consultant, 2010
96
Table 25: Exhaust emission volume and dust corresponding to number of trucks.
Number of
trucks
Dust
(g/min.) SO2
(g/min.) NOX
(g/min.) CO
(g/min.) HC
(g/min.)
1 0,5625 0,0128 9,0000 1,8125 0,5000
2 1,1250 0,0256 18,0000 3,6250 1,0000
Emission impacts:
Emission components include CO, SO2, NOx, HC. These are highly toxic for human
being and animal. The U.S. Environmental Protection Agency (USEPA) concluded that
emission from diesel-operated vehicles can cause cancer for people.
However, pollution of such gases depends on distance, time and space between
emission sources. When emission sources are concentrated in a place and simultaneously
emitted, its atmosphere pollution possibility is very high. To limit the pollution level, the
Employer will arrange vehicles and trucks as per proper time and space to minimize such
impacts on environment and people.
c) Impacts of noise and vibration
Noise and vibration also affect the atmosphere during constructing rain water and
wastewater drainage systems, waste water pumping station, Waste Water Treatment Plant and
connection system, noise and vibration caused by using pile driver, means of transportation,
construction machine (excavator, cranes, borer, concrete mixer, etc).
Vibration from the construction machines also affect land environment in the site and
propagating effects on roads near the Site. However, such vibration is insignificant.
Table. Areas may be affected by nosie during construction phase
Work items Affected locations Causes
Construction of
the drainage
sewer: D1000,
D800, D600
- Along national road 48 from national road 48
to Hieu bridge and Nghia Dan station and from
Nghia Dan station to Hieu bridge with total
length of 5,655m.
- Along road routes in the town such as
national road 15A, the area near Bau Sen lake,
national road 48 and Quang Phong ward with
total length of 4,455m.
- Along road in residential areas of
wards/communes in Thai Hoa town with total
length of 22734m.
Noise from operation
of construction
machinery such as
drilling, concrete
cutting machine,
transport trucks, from
the traffic vehicles on
the route.
Construction of
the wastewater
pumping station
(WWPS).
Location of 6 WWPS as at the table 3.7 above. Noise from operation
of construction
machinery such as
drilling, concrete
cutting machine,
transport trucks, from
the traffic vehicles on
Drainage and wastewater treatment system project for Thai Hoa town, Nghe An province”
Environmental Impact Assessment (EIA) PCO Consultant, 2010
97
the route.
Construction of
the two WWTPs
- WWTP 1: At the rice field of blocks 4, 5, 6 in
Long Son ward (near Giong area).
- WWTP 2: The plant is constructed in the rice
field in village 1, Nghia Tien commune.
Noise from
construction
machinery: bulldozers,
excavators, transport
vehicles, ...
According to formula calculating propagability of noise from construction machines to
neighboring area, the noise calculation results in the ambient air at distance of 100m, 200m
and 500m from the noise source are demonstrated in the table as follows:
Table 28: Maximum noise from operation of means of transportation and
mechanical construction machines
No. Equipment At source 100m 200m 500m
1 Truck 90 72 68 60
2 Borer 87 69 65 57
3 Motorized concrete 85 67 63 55
4 Concrete pump 83 66 62 55
5 Manual saw 82 64 60 52
6 Diesel operated mixer 80 62 58 50
7 Crane 82 68 64 58
8 Generator 82 68 64 58
TCVN 5949-1998: Acoustics - - 75 dBA (6-18h)
(*): Standard noise for each equipment (Source: Mackernize, L.da, 1985)
* Noise impacts
Noise higher than allowable limit will affect labor health and cause somnipathy,
fatigue, uncomfortable psychology. High noise level also reduce the productivity, labor health
in the production area. Long time exposure to the highly intensive noise will reduce the
hearing, resulting in the professional deaf.
According to the statistics released by Ministry of Health and Institute for Technical
and Scientific Research on Labour Protection under Vietnam General Confederation of
Labour, noise lays adverse impacts on most of human body organs. Noise impacts on human
body at different frequency range are described in Table 29.
Table 29: Adverse impacts on highly intensive noise for human health.
Drainage and wastewater treatment system project for Thai Hoa town, Nghe An province”
Environmental Impact Assessment (EIA) PCO Consultant, 2010
98
Noise level (dBA) Impacts on listeners
0 Threshold of audibility
100 Starting to change heart beats
110 Soaking the tympanic membrane
120 Threshold of pain
130 ÷ 135 Causing neuropathy, nausea, weakening thigmesthesia and muscles
140 Causing pain, psychopath and maddest
145 Maximum limit which can be suffered by people
150 If exposing for a long time, having perforation
160 If exposing for a long time, it is very dangerous
190 Only exposing for a short time is dangerous
In general, noise pollution is local, directly affecting workers mainly in the Project’s
area. Noise level due to the Project’s performance to surrounding is within the allowable
threshold.
3.4.2. Impacts on water
Wastewater from construction:
During the construction, water is less used. Water is only used in preparing mortar,
concreting. Most of water in this phase penetrates into the materials and gradually evaporate.
Waste water volume due to washing equipments in the Site is not high. Main pollution
components in waste water of construction are construction soil and sand which are less toxic.
Domestic wastewater:
Domestic waste water in this phase contains residuum, suspended substances (SS), organic
substances (BOD5, COD), nutrients (N,P) and pathogenic micro-organisms.
According to standard of WHO, pollutant load in domestic waste water if not treated will be
described as follows:
Table 30: Factor of pollutants in domestic waste water.
(Standard for 01 person)
Pollutants Weight (g/person/day)
BOD5 45 - 54
COD 72 - 103
TSS 70 - 145
NO3- (Nitrate) 6 - 12
PO43-
(Phosphate) 0.6 - 4.5
Ammoniac 3.6 - 7.2
Source: WHO - Evaluating soil, water and air pollution sources - Volume, Generva, 1993.
Drainage and wastewater treatment system project for Thai Hoa town, Nghe An province”
Environmental Impact Assessment (EIA) PCO Consultant, 2010
99
Water expected to use for toilet and daily living of workers at Site is about 45
liters/person/day. Waste water flow generated is approximately 80% supplied water flow. For
70 workers in the Site, domestic waste water flow is:
Q = (70 people x 45 l/person/dayx80)/100 = 2520 (l/day)= 2.52 (m3/day).
From the pollutant load and waste water follow, pollutant concentration can be
calculated during construction, demonstrated in Table 31 below:
Table 31: Pollutant load and concentration
Pollutants
Load
(g/day.night)
Concentration
(mg/l)
QCVN
14:2008/BTNMT
Cmax
BOD5 3.15 ÷ 3.78 1000 ÷ 1200 50
COD 5.04 ÷ 7.21 1600 ÷ 2289 -
TSS 4.90 ÷ 10.15 1556 ÷ 3222 100
NO3- (Nitrate) 0.42 ÷ 0.84 133 ÷ 267 50
PO43-
(Phosphate) 0.04 ÷ 0.32 13 ÷ 100 10
Ammoniac 0.25 ÷ 0.50 80 ÷ 160 10
Notes:
- QCVN 14:2008/BTNMT: the National technical standards on domestic waste water.
- Column B: Applied when domestic waste water is discharged into the sources not for
domestic water supply purpose.
Overflowing rainwater:
During construction, when it rains the overflowing rainwater is available. Such rainfall
depends on rainy regime of the area. According to hydro- meteorological statistics, heavy rain
often happens in some months in the summer from June to September. During this time, the
monthly average rainfall is relatively high.
The overflowing rainfall in the Project’s area is calculated in line with formula:
Qrain = A×F (m3/day.night)
Where:
A: Average rainfall of years in the area, A= 1465 mm/year.
F: Construction area (32,808 m2).
Calculation results are as follows:
Qrain = (32,808 ×1465)/1000 = 48063.72 m3/year
Residuum load: A large volume of impurities are often available in rainwater
accumulated in the surface such as oil, grease, dust, etc., from non-rainy days. Accumulated
impurities in a time is determined in accordance with following formula:
G = Mmax .[1 - exp (-kz.T)]. F (kg)
Where:
Mmax: Maximum dust volume in the area, 220 kg/ha.
kz : Dynamic coefficient of impurity accumulation in the area, kz = 0,3 ng-1
.
Drainage and wastewater treatment system project for Thai Hoa town, Nghe An province”
Environmental Impact Assessment (EIA) PCO Consultant, 2010
100
T : Time of impurity accumulation, T = 15 days.
F : Rainwater drainage catchment area; 3,2808 ha.
Therefore, pollutant load in rainwater is
G = 220× [1 - exp ( - 0.3×15)] ×3,2808 = 713.8 (kg).
Hence, impurities accumulated in about 15 days in the Project’s area is relatively
abundent with main components of sand and soil. The Employer will collect whole rainwater
volume into sewer and temporary sediment collection manholes to prevent sand and soil from
flowing into the receiving hydrology. If mitigation measures are not applied, adverse impacts
on environment will be available. Therefore all such rainwater will be flown into water
drainage ditch system at the Site without water stagnancy to cause disease germs and create
shelter for insects affecting health of workers and neighboring households.
3.4.3. Impacts on soil
* Impacts on current soil structure
The construction of rain water and wastewater drainage system, waste water pumping
station affects firstly on surface soil layer’s vegetable matter but it is regarded as insignificant.
The lost vegetable matter will affect surrounding environment such as loosing the protection
layer, temperature rise in the construction rise, surface washout phenomenon and impacts on
surface water environment, etc. Although soil is drug and after construction, construction
routes are restored as original condition.
For area of Waste Water Treatment Plant, soil is severely affected by earthworks, pile
driving, grading, etc, changing the soil layers’ current structure as well as properties, geology
and terrain of the Site. Impacts on soil are mainly in the Waste Water Treatment Plant. In
order to achieve the foundation level as specified in the technical design, soil impacts in this
area are very high. Changes in the Site’s soil structure and characteristics are indispensable.
* Impacts on soil surface due to transportation of soil, stone and construction
materials
Increase in toxin and heavy metal content in soil during construction should be
considered. The reasons may be petroleum, grease and lubricant leaked from construction
plants and equipments, vehicles, etc. However, trip frequency calculated in a day is not high.
Therefore, these impacts are considered to be within the management.
* Impacts on soil surface due to collection of construction materials
The collection of various kinds of construction materials at the Site also affect the soil
environment. These impacts are negligible and only available in a short time, changing as per
construction period with position, types and quantity of various materials. It is required to
have a proper plan of raw material transportation, collection and use to be able to limit
environmental impacts, especially convenient for builders, saving for the Contractor in terms
of prepaid capital outstanding for goods of construction materials. Therefore, such impacts are
generally negligible.
3.4.4. Impacts of solid waste
Solid waste in this phase includes soil, sand, formwork, steel and waste materials and
a domestic solid waste of workers.
Drainage and wastewater treatment system project for Thai Hoa town, Nghe An province”
Environmental Impact Assessment (EIA) PCO Consultant, 2010
101
However it is only the initial phase of the project. The environment impacts are
temporary, not lasting for long time. The Employer will take the mitigation measures to
minimize impacts on environment and direct labors at the Site.
Solid waste due to construction
Solid waste is waste construction materials such as broken brick, roof plate, wood
beams, formwork, cement packs, scrap metal. Volume of such solid waste depends on
construction and management of the Project Management Unit. Such solid waste will
not be decomposed and generated with bad smell. It can be recycled. This will
minimize its effects on the local environment. Depending on factual situation, the
Employer will make a specific collection & treatment plan.
Table. Estimated quantity of excavation and backfilling soil of the project
Item Excavation quantity (m3) Backfilling quantity (m3)
Drainage system 221,656 185,955
Sewerage system 68,526 38,139
Pressure pipeline system 13,415 7,466
Wastewater pumping station 60 10
2 treatment plants 199,214 34,855
TOTAL 502,871 266,425
(Source: Basic Design Report,, 2010)
One of the most effective measures to reduce the volume of solid waste generated
during construction process is making use of the backfilling of works after the
completion of construction to reinstate the site. For Thai Hoa drainage project, volume
of excavated soil can be made use for aggrading of about 65% of backfilling soil.
Therefore, according to the table of the volume of excavation and backfilling soil
during the construction of the project items, the volume of excavated soil need to be
dumped after making use for the backfilling is temporarily calculated 329.695m3. The
amount of spoil soil and rock will be dumped to the landfill of Thai Hoa town, located
on the high hill area of Nghia My commune (10 ha) through the contract between the
contractor and transport unit.
Domestic waste of workers at the Site
In the construction site, there are about 70 workers. Domestic solid waste is mainly
paper, nylon of various types, cigarette tips, bottles of beers and soft drinks.
Estimated volume of such waste is :
0.5 kg/person/day x 70 people = 35 kg/day.
Although such waste is not much, it will be a large amount if it is not collected daily.
It will pollute soil, water, air and landscape environment at the Site and neighboring area.
When waste is freely discharged, under the impact of the weather and bacteria, organic
compounds are decayed to make bad smell, resulting in the air pollution. In rainy days,
rainwater will flow such organic substances into river and water drainage ditches resulting in
surface water source pollution.
Drainage and wastewater treatment system project for Thai Hoa town, Nghe An province”
Environmental Impact Assessment (EIA) PCO Consultant, 2010
102
3.4.5. Impacts on landscape
Construction of drainage system (rain water and waste water), the waste water
pumping station does not lay remarkable impacts on the landscape.
Construction phases are carried out in each period as scheduled. Completion will be
accompanied with waste collection. Therefore, construction phases only affect landscape in a
short period of time. After completing works, the landscape is restored as original conditions
in the roads by re-planting original green trees. Some roads can be enhanced by green tree
belts to ensure aesthetics for the town.
For Waste Water Treatment Plant area, such impacts are generally positive. The
landscape here is completely changed, replacing the sugar cane fields by the construction site
with works items such as treatment areas and other auxiliary works.
Impacts on cultural architectures/sensitive facilities
The project construction does not directly affect (to demolition or relocation, land
acquisition) to the cultural hesitages: temples, shrines,… . However, these works may be
affected indirectly during the construction such as dust, noise, landscape and affect daily
activities when the construction is implemented along roads. These effects are short term and
may be mitigated.
Table 4: List of sensitive facilities to be affected during the construction period.
No. Sensitive
facilities
Location Ranking (If any) Distance to the
project site (m)
Cultural-historical works:
1. Bau Temple Bau Sen area – Hoa
Hieu ward
No 100m
2. Ba Chua Muong
temple
Quyet Thang block –
Hoa Hieu ward
No 100m
Sensitive area:
3. Bau Sen green Bau Sen area – Hoa
Hieu ward
No 0m (Near the road of
sewer line)
4. Flower gardern
at the
intersection
Kim Tan block
No 0m (Near the road of
sewer line)
3.3.6. Impacts on the socio-economic life
(1) Labor accidents during constructing water drainage sewers, pumping station and
Waste Water Treatment Plants
Risks to be the most concern is collapse of outlet sewers, manholes, construction pits
and other works within the construction site of Waste Water Treatment Plants; soil and stone
blocks and upper materials can be ton weight, this exceeds the resistance of workers. Most of
reasons for such accidents are due to workers’ low sense of compliance with labor safety
regulations. Unsafely operations and uninsured working conditions are the indirect causes of
the accidents and failures.
(2) Traffic congestion and potential accident risks
Drainage and wastewater treatment system project for Thai Hoa town, Nghe An province”
Environmental Impact Assessment (EIA) PCO Consultant, 2010
103
Rain water and wastewater drainage systems are constructed in the inner city wards
located on the main roads. Most of above roads have not large dimensions but many means of
transportation take part. Therefore, operations of trucks transporting raw materials and
construction process in these roads are partially restricted. Narrow space results in inner
traffic jam, especially traffic jam in the rush hours are inevitable.
Pipelines, sewers and ditches are randomly available a long with material storage
yards. If there is no clear signs and attention of road users, especially in nighttime, traffic
accidents are potentially happened surrounding the site.
(3) Impacts on the socio-economic life of the local people
When the Project is performed, activities such as road barrier and traffic restrictions
will partially affect the daily activities of the local people, especially production, business and
service households. This is an inevitable impact. However, during construction, such impact
should be shortened as per construction phase. The landscape is also restored as original
condition, therefore such impacts are negligible.
When constructing works items, underground works such as fiber cables, clean water
supply pipelines, electric wires, etc, can be affected. To avoid such effect, before constructing,
it is supposed to work closely with concerned authorities to arrange and adjust sequences of
underground work network layers such as solutions on power, water and works items as stated
in the Investment Project Report. Thanks to that, there is no overlap and reverse and mutual
impacts.
Besides the positive impacts, the Project performance also causes adverse impacts such
as:
- Concentration of manpower to construct from other areas will affect the local social
security, etc.
- Living habits of the local people is changed.
- The local economic structure is changed.
(4) Impacts on the community health
In addition to affected objects such as the local geological environment of the project
area, land, water and air resources, etc, there are direct affected objects especially human
being in general, workers, local people and road users in the on-going roads in particular.
High dust content causes lung-related diseases, asthma, diseases related to ears, noise and
eyes…. and obstruct the vision, affecting the road users.
Other emissions are mainly CO, SO2, NOx, hydrocarbon, dust pollutants (dust, flue
gas). CO affects people by combining wih Hb to replace O2 and reduce hematite in blood,
resulting in O2 insufficiency for living activities, NOx is exposed at 0.06ppm level can cause
serious lung-related diseases. Hydrocarbon make lung membranes swell, narrow the lung
vents and make eyes swell. Some combining with Hydrocarbon can cause cancer.
Drainage and wastewater treatment system project for Thai Hoa town, Nghe An province”
Environmental Impact Assessment (EIA) PCO Consultant, 2010
104
3.5. ENVIRONMENTAL IMPACT ASSESSMENT DURING OPERATION PHASE
Table 5: EIA for the operation
Impacts Sources
Assessment
Negative Positive
Short Long Short Long
I Drainage and wastewater collection system
1. Landscape
improving the city’s landscape H
improving Tay Yen Stream’s
landscape H
2. Noise Operation of the WWPS L
3. Smell
Operation of the WWPS L
Reducing smell from
wastewater H
4. Local flood Reducing of flooding risk H
5. Surface water temporarily discharging M
Operation of the WWPS L
6. Dredged sludge Pipeline system M
7. Community health Improving the community
health H
8. Health and career
safety
H2S, CH4 in the WWPS and
the sewerage system L
II WWTP
9. Air environment
Smell of toxic gas such as
H2S, CH4…from biological
ponds
M
Noise from the WWPS
operation process
The distance meets QCVN
07:2010/BXD ( 200 m), so the
impact is neligible
10. Removement of
solid waste
workers’ solid waste L
waste from screens and sludge
from biological ponds
11. Surface water
untreated wastewater in the
WWTP in case the WWTP is
in emergency
M
waterwater is treated and
discharged into Hieu River H
12. underground water
pollutiona
wastewater leaks and absorbs
into underground water
the cause is the pond bottom is
not constructed well
M
Drainage and wastewater treatment system project for Thai Hoa town, Nghe An province”
Environmental Impact Assessment (EIA) PCO Consultant, 2010
105
Impacts Sources
Assessment
Negative Positive
Short Long Short Long
13. traffic safety
traffic jam caused by the
vehicles such as sludge
truck…
L
14. Labor safety safety equipments for workers M
environment pollution M
electric danger M
fire M
contact to dangerous
microorganics M
15. Safety and
community health
smell and noise
domestic waste M
solid waste
workers’ activities
16. Landscape
changing the landscape of the
WWTP caused by the
existence of the works
L
Note: L (Low), M (Medium), H (High)
3.5.1. Bad smell and toxic gas
For the operation process and any wastewater treatment system consisting of
wastewater treatment plant, wastewater pumping station and manholes on wastewater
pipeline), the most concerned issues are: (1) Bad smell and toxic gas; (2) sludge; (3) Labor
and environment accidents.
Bad smell is characterized by toxic gas such as H2S, NH3, CH4, non-comfort smell,
etc, from waste water treatment process after microorganism decays the waste, especially
organic substance. Anaerobic pond, facultative pond in the treatment plant are the first one of
the treatment series where causes the bad odour. Bad smell and toxic gas will directly affect
operators and especially neighboring residential areas at the end of wind direction as per
season. However, the selection of biolake treatment technology with 500m distance from the
residential areas ensures to comply with sanitation safety distance for 02 WWTPs at Long
Son ward and Nghia Tien commune, in combination with a green tree system surrounding the
lakes will reduce the smell and toxic gas concentration which will be dispersed in the air.
Only impacts are found in the small scale.
As manholes and wastewater pumping stations are constructed underground, the bad
odour is minimized. Therefore, impacts on health of workers and neighboring residential
areas can be limited if the operation unit strictly comply with mitigation measures to be
recommended in this report at Chapter 4.
Moreover, the air is affected by noise and vibration during operating plants and
equipments as well as some emission from operating machines in internal-combustion engines
Drainage and wastewater treatment system project for Thai Hoa town, Nghe An province”
Environmental Impact Assessment (EIA) PCO Consultant, 2010
106
(CO, NO2, SO2…). However, such impacts are insignificant against the deign of underground
waste water pumping stations to limit noise and vibration. A few of equipments in the waste
water treatment technological line by biolakes as stated in the assesment of the technological
line selection applied for WWTPs of Thai Hoa town.
3.5.2. Waste water and overflowing rainwater
Impacts mentioned are domestic waste water of workers, impacts from waste water
drainage sewers during transportation from the pumping stations and overflowing rainwater
during operation of drainage system and waste water treatment system of the project.
- During operation, waste water volume is estimated in line with number of workers and
engineers operating the WWTPs, manpower in the water drainage pumping station,
drainage system. The special drivers are not considered because they not concentrate
in a certain area or they can live with their family. Therefore, it is calculated with a
number of operators of 10 people (1 chief, 1 accountant, 2 engineers, 2 lab technicians
and 4 operators). Domestic water volume used in the WWTP is 80 l/person/day, hence
each day, the WWTP need 0.8 m3 , equivalent to the domestic waste water volume of
0.8 m3. Generally, waste water load volume is not high, affected insignificantly.
- Overflowing rainwater affects water of the town mainly from WWTPs area.
Especially in the flood season, biolakes in the two WWTPs are open without cover,
therefore, when rainwater rises with limited water capacity and drainage ability of the
lakes, the overflowing rainwater will flow pollutants and discharge into surface water
sources, Hieu River in particular. However, such impact will be minimized by
calculating proper discharging outlets. Hence, such phenomenon is not happened. Vice
versa, with dilution of overflowing rainwater in lakes, the purification process will be
enhanced, laying the positive impacts on the treatment process.
- Impacts caused by wastewater penetration into soil and underground water
environment (in treatment ponds of 2 treatment plants: anaerobic pond, facultative and
stabilization pond), this is the most concerned issue when proposing the wastewater
treatment technology using biological pond series. Ponds are designed to use materials
that prevent water from penetration into soil environment and ground water source as
well as not affecting the living environment of local residents.
3.5.3. Sludge and domestic solid waste
For this phase, sludge and domestic solid wastes from bar screens and daily activities
of operators are the main impact sources during the operation of the drainage and waste water
treatment system of the town.
(1) Post-treatment sludge:
Amount of sludge is calculated basing on the TSS content of input waste water. Every
day, there is about 300mg/l TSS and total treatment capacity of 2 WWTPs is 6,000m3/day (=
4000 + 2000m3/day). Therefore, daily sludge volume is 300/1000 * 6,000*1000/1000000 =
1.8 tons. Such volume is relatively big with a large amount of pollutants, especially bio
criteria if it is not collected and treated daily. It will be an epidemic germs for local people.
However, such volume is concentrated in the drying yard to reduce their volume and
use sterilization measures such as spraying limestone powder, etc, before transporting to the
Drainage and wastewater treatment system project for Thai Hoa town, Nghe An province”
Environmental Impact Assessment (EIA) PCO Consultant, 2010
107
general landfill of the town. Hence, such impact can be minimized. Besides, it can be used as
fertilizer for agricultural production.
(2) Solid waste from bar screen and manholes:
Collected volume of solidwastes is mainly organic substance, nylon bags, paper, etc
with estimated weight of 1.5 kg/day. At collection pits, manholes are also the collection of
solidwastessuch as stagnant sludge with main components of organic substances being
decayed. Most of such solidwastes s are easily decomposed and collected with post-treatment
waste sludge. Hence, impacts on environment and workers at sewers, manholes and WWTPs
are insignificant.
(3) Domestic solidwastes s of employees:
With estimated daily load of each worker of 0.5 kg/person/day, total number of
operators in the WWTP is 10 people. While solidwastes load in this phase is 5kg/day. Hence,
the domestic waste generation is inevitable. However, mitigation measures for such impacts
should be applied before operating the WWTPs.
3.3.4. Impacts on landscape
During operation, when rainwater drainage system and wastewater drainage system as
well as pumping stations are put into operation, roads will be restored as original conditions
after construction completion. Post-construction areas wil be restored and can be furnished
with green coat for the Project’s area. Therefore, impacts on landscape and ecosystem are
regarded as positive.
Basically, impacts on WWTP construction will completely change the landscape and
ecosystem at the site. Post-treatment waste water quality will be qualified as stipulated in
QCVN 14: 2008/ BTNMT, Type B before discharging into Hieu River. Therefore there is no
impacts on micro-organism lives.
Area for traffic roads and green tree belts covers the large scale in the waste water
treatment area. The green tree and traffic road areas are specifically located in the detail
design. Such items are very important because it makes a remarkable contribution to
minimize impacts during operation of WWTPs.
In general, the local ecosystem is completely changed in terms of characteristics and
scale. However, such impacts on the ecosystem in terms of fauna and flora are regarded
insignificant. When WWTPs are available, the landscape is changed positively, demonstrated
in the infrastructure development. Thence, living standards are improved by developing and
perfecting the infrastructure in general.
3.3.5. Environment safety and risks
- Problemss of blocking the rain water and waste water drainage sewers at some
pipelines due to construction of other works such as: high-rise buildings, market, trade area,
power supply infrastructure perfection, fiber cables, IT, etc, or low awareness of a part of
local people on freely discharging waste. Such block can make local flood, affecting the
traffic and daily life of the local people.
- Problemss in the booster pumping station and WWTPs are one of risks affecting the
socio-economic life of the local people. In the rainy season with large volume of water due to
the underground pumps, hence, when water rises above the warning level, standby pumps will
Drainage and wastewater treatment system project for Thai Hoa town, Nghe An province”
Environmental Impact Assessment (EIA) PCO Consultant, 2010
108
be activated to pump water into the WWTPs or limit the water drainage capacity and life of
the pumping stations. In case of power cut off, the standby generator will be used to ensure
treatment capacity and performance of the station. Therefore, waste water is still treated in
such case without affecting the environment and local people.
- The flood problemss in the 2 WWTPs due to overflowing rainwater in the flood
season as stated above will flow impurities and micro-organism, epidemic germs, etc,
polluting water sources (Hieu River) in the area and affecting safety in the daily activities and
production of the local people.
- Output waste water quality is not ensured as stipulated in QCVN 14: 2008/ BTNMT,
type B before discharging into Hieu river if the operation fails to comply with treatment
process as well as discharging process as designed.
In addition to positive impacts, the environment problems can be available during
operating the drainage system and WWTPs. The construction of WWTPs generates jobs and
income for some workers involved in some services surrounding the WWTPs such as shops,
etc, to meet the demand of operators. Hence, living standards of the local people surrounding
the WWTPs in terms of supplying food and necessary services for operators in the WWTPs.
Accordingly, supply demand is developed. This is one of direction to increase income of the
local people and improve the regional economic growth in general.
Drainage and wastewater treatment system project for Thai Hoa town, Nghe An province”
Environmental Impact Assessment (EIA) PCO Consultant, 2010
109
CHAPTER IV:
MITIGATION MEASURES FOR ADVERSE IMPACTS, PREVENTATION AND
RESPONSE TO ENVIRONMENTAL PROBLEMS
4.1. MITIGATION MEASURES IN THE PRE-CONSTRUCTION PHASE
4.1.1. Research methodology and specific assesment on the project area’s location and
land situation
During the project preparing and design phases, he applies the general measures to
prevent pollution and creat favorable conditions for the environment protection in the next
phases as follows:
- To conduct detailed survey on the geological position and terrain of the project area
to completely evaluate the advantages and disadvantages for planning the infrastructure
development to obtain highest economic performance, save costs and investment time,
developing the project’s overall strengths.
- To conduct detailed survey on advantages in terms of climate, weather, hydrography
(water level, foundation grading level, etc) to make master plan in line with terrain, climate,
weather conditions as scheduled by the town.
- To evaluate the geological conditions of the project area to work out the work
foundation design.
- To suggest the construction land technical measures to minimize earthworks and air
pollution in the site clearance phase, creating natural water drainage channels, preventing
floods during constructing the technical infrastructure of the project.
- Before reclaiming land, land users are notified about the reason of such activities,
time and plan for moving as well as selecting the logical compensation proposals for affected
households as stipulated in the approved resettlement plan.
4.1.2. Site plans
To minimize adverse impacts on site clearance, the Employer conducts:
- Analysis and evaluation of land use situation, population, labor and construction land
fund to suggest the local planning structure solutions
- Determining land use functions for works items with the technical economic criteria
as required for the construction of water drainage & waste water treatment systems.
- Determination and caculation of the technical infrastructure such as traffic, technical
preparation, water supply, power supply, environment sanitation, etc to combine with the
local water drainage & waste water treatment systems .
- Organization of architectural plan space to create a beauty spots, harmonizing with
surrounding, especially in the two WWTPs.
Drainage and wastewater treatment system project for Thai Hoa town, Nghe An province”
Environmental Impact Assessment (EIA) PCO Consultant, 2010
110
4.2. MITIGATION MEASURES DURING CONSTRUCTION PHASE
4.2.1. Air pollution limitation
4.2.1.1. Dust minimization
The project owner/contractor must apply dust mitigation measures during backfilling
and construction of work items as follows:
- Make soil and canals wet, before digging or cutting out the roads and
sidewalks: 2 times a day to ensure land always in wet conditions. Therefore,
the amount of dust spreading away is limited (reduction levels is more than
75%);
- Isolate the construction area and have measures to cover the transport vehicles:
it can be used with mobile trees or fences to prevent emitted dust near the road
or in the construction area. This can be reduced by 80% due to dust released
when transporting;
- Reducing soil/land storage and cover land or construction materials by plastic
in the storage areas: it is necessary to pay attention to the construction areas
near residential areas. Book method of construction can be used. Therefore, the
amount of volume of waste is stored only in short time at the construction area
and using of cover material to limit the dust distribution. The volume dust
emission in this phase is insignificant;
- Maintenance construction and transport facilities and prevent leakage: ensuring
the design capacity so the volume waste disposal must be in accordance with
the calculation as in chapter on impact assessment. The right volume of
emission in the allowed limitation can be controlled when implementing
measures to minimize impacts on the environment;
- Inform people about the plan of improving and building to limit the
complaints from the people: generally, notify people in the project area at
least 2 weeks before implementing project and answering all questions and
recording all the responses of people to project construction to have optimized
construction plan.
- After construction works such as excavation of trench to install pipeline,
pumping station, it is required to clear the site and reinstate the plan.
Ensuring the implementation of methods to minimize impacts on above air quality can be
reduced to 95% of the impact on environment. The rest is contributed from the knowledge of
operators and conducting the suitable methods in line the proper guidance of the agency
responsible for issues related to environment.
4.2.1.2. Minimizing impacts of noise and vibration
To minimizing adverse impacts of noise and vibration generated during constructing
works items, it is required to apply mitigation measures as follows:
- Use the specific vehicles and periodic maintenance;
- Planning construction schedules to avoid the sensitive time and crowed
moments;
Drainage and wastewater treatment system project for Thai Hoa town, Nghe An province”
Environmental Impact Assessment (EIA) PCO Consultant, 2010
111
- Operating all devices with great noise levels in short time;
- Use fence, minimum distance to households in the construction process ( more
than 100 meter); Especially, in wastewater treatment plants it is vital to ensure
the distance for a safe construction to regional population (200 meter);
- Notify people about the construction plan (at least 2 weeks before
construction).
The impact of noise and vibration will be reduced by from 85 to 95% of noise from
construction areas. However, at the high level of construction, noise and vibration can be
reduced by 75% but only in a certain period of construction, expend the time between each
work item limit the influence of noise and vibration on environment
Besides, to minimize adverse impacts on the atmosohere in this phase it is supposed to
comply with some construction safety regulations and rule for some following measures in
addition to the aforesaide technical solutions:
- Trucks transporting construction materials must be diverged as stipulated to avoid
local pollution in the Project’s area.
- A proper construction and manpower plan must be prepared to avoid overlap
between implementation processes. It is necessary to apply modern construction methods,
advanced construction equipment, machanization and maximizing the construction process.
- Documents on construction plants and equipments must be fully provided.
Specifications must be regularly checked. Fire warnings and other necessary signs must be
installed.
- Proper construction plan and material supply schedule must be prepared. Materials
must not be collect at the same time.
- When loading the materials, worker must be provided with Personal Labor
Protection Equipment to limit dust impact on their health.
- It is required to raise the awareness on environment protection for workers and
managers at the Site to show the benefit of healthy working enviroment protecton attached
with their health and community health protection.
- Violation will be severly treated.
4.2.2. Mitigation of impact on water environment
This environment is quite sensitive and can spread out pollution in a large scale. Limiting this
impact is very essential and it should been had a clear plan, and specific progress of
construction. Minimizing flooding in local construction and the impact on water environment
needs necessary measures:
- Layout the temporary drainage canal system in the area of construction. The
contractor will arrange suitably in accordance with the area and scale of items
of construction;
- Layout scale pits in the river gates and when there is a large volume of
wastewater, the contractor will use pumps to pump water to the river;
Drainage and wastewater treatment system project for Thai Hoa town, Nghe An province”
Environmental Impact Assessment (EIA) PCO Consultant, 2010
112
- Design drainage system, temporary discharge sewer, maintain the working
condition of discharge sewers and install the system of temporary pumps to
pump water to discharge points;
- Use or transport immediately aggrading land (amount of aggrading land has
been specifically mentioned in above chapter), reduce the amount of land
stored in the construction areas;
- Arrange construction time reasonably and effective;
- Maintain equipment to limit the leakage of oil, fat ...
- Enhance the safety in the transportation of materials on the river, stream (if
any) to minimize ability to spread out pollutants;
- Collect and process wastewater, solid waste of construction process and
domestic solid waste occurred in the worker camp areas
4.2.3. Mitigation of impact on soil environment
Measures to minimize impacts mentioned include:
- When dredging and operating routine ditches, water drainage and building
treatment plants, a new block of land is generated. This volume of land should
be taken advantage of reimbursing surface to return the original surface; the
rest is collected and transported to make the basement of treatment plants.
Processing 100% of the waste rock at the right place;
- Sludge generated when dredging ditches needs a plan to sieve lime to prevent
disease spreading out quickly to workers, receiving sources and needed
transporting the sanitation beach for safely handling these waste. Process
thoroughly 100% of sludge disposal which affects environment and health of
workers directly involved in construction;
- The problems of land depression and destroying natural structure, it should
have calculated the specific load, density and the strength of materials used in
construction to have necessary backup measures. Plan for monitoring the land
depression levels: once per total duration of construction of the whole pipe
line system; once or twice for total construction time of all items of treatment
plants. However, monitoring frequency, depression measurement will be
decreased each year when the project is put into operation and depend on the
actual conditions of construction area. Therefore, they always are active in
monitoring the construction quality.
In addition, for the wastewater treatment plants, it is notified more about the additional
mitigation measures for some subjects as follow:
* Agricultural Solid waste
- Most types of solid waste originated from organic substances are easily
decayed in accordance with the biological process. But if not collected,
cluttered waste will affect environment. Conversely, if combined with
farmers to create the green fertilizers for agricultural cultivation, it is an
environment friendly method and save costs for transportation, handling in a
hygiene buried beach
Drainage and wastewater treatment system project for Thai Hoa town, Nghe An province”
Environmental Impact Assessment (EIA) PCO Consultant, 2010
113
* Land depression in the wastewater treatment plants
- Calculate these impacts from the actual survey, geological and topographical
investigation and previous research on characteristics and nature of land to
limit them when building work items (mentioned above). Simultaneously, it
needs a monitoring process on land depression level during the construction
to have the instant response to all possibilities that may occur and ensure
quality of construction
4.2.4. Mitigation of impact on transportation and flood in the construction
* Reducing the impacts to transportation
− The impacts to transportation is unavoidable to all the works in execution, so it is
necessary to properly divide the road lanes, ask the bidder to plant the warning
signs, to have the lane dividing guide, the indicator light at night and other
specific signs as defined by the current regulations of safety transportation;
− The work warning signs must have the name of the executors, local authorities,
address and telephone number of specific individuals in case of complaints or
arose problems;
− The bidders must have the detailed plan to seal off the road in minimum period of
time or not in the rush hours. Local community and the business units need to be
informed about the execution schedule 2 weeks in advance by the mass media
(radio, television, local radiocasting);
− This task will be done in collaboration with the transportation police, the
Department of Transportation and other relevant unities.
* Reducing the impacts of flooding
− Digging small ditches, trenches to drainage temperarily at sites of executing areas
and seting up moving pumps to pump water at temperary collected holes;
− When water level is up to max fix level holes, it’s necessary to pump into river,
specially, in rain- season;
− Executing how far, clearance up to there to avoid and mitigation flow jam on
draiage;
− In flooding and huge rain season, it’s necessary to have the reasonable option,
active- time and amount of pumps in active or standby have been operated
reasonable and optimum.
− Building the fence, temporary dykes to restrict phenonmenol of blow soil, stone...
on working;
4.2.5. Mitigation measures for environmental problems
− A Committee of Labor Safety and Environment Protection should be established at
the Site.
− Construction machines and equipments must be attached with records, checked
and regularly supervise specifications.
Drainage and wastewater treatment system project for Thai Hoa town, Nghe An province”
Environmental Impact Assessment (EIA) PCO Consultant, 2010
114
− It is supposed to set up regulations on working at Site including in/out of the Site;
regulations on labor protection clothes; regulations on using equipments, electric
safety and traffic safety.
− Operators directly handle with construction and machines must be trained and
practised properly.
− Regulations must be popularized to workers through various forms.
− Labor accidents must be controled to timely identify the causes and apply recovery
methods to avoid re-occurance of the similar accidents.
− It is required to install prohibition signs at the dangerous areas.
− Electric wire and switch systems which can spark must be safetly arranged.
− Manual fire extiguishers must be arranged at the most convenient positions for use.
Fire extinguishing medium must be regularly checked and ensured to be ready for
use.
− When installing the scarfold and equipment at height, safety lock belt must be
equipped.
− Medical team and cabinet must be available at site to timely provide first-aid in
serious accidents.
4.3. MITIGATION MEASURES DURING OPERATION PHASE
4.3.1. Minimizing impacts on air environment
In operation, impacts from air are clear. They are noise from pump operation in
pumping station and treatment plant, odor from exhausted gas in compositing organics in
wastewater. Many methodologies are applied as follows:
- Ferformance periodical maintenance;
- Operating as per the design capacity;
- Increasing surrounding green tree trips to limit noise and exhaust;
General measures to minimize air pollution for operation phase:
- Giving out plan for periodic checking, monitoring exhaust concentration to
have reasonable assessment and control in the operation process;
- Limiting exhaust and noise by operative machine and equipments with green
tree trips surrounded the treatment plant;
- Figuring ballpark pollution Load to have options for adjusting best capacity
during operation;
- Process of transporting waste (sludge, domestic solid waste) must be contained
in the standardized chamber to minimize spreading exhaust and solid waste to
the environment;
- Giving out plan for periodic control and maintenance for machines to ensure
good working condition during operation
Drainage and wastewater treatment system project for Thai Hoa town, Nghe An province”
Environmental Impact Assessment (EIA) PCO Consultant, 2010
115
4.3.2. Minimizing impact on water environment
- Performing periodic maintenance for drain, sewerage, wastewater pump house,
avoiding the jam and overwork condition;
- Giving out plan for dredging, collecting and treating absolutely wastes
collected from screen bar, grit tank, domestic solid waste of observing
Engineers and operative workers;
- Closely controlling the situation of local flooding caused by objective reasons
to insure good working condition of sewers;
- Complying full codes on operation and management of wastewater treatment
plant;
- Giving out frequent observation plan to control the pollution.
4.3.3. Minimizing impact on soil environment
- Wastewater anti-penetration method from reservoir into soil and ground water
environment when opearting the treatment plant.
According to Basic Design Report of the Project, the antipenetration method for ponds
are designed as follows:
+ Clay : 40 cm;
+ Anti-penetration meterial: HDPE, GUS;
+ Rubble
This structure has been tested ensuring anti-penetration and applied for wastewater
treatment technology using pond series similar to some cities metioned above such as Thai
Binh City, Lang Co – Hue City, etc.
- Sludge treatment method:
+ Sludge dredging from treatment pond to transfer to sludge drying bed is
implemented twice a year for one pond. Therefore, the Consultant proposes to use portable
pump to pump sludge from the pond to the sludge drying bed. These pumps are submersile
ones which are fixed on the platform and can be easily installed and dismantled. Sludge will
be gathered to this location and then transfered to the sludge drying bed. These submersile
pumps are equal to the normal pumping stations. They are advanced ones with auto-
controlling system to regulate flow, have high safety level and easy for management and
opeartion.
+ Sludge from screen, sedimentation tank after being grinded together with sludge
from oxidation ditch is pumped to the sludge drying bed where sludge is mixed with lime to
disinfect and handled through the press. Amount of water after being pressed will go back the
treatment work and dried sludge will be loaded into truckes to transfered to the Thai Hoa
landfill with area of 10ha on the high hill area of Nghia My commune.
- Number of pond 1 pond
- Area = 115 m2
- Width = 10 m
- Length = 11,5 m
Drainage and wastewater treatment system project for Thai Hoa town, Nghe An province”
Environmental Impact Assessment (EIA) PCO Consultant, 2010
116
- Depth = 1.7 m
Apart from the said methods, M&O unit must follow some following management
methods to minimize impacts of sludge on environment and public health.
- Gathered sludge should be stored in a short time not exceeding 48h and applied
measure of spraying disinfection lime to ensure safety for the environment;
- Not gathering sludge and waste at the treatment plant in a long time, especially
need designing far distance from the housing area of the operative workers;
- Giving out periodic maintenance for plant and equipment to monitor the
working condition and compliance during operation. Limiting fuel leakage into
soil environment;
- At storage, need spraying lime, closely covering, limit bacterium and diseases
causing factors and epidemic spreading elements
4.3.4. Reducing impact on ecosystem and socio-economy
- Returning green landscape for the area of the wastewater treatment plant;
- Creating green tree trips surrounding the treatment plant, housing area and
operation area of workers;
- Preparing plant for community education, heighten awareness of the people on
environmental protection in order to have effective operation and supported by
the people;
- Holding seminars, scientific conference on drawing experience surrounding
the project area;
- Co-coordinating with experts, management of local authority to performing
effective operation and absolute solving, meeting present demands, stepping up
to completing the project in the following phases.
4.4. MEASURES FOR PREVENTING ENVIRONMENT RISKS
In order to prevent fire, explosion, direct operative worker, Engineers have to strictly
regulations on fire, explosion prevention measures as follows:
- Machines, equipments operating at high pressure must be included clear
record, equipped with pressure meter and checked periodically;
- Installing fire alarm system, warning alarm system;
- Installing arrestor system for area with height;
- Electrical equipments should be maintained in the safety condition, preventing
impossibility of spark in the dangerous areas;
- Power using machines should be earthed to prevent leaky and electromagnet
charge;
- Chemicals storehouse must be situated at the end of wind direction, safe,
Chlorine containers must be checked periodically;
Drainage and wastewater treatment system project for Thai Hoa town, Nghe An province”
Environmental Impact Assessment (EIA) PCO Consultant, 2010
117
- Heightening technical skills especially safety regulations, fire prevention and
fighting regulations for operative workers. Frequently checking, reminding
regulations on environmental protection and fire prevention, and fighting.
Guardmen and fire fighters should be ready 24h/day;
- Building options for preventing, recovering environmental accidents: fire,
explosion, chemical leakage, accidents of environmental treatment plant
(wastewater, exhaust treatment), to submit to state authority for approval and
organizing implementation.
- Control solution for industrial wastewater (if any) as the units discharge into
the genaral drainage sewers that is required for industrial units/ industrial parks
in Thai Hoa Town discharge of sewage into the drainage system to achieve the
standard, type B - QCVN 24:2009 / BTNMT - National Technical Regulations
on industrial wastewater.
Table 6: Mitagation measures of risks and emergencies during the
construction and operation phase
No. Situations Action plan
1 Cultural and archaeological
antuques
Maintaining the existing status and reporting to
the supervisors and Client, the local museums and
the Department of Culture and Information
Submitting to museum management agencies /
cultural management agencies;
Determining that the excavation will be continued
or stopped to investigate further.
Director of Department of Culture and Information
is responsible for managing objects and antiques
under the provisions of Article 21 of Decree No.
92/2002 on guidelines on the implementation of the
Law on Cultural Heritage.
2 Graves
Protect status, and notify local authorities
Identify solutions and duties of the relevant
individuals, execution time and place to move if
any
Implementation of measures proposed
3
Complaints on environmental
issues
Immediately implement mitigatation measures if
possible
Recorded in the diary
Discuss with the Client and local authorities to
thoroughly resolve the conflict
4 Explore- fire
Protection status
Notify local authorities
Contact with the local military units for support
5 Fire
Notify agencies (especially, fire police).
Rescue of objects
Actively isolate the fire with the existing facilities
on site (fire extinguishers, sprinklers, fire
extinguishers (if any)).
Drainage and wastewater treatment system project for Thai Hoa town, Nghe An province”
Environmental Impact Assessment (EIA) PCO Consultant, 2010
118
No. Situations Action plan
Support under the guidance of the functional units
until they are at the scene (especially, mines,
explosives caused by chemicals, etc..)
Support the functional units, local governments
set up perimeter security around danger areas.
Check the fire safety conditions on site, make sure
this problem does not redo.
Suspend the work if workers break the regulations
on fire safety.
7 Electrical accident
Disconnect the power in the incident area and the
surrounding area
Immediately save the people in the danger areas
Find out what is causing accidents, power check,
wires and contacts ...
Recorded accidents
4.5. FLOOD CONTROLS
Risk and broken-down from nature are decisive factors to the sustainable character of
all infrastructure works. So, flooding is a factor that having market effects on. This is a natural
phenomenon, so, it need to having preventative option and dealing in- time to restrict the bad
impacts to quality and quantity of treatment plan.
In technical design, flooding and inundation factors have been considered to offer proper
options and minimize risks of flooding and inundations, especially in rainy season,
specifically:
- Ground leveling will be designed at higher level compared to the highest
level of flood in Thai Hoa of 47.5m (according to the sea level) over the past
years.
- Installing 01 standby pump in each wastewater pumping station
Therefore, by the design mentioned above, during heavy rain, water level is high, each
pumping station will operate one more pump and number of working hours of pump will meet
drainage ability in case of big water flow. When water level exceeds the allowable designed
limit, wastewater collection pumps will pump water directly to the discharge outlet to limit
long time inundation. Wastewater will be mixed with a big amount of rainwater, the
contaminated concentration will be reduced significantly and it will be further dilluted when
being discharged into river. Therefore, concentration of pollutants is not much and local
inundations are limited during flooding. This measure is considered as optimal option at the
moment.
Drainage and wastewater treatment system project for Thai Hoa town, Nghe An province”
Environmental Impact Assessment (EIA) PCO Consultant, 2010
119
4.6. SANCTION METHODS
In Chapter 5 - Environmental management and monitoring program of this report has
proposed a general environmental management and monitoring program in which it states
clear requirements for Project Owner and other relevant units to comply with proposed
minigation measures . This is the basis for the Department of Natural Resources and
Environment of Nghe An province, concerned units, the donor (World Bank) to make
inspection, supervision and punishment according to current Vietnam law when discoverying
the non-compliance with environmental protection and causing environmental pollution by
the Project Owner (eg: reserve the right to sanction under Decree No. 117/2009/ND-CP dated
December 31, 2009 of the Government on handling violations in the field of environmental
protection ,...).
Upon discovering the violations, non-compliance with the environmental protection
and environmental pollution caused by contractor, project owner, management and operation
uint during the construction and operation of Thai Hoa drainage and wastewater treatment
system, the competent authorities may reserve the right to sanction under Article 40, 41, 42 -
Section 2. Authority and procedures for sanction – Decree No.117/2009/ND-CP dated
December 31, 2009 of the Government on handling violations in the field of environmental
protection, including:
Article 40. The competence to dealing with administrative violations of People’s
Committee of all levels, of which: Chairman of wards/communes; People’s
committee of district, provinces.
Article 41. The competence to dealing with administrative violations of the people’s
public security in which: On-duty environmental police officer; head of commune
police, head of environmental police office, head of district police office; Director of
Environmental police bureau.
Article 42. The competence to dealing with administrative violations of special
inspections, in which: Environmental inspection of Department of Natural Resources
and Environment; chief inspector of Department of Naturla Resources and
Environment; Chief inspector of Environmental Bureau; Chief inspector of Ministry
of Natural Resources and Environment.
(Articles applied in Decree No. 117/2009/NĐ-CP dated 31/12/2009 of the Government on
dealing with law violations in the field of environmental protection).
Drainage and wastewater treatment system project for Thai Hoa town, Nghe An province”
Environmental Impact Assessment (EIA) PCO Consultant, 2010
120
CHAPTER V:
THE ENVIRONMENTAL MANAGEMENT PLAN
5.1. ENVIRONMENT MANAGEMENT PROGRAM
The objective of the environmental management plan for the project is to provide
guidance to the project can be assured in term of environment. Environmental management
plan to comply with current legislation on the environment of Vietnam and comply with
environmental safety policies, including:
+ Using the appropriate organizational structure for environmental protection in various
phases of project implementation to ensure that mitigation measures are implemented in all
phases and monitor the effectiveness of the mitigation measures proposed in the EIA report.
+ Management and monitoring plan proposed reduction in the EIA report for the bid
winner to build and operate.
+ Provide a contingency plan to rescue plans for environmental incidents occurred.
5.1.1. Organization for implementation of EMP
The effectiveness of the EMP depends on many factors and organizations, this is clearly
shown in the roles and responsibilities of the relevant bodies in ensuring environment safety
and managing environment. These responsibilities of the organizations and relevant bodies in
the execution of the EMP of “Drainage and wastewater treatment project for Tuyen Quan
town, Nghe An province”, are shown in the table below:
Table 5.1: Roles and fuctions of environment management of the project participants
Roles Functions
1. The implementation agencies:
The People’s Committee of Thai
Hoa town
Co-ordinate and manage the implementation of the project,
including project instruction and monitoring.
The People’s Committee of Thai
Hoa town
(Project Owner)
Have the responsibility to carry out completely the
management, deployment the EMP.
The Management Board of
“Drainage and wastewater
treatment project for Thai
Hoa town, Nghe An province”
• Have the responsibility to complete the daily tasks of the
project, including examining and monitoring the
implementation of EMP (when assigned)
• Have the responsibility to train and support the contrator
about issues of the environment; examining and
monitoring the process of implementing the project to
ensure that the proposed procedures are strictly followed.
Environment consultant Prepare the EMP
Construction contractors
Construction will comply with the following methods
• Apply the measures to reduce the impacts on environment
during the construction;
• Ensure the safety measures for the workers and local
people during the execution
• Follow all Vietnamese policies in conformity with
sponsor’s requests.
Project operating unit • Operate the project and implement the environment
Drainage and wastewater treatment system project for Thai Hoa town, Nghe An province”
Environmental Impact Assessment (EIA) PCO Consultant, 2010
121
Roles Functions
management and monitoring measures; report the results
frequently to the management unit.
• The wastewater examinating lab of the operating unit of
the treatment plant will be equipped adequate equipments
to quickly examine parameters in pre and post – treatment
wastewater, BOD5, COD and Coliform will be daily
monitored during the operation of the treatment plant.
2. Monitoring units
Nghe An Department of Natural
Resources and Environment
(The Environmental Projection
Branch office) and relevant
special agencies.
• Have the responsibility to follow the environment
management and protection according to the Law of
Environment Protection, 80/CP Decree, 21/CP-ND
Decree of the Government and 05/TT-BTN&MT Circular
• The “Drainage and wastewater treatment project for Thai
Hoa town, Nghe An province” belong to group II, so all
the reports on monitoring and implementing EMP will be
evaluated and approved by the Environment Management
Chamber in conformity with the constitutional framework
of environment management and protection.
• Ensure that the new urban areas and EMP must conform
with the environment regulations
• Inspect the implementation of the regulations, standards
of preventing and repairing the environment degradation
by pollution and other environmental issues during the
construction.
Internal monitoring
Supervise the contractor during the contruction process,
including the implementation of environment management
activities in the environmental action plan
Independent monitoring Supervise independently the implementation of EMP
3.The local authorities, social organizations and community
The People’s Committee of
communes/wards in the project
area
• Support the PMU in constructing the relationship with
community and compensating the site clearance
• Provide information about the relevant issues for Project
Owner in designing and implementing the project
• Ensure the safety, security of the work site in the their
own areas, supervise the implementation of the project
Drainage and wastewater treatment system project for Thai Hoa town, Nghe An province”
Environmental Impact Assessment (EIA) PCO Consultant, 2010
122
Roles Functions
The social bodies of
ward/commune level
• Play the bridge between the People Committe of the
Ward and community
• Support PMU and People Committee of the ward to
encourage the participation of the community in the
process;
• Provide the necessary information about the project so the
people can access and give ideas about the status of the
project area and when the project comes into execution.
Community
• Make suggestions about EMP
• Monitor and supervise the implementation of the
measures to reduce the negative impacts through the
Community monitoring Board (if any)
Nghe An Province’s People
Committee
People’ Committee
Related departments and
organisations
Nghe An Department of Natural
Resources and Environment
Thai Hoa town People’s
Committee _- PMU
Environmental Management
_- PMU
CONSTRUCTION
/OPERATION
ACTIVITIES
Contructor/Pub
lic services
companies -
operation unit
WORLD BANK
Local
government
Public representative
CMC
Figure 0–1 EMS in the implementation of the project
Responsibility
Cooperation
Drainage and wastewater treatment system project for Thai Hoa town, Nghe An province”
Environmental Impact Assessment (EIA) PCO Consultant, 2010
123
5.1.3. Estabilishment of EMP
The EMP of “Drainage and wastewater treatment system project for Thai Hoa town, Nghe
An province” was contructed on the basis of the combination from chapters I, II,III, IV. This
combination is the information about the activities os the project in preparation, construction
and operation time; impacts to environment; measures to reduce the negative impacts; the
costs; schedule; implementers and supervisors
The implementation of the project is to improve and increase the environment quality of the
town, each item of the project is the environment processing work itself whose objects are
rain-water and waste-water. The environment processing works of the project were specified
in chapter I of this report (especially the techical aspect)
The part 5.1.2 – Constructing EMP for the project will only give the most general
information about the activities of the project, the impacts to environment, the measures to
reduce the negative impacts ...as shown in the following table:
Drainage and wastewater treatment system project for Thai Hoa town, Nghe An province”
Environmental Impact Assessment (EIA) - 124 –
PCO Consultant,2010
Table 5.2: EMP of “Drainage and wastewater treatment project for Thai Hoa town, Nghe An province”
TT Impacts /
Issues Source of impacts Mitigation measure
Implementation period
Implementation
unit
Monitoring
unit
I Project preparation period
1 Choosing
receiving body
for treated
water
Surface water source
of the town (Hieu
river)
- Make a survey of current situation of surface water
sources in the project area (Hydrogeological regime,
self-cleaning ability, and stability of the reciving
body).
- Refer to yearly monitoring data of surface water
quality and self-cleaning ability.
- Check surface water quality and compare to
regulation QCVN 14:2009/BTNMT on National
technical regulation on wastewater quality in
order to serve the monitoring of treated water
discharged into surface water source when
opearating the treatment plant.
- Determine discharge locations: we have to consider
the water level, avoid locations at source, especially
where water is taken for domestic use.
Design Design
consultant
Client
2 Design of
treatment
technology
improper water
treatment Process /
treatment tank size
will influence
treatment efficiency
and output water
quality
- Client must select consultant who has experiences
in waste water treatment
- Treatment Technology should be easy to operate
for users, particularly; it must ensure the treated
water meet standards QCVN 14:2009/BTNMT on
National technical regulation on wastewater
quality.
- Process Technology must be Designed based on
the actual conditions of project area ( water
demand, water source characteristics)
- Scale and size of the treatment tank must be
calculated in detail, including the time and
effectiveness of treatment through each treatment
Design Design
consultant
Client
Drainage and wastewater treatment system project for Thai Hoa town, Nghe An province”
Environmental Impact Assessment (EIA) - 125 –
PCO Consultant,2010
TT Impacts /
Issues Source of impacts Mitigation measure
Implementation period
Implementation
unit
Monitoring
unit
process.
3 Safety of
drainage and
wastewater
treatment
works
Choosing locations for
water treatment
constructions,
- Location of water treatment works should be
surveyed in geography, geology, social issues, ...
ensure not threat to the safety of long-term
projects
- Location of wastewater treatment plant need to be
far away 250 m fromresidential area for treatment
technology of biological ponds. This ensures that
noise doesn’t affect inhabitants life.
- Avoid selecting location of wastewater treatment
plant, - wastewater pumping station, pipeline on the
cultivation land of high productivity, especially in
the rice field having 2-3 crops/year.
- Location of WWTP, WWPS, pipeline system of
waste water collection and drainage need to avoid
cultural, historical buildings such as funeral, temple,
church, pagoda, big tree, historical monument, etc.
Environmentail criteria and technical design: Including following items:
+ Water treatment system
- Fence, Warning and safety signing board
- WW treatment system with treatment ponds:
anaerobic pond, falcutative pond, aerobic ponds,
sludge drying yard, etc.
+ WWPS
- Direction of sewer gate, gate and replacement of
pump is optimized to minimize noise
- Anti-insulating plates such as Anti-insulating
Design Design
consultant
Client
Drainage and wastewater treatment system project for Thai Hoa town, Nghe An province”
Environmental Impact Assessment (EIA) - 126 –
PCO Consultant,2010
TT Impacts /
Issues Source of impacts Mitigation measure
Implementation period
Implementation
unit
Monitoring
unit
doors or plating trees
- Sound proofing by planting green trees
surrounding the treatment plant.
- Fire prevention equipments.
4 Trees are cut
down or
damaged.
Loss of arable
land
Land acquisition,site
clearance before
construction period
- Avoid WTP site selection, pipeline system,
WWPS on cultivation land for high yield,
especially in fields where rice can grow well.
- Avoid the design of pipeline along the grown
trees
- Design to plant trees in and around WTP
- Inform so timely to farmers that they can adjust
cultivation time if possible
Design Design
consultant
Client
5 Interruption to
existing
infrastructure
or services
such as
drainage,
power line,
telephone
cables,…
Operation of
transportation
equipment and
materials; digging and
leveling the site.
- Select the reasonable location of pipeline system,
treatment plant, .WWPS.., to avoid disrupting
existing infrastructures
- Design the temporary water pipeline for the
irrigation canals which were disrupted
Design Design
consultant
Client
6 Impacts on
cultural,
historical,
archaeological
sites
Digging and leveling
the site for
construction of WTP
and water supply
pipeline system.
- Select the location of construction of water
treatment plant, wastewater collection sewers
avoiding cultural works, historical graves,
churches, temples, pagodas, trees, historic
monuments, etc.
Design Design
consultant
Client
7 Recover land
for project, site
Policies of
compensation and
- Setup a management board for site clearance
including representatives of the People's
Design
Client (PPMU)
in coordination
Nghe An
PPC
Drainage and wastewater treatment system project for Thai Hoa town, Nghe An province”
Environmental Impact Assessment (EIA) - 127 –
PCO Consultant,2010
TT Impacts /
Issues Source of impacts Mitigation measure
Implementation period
Implementation
unit
Monitoring
unit
clearance resettlement of the
project
- Trees area cut down
or damaged.
- Loss of cultivation
land
Committee at commune level where the project
affected
- Minimize Recover land that has been granted to
households. Try using the land managed by the
commune People's Committee
- Inform people who are effected directly from the
project
- Have reasonable compensation policy for people
with land acquisition
- Avoid selection of water treatment plant, raw
water intake, pipes on the productive farming land.
- Avoid designing the pipelines along the available
trees
- Design trees in and around the water treatment
plant
- in Advance notice to the farmers so that they can
adjust crops.
with PPC and
other unit
II Construction
period
1 Landscape
and ecology
system:
Site clearance,
excavation:
- chage of surface soil
structure and using
target;
- destroy landscape;
- lose beauty;
- chop down tree
- Minimize the cut of trees or affecting the trees
around during clearance and construction.
-Limit the cutting of trees to build camps, gathering
materials.
- Planting trees in affected locations
- Keep the surface soil before digging to be used for
restoration.
- Collecting and authentic materials (trunks, leaves,
...) to handle, or for utilizing as fertilizer, for firing
Construction - Contractor;
- Client;
- Nghe An
DONRE;
- Inepenent
monitoring.
Drainage and wastewater treatment system project for Thai Hoa town, Nghe An province”
Environmental Impact Assessment (EIA) - 128 –
PCO Consultant,2010
TT Impacts /
Issues Source of impacts Mitigation measure
Implementation period
Implementation
unit
Monitoring
unit
...
- suitablly Covering excavated wastes, the materials,
waste ...
- Daily Collecting waste materials, sludge, domestic
waste, .. on the site.
2 Infrastructures
such as water
supply system,
power lines,
telephone
cables, roads
or drainage
cannels…are
damaged
Operation of
transportation means:
- gathering of
materials, parking;
- transporting
materials, soil;
- reasonablly Execute to minimize the impacts
during rush-hours: step-by-step construction
- minimize the impact on roads while gathering
materials and construction;
- Use of construction equipments with proper load,
no damage to existing roads.
- Do not use hook-trailer on paved roads;
- Require the contractor to be responsible for any
damage to any bridge/ road. - Repair the damage
they have caused.
(According to TCVN 4054-98- traffic flow during
rush-hours in the transportation route of materials)
- Coordination with concerned local authorities to
relocate infrastructures if neccessary.
- Inform the local people if having any temporary
cut off of service at least 3 days.
- Drivers must inspect and observe the height of
technical cable wire while driving before driving
under power lines or unloading of materials and
equipments under the cable.
Construction - Contractor;
- Client;
- Nghe An
DONRE;
- Inepenent
monitoring.
3 - Dust and
emissions
From the surface of
backfilling area.
- Excavated soil,
stone, activities of
- Spray water of road regularly (2 times / day) to
reduce dust dispersal to residential areas;
- digging temporarily excavated soil must be
covered appropriately (2 - 3 meter shield, cover…)
Construction - Contractor;
- Client;
- Nghe An
DONRE;
- Inepenent
Drainage and wastewater treatment system project for Thai Hoa town, Nghe An province”
Environmental Impact Assessment (EIA) - 129 –
PCO Consultant,2010
TT Impacts /
Issues Source of impacts Mitigation measure
Implementation period
Implementation
unit
Monitoring
unit
transportation
vehicles.
- Due to burning fuel
of construction
vehicles.
to avoid dust dispersal;
- Use leveled materials with high humidity. Using
sand with humidity from 50-60% for leveling). In
the process of leveling, we also intergrate with
bulldozing land. Reinforced the internal roads to
avoid dispersal of dust from the operation of
means of transportation.
Cleaning vehicle leaving the area of construction;
shield the vehicles to avoid dust and scatter material
on the road;
Clean the road daily.
- Only use vehicles and vehicles with low exhaust
emissions than permitted standards;
- Maintenance of vehicles and equipment frequently
(monthly);
Do not burn waste on site;
- Do not store the odor waste in the densely
populatation areas;
- Workers should carry the labor protective clothing,
masks, masks ...
- Monitoring the quality of air pollution by dust and
emissions during construction.
monitoring.
4 Noise an
Vibration
- Construction means
such as excavator,
pump, concrete mixer,
transportation
vehicles…
- Check the noise of the devices, if the noise exceds
the allowance, install equipments to reduce sound or
stop using;
- Only operate well maintained equipments;
maintain equipment during construction. Do not use
the old equipments which are outdated and high
noise.
Construction - Contractor;
- Client;
- Nghe An
DONRE;
- Inepenent
monitoring.
Drainage and wastewater treatment system project for Thai Hoa town, Nghe An province”
Environmental Impact Assessment (EIA) - 130 –
PCO Consultant,2010
TT Impacts /
Issues Source of impacts Mitigation measure
Implementation period
Implementation
unit
Monitoring
unit
- Plan reasonable use of vehicles to limit noise in
rush- peak hours.
- Use and maintenance of equipment and shielding
to reduce noise, turn off the machine if necessary.
- The machinery such as livestock machine, ironing
machine, hammer machine, excavators, drilling
machines ... causing much noise will not be operated
at night to avoid the impact on human activities and
surrounding areas.
- Reduce noise by planting trees, ensuring a clean
environment; just one can reduce the spread of noise
to the surrounding environment.
- Equipment for construction workers and labor
protection means to prevent noise, vibration.
- Monitoring noise during the construction.
- water pump plan should avoid sensitive time for
noise, if possible
- Use the elastic structure to reduce vibration such as
the oil shock box, knee elastic metal, the metal
elastic cushion, pillow elastic rubber, is mounted
between machines ... and plant stands, and be
periodically inspected or instead.
- Digging holes pour the sand around the area pilling
to limit the spread of vibration.
5 Waste water - overflow water in
the construction site
- domestic waste
water of workers
- Allocate drainage ditches around the construction
area to collect overflow rainwater and sedimentation
pits before leading into the general sewer system;
- Provide 01 public toilet in each route to collect and
store waste water: use casted RC septic tanks - 2 pits
Construction - Contractor;
- Client;
- Nghe An
DONRE;
- Inepenent
monitoring.
Drainage and wastewater treatment system project for Thai Hoa town, Nghe An province”
Environmental Impact Assessment (EIA) - 131 –
PCO Consultant,2010
TT Impacts /
Issues Source of impacts Mitigation measure
Implementation period
Implementation
unit
Monitoring
unit
(mobile).
6 Solid Waste -Construction and
-domestic waste
- Using excavated soil to fill in some areas of
construction;
- Solid waste is stored temporarily in sludge pits
must be covered to reduce the concentration of
dispersed waste, odors, dust into the environment;
not to obstruct traffic and loss of regional beauty;
- Solid wastes are disposed off daily (from 1-2
times/day, depending on the volume of waste);
- Do not burn waste on site;
- Clean up solid waste and wastewater, before
closing
Construction - Contractor;
- Service
contract unit
- Client;
- Nghe An
DONRE;
- Inepenent
monitoring.
7 - Safety and
community health:
+ environmental
problems
traffic safety;
- labor safety;
- burning/ explosion
- local flood on site
+ labor accidents, .,…
- Comply with safety regulations during
construction;;
- Maintain the emergency department on site;;
- There are reasonable plans to mobilize a car, avoid
traffic stuck; prohibit speeding when driving
through residential areas.
- making fence, barrier, warning of dangerous
signing board
- Provide safety and appropriate equipments/ tools
such as protective clothing as well as ensuring the
application of safety measures for construction;
- set up program of examination and following of
health periodically for the workers and operators of
WWTP.
- Set up reasonable temporary rain and waste water
drainage routes at construction area;
Construction - Contractor;
- Service
contract unit
- Client;
- Nghe An
DONRE;
- Inepenent
monitoring.
Drainage and wastewater treatment system project for Thai Hoa town, Nghe An province”
Environmental Impact Assessment (EIA) - 132 –
PCO Consultant,2010
TT Impacts /
Issues Source of impacts Mitigation measure
Implementation period
Implementation
unit
Monitoring
unit
- Make used of existing drainage ditches, , ponds ...
in the surrounding area.
- exame the worker’s health every 6 months
8 Effects for the
cultural,
historical,
archaeological
works
Excavation and
levelling on PS,
WWTP and WW
pipeline network
This does not exist in the subproject of 3 Thai Hoa
communes because the WWTP and pipe network are
all agricultural or public land without cultural,
historical and archaeological works, managed by
the CPC. In case unknown archaeological objects
are found during construction phase, act following
chance findings procedures described below:
- If cultural artifacts are uncovered the Contractor
must stop work at the site, secure the site and
inform the supervision Engineer.
- The Contractor should arrange with the Engineer
to move his activities to another site.
Construction works at the site where objects were
found only be resumed at permission of PPMU.
- The Engineer will inform PPMU, the one who
inform the provincial Department of Cultural,
Sports and Tourism (DCPS).
Officer from DCPS will inspect the side, evaluate
the importance of the objects found and decide on
the next steps. .
If graves discovered in the digging, notify the
PPMU. PPMU will coordinate with local authorities
to notify people in the village for at least two weeks
in advance to move. If people realized their tomb,
project will support and create conditions for them
to relocate. If many tombs found, draw diagrams of
Construction - Contractor;
- Client;
- Nghe An
DONRE;
- Inepenent
monitoring.
Drainage and wastewater treatment system project for Thai Hoa town, Nghe An province”
Environmental Impact Assessment (EIA) - 133 –
PCO Consultant,2010
TT Impacts /
Issues Source of impacts Mitigation measure
Implementation period
Implementation
unit
Monitoring
unit
the tombs location before moving and
documentation which notes clearly each tomb’s new
position. These records must be kept in the CPC.
9 Implementation of environmental observation and monitoring (air, waste water, surface
water, solid waste,...) during the construction period.
Time proposed
in the EMP
Contractor,
consultant
- Client;
- Nghe An
DONRE
III Operation period
1 Bad odor,
toxic gas
- Noise,
vibration
from
operation of
machinary,
equipments in
the TP
Operation of pump
and wastewater
treatment technology .
- Use of vehicles and machinery operating in
accordance with Designed standard and capacity;
- Periodically maintain pumps and treatment
equipments according to prescribed standards
- Fully equip labor protection for operators.
- Set water pump plan to avoid sensitive time
- Maintain buffer zones and green belts / grass
around the treatment plant;
Operating the
WWTP
– Project
operation unit;
- Consultant (if
any
- Client;
- Nghe An
DONRE;
-
Indepenent
monitoring.
2
Sludge
Sludge collected from
the biological ponds.
- Periodically sucking sludge to sludge drying bed
(2-3 months); Periodically dredging wastewater
collection manholes.
- Each province can use a dedicated car for
collecting dried sludge at water treatment plant to
landfill for treatment.
- If the condition does not allow, we can arrange a
private waste area and grow some plants to collect
the pollutants, especially heavy metals (spinach,
water-fern, bindweed..). However, these plants
must then be handled as hazardous solid waste
Operating the
WWTP
- Project
operation unit;
- Consultant (if
any
- Client;
- Nghe An
DONRE;
-
Indepenent
monitoring.
3 Environmental Safety for operators - Monitor ing the operation of the WW treatment Operating the - Project - Client;
Drainage and wastewater treatment system project for Thai Hoa town, Nghe An province”
Environmental Impact Assessment (EIA) - 134 –
PCO Consultant,2010
TT Impacts /
Issues Source of impacts Mitigation measure
Implementation period
Implementation
unit
Monitoring
unit
problems,
labour safety
Fire and explosion
Flooding and
inundations at the
WWTPs
plant and the treated water quality regularly
(monthly), to ensure meeting class B, QCVN
14:2008/BTNMT.
- Countermeasures in case stop operating when
pollution content parameters exceed the allowable
limit of the treated water. Ventilating or open
manhole cover when carrying out the dredge.
- Providing safety equipments and proper tools
and protective clothing as well as ensure the
application of safety measures for
construction;
- - Training, training in hygiene and labour
safety, fire prevention and fighting for
personnel to operate the wastewater
treatment plant periodically twice a year
- Periodical health check 06 months / time for
operators;
- Establish regulations on environmental
protection, fire prevention and fighting for
treatment plant.
WWTP operation unit;
- Consultant (if
any
- Nghe An
DONRE;
-
Indepenent
monitoring.
6 Implementing the observation, emvironmental monitoring (surouning environment, -
Obsering the wate quality of Hieu River when operating the WTP.
Time proposed
in the EMP
Contractor,
consultant
- Client;
- Nghe An
DONRE
Drainage and wastewater treatment system project for Thai Hoa town, Nghe An province”
Environmental Impact Assessment (EIA) - 135 –
PCO Consultant,2010
5.2. ENVIRONMENT MONITORING PROGRAM (EMP)
EMP is one of the vital tools in environment management. It is the combination of scientific,
technical, technological methods and organization to control, monitor strickly and
systematically the environment alteration trends. EM also help control the sources of diposal
which causes pollution, adjust the manufacture plan and reduce the impact, regulate the costs of
pollution mitigation and processing and protect the environment effectively. EM plays a part in
the evaluation of accuracy of the environment impact forecasts which were mentioned in the
EIA report of the project.
For the project, the target of EM is to timely find out the negative impacts on environment
and propose the measures to prevent and reduce pollution. In other hand, environment quality
monitoring also ensures the safe operation of wastewater treatment plant. ESP program is
focused specifically in monitoring each subject: (1) Monitoring of waste, (2) Monitoring the
surrounding environment, (3) others such as monitoring of the depression, , traffic, socio-
economy which are presented as follows:
(1) Monitoring waste
Due to the construction of works and the emission sources of drainage and wastewater
treatment system of Thai Hoa town, Nghe An province when it comes into operation, waste is
generated primarily during the construction and operation of the project (the preparation
period has no waste). Monitoring of waste, including monitoring the total volume /
wastewater flow and monitoring pollution parameters characterizing the generated waste.
(2) Monitoring surrounding environment
The process of construction and operation of the project also causes impacts on the
surrounding environment, affecting the lives and health of communities around the project area,
so monitoring the quality of the surrounding environment is also one important factors in any
investment project.
Based on the analysis of adverse impacts on the surrounding environment mentioned in
chapter III, in addition to the measures proposed to minimize adverse environmental impacts,
the surrounding environmental monitoring program for the project during the construction and
operation period will contribute actively to ensureing environmental safety during project
implementation.
(3) Others
In addition to monitoring waste and surrounding environment, the construction and
operation periods of the project should also pay attention to monitoring some other related
factors such as erosion, landslides, depression, health and labor safety, social-economy,
community’s complaints about nuisance and environmental impacts, ...
Futhermore, during the implementation of the project, the World Bank will have an
independent supervisor (to supervise the execution of mitigation measures of the Project
Owner as committed in the EIA report) and survey, monitor environmental quality criteria to
compare with the current background environment to see the level of violation in causing
environmental pollution during the execution of the project and deal with these violations.
Drainage and wastewater treatment project for Thai Hoa town, Nghe An province”
Environmental Impact Assessment (EIA) - 136 –
PCO Consultant, 2010
For independent environmental supervisor for each stage of the project, when
violations are discovered, non-compliance with environmental protection, environmental
pollution caused by contractors during construction period and by operation and mangement
unit during O&M period, requirements are needed:
(i) Contractor/O&M unit are required to follow mitigation measures and ensure
quality of environment as committed;
(ii) In case the contractor does not follow requirements, the independent supervisor
will inform the Project Owner as Thai Hoa People’s Committee to give timely
solutions together with the intervention of competent agencies, sponsor as
stated above.
The Project Owner may cancel or terminate the contract with the contractor if he does
not follow mitigation measures as well as ensure the environmental quality as committed.
5.2.1. Environment monitoring plan
a) Air quality and Noise Monitoring
* Objectives of monitoring of AQ and noise:
− Observe the concentration of the air pollution subtances originates from the
activities of the construction of the items; in and out the wastewater treatment
plant when it operates;
− Early notice the increase in the volume of subtances which cause air and noise
pollution to have the urgent reducing measures.
* Monitoring locations of the AQ, noise
− Focus on the safety issues in the construction period. The contractor need to
measure and observe the quanlity of atmosphere and noise in the construction
areas and surrounding resident areas…
− In the operation period, it is necessary to supervise the quality of atmosphere in
the positions of the processing assembly where the noxious gas and noise were
born (these positions already mentioned in chapter III), supervise and observe the
air and noise quality in the surrounding residential areas.
* Environmental parameters that need AQ and noise monitoring
+ Parameters in construction period:
− Meteorology: temperature, humid, wind speed, wind direction
− Suspended articles
− Noxious gas: CO2, SO2, No2
− Noise (dBA): instant noise and Octa range noise
+ Parameters in operation period
− Meteorological: temperature, humid, wind speed, wind direction
− Noxious gas: CO2, SO2, No2, H2S, CH4, NH3;
− Suspended articles
Drainage and wastewater treatment project for Thai Hoa town, Nghe An province”
Environmental Impact Assessment (EIA) - 137 –
PCO Consultant, 2010
− Noise (dBA): instant noise and Octa range noise
*Monitoring frequency of AQ and noise
+ Monitoring frequency in construction period
- At waste discharing source (in construction area) : Once per 3 months;
- At the surrounding area : once per six months
+ Monitoring frequency in operation period
- At the waste discharging source (the treatment plant and wastewater pumping
station): once per three months
- In the surrounding area: Once per 6 months
*Regulations of sample analysis and applicable standards
- QCVN 05:2009/BTNMT – National Technical Regulation on ambient air
quality
- QCVN 06:2009/BTNMT – National Technical Regulations on some hazardous
substances in ambient air..
- TCVN 5949:1998 - Noise in public areas and residential areas, the maximum
allowable noise level.
- TCVN 6962:2001 - Vibration and shock. Vibration caused by construction
activities and industrial production. Maximum levels permitted for industrial and
residential..
- Decision No. 3733/2002/QD-BYT of the Ministry of Health issued on
10/10/2002 regarding the application of 21 occupational sanitation standards.
b) Water quality monitoring (WQM):
* Objectives of WQM:
Objectives of the water quality monitoring system for this area is to monitor
components of wastewater and impact of discharging water after treatment to the surface
water source of Hieu River – Thai Hoa town.
* Location of WQM:
WQM is implemented all discharing souces in wastewater treatment plant and water in
surrounding. WQM is devided into 2 kinds: WQM after treatment and WQM of waste
receiving to change in operation
- During the construction period of the project: it is necessary to observe and
monitor surface water, wastewater in the construction area and the surrounding
area.
- During the operation period: The treated wastewater from treatment plant,
monitoring the surface water quality in receiving source after treatment of the
treatment plant and surrounding area (water in Hieu River).
*Environmental parameters that need to be supervised
Drainage and wastewater treatment project for Thai Hoa town, Nghe An province”
Environmental Impact Assessment (EIA) - 138 –
PCO Consultant, 2010
- Analized norms for surface water: temperature, pH, TDS, SS, DO, COD,
BOD5, total nitrogen, total phosphorus, sunfat, Coliform.
- Analized norms for treated water:, pH, BOD5, TDS, TSS, total P,
Coliform.
*Monitoring frequency
+Monitoring frequency in construction period
- At the generation source (the construction area): once per 3 month.
- Around the construction area : once per 06 months
+Monitoring frequency in operation period
- At generation source (at the treatment plant and wastewater pumping station):once
per 06 months.
*Sample analysis regulations and applicable standards
The parameters of outlet water quality of the treatment plant are sampled. These
norms are analized according to Vietnamese and international standards.
− QCVN 14: 2008/BTNMT: National technical regulation about domestic
wastewater quality;
− QCVN 08: 2008/BTNMT: National technical regulation about surface
water quality;
c, Monitoring the amount of generated waste and sludge
*During the construction period
The amount of waste and sludge generated is not big, mainly from the activities of the staff
and workers at the project area. This amount is collected daily then transported by Thai Hoa
town URENCO.
*During the operation period
According to the calculated figures, the amount of waste, sand, sludge generated at the
screens, biological ponds is rather big. Therefore, it is necessary to have the daily monitoring
program to find out and process timely the overloading problems. Signing the commercial
contract with the Thai Hoa town URENCO to collect waste from screens, gathering site and
sludge in the treatment plant constantly and periodically.
(1) The environmental parameters that need to be supervised (mainly with deposit)
The norms that need to be analized: humidity, total nitrogen, total
phosphorus, amoni, sunfat, Cr6+
, Pb, Zn, micro organism, total oragnic
(2) Monitoring frequency
Sludge is monitored once per three months.
Drainage and wastewater treatment project for Thai Hoa town, Nghe An province”
Environmental Impact Assessment (EIA) - 139 –
PCO Consultant, 2010
5.2.2. The proposed environmental monitoring program for the project.
The program of monitoring the disposal, surrounding environment and other supervisions for
the ”Drainage and wastewater treatment projcet for Thai Hoa town, Nghe An province” is
mentioned in the following table:
Table 5.3: Environmental monitoring program
No Monitoring
norms
Monitoring activities Monitoring
duration
Applied standards
A CONSTRUCTION PHASE
A.I WASTE MONITORING
1 The parameters
of dust, exhaust
fumes
Monitoring dust, exhaust fumes
at construction area
Once/03
months
QCVN
05:2009/BTN
QCVN
06:2009/BTNMT
2 Construction
disposal,
excavation soil
Monitoring the total amount of
dug earth, disposal from
construction activities
(components, mass, leave-out and
processing)
Once/03
months
TCXDVN 261-2001;
The contract’s terms
and agreement with
the bidders
3 Noise,
vibration
Monitoring the noise in the
places where the noise comes out.
Once/03
months
TCVN 5948-1998
A.II SURROUNDING ENVIRONMENT MONITORING
1 Surrounding
atmosphere
environment
Monitoring the air quality in the
”hot spot”
Once/06
months
QCVN
05:2009/BTN
QCVN
06:2009/BTNMT
2 Hydraulic
environment
(wastewater,
surface water,
underground
water)
Monitoring the quality of the
wastewater, surface water
surrounding the construction area
(especially in residential areas,
the drainage catchment near the
project)
Once/06
months
QCVN 14: 2008;
QCVN 08: 2008;
TCVN 6772-2000;
QCVN
01:2009/BYT;
QCVN 09: 2008.
3 Noise Monitoring the noise in the
sensitive spots around the
construction area
Once/06
months
TCVN 5949-1998
4 Inland and
hydraulic
ecosystem
Clarify the received water quality
and ecosystem – monitoring the
plants and basic creatures
Once/06
months
The terms in the
contract
The correspondent
Vietnamese
standards about
earth and water
quality
A.III OTHER MONITORING ACTIVITIES
1 Depression Monitor the depression in the
treatment plant
Once/06
months
2 Transportation Monitor in accordance with the
transportation management plan
and Monitor stricky the time of
Once/06
months
The contract’s terms
defined by the
Transportation
Drainage and wastewater treatment project for Thai Hoa town, Nghe An province”
Environmental Impact Assessment (EIA) - 140 –
PCO Consultant, 2010
No Monitoring
norms
Monitoring activities Monitoring
duration
Applied standards
execution management plan
which were verified
by the Department
of Natural Resources
and Environment,
The Department of
Transportation.
3 Health and
safety
- Periodically examine the health
of the staff and workers
- Examine, supervise the
implementation of the regulations
about hygience, labour safety
(labour protection, warning
signs...)
Once/06
months
according to
the general
requirements
Decision No
29/1999/QD-BXD;
Decress No
07/1999/TT-BXD;
Decision No
64/2003/QĐ-TTg.
4 Community
feedback
Supervise the complaints of the
community about the
inconveniences and the impacts
on environment in the
construction phase
06 times/total
construction
time
B OPERATION PHASE
B.I Waste monitoring
1 The quality of
water in and
out the
treatment plant
Supervise the water in and out the
treatment plant through the
parameters: BOD/COD and
coliform to clarify the degree of
pollution and contammination.
Onsite supervise the values of
TDS,TSS, etc.
Once per 03
months
QCVN 14: 2008;
QCVN 08: 2008;
TCVN 6772-2000;
QCVN
01:2009/BYT;
QCVN 09: 2008;
2 Wastewater
flow
Continuously supervise to define
the design capacity estimates of
the wastewater treatment plant
Once per 03
months
QCVN 14: 2008;
TCXD 188-1996;
3 Deposit from
the treatment
plant
Supervise the processing and
transporting the sludge
-Supervise the typical pollution
parameters
Once per 03
months
Contract of
operation
Contract of sample
analysis
4 Smelling from
the treatment
plant
Supervise the odour at the surface
points of the important
infrastructures: WW pumping
station, wastewater treatment .
Once per 03
months
QCVN
05:2009/BTN
QCVN
06:2009/BTNMT
5 Noise,
vibration at the
treatment plant
Supervise the noise, vibration at
the wastewater treatment plant,
wastewater transferring pumping
stations
Once per 03
months
TCVN 5948-1998
B.II SURROUNDING ENVIRONMENT MONITORING
1 The
surrounding
atmosphere
environment
The surrounding residential areas,
the wastewater pumping station
06
months/time
QCVN
05:2009/BTN
QCVN
06:2009/BTNMT
Drainage and wastewater treatment project for Thai Hoa town, Nghe An province”
Environmental Impact Assessment (EIA) - 141 –
PCO Consultant, 2010
No Monitoring
norms
Monitoring activities Monitoring
duration
Applied standards
2 Water
environment
(wastewater,
surface water)
Monitoring the quality of
wastewater, surface water
surrounding the wastewater
treatment plant to determine the
pollution, leakage.
06
months/time
QCVN 14: 2008;
QCVN 08: 2008;
TCVN 6772-2000;
QCVN
01:2009/BYT;
QCVN 09: 2008;
3 Noise Supervsise the noise in the hot
spots near the treatment plant (
the nearby residential areas)
06
months/time
TCVN 5949-1998
4 Inland and
hydraulic
ecosystems
Clarify the received water quality
and ecosystem – monitoring the
plants and basic creatures
06
months/time
The terms in the
contract
The correspondent
Vietnamese
standards about
earth and water
quality
B.III Other surpervising
1 The flood
controlling
measures
Supervise the conditions of the
drainage system and define the
place of water storage.
Rainny
reason
Decision No
752/QD-TTg
2 Health and
safety
- Periodically examine the health
of the staff and workers at the
wastewater treatment plant.
- Check out the implementation
of the regulations about hygience,
labour safety and fire fighting
06
months/time
Examine
according to
the
requirements
Decision No
29/1999/QD-BXD;
Decree No
07/1999/TT-BXD;
Decision
64/2003/QĐ-TTg.
3 Socio-economy Supervise the drainage fee
collecting in the town when the
wastewater treatment system
comes into life.
- Supervise the factors which
have negative impacts on local
socio-economy
06
months/time
According to the
general regulations
about drainage fee
approved by the
People Committee
of Thai Hoa town
4 Community
complaints
Supervise the complaints of the
community about the
inconveniences and the impacts
to environment when operate the
wastewater treatment plant.
06
months/time
Following the
contract’s conditions
Remark:
1. Applied standards
- Apply standards, regulations of Viet Nam as proposed in the section
5.2.1.Environment monitoring plan and section 2.2. Standards and regulations applied.
2. The positions to supervise environment quality
Drainage and wastewater treatment project for Thai Hoa town, Nghe An province”
Environmental Impact Assessment (EIA) - 142 –
PCO Consultant, 2010
The positions to supervise environment quality in the operation phase in terms of measuring,
analizing points and coincide with the sampled positions will be described in the base
environment status – chapter II of this report.
2. Cost estimation for environmental monitoring:
- Environmental mointoring cost of the construction period estimated is
70.000.000 VNĐ/period/the whole criteria as recommended above. This cost is
the budget of investment total of project.
- Environmental mointoring cost of the operation period estimated is 50.000.000
VNĐ/period/ the whole criteria as recommended above. This cost will be a part
of income from wastewatse dischage fee and allowance of local budget for
WWTP operation, especially for the first operation year.
Figure 14. Digrame of environment monitoring location
5.3. CAPACITY BUILDING
Raising awareness of the people
- The specialists are sent to receive training on protecting the environment and
preventing explosion.
- Holding the propaganda, education events about environment protection (collect,
process the waste, wastewater and hygience), labour safety (follow the labour safety
regulations..) during the execution of the work items and operation of wastewater
system for staffs, workers and operators in Thai Hoa town.
- Contruct the regulations about environment protection and fire fighting for the
treatment plant, including:
- Timely encourage the technical improvements, research works which have value in
increasing productivity, saving materials, protecting the environment and decreasing
the price
Education, training on environment and labour safety
- Education, training on environment and labour safety will increase the
competence for different target groups of the project. This will ensure the
implement of the measures to reduce the negative impacts to environment
from the bidders and wastewater treatment operating unit, specificially:
- For the Project Management Unit (PMU): higher training on monitoring
environment observation and reporting
- For the bidders: training on applying environment management plan on work,
carrying out reducing measures and observation reporting.
- For the community: the representatives of the community who are the people
in charge of environment monitoring will be trained to observe the impacts to
the environment, be informed to improve the awareness of environment and
be trained on maintainance the work during the utilization.
Drainage and wastewater treatment project for Thai Hoa town, Nghe An province”
Environmental Impact Assessment (EIA) - 143 –
PCO Consultant, 2010
- For the staffs, executing and operating workers: will receive training,
information about hygience and labour safety.
Table 7: Training cost for enhancing capability of environmental safety and protection.
Content Requirement Cost estimation Amount
(VND)
Construction period.
1 Training environmental staff
of the PMU and contractors.
Number of
participants: 5
1,000,0000
VND/person
5.000.000
Hire consulting
expert: 01
3,000,000
VND/person
3.000.000
Operation period
1 Training environmental staff
(environmental monitoring
and writing report).
Number of
participants: 2
1,000,000
VND/person
2.000.000
Hire consulting
expert: 01
3,000,000
VND/person
3.000.000
2 Visit and learn experience of
environmental protection
Number of
participants : 03
1,000,000
VND/person
3.000.000
Total 16.000.000
Drainage and wastewater treatment project for Thai Hoa town, Nghe An province”
Environmental Impact Assessment (EIA) - 144 –
PCO Consultant, 2010
CHAPTER VI:
PUBLIC CONSULTATION
6.1. OBJECTIVES OF PUBLIC CONSULTATION
The overall target of community consulting is to study the community’s interest of the project,
especiall ones who is directly affected by the deployment and operation of the project. In this
foundation, those interests will be reasonably deal with even in the phase of preparation,
option selecting, designing and constructing the measures to reduce the negative impacts on
environment and community’s health... The targets of community consulting consist of:
- Ensure that the local authority as well as the representatives of the affected households
will have their voices in the phase of planning and pre- decision making of the authority’s
approval.
- Share the information about the items, the planned activities of the project with the
relevant parties, especially the affected people.
- Help the organizations and individuals aware of the necessity of the project, the project
development as well as other requirement and purposes of environment impact evaluation.
- At the same time, hold the events of information spreading, environment consulting,
compensation polycies, site clearance and other relevant activities.
- Listen to the ideas and interests of the community in the project, especially the direct
impacts on the life of community
- Enhance the participation of the community, bring about the chance for the direct and
indirect affected people express and suggest their ideas.
- Have the participation of the community in direct seminar. Then, improve, settle down
their disputes, suggest the technological option, suitable reducing measures,..., deal with
the disputes arose from community side about environment protection issues.
- Define the resonability and legitimacy of authority’s decisions, respond the demand of
people, consider the proposal of local community and authority.
6.4. METHOD AND ORGANIZATION OF PUBLIC CONSULTATION
The method of spreading information and consulting community includes the method of quick
assessment and the method with the participation and consulting of relevant partners and use
the methods as follows:
- Deep interview (direct interview): Organize the dialogues, meeting and discussion with
local people and authoirity. The consultant supporting the Project Owner had some deep
interview with some household’s representatives and key staff (chairman, vice chairman
of people’s committee, statistical staff, land survey staff, etc) of wards, communes in the
project area during the socio-economic survey in Thai Hoa town in March, 2010.
- Gather information for questionaire survey (indirect interview) : Give the survey
questions to the local people and authority. Similar to the above, the consultant delivered
the questionaire to representatives of some households and local authority to get their
opinions.
Drainage and wastewater treatment project for Thai Hoa town, Nghe An province”
Environmental Impact Assessment (EIA) - 145 –
PCO Consultant, 2010
- Group discussion: The Consultant, the Project Owner had 2 periods (in March and June ,
2010) to organize the consultation meeting with representatives of some households,
institutional organizations and local authorities, etc with approximately 30 people in one
meeting. By applying the method of participatory assessment (MPA), opinions were
collected for the project: step 1 – the first environmental consultation about current status
of environment in the project area, priorities for environmental improvement, concerned
issues of local authority and households may affected due to the construction of project
works ; Step 2 – The second environmental consultation abouth draft EIA report of the
project to receive opinions and agreement for the project implementation.
(Details of minutes of community consultation meeting, questionaire surveys mentioned
above are attached in the annex of the EIA report)
According to the regulations of the Decree 05/2008/TT- BTNMT issued on 08/12/2008 of the
Ministry of Natural Resources and Environment about ” Guiding to evaluate the strategic
environment, environment impacts and commitment to protect the environment”, there are 2
objects that need to consult when reporting:
(1) The People Committees at ward/commune level
(2) The Fatherland Front Committee at ward/commune level
The PMU of the Drainage and wastewater treatment project for Thai Hoa town
(representative of the Project Owner is Thai Hoa commune People’s Committee) co-ordinate
with the PCO – the consultant for preparing EIA organizes to consult People Committees and
Fatherland Front Committee of wards/communes in the project area.
Letter No. 317/UBND-TNMT dated 12/08/2010 sent to People Committees and
Fatherland Front Committee of wards/communes with the main contents of notifying the
basic contents of the project badly affecting environment and mitigation measures will be
applied during the implementation process of construction and operation of the project.
Commit to comply with regulations, norms and standards of current law of Viet Nam.
6.3. PUBLIC CONSULTATION RESULTS
6.3.1. Consultation results of the affected people
The consultation results of the affected people in the communes/wards in the project area are
shown in the table below:
Drainage and wastewater treatment system project for Thai Hoa town, Nghe An province”
Environmental Impact Assessment (EIA) - 146 –
PCO Consultant,2010
Table. Public consultation results of the affected people
Form Location Discussion issues Considerations in the design Replies of the Project Owner (Thai
Hoa town People’s Committee)
I Public consultation of the step1 :
1 Interview local
residents/group
discussion
(3/2010)
6
wards/communes
of Thai Hoa
town : Hoa Hieu,
Long Son, Quang
Phong, Quang
Tien ward ; Nghia
Tien, Nghia My
commune.
- Current status of
infrastructure, water
supply, drainage, solid
waste management,
environmental
sanitation.
- Screening impacts that
may occur during
construction process
such as dust, noise,
waste water, solid waste
and traffic congestion.
- Consulting about
mitigation measures
from communities.
1. Current environmental conditions:
6 wards/communes agreed to support
the project because they realize the
benefits of improving draiange and
sanitation system of the project.
2. Impacts and mitigation measures
during construction period: In
addition, wards/communes giving
some opinions as follows:
+ The construction should be
implemented quickly.
+ Before land acquisition, it needs to
make appropriate compenstation for
people losing their agricultural
production land in Long Son and
Nghia Tien commune.
+ The site will be returned after
completion of the construction.
+ Avoid affecting the surrounding
local residents.
+ The contractor should minimize
noise, dust during construction and
rush hours.
+ Traffic signs must be prepared to
avoid congestion.
3. Impacts and mitigation measures
during operation period:
+The Feasibility Study report has clearly
stated the project implementation
schedule and construction measures to
avoid the delay.
+ Reasonable compensation for affected
households when carrying out the land
acquisition has been clearly stated in the
RP report on the basis of laws, decrees
and policy framework of the project, the
World Bank
+ Commitment the site will be returned
as the original state after completion
+ The report has proposed measures to
minimize impacts on surrounding
residents by: noise, dust, traffic, safety
signs, reasonable traffic flow division,
etc.
+ Operation: measures to reduce odors
have been proposed: distance from
residential area > 200m, as prescribed,
planting trees in the treatment plant,...
+ Sludge is treated after transportation
and dumped as prescribed.
Drainage and wastewater treatment project for Thai Hoa town, Nghe An province”
Environmental Impact Assessment (EIA) - 147 –
PCO Consultant, 2010
Form Location Discussion issues Considerations in the design Replies of the Project Owner (Thai
Hoa town People’s Committee)
All wards agreed with mitigation
measures during the operation phase.
2 Multi-sectoral
approach:
Sending
questionairies to
the local
-
Questionairies:
The affected
people in 6
wards/commun
es.
- Available
information
collection table
for the local
leader.
1201
households :deliv
ered with socio-
economic
questionaires.
6
wards/communes
were delivered
with the available
information
collection table
about natural,
socio-economic
conditions and
issues on water
supply, drainage
and sanitation.
- Current situation of
water supply, drainage
and sanitation.
Current situation:
- Water supply: about 34.9%
households in the project are use tap
water.
- Drainage: 68.2% of households
confirmed that local inundatins
occurred in the residential area;
56.2% said that there are only dug
small ditches; 66.7% said that
wasatewater from sanitation works of
households goes directly to garden.
- Environmental sanitation: 40.1% of
households have septic tanks, the rest
have unsanitary toilets, the efficiency
of wastewater collection only reached
about 40% of the waste volume
generated, mainly households burn
and burry in their garden,
representing 59.2%.
Data, information about this situation is
reviewed during the designing and
preparing the project.
II Public Consultation of the step 2
3 Group
discussion
The second group
discussion in June
of 2010 in 6
wards/communes
in the project
area.
- The draft EIA report.
- Mitigation measures
according to local
opinions.
- EIA draft report: All participants of
meetings agreed to the contents of
report: current situation, contents of
the project, impacts and mitigation
measures, ect.
- Mitigation measures/technical
+ Acknowledge and add in the EIA report
for submission to the competent
authorities for approval.
+ Commitment to carrying out the
mitigation measures proposed
+ Commitment to dissemination of
Drainage and wastewater treatment project for Thai Hoa town, Nghe An province”
Environmental Impact Assessment (EIA) - 148 –
PCO Consultant, 2010
Form Location Discussion issues Considerations in the design Replies of the Project Owner (Thai
Hoa town People’s Committee)
About 15 – 20
persons/meeting.
Applying the
participatory
assessment
method (MPA)
solutions must ensure the following
requirements:
+ Ensuring requirements on
technique, emission gas, vibrations.
+ Building and return promptly to
minimize travel and impacts on the
local life.
+ Avoid damaging sidewalk, existing
infrastructures: transportation,
electricity, cable, etc.
+ Dissemination of information about
contractor and the construction site,
contact unit is needed so that the
local people may reflect issues
relating to environmental safeguard
to the relevant stakeholders.
+There should be sanctions or fines
against the contractor deliberately
repeat violations of environmental
safeguard.
+ However, they are not clear about
the actual impacts when the plant is
put into operation. Most of them
concern about the impacts of the
operation period such as bad odor,
flies, insects and bacteria from sludge
caused, especially in the rivers.
information to local communities during
the project implementation.
(Details of MoM enclosed in the annex of the EIA report.)
Drainage and wastewater treatment system project for Thai Hoa town, Nghe An province”
Environmental Impact Assessment (EIA) - 149 –
PCO Consultant,2010
6.3.2. Results of local authorities consultation.
Comments to the group of specialists of the Consultant,PMU, Fatherland Committees,
Peoples’ Committee of wards/communes in Thai Hoa town with the main contents as follows:
- The People Commitees, the Fatherland Front Commitees of the ward in the project
area supported the implementation of the project. There, the project staff and
consultants gave information about the project, propagandized about the purposes and
benefits of the project- when the project complete, the people will live in a healthy
environment, less pollution, and hygience.
- The locals will provide every good conditions, support the implementation of the
project, especially the land taking-back in the phase of site clearance and the phase of
constructing the work’s items
- Through the EIA report, the People Commitees and the Fatherland Front Committees
agreed with the issues stated in the report. The impacts of the projects mostly are
positive. However, in the phase of deploying, especially in the construction period of
work’s items, there are certainly some impacts on environment and the lives of local
people.
- Suggest the Project Owner undertake to reduce the negative impacts caused by the
implementation of project as well as the environment quality management anf
observation
- The Fatherland Commitees and the People Committees are willing to coordiante to
settle down the issues in the phase of deploying the project.
(Detaisl of these decrees are attached in the appendix of this report)
6.6. DISCLOSURE
Beside the community consultation, the information popularization in the project area
is also very important. According to the environmental safety policies regulated by WB, the
Client/ project steering board/project preparation board must popularize all the project
information to the community. Thus, the Thai Hoa town project also requires community
consultation, information popularization.
Project Steering Committee / Board to prepare projects has to confirm with the bank
that the final EIA report (in Vietnamese) was announced to the locals uring the project
preparation. Also the environmental reports must also be sent to the Vietnam Development
Information Center (VDIC) for storage and information. The notification of the environmental
Impact assessment report must be conducted before implementing the project.
On that basis, the environmental protection commitment for the projects in Thai Hoa
town will be conducted as follows:
• To be exhibited publicly at the offices of Nghe An Provincial People's Committee
with: (1) Draft on 1/8/2010, (2) The official (after the approval of Thai Hoa DPC) on
1/10/2010 (two month after sending the manuscript).
Drainage and wastewater treatment project for Thai Hoa town, Nghe An province”
Environmental Impact Assessment (EIA) - 150 –
PCO Consultant, 2010
• To Save files at Nghe An provincial PMU office of clean Water and rural sanitation
(address: Kim Tan – Hoa Hieu ward – Thai Hoa town – Nghe An province) for the
public to access the expecte time mentione above: (1) Draft on 1/8/2010, (2) The
official (after the approval of Thai Hoa town People’s Committee) on 1/10/2010 (two
month after sending the manuscript).
• To Display the official version (attached copy appendix, approval of EIA report of
Thai Hoa town People’s Committee and Minutes of community consultations)
scheduled on 30/10/2010 at the Vietnam Information Center of the World Bank
(Vidic), floor 2 - No. 63 Ly Thai To – Hanoi.
• Advertising (upload) on the web: http:// www.worldbank.org, soft copy of final report
(attached copy of the annex of the approval letter for the Environmental Impact
Assessment of Nghe An province and Minutes of public consultation meeting)
scheduled on 12/01/2010.
Drainage and wastewater treatment project for Thai Hoa town, Nghe An province”
Environmental Impact Assessment (EIA) - 151 –
PCO Consultant, 2010
CONCLUSION AND RECOMMENDATION
I. CONCLUSION
1. The “Drainage and wastewater treatment project for Thai Hoa town, Nghe An province”
is a project of improvement and completion of the equipments and local infrastructures
mechanism and also one of the environmental friendly activities. The overall impact of the
project is positive, satisfies the people’s demand of a drainage and environment sanitation
service. So, it is a effective tool for the management, direction and environment protection.
2. This is one of the environment friendly projects among the investment projects of Nghe An
province. It provide the local people the synchronous drainage work, improve the living
conditions, increase awareness to protect the environment. So, the project responded the
expectation of the people about a healthy environment and contributed to beautify the urban
scenery, attractive to tourists and investors.
3.The scientific figures in this report confirm that the position and the wastewater treatment
technology is the best selection for Thai Hoa town and ensure the norms after processed
reached the environmental standards.
4. The problems arose from the phase of site clearance is not big, the existing land area is not
crowded and do not have important architecture, no tomb, no temple. This is very
advantageous for the project.
5. The problem arose from the phase of site clearance and constructing the items are:
- Exhaust fumes, dust and noise caused by the transporting and executing
vehicles, the activities of install the sewers, drainage of rain-water and wastewater.
- The wastewater of the local people and the workers at the temporary camps
- The solid waste of the workers in the field
These impacts only happen in the phase of construction and can totally overcome by the
reducing measures mentioned in chaper IV
6. The environment impacts includes:
The drainage system may not come into effect, the flood and waterlogging will happen if:
- The system to collect the rain water is broken, blocked by rock, earth or waste
- The dranage ditch is occupied by the people to build houses
- The consciousness to protect the environment, public works is not good, there
is no appropriate commendation or punishment
The quality of the wastewater after treatment may not reach the permitted standards because:
- There are poisonous substances in the wastewater or the processing is not
completed totally. It is necessary to have the specific mechanism for management
and punishment the disposal of the enterprises and manufacture units in the town.
- The pipes are blocked or broken due to the people’s activities (waste, road
digging, building house...)
Drainage and wastewater treatment project for Thai Hoa town, Nghe An province”
Environmental Impact Assessment (EIA) - 152 –
PCO Consultant, 2010
- The activities of the treatment plant can affect the surrounding atmosphere
environment by the odour from the biologic processing ditches and the sludge
processing area.
However, these impacts can be overcome by the effective methods: monitoring the steps of
processing technology, monitoring the wastewater quality periodically, examine and maintain
the equipments, machines of the treatment plants, the sewers, community education....
7. Environmental Managament Plan will be carried out seriously by the management and
operation units along with the coordination and direction of the local environment
management agency. The target of the environment quality monitoring program are: strickly
manage and limit the change of environment in the bad side, ensure the wastewater quality
reaches the current vietnamese standards.
8. By following seriously the regulations about environment and the proposals to reduce
pollution mentioned in this report, surely that the project will come into effect and gain the
positive impacts on socio-economy and environment.
II. RECOMMENTATIONS
1. Administrative organization on environment in Thai Hoa town supports Project Owners to
train and improve the awareness and skills of staff and workers n wastewater treatment plants;
organize the education session in community to raise awareness of environmental protection
for local people
2. To make drainage system and wastewater treatment plants of Thai Hoa town actually
operate effectively, the State management on environment should propose administrative
measures which force industrial production units generating wastewater to build a separate
wastewater treatment system meeting standard class B, QCVN 24:2009/BTNMT: National
technical standards about industrial wastewater to before discharging it to the centralized
wastewater collecting system.
3. The Project Owner must have plan in giving sanctions accompanied with the project to
submit Nghe An Provincial People’s Committee for review and approval.
4.It is proposed that Department of Natural Resources and Environment of Nghe An carries
out an assessment, approves the report which assesses environmental impacts and issues
licenses to let project soon to be implemented. Simultaneously these documents are the base
for managing and protecting environment when project is put into operation.
5. In the framework of this project, it only resolves pollution problem caused by rain water,
wastewater and solid waste, especially domestic solid waste. To make Thai Hoa town actually
become a green, clean and beautiful city, it needs a different project - project of constructing a
hygiene waste processing yard. It is suggested that authorities and relevant organization
propose a satisfactory measures.
Drainage and wastewater treatment project for Thai Hoa town, Nghe An province”
Environmental Impact Assessment (EIA) - 153 –
PCO Consultant, 2010
IX. COMMITMENTS OF THE PROJECT OWNER
Based on the environmental impacts arising from the operation of the project and the
terms of the Environmental Protection Law, decrees, circulars, decisions and ordinances on
environmental protection, the Project Owner – Thai HoaTown People's Committee commits
to implement the environmental management and monitoring program as outlined in Chapter
5; implementation of commitments to the community as outlined in Chapter 6 of the
Environmental Impact Assessment report; complying the general regulations on
environmental protection related to the phases of the project, as follows:
1. Commitments in basic construction:
- During construction, the Project Owner will comply with the steps prescribed
by the Government in the Decree 12/CP on management of construction
investment.
- Complying with regulations on design, basic construction and transportation of
construction materials.
- Collection and timely handling of waste generated during construction phase.
Spoil soil and rock, ground leveling soil, and other construction materials will
be gathered at the prescribed place with appropriate measures.
- Implementing well the policies on saving materials and resources
- Observing strictly regulations on labor safety and fire prevention. Timely
rescueing incidents, risk and natural disaster prevention.
- Building sufficiently and appropriately the environmental protection works
before the project operation.
- When performing the construction, comply with current regulations and the
decision on approving the project of Nghe An Provincial People’s Committee.
2. Commitments in the project operation period:
The Project Owner, operation and management unit commit to fully implement waste
treatment measures as follows:
- Smelling treatment: strictly following measures to reduce bad odors as
proposed in Chapter IV; Planting trees with an area of 10 - 15% of the total
land area surrounding the treatment plant, ensuring the treatment of bad odor
sludge generated from wastewater treatment plant ...
- For water resources: surface water resource protection in receiving source
(Hieu river); wastewater generated from daily acitivites of workers and the
storm water overflows at the waste water treatment plant is guaranteed as
proposed in the report (presented in Chapter IV) before being discharged into
the combined drainage system.
- Commitment on the treated water quality of waste water treatment plant
meeting QCVN 14:2008 / BTNMT with Cmax value, Column B.
- Solid waste treatment:
+ Domestic solid waste: equippe waste containers; arrange sanitation workers
to collect waste everyday, supervising the collection and treatment of operating
unit or the services.
Drainage and wastewater treatment project for Thai Hoa town, Nghe An province”
Environmental Impact Assessment (EIA) - 154 –
PCO Consultant, 2010
+ Sludge: collected to the separate containers, treated for fertilizer or burried in
sanitary landfills.
+ Other commitments:
- Commitment on compensation when environmental incidents causing damage
- Ensuring labour safety, fire and explosion prevention and other incidents, other
environmental risks.
- Commitment on managing the project activities in accordance with the law
(effective waste treatment, and continuous operation of wastewater treatment
plant).
- Implement fully the regulations on reasonable use, saving resources and
environmental protection.
- Co-ordinate closely with the Department of Natural Resources and
Environment of Nghe An province in the inspection and environmental
monitoring under the current regulations.
- Commitment on implementing the waste environment monitoring program (for
the project area, once every 3 months (4 times/year); for the surrounding areas,
once every 6 months (2 times/year ).
3. Commitments on following the environmental standards:
Implement the mitigation measures of environmental pollution in the process of
project operation according to the contents of the environmental impact assessment report,
Commit to comply strictly with Vietnames environmental standards and environmental
protection commitments.
- For treated water quality: The Project Owner commit to ensure the output
quality meeting QCVN 14 :2008/BTNMT, Colum B.
- For solid waste and sludge, the Project Owner commits to collect, store and
treat complying with regulations.
- Commitment to follow Decision No.22/2006/QĐ-BTNMT dated 18/12/2006
of Ministry of Natural Resources and Environment on forcing to applying
Vietnamese environmental standard.
- Commitment to follow Decision No.16/2008/QĐ-BTNMT dated 31/12/2008
of Ministry of Natural Resources and Environment on the issuance of national
environmental technical regulations.
- Commitment to implement regulations, decisions and circulars stated in
report.
- Commitment to compensate in case of environmental incidents and risks.
- Every year, using funds to perform environmental monitoring program. The
monitoring data will be fully updated to report periodically to the management
agency.
- Commitment to comply with the terms of the approval decision in this report.