EE Design Status D Cockerill CERN 19 July 2006. PATCH PANELS. ENVIRONMENTAL SHIELD. ECAL EE End Cap components. SUPPORT RING. SUPERCRYSTALS THIS FACE. BACKPLATE. ECAL EE End Cap Build – Layout. SUPPORT RING. BACKPLATE. ~3.6m. VFE ELECTRONICS. MODERATOR. END CAP DEE. SIDE VIEW. - PowerPoint PPT Presentation

Citation preview

Page 1: EE Design Status D Cockerill CERN 19 July 2006

ECAL – EE Design Status Presentation 19/7/06 D.J.A. Cockerill - RAL 1

EE Design Status

D CockerillCERN 19 July 2006

Page 2: EE Design Status D Cockerill CERN 19 July 2006

ECAL – EE Design Status Presentation 19/7/06 D.J.A. Cockerill - RAL 2

ECAL EE End Cap components

BACKPLATE

SUPPORT RING

SUPERCRYSTALS THIS FACE

PATCH PANELS

ENVIRONMENTAL SHIELD

Page 3: EE Design Status D Cockerill CERN 19 July 2006

ECAL – EE Design Status Presentation 19/7/06 D.J.A. Cockerill - RAL 3

ECAL EE End Cap Build – Layout

BACKPLATE

SUPPORTRING

VFEELECTRONICS

MODERATOR

END CAP DEE SIDE VIEW

~3.6m

Page 4: EE Design Status D Cockerill CERN 19 July 2006

ECAL – EE Design Status Presentation 19/7/06 D.J.A. Cockerill - RAL 4

ECAL End Cap Build - Layers

Arrangement at the Rear of the End Cap Backplate

Backplate Cooling, fitting of patch panels, FOM

Protection plates, HV support

End Cap inner Shielding, Front Moderator

Protection plates, LV support

Mechatronics Support plates

Umbilical connection, VFE Mothercards/support frames, LV

distributionMechtronics cooling system,

internal flow and return manifoldsVFE, LV and FE cards attachment, Inner Moderator

Data/trigger fibre boxes plus support

Rear Moderator, closure of End Cap

Page 5: EE Design Status D Cockerill CERN 19 July 2006

ECAL – EE Design Status Presentation 19/7/06 D.J.A. Cockerill - RAL 5

Backplate Cooling, fitting of patch panels, FOM

Backplate cooling

All 4 backplates have

their associated cooling

pipes

However these pipes

must be fitted to the

patch panels and ring

flange exit points to the

(non existant) blocks

for the quick disconnect

fittings

Design/fabrication of

blocks Mario

Mounting Jose

Page 6: EE Design Status D Cockerill CERN 19 July 2006

ECAL – EE Design Status Presentation 19/7/06 D.J.A. Cockerill - RAL 6

Backplate Cooling, fitting of patch panels, FOM

Cooling completion

Blocks for quick disconnect fittings mounted on

patch panels and ring flanges

Pipes cut to suit (use of CERN gases division?)

Fit pipes to backplate and to blocks

Dismount pipes

Apply thermal compound to cooling plates

Remount pipes, secure to blocks

Leak tests

Page 7: EE Design Status D Cockerill CERN 19 July 2006

ECAL – EE Design Status Presentation 19/7/06 D.J.A. Cockerill - RAL 7

Backplate Cooling, fitting of patch panels, FOM

Patch panels

Have to be redesigned and

remade due to the new

manifold design for the

electronics cooling bars

The ‘plane’ of cooling is 20mm

lower (nearer to

backplate) than before

Design John

Manufacture Mario?

Fitting Jose

Page 8: EE Design Status D Cockerill CERN 19 July 2006

ECAL – EE Design Status Presentation 19/7/06 D.J.A. Cockerill - RAL 8

Backplate Cooling, fitting of patch panels, FOM

Fibre Optic monitoring

The new laser layout has been

incorporated by Saclay, new

mounting drawings produced

Updated locations for the

diffusing spheres. Dees are

mirrors of each other on an

Endcap

Additional mounting holes on

backplate, according to Dee

location in CMS

Holes completed for all 4 Dees

by Jose

Page 9: EE Design Status D Cockerill CERN 19 July 2006

ECAL – EE Design Status Presentation 19/7/06 D.J.A. Cockerill - RAL 9

Backplate Cooling, fitting of patch panels, FOM

VPT stability pulser

One Patch Panel location per

Dee for LED array and

associated electronics

Must serve 18 L1 diffusers

Allocated volume only

4cm x 15cm x 4.5cm

Design RAL/UVa

RISK: Is volume enough ??

Page 10: EE Design Status D Cockerill CERN 19 July 2006

ECAL – EE Design Status Presentation 19/7/06 D.J.A. Cockerill - RAL 10

EndCap EE

All large mechanical pieces are at CERN

Dry assembly of env. screen produced in Russia

Page 11: EE Design Status D Cockerill CERN 19 July 2006

ECAL – EE Design Status Presentation 19/7/06 D.J.A. Cockerill - RAL 11

EE: VPT production & gluing, Supercrystals

EE VPT to crystal gluing

2800 VPTs shipped from UK to CERNAll tested upon receipt by Russia - INR

Up to 50 EE crystals/VPTs glued each week

110 of current EE crystal stock (~350 xtals) done

First “Russian” SC completed

in June 2006 built using CRISTAL database

Page 12: EE Design Status D Cockerill CERN 19 July 2006

ECAL – EE Design Status Presentation 19/7/06 D.J.A. Cockerill - RAL 12

EE electronics

Preliminary results, ~ 3900 e- per channelCross talk < 0.1%Meets EE requirements

SC HV cards 105 pre-production cards completed All R & C components for EE delivered

Motherboards 2 prototypes on Dee4 600 cards by end 2006

EE VFE cardsRC feedback on MGPA tuned for EEInput diode for VPT spark protection 30 prototypes produced in Feb 06 250 cards now under test

3130 cards by end July 06

FE cards80 pre-production cards tested

800 cards produced by Sep 2006

Page 13: EE Design Status D Cockerill CERN 19 July 2006

ECAL – EE Design Status Presentation 19/7/06 D.J.A. Cockerill - RAL 13

EE trigger

Pseudostrip (5 crystal) allocationsEE+ towards I.P

Consequent trigger towers (TCC level)EE+ towards I.P

Page 14: EE Design Status D Cockerill CERN 19 July 2006

ECAL – EE Design Status Presentation 19/7/06 D.J.A. Cockerill - RAL 14

EE : preparing for the assembly

Ensuring correct cabling of the channels

Trigger map (H.Heath)LED cabling tester from UVa

Page 15: EE Design Status D Cockerill CERN 19 July 2006

ECAL – EE Design Status Presentation 19/7/06 D.J.A. Cockerill - RAL 15

EE data and trigger readout

The fibre readout fan-out boxes (two layers) serving the EE DCCs and TCCs in the control room

900 readout fibres to correctly route per Dee

Page 16: EE Design Status D Cockerill CERN 19 July 2006

ECAL – EE Design Status Presentation 19/7/06 D.J.A. Cockerill - RAL 16

“Dee4” project

“Dee4”

First large scale test of integration philosophy

20 SCs mounted on BP Dee4 by end 2006

Trigger mapping at motherboard

10 cooling blocks, main manifold

“Dee4” to testbeam in May 2007

EE assembly has started

“Dee4” will provide crucial assembly and test beam insights

Dee1 assembly from September 2006

Page 17: EE Design Status D Cockerill CERN 19 July 2006

ECAL – EE Design Status Presentation 19/7/06 D.J.A. Cockerill - RAL 17

EE Planning

Dee 1 End Sep 2007Dee 2 End Dec 2007Dee 3 Mid Mar 2008Dee 4 Mid Apr 2008

CMS windowfor Dee1end Sep 07

EE+mid Jan 08

EE-mid Mar 08

Page 18: EE Design Status D Cockerill CERN 19 July 2006

ECAL – EE Design Status Presentation 19/7/06 D.J.A. Cockerill - RAL 18

EE planning

Crucial to introduce as much parallel assembly and integration as possible

Quality control at each crucial step

Suggestion to carry out all SC mounting and Dee assembly in bldg 867

This offers many very attractive features- all major activities under one roof- proximity of expert teams- realisation of the EE trigger, from motherboard level to fibre readout level- multiple DAQ test systems, needed for EE QA, available locally- cooling capacity for one entire Dee- LV power

Crystal Palace

Advance preparation of all large mechanics- Dees into OPAL frames- dry assembly tests of Environmental screens- BP cooling installation- Mounting laser monitoring system

Page 19: EE Design Status D Cockerill CERN 19 July 2006

ECAL – EE Design Status Presentation 19/7/06 D.J.A. Cockerill - RAL 19

EE - Conclusions

EE assembly has started

Much progress with the EE large mechanics, VPTs, SC assembly, electronics, and trigger and data mapping

“Dee4” will provide crucial assembly and test beam insights Dee1 assembly from September 2006

We are on the learning curve for EE assembly

Page 20: EE Design Status D Cockerill CERN 19 July 2006

ECAL – EE Design Status Presentation 19/7/06 D.J.A. Cockerill - RAL 20

Additional info follows, next slide