92
DURHAM UNIVERSITY School of Engineering and Computing Sciences Level 2 Design Feasibility Report on Rainwater Storage and Filtration in the Mekong Delta Mission Statement: To design and provide a water collection, storage and filtration system that is both affordable and effective for a household in the Mekong Delta. Authors: Kevin De Michelis, Charles Heard, Tom Pallister, Nick Sidwell, Callum Stephen, Xaver Touschek Supervisors: John Garside and Peter Waugh

Design Project EWB

Embed Size (px)

Citation preview

DURHAM UNIVERSITY

School of Engineering and

Computing Sciences

Level 2 Design

Feasibility Report on Rainwater Storage

and

Filtration in the Mekong Delta

Mission Statement: To design and provide a water collection, storage

and filtration system that is both affordable and effective for a

household in the Mekong Delta.

Authors: Kevin De Michelis, Charles Heard, Tom Pallister, Nick Sidwell,

Callum Stephen, Xaver Touschek

Supervisors: John Garside and Peter Waugh

Group 17.

1

Executive Summary

The objective of this project is to design and provide a water collection, storage and filtration system

that is both affordable and effective for a household in the Mekong Delta.

The Mekong Delta is an agricultural region in the south of Vietnam that experiences an annual rain

cycle consisting of a dry and wet season each of which lasts roughly 6 months. The average farmer

has a family of four and lives in a commune with a salary of less than $10 per day. This region is

difficult to access due to poor infrastructure and can mainly be reached by using the many rivers and

canals.

Currently, drinking water is collected from three sources: rainwater, borehole water, and surface

water. This water is typically stored in open cement or ceramic jars during the wet season. However,

this barely provides a family with enough water to last the dry season. Furthermore there is often a

build-up of impurities in their storage jars that leads to water contamination. There is also a lack of

adequate filtration which can cause severe water borne diseases and infections.

A domestic system that harvests rainwater was concluded as the most appropriate solution for the

Mekong Delta. A central communal water filtration plant had no way to distribute water due to a

lack of piping infrastructure and rainwater was deemed as the cleanest and most plentiful option.

The domestic approach means having to provide the knowledge and designs of the system to the

average farmer. Therefore the solution took into account locally sourced materials and local

businesses as well as providing clear and concise instructions for construction.

To make the process clear the solution was divided into three parts:

A more detailed and quantified user requirement specification table has been written up in the

main report for each section. However, these are the decisive factors that stood out:

Collection Storage Filtration

System User Requirement Specification

Collection Collection of 4m3 in 2 months.

Must allow water to be diverted away from tank to wash the roof.

Storage Removal of any initial contaminants.

Storage of 3600 litres.

Prevents sunlight access.

Costs less than $80.

Can be built by unskilled labourer.

Exit flow rate of 7.5 litres/min.

Filtration Filters > 90% of organic material.

No operational costs.

Flow rate > 3litres/person per day.

Costs less than $10.

2

Collection:

Guttering System Final Design Key Physical aspects

Simple open gutters between roof and tank.

Removable section to allow water to be diverted away from tank.

Both gutters and supports made of bamboo.

Functionality Fully capable of filling the tank during the wet season (several times over)

Allows siphoning of water where required (eg to clean the roof) by the removable section.

Very easy for anyone to erect, maintain, and repair.

Total cost: $8.88

Storage:

Storage Tank Final Design Key Physical aspects

Built using ferrocement.

Bowl beneath tap to allow for water access.

Overflow pipe at top of tank.

Wash out pipe at bottom of tank.

Collection hole on sloped roof.

Inlet filter at entrance to tank

Functionality Stores 3,600 litres of water; enough to last a family of four through the six month dry season.

Does not allow exposure to sunlight.

It is robust enough to withstand flooding.

Construction time is under 2 weeks.

Instruction manual allows the tank to be built by an unskilled labourer.

Can safely withstand internal hydrostatic pressures at full capacity.

Water access has flow rate over 7.5 litres/minute

Tank can be easily maintained by an unskilled labourer

Initial filtration unit at the top avoids debris and insects from entering the tank.

Total cost: $65.38

3

Filtration:

Filtration System Final Design Key Physical aspects

Clay pot filter running into plastic water butt

Ceramic pot is made from a 3:1 clay: rice husk mix

System is 660mm tall and 500mm wide

Plastic Butt is wider at the bottom for increased stability

Water is cleaned by physical straining and chemical action

Functionality Filters 3L of water per hour

Removes over 90% of bacteria

Reduces water turbidity to under 5%

Has zero power requirements

Only requires cleaning once a month

Very affordable at only $8.10

$8.10

Total cost:

The layout of each household in the Mekong Delta will inevitably differ from one another. However,

the design and implementation of each section within the project has allowed for greater

adaptability. The guttering system is fully adjustable to any roof dimensions whilst also providing

initial filtration. The storage tank can be positioned where ever the user desires it to be and has the

potential to be connected to the household via water piping. The filtration unit is easily portable and

unobtrusive within the home.

The collection, storage, and filtration designs have all successfully fulfilled their respective user

requirement specifications. Therefore this integrated system is the optimum rainwater storage and

filtration solution available to the people of the Mekong Delta.

4

Table of Contents

Executive Summary ................................................................................................................................. 1

Collection: ........................................................................................................................................... 2

Storage: ............................................................................................................................................... 2

Filtration: ............................................................................................................................................. 3

Team Assignment Overview ................................................................................................................... 9

1. Introduction ...................................................................................................................................... 10

1.1 Project Statement ....................................................................................................................... 10

1.2 Mekong Delta .............................................................................................................................. 10

1.3 Current Practice .......................................................................................................................... 10

1.4 Approach and Philosophy ........................................................................................................... 11

1.5 Project Management .................................................................................................................. 12

1.5.1 Planning ................................................................................................................................ 12

1.5.2 URS and feasibility report .................................................................................................... 12

1.5.3 Teamwork ............................................................................................................................ 12

Charlie Heard & Kevin De Michelis ....................................................................................................... 13

2. Collection .......................................................................................................................................... 14

2.1 Water sources ............................................................................................................................. 14

2.2 Concept developments ............................................................................................................... 15

2.3 Final design ................................................................................................................................. 16

2.3.1 Attaching to the roof ............................................................................................................ 16

2.3.2 Supporting the system ......................................................................................................... 17

2.3.3 The siphon ............................................................................................................................ 17

2.4 Sustainability ............................................................................................................................... 17

2.5 Manufacture ............................................................................................................................... 18

2.6 Final Costs ................................................................................................................................... 19

Thomas Pallister & Xaver Touschek ...................................................................................................... 20

3 Storage ............................................................................................................................................... 21

3.1 Current storage methods in the Mekong Delta .......................................................................... 21

3.1.1 Flow chart of processes ........................................................................................................... 21

3.2 Requirements for Storage system .............................................................................................. 22

3.3 Ferrocement as a material .......................................................................................................... 24

3.3.1 Material composition matrix ............................................................................................... 25

5

3.4 Availability of materials for construction .................................................................................... 27

3.4.1 Portland cement .................................................................................................................. 27

3.4.2 Fine grain sand ..................................................................................................................... 27

3.4.3 Potable water ....................................................................................................................... 27

3.4.4 Bamboo: ............................................................................................................................... 27

3.4.5 Wire mesh: ........................................................................................................................... 28

3.5 Ferrocement foundation theory ................................................................................................. 28

3.6 Water access ............................................................................................................................... 29

3.7 Concept design ........................................................................................................................ 31

3.8 Design development .............................................................................................................. 31

3.8.1 Problem Identification ......................................................................................................... 31

3.8.2 Problem solutions ................................................................................................................ 32

3.9 Final design ................................................................................................................................. 34

3.10 Structural Analysis: ................................................................................................................... 35

3.10.1 Analytical Conclusion: ........................................................................................................ 35

3.11 Inlet filter .................................................................................................................................. 35

3.12 Sustainable storage ................................................................................................................... 35

3.12.1 Life span of Tank ................................................................................................................ 35

3.12.2 Reducing ground Erosion ................................................................................................... 36

3.12.3 Flood Resistance ................................................................................................................ 36

3.12.4 Reduced Maintenance ....................................................................................................... 36

3.12.5 Locally Sourced Materials .................................................................................................. 36

3.13 Storage Manufacture ................................................................................................................ 36

3.14 Final Costing .............................................................................................................................. 37

3.15 Storage System Conclusion ....................................................................................................... 38

Callum Stephen & Nicholas Sidwell ...................................................................................................... 40

4 Filter Solutions ............................................................................................................................... 41

4.1 User Requirement Specifications ............................................................................................ 41

4.2 Potential Filtration Techniques ............................................................................................. 43

4.2.1 Slow Sand Filter .................................................................................................................... 43

4.2.2 Clay Pot ................................................................................................................................ 43

4.2.3 Why the Clay Pot? ................................................................................................................ 44

4.2.4 How the clay pot Works ....................................................................................................... 44

4.2.5 Silver Nitrate Solution .......................................................................................................... 45

4.3 Filtration System Development .................................................................................................. 46

6

4.4 Clay Pot Filter development ........................................................................................................ 47

4.4.3 Clay Pot Capacity .................................................................................................................. 47

4.4.4 Pot Lip .................................................................................................................................. 49

4.4.5 Shrinkage during Firing ........................................................................................................ 49

4.5 Chemical Treatment of the water ............................................................................................... 50

4.5.1 Water Treatment Chemicals ................................................................................................ 50

4.5.2 Silver Nitrate Solution .......................................................................................................... 50

4.6 Plastic Barrel Development ......................................................................................................... 51

4.6.1 Types of plastic ..................................................................................................................... 51

4.6.2 Initial Design ......................................................................................................................... 51

4.6.3 Changes in the design .......................................................................................................... 52

4.6.4 The Lid .................................................................................................................................. 52

4.7 Detailed filtration design ............................................................................................................ 52

4.7.1 Key Dimensions .................................................................................................................... 53

4.7.2 Clay Pot ................................................................................................................................ 53

4.8 Manufacturing Filtration System ................................................................................................ 54

4.8.1 Manufacture of Clay Pot Prototype in the UK ..................................................................... 54

4.8.2 Clay Mix ................................................................................................................................ 54

4.8.3 Clay Pot ................................................................................................................................ 54

4.8.4 Testing .................................................................................................................................. 54

4.8.5 Costs ..................................................................................................................................... 55

4.9 Manufacture in Vietnam ............................................................................................................. 56

4.9.1 Sourcing Clay Mix ................................................................................................................. 56

4.9.2 Clay Pot Moulding ................................................................................................................ 57

4.9.3 Drying and Firing .................................................................................................................. 57

4.9.4 Reusing discarded Pots ........................................................................................................ 58

4.9.4 Treating with Silver Nitrate .................................................................................................. 59

4.9.5 Making the solution ............................................................................................................. 59

4.9.6 Applying the Silver Solution ................................................................................................. 60

4.9.7 Cost of Silver Solution .......................................................................................................... 60

4.10 Water Butt Manufacture .......................................................................................................... 60

4.10.1 Plastic Barrel ...................................................................................................................... 60

4.10.2 Plastic Lid............................................................................................................................ 61

4.10.3 Plastic Tap .......................................................................................................................... 61

4.11 Manufacture Costing ................................................................................................................ 62

7

4.12 Filter Conclusion........................................................................................................................ 63

5 Discussion ...................................................................................................................................... 64

5.1 Adaptability of the integrated system ........................................................................................ 64

5.2 Improvements on current methods............................................................................................ 64

5.3 Total cost of integrated system and funding: ............................................................................. 65

5.4 Worst Case Scenarios and Contingency Plans ............................................................................ 66

5.4.1Flooding ................................................................................................................................ 66

5.4.2 Typhoons .............................................................................................................................. 66

6 Conclusion .......................................................................................................................................... 67

7 References ......................................................................................................................................... 68

Appendix A - Material Calculations ....................................................................................................... 69

Appendix B – Construction Guidelines ................................................................................................. 70

Appendix C – Stress Analysis of Tank .................................................................................................... 76

Appendix D – CAD Drawings ................................................................................................................. 83

Appendix E – Bamboo Handling Techniques ........................................................................................ 84

Instructions for cutting ..................................................................................................................... 84

Instructions for splitting .................................................................................................................... 85

How to Split Bamboo? ...................................................................................................................... 85

Important: Bamboo has 2 sides! .............................................................................................. 87

1. Straight Front: ......................................................................................................................... 87

2. Straight Cut Surface: ............................................................................................................. 88

Appendix F – Rainfall Data + Calculations ............................................................................................. 89

Appendix G – Example Meeting Minutes ............................................................................................. 90

Post holiday meeting (week 5) ......................................................................................................... 90

General points arising: .................................................................................................................. 90

Sectional updates: ......................................................................................................................... 90

Collection ...................................................................................................................................... 90

Storage .......................................................................................................................................... 90

Filtration ........................................................................................................................................ 90

Other general points: .................................................................................................................... 90

Weekly meeting – week 12 ............................................................................................................... 91

General points arising: .................................................................................................................. 91

Sectional updates: ......................................................................................................................... 91

Collection ...................................................................................................................................... 91

Storage .......................................................................................................................................... 91

8

Filtration ........................................................................................................................................ 91

Other general points: .................................................................................................................... 91

Figure 1 - Current guttering systems .................................................................................................... 14

Figure 2 - Manual (left) vs. automatic (right) siphon ............................................................................ 15

Figure 3 - Examples of automatic siphons ............................................................................................ 16

Figure 4 - Different methods to attach gutter to roof .......................................................................... 16

Figure 5 - Proposed method to attach gutter to roof ........................................................................... 17

Figure 6 - Supported guttering .............................................................................................................. 17

Figure 7 - Vietnamese People Splitting Bamboo .................................................................................. 18

Figure 8 - Guttering on the Roof ........................................................................................................... 18

Figure 9 - Shaping Bamboo Supports to Hold Guttering ...................................................................... 18

Figure 10 - Storage process flowchart .................................................................................................. 21

Figure 11 - Wire mesh ........................................................................................................................... 26

Figure 12 - Ferrocement foundation ..................................................................................................... 28

Figure 13 - Screw down tap .................................................................................................................. 29

Figure 14 - Ball valve hose tap .............................................................................................................. 29

Figure 15 - Loose head handle .............................................................................................................. 29

Figure 16 - Bent nose hose tap ............................................................................................................. 29

Figure 17 - Gate Valve tap ..................................................................................................................... 29

Figure 18- Design concept for ferrocement tank .................................................................................. 31

Figure 19 - Magnified view of tank displacements under load............................................................. 33

Figure 20- Final tank design .................................................................................................................. 34

Figure 21 - CAD drawing of inlet filter .................................................................................................. 35

Figure 22 - Filtration Process Flow Chart .............................................................................................. 44

Figure 23 – Pore Size ............................................................................................................................. 45

Figure 24 - Filtration Processes ............................................................................................................. 45

Figure 25 - Filter Composition ............................................................................................................... 46

Figure 26 - Exploded View Of Filter System .......................................................................................... 46

Figure 27 - Clay Pot Internal Angle........................................................................................................ 47

Figure 28 - Final Filter Process .............................................................................................................. 49

Figure 29 - Pot Lip ................................................................................................................................. 49

Figure 30 - Exploded View of Initial Design........................................................................................... 51

Figure 31 - Detailed Filter Design .......................................................................................................... 52

Figure 32 -Key Dimensions of detailed design ...................................................................................... 53

Figure 34 - Clay Pot Manufacturing Process ......................................................................................... 56

Figure 35 – Dry Bricks............................................................................................................................ 56

Figure 36 – Hammer Mill ...................................................................................................................... 57

Figure 37 - Press Mould ........................................................................................................................ 57

Figure 38 - Firing Process ...................................................................................................................... 58

Figure 39 - Recycling Process ................................................................................................................ 58

Figure 40 - Painting the Pot with Silver Solution .................................................................................. 60

Figure 41: Blow Moulding ..................................................................................................................... 60

Figure 42 - Joining the Handle to the Lid .............................................................................................. 61

Figure 43: Plastic Tap ............................................................................................................................ 61

9

Figure 44 - Final cost breakdown .......................................................................................................... 65

Table 1 - Water source decision matrix ................................................................................................ 14

Table 2 - Collection System Costing ...................................................................................................... 19

Table 3 - Currently available storage options ....................................................................................... 21

Table 4 - Storage URS ............................................................................................................................ 22

Table 5 - Decision matrix of different available storage methods ........................................................ 23

Table 6 - Sang grading scale .................................................................................................................. 25

Table 7 - Material availability ................................................................................................................ 28

Table 8 - Tap decision matrix ................................................................................................................ 30

Table 9 - Tank construction process ..................................................................................................... 37

Table 10 - Final tank costings ................................................................................................................ 38

Table 11 - Cost comparison ................................................................................................................... 39

Table 12 - Tank URS check .................................................................................................................... 39

Table 13 - Filtration URS ....................................................................................................................... 42

Table 14 - Filter Decision Matrix ........................................................................................................... 43

Table 15 - Pros and Cons of a Larger Clay Pot....................................................................................... 48

Table 16 – Types of Plastic .................................................................................................................... 51

Table 17 - Filter Costs ............................................................................................................................ 55

Table 18 - Manufacture Costs ............................................................................................................... 62

Table 19 - Completed Filtration URS ..................................................................................................... 63

Team Assignment Overview

• Project Manager

• Storage design Tom Pallister

• Collection design

• Introduction

• Team sketch artist

Kevin de Michelis

• Collection design

• Worst Case Scenarios

• Project Management

Charles Heard

• Filtration design Nicholas Sidwell

• Filtration design Callum

Stephen

• Storage

• Executive Summary

• Conclusion

• Construction Guide

Xaver Touschek

10

1. Introduction

This report is a design solution for an Engineers Without Borders (EWB) Project in Vietnam.

1.1 Project Statement Access to clean drinking water is an important issue that needs to be addressed throughout the

Mekong Delta region. Drinking water is currently collected from three sources: rainwater, boreholes

and surface water. Rainwater is collected in open cement /ceramic jars during the wet season and

will typically provide a family with water for approximately five months of the year. Impurity build

up in the jars is a problem. The approach should take account of the nature of the terrain and

culture of the region make good use of renewable sources of energy and the nature of the materials

available and include mechanism of decanting the water to and from storage.

1.2 Mekong Delta The Mekong Delta is the region in the Anh Minh district in south-western Vietnam where the

Mekong River approaches and empties into the sea through a network of distributaries. Due to this

abundance of water and a six month monsoon season this is also an agricultural haven for the

Vietnamese rice farmers, and has numerous canals to aid the irrigation of the many rice fields. Thus

the area is referred to as flat flood plains and is, as implied, susceptible to floods during the wet

season. The wet season is a six month monsoon that South East Asia experiences in an annual rain

cycle, followed by a six month season of drought. The profusion of waterways means that the

principle mode of transport for both people and goods is boats and is otherwise very difficult to

access.

The average size for a rice farming family is 4.4 and they typically live in a house by the river or canal

to maximise the area of cultivatable land. The farmers are usually men as the work in the field is

considered ‘heavy’ work and for a man to do ‘light’ work, such as working in a factory, is culturally

unacceptable. However, though the women customarily do the ‘light’ work, they can work in the rice

fields too helping the men with several tasks, this is applicable to house building as well. Despite the

cultural gender separation in labour, men and women can work together to complete any necessary

task at hand; therefore any maintenance or construction can be performed by any member of the

family. The average wage of the rice farmers ranges from 6 - 9 USD/day.

1.3 Current Practice As mentioned in the project statement drinking water is primarily collected from three sources

during the wet season. This water stored provides the family with enough to last them most of the

dry season. However, this means the farmers must compensate, for the deficiency of water, using

boreholes throughout the dry season, yet only 85% of the families have access to them. There is also

a lack of proper maintenance in there storage system; impurities build-up, in the open aired

jars/tanks, and requires too much time and effort to upkeep them leading to water contamination.

Moreover, there is no current practice with which to filter the water afterwards causing possible

infections and severe diseases due to bacterial accumulation and viral contagions.

Having assessed the major problems with the system currently in place, a preliminary set of criteria

was stated. Firstly, an improved system of storage had to be implemented, the new method had to

provide the family with sufficient water and minimise the risk of water contamination. Secondly,

filtered water adhering to international SPHERE standards had to be introduced to the families’ daily

lives to reduce the number of infection and disease outbreaks. For these two measures to be

11

effective an efficient and clean water collection system also had to be added before the water

storage, to facilitate the rest of the operation. Finally, because of the very low salary of the people in

the region, the new system had to be financially viable and hence less expensive than the current

option.

1.4 Approach and Philosophy There were two lines to follow when thinking of a solution to the problem at hand. There was a

communal approach and a domestic approach. The communal methodology was based around a

centralised water filtration plant, while a domestic attitude would have a system in and around the

homes of the agriculturalists. The communes, however, are not organised into villages with typical

clusters of housing or buildings. Although they are more densely populated in the centre, the houses

are spread out along the banks of the canals and waterways that criss-cross the district. It was

evident that having water filtration plants spread across the Anh Minh district would have been

cheaper to the individuals but that there was currently a lack of piping infrastructure; the

construction and maintenance of such a network would have been near impossible with the regular

floods. On the other hand a domestic approach encouraged better accessibility and higher flexibility

to the clean water, thus a domestic design was chosen.

The prerequisites to the design solution lead to an obvious attitude with which the project would be

handled. The knowledge and designs provided had to be accessible, understandable and executed

by the average farmer, allowing him to self-build his own clean water system. To implement this, the

design uses locally sourced materials and local businesses as well as providing clear instructions for

the construction. To make the process clear the solution was divided into three parts: the water

collection, the water storage and the water filtration. Each section can be addressed and dealt with

separately despite them complementing each other; this method facilitates the manipulation and

correction of any part. The final design provides a system that safely stores the water in a closed

environment before it is filtered and drunk. The ensuing report is thus separated into the following

three sections:

12

1.5 Project Management

1.5.1 Planning

The project was split into the three sections early on, and each section was assigned two team

members;

Collection – Charlie and Kevin

Storage – Tom and Xaver

Filtration – Callum and Nick

All the research and report writing for these sections were then to be done by their respective

members. Other areas were also assigned based on expected workload in the main sections;

Introduction – Kevin

Executive Summary – Xaver

Worst Case Scenarios – Charlie

Conclusion - Xaver

A Gantt chart was then made giving a schedule to the project (Appendix H).

Overall, the project followed the plan to a greater extent, some things took longer than expected –

the presentation for example put a complete stop to report writing for a week. The final order in

which the report was written and structured was changed adopt for this unexpected setback. An

initial finish date of three days before the deadline became just one; in which proof reading and final

editing took place.

1.5.2 URS and feasibility report

After the feasibility report, the group had a URS to work to and certain expectations of the project.

Unfortunately some of these quickly changed when detailed designs were drawn up. Costing, for

example, went up from $60 for the total system, to a total of just under $85. It was also discovered

that the guttering system should include a way to discard initial rainfalls; something not yet

discovered when the feasibility report was written.

The large initial URS was therefore edited slightly, removing some superfluous requirements, editing

others, and splitting it into sections for each part of the project.

1.5.3 Teamwork

The team met a minimum of twice a week throughout the project, these frequent meetings meant

that all members of the team were kept up to date with all other aspects of the project (Example of

minutes from some of these meetings can be found in Appendix G).

It also meant that most important decisions were made by the team as a whole rather than just the

team members assigned to that particular section. In a larger scale project this may have been

impractical but for this project it was a useful way to allow team members to support each other and

for no one team member to be overburdened at any point. The explanation of individual sections to

the whole team also worked as a way of reinforcing the understanding of one’s own and others’

sections as it highlighted things that were not fully understood or explained.

13

Water collection

Charlie Heard & Kevin De Michelis

14

Table 1 - Water source decision matrix

2. Collection There are two main concerns to be addressed within the water collection: collecting and delivering

the water to the tank and removing any initial impurities that could contaminate the water before

storage. This comes in two statements in the URS;

Collection of 4m3 in 2 months.

Must allow water to be diverted away from tank to wash the roof.

The 4m3 was calculated for an average family of 4 requiring 3.8 litres/person/day for both drinking

and cooking.

2.1 Water sources Currently in the Mekong Delta, there are three main sources of water used for both drinking and

cooking; canals, bore holes and rainwater. The three sources were analysed using the decision

matrix shown below and it was decided that, because “Falling rain can provide some of the cleanest

naturally occurring water that is available anywhere.”1 and can be collected with minimal effort, the

system should be designed around rainwater as a main source of water with contingency plans in

case this was not sufficient over the year. Calculations for rainfall data (table in Appendix F) between

years 2006 – 2010 shows that the wet season provides at least 83% of the year’s rainwater and that

a roof of 16m2 provides over 20m3 during this time. This quantity provides more than the required

needs.

Currently, those who use rainwater as a source of water

have some form of improvised guttering system, often

made from recycled materials and rubbish. While in

many cases this may be sufficient, customers will be

provided with a cheap effective alternative solution

either to replace the existing system if desired, or put in

place where a system is currently not present.

One key change to the guttering system will be the

addition of a siphon. After the dry season, it is likely that

dirt, bird droppings etc. will have built up over the roof

leaving it contaminated. This contamination should not

be allowed into the tank to help prevent bacteria build

up during storage. The simplest solution to this problem is to use the initial rainfall to wash the roof

and let the water flow elsewhere.

1http://www.wateraid.org/uk/what_we_do/sustainable_technologies/technology_notes/246.asp

last access: 19/02/2013 12:16

Figure 1 - Current guttering systems

15

2.2 Concept developments Getting the water from the roof to the tank will be a different challenge for every home; the roofing

will be different in almost every case and the tank may not necessarily be built very close to the

house. It is therefore difficult to come up with a single standard system. Instead, as the whole

system is to be self-built, rough instruction guidelines will be provided to the user on how to build a

system based on general guidelines and construction techniques.

The main construction material chosen was bamboo; it is the most readily available material, very

inexpensive and environmentally friendly. It will be used both as structural support and, when split,

the gutter itself.

As for the initial filter, this will be the same design for every customer. The first two rainfalls2 at the

start of the rainy season will be drained away to ensure none of the dirt accumulated on the roof

over the dry season pollutes the tank water. While the water is destined for a filter, it is beneficial to

store the water as cleanly as possible to prevent obstructing the tap or breeding bacteria. So to

implement this effectively a system had to be designed to allow for water to be diverted away from

the tank and then easily redirected.

There are essentially two ways to approach this, an automated system, whereby the system will

automatically siphon off the initial water and then divert the rest into the tank, or a more basic

system whereby the user will have to divert the water themselves.

Figure 2 - Manual (left) vs. automatic (right) siphon

The manual siphon, shown in Figure 2 demonstrates the basic concept of ‘completing the circuit’. By

having a removable piece the customer decides when to allow the water to flow into the tank, thus a

reference must be accompanied with the siphon to indicate the appropriate amount of water to

discard before ‘completing the circuit’.

As for the automatic system, there are several simple mechanical systems that could be considered,

most utilising something buoyant to close up a valve or fill a hole once 20 litres have been stored in a

container. Then the only maintenance is to empty it once a year before the rainy season starts

2 www.unicef.org/eapro/Harvesting_the_rain_p_29-42.pdf (last viewed 4/3/13 15:47)

16

Figure 3 - Examples of automatic siphons

In figure 3, two examples are given of simple systems;

On the left is an example using two buoyant balls. As the container fills with water, the ball inside

floats to the top of the container and pulls, via the rope, the left hand ball into the hole, filling it and

diverting the rest of the water straight down the gutter.

On the right is a simple float in a tank, which floats to the top, filling the hole and diverting the water.

Both are very simple to implement and contain only a few moving parts which are unlikely to fail or

require much maintenance.

While an automatic system removes the chances of human error (the manual system requires the

user to remember to remove and replace the section of gutter) and is much more user friendly,

there are some downsides. The mechanical system is more complicated, both to make and maintain

and requires additional materials to construct. Moreover, the weight of the collected water has to

be supported in addition to the gutter.

2.3 Final design The three final detailed aspects of the design are attaching the gutter to the roof, supporting the

system and the manual siphon.

2.3.1 Attaching to the roof

Figure 4 - Different methods to attach gutter to roof3

Several methods were examined as shown in figure 4. To best suit the available materials however, a

slightly altered method has been adopted. Using smaller diameter bamboo poles, two runners will

be made to hold the gutter. These can then be lashed to the struts in the roof with rope.

3http://www.unicef.org/eapro/Harvesting_the_rain_p_29-42.pdf (last viewed 4/3/13 19:17)

17

Figure 6 - Supported guttering

Figure 5 - Proposed method to attach gutter to roof

Figure 5 illustrates this system put into place. This solution is simple and in-keeping with the current

construction of the roof and allows for guttering to be attached to multiple sides of the roof to

collect the desired amount of water.

2.3.2 Supporting the system

In appendix E is a set of instructions provided by guaduabamboo on

using bamboo as a construction material. Using these methods the

user will be required to erect some supporting poles to take the

weight of the gutter full of water.

These poles should be dug into the ground, approximately 30cm to

ensure they don’t fall over, and need to be provided every 1m along

any guttering between the roof and the tank.

2.3.3 The siphon

It was decided that a manual siphon was a more feasible solution due to the increased construction

and weight of the automatic system. The system is very easy to implement. In the section of

guttering between the roof and the tank a piece of gutter shall be made to be removable.

This system fully completes the desired requirements set out in the URS – it is capable of collecting

4m3 and has a siphon to remove water.

2.4 Sustainability Bamboo is the most readily available material to the Mekong Delta. It is grown in communal farms

for various purposes, mainly construction. The local inhabitants can easily access the bamboo grown

on these farms, however, the high demand of this material makes these communes very difficult to

maintain. Therefore the sustainability of these bamboo farms must be taken into consideration to

ensure that the material is still readily available to other people in the Mekong Delta. If necessary, it

is possible to purchase the bamboo that has been cut and pre-treated for construction purposes.

The bamboo can be delivered to the Mekong Delta however, the cost must inevitably be considered

if this choice were to be acted upon.

If you put the bamboo into the ground, it will last up to 2 years, then it will rot off at the ground level.

Above the ground the bamboo will last many, many years. If outdoors in the elements it will likely

last more than 10 years. It is naturally rot and pest resistant.4

4Reference: www.bamboosupply.net/faq.htm

18

Figure 7 - Vietnamese People Splitting Bamboo

Figure 8 - Guttering on the Roof

2.5 Manufacture This design for manufacture will be made for a standard sized roof of 4m x 4m. The design standard

is simply to facilitate a manufacturing guide as all the roof sizes, and hence material requirements,

will be different. Though it cannot be assumed that the user knows the process of making guttering,

it is well known that the farmers have their own self-built guttering system. Therefore, the following

is a rough guide and not a set of strict instructions. It is even possible that there is no need to supply

them with the guide as they may very well have their own system in place; therefore these

guidelines may not be applicable to all users but are of a higher importance if a new house is to be

built.

A 4m x 4m roof will have gutters running along three sides of it, two on the ends of the slants and

one connecting them. A fourth piece of guttering, again adjustable to user requirements, will join

the set of gutters to the tank; this piece will be taken to be 4m long as well. The fourth gutter will be

tied and supported further along. The support will also be made of bamboo as it is sufficient for the

job at hand.

A total of 20m, of a 10cm diameter bamboo species,

for the gutters and supports will be used. The roof

support bamboo should use small, sturdy poles,

typically with diameter of 2cm; a total of 19.2m will be

used. For the construction of the gutters two of the

large poles will be cut into 4m lengths and split in half

(using the techniques given in the Appendix E), then,

the nodes are removed with a knife or chisel, to make

a gutter shape. There should now be four 4m gutters

ready for installation.

The two gutters on the roof that capture the runoff

water will be attached to the roof using natural fibre

ropes and the small bamboo poles. There are two 4m

runners per side and then two 30cm strips per metre per

side, thus eight support junctions in total. Each of the

support junctions will use 2m of fibre rope. The third roof

gutter will be placed on the side of the house closest to

the tank. One end will be attached to one gutter while

the other end will rest on the fourth tank-gutter, as

shown in figure 8.

Supports will be placed with two meter

spacing along the fourth gutter: one at the

connection point with the roof gutters, and

one halfway along. The final support will be

the tank. To make the supports a shape that

will better accommodate the resting gutters,

Figure 9 - Shaping Bamboo Supports to Hold Guttering

19

the end must be cut in a ‘U’ shape as shown in figure 9. The supports should be buried at least 30cm

into the ground to ensure adequate stability. Four metres of bamboo has been estimated for the

supports though the height of the bamboo poles needed depends wholly on the height of the user’s

house.

The fourth gutter can now be cut in half; leaving one end permanently fixed at the roof connection

and the other half now a removable piece as discussed in the concept development.

2.6 Final Costs Using the lengths and quantities stated in the manufacturing for design, the costs calculated are

given in table 2.

Table 2 - Collection System Costing

Material Cost per unit Quantity Cost

10cm Bamboo $0.1/m 4 x 5 =20 metres $2.00

2cm Bamboo $0.1/m (4 x 4) + (2 x 8 x 0.3) =

20.8 metres

$2.08

Fibre Rope $0.3/m 2 x 8 = 16 metres $4.80

Total Cost: $8.88

20

Water Storage

Thomas Pallister & Xaver Touschek

21

3 Storage

3.1 Current storage methods in the Mekong Delta

Rainwater harvesting is common throughout the Mekong Delta region. The current storage method

adopted by many households is to have large ceramic, open-top jars placed adjacent to the

household. This is normally accompanied by an improvised guttering system that channels rainwater

from the roof to the jar itself. However, there are many disadvantages with this method. Firstly the

storage capacity of these jars is limited to a maximum of 1000 litres which is an insufficient volume

to adequately provide for a family of 4 during the 6 month dry season. Secondly, the fact that these

jars are open-top means that there are serious implications for the quality of water stored inside.

When stored water is exposed to sunlight and air, bacteria can grow as well as other water borne

viruses such as e-coli. This exposure also allows the water to be contaminated with impurities such

as debris or insects. Lastly, these jars are prone to breaking and frequently need to be replaced

which places a financial strain on the families.

There are other storage options available in the Mekong Delta such as plastic water tanks.

However, these options are frequently more expensive than the ceramic jars. Table 3 shows the

projected cost of installing a sufficient number of water tanks that will provide for a family of 4

during a 6 month dry season:

Table 3 - Currently available storage options

Storage option Capacity Individual Cost Total Cost

Ceramic Jars 1000 litres $20 $80

Plastic Water Tanks 1000 litres 500 litres

$80 $50

$320 $400

As illustrated, it is far less expensive to install a system of ceramic jars rather than plastic tanks.

However, installing ceramic jars incurs all the disadvantages mentioned previously.

3.1.1 Flow chart of processes Figure 10 illustrates the processes that have to be considered when approaching a final design of the

storage system.

Figure 10 - Storage process flowchart

Water entrance

•How the water will enter the storage system from the guttering.

Storage •Manner in which the

water is stored in the system.

Water access

•How the user can easily access the water when required

22

3.2 Requirements for Storage system

The design concept for the water tank will be based upon the following requirement specifications.

Should any aspect of the tank design not fulfil the requirements table below then it will not be

considered for further development.

Table 4 - Storage URS

Category Requirements

Functional

Requirements Must store 3,600 litres of water (900 litres per person).

Technical Requirements

Must not allow direct exposure to sunlight.

Materials used be available locally in the Mekong Delta.

Tank must be available to build for under $80.

Implementation and on-site construction time must be under 2

weeks to allow for immediate use.

Can be built by an unskilled labourer.

Must safely withstand the internal pressures of the tank at full

capacity.

Operational

Requirements

Water access must have a minimum flow rate of 7.5

litres/minute.

Tank can be easily maintained by an unskilled labourer.

The main problem to solve with the water storage solution is the sheer amount of water that needs

to be stored. To see the average family of 4 through a 6 month dry season, 3600L (900L per person)

is needed for cooking and drinking. Another main factor to consider is the cost of the tank. It must

be affordable on the average wage of a Mekong Delta rice picker to ensure the tank can be

purchased by the people who need it most. The target cost was less than $80 as this is the price to

store the same amount of water using the current ceramic jars. This would make the tank an

extremely attractive option as it would be cheaper and more hygienic. The last major challenge to

face is creating a tank that is hygienic. To do this the tank must be kept out of direct sunlight and

allow minimal exposure to air. This is a significant challenge as the tank must have entry and exit

points for the water.

Research was then conducted into the various methods of rainwater storage currently used around

the world. The methods investigated and the decision matrix are shown on the following page.

23

This m

atrix is based

on

a colo

ur cate

gory an

d q

uan

tified system

. The key fo

r each co

lou

r is sho

wn

(bo

ttom

right) an

d a valu

e for each

colo

ur is given

. The

specificatio

ns are d

ivided

into

‘Mu

sts’ and

‘Wan

ts’. Each sp

ecification

has a n

um

erical value relatin

g to its im

po

rtance w

hich

is then

mu

ltiplied

by th

e

value o

f the co

lou

r, the p

rod

uct o

f wh

ich is sh

ow

n in

the b

ox. Th

e ‘Feasible’ sectio

n is th

e sum

of e

ach sto

rage meth

od

. The m

etho

ds w

ith th

e high

est

values w

ill be th

e on

es that sh

ou

ld b

e furth

er con

sidered

There are several d

ifferent m

etho

ds o

f wate

r storage availab

le to th

e develo

ped

wo

rld. H

ow

ever, as the d

ecision

matrix sh

ow

s, man

y of th

ese do

no

t mee

t the

UR

S.

Table 5 - Decision matrix of different available storage methods

24

3.3 Ferrocement as a material

Ferrocement is a form of reinforced concrete that differs from the conventional reinforced or pre-

stressed concrete that is commonly used in industrial building. The principle difference between the

two is the manner in which the reinforcing elements are arranged and dispersed within the mortar.

The reinforcement for ferrocement normally consists of closely spaced layers of wire mesh that are

supported by rods or poles; cement mortar is then applied over the mesh. The resultant composite

material formed has different behavioural characteristics in terms of strength, deformation and

potential applications.

Although the name implies a ferrous reinforcement, the same characteristics can still be achieved

using materials other than steel meshes or rod. This ensures that the use of ferrocement is not

subjected purely to countries or communities that have quick and inexpensive access to ferrous

materials. Indeed, replacement materials for steel meshes that have been used, either in practice or

purely for experimentation, have included organic woven fabrics such as polypropylene and organic

natural fabrics made with jute, burlap, or bamboo fibres.

Ferrocement also has a very high tensile strength-to-weight ratio and a superior cracking behaviour

in comparison to conventional reinforced concrete. This means that structures made out of

ferrocement can be made relatively light and water tight. Furthermore the malleability of the

reinforcement meshes allows one to easily alter the dimensions of a structure. These characteristics

make ferrocement an attractive material for water tight structures such as water tanks and barges.

The basic construction process for any ferrocement structure is as follows:

1. Initial foundation that is appropriate to the structure being built.

2. Construction of steel rods (or other material) to form a skeletal framing.

3. Attaching mesh to skeletal framing.

4. Plastering of mortar.

5. Curing.

The simplistic construction processes means that only low level technical skills are required and the

fabrication of small scale projects can be performed by an unskilled labourer.

The following conclusions are based on a report on ferrocement water tanks, conducted by the

Science Museum of Virginia:5

1. Ferrocement is an economically feasible material for the construction of water storage tanks.

2. Flexibility of shape, freedom from corrosion, possibility of hot storage, relative lack of

maintenance, and ductile mode of failure are important advantages of ferrocement over

other materials commonly used for low to medium pressure (up to 345kPa) storage of fluids.

3. Ferrocement tanks require less energy to produce than steel tanks.

Therefore ferrocement, as a material, appears to have the largest potential to fulfil the user

requirements specifications.

5http://www.bpesol.com/bachphuong/media/images/book/549r_97.pdf (last accessed 5/3/2013 15:31)

25

3.3.1 Material composition matrix

Ferrocement consists of Portland mortar, reinforcement, admixtures and coatings. To achieve the

appropriate tensile and compressive strength characteristics of the tank it is necessary to perfect the

proportions of the mortar components. This is dependent upon the nature of the sand, chemical

composition of the cement, the water-cement ratio and the curing of the finished tank.

3.3.1.1 Matrix mix proportions

The mix proportions’ ranges for ferrocement mortar are as follows6:

• Sand - Cement ration by weight: 1.4 - 2.5 : 1

• Water - Cement ratio by weight: 0.3 - 0.5 : 1

These ranges have yielded satisfactory results and should be adhered to when constructing the tank.

The quality of sand factors greatly towards a high calibre mortar. Well graded, rounded, natural sand

having a maximum top size of about one-third of the smallest opening in the reinforcing system to

ensure proper penetration. 7 The water used should also be of relatively high quality and free from

contaminated organic matter. The presence of these impurities will weaken the mortar matrix.

Curing the ferrocement once construction has finished is important for attaining the maximum

strength characteristics of the mortar and the prevention of cracking. Curing can be performed by

either wetting the surfaces regularly or covering the structure in polythene sheeting to contain the

moisture. This process must be maintained for at least two weeks before the structure is suitable for

use.

3.3.1.2 Sand

The desirable sand grading for ferrocement mortar is as follows:8

Table 6 - Sang grading scale

Sieve Per cent Passing 3/8 in. (9.5 mm) 100

No. 4 (4.75mm) 95 – 100

No. 8 (2.36mm) 80 – 100

No. 14 (1.18mm) 50 – 85

No. 30 (600μm) 25 – 60

No. 100 (150μm) 2 – 10

3.3.2 Reinforcement

The reinforcement of ferrocement is commonly in the form of intertwined wire that creates a mesh.

Traditionally the mesh layers are attached by hand to a framework of poles and the mortar is applied

to the meshed structure and plastered on either side. The wire mesh acts to distribute the loads

experienced within the tank through the mortar and across the structural frame. However, this

method is liable to create voids on the peripheries of the rods. In fact, U.S. Navy research on high-

performance ferrocement hulls concluded that steel rods were ineffective at reinforcing a structure

6 ACI Committee 549, ‘State-of-the-art Report on Ferrocement’, January 24 1997, p 7.

7 Ibid p. 7. 8 United Nations High Commissioner for Refugees, ‘Large Ferro-Cement Water Tank, Design Parameters and

Construction Details’, July 2006, p. 16.

26

and in some cases are detrimental to the structural stability of the final product9. This is because the

poles are not loaded to take advantage of their strength; the spacing they create when the mortar is

applied allows for regions of unreinforced mortar that contributes to weight but not to strength.

They actually act as stress concentrators. The need for steel rods was eliminated by applying the

mortar to the mesh which is supported by frames made of wood strips, ply wood and even bamboo.

Therefore the requirements for the reinforcement of the ferrocement tank can easily be

accomplished using bamboo for the structural framework and chicken wire as the mesh. Not only

can the same strength characteristics be achieved using these materials but it also eliminates the

need for steel to be used for the framework which saves money on material expenses.

3.3.2.1 Wire Mesh

According to the United Nations High Commission for Refugees,

the ideal type of wire mesh for use in ferrocement structures

should have the following properties.10

1. Must be easy to handle and flexible enough to bend.

2. Galvanized wire mesh is preferable as it is less likely to rust or

corrode.

3. 0.5 - 1.0 mm diameter with 10 - 25 mm mesh opening.

4. Free from grease and anything that might reduce bond.

3.3.2.2 Bamboo

Despite the convenience of using bamboo for the framework, it still needs to well treated before

construction. Untreated bamboo poles have the distinct risk of swelling when in contact with

ferrocement that is settling. Therefore preparation must be taken with the sizing, seasoning and

waterproofing.

Split bamboo is generally more desirable than whole culms as reinforcement. Hollowed

bamboo creates stress concentration points within the ferrocement which can affect the structural

stability of the tank. By splitting the culm in half these stress concentration points are avoided.

Splitting the bamboo can be done by separating the base with a sharp knife then, using a dull blade,

continue this separation throughout the culm.

When possible, the bamboo should be cut and allowed to dry and season at least 3 – 4

weeks prior to construction 11 . Seasoning the bamboo allows it to increase its strength

characteristics. During this process the culms should be supported at regular intervals to avoid

warping.

When seasoned bamboo, either split or whole, is used as reinforcement, it should receive a

waterproof coating to reduce swelling when in contact with concrete. Without any coating the

bamboo will swell before the ferrocement has settled and developed sufficient strength to prevent

cracking. However, only a thin layer should be applied; thick layers tend to lubricate the surface of

the bamboo and consequently the bonds with the ferrocement mortar will weaken. The type of

coating will inevitably depend on the materials available in the Mekong Delta.

9 ACI Committee 549, ‘State-of-the-art Report on Ferrocement’, January 24 1997, p 7.

10 United Nations High Commissioner for Refugees, ‘Large Ferro-Cement Water Tank, Design Parameters and

Construction Details’, July 2006, p. 16. 11

Francis E. Brink and Paul J. Rush ‘BAMBOO REINFORCED CONCRETE CONSTRUCTION’, Port Hueneme, California, February 1966, p.4.

10 -25 mm

Figure 11 - Wire mesh

27

3.4 Availability of materials for construction

When building any structure using ferrocement it is highly important that the ingredients are readily

and locally available. In the research it was ensured that there were two reliable sources of

materials; an ideal first option and a contingency option if the 1st proves to be unfeasible. The

principle materials required for the construction of a ferrocement structure are listed as follows:

• Portland cement.

• Fine-grain sand.

• Potable and organic matter-free water.

• Wire mesh.

• Bamboo poles for frame work.

3.4.1 Portland cement The most readily available cement to the Mekong Delta is Portland cement PCB40 which has various

advantageous characteristics. Its low alkali content helps improve the concrete’s durability and

prevents steel inside the concrete from being corroded by alkali-aggregate reactions, PCB40 meets

the American standards for cement12. This cement is manufactured by a Vietnamese based company

called Thang Long Cement who supplies their products to the Mekong Delta Region. However, if for

some unexplained reason this option is unfeasible then there is a cement factory located in Rach Gia

which is in the Mekong Delta region13. Portland cement can very easily be sourced from this factory.

3.4.2 Fine grain sand

According to the research this is readily available to the communes of the Mekong Delta. In fact the

sand on the banks of the Mekong Delta is used as a source of mortar sand for the whole of Vietnam.

Its quality and abundance fortunately means that there is a plentiful supply of mortar sand available

to people in the Mekong Delta.

3.4.3 Potable water

The water quality of borehole water and harvested rainwater is sufficient enough to yield a good

quality mortar but not water from the river. Borehole wells are accessible to 85%14 of households in

the Mekong Delta whilst all other households already have in place methods of storing large

quantities of rainwater. Rainwater is the preferable option for mixing the mortar as it is of a better

quality than borehole water. However, stored rainwater is obviously a precious commodity so any

opportunity to conserve it must be acted upon. If the use of rainwater proves to be far too

impractical and detrimental to a household then borehole water is of a satisfactory quality for

mortar mixing.

3.4.4 Bamboo: As stated in section 2.4, bamboo is a highly adequate material and ideal for the construction of the

tank.

12

http://thanglongcement.com.vn/en/news/company-news/thang-long-cement-jsc-is-listed-in-the-prestigious-vnr500-ranking-board. Last accessed 03/03/2013. 13

http://www.ewb.org.au/discussions/1273/11437’ last accessed 05/03/2013. 14

http://www.ewb.org.au/explore/initiatives/ewbchallenge/hfhewbchallenge/hfhwash last accessed 01/03/2013

28

Rebar frame

Figure 12 - Ferrocement foundation

3.4.5 Wire mesh:

Wire mesh is a very common material available to everyone in the Mekong Delta at a set price. Sold

at a set width of 1.6 metres it is an essential material for farming and fishing techniques of all

families.15

The table below summarises the ideal and contingency material availability in the Mekong Delta.

Table 7 - Material availability

3.5 Ferrocement foundation theory

The construction of a secure and level foundation is crucial for the structural stability of any building.

The process can often be very time-consuming as well as requiring a large work force. Fortunately, in

the case of small scale ferrocement water tanks, the construction process for a suitable foundation is

not complicated and does not require many labour hours.

As with all building processes, the initial step is to clear all debris and level the site upon which the

storage system will be constructed. After this the topsoil is removed to an appropriate depth. In

cases where structures exert large stresses upon the soil beneath the foundation it is usually

compressed to help it attain maximum strength. This is also necessary for a domestic water storage

system but since the hydrostatic stresses are well below those exerted by large buildings the

compaction does not need to be

extensive. The next stage is to lay the

rebar frames which are normally steel

bars; however, this material may be an

expensive commodity locally. It is

possible, though, to replace the steel

bars with bamboo poles. The rebar

frames provide reinforcement for the

ferrocement mortar that is then

poured on top. There is the option of

placing a layer of gravel beneath the rebar frames, however, this is not essential for small scale

water tanks. The frame work for the tank then needs to be attached to the rebar frames and

embedded into the ground. The frame work provides the skeletal shape of the final tank. After the

frame work poles are inserted comes the final stage of pouring the cement mortar over the rebar

frame. The concrete pad should be left to settle and once dry, building the tank can commence.

15

http://www.ewb.org.au/discussions/1273/11407’ last accessed 07/03/2013

Material 1st Option Contingency

Cement Thang Long cement (PCB40). Local factory in Rach Gia.

Sand Sourced from Mekong River banks. Purchased locally.

Bamboo Bamboo poles from communal farms. Purchase pre-treated bamboo locally.

Water Rainwater from harvested sources. Borehole water.

Wire mesh Readily available at local hardware stores

29

3.6 Water access

The selection of an appropriate, effective tap is an important decision for ease of user interface. A

valve or tap is the only means for the consumer to gain access to the harvested water. A tap

attached to a tank is often gravity fed by the pressure of the water from the tank. It is also safe to

assume that the tap will be in constant daily use. Therefore it is necessary to choose a tap that can

deal with both heavy usage and large pressures without failing or, more importantly, wasting water.

Consideration must also be given as to the ease of pouring the water into a bucket without risk of

waste. To finalise a solution, it is necessary to research the positives and negatives of the different

types of water valves and taps available.

Screw down tap

These taps use a screw valve mechanism and are the most popular type of outdoor tap used by

homeowners. The handle or wheel of the tap is turned by the user and this causes the internal stem

to move up or down, thereby controlling the exit flow of water. However, because of the screw valve

design, these taps tend to wear out frequently and can be difficult to turn after long periods of

disuse.

Figure 13 - Screw down tap Figure 14 - Ball valve hose tap Figure 15 - Loose head handle

Figure 17 - Gate Valve tap Figure 16 - Bent nose hose tap

30

Decision Analysis

Tap types

Mus

t cop

e with

larg

e pr

essu

res

Eas

e of

use

r int

erfa

ce

Wid

e ra

nge

of a

djus

tabl

e wat

er fl

ow

Leng

th o

f tim

e of

func

tiona

lity

Eas

e of

maint

enan

ce /

replac

emen

t

Scr

ew th

read

s to

allo

w a

ttach

men

ts

Saf

ety

agains

t una

utho

rised

wat

er colle

ctio

n

Pre

sens

e of

noz

zle

for e

asie

r col

lect

ion

Feasibl

e

Screw down tap 5 5 5 3 3 1 1 5 28 5 Suitable

Ball-valve hose tap 5 5 3 5 5 1 1 5 30 3 Not quite suitable

Loose-key handle tap 5 5 5 3 3 1 5 5 32 1 Unsuitable

Bent-nose taps 5 3 3 3 3 5 1 1 24 0 Completely Unsuitable

Gate valves 5 3 3 5 3 5 1 1 26

Ball-valve hose tap

Ball valve hose taps use a rotational-motion handle (usually a 90° lever or quarter turn wheel) to

access water quickly and easily. The ball-valve style is a simple yet effective mechanism that is

durable, long-lasting and easy to use. These taps are also available with a nozzle to allow for the

water to be ejected horizontally. However, the tap doesn’t allow for mid-range water flow

adjustment.

Loose-Key Handle taps

These taps function in the same manner as screw down taps however, the handles can be removed

when not in use to control the water. This helps reduce water wastage and prevents unauthorised

water usage. However, the same problems are encountered as the screw down tap.

Bent-Nose Hose Taps

Bent-nose hose taps are screw-style valves attached to vertical pipes that have outlets slanted down

at a 45-degree angle to avoid hose crimping. These taps are generally placed in garden and lawn

areas as a stand-alone water source for hose or sprinkler hook-ups.

Gate valves

Gate valves are controlled by a wheel-style handle. The mechanism allows for adjustable flow

control and requires little maintenance. The valves function well for both high and low pressure

systems and is relatively inexpensive. However, the lack of a nozzle will result in difficulties in

collecting the water and the valve is not very forgiving of grit in water.

Decision Matrix

Conclusion:

From the decision matrix it is clear that the loose-key handle tap best satisfies the user requirements.

The tap has the best combination of both ease of user interface and safety against unauthorised

water collection. However, despite the positive aspects of this tap there is the distinct danger that

the detachable handle can either be lost or stolen, rendering access to the harvested water

impossible.

Table 8 - Tap decision matrix

31

3.7 Concept design Once ferrocement had been confirmed as a viable building

material the procedure of implementing it in a water tank

design was undertaken. Figure 18 shows the concept design

of the tank. The tap was located 10cm above the base of the

tank to allow access to 93.3% of the 4m3. The remaining

water left at the bottom of the tank is used to allow a degree

of debris to be deposited before the water extracted contains

any debris. A wash out pipe of 2.5cm is located at ground

level so if contamination is identified it is possible to evacuate

the tank to clean it. This washout pipe is blocked by a bung.

The initial did not include a roof thus allowing access to the

tank. This also allowed the tank to collect water that lands on

the area. Although this does allow exposure to direct sunlight,

which aids bacteria growth, as filtration occurs after storage;

the problem was considered less important than access to the

tank.

The tank dimensions are 1.5m in height with a diameter of 1.85m. The foundations extend 10cm into

the ground to ensure a secure structure. 20 bamboo poles are used in the outer wall as supports for

the wire mesh to be wrapped around. This means a support every 30cm around the perimeter;

ensuring a pure curve is retained when the wire mesh is wrapped round. A pure curve ensures that

the tank does not experience stress concentrations in corners unlike a square structure. The wall

thickness used is 3cm, as research on current ferrocement tanks used in Western African countries16

revealed this thickness is sufficient, and their African counterparts experience a higher hydrostatic

pressure. The maximum hydrostatic pressure experienced in the concept tank is 15kPa giving the

concept tank a factor of safety of 10. The advantage of a higher pressure is an increased flow rate of

water; however, a more robust wall is required to withstand a higher pressure.

3.8 Design development

3.8.1 Problem Identification

The initial concept achieved some of the URS, however, failed in other key areas; mainly as it

allowed exposure to direct sunlight. Another potential failure was that, although when properly

constructed the tank easily withstood the hydrostatic pressure, the tank was to be constructed by an

unskilled labourer. This may result in thin areas that could result in cracks. Exposure to air is another

problem; that can result in bacteria growth acceleration or mosquito infection and ideally would be

eliminated or minimised.

The tank has a volume of 4m3 due to its height and diameter, but 0.27m3 of this is inaccessible as it

is stored below than the level of the tap and 0.13m3 is not able to store water as it is above the level

of the overflow pipe. This leaves 3.6m3 of accessible water. This meets our requirement, however,

does not allow for a margin of error for the mistakes of an unskilled worker, or for a head of water to

create pressure for the tap. Using hollow bamboo poles was also identified as a possible weakness in

16 http://www.akvo.org/blog/?p=997 last accessed 2/3/13

Figure 18- Design concept for ferrocement tank

32

the design, as with a diameter of 2cm, the poles would only have 0.5cm wall thickness. This

significantly reduces the strength of the tank around the pole areas.

3.8.2 Problem solutions

3.8.2.1 Addition of a Roof

As a result of these problems modifications were made to the tank design. A roof and inlet filter

were added as this eliminated exposure to sunlight achieving another URS target. The roof slants at

a shallow angle into the centre of the tank, meaning water that lands on the tank can flow into it.

This also allowed the tank to be filled with borehole water in the event of a severe drought or similar

event. However, as a slope was required this meant that 10cm at the top of the tank volume was

lost. The inlet filter is constructed of two layers; one wire mesh layer followed by a cloth layer. The

wire mesh first filters out any large debris like leaves and twigs whereas the cloth filters out smaller

particles like sand and silt in borehole water. The cloth layer also stops mosquitos accessing the tank

to breed. To stop mosquitos accessing the tank the overflow pipe was also covered with a cloth layer.

3.8.2.2 Increasing the Diameter of the Washout Pipe

Adding the lid did remove the ability to access the tank insides, however, as it hugely reduced the

chance of contamination and reduced the amount of maintenance. The largest particle that can fit

through the wire mesh is 2.5cm. Due to this, the washout valve diameter was increased from 2.5cm

to 5cm allowing the maximum sized particle to be expelled from the tank easily. To support the roof

two internal walls were added extending from opposite sides of the tank towards each other, leaving

a 10cm gap between them, allowing water flow throughout the tank. This internal wall also

increased the factor of safety of the tank.

3.8.2.3 Increasing Tank Capacity

The diameter of the tank was increased from 1.85m to 1.95m in order to store more water. This left

a margin of error for an unskilled worker. It also equated for the loss of water due to the slope of the

roof. The increase in volume left a volume of 0.28m3 as a margin of error for the unskilled worker

and water pressure.

3.8.2.4 Addition of Basion

To make the tank a more sustainable structure a basin was added to the water access point. This

reduces erosion around the tap area that could potentially compromise the integrity of the

foundations. The basin is dug into the ground which allows easy water access. Without the lowered

basin; there is only a 10cm space to fit a water carrying vessel under the tap. Conversely, with the

basin, this is increased to a 25cm space. This also provides a deeper foundation point as it goes 30cm

into the ground increasing flood resistance

3.8.2.5 Increasing Wall Thickness

Another problem to overcome was the wall dimensions; which could be inconsistent. The wall

thickness was increased to 5cm instead of 3cm to account for this. As a result; there is a large margin

of error in construction in case of wall thickness inconsistency or an incorrect cement ratios.

Hopefully these problems will be minimised by the construction guide shown in Appendix B. This

adjustment resulted in a minimum factor of safety of 36 increasing to a maximum of 39000, as

shown in the structural analysis in Appendix C. This is far in excess of the 10 required for tanks, and

means that the tank is extremely resistant to impacts such as debris in flooding.

33

3.8.2.6 Splitting Bamboo

To solve the problem of using hollow

bamboo poles it was decided to use split

poles for the tank construction. This helps

improve the strength of the tank as there

are no longer cavities in the structure.

Splitting the poles also prolongs the life of

the tank by reducing the bamboos exposure

to air which carries microbes capable of

reducing the strength of the bamboo.

Figure 19 - Magnified view of tank displacements under load

34

3.9 Final design

Washout valve to allow evacuation

if the tank becomes contaminated

(located behind tank)

Overflow valve to stop tank

overflowing, slew gate system

to stop exposure to the air

(located behind tank)

Inlet filter to stop dirt and

debris entering the tank also

reducing exposure to air and

sunlight

5cm thick walls to help withstand

impacts in flood situations

Loose key tap to allow

restricted water

access

10cm foundation to provide a solid

base for flood resistance

Water basin to stop

ground erosion and

reduce water

spillage

Roof slanted to capture

water landing on the area

Internal walls used to support roof

structure and strengthen tank

Cylinder chosen

to reduce stress

concentration in

corners

Tap located 10cm above

foundation to access the majority

of water in the tank and allows any

debris to sink; not contaminating

the access point.

Figure 20- Final tank design

For dimensions please see CAD drawings in Appendix D

35

3.10 Structural Analysis:

The stress analysis of the ferrocement water tank is of critical importance to the success of the

project. If the design fails to cope with the considerable internal hydrostatic pressure then it would

be entirely unfeasible to construct the tank.

The model program used for analysis is SolidWorks Simulation and this report summarizes the

stress analysis results of the water tank simulation. The stress analysis report can be found in

Appendix C.

3.10.1 Analytical Conclusion:

From the stress analysis report, the factor of safety for the tank under the Max von Mises stress

ranges from a minimum of 30 to a maximum of 39000. These values were calculated using a

uniformly distributed pressure within the tank of 15 kPa; the maximum hydrostatic pressure

experienced at the bottom of the tank at full capacity. The safety factor range is far in excess of

what is required to create a water tank, however, as the tank is constructed by an unskilled

worker, this margin of error is required to make up for any mistakes of procedural errors in the

manufacturing process. It is therefore safe to assume that the structure of the tank will not fail

under full capacity and can therefore be constructed.

3.11 Inlet filter

In the URS, one of the requirements was to avoid exposure to sunlight and fresh air. To achieve this,

yet still have the ability for water to pour in through the top of the tank, a special inlet filter has

been designed.

This simple, small, removable device is aimed at preventing mosquitoes and debris from entering the

tank. It includes the same wire mesh used in the walls of tank but here, as a sieve; to remove large

debris. Then, wrapped around the bottom, some cloth/nylon to act as a porous membrane –

allowing water flow, but not silt, dirt or mosquitoes. Combined, these two filters will prevent most

non-microscopic contaminants from entering the tank.

The device is designed to sit in the hole at the top of the tank,

and to be removable when required. Either to remove debris

from the filter or possibly replace the cloth when required.

One of the advantages of this design, is that it can be

constructed with the waste materials from the tank

construction; wire mesh cut-offs and spare cement are all that is

needed to build it.

3.12 Sustainable storage

3.12.1 Life span of Tank

The sustainability of the tank is based on the long working life and minimal damage to the area

around the tank. The tank has a life span of over 20 years; this is due to the construction techniques

used. The material used most susceptible to failure is the bamboo struts; which have a life span of

10 years when they are not in contact with the soil. In our construction, the bamboo is completely

encased in cement which increases the working life of the bamboo. This is achieved by eliminating

Figure 21 - CAD drawing of inlet filter

36

many of the factors that encourage and cause rotting such as exposure to insects and

microorganisms carried in air. The structural integrity of the tank is also a major contributor to the

tanks sustainability. The high factor of safety means the tank can withstand substantial flooding and

other trauma.

The tank is more sustainable than the current clay pots used as they are prone to cracking. The life

span of a clay pot is usually around 10 years which is only half the time of the ferrocement tank. The

mesh reinforcement in the ferrocement makes it highly resistant to crack propagation unlike the clay

pots.

3.12.2 Reducing ground Erosion

Sustainability is also achieved by reducing erosion around the water exit points. All the water exit

points have cement underneath to stop soil erosion from weakening the foundations of the tank.

This reduces the damage caused to the surrounding area of the tank resulting in the foundations

staying solid, due to this; the tank’s resistance to flooding is not diminished over time.

3.12.3 Flood Resistance

The current clay pot method of storage is also very vulnerable to flood damage as with floods of 2-

3m the water pots are often smashed by floating debris or carried away in the rising water. Our

design would ideally be able to withstand such flooding or at least be resistant to the flooding. The

shape of the tank will also be an important design consideration as to reduce impact damage the

tank shape should distribute point loads through the whole structure. The shape should also be a

streamline so the water passes easily round the structure to reduce the force experienced by the

tank. This will reduce fatigue on the structure that will eventually cause flaws and cracks.

3.12.4 Reduced Maintenance

Maintenance on the tank is also minimal which means even when the tank is neglected it stays in

good condition. The design has been made to have very few moving parts to keep this low level of

maintenance. Repairing the tank is also a simple procedure and requires very little cost or skill. If

cracks or weak spots are identified they can be filled with a mix of cement. The repair will need to be

reasonably thick as it will not give the same strength for the same thickness as the original tank due

to the mixes curing at different times.

3.12.5 Locally Sourced Materials

By using locally sourced bamboo and locally manufactured wire mesh the environmental impact of

transporting the materials is reduced. Purchasing or harvesting products from the region, also means

that the money spent purchasing the materials to build the tank, support small local businesses

helping the community as a whole.

3.13 Storage Manufacture

The ferrocement tank has been designed so it can easily constructed by either a single person or a

group of unskilled labourers. This is an essential requirement to keep costs down and give the users

a sense they are building their way to a more hygienic future. The most labour intensive part of the

build is mixing the cement; 1.2m3 is required in total. The maximum recommended amount to be

mixed by hand in the UK is 0.3-0.4m3 per day by a reasonably fit person. This had potential to make

the build unfeasible. The problem is avoided by building the tank in sections. The foundations can be

completed in 1 day the outer and inner walls can be split over 2-3 days and the roof in 1 day. The

37

tank will need to be kept moist over the period of the build to prevent flaws between the dried and

wet mixes. Keeping the tank moist is an essential part of the curing process anyway as the tank

should be allowed to cure over 1-2 weeks to achieve the maximum structural integrity. The Mekong

Delta is an extremely humid region which will naturally aid the curing process; however, the tank will

need to be dabbed with a wet sponge or towel daily as well.

The first draft of an easy to read construction guide can be seen in Appendix B. The intention is to

give the guide to a family in the Mekong Delta that will give them the knowledge to build a more

hygienic water storage solution. A brief overview of the process is given in table 9.

Table 9 - Tank construction process

Step 1 Dig a 10cm deep circle with a diameter of 2.1m

Step 2 Dig a 30cm deep whole where the tap is to be located of oval shape as shown

in the design drawings.

Step 3 Mix 0.32m3 of cement and pour into the foundation hole. (note any cement laid

should be kept moist with a wet sponge or towel for 2 weeks after laying)

Step 4 Split 25 bamboo poles of 5 cm diameter length 1.6m down the middle and

place them in a circle diameter of 1.975m

Step 5 Split 8 bamboo poles of 5 cm diameter length 1.6m and place them, evenly

spaced, in a line across the centre of the tank. ( there should be a slight slope

to the centre of the tank)

Step 6 Next roll the 1.6m tall wire mesh along the internal bamboo struts( Leaving a

10cm gap at the centre of the tank) and around the external circle of struts

Step 7 Mix and paste cement to a thickness of 5cm over the wire mesh making sure to

place the tap 10cm from the base of the tank, the wash out pipe on the tank

floor and the overflow pipe 10cm below the top of the tank

Step 8 Place 40 split bamboo poles of 5 cm diameter length 1m from the top of the

outer wall onto the centre wall creating a centre hole of 10cm diameter to

allow water entry

Step 8 Place the wire mesh over the roof struts

Step 9 Paste cement over the wire mesh to a thickness of 5cm.

Step 10 Create and place entry system in place at the centre of the tank

3.14 Final Costing

For the final costing the amount of material required and the cost per unit is required. The amount

of material was finalised when the design was completed. The requirements can be seen in the

“Amount required” column and the makeup of each material can be viewed in Appendix A. For the

individual costing, research was undertaken; initially using information provided on the Engineering

without borders website for basic materials progressing to using an in country agent who sourced

prices for more unusual building materials and items.

38

Table 10 - Final tank costings

The target price for the water storage tank was under $80 which is the price currently needed to

store enough water to get a family through the dry season using clay jars. Our design costs $12 less

than this making the tank financially appealing. The tank also has the added incentive of being more

robust, easily accessible and hygienic.

3.15 Storage System Conclusion

To conclude, the ferrocement storage tank is the optimum solution for the rainwater harvesting

problems currently endured by families in the Mekong Delta. As well as fulfilling all essentialities in

the user requirement specifications, the design has the added advantages of being both sustainable

and culturally appropriate to the lives of families in the Mekong Delta.

The improvements that this storage design will have upon the current storage methods adopted in

the Mekong Delta will be invaluable. Firstly the design now has the storage capacity to provide an

average family of 4 with enough drinking and cooking water during the six month dry season.

Furthermore, the storage design is easily adaptable to families of varying numbers through our

construction guide. Secondly the tank has reduced, to a bare minimum, the dangers of storing water

for extended periods of time. By having a closed roof with a removable filtration unit at the tank

entrance we have protected the water from sunlight and air as well as preventing debris and insects

from contaminating the water. Lastly the sustainability of our design ensures that the ferrocement

tank’s longevity far exceeds that of the ceramic storage jars currently installed by many families in

the Mekong Delta; not only can the tank be easily maintained by an unskilled labourer but it can also

withstand the regular damaging floods experienced in the region. Yet perhaps the greatest asset to

the design is its potential to be constructed on site without the need of importing any pre-

manufactured components.

The research conducted into the Mekong region has ensured that all the necessary materials

required to build the ferrocement tank are locally and readily available. This advantage has not only

reduced the financial burden to families but has also afforded them the opportunity to construct the

tank themselves without depending upon specific or bespoke components. The only detriment to

the construction process is the lack of quality control of the final tank. However, this is compensated

by the fact that the stress analysis has given the structural integrity a factor of safety of 30. Such a

high safety factor compared to what is normally acceptable in buildings does allow for the lack of

construction skill. Nevertheless this design is vastly more inexpensive than the price of the cheapest

Material Amount required Cost per

unit Individual material cost Total cost

Cement 0.236 m3

= 354 Kg $0.086 $30.44

$67.81

Sand 0.944 m3

$7.20 $6.80

Wire mesh 9.65 m (1.6m tall rolls) $1.80 $17.37

Bamboo 82m $0.10 $8.20

Loose key tap 1 $5.00 $5.00

39

equivalent storage method available to families in the Mekong Delta. The table below compares the

prices of the two methods for roughly the same amount of storage capacity

Table 11 - Cost comparison

Storage Method Capacity Total cost for equal storage capacity

Ceramic Jars 1000 litres $80

Group 17 Ferrocement tank 3,600 litres $67.81

Table 12 displays the user requirement specifications previously given on page 21. An additional

column has now been added to confirm the storage design has successfully fulfilled a specific

requirement.

Table 12 - Tank URS check

Category Requirements Status

Functional

Requirements Must store 3,600 litres of water (900 litres

per person).

Technical

Requirements

Must not allow direct exposure to sunlight.

Materials used must be available locally in

the Mekong Delta.

Tank must be available to build for under

$80.

Implementation and on-site construction

time must be under 2 weeks to allow for

immediate use.

Can be built by an unskilled labourer.

Must safely withstand the internal

pressures of the tank at full capacity.

Operational

Requirements

Water access must have a minimum flow

rate of 7.5 litres/minute.

Tank can be easily maintained by an

unskilled labourer.

40

Water Filtration

Callum Stephen & Nicholas Sidwell

41

4 Filter Solutions Access to clean drinking water is a basic necessity for humans. Dirty water and poor sanitation kills

over 5000 children every day around the world17. Reports show that 61% of people living in rural

Vietnam do not have access to clean drinking water; what’s more 80% of diseases in Vietnam are

water borne diseases such as Cholera, Typhoid and Malaria18. Currently the traditional methods of

water collection involve rivers, ground water and rain water from the roofs of homes stored in large

open topped ceramic jars. The water does not undergo any sort of filtration so diseases are rife.

Contaminated drinking water can cause diarrhoea, cholera and many other diseases. Contamination

occurs mainly from:

Bacteria: bacteria build up is common in stagnant water

Viruses: Viruses such as Hepatitis can develop in unfiltered water

Pollution: Vietnam is a developing country and new industry has resulted in widespread

pollution of the rivers

Mosquitos: Mosquitos lay their eggs in stagnant water which spreads Malaria

Water borne diseases have knock on effects for families; if one of the parents in a family becomes

unable to work due to illness or death, the children will be required to begin work at an earlier age,

impeding their education. This can have more widespread effects on the country as a whole. If the

occurrence of water borne diseases can be reduced by filtration and education then it will ultimately

help Vietnam to prosper and develop into a More Economically Developed Country.

4.1 User Requirement Specifications

The design concept for the water filtration system is relatively simple; a system must be designed to

take dirty rain water and pass it through a filter so that it is safe to drink for the people of the

Mekong Delta. Currently there is a variety of different water filtration techniques used around the

world but not all of these are viable solutions for Vietnam. Table 13 shows the Musts and Wants for

our water filtration system.

17

http://www.unicef.org/publications/files/UNICEFAnnualReport2004_eng.pdf 26/2/13 18

http://www.ngocentre.org.vn/content/80-diseases-vietnam-caused-polluted-water-resources 27/2/13

42

Table 13 - Filtration URS

Category Musts Wants

Functional

Requirements

Must have a flow rate >3 litres/day per

person in a household

Technical

Requirements

Must filter >90% organic materials

(bacteria) out of the water

Remove dissolved substances

(e.g. salt)

Must have zero power requirement for

operation

Materials are available locally

Must reduce water to <5% turbidity Compatible with other

methods of filtration

Must be able to operate at atmospheric

pressure

Materials are renewable

Must cost <$10

Operational

Requirements

Must be easy to operate/maintain by an

unskilled worker

Fit discretely in household

(0.5m x 0.5m x 1.5m)

43

A selection of water filtration techniques has been considered against the URS by using the decision

matrix shown in table 14. The Musts and Wants have been ‘weighted’ with a value designating there

importance; this score is then multiplied by how successfully the filtration method accomplishes that

requirement. The filtration method with the highest overall score can be considered the most

feasible option and will be carried on for further development.

4.2 Potential Filtration Techniques

Based on the decision matrix, there were two methods requiring further consideration:

1. Slow Sand Filter (136/140)

2. Clay Pot (137/140)

4.2.1 Slow Sand Filter

Used in both the 1st and 3rd world this method can be used both municipally and on an individual

scale. Dirty water is passed through several layers of sand and gravel moving from the smallest

granule size to the largest. During the first 10 days a gelatinous layer forms in the top millimetres of

fine sand within which bacteria begins to grow; this layer (known as biofilm) traps foreign matter

and any organic objects are degraded and absorbed by the bacteria. Due to its relatively simplistic

design small filters can be constructed in the home, whilst its unique biofilm layer means that

maintenance is cheap, unskilled and only required on a monthly basis. The compact design allows it

to be left free standing indoors with the potential of being combined with other methods, such as

aeration, to improve water quality.

4.2.2 Clay Pot

Is a very simple method for producing clean water, first used almost 1000 years ago in China. Wet

clay is mixed with a fine-grained organic waste material such as rice husk and then fired; the organic

material burns away during firing, leaving small holes in the clay. This new porous material when in

the shape of a pot is an effective filter for removing more than 90% of bacteria from water. This

simple design can be mass produced using a kiln or fired on an individual scale using certain manure

firing techniques. Its flow rate is lower than many of the other filter techniques but is more than

adequate to meet the needs of a family in the Mekong Delta.

Table 14 - Filter Decision Matrix

44

4.2.3 Why the Clay Pot?

After a secondary comparison the clay pot was selected for several reasons:

The large number of component parts for the Sand filter makes it harder and more

expensive to transport.

The materials required for the clay pot are far easier and cheaper to source, as rice husks are

a waste product from the large rice industry in Vietnam.

Clay pots are simpler to test for faults during the large scale manufacturing process

compared with individually constructed slow sand filters.

4.2.4 How the clay pot Works

Clay has been used by humans since the Neolithic period to make pots and bowls; nowadays

ceramics have been used in all areas of life from buildings to art. There are many different types and

combinations of clay in the world some of which are useful and some which are not. Dry Clay’s

properties are dictated by its material composition as well as the firing process (duration and peak

temperature). Several varieties of clay can be used in pottery however, the final product’s

characteristics are primarily dependent upon the firing process. The majority of pottery in the world

falls into three categories: Earthenware, Stoneware and Porcelain.

A key aspect to this design is derived from Earthenware Pottery; whereby if the dried clay is fired to

beneath 1000 degrees Celsius the resulting product remains porous. This is the base for the water

filtration process as any water passing through this porous material will be filtered of all solid

particles (reducing turbidity) and a large proportion of bacteria. However, these pores are very small

resulting in a very low rate of flow meaning the filter would not provide enough clean water to

sustain a family. For this reason, as previously mentioned, a fine-grained inflammable material,

intended to burn away during firing, is added to the clay mix. This process creates small gaps or

pores in the clay which reduces the effective thickness of the pot and therefore increases the flow

rate without reducing the vessels integrity or the quality of the water filtration.

Figure 22 demonstrates the flow of water through the filtration system.

Figure 22 - Filtration Process Flow Chart

Dirty Water

•Small quantity of water stored before filtration in ceramic pot

Filtration •>90% of bacteria removed

•Turbidity reduced to <5%

Clean Water

• Large quantity stored after filtration

• Accessed via tap

45

Figure 23 shows how the pore size in the fired earthenware clay compares to other objects such as

human hair and bacteria. It demonstrates quite clearly how small the pores are in the clay at only

0.2μm which is ten times smaller than the size of bacteria thus any bacteria present in the water will

not be able to pass through the filter. However, viruses are much smaller so the pores will have no

effect on them. This is why there is a need for a secondary chemical filtration method.

4.2.5 Silver Nitrate Solution

The main problem with the Clay Pot design is its inability to kill viruses and bacteria present in the

water. To overcome this shortcoming silver nitrate solution can be painted onto the surface of the

pot which acts as a biocide. The silver ions kill pathogens in the water as the water is filtered through

the pores in the clay pot; it also prevents the build-up of bacteria within the pores.

Figure 24 is a flow chart outlining the filter actions at work in the ceramic pot.

Filtration at work in clay pot

Physical Sieving

Bacteria and dirt cannot pass

through microscopic pores

Chemical Action

Silver ions kill bacteria and

viruses

Figure 23 – Pore Size

Figure 24 - Filtration Processes

46

4.3 Filtration System Development

The Filtration process will consist of two main parts, the Clay Pot that filters the water and the

plastic barrel for clean water storage. Figure 25 shows the component parts of the system.

The proposed filtration system consists of two main parts: the Clay Pot and the Plastic Water Barrel

as shown in Figure 26. The clay pot rests on the top of the plastic barrel by its lip and water is filtered

through the clay pot into the plastic water barrel. Clean water then sits in the plastic barrel until

needed by the user when it can be accessed via the plastic tap. The pot and barrel are independent

of each other so should either part be broken or damaged they can easily be replaced.

Clay Pot Filter

Clay Pot

Clay Rice Husks Silver Nitrate

Solution

Plastic Water Barrel

Plastic Barrel Plastic Tap Plastic Lid

Figure 25 - Filter Composition

Figure 26 - Exploded View Of Filter System

47

4.4 Clay Pot Filter development

4.4.1 Rice Husk and clay mix

The Most crucial aspect of the clay pot design is the ratio of clay to burn-off material (Rice Husk) as

this alters both the flow rate and the effectiveness of filtration. However, it must be noted that the

clay is porous and will filter water without the inclusion of the burn-off material. When looking at

the URS, three Musts for the clay pot are dependent upon the rice husk mix. Too much rice husk

reduces the pots effective thickness increasing the likelihood of incomplete filtration and lowering

the vessels strength encouraging breakages. In contrast, too little rice husk causes an inefficient flow

rate incapable of supplying the required amount of clean water for the family. A clay: rice husk mix

of (3:1) will give the right balance of high quality filtration and an appropriate flow rate of about

3.2L/hour for the user.

4.4.2 Filtration Zone

During the filtration process it is clear that the fastest rate of flow through the clay pot will occur

between the outside and inside faces of the pot’s base. Therefore, to increase flow rate and

filtration efficiency, this surface area must be maximised to ensure as much water as possible passes

through this zone.

To achieve this objective an internal angle of 94°

between the pot base and side wall was selected (as

seen in Figure 27). This angle creates a base with a

similar area to the open top of the pot whilst still

creating a tapering/cone effect for the side surface. The

cone effect, as opposed to a completely cylindrical shape,

reduces the contact between the pot’s sides and the

plastic barrel’s top edge during removal of the pot. Any

contact between these two surfaces will cause friction

which can damage either unit as well as creating

difficulties for the user. As part of the maintenance

process it is important to make the removal of the pot as

simple and easy as possible to ensure cleaning is carried

out; otherwise the quality of filtration will drop

increasing chances of incomplete filtration.

4.4.3 Clay Pot Capacity

Due to the rate of flow stated above the system requires the user to fill the filter with dirty water,

probably at the beginning of the day, and return at a later time, after filtration has occurred, to

collect the clean water. The farmers of the Mekong Delta work long hours in the paddy fields to earn

their wages and it is therefore crucial that other aspects of their day to day lives are made as simple,

easy and quick as possible. Therefore, it is important that the filter must be filled as few times as is

necessary per day. To end this both the clay pot and the plastic barrel must have a large enough

capacity to cope with this.

Internal Angle 96°

Figure 27 - Clay Pot Internal Angle

48

When considering a realistic capacity for the pot there are several other aspects that will be affected

Table 15 shows the positive and negatives of having a greater capacity and therefore a larger pot.

Table 15 - Pros and Cons of a Larger Clay Pot

Positives Negatives

Reduced Frequency of refills Material Costs are greater

Faster filtration rate (increased active filtration

surface) Transportation is harder

Reduced stability for whole filtration system

Increased strength requirements for barrel

Greater chance of faults during manufacture

Firing Costs are greater (fewer pots per kiln)

After considering these outcomes it was decided that a pot with capacity of approximately 13L

would be appropriate as this could provide for a family of four with only one load per day.

Consequently, the pot would only weigh 11 kg empty making it easy to carry and its dimension

would allow at least 80 pots to be fired in a standard Vietnamese industrial kiln.

It is important that the barrel can store a considerable amount more clean water than the clay pot

can store. Otherwise it is highly likely that the system will overflow; not only wasting water but

increasing the likelihood of contaminating the already filtered supply. As the clay pot will be situated

inside the plastic barrel there are two figures to be considered: the plastic barrel’s standard capacity

and the barrel’s effective capacity (standard capacity minus the clay pot). It is the effective capacity

that states how much clean water can be held by the barrel. In order to incorporate a degree of

safety for the system it was thought the barrel should be able to contain at least five days of filtered

water, without being emptied, this equated to 65L of effective capacity. Figure 28 shows a flow chart

of the storage and flow rate of the whole system.

49

Figure 28 - Final Filter Process

4.4.4 Pot Lip

By manufacturing the pot with a 2 centimetre lip on the

outside edge of the rim, as seen in figure 29, the system

benefits in two ways. Primarily, the pot is more user friendly as

it is easier to lift and therefore easier to manoeuvre when

being cleaned; encouraging more frequent cleaning and thus a

more hygienic system.

The secondary benefit arises from the marriage of the clay pot

to the plastic barrel. The lip creates an overlap enabling a

smarter fit improving the aesthetics of the system but more

importantly acting as a barrier again dirty water leaking into

the barrel and contaminating the already filtered reservoir.

This is a simple solution to a problem that is capable of being

highly detrimental to the effectiveness of the filter. The additional clay required for the lip is

negligible in comparison to the rest of the pot and is very simple to manufacture, which makes it an

inexpensive addition to the design.

4.4.5 Shrinkage during Firing

During the moulding process Clay is referred to as plastic clay, where it is highly malleable due to its

high water content (approximately 10-30%). However, expanding water in the firing process can

easily cause failures in the products; to avoid this, pots are dried to a state of <5% water content

before being placed in the Kiln. The firing process takes further care to avoid expanding the

remaining water too rapidly; however, the secondary outcome of evaporating water is shrinkage of

the product. After firing, clay products will shrink up to around 10% of their original size; in pots and

vases this shrinkage normally manifests itself in the wall thickness of the vessel rather than the

larger dimensions such as height or overall width.

To account for shrinkage two sets of dimensions are required: one before firing and another after

firing. Obviously, all dimensions discussed for the final product are for the pot after firing.

Clay Pot •13L stored before filtration

Filtration •Flow rate of 3.2 L/hr

Water Barrel

• >65L stored after filtration

• Accessed via tap

Figure 29 - Pot Lip

50

4.5 Chemical Treatment of the water From our research it became clear that although the ceramic filter was very good at removing

particles suspended in the water it was not very good at killing bacteria and viruses. This meant that

another purification process would have to be implemented in order for the filtered water to adhere

to the SPHERE standards for water quality.

4.5.1 Water Treatment Chemicals

There are various chemicals that can be used to treat water to make it safer for consumption:

Algaecide: an algaecide is a chemical such as copper sulphate that can be added to water to

prevent the build-up of algae

Chlorine: chlorine is a very effective disinfectant that is widely used to kill pathogens in

water

Sodium Bicarbonate: Sodium Bicarbonate can be added to acidic water to increase the pH

Muriatic Acid: Muriatic Acid can be added to alkali water to decrease the pH

These are but a few chemicals that are used to treat water around the world. The main problem

with the water in the Mekong Delta is the build-up of bacteria and viruses in the water supply. Since

the main source of water is rain water there is no need to alter its pH as it should be fairly neutral

assuming they do not get acid rain in the area and an algae problem is highly unlikely as the water is

being stored in a sealed ferrocement tank so there will be no sunlight enabling algae to grow.

Thus if the water is to be treated by chemicals it should be treated by a disinfectant as the build-up

of pathogens is the main issue in the Mekong Delta. Chlorine is a very effective biocide which would

fulfil this role; however, the problem with chlorine is that it has to be added to the water either in

the storage tank or to the filtered water. This would work but it is an added cost and makes the

whole process more complicated; which encourages the user to miss this stage out due to lack of

education or lack of money for the chlorine.

A chemical that can treat the water that does not get used up or have to be replaced is what is most

appropriate for the Mekong Delta.

4.5.2 Silver Nitrate Solution

Silver is a biocide that has many different applications; it was used by NASA on the space shuttle

Orbiter to treat the water on board and is used widely in medical applications to prevent the build-

up of bacteria in wounds. Silver Nitrate is currently used in conjunction with a ceramic water filter in

Cambodia which has resulted in a 46% reduction in diarrheal diseases, a 95.1% reduction of E.coli

and lab tests have shown a 90-99% reduction of viruses.19 The silver does not get depleted during

the filtration process so remains effective throughout the lifetime of the pot. It does however,

reduce the frequency the pot has to be cleaned as the silver ions help prevent bacteria growth inside

the filter thus reducing the maintenance requirements on the user. One thing to note with the silver

solution is the need to filter around 3 pots worth of water before use; this will make sure that any

chemicals that leach out of the pot do not contaminate the water supply.

19 http://www.rdic.org/ (last accessed (5/03/2013)

51

4.6 Plastic Barrel Development The plastic barrel sits under the clay pot and as water filters through the pot it gathers in the barrel

where it sits until it is required by the user. The plastic barrel must be:

Strong enough to support the clay pot and withstand any impacts

Made of a high quality plastic that does not contaminate the filtered water

Made of a transparent plastic so that the water level can be seen

Be large enough to store water for at least five days

4.6.1 Types of plastic

There are a vast range of plastics used for all sorts of applications in everyday life. The plastic used

for the barrel must be a high quality plastic that satisfies all of the needs above. Table 16 shows a

few of the more common plastics along with an example of their use.

Table 16 – Types of Plastic

Type of Plastic Example Application

Polyethylene Terephthalate (PET) Water bottles and food packaging

High Density Polyethylene (HDPE) Milk cartons and buckets

Low Density Polyethylene (LDPE) Carrier bags and films

Polypropylene (PP) Microwaveable containers

Polystyrene (PS) Electronics Packaging

Some of these plastics are clearly not suitable for manufacturing a robust plastic barrel such as

polystyrene due to its poor structural properties.

HDPE is much better suited to manufacturing plastic barrels; it is a very strong and rigid plastic that

is resistant to wear and tear. It also safe to use in food products as it does not leach out any harmful

chemicals that could potentially contaminate the water and has a very low absorption of water

making it ideal for storing liquids. HDPE is transparent which allows the user to view the water level

within the bucket making the system more practical in the home.

4.6.2 Initial Design

The initial design as shown in the exploded view Figure 30 shows a

blue plastic barrel with the ceramic filter inserted at the top with a

plastic lid that sits on top to keep the contents clean.

The plastic barrel sits at a height of 660mm and a diameter of

500mm at the bottom. These dimensions were chosen with

functionality in mind, it gives the barrel an operating capacity of

approximately 85L with the filter in place which is more than

enough for the average families daily requirements. The system is

relatively small so can easily be placed in a house without imposing

on living space. The barrel has a wide base making the potentially

top heavy system much more stable thus reducing the chance of the

system being knocked over and the ceramic filter breaking. The lip

on the ceramic pot is slightly larger than the diameter of the barrel so Figure 30 - Exploded View of Initial

Design

52

if any dirty water is spilt while filling the filter it will not mix with the clean water but instead either

trickle into the filter or end up on the floor which is better than contaminating the filtered water.

4.6.3 Changes in the design

The main development in this design is the change of the colour of the plastic barrel from blue to

transparent. This was for a number of reasons, blue dye in the plastic prevents the user from being

able to see the contents of the container. Also following further research into Food Grade HDPE it

was found that not all plastic dyes were Food Grade as some dyes can leach into the contents of the

barrel. This posed an unnecessary hazard to the user so the decision was made to remove the

pigment making the barrel much safer and easier to use.

4.6.4 The Lid

The need to keep the filtration element clean and free from insects was identified so to solve this

problem a lid was designed for the system. It is a very simple solution; the lid is a piece of HDPE that

sits on top of the filter preventing dust or insects from contaminating the water supply. It has a

handle to make it easy for the user to remove and replace when they wish to top the system up with

water.

4.7 Detailed filtration design Figure 31 shows a cross section of the Full System annotated with the key design features of the

system.

Figure 31 - Detailed Filter Design

This system fulfils all of the URS musts outlined at the start of the project. It is both affordable and

well suited to households in the Mekong Delta Region.

53

4.7.1 Key Dimensions

A summary of the key dimensions are shown in figure32 below.

Figure 32 -Key Dimensions of detailed design

These dimensions were chosen with the user in mind; at 660mm tall and 541mm diameter the

system can easily be placed on a surface in the corner of a room whilst still being large enough to

hold a considerable amount of water at 85L which is far more than the average family of 4 would

require in a day.

4.7.2 Clay Pot

The pot has a diameter of 300mm and a height of 220mm which gives the pot an approximate

capacity of 13L. These dimensions were chosen for a couple of reasons: any bigger and the pot

would become too heavy to be supported by the plastic barrel but any smaller and it would be

impractical for the user as they would have to make numerous trips from the tank in order to filter

enough water for the day.

The technical drawings for each part can be found in Appendix D.

54

4.8 Manufacturing Filtration System

4.8.1 Manufacture of Clay Pot Prototype in the UK

The aim of the Prototype phase is to produce a batch of Clay pot Filters, manufactured to the final

specifications seen in Appendix D, in order to run a final feasibility test in the UK. This process

ensures that the Clay pot design meets its requirements prior to the large investment in capital

required to begin production in Vietnam.

4.8.2 Clay Mix

It has already been explained in section 4.2.4 how there are many different types of clay and pottery

throughout the world; therefore it was crucial that the clay used for the UK prototype was similar if

not the same as Vietnamese clay. If standard British clay was used then it is likely that a different

flow rate and filtration effect would occur, making the UK tests inaccurate and to a large extent

pointless.

To ensure an accurate sample of clay was used a professional clay manufacturer was contacted

(Potclays Ltd.). It was highlighted that as the Vietnamese Mekong Area is a Delta Region the clay has

a high silt content (similar to Egyptian Nile clay); to mimic this, a mix of red clay/fireclay and sand in

a ratio of 3 to 1 would be appropriate. To further replicate the conditions in Vietnam this mix would

be provided as a powder which can then be mixed in a 4-1 ratio (powder to water) in order to form a

plastic malleable clay. The powder mix represents the common Vietnamese practice of transporting

clay in the form of dried bricks before grinding them into powder at the factory; this method will be

discussed later in section 4.9.

The cost and manufacturing time for producing the mixture in the UK can be seen in table 17.

4.8.3 Clay Pot

One major benefit of the clay pot filter is its manufacturing versatility; the shape of the pot is of

tertiary importance after the firing process and rice husk mix. This allows the pot to be formed from

any pottery technique and also that the prototype can still be an accurate representation of the final

product if produced using a difference moulding technique. To produce the batch of prototype pots

and for extra information on the technique, a local potter (Hugh Penney) was approached. Hugh

runs a small business producing pottery using the traditional turning method and a small kiln.

This is the key point in the project when the shrinkage of the clay pots during firing can be assessed.

After firing the diameter of each pot’s lip must be measured to ensure that it is the correct

dimensions to properly connect with the plastic barrel. If the pots are unsuitable the dimensions for

the wet clay pot must be altered and the prototype process carried out again. The cost and

manufacturing time for the pot production can be seen in table 17.

4.8.4 Testing

Once the Clay Pot is complete it must be tested in several ways:

Water quality is the most important condition. The clean water must meet the requirements

for levels of bacteria and turbidity stated in the URS. If these objectives are not fulfilled then

reasons for this must be located and analysed.

Once adequate water filtration has been confirmed the flow rate must be measured for two

values:

55

The real time flow rate must meet the requirements stated in the URS in order to meet the

volume of water required per day by a family.

The second step is to measure the variation in flow rate within the batch of pots. The flow

rate error can be no more than ± 0.3L. This is important because in Vietnam the flow rate is

the primary method of checking a clay pot is functioning properly. If the error is any greater

than this it becomes unclear whether a pot has a leak allowing dirty water through.

4.8.5 Costs

Table 17 shows the costs and manufacturing time for the UK production of both the clay mixture and

the clay pot.

Table 17 - Filter Costs

Component Quantity Cost (£) Time (hrs)

Clay mix Total 200kg 154 8

-Clay 150kg 64

N/A -Rice Husks 50kg 15

-Labour costs N/A 75

Firing

16pots

234 76

-Kiln 120 72

-Labour 60 4

-Contingency 54 N/A

Total 16pots (200kg) 388 84

56

4.9 Manufacture in Vietnam Figure 34 outlines the complete manufacturing process for the clay pot.

Figure 33 - Clay Pot Manufacturing Process

4.9.1 Sourcing Clay Mix

Due to the filters completely functional role

the clay used does not require any other

traits than being unfired. This makes

hollow clay bricks, seen in figure 35, the

obvious choice because they are abundant,

inexpensive and easy to transport. The

bricks must, firstly, be broken up and

ground into a powder to allow mixing with

the rice husk; this can be done by hand

using hammers but there are also several

machines capable of this process. One

commonly used machine is a rice hammer

mill seen in figure 36, primarily designed to separate

rice husks from rice crops; however, it can

effectively crush lumps of clay into powder.

Hollow Dry Clay bricks are broken down to

form a powder

Powder Clay and Rice husk are mixed and

water is gradually added to form a paste

Clay mixture is made into approx. 12kg bricks

Bricks are put into the press and the ceramic pot shape is formed

Pots are removed from press, dried for a couple

of hours in the shade and inspected for any

cracks

Surface of pot is smoothed, any pots that

failed the test are remoulded into a brick

and pressed again

Pots are left to dry in the sun for 10 days to make sure there is no

moisture left in the clay

Pots are slowly fired in a kiln at roughly 900°C

Soak the filters min 5hrs and then test flow rate. Should be approx 3L/hr

Allow filters to dry fully Apply Silver Nitrate

Solution to each filter Package filter and

distribute

Figure 34 – Dry Bricks

57

Figure 35 – Hammer Mill

Figure 36 - Press Mould

Once the clay is in powder form it is mixed with the rice

husk and water in a 3:1:1 ratio thus producing a plastic

clay mix ready to be moulded. Rice husk is a waste

product from rice farming in the paddy fields; therefore

it is very cheap but could also be used in a trade in

scheme. Whereby, farmers supply the required amount

of rice husk for their personal filter or a reduction in

price. The mixing process is best carried out in a cement

mixer or other such machine in two stages: firstly, the

clay powder and rice husk are added and mixed for 10

minutes; secondly, the water is added and mixed for

another 10 minutes. Once this process is completed the

clay has changed from a powder to a malleable lump

and is ready to be moulded.

4.9.2 Clay Pot Moulding

There are many different methods of moulding clay, each with its own pros and cons, the most

commonly used techniques include: Pressing, Turning, Hand Building, Injection and slip casting. As

previously stated the versatility of the Clay Pot Filter means it can be moulded using the majority of

these techniques and still work effectively.

Press moulding was selected as the most appropriate method for this manufacturing process due to

its ease of use and short process time. Figure 37 shows a standard Hydraulic press for moulding Pots;

this machine is operated by a single worker and can produce approximately one pot per minute,

however, as this is a standalone machine other workers are required to transport the pots if this rate

of work is to be maintained.

The moulding process consists of a plastic clay block (3

parts clay, 1 part rice husk, 1 part water) weighing

approximately 12kg being placed between a male and

female mould protected by plastic sheeting. The operator

pulls the handle to activate the hydraulics pressing the clay

into shape and then removes the excess clay being pushed

out between the moulds. The pressing lasts 10 seconds

before releasing the pot which is ejected by three pins.

At this point the Pots must pass the first quality control

test; consisting of a visual observation, checking the

general shape and thickness of the product. Any pots that

fail this stage can quickly be collapsed and returned to the

pre-moulded stock of clay.

4.9.3 Drying and Firing

After being pressed the pot must be extensively dried

before firing; this is a key process as rapidly expanding

water during firing is the most common cause of failure inside the kiln. To achieve the required

moisture content the pots are primarily dried for four hours in the shade immediately after the

58

pressing process before being moved outside to dry for 10 days. During this period contact with the

sun and windy conditions is encouraged but contact with rain is a major setback for the process.

At this point a second visual quality control check takes place; whereby any pots that have collapsed

or cracked during the drying process are removed. These pots can be returned to the powder stage

but must be crushed separately to the clay bricks as they already contain rice husk.

Once successfully dried the pot is moved to the kiln for firing. Due to the large pottery industry in

Vietnam kilns are common and cheap to construct from clay bricks. A kiln with 5 metres squared of

floor space and an internal height of 1.6 metres (a standard industrial size) can fire 100 pots when

stacked correctly. Figure 38 shows the firing process inside the kiln.

Figure 37 - Firing Process

4.9.4 Reusing discarded Pots

100⁰C

•Maintained for 2 hours

•Removes last elements of water

•If fractures occur kiln can be stopped and clay reused

600⁰C

•Temperature gradually increased past this value

•Vitrification begins (chemical make up of clay begins to change)

•Rice husks burn away

850⁰C •Takes 8-10 hours to reach this point

•Maintaind for 9 Hours. Complete Vitrification occurs

0⁰C •Fuel removed, kiln left to cool for up to 24 hours

•Clay Pots removed and ready for testing

Figure 38 - Recycling Process

59

Figure 39 demonstrates the feedback system for returning failed pots to a previous stage in the

manufacture process thus saving on material costs. The feedback loops clearly show the reuse of

failed pots can only occur before the filter is fired above 100⁰C, as once vitrification occurs the

chemical makeup of the clay changes and it will no longer return to its plastic state used for

moulding.

4.9.4 Treating with Silver Nitrate

After the pots have been fired and tested they are painted with the silver nitrate solution.

4.9.5 Making the solution

The silver solution painted on the surface of the pot is a very dilute solution. To make the solution

water and silver nitrate crystals are all that is required.

100g of silver nitrate crystals is mixed with 1.5L of water-this makes a concentrated solution

0.1L of the concentrated solution is diluted with 18L of water, this forms the silver solution

and will cover approximately 50 pots

The solution is very simple to make but these quantities should be followed closely because if the

solution is too weak then the silver will not have its desired effect and too strong it may be toxic.

Note: the silver solution should be kept in an air tight container as silver nitrate oxidises upon

contact with air.

60

4.9.6 Applying the Silver Solution

The silver solution should be painted on all the surfaces of

the pot using a paint brush as shown in Figure 40 and then

left to dry. The silver solution will soak into the pores

where the silver will form and act as a biocide. When the

silver solution has dried on it will not be apparent that it is

even there. Around 30% of the silver solution will leach out

of the pot so it is recommended that around 3 potful’s of

water are filtered and discarded prior to initial use.

4.9.7 Cost of Silver Solution

The cost of silver solution is very low at around 16p per pot. 100g of Silver Nitrate Crystals can be

bought in the UK for £120 which is enough to make a solution for 750 pots. It is anticipated that this

cost will be even less in Vietnam but gathering an accurate price has been difficult so the UK price is

being used for the final costing.

4.10 Water Butt Manufacture

4.10.1 Plastic Barrel

The plastic barrel is to be manufactured using Plastic Blow Moulding, this method is ideal for making

hollow containers such as a plastic barrel. There are 3 main stages in blow moulding outlined below:

Injection: Molten plastic is injected into a pre-heated mould of the barrel.

Blowing: Air is then injected into the mould “inflating” the plastic so that it takes on the

shape of the mould, in this case the barrel

Ejection: The mould is cooled and the finished product drops out. It then undergoes quality

testing to make sure there are no flaws or leaks in the plastic as cracks in the barrel are a

haven for bacteria

Figure 40: Blow Moulding

Figure 39 - Painting the Pot with Silver Solution

61

Moulds for the barrel would have to be manufactured typically from steel or an aluminium alloy.

This would entail a large start-up cost should this design go ahead but the money would be

recouped if it was done on a large scale.

4.10.2 Plastic Lid

The plastic lid consists of two parts; the lid and the handle. Both of these parts will be manufactured

using plastic injection moulding and then joined using two screws as shown below in figure 42.

Figure 41 - Joining the Handle to the Lid

4.10.3 Plastic Tap

The tap is a more complex shape to manufacture and has moving parts. Plastic Taps are readily

available in Vietnam either imported in bulk from China or available at local markets so it would be

better to buy these parts in for around $1.50 per tap opposed to manufacturing them on site. An

example of the type of tap required for the design can be seen below in figure 43. This kind of tap

can easily be screwed into the hole in the barrel making assembly trivial.

Figure 42: Plastic Tap

62

4.11 Manufacture Costing Table 18 - Manufacture Costs

Component Cost ($)

Clay Pot 2.60

-Clay 0.35

-Silver Nitrate 0.25

-Rice Husks N/A

- Overhead 2.00

Plastic Barrel 3.50

Plastic Tap 1.50

Plastic Lid 0.50

Total 8.10

63

4.12 Filter Conclusion The Ceramic Water filter fulfils the URS outlined at the start of the project, the system has a flow

rate of 3.2L/hour which is more than enough to satisfy the average family’s needs. It also produces

very clean water with over 90% of organic material being filtered out and a reduction of water

turbidity to less than 5%. This is a vast improvement as currently there is no filtration system in use

so they are drinking unclean water making water borne diseases prolific. The system makes use of

local materials such as the rice husk and ceramics, this makes manufacture of the system much

easier as it makes use of the industry already in place in Vietnam. At only $8.10 for the entire system

it is very affordable average farmer in the Mekong Delta Region.

Table 19 - Completed Filtration URS

Category Musts Achieved

Functional Requirements

Must have a flow rate >3 litres/day per person in a household

Technical

Requirements

Must filter >90% organic materials (bacteria) out of the water

Must have zero power requirement for operation

Must reduce water to <5% turbidity

Must be able to operate at atmospheric pressure

Must cost <$10

Operational

Requirements

Must be easy to operate/maintain by an unskilled worker

64

5 Discussion

5.1 Adaptability of the integrated system

The greatest issue with a domestic design approach is accounting for the inevitable differences in

the layout of each household within the Mekong Delta. Although the storage methods of each family

are similar in principle, it is the implementation of these methods that differ because it has been

adapted to the housing styles of each family. The purpose of separating the key aspects of this

project was to continue this adaptability to the dimensions of any household. The guidelines for the

guttering system allow the rainwater to be collected from any roof shape to the storage unit itself.

The ferrocement water tank, though permanent once built, can be located where ever the family

wishes it to be and has the potential to be connected to the household via water piping. The

filtration unit has been designed to be portable and unobtrusive within the home itself. Effort is

inevitably required to transfer water from the storage unit to the filter but to design a fully

automated system that would perform this task will not only increase expenditure but restrict

adaptability. Such a system would involve mechanical parts that, in order to function, are highly

dependent on specific locations.

5.2 Improvements on current methods

The improvements that this integrated design provides will be invaluable compared to the current

water storage and drinking habits in the Mekong Delta. Each section of the project will have a

positive effect on the livelihoods of families in the region. Although the guttering system may not

differ vastly in principle from the current adopted guttering methods, it does have the added feature

of allowing heavily contaminated water from the roofs to be siphoned off. The ferrocement tank has

condensed what would currently be four separate ceramic jars into one storage unit whilst still

providing sufficient amounts of drinking and cooking water during a six month dry season. Whereas

the filtration unit will provide an opportunity for cleaner water that many households have never

had.

Despite the marked improvements that this system will have, the cultural integrity of Vietnamese

people will still remain undisturbed. The culture of the region would dictate that the construction of

the storage facility would be performed by a male. However, the same cultural dictation would also

apply to moving and installing the extremely heavy ceramic jars. Furthermore the ease of

maintenance of the ferrocement tank allows both genders to perform this task. This complies, yet

again, with the cultural view that general housekeeping is done by both male and females.

65

1. P

roje

ct

$8

4.7

9

1.1 Collection

$8.88

1.1.1 Guttering

$6.88

1.1.1.1 Bamboo

$2.08

1.1.1.2 Fastenings

$4.80

1.1.2 Supports

$2.00

1.1.2.1 Bamboo

$2.00

1.2 Storage

$67.81

1.2.1 Construction $62.81

1.2.1.1 Cement

$30.44

1.2.1.2 Sand

$6.80

1.2.1.3 Wire Mesh

$17.37

1.2.1.4 Bamboo

$8.20

1.2.2 Tap

$5.00

1.2.2.1

$5.00

1.3 Filter

$8.10

1.3.1 Clay Pot

$2.60

1.3.1.1 Clay

$0.35

1.3.1.2 Silver Nitrate

$0.25

1.3.1.3 Rice Husks

$0.00

1.3.1.4 Overhead

$2.00

1.3.2 Plastic Barrel

$3.50

1.3.2.1

$3.50

1.3.3 Plastic Tap

$1.50

1.3.3.1

$1.50

1.3.4 Plastic Lid

$0.50

1.3.4.1

$0.50

Figure 43 - Final cost breakdown

5.3 Total cost of integrated system and funding:

66

The previous table illustrates the costs of the entire integrated system. The ambiguity of the

collection system is due to the unknown dimensions of households. The price of this system will

inevitably vary according to the size of the home in question. The projected total cost comes to little

over $80, however, this value is based on the assumption that every system is constructed and

installed by an unpaid labourer or volunteer.

The project at hand is an Engineers Without Borders (EWB) project, so it is in its nature to be cost-

effective and funded by charities, humanitarian projects or affordable for the users. The final cost of

the design came out to be less than their current option, for which they receive no funding, so the

design can already be implemented without any external resourcing. However, as this is part of a

humanitarian project the initial funding should come from EWB. EWB can provide funding and

volunteers to go out and aid with the construction and finance of the project.

5.4 Worst Case Scenarios and Contingency Plans

5.4.1Flooding

The main contingency with which the system has had to be designed to consider is flooding. With

flood levels now reaching as high as four metres[20] due to global warming, both large walls of water

and floating debris are expected to be a major issue.

A four metre flood of course, is not the norm, merely an extreme. Water that deep will have fully

enveloped the house and the water system is unlikely to be the major concern. The filter is portable

so can be taken with the user to any temporary accommodation but the tank and guttering will have

to be left to the elements with the house.

In smaller scaled floods however, the system should cope relatively well. The tank has been designed

so that it is strong and rigid with a factor of safety three times as large as the 10 needed for a water

tank. Floating debris such as uprooted trees may crash into walls cracking them, and if the flood

waters rise above the top of the tank contaminated water can pour in, but neither of these problems

are without a solution. The ferrocement used to build the tank, is as easy to repair as it is to

construct, with small amounts of cement pasted into the cracks filling them. As for the contaminated

water, the washout valve is there to remove it. The guttering is less durable, but as it is so cheap (or

the bamboo can be harvested locally for free) and simple, it can merely be replaced where required

and as stated before, the filter is portable so should avoid any flood.

5.4.2 Typhoons

Near to the coast, typhoons are relatively common in Vietnam. Severe typhoons hit about once

every 5 years on average21. These tropical storms bring strong winds from the oceans causing further

flooding and gale force winds. Flooding, as discussed, should not be a major concern and neither,

should the winds.

The circular nature of the tank should help somewhat in dealing with the strong winds as

aerodynamically, with no flat faces, the wind should pass by easily, and the strong foundations and

large weight will prevent the tank blowing away.

20

http://www.ifrc.org/en/news-and-media/news-stories/asia-pacific/vietnam/emerging-crisis-in-viet-nam-as-mekong-delta-reaches-record-levels/ - last accessed 3/3/13 21

http://www.holiday-weather.com/country/vietnam/ - last accessed 3/3/13

67

The guttering is attached to both supports on the roof and struts planted in the ground. This is not as

secure as the tank and the lightweight bamboo poles are liable to blow away. However, as

mentioned, these are cheap/free to replace. The filter, again, will be kept safe inside.

6 Conclusion

The design mission was to design and provide a water collection, storage and filtration system that is

both affordable and effective for a household in the Mekong Delta.

By comparing the proposed integrated design to this mission statement it is clear that the objective

of this project has been successfully completed. The collection system has been designed to harvest

the required rainwater and has been adapted to their current method whilst also including an initial

filtration.

The water then flows into the storage that will contain it throughout the dry season, protecting it

from the sunlight and other bacteria culture factors. This is all in a ferrocement tank that costs less

than their current option and can be built by an unskilled labourer. When necessary the water can

then be extracted at more than the minimum flow rate given by the International SPHERE Standards.

After extraction, the water is then carried to the in house filtration system where it is filtered a

second, more thorough, time. This is done at atmospheric pressure and at three litres per hour;

again this is faster than the minimum SPHERE standard requirement. This easily replaceable filter is

also cost-effective at less than $10.

The proposed integrated system is more affordable than the current option, cleaner than the

current option, provides sufficient amount of water and is adjustable to user parameters. The design

has successfully fulfilled every user requirement specification and is therefore the optimum

rainwater storage and filtration solution available to the people of the Mekong Delta.

68

7 References United Nations High Commissioner for Refugees, ‘Large Ferro-Cement Water Tank, Design

Parameters and Construction Details’, July 2006.

Sakthivel, P.B., Jagannathan, A. ‘Ferrocement Construction Technology and its Applications – A

Review’, 2010.

American Concrete Institute (ACI) Committee 549, ‘State-of-the-art Report on Ferrocement’, January

24 1997, pp. 3 -15.

Brian Skinner, Bob Reed and Rod Shaw, ‘Ferrocement Water Tanks’, Loughborough University.

Chindaprasirt, P., et al. A Study and Development of Low-Cost Rainwater Tanks, Khon Kaen

University, Bangkok, 1986.

Nissen-Petersen, K., How to Build Smaller Water Tanks and Jars, ASAC Consultants Ltd., Kitui, Kenya,

1992.

Francis E. Brink and Paul J. Rush ‘BAMBOO REINFORCED CONCRETE CONSTRUCTION’, Port Hueneme,

California, February 1966.

‘http://diydata.com/general_building/concrete/concrete_mixing.php’ (last accessed 25/02/2013)

‘http://www.ewb.org.au/discussions/1273/11437’ (last accessed (5/03/2013)

Disenbacher, A. L. and Brauer, F. E., “Material Development Design, Construction and Evaluation of

Ferrocement Planning Boat,” Marine Technology & S., V. 11, No. 3, July 1984, pp. 277-296.

http://www.potterswithoutborders.com/ (last accessed (2/03/2013)

http://wateradvocate.org/potters.htm (last accessed (23/02/2013)

http://www.rdic.org/ (last accessed (5/03/2013)

http://www.amazon.co.uk/ (last accessed (5/03/2013)

http://www.bamboocraft.net/forums/showthread.php?t=382 (last accessed (5/03/2013)

http://www.ehow.com/how_8490856_split-bamboo-poles.html#ixzz2Ii8WAQXP(lastaccessed

(5/03/2013)

http://www.guaduabamboo.com/how-to-split-bamboo.html#ixzz2Ii9ZXReL(lastaccessed (5/03/2013)

http://www.milmour.com/milmour/blow_molding_images.asp (last accessed (3/03/2013)

69

Appendix A - Material Calculations

Sand to cement ratio of 4:1 by mass

Cement:

Foundation: 10cm thick, 2.1m diameter =0.346m3

Walls: 1.975m diameter cylinder, 5cm thick walls, 1.5m high =0.465m3

1.85m internal walls 5cm thick 1.45m (average height) =0.134m3

Roof: 1.96m diameter, 5cm thick = 0.150m3

Basin: 0.08m3 (calculated on solid works)

Total= 1.18m3 of cement mix = 0.944m3 sand + 0.236m3 cement

Wire mesh: Roll are purchased at 1.6m tall

Walls: 1.975m diameter cylinder =6.2m of roll

1.85m internal walls = 1.85m

1.6m required for roof = 1.6m

Total= 9.65m

Bamboo:

Walls: 20 supports in cylinder, 1.6m tall = 32m

8 supports in internal wall 1.6m tall = 12.8m

40 roof struts length 0.93m =37.2 m

Total= 82m

70

Appendix B – Construction Guidelines

71

72

73

74

75

76

Appendix C – Stress Analysis of Tank

77

78

79

80

81

82

83

Appendix D – CAD Drawings

84

Appendix E – Bamboo Handling Techniques

Instructions for cutting Bamboo can be split length-wise using various tools and techniques.

The splitting tool follows along the path of the fiber strands. Practice and experience is

needed to ensure that it splits where you want it to.

If the pole has bends and wavers, the split will want to follow these bends.

This is alright if you are making strips that don't matter if they are bent.

I like to use a bandsaw for the following situations:

- To cut a longer piece in half, and to have a flat,

even surface on the cut side.

- Or when a 2/3 - 1/3 ratio cut is desired.

- Or to cut a distorted length of bamboo in half.

- Or if one doesn't want the node partition inside the culm node to be cracked or broken,

which happens when using splitting methods.

A band saw can work great - when you want flat half-rounds for paneling, picture frames,

or any situation where the length-wise cut has to be very straight, and have a smooth

finish on the cut.

At least for up to 3 inch diameter bamboo, (which is the largest diameter that my

benchtop bandsaw can cut), I always use a bandsaw blade with the greatest number of

teeth per inch that I can get, (15 tpi).

A method is to attach a guide rail to your band saw.

Then fit on another board that will slide along with the piece of bamboo you are cutting.

You will have to position the bamboo piece where you want the cut.

If it's got bends, practice will show the best way to align the bamboo to suit your needs.

If the pole is strongly tapered and you want the cut to be in the exact middle, you may

need to fit a thin wedge of wood at one end of the board that moves along with the cut,

to compensate for the taper.

Sawing a length of Phyllostachys aurea with a bandsaw

Notice that on the shortened internode, that there is a hole in

the bamboo.

This occasionally occurs when the nodes of Phyllostachys aurea

grow closer together, further up the

culm, where it branches. I think what happens is that the branch

grows similar to an ingrown toenail but then dies and leaves a

hole where the branch would be. This hole is not caused by

insects.

Two lengths cut in half

Notice the pieces to the left that had the hole in it is darker

inside because it wasn't sealed from the weather during its

lifetime.

85

Instructions for splitting

Examine both ends of the bamboo pole and determine which end is thinner. Always begin splitting

from the thin end of the bamboo pole.

Put on work gloves and place the thick end of the bamboo pole against a sturdy, unmovable object,

such as the base of a wall or building. Angle the other end of the pole upward until it is between

waist and shoulder height. It helps to have another person assist with holding the pole.

Grasp the pole firmly in one hand approximately 6 to 12 inches from the end. Place the blade of a

bamboo hatchet across the top end of the pole perfectly centered.

Tap the top of the hatchet blade with a mallet until it begins to cut into the bamboo pole. Continue

tapping the top of the blade until the bamboo splits down to the third round joint on the outside. As

you split the pole, the upper sections separate, allowing you to hit the top of the blade.

Set the mallet aside and push the blade down as far as possible. Twist the blade one or two degrees

to the side to split the bamboo pole a little further. Continue sliding the blade down and twisting it

until the entire pole splits in half.

If the bamboo pole already has a split in one end, which occurs naturally during the drying process,

insert the hatchet into it to begin the cut. You can also use a machete or any other thick-bladed knife

to cut the bamboo poles.

How to Split Bamboo?

Splitting bamboo, is another basic technique when working with bamboo. Split bamboo is often used in bamboo

fences, wall decoration, furniture, etc. The applications are endless and it basically all depends on your own creativity. Below I have set up a very easy step by step DIY action guide on how to split bamboo poles.

1. Press the bamboo cane firmly against a wall or any other unmovable object.

2. Be sure to split the bamboo cane beginning from the thinner end with the cutting edge of a bamboo hatchet

(or machete) positioned in the exact center of the cane. Strike the blade on the back with a mallet (using a regular hammer may damage the blade).

86

3. After the hatchet has cut into the bamboo, strike the blade on the back gently with a mallet until the cane is

split through two or three joints.

4. As the bamboo cane is split further, the splitting line will often go off center.

5. To correct this, hold the unsplit part of the cane, by stepping on it, with the smaller portion facing down and

pull the bigger portion upward by hand. This way, the difference in thickness will be corrected.

6. During this process, be sure to always check the thickness of the upper and lower portions. Make sure the thinner portion always faces down.

87

7. Continue this process, changing the vertical direction of the cane as required, until the split reaches the

other end. Be sure not to hurry this process.

Important: Bamboo has 2 sides!

Remember that bamboo has actually 2 different sides; a straight side and a bent side. A bamboo cane will look straight or nearly straight when viewed from the branched side. When viewed at an angle of ninety degrees, however, the bamboo cane looks bent at each node. So, depending on the project you might want to split bamboo with a straight front or with a straight cut surface.

1. Straight Front:

When splitting bamboo canes with the branched side facing upward, the half-split cane will look straight from

the front. When viewed from the side, the cut surface will have bents at the joints.

88

2. Straight Cut Surface:

When splitting bamboo canes with the branched side positioned vertically to the horizontal plane, the cut

surface will look straight. When viewed from the front, the half-split cane has bents at the joints.

89

Appendix F – Rainfall Data + Calculations

Tota

l Avera

ges

2006

2007

2008

2009

2010

January

10

29

21

41

521.2

Febru

ary

40

49

98

030.2

Marc

h67

104

082

12

53

April

74

81

133

66

772.2

May

386

298

229

403

166

296.4

June

381

286

354

196

264

296.2

July

416

411

214

435

271

349.4

August

278

504

359

189

312

328.4

Septe

mber

526

277

304

295

194

319.2

Octo

ber

232

583

331

237

203

317.2

Novem

ber

69.3

98.1

184.5

33.7

237

124.5

2

Decem

ber

8.8

48.8

154

18.8

41

54.2

8

Tota

l over

Year

2452.1

2719.9

2332.5

2094.5

1712

2262.2

Tota

l over

Wet

Season

2219

2359

2129.5

1755

1647

2021.9

Wate

r cole

cte

d o

ver

16m

2 r

oof

(m3)

39.2

336

43.5

184

37.3

233.5

12

27.3

92

36.1

952

Wate

r cole

cte

d o

ver

16m

2 r

oof

in w

et

season (

m3)

35.5

04

37.7

44

34.0

72

28.0

826.3

52

32.3

504

Avera

ge f

low

rate

in r

ain

iest

month

(lit

re/h

our)

11.3

11828

12.5

376344

7.7

2043011

9.3

5483871

6.7

0967742

9.5

2688172

Perc

enta

ge o

f ra

inw

ate

r fa

llen d

uring w

et

season (

%)

90.4

938624

86.7

311298

91.2

968917

83.7

908809

96.2

03271

89.7

0320718

Year

Are

a o

f ro

of:

16m

3

Ref

ere

nce

: htt

p:/

/ww

w.e

wb

.org

.au

/res

ou

rces

/do

wn

load

/24

16P

20

12

-02

-

26

_23:

58:3

1

90

Appendix G – Example Meeting Minutes 11/01/2013 Engineering computer suite

Group 17

Post holiday meeting (week 5) Following are the minutes from the 5 th weekly meeting

Members present -

Callum Stephen

Charles Heard

Kevin De Michelis

Nicholas Sidwell

Thomas Pallister

Xaver Touschek

Following the agenda:

General points arising:

Happy new year all

Final report writing to begin

Notes from feasibility report feedback

o URS needs re-visiting and simplification + quantification in places

o Title page of main report needs to be more exciting

o Problem statement not clear enough

o Process flow chart needed

Sectional updates:

Collection

Identified the need to wash the roof after the dry season... Bird poo, dust etc all builds up.

Storage

Roof of tank needs some sort of seal

Filtration

Decision to be made between sand filter and clay pot filter

Other general points:

Get writing guys!

Jobs to do for Tuesday:

o Figure out how to wash roof

o Figure out how to seal tank

o Look at URS

o More research to be done on clay pot and sand filter

o Report back with finding and decision will be made next week

91

01/02/2013 Bill Bryson Library

Group 17

Weekly meeting – week 12 Members present -

Charles Heard

Callum Stephen

Nicholas Sidwell

Thomas Pallister

Kevin De Michelis Xaver Touschek

Following the agenda:

General points arising:

Congratulations to all on a good presentation

With both the introduction and executive summary now written by Kevin and Xaver

respectively, both are now uploaded to dropbox for general approval/criticism

Images needed for all section intro pages (same ones as presentation suggested by Charlie)

All figures and tables from now on to be labelled using the references/captions feature in

word to help keep track of numbering and create a list at the beginning of the report

Group room booked for Sunday 12am, Monday 5pm Tuesday 5:30 pm Wednesday 5pm for

proof reading sections

Meeting booked for Tuesday following update from supervisors

Sectional updates:

Collection

All finished except “final design” and “manufacture” write up

Storage

“Manufacture” section to be completed

Structural analysis figures need updating to include tap and washout valve

Filtration

Still small bits of work needed on all sections but only minimal amounts

Other general points:

Updated costings – still under $80

Jobs to do for Tuesday:

o Update figure labels

o Read through summary + introduction

o Proof read each other’s work when uploaded to dropbox, post comments on

facebook group

o Add sections to final report and start combining everything together.