8/16/2019 DC Water 1st Street Tunnel Forum Presentation 2016 05 26
1/39
Thursday, May 26, 2016
Briefing
for:
Briefing
on:
DC CLEAN RIVERS PROJECT
First
Street
Tunnel
Construction
Update
and
Community
Mitigation
Measures
First
Street
Tunnel
Forum/Community
Group
District of Columbia Water and Sewer AuthorityGeorge S. Hawkins, General Manager
8/16/2019 DC Water 1st Street Tunnel Forum Presentation 2016 05 26
2/39
Tunnel ForumRepresentatives and Alternates
Location/Group Representative Alternate
First Street NW Dr. Marilyn Lashley Tomas Encaracion
Bryant / Channing Streets Renee Peres Philomena FritzFlagler Place Vacant Vacant
Adams Street Shelly Parker Dianne Barnes
W Street Joe Levesque Neal Herman
First and V Streets Angela Ray Theodore Bush and Derrick Jones
U Street Serita Sanders Jean Marie Thomas
Thomas St / Rhode Island Ave Chris Von Ferro Vacant
Local Blogs Scott Roberts Betsy McDaniel
Government Teri Janine Quinn,
ANC 5E
Bertha Holliday, ANC 5E
Laisha Dougherty, Councilmember
McDuffie’s office, Ward 5
Civic Associations Sherry Howard John MacNeil
All meetings are open to the public. 2
8/16/2019 DC Water 1st Street Tunnel Forum Presentation 2016 05 26
3/39
Welcome and Introductions
Meeting Dates for 2016
Two-Month Construction Update at
Construction Staging Areas (CSAs)
Channing Street CSA
Adams and Flagler CSA First and V CSA
First and Thomas CSA (Pumping Station)
Instrumentation and Monitoring
Long-Range Construction Schedule
What to Expect in Coming Months
3
Progress-at-a-Glance
Small Diameter Water Main Project
Update on Alternative Parking Areas
Shuttle Service Has Been Replaced
with Uber
Restoration Plans at or nearConstruction Staging Areas
Tree Planting Initiative and Locations
Post-Construction Surveys
FEMS Door Mural Giveaways
Next Steps
Agenda
8/16/2019 DC Water 1st Street Tunnel Forum Presentation 2016 05 26
4/39
MEETING
DATES
FOR
2016
Tom Lindberg, DC Water
8/16/2019 DC Water 1st Street Tunnel Forum Presentation 2016 05 26
5/39
Meeting Dates for 2016
Discussion Topic Meeting Date* Location
First Street Tunnel (FST) ConstructionUpdate January 28, 2016 St. George’s Episcopal Church
FST Update and Landscaping and
Restoration Plans
March 24, 2016 St. George’s Episcopal Church
FST Update and Landscaping andRestoration Plans May 26, 2016 St. George’s Episcopal Church
System Start-Up Event July Pumping Station Site, Thomas
Street, NW
FST Update, Landscaping andRestoration Plans, Freeze-Thaw
Update, and Small Diameter Water
Main Project
July 28, 2016 St. George’s Episcopal Church
5
8/16/2019 DC Water 1st Street Tunnel Forum Presentation 2016 05 26
6/39
This page intentionally left blank.
8/16/2019 DC Water 1st Street Tunnel Forum Presentation 2016 05 26
7/39
TWO‐
MONTH
CONSTRUCTION
UPDATE
AT CONSTRUCTION STAGING AREAS
Scott Hoffman and Thomas March, SKJD
8/16/2019 DC Water 1st Street Tunnel Forum Presentation 2016 05 26
8/39
Channing StreetConstruction Staging Area
MainMiningShaft
N DC WaterTrailer SKJD Trailer
Muck
Pit
Grout Plant
Mechanic
Shop
Freeze Plant
Natural Gas Generators
Moretrench
Storage & Office
S e d i m e n t P o n d
Safety Trailer
8
The freeze plant, natural gas
generators, grout plant and
segment storage area
decommissioned.
Shown as ( ).
Segment Storage Area
Channing St Diversion Sewer
Vent
Control
Vault
8/16/2019 DC Water 1st Street Tunnel Forum Presentation 2016 05 26
9/39
8/16/2019 DC Water 1st Street Tunnel Forum Presentation 2016 05 26
10/39
Adams and Flagler IntersectionConstruction Staging Area
Building entrance
Construction traffic entrance and exit
CSA
CWZ
Road Closed ‒ No thru
traffic. Local accessonly at intersection ofFirst Street and AdamsStreet).
AbbreviationsCSA ‒ Construction Staging AreaCWZ ‒ Construction Work Zone
FEMS ‒ Fire and EMS Department
CSA
CWZ
FEMS Access Zone
4’-wide Pedestrian Sidewalk
Local Traffic
14 feet
55 feet
Fire department
ladder truck clearances
Legend
Centrifuge
Polymer Mix Transformer
7 8 9 10
Pipes 7,8, 9,10
Electrical Pad
160'
10
Reduce CSA, June 2016
Adams St
F l a g l e r P l
8/16/2019 DC Water 1st Street Tunnel Forum Presentation 2016 05 26
11/39
Adams and Flagler IntersectionConstruction Staging Area
Completed mining of the adit
Completed construction of near surface structures onFlagler Place
Constructing shaft internal structures
East side of the Adams Street Construction Staging Areawill be restored in June 2016
Continuing utility (water, storm, sewer) restoration onFlagler Place through June 2016
Final restoration to begin in June and end in August 2016
11
8/16/2019 DC Water 1st Street Tunnel Forum Presentation 2016 05 26
12/39
V Street
F i r s t
S t r e e t
Legend
CSA
CLC
CSA
CLC
4'-wide Pedestrian Walkway
FEMS Access Zone
Building Entrance
ConstructionTraffic Entrance & Exit
CSA ‒ Construction Staging Area
CLC ‒ Construction Lane Closure
FEMS ‒ Fire and EMS Department
Abbreviations
14 feet
55 feet
Fire department
ladder truck clearances
Local Traffic
12
Currently
Fenced
Alley toremain closed
Alley toremain closed
First and V IntersectionConstruction Staging Area
Maintain one pedestrianwalkway on either sideof V Street.
54′
44′
11′
44′
Reduce CSA on First Street, July 2016
8/16/2019 DC Water 1st Street Tunnel Forum Presentation 2016 05 26
13/39
First and V IntersectionConstruction Staging Area
Constructing shaft internal structures
Construction of near surface structures will be completedJune 2016
Reopening First Street by end of July 2016
V Street portion of construction staging area will remain
closed through completion
Begin final restoration in July 2016
13
8/16/2019 DC Water 1st Street Tunnel Forum Presentation 2016 05 26
14/39
Legend CSA
CLC
CSA FEMS accesszone
Building entrance
Construction traffic entrance and exit
CSA ‒ Construction Staging AreaCLC ‒ Construction Lane Closure
FEMS – Fire and EMS Department
Abbreviations
First and Thomas IntersectionConstruction Staging Area (Pumping Station)
14 feet
55 feet
Fire department
ladder truck clearances
Local Traffic
14
P S -V V
P S -T V
PS-VF
PS-MV
Reduce CSA, June 2016
8/16/2019 DC Water 1st Street Tunnel Forum Presentation 2016 05 26
15/39
First and Thomas IntersectionConstruction Staging Area (Pumping Station)
Continue construction of near surface structures
through June 2016
Continue mechanical and electrical work at near
surface structures to shaft through June 2016
Commission pumping station through June 2016
Reopening Thomas Street by end of June 2016
Final restoration will continue in parking lot through
July 2016
15
8/16/2019 DC Water 1st Street Tunnel Forum Presentation 2016 05 26
16/39
This page intentionally left blank.
8/16/2019 DC Water 1st Street Tunnel Forum Presentation 2016 05 26
17/39
Instrumentation and Monitoring
17
Monitoring of private properties along the FirstStreet tunnel alignment and outside construction
staging areas has ceased because data as beenstable for more than three months
Upon completion, SKJD will contact homeowners toschedule removal of the instrumentation and
monitoring devices and restoration; you need notbe present for this operation
The freeze process is shut off at all locations, andwe are continuing to monitor the freeze-thaw data
Instrumentation device installed.
8/16/2019 DC Water 1st Street Tunnel Forum Presentation 2016 05 26
18/39
LONG‐
RANGE
CONSTRUCTION
SCHEDULE AND PROGRESS
Scott Hoffman, SKJD and John Kennedy, DC Water
8/16/2019 DC Water 1st Street Tunnel Forum Presentation 2016 05 26
19/39
19
Long-Range Construction Schedule
8/16/2019 DC Water 1st Street Tunnel Forum Presentation 2016 05 26
20/39
What to Expect in Coming Months
Heavy construction will continue, including surface activities,
concrete deliveries, and the removal of the top of secant
piles around drop shafts and diversion chambers
Near surface structures and the tunnel will be operational by
July 2016
Landscaping and restoration will follow after the project isoperational: June ‒ July 2016
Coordination of the Small Diameter Water Main project and
the First Street Tunnel project will occur in August 2016
20
8/16/2019 DC Water 1st Street Tunnel Forum Presentation 2016 05 26
21/39
What to Expect in Coming Months, continued
Completion dates are defined as:
Substantial Completion (July 2016): Completion of the pumping
station and all near surface structures, so that the system isoperational
Final Completion (Sept 2016): Work remaining after substantialcompletion includes the removal and restoration of the freeze trench
and street restoration and landscaping at the CSAs and APAs. Thediversion chamber and ventilation control vault at the ChanningStreet CSA will also be completed.
21
8/16/2019 DC Water 1st Street Tunnel Forum Presentation 2016 05 26
22/39
22
First Street TunnelProgress-at-a-Glance as of April 30, 2016; 84.63% Complete
CS‐MS Inflow / Ventilation
Chamber
• Continued installing beams
and building working
platforms for Inflow
Chamber & Vent Facility.
CS Approach Channel & VCV
• Started excavating channel.
• Started excavating
Ventilation Control Vault.
V Street – NCS‐DC & FS‐DC
• Continued installing and
tying rebar.
• Continued
setting
concrete
forms and pouring
concrete for walls & slabs.
First Street – Diversion Chamber
• Finished excavation.
• Started installing & tying
rebar
slab.
PS – Vent Facility
• Continued installing
& tying rebar.
• Setting
wall
forms
and
poured concrete.
PS – Drop Shaft
• Started installing anchor
bolts
for
discharge
pipes
at shaft wall.
• Formed and poured
pump pedestals.
AS – MTBM & Pipe Jacking
• Finished mining and
installing pipe.
• Started disassembling
equipment.
AS – Diversion Channel
• Finished installing
MH covers.
• Finished pouring
concrete around MH
covers & slab.
8/16/2019 DC Water 1st Street Tunnel Forum Presentation 2016 05 26
23/39
ONGOING
ACTIVITIES
Tom Lindberg, DC Water
8/16/2019 DC Water 1st Street Tunnel Forum Presentation 2016 05 26
24/39
Small DiameterWater Main Project
DC Water’s small diameter water mainwork will follow the First Street Tunnel
project Limits of Bloomingdale project area are
shown by green dashed border ( )
Approximately 25 water main breaks or
leaks since 2000 shown in red ( ) Small diameter water mains (
8/16/2019 DC Water 1st Street Tunnel Forum Presentation 2016 05 26
25/39
Small DiameterWater Main Project Schedule
The Small Diameter Water Main project has been coordinated with
DC Water’s engineering department over the past year
DC Water is acquiring permits for the proposed Bloomingdale water
main work
The project was advertised in April 2016
The contract will be awarded in June 2016
The project will start in August 2016
DC Water’s outreach contact for construction:
Tanya Hedgepeth, [email protected]
25
8/16/2019 DC Water 1st Street Tunnel Forum Presentation 2016 05 26
26/39
Update onAlternative Parking Areas
143 W Street Alternative Parking Areaclosed on March 31, 2016
W Street Alternative Parking Area isscheduled to close on June 1, 2016
Bryant Street Alternative Parking Area will
remain open for the duration of the project
26
Bryant Street APA will remain open. W Street APA will close on June 1.
ADAMS ST NW
W ST NW
V ST NW
143 W STREET APA
(CLOSED MARCH 31)W STREET APA
(CLOSING
JUNE 1)
Sh l S i H B
8/16/2019 DC Water 1st Street Tunnel Forum Presentation 2016 05 26
27/39
Shuttle Service Has BeenReplaced with Uber
The First Street Tunnel team has replaced the shuttle van
service because requests have been and continue to be
extremely low
Now using Uber as an alternative to the shuttle buses
We will continue to offer 24/7 neighborhood transportation
Call the FST Hotline at 1-844-FST-INFO (1-844-378-4636)
and press 1 for shuttle service
We will dispatch an Uber driver
27
8/16/2019 DC Water 1st Street Tunnel Forum Presentation 2016 05 26
28/39
DC W t DDOT d Bl i d l Ci i
8/16/2019 DC Water 1st Street Tunnel Forum Presentation 2016 05 26
29/39
DC Water, DDOT, and Bloomingdale CivicAssociation Tree Planting Initiative
DC Water/SKJD will plant 35 additional trees in
Bloomingdale
Plantings will be done by SKJDs subcontractor
Planting location diagrams are provided following the list
of plantings on the next page
29
8/16/2019 DC Water 1st Street Tunnel Forum Presentation 2016 05 26
30/39
List of Plantings by Street Address
30
Street Address Species120 U ST NW Hackberry
2208 FLAGLER PL NW Hackberry
156 ADAMS ST NW Tulip popular 2131 1ST ST NW Tulip popular
OPP 2911 NORTH CAPITOL ST NW Bur oak
OPP 44 FLORIDA AVE NE Nuttall oak
48 R ST NW Tulip popular
151 S ST NW Shurmard oak
2645 1ST ST NW Catalpa
2000 NORTH CAPITOL ST NW Chinkapin oak
2102 FLAGLER PL NW Nuttall oak
2645 1ST ST NW Catalpa
2645 1ST ST NW Catalpa
87 V ST NW Blackgum29 S ST NW Hackberry
OPP 66 CHANNING ST NW Bur oak
OPP 60 CHANNING ST NW Bur oak
Street Address Species2 ADAMS ST NW Scarlet oak
1822 NORTH CAPITOL ST BN Chinese pistache
74 ADAMS ST NW London planetree2030 FLAGLER PL NW Blackgum
44 CHANNING ST NW Bur oak
OPP 54 CHANNING ST NW Bur oak
2100 BLK 2ND ST NW Shingle oak
OPP 128 RHODE ISLAND AVE NW Japanese apricot
UNIT BLK QUINCY PL NW Nuttall oak
OPP 130 RHODE ISLAND AVE NW Japanese apricot
OPP 128 RHODE ISLAND AVE NW Japanese apricot
OPP 22 CHANNING ST NW Tulip popular
UNIT BLK R ST NE Hackberry
49 BRYANT ST NW Tulip popular 2312 NORTH CAPITOL ST NW Bur oak
OPP 138 RHODE ISLAND AVE NW Japanese apricot
81 SEATON PL NW Japanese apricot
UNIT BLK BRYANT ST NW Blackgum
8/16/2019 DC Water 1st Street Tunnel Forum Presentation 2016 05 26
31/39
Tree Planting Locations
31
On First Street, south of Michigan Avenue. On North Capitol Street, south of Michigan Avenue.
‒ Newly planted 2-inch caliber tree.
‒ Existing trees.
8/16/2019 DC Water 1st Street Tunnel Forum Presentation 2016 05 26
32/39
32
Along Channing Street. Along Channing Street.
‒ Newly planted 2-inch caliber tree.
‒ Existing trees.
Tree Planting Locations, continued
8/16/2019 DC Water 1st Street Tunnel Forum Presentation 2016 05 26
33/39
33
On Bryant Street and North Capitol Street. Along Adams Street and First Street.
Tree Planting Locations, continued
‒ Newly planted 2-inch caliber tree.
‒ Existing trees.
8/16/2019 DC Water 1st Street Tunnel Forum Presentation 2016 05 26
34/39
34
Second and Adams Streets, and Flagler Place. Flagler Place, and First, U, and North Capitol Streets.(Graphic missing existing trees.)
‒ Newly planted 2-inch caliber tree.
‒ Existing trees.
Tree Planting Locations, continued
8/16/2019 DC Water 1st Street Tunnel Forum Presentation 2016 05 26
35/39
35
Median along Rhode Island Avenue. Seaton Place, S Street, and North Capitol Street.
‒ Newly planted 2-inch caliber tree.
‒ Existing trees.
Tree Planting Locations, continued
8/16/2019 DC Water 1st Street Tunnel Forum Presentation 2016 05 26
36/39
S Street. R Street and Florida Avenue.
‒ Newly planted 2-inch caliber tree.
‒ Existing trees.
Tree Planting Locations, continued
P t C t ti
8/16/2019 DC Water 1st Street Tunnel Forum Presentation 2016 05 26
37/39
Post-ConstructionSurveys
Property owners that participated in the
First Street Tunnel Pre-construction
Survey Program have the opportunity fora post-construction survey
The post-construction surveys will be
scheduled in the summer and fall 2016
If you would like a post-construction
survey, please email
[email protected] and we will
contact you when the program begins
Please be advised that post-construction
surveys will only be performed on prop-
erties that had a pre-construction survey
37
If you participated in
the Pre-constructionSurvey Program, youare eligible to receivea post-construction survey.
Crispus Attucks Park
McMillan Reservoir
8/16/2019 DC Water 1st Street Tunnel Forum Presentation 2016 05 26
38/39
FEMS Door Mural Giveaways
We will be dismantling the Adams and Flagler CSA inphases, and we have provided the homeowners who reside
near the CSA with the opportunity to retain the door for theirpersonal use
Those who responded approvingly to our door giveawayrequest will receive the requested door when the CSA gets
smaller or is dismantled
Skanska will place the door near the gate on their privateproperty; the doors will be provided as-is
If the door is not wanted by the homeowner, DC Water willstore it at the project site office and discuss with communityand Tunnel Forum members alternative uses
38
8/16/2019 DC Water 1st Street Tunnel Forum Presentation 2016 05 26
39/39
Next Steps
The next Tunnel Forum Meeting on Thursday, July 28at 7 PM, at St. George’s Episcopal Church
For construction issues or problems, please call the24/7 FST Hotline at 1-844-FST-INFO (1-844-378-4636)
An event will be planned when the system and pumping
station are operational, date to be determined
39
For updates, go towww.dcwater.com/workzones/projects/first_street_tunnel