Building COLOMBIA’S next MAJOR GOLD MINE
Corporate PresentationJuly 2020
TSX-V: CGCOCTQX: ALLXF
Forward-Looking StatementsThis presentation of Caldas Gold Corp. (the “Company” or “Caldas”) is for information only and contains "forward-looking information", under applicable securities law, which may include, but is not limited to,statements with respect to strategies, expectations, planned operations, future actions or the future financial or operating performance of the Company and its projects, and, specifically, statements concerninganticipated growth in annual gold production, the completion of anticipated financing and security offerings, the development of the Marmato Project including the building or expansion of any processing facilitiesor the achievement of future production levels, the exploration upside at Marmato, the anticipated cash flow and internal rate of return from expanding the Marmato Project, and the performance of the Company’sstock. Statements as to Mineral Reserves and Mineral Resources are further qualified by the language continued under “Technical Information” below. All statements, other than those of historical fact, whichaddress activities, events, outcomes, results, developments, performance or achievements that the Company anticipates or expects may or will occur in the future (in whole o in part) should be considered forward-looking information. Often, but not always, forward-looking statements can be identified by the use of words such as "plans", "expects", "is expected", "budget", "scheduled", "estimates", "forecasts", "intends","anticipates", or "believes" or variations (including negative variations) of such words and phrases, or state that certain actions, events or results "may", "could", "would", "might" or "will" be taken, occur or beachieved. Forward-looking statements involve known and unknown risks, uncertainties and other factors which may cause the actual results, performance or achievements of Caldas to be materially different fromany future results, performance or achievements expressed or implied by the forward-looking statements. Factors that could cause actual results to differ materially from those anticipated in these forward-lookingstatements are described under the caption "Risk Factors" in the Company's Filing Statement dated as of February 19, 2020 and filed at www.sedar.com. Such factors are based on information currently available tothe Company, including information obtained from third-party industry analysts and other third-party sources, and are based on management’s current expectations regarding future growth, results of operations,future capital (including the amount, nature and sources of funding thereof) and expenditures. Forward-looking statements contained herein are made as of the date of this presentation and Caldas disclaims, otherthan as required by law, any obligation to update any forward-looking statements whether as a result of new information, results, future events, circumstances, or if management's estimates or opinions shouldchange, or otherwise. There can be no assurance that forward-looking statements will prove to be accurate, as actual results and future events could differ materially from those anticipated in such statements.Accordingly, the reader is cautioned not to place undue reliance on forward-looking statements. The forward-looking information contained in this presentation is expressly qualified by the cautionary statement.
Technical InformationA Preliminary Feasibility Study is a comprehensive study of a range of options for the technical and economic viability of a mineral project that has advanced to a stage where a preferred mining method, in the caseof underground mining, or the pit configuration, in the case of an open pit, is established and an effective method of mineral processing is determined. It includes a financial analysis based on reasonableassumptions on any modifying factors and the evaluation of any other relevant factors which are sufficient for a Qualified Person, acting reasonably, to determine if all or part of the Mineral Resource may beconverted to a Mineral Reserve at the time of reporting. A Preliminary Feasibility Study is at a lower confidence level than a Feasibility Study.
The Mineral Resources and Mineral Reserves described in this presentation were estimated using the Canadian Institute of Mining Metallurgy and Petroleum (“CIM”) Standards on Mineral Resources and Reserves,Definitions and Guidelines prepared by the CIM Standing Committee on Reserve Definitions and adopted by the CIM Council and incorporated by reference in National Instrument 43-101 – Standards of Disclosure forMineral Projects (“NI 43-101”). Mineral Resources that are not Mineral Reserves do not have demonstrated economic viability. The estimate of Mineral Resources may be materially affected by environmental, permitting,legal, title, taxation, socio-political, marketing, or other relevant issues. The Inferred Mineral Resource in this estimate has a lower level of confidence than that applied to an Indicated Mineral Resource and must not beconverted to a Mineral Reserve. There is no certainty that Inferred Mineral Resources will be converted to the Measured and Indicated Resource categories through further drilling, or into Mineral Reserves, once economicconsiderations are applied. As such, readers are cautioned not to assume that part or all of an Inferred Mineral Resource exists, or is economically or legally mineable.
For all Marmato Project drilling results described in this presentation, verification by the Qualified Person included a review of the quality assurance and quality control samples, and review of the applicable assaydatabases and assay certificates. The core samples were prepared by SGS Laboratories Ltd (ISO 9001:2008) at their laboratory in Medellin, and assayed in their laboratory in Segovia, Colombia. Gold was assayed by30 g fire assay with atomic absorption spectrophotometer (“AAS”) finish. Samples over 10.0 g/t gold were re-assayed by 30 g fire assay with gravimetric finish. Silver was assayed by aqua regia digestion and AASfinish. Blank, standard and duplicate samples were routinely inserted for quality assurance and quality control.
Technical Disclosure Footnotes:A. Disclosure with regard to the updated Mineral Resource estimate for Caldas’ Marmato Project was prepared in accordance with the CIM Definition Standards incorporated by reference in NI 43-101 with an
effective date of March 17, 2020, as disclosed in the Company’s press release dated July 6, 2020. The Mineral Resources were estimated by Benjamin Parsons, MSc, MAusIMM #222568 of SRK, a QualifiedPerson pursuant to NI 43-101. The Veins and Transition Mineral Reserves were estimated by Fernando Rodrigues, BS Mining, MBA, MMSAQP #01405, MAusIMM #304726 of SRK, a Qualified Person pursuant toNI 43-101. The MDZ Mineral Reserves were estimated by Joanna Poeck, BEng Mining, SME-RM, MMSAQP #01387QP, a Qualified Person pursuant to NI 43-101. For a full description of the “Veins”, “Transition”and “MDZ” zones, please see the Company’s press release dated July 6, 2020
B. Refers to the preliminary results of a Preliminary Feasibility Study (“PFS”) for the Marmato Project, focused on the Zona Baja mining operations, effective March 17, 2020, and was prepared in accordance withthe CIM Definition Standards incorporated by reference in NI 43-101, as disclosed in the Company’s press release dated July 6, 2020. Fernando Rodrigues, BS Mining, MBA, MAusIMM, MMSAQP PracticeLeader/Principal Consultant (Mining Engineer) with SRK, prepared the PFS according to CIM Definition Standards and will be supported by a NI 43-101 independent report which will be published and filed onthe Company’s website and SEDAR profile within 45 days. Mr. Rodrigues is a Qualified Person as defined by NI 43-101.
C. Disclosure with regard to the exploration drilling program at the Marmato Project is derived from the press release of Gran Colombia Gold Corp dated February 3, 2020, which contains details of all drill holesto date from the exploration campaign, other than drill hole MT-IU-053A. Dr. Stewart D. Redwood, PhD, FIMMM, Senior Consulting Geologist to the Company, is a qualified person as defined by NI 43-101 andprepared or reviewed the preparation of the scientific and technical information in such press release.
D. Disclosure with regard to the exploration upside at the Marmato Project described in this slide is taken from the press release of the Company dated March 2, 2020, which contains details on drill hole MT-IU-053A from the exploration campaign. Dr. Stewart D. Redwood, PhD, FIMMM, Senior Consulting Geologist to the Company, is a qualified person as defined by NI 43-101 and prepared or reviewed thepreparation of the scientific and technical information in such press release.
E. Disclosure with regard to the exploration upside at the Marmato Project described in this slide is taken from the press release of the Company dated May 13, 2020, which contains details on all drill holescompleted to date since the previous press release. Dr. Stewart D. Redwood, PhD, FIMMM, Senior Consulting Geologist to the Company, is a qualified person as defined by NI 43-101 and prepared or reviewedthe preparation of the scientific and technical information in such press release.
DISCLAIMER
2
TSX-V: CGCOCTQX: ALLXF
TSX‐V: CGCJune 2020
Caldas Gold Corp (TSX-V: CGC, OTCQX: ALLXF) was formed in a spin out by Gran Colombia Gold (TSX: GCM) in February 2020; GCM holds a 57.5% equity interest(1).
Caldas Gold is focused on a major underground mine expansion at Marmato to incorporate the Deep Zone mineralization.
The existing mine has been in operation since 1991 and has produced an average of ~24,000 ozs of gold annually over the last 10 years (2019 – 25,750 ozs).
Exploration drilling is continuing to upgrade and expand the Deep Zone mineralization.
$US110M stream financing with Wheaton Precious Metals to fund mine expansion.(2)
Proposed US$150M Gold-Linked Notes Offering.(2)
Located in a Historic Mining District about 80 km south of Medellin
TSX-V: CGCOCTQX: ALLXF
Mine Expansion into the DEEP ZONEBUILDING COLOMBIA’S NEXT MAJOR GOLD MINE
(1) As of July 2, 2020, Gran Colombia now owns 44,547,100 common shares of Caldas Gold.(2) Refer to Company press release dated June 22, 2020.
3
TSX‐V: CGCJune 2020
WarrantsUnlisted: 10.8 million @ CA$3.00 (2024 expiry)
Stock Options0.3 million @ CA$2.10 (2021 expiry)4.6 million @ CA$2.00 (2025 expiry)0.1 million @ CA$2.50 (2025 expiry)
Broker Warrants0.1 million @ CA$2.00 (2022 expiry)
Common Shares
77.5 millionMarket Capitalization
CA$216.2 million(1)
52 Week Low: CA$1.3052 Week High: CA$2.80
As of July 3, 2020CAPITAL STRUCTURE
(1) Market cap based on C$2.79 TSX-V closing price on July 3, 2020.
TSX-V: CGCOCTQX: ALLXF
4
$1.40
$1.60
$1.80
$2.00
$2.20
$2.40
$2.60
$2.80
$3.00
04Apr2020 19Apr2020 04May2020 19May2020 03Jun2020 18Jun2020 03Jul2020
TSX‐V: CGCJune 2020
GRAN COLOMBIA 2.0
DEMONSTRATED OPERATING EXPERIENCE IN LATIN
AMERICAPROVEN SUCCESS
STRONG HEALTH & SAFETY RECORD
FOCUSED ON BUILDING STRONG COMMUNITY
RELATIONSHIPS
Serafino Iacono, Executive Chairman and CEO Company founder with 30+ years of experience in capital markets and public companies
Lombardo Paredes, President 20+ years of corporate leadership and operations management experience in the resource sector in Latin America
Robert Parr, COO Australian mining engineer with 20+ years of international operations and technical experience
Mike Davies, CFO CPA,CA with 20+ years of international and public company experience in resource and other sectors
Board of DirectorsSerafino IaconoMiguel de la CampaLombardo ParedesHernan Juan Jose Martinez TorresRobert DoyleBelinda LabatteHumberto Calderon Berti
Experienced Management TeamSTRONG LEADERSHIP
0
10
20
30
2012 2013 2014 2015 2016 2017 2018 2019
Gold Production (ozs)
84 67
33 3528
2016 2017 2018 2019 2020
LTI Frequency Rate
Mining Operations
Marmato Lost Time Incidents
TSX-V: CGCOCTQX: ALLXF
5
TSX‐V: CGCJune 2020
HighlightsINVESTING IN CALDAS GOLD
Highly Attractive Project with Low Cost Position and High Margins
Funded with External Validation and Shareholder Support from Gran Colombia Gold
Strong Management with Experience Building Mines in Colombia
Commitment to ESG
TSX-V: CGCOCTQX: ALLXF
6
Significant Exploration Upside in Historic Mining Districts
Equity Re-rating Potential in Current Gold Price Environment
TSX‐V: CGCJune 2020
2020MILESTONES
FEB
TSX-V: CGCOCTQX: ALLXF
7
MAR APR MAY JUN
Completed RTO and Listed on the TSX-V (CGC)
Drilling Results at Marmato Prove the Down-Dip Extension of the Recently Discovered New Zone
During the COVID-19 pandemic, Caldas provided support to vulnerable low-income families in the local mining communities of Marmato, Supia, Riosucio
Drilling Results at Marmato Extend the Strike of the Recently Discovered New Zone to More Than 400 Meters
Announced US$110 Million Precious Metals Stream with Wheaton Precious Metals on the Marmato Project; Launched Proposed Issuance of Up To US$150 Million of Gold Notes and Concurrent Equity Financing up to CA$50 Million to Fund the Marmato Project Expansion
CA$14 Million Private Placement With Gran Colombia to Fund JubyProject Acquisition
Shares begin trading on the OCTQX (ALLXF)
JUL
Juby Project Acquisition Closed on July 2, 2020
Announced PFS Results for Marmato Project on July 6, 2020
TSX‐V: CGCJune 2020
Mine Expansion into the DEEP ZONEMARMATO PROJECT
Upper ZoneExisting mine and expanding 1,200 tpdMerrill Crowe plant to 1,500 tpd
Deep Zone (“MDZ”)Future mine with new 4,000 tpd CIL plant Zona Baja
Mining License
Excellent infrastructure: • located by the Pan
American Highway with access to Medellin to the north and Manizales to the south
• access to the national electricity grid
TSX-V: CGCOCTQX: ALLXF
8
TSX‐V: CGCJune 2020
Mineral Resource Estimate (A)As of March 17, 2020
MARMATO PROJECT
Deposit Area
Measured Indicated Measured & Indicated Inferred
Tonnes(kt)
Grade(g/t)
Au Metal(koz)
Tonnes(kt)
Grade(g/t)
Au Metal(koz)
Tonnes(kt)
Grade(g/t)
Au Metal(koz)
Tonnes(kt)
Grade(g/t)
Au Metal(koz)
Zona Baja (4)
Veins 2.1 5.6 387 7.2 5.0 1,156 9.3 5.2 1,543 2.7 4.4 386
Porphyry 2.1 2.5 165 2.1 2.5 165 1.7 2.6 145Transition
Zone 3.4 2.7 294 3.4 2.7 294 0.0 2.0 2
MDZ 24.7 2.6 2,085 24.7 2.6 2,085 21.9 2.3 1,639
Total 2.1 5.6 387 37.3 3.1 3,699 39.4 3.2 4,086 26.4 2.6 2,172
1) Mineral resources are not mineral reserves and do not have demonstrated economic viability.2) All figures are rounded to reflect relative accuracy of the estimate. All composites have been capped where appropriate.3) Vein and Porphyry mineral resources are associated with the current Upper Zone mine using existing cut and fill mining methodology and are
reported at a cut-off grade of 1.9 g/t and gold recoveries of 90% for underground resources without considering revenues from other metals.4) Transition Zone is defined as mining of the MDZ above an elevation of 950 m accessed from the Upper Zone mine using a modified longhole
stoping method.5) MDZ mineral resources are reported at a cut-off grade of 1.3 g/t. Cut-off grades have been based on a price of US$1,500 per ounce of gold and
gold recoveries of 95% for underground resources, without considering revenues from other metals within a limiting pit shell. The MDZ isdefined as mining below an elevation of 950 m using longhole stope mining methods.
TSX-V: CGCOCTQX: ALLXF
9
(A) Please refer to Technical Disclosure footnote (A) at page 2 of this presentation.
TSX‐V: CGCJune 2020
Mineral Reserve Estimate (A)As of March 17, 2020
MARMATO PROJECT
Deposit Area
Proven Probable Total
Tonnes(kt)
Grade(g/t)
Au Metal(koz)
Tonnes(kt)
Grade(g/t)
Au Metal(koz)
Tonnes(kt)
Grade(g/t)
Au Metal(koz)
Zona Baja (4)
Veins 0.8 5.0 123 3.0 4.2 412 3.8 4.4 535Transition
Zone 0.0 7.6 10 1.3 3.4 143 1.3 3.6 152
MDZ - - - 14.6 2.9 1,333 14.6 2.9 1,333
Total 0.8 5.1 133 18.9 3.1 1,888 19.7 3.2 2,020
1) Mineral resources are inclusive of mineral reserves.2) All figures are rounded to reflect relative accuracy of the estimate. All composites have been capped where appropriate.3) Veins ore reserves are reported using a CoG of 2.23 g/t Au. The Veins CoG calculation assumes a US$1,400/oz Au price, 85% Au metallurgical recovery,
US$49.45/t mining cost, US$13.63/t G&A, US$12.24/t processing cost, and US$8.96/t royalties. Transition ore reserves are reported using a CoG of 1.91 g/t Au.The Transition Zone CoG calculation assumes a US$1,400/oz Au price, 95% Au metallurgical recovery, US$46/t mining cost, US$13.63/t G&A, US$12.24/tprocessing cost, and US$8.96/t royalties. MDZ ore reserves are reported using a CoG of 1.61 g/t Au. The Deep Zone CoG calculation assumes a US$1,400/oz Auprice, 95% metallurgical recovery, US$42/t mining cost, US$14/t processing cost, US$6.75/t production royalties/taxes, US$3/t G&A, and US$3/t tailings cost.Note that costs/prices used here may be somewhat different than those in the final economic model. This is due to the need to make assumptions early on formine planning prior to finalizing other items and using long-term forecasts for the LoM plan.
4) The Veins area is currently mined using cut-and-fill methods. Mining dilution ranges from 20% - 55%, averaging 26%, is included in the Reserves using a zerograde for dilution. A mining recovery of 90% is applied to stopes. The Transition Zone is envisioned to be mined using a modified longhole stoping method. Amining dilution of 7% is included in the Reserves using a zero grade for dilution. A mining recovery of 90% is applied to stopes.
5) The MDZ portion of the project is amenable to underground longhole open stoping mining methods. Mining dilution (internal and external) is included in theReserve. Stope dilution is 8%, and a portion of the stope dilution is applied using grade values based on average surrounding block information. A miningrecovery of 92.5% is applied to stopes.
TSX-V: CGCOCTQX: ALLXF
10
(A) Please refer to Technical Disclosure footnote (A) at page 2 of this presentation.
TSX‐V: CGCJune 2020
Life-of-Mine Plan (“PFS”) Results (B)MARMATO PROJECT
Marmato mine in Zona Baja will comprise of two distinct operations: Upper Zone and MDZ.
Upper Zone: Immediate optimization of existing mining operation to reduce dilution, improving production and reducingcash costs, together with an expansion of the existing processing plant over the next two years from 1,200 tpd to 1,500 tpd.A total pf 5.1M tonnes to be processed over 13-year life with average LoM Au grade of 4.2 g/t resulting in 0.6M ounces ofgold (32% of total).
MDZ: US$269M initial capital in 2020 to 2023. Total of 14.6M tonnes processed over a 10 ½ year life starting in mid-2023 atan average LoM Au grade of 2.9 g/t resulting in 1.3M ounces of gold (68% of total).
Combined: 1.9M ounces of gold with LoM cash cost of US$772 per ounce and LoM AISC of US$872/oz. At US$1,400 per ounce long-term gold price, total undiscounted LoM after-tax project cash flow of US$501M (NPV
5% - US$263M). Before financing, after-tax IRR = 20% and payback by 2026.
Precious Metal Production Profile (ozs/year)
TSX-V: CGCOCTQX: ALLXF
11
‐
50,000
100,000
150,000
200,000
2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030 2031 2032 2033
Gold Silver
(B) Please refer to Technical Disclosure footnote (B) at page 2 of this presentation.
TSX‐V: CGCJune 2020
General Infrastructure LocationMARMATO PROJECT
TSX-V: CGCOCTQX: ALLXF
12
Source: SEDAR, PEA dated February 6, 2020
Deep Zone Mineralization
TSX‐V: CGCJune 2020
Non-binding term sheet (1) signed with Wheaton Precious Metals for US$110M streaming agreement to fund mine expansion at the Marmato Project.
6.5% and 100% of payable gold and silver delivered to Wheaton until 190koz and 2.5Moz of payable gold and silver delivered, stepping down to 3.25% and 50% thereafter.
External Validation from a World Class PartnerPROJECT FINANCING
TSX-V: CGCOCTQX: ALLXF
For each ounce of delivered gold and silver, Wheaton will make a cash payment to Caldas of 18% of spot gold and silver, increasing to 22% once the upfront deposit has
been reduced to nil.
13
(1) Refer to Company press release dated June 22, 2020.
TSX‐V: CGCJune 2020
Exploration Upside (C)MARMATO PROJECT
Source: GCM press release dated February 3, 2020
The 2019 Phase 2 drilling continued to
demonstrate an improvement of
grades in the MDZ
TSX-V: CGCOCTQX: ALLXF
14
(C) Please refer to Technical Disclosure footnote (C) at page 2 of this presentation.
TSX‐V: CGCJune 2020
Hole ID From (m) To (m) Width (m) Au Grade (g/t) Ag Grade (g/t)
Grade-WidthAu (g/t *m) Zone
MT-IU-050 226.75 696.25 469.50 2.29 3.2 1075 Deepsincluding 246.75 301.17 54.42 3.65 4.3 199 Deepsincluding 379.30 431.10 51.80 3.00 6.0 155 Deepsincluding 449.00 490.35 41.35 4.14 4.3 171 Deepsincluding 538.25 615.00 76.75 3.12 1.9 239 Deeps
Source: GCM press release dated February 3, 2020
Exploration Upside (C)DEEP ZONE
Significant Drill Intersections of 2020 to Date - TSX TOP 10(1)
(1) OPAXE Report from June 22‐28, 2020
TSX-V: CGCOCTQX: ALLXF
15
(C) Please refer to Technical Disclosure footnote (C) at page 2 of this presentation.
TSX‐V: CGCJune 2020
Source: Caldas Gold press release dated March 2, 2020
Exploration Upside (C)(D)DEEP ZONE
New Zone discovered down-plunge by more than 200 meters at its Marmato
Project
TSX-V: CGCOCTQX: ALLXF
16
(C) Please refer to Technical Disclosure footnote (C) at page 2 of this presentation.(D) Please refer to Technical Disclosure footnote (D) at page 2 of this presentation.
TSX‐V: CGCJune 2020
Hole ID From (m) To (m) Width (m) Au Grade (g/t) Ag Grade (g/t) Grade-Width Zone
MT-IU-058 114.90 130.60 15.70 2.06 6.38 32.3 EVSand 337.05 767.57 430.52 1.82 1.6 784.0 MDZ
including 337.05 380.90 43.85 2.48 3.6 108.9 MZincluding 489.60 511.85 22.25 2.34 1.7 52.0 MZincluding 535.80 609.00 73.20 2.44 1.5 179.0 MZincluding 735.72 767.57 31.85 3.24 2.5 103.2 MZ
Source: Caldas Gold press release dated May 13, 2020
Marmato Producing Some of the Best Drill Holes in 2020EXPLORATION UPSIDE (E)
Significant Drill Intersections of the Month of May(1)
(1) OPAXE Report from May 18-24, 2020
TSX-V: CGCOCTQX: ALLXF
17
(E) Please refer to Technical Disclosure footnote (E) at page 2 of this presentation.
TSX‐V: CGCJune 2020
Environment• Zero major environmental incidents• Reduce impacts of development projects on water, air and biodiversity• Advocate solutions that restore access to clean water in the community• Incorporate renewable energy initiatives in our ESG strategy
Social• Zero fatalities• Reduce LTI FR and LTI SR through full implementation of health & safety
programs• Commitment to local procurement and hiring• Implementation of health, wellness and education programs• Local community support via food donations to over 5,000 families in
Marmato, Supi and Riosucio during the COVID1-19 pandemic• Ongoing commitment to Community Food Program• Supply of PPE kits to security forces, formalized miners, vulnerable families
and the city halls in Marmato
Governance• Hardwire ESG into Caldas Gold’s culture through the “tone from the top”• Establish a framework to train, track and report ESG compliance• Implement ESG initiatives tailored to the operations and community based
on a materiality assessment of key ESG risks and needs• Integrate a sustainability strategy into Caldas Gold’s long-term planning
ESG Commitments and GoalsMARMATO PROJECT
TSX-V: CGCOCTQX: ALLXF
18
TSX‐V: CGCJune 2020
Completed acquisition of 100% interest on July 2, 2020
GCM funded cash portion of acquisition cost with a CA$14M private placement (7,000,000 shares at CA$2.00).
GCM now owns ~57.5% of the total number of issued and outstanding common shares of Caldas Gold.
Advanced exploration-stage gold project within the Shining Tree area in the southern part of the Abitibi greenstone belt.
Gold was discovered in the Shining Tree area in the 1930’s.
Over 14,000 acres controlled through claims covering 10 km strike length on the mineralized trend.
Last 43-101 was prepared by Temex Resources in 2014 with 1.1 Mozs M&I @ 1.28 g/t and 2.9 Mozs Inferred @ 0.94 g/t.
Initial exploration phase will evaluate historical data incorporating machine learning and other studies to develop a drilling program for execution in 2021.
Exploration PipelineJUBY PROJECT
TSX-V: CGCOCTQX: ALLXF
19
TSX‐V: CGCJune 2020
For Further Information, Contact:Mike Davies
Chief Financial Officer(416) 360-4653