Upload
others
View
31
Download
0
Embed Size (px)
Citation preview
CHAPTER VII
PIPING LAYOUT
7.1 INTRODUCTION
A piping layout or piping general arrangement drawing is the most significant drawing
developed by a piping designer. The piping arrangement drawing evolves from the
foundation location and equipment location drawings. It shows all mechanical equipment
and vessels in the unit and the pipes connecting them, including manholes, ladders,
platforms, and davits. It identifies all structural supports such as pipe racks, equipment
structures, columns, braces and any fireproofing they may have. Once locations for
foundations and equipment have been established, piping configurations are added to the
drawing with the aid of symbols that represent fittings, flanges, and valves. Written
information placed on the arrangement drawing includes equipment coordinates,
identification numbers, elevation callouts, line numbers, flow arrows, and dimensions
establishing pipe locations. Instrumentation symbols are included to indicate type,
position, and orientation for accessibility by plant personnel. Ladders and platforms are
also shown on equipment and structures that have them. A nozzle schedule is included
that contains detailed information about all piping and instrument connections for every
piece of equipment. Information such as nozzle number, size and pound rating,
orientation, elevation, and projection is also included. With so much required information
on a drawing, it is easy to understand why the piping arrangement drawing must be neat,
accurate, and legible.
Piping is a major expenditure in the design and construction of industrial, refinery,
petrochemical, or power-generating plants when one considers engineering costs,
material costs, and fabrication and field labor costs. Proper planning and execution of the
design and routing of pipe can have a major impact on controlling the total installed cost.
The design department designing a refinery or petrochemical complex consists of four
main functions:
• Piping .
• Structural/ civil.
• Electrical & instrumentation.
• Equipments.
An experienced piping designer should have thorough knowledge of functions of the
piping department activities. In addition to this, he should have a broad knowledge of the
other sections also.
A piping designer must also know about the following:
• Details and specific requirements of various equipments which are connected by
his piping.
• Materials necessary for various services
• Piping flexibility basics.
• Field construction practices and constraints.
• General knowledge of plant operation and maintenance.
Piping design and equipment arrangement are interrelated subjects that cannot be well
taught in the classroom. Most good designers throughout history have learned their
profession by a combination of academic and practical work. Field and design office plus
a little shop experience is good preparation for designing.
The piping layout design is developed through three major sets of drawings. They are
• Equipment layout / plot plan.
• Piping General Arrangement drawing (piping plan).
• Piping isometrics.
To develop the above drawings the piping designer needs lot of information and
documents from various disciplines. Some of the major inputs required to start the piping
design are:
• Piping and Instrumentation Diagram (P&ID) from process department .
• Line list from process department.
• Piping material specification.
• Overall site plan from civil department.
• Major equipment sizes and details.
• Drawings from other sources .
7.2 PROCESS FLOW DIAGRAM
Flow diagrams describe in a schematic drawing format the flow of fluids and gases
through a unit or an entire plant. By using symbols to represent various pieces of
equipment, the flow diagram provides the piping designer with an overall view of the
operation of a facility. The flow diagram is used by the piping group to develop and lay
out the plot plan. When developing the plot plan, the arrangement of the equipment in the
facility reflects, in part, the logical sequence of flow depicted on the flow diagram.
However, many other factors such as code requirements, client standards and preferences,
worker safety, and cost also influence the positioning of equipment.
Once the plot plan is finalized, the piping designer routes the pipe between two vessels as
indicated by the
flow diagram using piping specifications and accepted design practices. The flow
diagram is usually “yellowed out” as each line is completed and incorporated into the
design. Process engineers are responsible for developing flow diagrams. In many large
engineering firms, an entire department is dedicated to the development of flow
diagrams. The process flow diagram is the first flow diagram
developed by the flow diagram department. It includes the following:
• major equipment
• main piping
• direction of flow
• operating pressure and temperature
• major instrumentation
SCHEMATIC DIAGRAM OF A UNIT:
PROCESS FLOW DIAGRAM:
7.3 PIPING AND INSTRUMENTATION DIAGRAM (P&ID)
P&ID is the main input required for piping design. It indicates the design process
equipment and interconnecting piping required to perform the function for which the
system is intended. It also indicates the instrumentation and control requirements. It
defines the sequence of equipment, valves, inline components, pipeline sizes, and overall
system arrangement required for proper system function. Piping and instrumentation
diagrams are the piping designer’s roadmap for laying out piping systems. The designer
should understand the P&ID and the specific system characteristics. P&ID are
representative schematics and are not drawn to scale.
The following information are taken from the P&ID by piping designer:
• Flow scheme.
• Piping material for each piping sections.
• Valve requirements and types of valves.
• Line size.
• Insulation and heat tracing requirements.
• Equipment connection details.
• Process vents and drain requirements.
7.4 EQUIPMENT LAYOUT / PLOT PLAN
Plot plan is derived from two drawings, site plan and equipment arrangement drawing.
The piping group produces a site plan into a small scale. It shows whole site including
boundaries, roads, buildings, railroad spurs, pavement, process plant areas, large
structures, storage areas, effluent ponds, waste disposal, shipping and loading areas. True
or geographic and assumed or plant north are marked and their angular separation is also
shown. Then a key plan is produced by adapting the site plan and dividing the area of the
site into smaller areas identified by key letters or key numbers. Equipments are arranged
by a piping group. The piping group usually makes several viable arrangements of
equipment, seeking an optimal design that satisfies process requirements. When the
equipment arrangement drawings are approved, they are developed into plot plans by the
addition of dimensions and coordinates to locate all major items of equipment and
structures. A pot plan shows the following:
• All equipments.
• Major structures.
• Main and sub pipe racks.
• Access ways.
• Control room.
• Space for future expansion.
• North and east extremities of building, center lines of steel work or other
architectural constructions.
• Plant north and true north
• Any other items of important.
Equipment layouts are drawn to scale of 1:50, 1:100, 1:250 etc depending on the size of
the plant and the number of equipments. Updated copy of the above drawings are sent to
civil, structural, electrical or other groups involved in design, to inform them about
requirements as the design develops.
For the correct placing of all the above items in an equipment layout, following inputs are
required:
• Available plot area.
• Process flow diagram.
• P&ID.
• Line list for sizing rack.
• Dimension of equipments / data sheets of equipments.
• Type of building, structures and foundations.
• Wind directions.
• Equipment erection, maintenance and operation requirements.
7.5 DRWAINGS FROM OTHER SOURCES
Piping drawings should be correlated with the following from design group and from
vendors. Points to be checked are listed:
7.5.1 ARCHITECTURAL DRWAING
• Outlines of walls or sidings, indicating thickness.
• Floor penetrations for stairways, lifts, elevators, ducts, drains etc.
• Positions of doors and windows.
7.5.2 CIVIL ENGINEERING DRWAING
• Foundation, underground piping, drains etc.
7.5.3 STRUCTURAL STEEL DRWAING
• Position of steel columns supporting next higher floor level.
• Supporting structures such as overhead cranes, monorails, platforms or beams.
• Wall bracing where pipes may be taken through walls.
7.5.4 HEAT VENTILATING & AIR CONDITIONING (HVAC) DRWING
• Paths of drawing and rising ducts, fan room, space heater etc.
7.5.5 ELECTRICAL DRWAING
• Positions of motor control centers, junction boxes& control panels.
• Major conduits or wiring runs(including buried runs)
• Positioning of light.
7.5.6 INSTRUMENTATION DRWAING
• Instrumentation panel& console locations.
7.5.7 VENDOR DRWAING
• Dimension of equipment.
• Position of nozzle, flange type& pressure rating etc.
7.5.7 MECHANICAL DRAWING
• Position and dimension of mechanical equipment.
• Piped service needed for mechanical equipment.
7.6 LINE LIST
Line list is a document prepared by process engineers. Each line in a unit is listed in the
list.
Line list (line designation sheet or table) include:
• The number of the line
• Line size
• Material of construction
• Conveyed fluid
• Pressure, temperature, flow rate
• Test pressure
• Insulation and jacketing
• Connected line (which will usually branch)
A line list will look like as follows:
7.7 PIPING GENERAL ARRANGEMENT DRAWING
Once, the equipment layout in finalized, the next step is to introduce the piping network
connecting the various equipments. This is done in another set of drawings called the
piping plan or piping general arrangement drawing.
The entire plant will be divided into numerous units or sections and each piping plan
shows the piping arrangement of a section.
Piping plans are normally drawn to scale of 1: 33.33. it shows the plan view of the plant
with detailed dimensions of the piping arrangement. Where required, sectional views and
elevations are also shown for more clarity.
7.8 CONSIDERATION FOR PLANT AND PIPING LAYOUT
As we have seen, developing a plant layout involves locating various equipments like
pumps, compressors, vessels, towers, furnaces etc. and arranging the piping network
connecting these equipments as per process schematic requirements given in the P&ID.
A good plant layout takes into account, the most important features of the plant such as
plant economy, appearance and arrangement of the equipment from aesthetic point of
view, proper maintenance facilities, safety considerations and to facilitate movement of
erection machinery like crane etc during the construction activities.
All these featured have direct bearing on the economy of the plant and a plant layout
designer has to consider carefully, all the above aspects to arrive at an optimum plant
layout.
Plant Economy:-
Second biggest cost factor for a plant like refinery, petrochemical or other process plant
is the piping cost. There is a good scope to achieve an economy by way of saving in
piping cost by improving up on plant layout. Basically, plant economy means installing a
plant in a smallest possible space, consistent operability , safety and law of maintenance
and using the smallest possible amount of piping material, structural steel or concrete.
Erection / Construction equipments:-
Erection scheme of all equipment must be considered during equipment layout. While
developing the equipment layout, the construction dept must be consulted for erection of
equipment. Adequate clearance and open access should be provided for erection of tall
columns, and heavy equipments.
Safety Requirements:-
Various international regulations, guidelines and safe practices set rules for minimum
distance between different types of equipments. The distance between fired heaters, Fuel
oil dry tank, control room, fire water hydrant /monitors, blow down facilities, water
spray deluge valve etc are mainly detected by safety consideration.
For e.g.:-Fired heaters shall be located minimum 15 m away from other hydrocarbon
units, to avoid a fire incase of a gas leak etc.
Similarly fire hydrant/monitors should be so located that incase of a fire, the operator
should be able to safety operate the Hydrant / Monitor.
Operation and maintenance requirements:-
Any plant is run by operators and adequate access for the operation to perform various
activities shall be provided. All the manually operated valves, instruments etc should
either be located at grade level or if at a higher level, suitable platforms, ladders etc shall
be provided. Similarly maintenance of equipments need adequate space. Sufficient
overhead and horizontal clearances shall be provided around each equipment for crane
access, removal of parts etc. It is also essential to have road access to equipments
facilitate access for cranes, trucks etc.
7,9 LAYOUT CONSIDERATION FOR PIPE RACK
Pipe rack is the structure with tiers at generally 3 to 4 levels and pipe laid on these tires.
One of the important steps in preparing an equipment layout is the arrangement of the
pipe rack with relation to the equipment. The simplest arrangement is the pipe rack in the
middle and the row of equipment on either side and access roads parallel to the row of
equipment on the both sides. But these type of arrangement require a long plot area and
in several cases, it may not be feasible. Hence “L” Shape, “H” shaped racks may be
considered.
The total width of the rack can be 6m, 8m and 10m for single bay and 12m and 16m for
double bay having three tires maximum.
• The spacing between pipe rack portals is generally taken as 3m.
• Clearance beneath pipe rack shall be 3m.
• Road clearance beneath pipe rack should be 7m for main road and 5m for
secondary road.
• A head room clearance of minimum 2.2 m is provided. For all lines to clear man
height.
• Locate the largest bore and the heaviest piping as close to stanchions as possible.
• Lines requiring a constant fall (relief headers) can be run on cantilevers from
pipe-rack stanchions or on vertical extensions to pipe-track stanchions.
• Run the hot line requiring expansion loops on the outside edge of pipe way to
permit loops to have greatest width over the pipe way and facilitate nesting.
• Takeoff elevations from pipe ways should be at a constant elevation, consistent
with the range of pipe sizes involved.
• Change elevation whenever banks of pipes, either on pipe ways at grade or at
higher elevations on pipe racks, change direction.
• Elevations to the underside of pipe racks should be the minimum for operation
and mobile maintenance equipment and consistent with allowable clearances.
• Open pipe trenches may be used between plants where there is no risk of
flammable vapors collecting.
• It sometimes is convenient to run open trenches alongside roadways. (Soil from
the trench can be used to build up the road.)
• Where a pipe way or road changes from a parallel direction, the pipe generally is
run beneath the road.
7.10 PIPE RACK SPACING
Arrangement and positioning are important factors in the layout of a piping facility.
Space is limited. Area and boundary limits force conservation of space. Arranging
equipment throughout the unit in an orderly and sequential fashion is a necessity.
Therefore, proper spacing and arrangement of pipe in the pipe rack requires special
attention. A pipe rack has a defined width; therefore, working within the allotted space
makes spacing crucial. Not only must pipe be arranged to take up a minimum amount of
space, but allowances should be made for any pipe that might be added in the future. Line
spacing dimensions are based on a clearance of 1” between the outside diameter of the
largest flange and the outside diameter of the adjacent pipe. The minimum spacing
between any two lines is 4”. If either of the lines is insulated, the thickness of the
insulation must be added. When lines are placed adjacent to a wall, column, building, or
other structure, a minimum clearance of 2’-0” is required from the outside diameter of a
flange. Pipes having orifice flanges also require a minimum clearance of 2’-0” on either
side of the pipe. Figure shows the requirements for establishing the minimum clearances
for line spacing. The line spacing chart shown in Table provides the minimum clearances
for pipe without insulation.
DRAWING PIPE IN THE RACK
When representing pipe in a pipe rack, the careful arrangement and organization of
names, dimensions, and line numbers will make the drawing easier to read. Figure shows
a pipe rack that has been well organized. Notice how the alignment of notes, dimensions,
and other callouts makes the drawing easy to read. The following guidelines will help
you organize your drawing:
• Keep flow arrows the same size and aligned.
• Line numbers should be left justified when possible.
• Pipe commodity should be identified on utility lines only.
• Line spacing dimensions should align across the pipe rack from one pipe support
column to the other. This allows coordinates for each pipe to be calculated since
each pipe support column is positioned using a coordinate.
7.11 LAYOUT CONSIDERATION FOR EQUIPMENTS
7.11.1 Layout consideration for pumps
• Locate pumps close to equipment from which they take suction.
• Consideration should be made to locate pumps under structures or with their
motor ends under a pipe rack.
• Pump suction lines are generally larger than discharge line to avoid problems
arising from a low net positive suction head (NPSH).
• End suction top discharge is the preferable option for pumps, when taking suction
directly from tanks or vessels located at grade.
• Pumps should be arranged in rows with center line of discharge is on a common
line.
• Clearance between pumps or pumps and pipes are a minimum of 900mm.
7.11.2 Layout consideration for compressors
• It is important to locate reciprocating compressors, anchors, and restraints for
pipes belonging to the compressor system on foundations that are independent of
any building, structure, or pipe track or rack. This independence gives the
associated piping stability and minimizes unnecessary fatigue and possible failure.
• Spacing between compressors and other equipment varies with the type of
machine and its duty.
• Particular attention must be paid to withdrawal of engine and compressor pistons,
cam shaft, crank shaft, and lube oil cooler bundle; cylinder valve maintenance
clearance with the least possible obstruction from piping supports.
• Compressors generally are provided a degree of shelter, that is, a sheets building.
Keep the sides up to 8 feet above grade and open and vent the ridge to allow for
escape of flammable gas, which might leak from the machines.
• Certain types of compressors, owing to the height of the mass foundation above
grade level, require a mezzanine floor of a grid construction to avoid trapping any
gas and for operation and maintenance.
7.11.3 Layout consideration for exchangers
• Tubular exchangers usually have standard length tubes of 2.5, 4, 5, and 6 m.
• Whenever possible locate exchangers at grade to facilitate maintenance and tube
withdrawal.
• Two or more shells forming one unit can be stacked or otherwise arranged as
indicated on the exchanger specification sheet, which is delineated by the
manufacturer.
• Exchangers with dissimilar service can be stacked, but rarely more than three
high, except for fin-tube-type units.
• Horizontal clearance of at least 900 mm should be left between exchangers or
between exchangers and piping.
• Where space is limited, clearance may be reduced between alternate exchangers,
providing sufficient space is left for maintenance and inspection access.
• Where a rear shell cover is provided with a davit, allow clearance for the full
swing of the head. Set overhead vapor exchangers or condensers at such elevation
that the exchanger is self-draining.
• Arrange outlets to a liquid hold pot or trap, so that the underside of the exchanger
tubes is above the liquid level in the trap.
• Arrange exchangers so that the fixed end is at the channel end.
• Vertical exchangers should be set td allow lifting or lowering of the tube bundle.
• Consult the Vessel Department as to the feasibility of supporting vertical
exchangers from associated towers.
• Space should be left free for tube or bundle withdrawal, with the exchanger
channels preferably pointing toward an access area or road.
• If an exchanger is situated well within the plot, leave a free area and approach for
mobile lifting equipment.
• Air fin exchangers, preferably, should be located in a separate row outside the
main equipment row, remote from the central pipe way.
• Consider locating air fin exchangers over the central pipe way if plot space if very
limited.
7.11.4 Layout consideration for fired heaters
• Fired heaters should be located at least 15 m away from other equipment that
could be a source of liquid spillage or gas leakage.
• To avoid accumulation of flammable liquids, no pits or trenches should be
permitted to extend under furnaces or any fired equipment, and if possible, they
are to be avoided in furnace areas.
• Ensure ample room at the firing front of the fired heater for operation and removal
of the burners and for the burner control panel, if required.
• Bottom-floor fired furnaces require adequate headroom underneath the furnace.
Wall fired furnaces require an adequate platform width with escape routes at each
end of the furnace.
• Apart from adequate platform and access to the firing front, other structural
attachments and platforms around furnaces should be kept minimum. Access by
means of stepladder is sufficient.
• Arrange fired heaters on a common center line, wherever possible.
• Provide unobstructed space for withdrawal.
• Operation and maintenance platforms should be wide enough to permit a 1-m
clear walkway.
• Escape ladders should be provided on large heaters.
• Vertical heaters usually are supplied with stub supporting feet; ensure drawings
show adequate supports elevated to the required height.
• Headroom elevation from the floor level to the underside of heater should be 2.3
m, to provide good firing control operation.
7.11.5 Layout consideration for columns
• Columns usually are self-supporting with no external structures.
• Circular or segmental platforms with ladders are supported from the shell.
• The maximum allowable straight run of a ladder before a break platform should
not exceed 9 m.
• The factors influencing column elevation are the provision of a gravity flow
system and installation of thermosyphon reboilers.
• Depending on the plant arrangement, columns may have to be elevated to a height
in excess of the normal requirements to allow for headroom clearance from lower-
level piping off-takes.
• The skirt height of all columns or vessels providing suction to pumps, particularly
if handling hot or boiling liquids should be adequate for the pump NPSH
requirements.
• Access platforms should be provided on columns for all valves 3" and above,
instrument controllers and transmitters, relief valves, manholes and blinds or
spades, and other components that require periodic attention.
• Platforms for access to level gauges and controllers should not be provided if
underside of supporting steelwork is less than normal headroom clearance from
grade.
• Adjacent columns should be checked, so that platforms do not overlap. For
layout, 2.0-2.5 m between shells, depending on insulation, should suffice.
• Allow a 900 mm minimum clearance between column foundation and the
adjacent plinth.
• Provide clearance for the removal of internal parts and attachments and for davits
at top of columns, if relevant.
• The center line of manholes should be 900 mm above any platform.
• Horizontal vessels should be located at grade, with the longitudinal axis at a right
angle to the pipe way, if possible.
• Consider saving plot space by changing vessels from the horizontal to the vertical,
if possible, and combining vessels together with an internal head (subject to
project or process approval).
• The size and number of access platforms on horizontal vessels should be kept to a
minimum and are not to be provided on horizontal vessels or drums when the top
of the vessel is 2.5 m or less from the grade.
• The channel end of vessels provided with internal tubular heaters should face
toward an open space. The withdrawal area must be indicated on studies, general
arrangements (GAs), and plot plans.
• Internal agitators or mixers are to be provided with adequate clearance for
removal. Removal area must be indicated on studies, GAs, and plot plans.
(COLUMN PIPING)
7.11.1 Layout consideration for tanks
• The layout of tanks, as distinct from their spacing should always take into
consideration the accessibility needed for firefighting and the potential value of a
storage tank in providing a buffer area between process plant and for example,
public roads and houses, for safety and environmental reasons.
• The location of tanks relative to process units must be such as to ensure maximum
safety from possible incidents.
7.12 LAYOUT CONSIDERATIONS TO ENSURE PIPING FLEXIBILITY AND
FACILITATE SUPPORTING
While routing the piping every effort has to be made to provide adequate flexibility in the
piping using a minimum number of fittings, loops at appropriate locations and flexible
joints. When a quick check the determines that the system is not flexible enough, the
designer reviews the system to determine whether or not he can re design, may be by
adding an elbow or two to increase flexibility.
Two cardinal principles in routing lines for economic support , restraint are:-
• Group the pipe lines so as to minimize the number of structures needed solely for
pipe supports and restrains.
• Keep lines located close to possible points of supports. i.e.:- Either to grade or
two structures which are to be provided for other purposes.
EQUIPMENT PIPING
While routing the piping to the equipments, care has to be taken to ensure that any special
requirements and constraints of the equipments operation, maintenance etc are taken in to
consideration.
For e.g. :- Pump suction piping shall be arranged with a particular care to avoid various
pockets or un necessary pressure drip and piping shall be as short as possible, to avoid
cavitations and ensured the required NPSH at the pump suction.
While routing compressor piping, adequate supports and clamps need to be provided to
contain vibration
Suction piping to centrifugal compressors should be designed to allow sufficient straight
length. i.e. 5D minimum of pipe (D= Diameter of pipe) immediately ahead of suction
nozzle to allow dissipation of un desirable flow distortion causes by elbows, valves or
other fittings At heat exchangers the piping shall not run in the way of the handling
facilities for tube-bundle removal.
The basic rule for the piping at the heat exchangers is- fluid being heated should flow up
and fluid being cooled will flow down. However if no considering or vaporizing can
occur during heat transfer, flow can be routed in any manner. In any case for best heat
transfer, reverse flow must be maintained. i.e. the flow should be in opposite directions.
Hence, designing the piping layout requires through understanding of the process
conditions and requirements, mechanical design, operation and maintenance features of
the connected equipments, Special requirements of the instruments, valves etc in the line,
to name a few.
Mastery in piping design can be achieved only by vast experience, continuous learning
process and interaction with various departments.
7.13 PIPING ISOMETRICS
Piping isometric drawings shows the pipe routing in the isometric view with detailed
dimensions, which can be used for fabrication of the piping spools. Isometrics are not
drawn to scale.
Other information shown in the isometric are
• Plant north
• Line number and specification
• Bill of material
• Stress analysis requirements
• Design temperature and pressure.
• Hydro test pressure.
• NDT requirements