7
SGS INTRON Laboratory P.O. box 5187 6130 PD Sittard The Netherlands t +31 (0) 46 - 4 204 204 f +31 (0) 46 - 4 529 060 Author: F. Meijers projectleader Authorisation: H.P.H. Creemers accountmanager Page 1 of 7 Keurap04 Unless otherwise agreed, orders are executed in accordance with the latest version of the SGS INTRON B.V. General Conditions. Upon simple request the conditions will again be sent to you. Attention is drawn to the limitation of liability, indemnification and jurisdiction issues defined therein. Without written permission from SGS INTRON Laboratory, this report may only be reproduced entirely. The results are only related to the investigated samples.The scope of the accreditation involves all results belonging to analyses marked with Q at the methods section. The used significances of the results represent their uncertainty. Other performance characteristics are available upon request. Certificate Of Analysis TRADECC Belgium attn. Mr dr.ing. B. De Clercq Terbekehofdreef 50-52 2610 WILRIJK Belgium Date : 27/10/2017 Subject : Water tightness under pressure tests PC Elastoswell Your Code : Purchase order IOR1617/01412 dd. 30/06/2017 Laboratory Number : 171779 UK Sampling : By client Period of Investigation : 01/08/2017 until 16/10/2017 Purpose of the investigation Determine PC Elastoswell waterproofing at a water pressure of 7, 8 and 9 bar. Conclusion The test pieces with PC Elastoswell, tested as described, do not leak at 9.2 bar water pressure. Also at a peak load of 10 bar there is no leakage.

Certificate Of Analysis TRADECC Belgiumdocserv.ercatec.net/asoka/d/zert/YTc1YjUxM2V8Q0NFREFSVAaa/Ela… · SGS INTRON Laboratory P.O. box 5187 6130 PD Sittard The Netherlands t +31

  • Upload
    others

  • View
    4

  • Download
    1

Embed Size (px)

Citation preview

Page 1: Certificate Of Analysis TRADECC Belgiumdocserv.ercatec.net/asoka/d/zert/YTc1YjUxM2V8Q0NFREFSVAaa/Ela… · SGS INTRON Laboratory P.O. box 5187 6130 PD Sittard The Netherlands t +31

SGS INTRON Laboratory P.O. box 5187 6130 PD Sittard The Netherlands

t +31 (0) 46 - 4 204 204 f +31 (0) 46 - 4 529 060

Author:

F. Meijers projectleader

Authorisation:

H.P.H. Creemers accountmanager

Page 1 of 7 Keurap04

Unless otherwise agreed, orders are executed in accordance with the latest version of the SGS INTRON B.V. General Conditions.

Upon simple request the conditions will again be sent to you.

Attention is drawn to the limitation of liability, indemnification and jurisdiction issues defined therein. Without written permission

from SGS INTRON Laboratory, this report may only be reproduced entirely.

The results are only related to the investigated samples.The scope of the accreditation involves all results belonging to

analyses marked with Q at the methods section.

The used significances of the results represent their uncertainty. Other performance characteristics are available upon request.

Certificate Of Analysis TRADECC Belgium

attn. Mr dr.ing. B. De Clercq

Terbekehofdreef 50-52

2610 WILRIJK

Belgium

Date : 27/10/2017

Subject : Water tightness under pressure tests PC Elastoswell

Your Code : Purchase order IOR1617/01412 dd. 30/06/2017

Laboratory Number : 171779 UK

Sampling : By client

Period of Investigation : 01/08/2017 until 16/10/2017

Purpose of the investigation

Determine PC Elastoswell waterproofing at a water pressure of 7, 8 and 9 bar.

Conclusion

The test pieces with PC Elastoswell, tested as described, do not leak at 9.2 bar water pressure. Also

at a peak load of 10 bar there is no leakage.

Page 2: Certificate Of Analysis TRADECC Belgiumdocserv.ercatec.net/asoka/d/zert/YTc1YjUxM2V8Q0NFREFSVAaa/Ela… · SGS INTRON Laboratory P.O. box 5187 6130 PD Sittard The Netherlands t +31

SGS INTRON Laboratory P.O. box 5187 6130 PD Sittard The Netherlands

t +31 (0) 46 - 4 204 204 f +31 (0) 46 - 4 529 060

Laboratory Number: 171779 UK Page 2 of 7 Keurap04F

Without written permission from SGS INTRON Laboratory, this report may only be reproduced entirely.

The results are only related to the investigated samples.

The used significances of the results represent their uncertainty. Other performance characteristics are available upon request.

Set up of the investigation

TRADECC has made tree configurations A, B and C specified by SGS INTRON:

Configuration A Pretest reference concrete, 1 layer without PC Elastoswell

Based on these test pieces, we will understand how long it takes at 7 bar water

pressure to saturate the concrete that is above the PC Elastoswell. Below is a

schematic section of this configuration.

Figure 1. Configuratiion A

Configuration B 2 layer reference test piece without PC Elastoswell and in the lower concrete a

gap of about 1 mm. Through this configuration we want to determine at what time

the test pieces will leak at a water pressure of 7 bar. To ensure that the water

pressure is sufficiently present on the test surface the concrete is drilled with a

diamond drill. Below is a schematic representation of the test pieces used in

configuration B.

Figure 2. Configuration B

100

75

75Waterpressure

7 bar max

Concrete A

Test piece sealed,(in red)

bottom side is open

Moist

dimensions in mm

Page 3: Certificate Of Analysis TRADECC Belgiumdocserv.ercatec.net/asoka/d/zert/YTc1YjUxM2V8Q0NFREFSVAaa/Ela… · SGS INTRON Laboratory P.O. box 5187 6130 PD Sittard The Netherlands t +31

SGS INTRON Laboratory P.O. box 5187 6130 PD Sittard The Netherlands

t +31 (0) 46 - 4 204 204 f +31 (0) 46 - 4 529 060

Laboratory Number: 171779 UK Page 3 of 7 Keurap04F

Without written permission from SGS INTRON Laboratory, this report may only be reproduced entirely.

The results are only related to the investigated samples.

The used significances of the results represent their uncertainty. Other performance characteristics are available upon request.

Configuration C 2 layer PC Elastoswell test piece and in the lower concrete a gap of about 1 mm.

Through this configuration we want to determine at what time the PC Elastoswell

test pieces will leak. To ensure that the water pressure is sufficiently present on

the test surface the concrete is drilled with a diamond drill to just above the PC

Elastoswell. We start the water pressure in three steps: from 7 to 8 and then to

9.2 bar. During each step, we assess whether the test pieces will leak. Below is a

schematic representation of the test pieces used in configuration C.

Figure 3. Configuration C

Sample Data

Sample-

number

Sample-

type

Sample-

code

Acceptance-

date

1 to 4 1 layer concrete Configuration A 01/08/2017

5 to 8 2 layer concrete without PC Elastoswell Configuration B 01/08/2017

9 to 12 2 layer concrete with PC Elastoswell Configuration C 01/08/2017

All test pieces were made by TRADECC Belgium and handed to SGS Intron in Sittard.

Photos of the samples supplied are listed in Annex A.

Methods

Analysis Method Q u

Water pressure SGS INTRON

Q = Accredited by RvA, u = Subcontracted, Qu = Accredited with Subcontractor

Page 4: Certificate Of Analysis TRADECC Belgiumdocserv.ercatec.net/asoka/d/zert/YTc1YjUxM2V8Q0NFREFSVAaa/Ela… · SGS INTRON Laboratory P.O. box 5187 6130 PD Sittard The Netherlands t +31

SGS INTRON Laboratory P.O. box 5187 6130 PD Sittard The Netherlands

t +31 (0) 46 - 4 204 204 f +31 (0) 46 - 4 529 060

Laboratory Number: 171779 UK Page 4 of 7 Keurap04F

Without written permission from SGS INTRON Laboratory, this report may only be reproduced entirely.

The results are only related to the investigated samples.

The used significances of the results represent their uncertainty. Other performance characteristics are available upon request.

Results

Test Leakage Time Saturation Remark

Pretest configuration A, 7 bar Yes 4 hours fully saturated

Pretest configuration B, 7 bar Yes 24 to 48 hours fully saturated, and

leakage visual.

Test configuration C, 2 days 7 bar No -

Test configuration C, 5 days 8 bar No -

Test configuration C, 5 days 9,2 bar No - peak pressure of 10 bar

When setting an average working pressure of 9.2 bar, the peak load rises to 10 bar

.

Photo 1. Sample 5 to 7, configuration B Fully saturated top and leakage with water at 7 bar after 24 hours

Page 5: Certificate Of Analysis TRADECC Belgiumdocserv.ercatec.net/asoka/d/zert/YTc1YjUxM2V8Q0NFREFSVAaa/Ela… · SGS INTRON Laboratory P.O. box 5187 6130 PD Sittard The Netherlands t +31

SGS INTRON Laboratory P.O. box 5187 6130 PD Sittard The Netherlands

t +31 (0) 46 - 4 204 204 f +31 (0) 46 - 4 529 060

Laboratory Number: 171779 UK Page 5 of 7 Keurap04F

Without written permission from SGS INTRON Laboratory, this report may only be reproduced entirely.

The results are only related to the investigated samples.

The used significances of the results represent their uncertainty. Other performance characteristics are available upon request.

Configuration C, The following pictures of a split 2-layer test specimen with Elastoswell, after 9.2 bar

test.

Photo 2. Configuration C, test piece is split after test. No leakage visible

Photo 3. Configuration C, Detail of PC Elastoswell, no leakage visible

Concrete

Concrete

Seal

Gap

PC Elastoswell

Page 6: Certificate Of Analysis TRADECC Belgiumdocserv.ercatec.net/asoka/d/zert/YTc1YjUxM2V8Q0NFREFSVAaa/Ela… · SGS INTRON Laboratory P.O. box 5187 6130 PD Sittard The Netherlands t +31

SGS INTRON Laboratory P.O. box 5187 6130 PD Sittard The Netherlands

t +31 (0) 46 - 4 204 204 f +31 (0) 46 - 4 529 060

Laboratory Number: 171779 UK Page 6 of 7 Keurap04F

Without written permission from SGS INTRON Laboratory, this report may only be reproduced entirely.

The results are only related to the investigated samples.

The used significances of the results represent their uncertainty. Other performance characteristics are available upon request.

Photo 4. Configuration C, Detail of PC Elastoswell, no leakage visible

Gap

PC Eastoswell

Page 7: Certificate Of Analysis TRADECC Belgiumdocserv.ercatec.net/asoka/d/zert/YTc1YjUxM2V8Q0NFREFSVAaa/Ela… · SGS INTRON Laboratory P.O. box 5187 6130 PD Sittard The Netherlands t +31

SGS INTRON Laboratory P.O. box 5187 6130 PD Sittard The Netherlands

t +31 (0) 46 - 4 204 204 f +31 (0) 46 - 4 529 060

Laboratory Number: 171779 UK Page 7 of 7 Keurap04F

Without written permission from SGS INTRON Laboratory, this report may only be reproduced entirely.

The results are only related to the investigated samples.

The used significances of the results represent their uncertainty. Other performance characteristics are available upon request.

ANNEX A. Pictures of received test samples Configuration A, B & C

Gap

Configuration A, 1 layer concrete

Configuration B, 2-layer concrete without

PC Elastoswell

Configuration C, 2-layer concrete with